JP2006274655A - Drain structure of banking levee body and its construction method - Google Patents

Drain structure of banking levee body and its construction method Download PDF

Info

Publication number
JP2006274655A
JP2006274655A JP2005094750A JP2005094750A JP2006274655A JP 2006274655 A JP2006274655 A JP 2006274655A JP 2005094750 A JP2005094750 A JP 2005094750A JP 2005094750 A JP2005094750 A JP 2005094750A JP 2006274655 A JP2006274655 A JP 2006274655A
Authority
JP
Japan
Prior art keywords
embankment
artificial
drain
drain material
bank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005094750A
Other languages
Japanese (ja)
Other versions
JP4675130B2 (en
Inventor
Shigeyuki Mouri
栄征 毛利
Toshikazu Hori
俊和 堀
Takeshi Ishiguro
健 石黒
Hiroshi Takahashi
浩 高橋
Kazuyuki Maeda
和亨 前田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
National Institute for Rural Engineering
Maeda Corp
Original Assignee
National Institute for Rural Engineering
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by National Institute for Rural Engineering, Maeda Corp filed Critical National Institute for Rural Engineering
Priority to JP2005094750A priority Critical patent/JP4675130B2/en
Publication of JP2006274655A publication Critical patent/JP2006274655A/en
Application granted granted Critical
Publication of JP4675130B2 publication Critical patent/JP4675130B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a drain structure of a banking levee body and its construction method capable of simply and effectively carrying out a repair and maintenance by improving workability and maintenance efficiency of the drain structure for raising mechanical stability by lowering a seepage line in the banking levee body. <P>SOLUTION: The drain structure of the banking levee body is equipped with an artificial drain material 4 consisting of at least either one of a pipe-like drain material buried in the back slope side of the banking levee body 2 and passing seepage water there-through or a sheet drain material. Namely, the back slope side of the banking levee body 2 is excavated, and after the artificial drain material 4 consisting of at least either one of the pipe-like drain material passing the seepage water there-through or the sheet drain material has been constructed in the excavated section, the excavated section is made to back fill to bury the artificial drain material 4 in the banking levee body 2. Concretely, after the artificial drain material 4 has been constructed, the excavated section is made to back fill to bury also the artificial filter material 5 in the banking levee body 2 after the artificial filter material 5 has been constructed in the back slope side of the banking levee body 2 to connect with the artificial drain material 4. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、盛土堤体の補修・維持管理を簡便とするドレーン構造と、その施工方法に関する。   The present invention relates to a drain structure that simplifies repair / maintenance of a bank embankment and a construction method thereof.

河川や溜池等において、一般に浸潤線(地下水位)が上昇し力学的に不安定になった盛土堤体を補修する際には様々な方法がある。例えば盛土堤体を撤去し新たに盛土を築堤する方法、現状の盛土堤体に押え盛土をする方法、盛土堤体の法面にシートを貼り付けて遮水する方法、盛土堤体内に天然材料のドレーン・フィルター材(礫、砂等)を敷設して排水する方法(例えば特許文献1参照)が一般的である。
特開2002−121720号公報
In rivers and ponds, there are various methods for repairing embankments that are generally unstable due to rising infiltration lines (groundwater level). For example, a method of removing a bank embankment and building a new bank, a method of embedding the embankment on the current bank, a method of attaching a sheet to the slope of the bank and blocking the water, natural materials in the bank In general, a drain filter material (gravel, sand, etc.) is laid and drained (see, for example, Patent Document 1).
JP 2002-121720 A

しかし、盛土堤体を撤去し新たに盛土を築堤する方法の場合、長い工期と多大な費用を要する。特に溜池などの堤体の場合には工期が長いと作付けができない問題が生じる。
また、盛土堤体に押え盛土をする方法では、新たな用地買収の必要があり、盛土堤体の法面にシートを貼り付けて遮水する方法は、豪雨時にあまり効果が無いなどの問題がある。
そして、特許文献1のように、盛土堤体内に天然材料のドレーン・フィルター材(礫、砂等)を敷設して排水する方法の場合には、礫、砂等の天然材料の枯渇化に伴い良質な材料の入手が困難であり、礫、砂等の採取に際しては自然破壊につながる恐れがあり、長期的には礫、砂等によるドレーン・フィルター材の目詰まりの問題もあり、容易に交換等のメンテナンスができない。また、礫、砂等の敷設には大型重機や大量の材料が必要となるため、材料や重機の運搬のための工事用道路を建設する必要があることから、コストが増大する問題がある。
However, in the case of the method of removing the embankment embankment and newly embanking the embankment, a long construction period and a great expense are required. In particular, in the case of a bank such as a reservoir, if the construction period is long, there will be a problem that it cannot be planted.
In addition, the method of embankment embankment embankment requires the acquisition of a new site, and the method of pasting sheets on the slope of embankment embankment and blocking the water is not very effective during heavy rain. is there.
And, as in Patent Document 1, in the case of a method of draining by draining a natural material drain filter material (gravel, sand, etc.) in the embankment embankment, with the depletion of natural materials such as gravel, sand, etc. Obtaining high-quality materials is difficult, and there is a risk of natural destruction when collecting gravel, sand, etc., and there is a problem of clogging of drain and filter materials due to gravel, sand, etc., and replacement is easy. Such as maintenance is not possible. In addition, since large heavy machinery and a large amount of material are required for laying gravel, sand, etc., it is necessary to construct a construction road for transporting the material and heavy machinery, which increases the cost.

本発明の課題は、盛土堤体において、浸潤線を下げて力学的安定性を高めるためのドレーン構造の施工性・メンテナンス性を向上して、補修・維持管理が簡便で効果的に行えるようにすることである。   The object of the present invention is to improve the workability and maintainability of the drain structure for lowering the infiltration line and increasing the mechanical stability in the embankment embankment so that repair and maintenance can be performed easily and effectively. It is to be.

以上の課題を解決するため、請求項1に記載の発明は、盛土堤体の浸透水を裏法面側に排水するドレーン構造であって、例えば図1及び図2に示すように、盛土堤体2の裏法面側に埋設され、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材4を備えることを特徴とする。   In order to solve the above problems, the invention described in claim 1 is a drain structure for draining the seepage water of the embankment bank body to the back slope side, for example, as shown in FIG. 1 and FIG. An artificial drain material 4 is provided which is embedded on the back slope side of the body 2 and is made of at least one of a pipe-shaped drain material or a planar drain material through which permeated water passes.

このように、盛土堤体の裏法面側に、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材を埋設することで、盛土堤体の浸透水(間隙水)を人工ドレーン材に通して裏法面側に排水できる。これにより盛土堤体の浸潤線(地下水位)を下げて、盛土堤体の力学的安定性が高められる。
しかも、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材を埋設すれば良いことから、礫、砂等の天然材料を埋設する場合と比べて、施工性に優れるとともに、ドレーン材の洗浄や交換等のメンテナンス性にも優れる。
In this way, by embedding an artificial drain material composed of at least one of a pipe-shaped drain material or a planar drain material through which osmotic water passes on the back slope side of the embankment levee body, ) Can be drained to the back slope side through artificial drain material. This lowers the infiltration line (groundwater level) of the embankment embankment and increases the mechanical stability of the embankment embankment.
Moreover, since it is only necessary to embed an artificial drain material composed of at least one of a pipe-shaped drain material or a planar drain material through which permeated water passes, it is excellent in workability compared to the case of embedding natural materials such as gravel and sand. At the same time, it is excellent in maintenance such as cleaning and replacement of the drain material.

請求項2に記載の発明は、請求項1に記載の盛土堤体のドレーン構造であって、例えば図1及び図2に示すように、盛土堤体2の裏法面側において、前記人工ドレーン材4に接続される人工フィルター材5を備えることを特徴とする。   The invention according to claim 2 is the drainage structure of the embankment bank body according to claim 1, and the artificial drain is formed on the back slope side of the embankment bank body 2, for example, as shown in FIGS. 1 and 2. An artificial filter material 5 connected to the material 4 is provided.

このように、盛土堤体の裏法面側において、人工ドレーン材に人工フィルター材を接続しておくことで、排水に伴う盛土の流出を防げる。   Thus, the outflow of the embankment accompanying drainage can be prevented by connecting the artificial filter material to the artificial drain material on the back slope side of the embankment bank body.

請求項3に記載の発明は、請求項1または2に記載の盛土堤体のドレーン構造であって、例えば図1に示すように、前記人工ドレーン材4は、間隔を置いて平面視で櫛形に設けられることを特徴とする。   The invention according to claim 3 is the drainage structure of the embankment embankment according to claim 1 or 2, wherein, for example, as shown in FIG. 1, the artificial drain material 4 is comb-shaped in plan view at intervals. It is provided in.

このように、人工ドレーン材を、間隔を置いて平面視で櫛形に設けるようにすれば、全面にドレーン材を敷設する場合よりも施工が容易であり、ドレーン材の洗浄や交換等のメンテナンスも容易になる。   In this way, if the artificial drain material is provided in a comb shape in plan view at intervals, the construction is easier than when the drain material is laid on the entire surface, and maintenance such as cleaning and replacement of the drain material is also possible. It becomes easy.

請求項4に記載の発明は、請求項1から3のいずれか一項に記載の盛土堤体のドレーン構造であって、例えば図2に示すように、前記人工ドレーン材4は、裏法面側と反対側が盛土堤体2内で立ち上げられていることを特徴とする。   Invention of Claim 4 is the drainage structure of the embankment embankment body as described in any one of Claim 1 to 3, Comprising: For example, as shown in FIG. 2, the said artificial drain material 4 is a back slope. It is characterized in that the opposite side is raised in the embankment bank body 2.

このように、人工ドレーン材を、裏法面側と反対側を盛土堤体内で立ち上げておけば、ドレーン材の集水面積を増やせる。   Thus, if the artificial drain material is started up in the embankment on the opposite side to the back slope side, the water collection area of the drain material can be increased.

請求項5に記載の発明は、盛土堤体の浸透水を裏法面側に排水するドレーン施工方法であって、例えば図4から図7に示すように、盛土堤体2の裏法面側を掘削し、その掘削部21に、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材4を敷設した後、掘削部21を埋め戻して前記人工ドレーン材4を盛土堤体2内に埋設することを特徴とする。   The invention according to claim 5 is a drain construction method for draining the seepage water of the embankment bank body to the back slope side, for example, as shown in FIGS. 4 to 7, the back slope side of the embankment bank body 2. In the excavation part 21, the artificial drain material 4 made of at least one of a pipe-like drain material or a planar drain material through which permeated water passes is laid, and then the excavation part 21 is backfilled to attach the artificial drain material 4. It is embedded in the embankment dike body 2.

このように、盛土堤体の裏法面側の掘削部に、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材を敷設し、掘削部を埋め戻して盛土堤体内に埋設することで、請求項1に記載の発明と同様、礫、砂等の天然材料を埋設する場合と比べて、施工性に優れるとともに、ドレーン材の洗浄や交換等のメンテナンス性にも優れる。   In this way, artificial drainage material consisting of at least one of pipe-like drainage material or planar drainage material through which osmotic water passes is laid in the excavation part on the back slope side of the embankment bank body, and the excavation part is backfilled to fill the embankment bank By embedding in the body, as in the case of the invention described in claim 1, it is excellent in workability as compared with the case of embedding natural materials such as gravel and sand, and also in maintenance properties such as cleaning and replacement of drain materials. Excellent.

請求項6に記載の発明は、請求項5に記載の盛土堤体のドレーン施工方法であって、例えば図7に示すように、前記人工ドレーン材4の敷設後、盛土堤体2の裏法面側に人工フィルター材5を敷設して前記人工ドレーン材4に接続した後、前記掘削部21を埋め戻して前記人工フィルター材5も盛土堤体2内に埋設することを特徴とする。   The invention according to claim 6 is a method for draining a bank embankment according to claim 5, for example, as shown in FIG. 7, after laying the artificial drain material 4, the backside of the bank embankment body 2. After the artificial filter material 5 is laid on the surface side and connected to the artificial drain material 4, the excavation part 21 is backfilled and the artificial filter material 5 is also buried in the embankment bank 2.

このように、人工ドレーン材の敷設後、盛土堤体の裏法面側に人工フィルター材を敷設して人工ドレーン材に接続した後、掘削部を埋め戻して人工フィルター材も盛土堤体内に埋設することで、請求項2に記載の発明と同様、排水に伴う盛土の流出を防げる。   In this way, after laying the artificial drain material, lay the artificial filter material on the back slope side of the embankment dike body and connect it to the artificial drain material, then backfill the excavated part and embed the artificial filter material in the embankment dike body By doing so, the outflow of the embankment accompanying drainage can be prevented like the invention of Claim 2.

請求項7に記載の発明は、盛土堤体の浸透水を裏法面側に排水するドレーン施工方法であって、盛土堤体2の裏法面側に、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材4を、例えば圧入や水平ボーリング等して挿入することにより、盛土堤体2内に前記人工ドレーン材4を埋設することを特徴とする。   The invention according to claim 7 is a drain construction method for draining the infiltrated water of the embankment bank body to the back slope side, and a pipe-shaped drain material for passing the infiltrated water to the back slope side of the embankment bank body 2 or The artificial drain material 4 made of at least one of the planar drain materials is inserted by, for example, press-fitting or horizontal boring to embed the artificial drain material 4 in the embankment bank 2.

このように、盛土堤体の裏法面側に、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材を挿入して盛土堤体内に埋設することで、請求項1または5に記載の発明と同様、礫、砂等の天然材料を埋設する場合と比べて、施工性に優れるとともに、ドレーン材の洗浄や交換等のメンテナンス性にも優れる。   Thus, by inserting an artificial drain material consisting of at least one of a pipe-shaped drain material or a planar drain material through which permeated water passes into the back slope side of the embankment embankment, it is embedded in the embankment bank. Similar to the invention described in 1 or 5, it is excellent in workability as compared with the case of embedding natural materials such as gravel and sand, and is excellent in maintenance properties such as cleaning and replacement of the drain material.

請求項8に記載の発明は、請求項7に記載の盛土堤体のドレーン施工方法であって、前記人工ドレーン材4の挿入後、盛土堤体2の裏法面側に人工フィルター材5を、例えば圧入や水平ボーリング等により挿入して前記人工ドレーン材4に接続することにより、盛土堤体2内に前記人工フィルター材5も埋設することを特徴とする。   Invention of Claim 8 is the drain construction method of the embankment bank body of Claim 7, Comprising: After insertion of the said artificial drain material 4, the artificial filter material 5 is put on the back slope side of the embankment body 2 For example, the artificial filter material 5 is also embedded in the embankment bank body 2 by being inserted by press-fitting or horizontal boring or the like and connected to the artificial drain material 4.

このように、人工ドレーン材の挿入後、盛土堤体の裏法面側に人工フィルター材を挿入して人工ドレーン材に接続することにより、盛土堤体内に人工フィルター材も埋設することで、請求項2または6に記載の発明と同様、排水に伴う盛土の流出を防げる。 Thus, after inserting the artificial drain material, by inserting the artificial filter material on the back slope side of the embankment bank body and connecting it to the artificial drain material, the artificial filter material is also embedded in the embankment bank body, Similarly to the invention according to Item 2 or 6, the embankment can be prevented from flowing out due to drainage.

請求項9に記載の発明は、請求項5から8のいずれか一項に記載の盛土堤体のドレーン施工方法であって、例えば図5から図7に示すように、前記人工ドレーン材4を、間隔を置いて平面視で櫛形に敷設することを特徴とする。   Invention of Claim 9 is the drain construction method of the embankment embankment as described in any one of Claim 5 to 8, Comprising: As shown, for example in FIGS. 5-7, the said artificial drain material 4 is used. Laid out in a comb shape in plan view at intervals.

このように、人工ドレーン材を、間隔を置いて平面視で櫛形に敷設することで、請求項2に記載の発明と同様、全面にドレーン材を敷設する場合よりも施工が容易であり、ドレーン材の洗浄や交換等のメンテナンスも容易になる。   In this way, by constructing the artificial drain material in a comb shape in plan view at intervals, the construction is easier than in the case of laying the drain material on the entire surface, as in the invention of claim 2. Maintenance such as cleaning and replacement of materials is also facilitated.

本発明によれば、浸透水を人工ドレーン材に通して裏法面側に排水することにより盛土堤体の浸潤線を下げて、盛土堤体の力学的安定性を高めることができ、しかも、パイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材のため、礫、砂等の天然材料を埋設する場合と比べて、施工性に優れるとともに、ドレーン材の洗浄や交換等のメンテナンス性にも優れるといった利点が得られる。   According to the present invention, the infiltration line of the embankment can be lowered by draining the permeated water through the artificial drain material to the back slope side, and the mechanical stability of the embankment can be improved. Because it is an artificial drain material consisting of at least one of a pipe-shaped drain material or a planar drain material, it offers superior workability compared to the case of embedding natural materials such as gravel and sand, and maintenance such as cleaning and replacement of the drain material. Advantages such as excellent properties can be obtained.

以下、図を参照して本発明を実施するための最良の形態を詳細に説明する。
本発明を適用した一実施形態の構成を示す図1及び図2において、1は貯水、2は盛土堤体、3は底樋(樋管)、4は人工ドレーン材、5は人工フィルター材、Lは浸潤線である。
Hereinafter, the best mode for carrying out the present invention will be described in detail with reference to the drawings.
1 and 2 showing the configuration of an embodiment to which the present invention is applied, 1 is water storage, 2 is a bank embankment, 3 is a bottom gutter (pipe), 4 is an artificial drain material, 5 is an artificial filter material, L is an infiltrating line.

人工ドレーン材4は、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなるもので、盛土堤体2の裏法面側において、図1に示すように、間隔を置いて平面視で櫛形に配設して埋設されている。
また、人工ドレーン材4は、集水面積を増やすため、裏法面側と反対側が盛土堤体2内で立ち上げられている。図2の例において、人工ドレーン材4は、水平部41と、浸潤線L部分で水平部41に連続する垂直な立ち上がり部42とから構成されている。
The artificial drain material 4 is composed of at least one of a pipe-shaped drain material or a planar drain material through which permeated water passes, and on the back slope side of the embankment dike body 2, as shown in FIG. Arranged in a comb shape when viewed.
In addition, the artificial drain material 4 is raised in the embankment bank 2 on the opposite side to the back slope side in order to increase the water collection area. In the example of FIG. 2, the artificial drain material 4 includes a horizontal portion 41 and a vertical rising portion 42 that is continuous with the horizontal portion 41 at the infiltrating line L portion.

この人工ドレーン材4としては、例えば硬くて弾力性のあるPETボトルリサイクルのモノフィラメントをチューブ状に編み、PETリサイクルのスパンボンド不織布でくるんだ暗渠排水管で、パイプ状排水材と面状排水材の両方の機能をあわせ持ち、各種排水工において効果を発揮するモノドレン(登録商標)を使用する。
このモノドレン(登録商標)は、チューブ並列構造であるため集水性に優れ、フレキシブルで地山の凹凸になじみ、耐寒性・耐微生物性・耐薬品性に優れ、長尺・軽量で運搬・取付けが容易といった特長を具備する。
The artificial drain material 4 is, for example, a culvert drain pipe made of a hard and elastic PET bottle recycled monofilament knitted into a tube shape and wrapped with a PET recycled spunbond nonwoven fabric. Monodren (registered trademark) that has both functions and is effective in various drainage works is used.
This monodrain (registered trademark) has a tube-parallel structure, so it has excellent water collection, is flexible and conforms to the unevenness of the natural ground, is excellent in cold resistance, microbial resistance, and chemical resistance, and is long and lightweight for transportation and mounting. Features such as easy.

人工フィルター材5は、図1及び図2に示すように、盛土堤体2の裏法面において、前述のように平面視で櫛形に配設した複数の人工ドレーン材4に接続して埋設されている。
この人工フィルター材5としては、水を通し細流土砂を通さないフィルター材を使用する。例えばPETボトルリサイクルのポリエステルを素材に、ニードルパンチ及びバインダー加工した不織布で、ファイルター性、耐久性及び強度をあわせ持ち、各種土木工事(河川、造成等)において効果を発揮するサンドフ(登録商標)を使用する。
このサンドフ(登録商標)は、不織布構造のため目詰まりを起こさない、土圧により圧縮されても高い透水性を保持する、腐食しない、軽量のため取り扱い容易で施工が簡単といった特長を具備する。
As shown in FIGS. 1 and 2, the artificial filter material 5 is embedded on the back slope of the embankment dike body 2 by connecting to the plurality of artificial drain materials 4 arranged in a comb shape in plan view as described above. ing.
As the artificial filter material 5, a filter material that allows water to pass and does not pass trickle sand is used. For example, Sandf (registered trademark) is a non-woven fabric that is made of polyester recycled from PET bottles, needle punched and binder processed, and has both filterability, durability, and strength, and is effective in various civil engineering works (rivers, creation, etc.) Is used.
This Sandoff (registered trademark) has features such as no clogging due to a non-woven structure, high water permeability even when compressed by earth pressure, no corrosion, light weight and easy handling and easy construction.

なお、図3は盛土堤体2の水みちA及びエロージョンゾーンBを説明するものである。
本発明は水みちAによるパイピングの発生・進行を防止するドレーン施工である。図1では、エロージョンゾーンBの問題を防止するため、底樋3の周りに遮水部31を施工している。すなわち、底樋3の周りの漏水に対して盛土堤体2を掘削することなく、薬液やモルタルなどを注入することにより遮水部31を施工している。
FIG. 3 illustrates the water channel A and the erosion zone B of the embankment bank body 2.
The present invention is a drain construction for preventing the occurrence and progression of piping by the water channel A. In FIG. 1, in order to prevent the problem of the erosion zone B, the water-impervious portion 31 is constructed around the bottom gutter 3. That is, the water-impervious portion 31 is constructed by injecting a chemical solution, mortar, or the like without excavating the embankment bank body 2 against water leakage around the bottom gutter 3.

次に、具体的な盛土堤体ドレーン施工方法について説明する。
図4は掘削工程を示しており、まず、図示のように、底樋3から排水して貯水1の水位を低下させてから、盛土堤体2の裏法面を部分的に地盤まで掘削して部分掘削部21を形成する。この部分掘削部21は地盤までの掘削底面22から掘削法面23が連続している。
ここで、部分掘削部21から出た土砂は一時仮置きする。また、掘削法面23は安定勾配を確保しておきもしくは場合によっては補強材で支保する。
Next, the concrete embankment body drain construction method is demonstrated.
FIG. 4 shows the excavation process. First, as shown in the figure, after draining from the bottom gutter 3 to lower the water level of the reservoir 1, the back slope of the embankment dike body 2 is partially excavated to the ground. The partial excavation part 21 is formed. This partial excavation part 21 has an excavation slope 23 continuous from an excavation bottom surface 22 to the ground.
Here, the earth and sand coming out from the partial excavation part 21 is temporarily placed. Further, the excavation slope 23 has a stable gradient or is supported by a reinforcing material in some cases.

その後、次の人工ドレーン材敷設工程を示した図5のように、部分掘削部21において、底樋3と平行に人工ドレーン材4を敷設する。すなわち、掘削底面22に沿って人工ドレーン材水平部41を底樋3と平行に敷設して、掘削法面23に沿って人工ドレーン材立ち上がり部42を底樋3と平行に敷設する。
このようにして、人工ドレーン材4を、部分掘削部21に間隔を置いて平面視で櫛形に敷設していく。図示例は部分掘削部21に人工ドレーン材4を並べて5本敷設したものである。
After that, as shown in FIG. 5 showing the next artificial drain material laying step, the artificial drain material 4 is laid in parallel with the bottom rod 3 in the partial excavation portion 21. That is, the artificial drain material horizontal portion 41 is laid in parallel with the bottom rod 3 along the excavation bottom surface 22, and the artificial drain material rising portion 42 is laid in parallel with the bottom rod 3 along the excavation slope 23.
In this way, the artificial drain material 4 is laid in a comb shape in plan view with an interval between the partial excavation portions 21. In the illustrated example, five artificial drain members 4 are arranged on the partial excavation part 21 and laid.

その後、次の掘削部埋め戻し、人工フィルター材敷設及び近接部掘削工程を示した図6のように、隣接する部分を掘削するとともに、その掘削した土砂を既に人工ドレーン材4が敷設された部分掘削部21に埋め戻していく(埋め戻し土砂25参照)。この時、人工ドレーン材4の端部に接続させた状態で掘削底面22の端部に沿って人工フィルター材5を底樋3と直角に敷設する。   After that, as shown in FIG. 6 showing the next excavation part backfilling, artificial filter material laying and proximity part excavation steps, the adjacent part is excavated, and the excavated earth and sand is already laid with the artificial drain material 4 It backfills in the excavation part 21 (refer to the backfill earth and sand 25). At this time, the artificial filter material 5 is laid at right angles to the bottom rod 3 along the end portion of the excavation bottom surface 22 in a state of being connected to the end portion of the artificial drain material 4.

その後、次の繰り返し工程を示した図7のように、図5の人工ドレーン材敷設工程、図6の次の掘削部埋め戻し、人工フィルター材敷設及び近接部掘削工程を繰り返す。
ここで、底樋3の周辺の埋め戻しの際には、底樋3にベンドナイト等で吹き付け処理を行っておく。
Thereafter, as shown in FIG. 7 showing the next repetition process, the artificial drain material laying process of FIG. 5 and the next excavation part backfilling, artificial filter material laying and proximity part excavation process of FIG. 6 are repeated.
Here, at the time of backfilling around the bottom gutter 3, the bottom gutter 3 is sprayed with bendnite or the like.

以上により、図8に示したように、盛土堤体2に対するドレーン構造の施工が完成する。
以上のドレーン構造によれば、盛土堤体2の一部を掘削改良するため、供用中の施工が可能である。
しかも、ドレーン及びフィルターに人工材料を使用することにより軽量で施工性が優れているので、大型の重機や大型ダンプが不要であり、狭隘な地形や敷地が狭いサイトであっても施工が可能である。従って、工期・コストともに縮減できる。
As described above, as shown in FIG. 8, the construction of the drain structure for the embankment bank body 2 is completed.
According to the above drain structure, in order to excavate and improve a part of the embankment embankment body 2, construction in service is possible.
In addition, the use of artificial materials for drains and filters is lightweight and has excellent workability, so there is no need for large heavy machinery or large dump trucks, and construction is possible even in narrow terrain or sites with small sites. is there. Therefore, both the construction period and cost can be reduced.

そして、施工後においては、人工ドレーン材4及び人工フィルター材5により盛土堤体2内の間隙水を排水できるため、浸潤線Lが低下し、盛土堤体2の土粒子間の有効応力が増大する。従って、盛土堤体2の力学的安定性が増加し、豪雨時の決壊や破堤を防ぐことができる。
また、人工ドレーン材4及び人工フィルター材5は経時的に土粒子の流入により目詰まりが発生し排水機能が低下するが、盛土堤体2の裏法面側を掘削することによる人工ドレーン材4及び人工フィルター材5の洗浄・交換等のメンテナンス作業が容易であり、メンテナンスコストを低くして機能を回復することができる。
And after construction, since the drainage water in the embankment bank body 2 can be drained by the artificial drain material 4 and the artificial filter material 5, the infiltration line L is lowered, and the effective stress between the soil particles of the embankment bank body 2 is increased. To do. Therefore, the mechanical stability of the embankment dike body 2 is increased, and it is possible to prevent breakage and breakwater during heavy rain.
Further, the artificial drain material 4 and the artificial filter material 5 are clogged due to the inflow of soil particles over time and the drainage function is lowered. However, the artificial drain material 4 is obtained by excavating the back slope side of the embankment bank 2. In addition, maintenance work such as cleaning and replacement of the artificial filter material 5 is easy, and the function can be recovered by reducing the maintenance cost.

以上の実施形態は、盛土堤体2の裏法面側を掘削して人工ドレーン材4及び人工フィルター材5を敷設したが、盛土堤体2の裏法面側に人工ドレーン材4及び人工フィルター材5を挿入して敷設しても良い。
すなわち、盛土堤体2の裏法面側において、人工ドレーン材4及び人工フィルター材5を圧入したり、水平ボーリングしてから人工ドレーン材4及び人工フィルター材5を挿入する施工方法を採用することも可能である。
In the above embodiment, the artificial drain material 4 and the artificial filter material 5 are laid by excavating the back slope side of the embankment bank body 2, but the artificial drain material 4 and the artificial filter are disposed on the back slope side of the embankment bank body 2. The material 5 may be inserted and laid.
That is, on the back slope side of the embankment embankment body 2, a construction method is adopted in which the artificial drain material 4 and the artificial filter material 5 are press-fitted, or after the horizontal boring, the artificial drain material 4 and the artificial filter material 5 are inserted. Is also possible.

図9はドレーン材とフィルター材の接続例を示すもので、人工ドレーン材4の水平部41及び立ち上がり部42を接続し、その人工ドレーン材4の水平部41の先端に人工フィルター材5を接続する。すなわち、図示のように、不織布タイプの人工フィルター材5に水平部41の先端を差し込むように挟み込んで人工ドレーン材4と接続状態にする。   FIG. 9 shows a connection example of the drain material and the filter material. The horizontal portion 41 and the rising portion 42 of the artificial drain material 4 are connected, and the artificial filter material 5 is connected to the tip of the horizontal portion 41 of the artificial drain material 4. To do. That is, as shown in the drawing, the nonwoven fabric type artificial filter material 5 is sandwiched so as to insert the tip of the horizontal portion 41 to be connected to the artificial drain material 4.

以上において、盛土堤体2内に水位計もしくは間隙水圧計を設置して、浸潤線Lをモニタリングすることにより、盛土堤体2の安全性を随時確認するとともに、人工ドレーン材4及び人工フィルター材5のメンテナンス時期を把握する。
こうして、浸潤線Lの位置を定量的に把握することにより、盛土堤体2の力学的安定性を定量的に把握でき、すなわち、盛土堤体2の現在の安定性を定量的に評価・判断することができる。従って、盛土堤体2の維持補修の計画や災害時の現像把握に役立てることができる。
さらに、計測データを電話回線、インターネット等で転送することにより、災害時の避難指示等の判断材料とすることができる。
In the above, by installing a water level meter or a pore water pressure meter in the embankment dike 2 and monitoring the infiltration line L, the safety of the embankment dike body 2 is confirmed as needed, and the artificial drain material 4 and the artificial filter material 5 to know the maintenance time.
Thus, by quantitatively grasping the position of the infiltrating line L, the mechanical stability of the embankment body 2 can be grasped quantitatively, that is, the current stability of the embankment body 2 can be quantitatively evaluated and judged. can do. Therefore, it can be used for the maintenance repair plan of the embankment bank body 2 and the development grasp at the time of disaster.
Furthermore, by transferring the measurement data via a telephone line, the Internet, etc., it can be used as a judgment material such as an evacuation instruction at the time of a disaster.

図10は盛土堤体のモニタリングシステムの構成例を示すものである。
このモニタリングシステム例では、図示のように、貯水1中に水位計101を沈設して、盛土堤体2内に間隙水圧計102及び浸潤線計測器103を埋設し、盛土堤体2上に雨量計104を設置する。これら水位計101、間隙水圧計102、浸潤線計測器103及び雨量計104の計測データは現地計測システム110に送られる。
すなわち、現地計測システム110は、図示のように、水位計101、間隙水圧計102、浸潤線計測器103及び雨量計104の計測データをスイッチボックス111を介してデータロガー112に取り込む。そして、その計測データは、通信モデム113により電話回線または携帯電話回線116を介して通信モデム120に送信されて、計測用パソコン121に取り込まれる。
FIG. 10 shows a configuration example of the embankment monitoring system.
In this monitoring system example, as shown in the figure, a water level gauge 101 is set in the reservoir 1, a pore water pressure gauge 102 and an infiltrating line measuring instrument 103 are embedded in the embankment bank body 2, and the rainfall on the embankment bank body 2 A total of 104 is installed. The measurement data of the water level gauge 101, the pore water pressure gauge 102, the infiltrating line measuring instrument 103 and the rain gauge 104 are sent to the local measurement system 110.
That is, the on-site measurement system 110 takes in the measurement data of the water level meter 101, the pore water pressure meter 102, the infiltration line measuring device 103, and the rain gauge 104 into the data logger 112 via the switch box 111 as shown in the figure. Then, the measurement data is transmitted to the communication modem 120 via the telephone line or the cellular phone line 116 by the communication modem 113 and is taken into the measurement personal computer 121.

なお、以上の実施形態においては、人工ドレーン材を櫛形に敷設して設けたが、本発明はこれに限定されるものではなく、掘削部の全面に人工ドレーン材を並べて敷設しても良い。
また、実施形態では溜池の盛土堤体に適用したが、河川の盛土堤体にも同様に適用可能である。
さらに、人工ドレーン材や人工フィルター材の材質や形状等も実施形態に限らず任意であり、その他、具体的な細部構造等についても適宜に変更可能であることは勿論である。
In the above embodiment, the artificial drain material is laid in a comb shape, but the present invention is not limited to this, and the artificial drain material may be laid side by side on the entire surface of the excavation part.
Moreover, although it applied to the embankment body of a pond in embodiment, it is applicable similarly to the embankment body of a river.
Furthermore, the material, shape, and the like of the artificial drain material and the artificial filter material are not limited to those in the embodiment, and it is a matter of course that specific detailed structures and the like can be appropriately changed.

本発明を適用した盛土堤体の一実施形態の構成を示す概略斜視図である。It is a schematic perspective view which shows the structure of one Embodiment of the embankment embankment to which this invention is applied. 図1の盛土堤体の要部縦断面図である。It is a principal part longitudinal cross-sectional view of the embankment bank of FIG. 盛土堤体の水みち及びエロージョンゾーンを説明する縦断面図(a)及び概略平面図(b)である。It is the longitudinal cross-sectional view (a) and schematic plan view (b) explaining the water path and erosion zone of a bank embankment. 本発明によるドレーン施工手順を示すもので、掘削工程を示した縦断面図(a)及び概略平面図(b)である。The drain construction procedure by this invention is shown, and it is the longitudinal cross-sectional view (a) and schematic plan view (b) which showed the excavation process. 次の人工ドレーン材敷設工程を示した縦断面図(a)及び概略平面図(b)である。It is the longitudinal cross-sectional view (a) and schematic plan view (b) which showed the next artificial drain material laying process. 次の掘削部埋め戻し、人工フィルター材敷設及び近接部掘削工程を示した縦断面図(a)及び概略平面図(b)である。It is the longitudinal cross-sectional view (a) and schematic plan view (b) which showed the following excavation part backfilling, artificial filter material laying, and the proximity | contact part excavation process. 次の繰り返し工程を示した縦断面図(a)及び概略平面図(b)である。It is the longitudinal cross-sectional view (a) and schematic plan view (b) which showed the next repeating process. ドレーン施工完成を示した縦断面図(a)及び概略平面図(b)である。It is the longitudinal cross-sectional view (a) and schematic plan view (b) which showed drain construction completion. ドレーン材とフィルター材の接続例を示す平面図(a)と側面図(b)及び断面図(c)である。It is the top view (a) which shows the example of a connection of a drain material and a filter material, a side view (b), and sectional drawing (c). 盛土堤体のモニタリングシステムの一例を示す概略構成図である。It is a schematic block diagram which shows an example of the monitoring system of a bank embankment.

符号の説明Explanation of symbols

2 盛土堤体
21 掘削部
22 掘削底面
23 掘削法面
25 埋め戻し土砂
4 人工ドレーン材
41 水平部
42 立ち上がり部
5 人工フィルター材
L 浸潤線
2 Embankment 21 Excavation part 22 Excavation bottom face 23 Excavation slope 25 Backfill earth and sand 4 Artificial drain material 41 Horizontal part 42 Rising part 5 Artificial filter material L Infiltrating line

Claims (9)

盛土堤体の浸透水を裏法面側に排水するドレーン構造であって、
盛土堤体の裏法面側に埋設され、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材を備えることを特徴とする盛土堤体のドレーン構造。
A drain structure that drains the seepage water of the embankment bank to the back slope side,
A drainage structure for an embankment bank, comprising an artificial drain material that is embedded on the back slope side of the embankment bank and is made of at least one of a pipe-like drainage material or a planar drainage material through which permeated water passes.
盛土堤体の裏法面側において、前記人工ドレーン材に接続される人工フィルター材を備えることを特徴とする請求項1に記載の盛土堤体のドレーン構造。   The drain structure of the embankment bank according to claim 1, further comprising an artificial filter material connected to the artificial drain material on the back slope side of the embankment bank body. 前記人工ドレーン材は、間隔を置いて平面視で櫛形に設けられることを特徴とする請求項1または2に記載の盛土堤体のドレーン構造。   The drainage structure of an embankment embankment according to claim 1 or 2, wherein the artificial drain material is provided in a comb shape in plan view at intervals. 前記人工ドレーン材は、裏法面側と反対側が盛土堤体内で立ち上げられていることを特徴とする請求項1から3のいずれか一項に記載の盛土堤体のドレーン構造。   The drainage structure of a bank embankment according to any one of claims 1 to 3, wherein the artificial drain material is raised on the opposite side to the back slope side in the bank embankment. 盛土堤体の浸透水を裏法面側に排水するドレーン施工方法であって、
盛土堤体の裏法面側を掘削し、
その掘削部に、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材を敷設した後、
掘削部を埋め戻して前記人工ドレーン材を盛土堤体内に埋設することを特徴とする盛土堤体のドレーン施工方法。
A drain construction method of draining the seepage water of the embankment bank to the back slope side,
Excavate the back slope side of the embankment bank,
After laying an artificial drain material consisting of at least one of a pipe-like drain material or a planar drain material that allows permeate water to pass through the excavated part,
A drain construction method for a bank embankment, wherein the excavated portion is backfilled and the artificial drain material is embedded in the bank embankment.
前記人工ドレーン材の敷設後、
盛土堤体の裏法面側に人工フィルター材を敷設して前記人工ドレーン材に接続した後、前記掘削部を埋め戻して前記人工フィルター材も盛土堤体内に埋設することを特徴とする請求項5に記載の盛土堤体のドレーン施工方法。
After laying the artificial drain material,
The artificial filter material is laid on the back slope side of the embankment bank and connected to the artificial drain material, and then the excavation part is backfilled to embed the artificial filter material in the embankment bank. 5. A method for drain construction of embankment embankment according to 5.
盛土堤体の浸透水を裏法面側に排水するドレーン施工方法であって、
盛土堤体の裏法面側に、浸透水を通すパイプ状ドレーン材または面状ドレーン材の少なくとも一方からなる人工ドレーン材を挿入することにより、盛土堤体内に前記人工ドレーン材を埋設することを特徴とする盛土堤体のドレーン施工方法。
A drain construction method of draining the seepage water of the embankment bank to the back slope side,
The artificial drain material is embedded in the embankment bank by inserting an artificial drain material made of at least one of a pipe-shaped drain material or planar drain material through which permeated water passes on the back slope side of the embankment bank. Drain construction method for the embankment embankment that is characteristic.
前記人工ドレーン材の挿入後、
盛土堤体の裏法面側に人工フィルター材を挿入して前記人工ドレーン材に接続することにより、盛土堤体内に前記人工フィルター材も埋設することを特徴とする請求項7に記載の盛土堤体のドレーン施工方法。
After inserting the artificial drain material,
8. The embankment according to claim 7, wherein the artificial filter material is also embedded in the embankment by inserting an artificial filter material on the back slope side of the embankment and connecting to the artificial drain material. Body drain construction method.
前記人工ドレーン材を、間隔を置いて平面視で櫛形に敷設することを特徴とする請求項5から8のいずれか一項に記載の盛土堤体のドレーン施工方法。   The drainage construction method for a bank embankment according to any one of claims 5 to 8, wherein the artificial drain material is laid in a comb shape in plan view at intervals.
JP2005094750A 2005-03-29 2005-03-29 Drain structure of embankment bank and its construction method Active JP4675130B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005094750A JP4675130B2 (en) 2005-03-29 2005-03-29 Drain structure of embankment bank and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005094750A JP4675130B2 (en) 2005-03-29 2005-03-29 Drain structure of embankment bank and its construction method

Publications (2)

Publication Number Publication Date
JP2006274655A true JP2006274655A (en) 2006-10-12
JP4675130B2 JP4675130B2 (en) 2011-04-20

Family

ID=37209679

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005094750A Active JP4675130B2 (en) 2005-03-29 2005-03-29 Drain structure of embankment bank and its construction method

Country Status (1)

Country Link
JP (1) JP4675130B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2009016854A1 (en) * 2007-08-01 2009-02-05 Hidemasa Ota Method for preventing collapse of dike
JP2013060731A (en) * 2011-09-13 2013-04-04 Civil Engineering Research Laboratory Survey instrument for measuring pore water pressure
JP2020133311A (en) * 2019-02-22 2020-08-31 株式会社安藤・間 Reinforced earth structure, and earth structure reinforcing method
US10947690B2 (en) * 2019-04-18 2021-03-16 Hydro-Klean, Llc Trenchless method of installing a monolithic manhole in a levee for pipe access
CN114703799A (en) * 2022-03-18 2022-07-05 西安理工大学 Method for reducing dam slope infiltration surface of tailing dam with mud interlayer

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5760917U (en) * 1980-09-29 1982-04-10
JPH0734039U (en) * 1993-12-01 1995-06-23 開発工建株式会社 Underdrain drainage pipe
JPH07207639A (en) * 1994-01-20 1995-08-08 Unyusho Kowan Gijutsu Kenkyusho Beach stabilizing device
JP2002121720A (en) * 2000-10-12 2002-04-26 Kanto Regional Development Bureau Ministry Of Land Infrastructure & Transport Levee drain structure and its construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5760917U (en) * 1980-09-29 1982-04-10
JPH0734039U (en) * 1993-12-01 1995-06-23 開発工建株式会社 Underdrain drainage pipe
JPH07207639A (en) * 1994-01-20 1995-08-08 Unyusho Kowan Gijutsu Kenkyusho Beach stabilizing device
JP2002121720A (en) * 2000-10-12 2002-04-26 Kanto Regional Development Bureau Ministry Of Land Infrastructure & Transport Levee drain structure and its construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2009016854A1 (en) * 2007-08-01 2009-02-05 Hidemasa Ota Method for preventing collapse of dike
JP2013060731A (en) * 2011-09-13 2013-04-04 Civil Engineering Research Laboratory Survey instrument for measuring pore water pressure
JP2020133311A (en) * 2019-02-22 2020-08-31 株式会社安藤・間 Reinforced earth structure, and earth structure reinforcing method
JP7240667B2 (en) 2019-02-22 2023-03-16 株式会社安藤・間 Reinforced soil structure and soil structure reinforcement method
US10947690B2 (en) * 2019-04-18 2021-03-16 Hydro-Klean, Llc Trenchless method of installing a monolithic manhole in a levee for pipe access
CN114703799A (en) * 2022-03-18 2022-07-05 西安理工大学 Method for reducing dam slope infiltration surface of tailing dam with mud interlayer

Also Published As

Publication number Publication date
JP4675130B2 (en) 2011-04-20

Similar Documents

Publication Publication Date Title
KR100593786B1 (en) The construction of waterway for tunnel
US20030059258A1 (en) Under drainage method for building using perforated drain pipes
CN108487276A (en) A kind of embed-type shallow-layer combined water drain pipe and construction method
CN110029690B (en) Percolate leakage detection and collection structure and construction method thereof
JP4675130B2 (en) Drain structure of embankment bank and its construction method
CN114855846A (en) Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
CN208346836U (en) A kind of hidden drainage system
CN214194602U (en) Precipitation structure suitable for deep foundation pit of high-pressure-bearing water-rich karst stratum
CN104343177A (en) Subsurface drainage channel
CN109339095B (en) Retaining wall drainage system and wall back inverted filter layer construction method thereof
Heibaum et al. Hydraulic applications of geosynthetics
CN107724405B (en) Dewatering of foundation construction method in a kind of underground pipe construction
CN203057815U (en) Coastal saline-alkali soil greening alkali discharging system
Chu et al. Embankments on soft ground and ground improvement
KR101072407B1 (en) A build up method of filter layer for bank filtered water and a catchment apparatus of bank filtered water
CN112281806A (en) Spring soil roadbed unsaturated horizontal drainage device and construction method thereof
CN111676890A (en) Ecological reconstruction construction method for river bottom of black and odorous water body river
CN217480203U (en) Roadbed slope drainage
CN110616772A (en) Recharge system for rainwater storage and monitoring and construction method of recharge system
CN221167881U (en) Foundation pit hydrophobic structure suitable for under rich water stratum condition
CN109467143A (en) Phreatic water extracts restoration processing system and method out
CN219490576U (en) Drainage blind ditch structure
CN218713712U (en) Water guide structure for preventing water drainage channel from being frozen and expanded in high and cold areas
CN212426972U (en) Firmer pond dam protecting and building structure
CN217679251U (en) High and cold district retaining wall blind pipe water guide structure

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20060803

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080128

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20080128

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20080128

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090924

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20091013

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20091130

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110104

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110125

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140204

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4675130

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250