CN208346836U - A kind of hidden drainage system - Google Patents

A kind of hidden drainage system Download PDF

Info

Publication number
CN208346836U
CN208346836U CN201820648376.7U CN201820648376U CN208346836U CN 208346836 U CN208346836 U CN 208346836U CN 201820648376 U CN201820648376 U CN 201820648376U CN 208346836 U CN208346836 U CN 208346836U
Authority
CN
China
Prior art keywords
pipe
drainage system
horizontal
vertical
hidden drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820648376.7U
Other languages
Chinese (zh)
Inventor
杨庭友
余仁国
段军朝
龙宇
李宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201820648376.7U priority Critical patent/CN208346836U/en
Application granted granted Critical
Publication of CN208346836U publication Critical patent/CN208346836U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses a kind of hidden drainage systems, including horizontal collection system and vertical flow guide system, horizontal collection system is made of multiple horizontal collector pipes, and vertical flow guide system is made of multiple vertical diversion pipes, and horizontal collector pipe is connected with vertical diversion pipe by three-way connector.The hidden drainage system of the utility model, advantageously ensure that the stability of branch armour layer, improve the safety of entire base pit engineering, dry, clean working face is provided for subsequent waterproofing work simultaneously, the advantageous overall effect for improving main structure outsourcing waterproof, and this drainage system is easy for construction, flow path is clear, has taken into account safety and environmental protection and economic benefit, has good promotional value.

Description

A kind of hidden drainage system
Technical field
The utility model relates to construction field, in particular to a kind of hidden drainage system.
Background technique
In recent years, the numerous metro constructions in China are like a raging fire, urban track traffic be often in surrounding enviroment it is complicated, The intensive location of construction of structures, thus campshed system is largely used.The soil layer and foundation depth that campshed spacing is passed through according to it It is determined after being computed, branch of the injection pea gravel concreten retaining wall as branch armour layer for inter-pile soil is then added using steel mesh between stake Gear.
When foundation pit side-wall seeps water, the bright heat-extraction system such as aqueduct, disposal ditches need to be set, direct insertion draining is generallyd use System, i.e., for from passing through branch armour layer in the soil body of foundation pit periphery on the inside of foundation pit, at a certain angle and spacing is inserted into long 1m, diameter The PVC drain pipe of 50mm fills rubble along pvc pipe length direction, wraps up in geotextiles outside.But this method is without vertical guide system, only simple Chief of the Xiongnu in Acient China's foundation pit side-wall branch armour layer stretches out certain distance, and the infiltration of discharge is flowed directly to foundation pit side-wall branch armour layer by pvc pipe, suitable Side wall cross flow is to foundation pit bottom intercepting ditch, if meeting rainy season, backwater and diving amount are very big at the middle and upper levels for the soil body, and Interstitial Water is by pvc pipe in spray Shape injection is gushed, foundation pit side-wall branch armour layer is then in water scouring state with pressure for a long time, and local location meets with larger hydraulic pressure punching Brush, branch armour layer are easily destroyed weakening, form weak part, generate security risk.In addition, side wall branch armour layer is as draining road A ring in diameter, wall surface cannot keep dry, cleaning, when foundation pit waterproof roll is laid with, it is difficult to guarantee the closely connected of waterproof roll, Easily have an adverse effect to later period waterproof effect.
Therefore, it is badly in need of designing a drainage system that can satisfy demand.
Utility model content
The technical problem to be solved by the utility model is to provide a kind of hidden drainage system, be conducive to keep foundation pit Reliable and stable, dry, the clean drainage system of side wall, being used for Support types is campshed, and there are a large amount of upper layers are stagnant for local environment The deep-foundation pit engineering of water, diving.
Technical problem to be solved in the utility model is achieved through the following technical solutions:
A kind of hidden drainage system, including horizontal collection system and vertical flow guide system, the horizontal collection system by Multiple horizontal collector pipes are constituted, and the vertical flow guide system is made of multiple vertical diversion pipes, the horizontal collector pipe and described Vertical diversion pipe is connected by three-way connector.
Preferably, in above-mentioned technical proposal, the level set water pipe end is terminated on the inside of supporting surfacing steel bar net, each soil layer Infiltration converges through the three-way connector to the vertical diversion pipe after being collected by the horizontal collection system.
Preferably, in above-mentioned technical proposal, the vertical diversion pipe elongated setting on the inside of supporting surfacing steel bar net.
Preferably, in above-mentioned technical proposal, the vertical diversion pipe extends to bottom of foundation ditch along foundation pit side-wall, in bottom of foundation ditch By being pierced by branch armour layer, charge for remittance in pipe is expelled to the intercepting ditch of bottom of foundation ditch.
Preferably, in above-mentioned technical proposal, the horizontal collector pipe is the pvc pipe of diameter 50mm.The tube wall of the pvc pipe It is provided with the inlet opening of diameter 8mm spacing 100mm.
Preferably, in above-mentioned technical proposal, the vertical diversion pipe is the pvc pipe or soft water-permeable pipe of diameter 50mm.
Preferably, in above-mentioned technical proposal, the horizontal collector pipe and horizontal direction slightly form certain inclination, in order to Water energy is enough to be flowed downwardly into three-way connector along horizontal tube.
The utility model above-mentioned technical proposal, has the following beneficial effects:
Compared with prior art, the hidden drainage system of the utility model is suitable for the foundation pit work using campshed supporting Journey, for the hydrogeological environment locating for the base pit engineering there are when a large amount of perched water, diving, which advantageously ensures that supporting The stability of surface layer improves the safety of entire base pit engineering, while providing dry, clean work for subsequent waterproofing work Face, the advantageous overall effect for improving main structure outsourcing waterproof, while this drainage system is easy for construction, flow path is clear, simultaneous Safety and environmental protection and economic benefit have been cared for, there is good promotional value.
Detailed description of the invention
Fig. 1 is the plan view of the utility model.
Fig. 2 is vertically arranged schematic diagram for the utility model.
Fig. 3 is the main view of the utility model.
Fig. 4 is the horizontal collecting pipe drawing of the utility model.
Fig. 5 is the vertical water conservancy diversion tube end drawing of the utility model.
Specific embodiment
Specific embodiment of the present utility model is described in detail below, it is practical new in order to further understand this Type.
As shown, a kind of hidden drainage system, comprising: horizontal collection system and vertical flow guide system.Specifically:
Horizontal collection system is made of horizontal collector pipe 1, and vertical flow guide system is made of vertical diversion pipe 3, each component by Three-way connector 2 is connected.
Specifically, horizontal 1 end of collector pipe terminates in 4 inside of supporting surfacing steel bar net, and each soil layer infiltration collects system by level System converges through three-way connector 2 to vertical diversion pipe 3 after collecting.Preferably, horizontal collector pipe 1 is the pvc pipe of diameter 50mm.PVC The tube wall of pipe is provided with the inlet opening of diameter 8mm spacing 100mm.Certainly, the utility model is not limited thereto, art technology Personnel can select suitable pipe type and size as needed.
That is, horizontal collection system is similar to conventional direct insertion tapping pipe, after foundation pit successively excavates, in branch mask Pvc pipe, rectangular arrangement, according to the vertical spacing of each soil layer water percolating capacity controlled level collecting pipe and horizontal spacing are inserted into after layer.PVC Tube wall sets the inlet opening of diameter 8mm spacing 100mm, fills rubble pipe week to guarantee that water flow is unobstructed, wraps up in geotextiles outside to filter Infiltration avoids line clogging, and end is terminated in 4 inside of supporting surfacing steel bar net, reliably connected using three-way connection and vertical diversion pipe It connects, each soil layer infiltration is unified after being collected by horizontal collection system to converge to vertical diversion pipe.
Specifically, vertical diversion pipe 3 is along the 4 elongated setting in inside of supporting surfacing steel bar net.Vertical diversion pipe 3 is along foundation pit side-wall Bottom of foundation ditch is extended to, in bottom of foundation ditch by being pierced by branch armour layer, charge for remittance in pipe is expelled to the intercepting ditch 5 of bottom of foundation ditch.It is perpendicular The pvc pipe or soft water-permeable pipe for being diameter 50mm to diversion pipe 3.Certainly, the utility model is not limited thereto, art technology Personnel can select suitable pipe type and size as needed.
That is, the elongated setting on the inside of supporting surfacing steel bar net of vertical diversion pipe, by first of horizontal collecting pipe Begin, foundation pit bottom is extended to along foundation pit side-wall, using three-way connector (three-way connection), by all levels in same vertical plane Collecting pipe is connected, and forms one group of complete drainage channel in bottom of foundation ditch by being pierced by branch armour layer and charge for remittance in pipe is expelled to base Bottom intercepting ditch is cheated, the hole bright heat-extraction system in bottom is thus imported.Vertical diversion pipe is not necessarily to once mounting in place, with the layering of the earthwork Excavation is installed section by section according to the spacing of horizontal collecting pipe, and each section is reliably connected with finer wire and retaining wall steel mesh perpendicular to guarantee It is not shifted to diversion pipe when branch armour layer carries out concrete ejection, is indeformable.Should be noted while installation vertical diversion pipe away from Clear distance from steel mesh meets dado thickness design requirement, forms structural weak point after avoiding dado thickness from being weakened, is unfavorable for The safety of foundation pit.
In drainage system construction and use process, vertical water conservancy diversion pipe end should be made to be placed in always, concrete ejection is completed Branch armour layer lower end, to guarantee its drainability in the construction process, while answering the vertical diversion pipe nozzle of running check, with Blocking is excluded, keeps draining unobstructed.
Cubic metre of earth every excavation certain depth, in the soil body on the inside of horizontal collector pipe insertion branch armour layer, will fill in pipe week rubble with Guarantee that water flow is unobstructed, wraps up in geotextiles outside to avoid line clogging, controlling length makes horizontal tube end of collecting terminate in branch armour layer steel On the inside of muscle net, it is reliably connected followed by three-way connection and vertical diversion pipe.
The elongated setting on the inside of supporting surfacing steel bar net of vertical diversion pipe, but in place without once mounting, with the earthwork Stage excavation installed section by section according to the spacing of horizontal collecting pipe, complete this layer sewerage system installation after carry out foundation pit retaining wall reinforcing bar Rack is set, then is reliably connected the vertical diversion pipe of each section with retaining wall steel mesh with finer wire, to guarantee that vertical diversion pipe is propping up Armour layer do not shift when concrete ejection, is indeformable.Installation is originated by first of horizontal collecting pipe, layer-by-layer along foundation pit side-wall To foundation pit bottom, tube bottom end penetrates branch armour layer and stretches out certain length for installation, and charge for remittance is imported the hole bright heat-extraction system in bottom.In installation process It need to guarantee that vertical water conservancy diversion bottom of the tube is always positioned at concrete ejection finished surface or less to guarantee the drain function in work progress.
Hidden drainaging scheme is suitable for the base pit engineering of campshed supporting, which advantageously ensures that branch armour layer Stability, improves the safety of entire base pit engineering, while providing for the construction of subsequent outsourcing waterproofing work dry, clean Working face.
Although the utility model is disclosed as above with embodiment, so it is not intended to limit the utility model, any ability Field technique personnel can make a variety of different selections and modification, therefore this without departing from the spirit and scope of the utility model The protection scope of utility model is limited by claims and its equivalents.

Claims (8)

1. a kind of hidden drainage system, which is characterized in that including horizontal collection system and vertical flow guide system, the horizontal receipts Collecting system is made of multiple horizontal collector pipes (1), and the vertical flow guide system is made of multiple vertical diversion pipes (3), the water Flat collector pipe (1) is connected with the vertical diversion pipe (3) by three-way connector (2).
2. a kind of hidden drainage system according to claim 1, which is characterized in that horizontal collector pipe (1) end Terminate on the inside of supporting surfacing steel bar net (4), each soil layer infiltration collected by the horizontal collection system after through the three-way connector (2) it converges to the vertical diversion pipe (3).
3. a kind of hidden drainage system according to claim 1, which is characterized in that the vertical diversion pipe (3) is along branch Elongated setting on the inside of armour layer steel mesh (4).
4. a kind of hidden drainage system according to claim 1, which is characterized in that the vertical diversion pipe (3) is along base Hole side wall extends to bottom of foundation ditch, and in bottom of foundation ditch by being pierced by branch armour layer, charge for remittance in pipe is expelled to intercepting water for bottom of foundation ditch Ditch (5).
5. a kind of hidden drainage system according to claim 1, which is characterized in that the horizontal collector pipe (1) is PVC Pipe.
6. a kind of hidden drainage system according to claim 5, which is characterized in that be arranged on the tube wall of the pvc pipe There are the inlet opening of diameter 8mm, spacing 100mm.
7. a kind of hidden drainage system according to claim 1, which is characterized in that the vertical diversion pipe (3) is PVC Pipe or soft water-permeable pipe.
8. a kind of hidden drainage system according to claim 7, which is characterized in that the diameter of the pvc pipe is 50mm.
CN201820648376.7U 2018-05-02 2018-05-02 A kind of hidden drainage system Expired - Fee Related CN208346836U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820648376.7U CN208346836U (en) 2018-05-02 2018-05-02 A kind of hidden drainage system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820648376.7U CN208346836U (en) 2018-05-02 2018-05-02 A kind of hidden drainage system

Publications (1)

Publication Number Publication Date
CN208346836U true CN208346836U (en) 2019-01-08

Family

ID=64886737

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820648376.7U Expired - Fee Related CN208346836U (en) 2018-05-02 2018-05-02 A kind of hidden drainage system

Country Status (1)

Country Link
CN (1) CN208346836U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826199A (en) * 2019-04-09 2019-05-31 甘肃中建市政工程勘察设计研究院有限公司 Seep water white-out structure and its construction method outside a kind of foundation pit side-wall
CN111042162A (en) * 2019-12-18 2020-04-21 沈阳市政集团有限公司 Construction method for solving upper layer stagnant water in deep foundation pit construction by small-conduit drainage technology
WO2020147237A1 (en) * 2019-01-16 2020-07-23 济南城建集团有限公司 Method for construction of underground space structure across stratum in vadose zone

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020147237A1 (en) * 2019-01-16 2020-07-23 济南城建集团有限公司 Method for construction of underground space structure across stratum in vadose zone
CN109826199A (en) * 2019-04-09 2019-05-31 甘肃中建市政工程勘察设计研究院有限公司 Seep water white-out structure and its construction method outside a kind of foundation pit side-wall
CN111042162A (en) * 2019-12-18 2020-04-21 沈阳市政集团有限公司 Construction method for solving upper layer stagnant water in deep foundation pit construction by small-conduit drainage technology

Similar Documents

Publication Publication Date Title
CN104480974B (en) Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN208346836U (en) A kind of hidden drainage system
CN210066791U (en) A precipitation combined system that is used for foundation ditch pressure release precipitation and dredges precipitation
CN210658227U (en) Ecological slope protection structure
CN106087953B (en) A kind of drainage and construction method for preventing and treating mountain area large size spoil ground mud-rock flow
CN106192665A (en) A kind of sponge urban road rain infiltration system and construction method thereof
CN104499560A (en) Combined rainwater seepage well and construction method
CN106193249B (en) Water collecting and leaching system and construction method thereof
CN206667420U (en) Sponge city high-effective penetrating type greenery patches constructs
CN209824682U (en) Slope greening structure
CN103266633A (en) Seepage-proof sewage discharging and floodwater draining method for tailing reservoir in wet metallurgy
CN206245444U (en) Rainwater penetration system
WO2024174557A1 (en) System for rapid desalination of sandy soil blown into dike at estuary before planting green plants
CN210797594U (en) Ecological reinforced structure of side slope
CN105970882B (en) Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN210797803U (en) Anti-blocking drain pipe
CN109826199A (en) Seep water white-out structure and its construction method outside a kind of foundation pit side-wall
CN205935147U (en) Water collecting, draining and leaching system
CN212153625U (en) Urban construction rainwater garden
CN212983770U (en) Hydraulic engineering protects bearing structure with ecological bank protection
CN209397606U (en) Near-river sinking tunnel foundation pit excavation is strutted and is fallen stagnant water structure
CN211036611U (en) Road surface structure in sponge city
CN112095548A (en) Method for treating river landslide
CN208917962U (en) A kind of sponge type bimetallic tube drainage system
CN112088602A (en) Saline-alkali soil salt elimination concealed conduit and construction method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190108

Termination date: 20190502