US10947690B2 - Trenchless method of installing a monolithic manhole in a levee for pipe access - Google Patents

Trenchless method of installing a monolithic manhole in a levee for pipe access Download PDF

Info

Publication number
US10947690B2
US10947690B2 US16/851,772 US202016851772A US10947690B2 US 10947690 B2 US10947690 B2 US 10947690B2 US 202016851772 A US202016851772 A US 202016851772A US 10947690 B2 US10947690 B2 US 10947690B2
Authority
US
United States
Prior art keywords
levee
manhole
tubular member
pipe
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active, expires
Application number
US16/851,772
Other versions
US20200332488A1 (en
Inventor
Matt Huston
Michael Ingham
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydro Klean LLC
Original Assignee
Hydro Klean LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydro Klean LLC filed Critical Hydro Klean LLC
Priority to US16/851,772 priority Critical patent/US10947690B2/en
Assigned to HYDRO-KLEAN, LLC reassignment HYDRO-KLEAN, LLC ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: HUSTON, MATT, INGHAM, MICHAEL
Publication of US20200332488A1 publication Critical patent/US20200332488A1/en
Application granted granted Critical
Publication of US10947690B2 publication Critical patent/US10947690B2/en
Assigned to NXT CAPITAL, LLC, AS AGENT reassignment NXT CAPITAL, LLC, AS AGENT SECURITY INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: HYDRO-KLEAN, LLC
Active legal-status Critical Current
Adjusted expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/14Covers for manholes or the like; Frames for covers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving

Definitions

  • the present invention is directed toward a method of forming a manhole in a levy, without trenching, to provide access to drain pipes in the levee, so the pipes can be maintained or repaired.
  • Drain tile pipes are typically installed within a levee that run parallel with the levee along the body of water.
  • a perforated pipe installed within the body of the levee is designed to carry away water that has saturated the levee during various levels of river flood stage.
  • the perforated pipe is connected to a transverse solid collector pipe, which in turn is connected to a pump for the purpose of pumping the collected water back to the river side of the levee.
  • there is no access to the drain tile pipes for maintenance and repair thus requiring a trench to be dug into the levee for access to the pipes.
  • the trench can compromise the integrity of the levee, and lead to potential failure of the levee and subsequent flooding.
  • a primary objective of the present invention is the provision of a trenchless method of installing a manhole in a levee for drain pipe access.
  • Another objective of the present invention is the provision of a method of installing a manhole in a levee which preserves the strength and integrity of the levee.
  • Yet another objective of the present invention is the provision of a manhole levee which can be retrofit into an existing levee.
  • a further objective of the present invention is the provision of a method of constructing a levee manhole having any desired diameter and height.
  • Another objective of the present invention is the provision of a method of constructing a manhole in a levee for accessing a drain line without trenching into the levee.
  • Still another objective of the present invention is the provision of a method of installing a monolithic manhole in a levee which is economical and safe.
  • a trenchless method of installing a monolithic manhole in the levee for pipe access is economical and safe.
  • the method includes an initial step of pushing an outer tubular member downwardly into the earthen levee, preferably by vacuum excavation.
  • a floor or base may be formed in the bottom of the outer tube, such as with poured concrete.
  • an inner tubular member is lowered into the outer tubular member, with a gap or annular space between the outer and inner tubular members.
  • the space is then filled with concrete, or other material, to form a monolithic manhole from the floor to the ground surface.
  • an upper portion of the exposed pipe within the manhole can be removed for internal access to the pipe.
  • a sloped cap may also be poured on top of the floor to drain toward the pipe opening.
  • a cover may be bolted or otherwise removably connected to the top of the manhole wall.
  • FIG. 1 is an elevation view of the levee with a drain pipe, a collection pipe, and a manhole formed in accordance with the present invention.
  • FIG. 2 is an exploded schematic of the components for forming the manhole in the levee.
  • FIG. 3 is a sectional view of the monolithic manhole, taken along lines 3 - 3 of FIG. 1 .
  • FIG. 1 shows a levee 10 with at least one perforated drain tile pipe 11 running lengthwise along the levee, and at least one solid collector drain pipe 12 , extending transverse to the levee from the drain tile pipe 11 to a pump station (not shown), at the base of the levee on the land side 16 .
  • the levee 10 is constructed adjacent a body of water 14 to protect the land 16 from flooding.
  • the pump station is operatively connected to the collector pipe 12 to pump collected water back to the water side 14 of the levee 10 .
  • the levee 10 and drain pipes 11 , 12 are conventional and may have a variety of constructions.
  • the method of installing the new, poured-in-place manhole 20 begins by determining the location that the manhole is to be installed in the levee 10 for intersecting with one or both of the drain pipes 11 , 12 .
  • One option for selecting or determining the manhole location is to extend a camera with a transmitter, such as a Sonde transmitter, in one end of the pipe 11 or 12 or at a downstream access point. The camera is pushed upstream to view the pipe and to position a transmitter. An above-ground receiver senses a signal from the transmitter within the pipe. The camera is moved through the pipe to a position corresponding to the desired position for the manhole.
  • a transmitter such as a Sonde transmitter
  • a hollow tube 22 is forced downwardly from the upper surface of the levee 10 using a vacuum excavator.
  • the tube 22 is approximately 60 inches in diameter and made of any suitable material, such as fiberglass.
  • the tube 22 may have other dimensions and may be made of different materials.
  • the vacuum excavator removes the levee material or soil from the interior of the tube 22 , thereby allowing the tube 22 to be lowered into the levee.
  • the tube 22 is notched 24 at the lower end, which allows the tube 22 to be saddled over the pipe 11 or 12 until the tube is at the desired final elevation, with the bottom of the tube 22 being approximately 6 inches below the pipe.
  • the tube 22 may be position over the perforated pipe 11 or the solid collector pipe 12 , or at the T intersection of these pipes.
  • concrete such as ready-mixed concrete
  • the base 25 is sloped downwardly toward the pipe, as shown in FIG. 3 , though the base may be horizontal.
  • the pipe 11 and/or 12 is opened by cutting and removing the top half of the pipe inside the tube 22 . The opening may extend the full diameter of the tube or may be a shorter segment of the pipe.
  • the soil surrounding the exterior of the tube 22 that has been disturbed during the vacuum excavation process may need stabilization.
  • One method for stabilizing the soil is by injecting hydrophobic liquid polyurethane to fill voids and fissures.
  • the stabilizing material may be injected through ports drilled through the tube 22 or through probes installed vertically around the exterior of the tube 22 .
  • the stabilization step creates a rigid and dense closed soil/grout matrix to solidify soils on the exterior of the manhole 20 .
  • Other soil stabilization methods may also be used.
  • a cylindrical manhole forming system 26 is lowered into the tube 22 so as to be concentric within the tube 22 and define an annular space 28 between the interior of the tube 22 and the exterior of the forming system 26 .
  • a forming system is the Monoform by HydroKlean, LLC used for rehabilitating deteriorated manholes, such as old brick manholes.
  • the gap 28 between the tube 22 and the forming system 26 is approximately 10 inches but can vary in thickness based on factors such as buoyancy mitigation calculations.
  • the forming system 26 may include multiple cylindrical sections 30 with various diameters and rise heights, with tapered reducing sections to connect the different diameter straight sections.
  • the initial base or bottom section may have a 40-inch diameter and is set level and plum on the base 25 , which serves as the footing for the forming system 26 .
  • both the drainage pipe 11 and the collector pipe 12 will be slipped or “blocked out”, with inserts butted to the base and extending slightly into the pipe connections.
  • the additional sections of the forming system 26 are then installed above the base 25 , to the final elevation height of the manhole 20 .
  • the top of the forming structure 26 includes a conical section 32 , which can reduce the diameter of the forming system to approximately 26 inches.
  • the conical section 32 defines an access opening 34 at the top of the manhole 20 .
  • the opening 34 may be concentric or eccentric to the center axis of the manhole 20 .
  • Concrete such as ready-mixed concrete, or other material is then poured into the annular space 28 between the outer tube 22 and the inner forming tubes 26 so as to create the new monolithic concrete manhole wall 36 .
  • the final height or elevation of the wall 36 may be flush with the levee 10 or may extend above the levee.
  • the forming system 26 is removed to expose the newly poured walls.
  • the pipe slips or “block out” inserts (not shown) can also be removed from the pipe 11 , 12 so that the upper cut out 38 is open.
  • a cap 40 may be formed in the bottom of the manhole, on top of the base 25 , after the concrete wall 36 is poured.
  • the cap 40 has a 1 inch per foot slope from the spring-line of the exposed pipe 11 , 12 and extending to the manhole wall. The cap provides a seal at the interface of the base 25 and the wall 36 .
  • the top is provided with a frame 42 and a removable cover 44 .
  • the frame 42 may be set on a gasket and fastened or otherwise secured to the top of the wall with stainless steel anchor bolts.
  • the cover 44 is preferably bolted to the frame 42 , for example using stainless steel bolts, or may be pivotally connected to the frame for movement between open and closed positions.
  • the site may be cleaned up by disposal of the levee soil and materials removed from inside the tube 22 .
  • the soil around the top of the manhole 20 can be finished to eliminate any remaining evidence of the construction process, such as mulching, seeding, or sodding.
  • the manhole installation method of the present invention eliminates trenching of the levee and produces a monolithic concrete wall without affecting the integrity of the levee 10 .
  • the manhole may be made to any desired height and diameter.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Sewage (AREA)

Abstract

A monolithic manhole is formed in a levee without trenching, to provide access to drain pipes within the levee for maintenance and repair of the pipes. The manhole is formed by first forcing an outer tube downwardly into the earth and levee and removing soil from within the outer tube to expose the pipe. An inner tube is lowered into the outer tube, with an annular space maintained between the tubes. The annular space is filled with concrete, which hardens to form a monolithic vertical wall. A concrete floor may be poured at the bottom of the wall and a cover attached to the top of the wall. A hole is cut in the pipe inside the wall to provide internal access to the pipe.

Description

CROSS-REFERENCE TO RELATED APPLICATIONS
This application claims priority to Provisional Application U.S. Ser. No. 62/835,567, filed on Apr. 18, 2019, which is herein incorporated by reference in its entirety.
FIELD OF INVENTION
The present invention is directed toward a method of forming a manhole in a levy, without trenching, to provide access to drain pipes in the levee, so the pipes can be maintained or repaired.
BACKGROUND OF THE INVENTION
Earthen levees are often built along rivers, and other bodies of water for flood control. Drain tile pipes are typically installed within a levee that run parallel with the levee along the body of water. For example, a perforated pipe installed within the body of the levee is designed to carry away water that has saturated the levee during various levels of river flood stage. The perforated pipe is connected to a transverse solid collector pipe, which in turn is connected to a pump for the purpose of pumping the collected water back to the river side of the levee. Often, there is no access to the drain tile pipes for maintenance and repair, thus requiring a trench to be dug into the levee for access to the pipes. However, the trench can compromise the integrity of the levee, and lead to potential failure of the levee and subsequent flooding.
Therefore, there is a need to provide access to drain pipes within a levee, without jeopardizing or damaging the integrity of the levee.
Accordingly, a primary objective of the present invention is the provision of a trenchless method of installing a manhole in a levee for drain pipe access.
Another objective of the present invention is the provision of a method of installing a manhole in a levee which preserves the strength and integrity of the levee.
Yet another objective of the present invention is the provision of a manhole levee which can be retrofit into an existing levee.
A further objective of the present invention is the provision of a method of constructing a levee manhole having any desired diameter and height.
Another objective of the present invention is the provision of a method of constructing a manhole in a levee for accessing a drain line without trenching into the levee.
Still another objective of the present invention is the provision of a method of installing a monolithic manhole in a levee which is economical and safe.
These and other objectives will become apparent from the following description of the invention.
SUMMARY OF THE INVENTION
A trenchless method of installing a monolithic manhole in the levee for pipe access is economical and safe. The method includes an initial step of pushing an outer tubular member downwardly into the earthen levee, preferably by vacuum excavation. After the outer tube reaches the depth of the pipe, a floor or base may be formed in the bottom of the outer tube, such as with poured concrete. After the floor is formed, an inner tubular member is lowered into the outer tubular member, with a gap or annular space between the outer and inner tubular members. The space is then filled with concrete, or other material, to form a monolithic manhole from the floor to the ground surface. Then, an upper portion of the exposed pipe within the manhole can be removed for internal access to the pipe. A sloped cap may also be poured on top of the floor to drain toward the pipe opening. A cover may be bolted or otherwise removably connected to the top of the manhole wall.
BRIEF DESCRIPTION OF THE DRAWINGS
FIG. 1 is an elevation view of the levee with a drain pipe, a collection pipe, and a manhole formed in accordance with the present invention.
FIG. 2 is an exploded schematic of the components for forming the manhole in the levee.
FIG. 3 is a sectional view of the monolithic manhole, taken along lines 3-3 of FIG. 1.
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 shows a levee 10 with at least one perforated drain tile pipe 11 running lengthwise along the levee, and at least one solid collector drain pipe 12, extending transverse to the levee from the drain tile pipe 11 to a pump station (not shown), at the base of the levee on the land side 16. The levee 10 is constructed adjacent a body of water 14 to protect the land 16 from flooding. The pump station is operatively connected to the collector pipe 12 to pump collected water back to the water side 14 of the levee 10. The levee 10 and drain pipes 11, 12 are conventional and may have a variety of constructions.
The method of installing the new, poured-in-place manhole 20 begins by determining the location that the manhole is to be installed in the levee 10 for intersecting with one or both of the drain pipes 11, 12. One option for selecting or determining the manhole location is to extend a camera with a transmitter, such as a Sonde transmitter, in one end of the pipe 11 or 12 or at a downstream access point. The camera is pushed upstream to view the pipe and to position a transmitter. An above-ground receiver senses a signal from the transmitter within the pipe. The camera is moved through the pipe to a position corresponding to the desired position for the manhole.
Once the new manhole position is set, a hollow tube 22 is forced downwardly from the upper surface of the levee 10 using a vacuum excavator. In one embodiment, the tube 22 is approximately 60 inches in diameter and made of any suitable material, such as fiberglass. The tube 22 may have other dimensions and may be made of different materials. The vacuum excavator removes the levee material or soil from the interior of the tube 22, thereby allowing the tube 22 to be lowered into the levee. The tube 22 is notched 24 at the lower end, which allows the tube 22 to be saddled over the pipe 11 or 12 until the tube is at the desired final elevation, with the bottom of the tube 22 being approximately 6 inches below the pipe. The tube 22 may be position over the perforated pipe 11 or the solid collector pipe 12, or at the T intersection of these pipes.
Next, concrete, such as ready-mixed concrete, is placed at the bottom of the fiberglass tube 22 and poured to a thickness of approximately 6 inches, or to the lowest pipe invert elevation, so as to form a base or foundation 25. Preferably, the base 25 is sloped downwardly toward the pipe, as shown in FIG. 3, though the base may be horizontal. After the concrete has sufficiently cured, the pipe 11 and/or 12 is opened by cutting and removing the top half of the pipe inside the tube 22. The opening may extend the full diameter of the tube or may be a shorter segment of the pipe.
The soil surrounding the exterior of the tube 22 that has been disturbed during the vacuum excavation process may need stabilization. One method for stabilizing the soil is by injecting hydrophobic liquid polyurethane to fill voids and fissures. The stabilizing material may be injected through ports drilled through the tube 22 or through probes installed vertically around the exterior of the tube 22. The stabilization step creates a rigid and dense closed soil/grout matrix to solidify soils on the exterior of the manhole 20. Other soil stabilization methods may also be used.
A cylindrical manhole forming system 26 is lowered into the tube 22 so as to be concentric within the tube 22 and define an annular space 28 between the interior of the tube 22 and the exterior of the forming system 26. One example of a forming system is the Monoform by HydroKlean, LLC used for rehabilitating deteriorated manholes, such as old brick manholes. Preferably, the gap 28 between the tube 22 and the forming system 26 is approximately 10 inches but can vary in thickness based on factors such as buoyancy mitigation calculations. The forming system 26 may include multiple cylindrical sections 30 with various diameters and rise heights, with tapered reducing sections to connect the different diameter straight sections. For example, the initial base or bottom section may have a 40-inch diameter and is set level and plum on the base 25, which serves as the footing for the forming system 26. Preferably, both the drainage pipe 11 and the collector pipe 12 will be slipped or “blocked out”, with inserts butted to the base and extending slightly into the pipe connections. The additional sections of the forming system 26 are then installed above the base 25, to the final elevation height of the manhole 20. The top of the forming structure 26 includes a conical section 32, which can reduce the diameter of the forming system to approximately 26 inches. The conical section 32 defines an access opening 34 at the top of the manhole 20. The opening 34 may be concentric or eccentric to the center axis of the manhole 20.
Concrete, such as ready-mixed concrete, or other material is then poured into the annular space 28 between the outer tube 22 and the inner forming tubes 26 so as to create the new monolithic concrete manhole wall 36. The final height or elevation of the wall 36 may be flush with the levee 10 or may extend above the levee. After the concrete has cured or obtained sufficient strength so as to avoid slumping, the forming system 26 is removed to expose the newly poured walls. The pipe slips or “block out” inserts (not shown) can also be removed from the pipe 11, 12 so that the upper cut out 38 is open.
A cap 40 may be formed in the bottom of the manhole, on top of the base 25, after the concrete wall 36 is poured. Preferably, the cap 40 has a 1 inch per foot slope from the spring-line of the exposed pipe 11, 12 and extending to the manhole wall. The cap provides a seal at the interface of the base 25 and the wall 36.
After the concrete wall 36 has cured, the top is provided with a frame 42 and a removable cover 44. The frame 42 may be set on a gasket and fastened or otherwise secured to the top of the wall with stainless steel anchor bolts. The cover 44 is preferably bolted to the frame 42, for example using stainless steel bolts, or may be pivotally connected to the frame for movement between open and closed positions.
After the manhole 20 is constructed, the site may be cleaned up by disposal of the levee soil and materials removed from inside the tube 22. The soil around the top of the manhole 20 can be finished to eliminate any remaining evidence of the construction process, such as mulching, seeding, or sodding.
The manhole installation method of the present invention eliminates trenching of the levee and produces a monolithic concrete wall without affecting the integrity of the levee 10. The manhole may be made to any desired height and diameter.
The invention has been shown and described above with the preferred embodiments, and it is understood that many modifications, substitutions, and additions may be made which are within the intended spirit and scope of the invention. From the foregoing, it can be seen that the present invention accomplishes at least all of its stated objectives.

Claims (20)

What is claimed:
1. A method of creating a manhole in a soil levee having a drain pipe, comprising:
determining a location of the manhole so as to intersect the drain pipe;
inserting an outer tube vertically into the levee by vacuum excavation, so as to remove soil from inside the outer tube;
inserting an inner tube inside the outer tube so as to provide an annular space between the tubes; and
pouring concrete into the space to form a monolith concrete manhole wall.
2. The method of claim 1 further comprising removing the inner tube after the concrete has cured to a non-slump strength.
3. The method of claim 1 further comprising pouring a concrete base in the bottom of the outer tube before the inner tube is inserted.
4. The method of claim 3 further comprising forming a sloped cap on the base after the inner tube is inserted.
5. The method of claim 1 further comprising adding a stabilizer to the soil around the outer tube.
6. The method of claim 1 further comprising providing a cover on top of the manhole wall.
7. The method of claim 6, further comprising attaching a frame to a top of the manhole wall, with the cover being secured to the frame.
8. The method of claim 1 wherein the inner tube includes multiple cylindrical sections stacked one upon another.
9. The method of claim 8 wherein the sections have different diameters to create different diameters along the manhole wall.
10. The method of claim 1 wherein the manhole is formed without digging a trench in the levee.
11. A method of providing access to a pipe in an earthen levee, comprising:
forcing an outer tubular member downwardly into the levee until a bottom of the outer tubular member is at least level with the pipe; then
removing soil within the outer tubular member; then
lowering an inner tubular member into the outer tubular member so as to form an annular space between the outer and inner tubular members; then
filling the annular space with material to form an annular wall; and
removing an upper piece of the pipe within the annular wall to expose the interior of the pipe.
12. The method of claim 11 wherein the inner tubular member has multiple stacked sections.
13. The method of claim 11 further comprising removing the inner tubular member after the annular wall is solidified.
14. The method of claim 11 further comprising forming a floor inside the outer tubular member before the inner tubular member is lowered.
15. The method of claim 14 further comprising forming a cap on top of the floor sloping downwardly from the annular wall to the pipe.
16. The method of claim 11 further comprising adding soil stabilizer material around the outer tubular member.
17. The method of claim 11 further comprising providing a cover on top of the annular wall above the levee.
18. The method of claim 11 wherein the annular wall is formed without trenching into the levee.
19. The method of claim 11 wherein the soil is removed from inside the outer tubular member by vacuum excavating.
20. The method of claim 11 wherein the soil is removed as the outer tubular member is forced downwardly into the levee.
US16/851,772 2019-04-18 2020-04-17 Trenchless method of installing a monolithic manhole in a levee for pipe access Active 2040-05-06 US10947690B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US16/851,772 US10947690B2 (en) 2019-04-18 2020-04-17 Trenchless method of installing a monolithic manhole in a levee for pipe access

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US201962835567P 2019-04-18 2019-04-18
US16/851,772 US10947690B2 (en) 2019-04-18 2020-04-17 Trenchless method of installing a monolithic manhole in a levee for pipe access

Publications (2)

Publication Number Publication Date
US20200332488A1 US20200332488A1 (en) 2020-10-22
US10947690B2 true US10947690B2 (en) 2021-03-16

Family

ID=72833030

Family Applications (1)

Application Number Title Priority Date Filing Date
US16/851,772 Active 2040-05-06 US10947690B2 (en) 2019-04-18 2020-04-17 Trenchless method of installing a monolithic manhole in a levee for pipe access

Country Status (1)

Country Link
US (1) US10947690B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20240011237A1 (en) * 2022-07-11 2024-01-11 Hydro-Klean, Llc System and method for extending the height of a manhole

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11808003B2 (en) * 2021-02-01 2023-11-07 Hydro-Klean, Llc Method of rehabilitating a manhole

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3621623A (en) * 1970-03-23 1971-11-23 Allan Macmillan Downes Apparatus for temporarily closing an opening formed at the top of vertical walls of a catch basin manhole or the like
US4127990A (en) * 1977-01-21 1978-12-05 Morrow Otis L Drainage structure forming method
JPH08333763A (en) * 1995-06-06 1996-12-17 Ichisawa Concrete Kogyo Kk Manufacture of pipe mounting block of manhole
JP2006274655A (en) * 2005-03-29 2006-10-12 National Institute For Rural Engineering Drain structure of embankment and its construction method
JP2012237094A (en) * 2011-05-10 2012-12-06 Nit:Kk Manhole flotation preventing method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3621623A (en) * 1970-03-23 1971-11-23 Allan Macmillan Downes Apparatus for temporarily closing an opening formed at the top of vertical walls of a catch basin manhole or the like
US4127990A (en) * 1977-01-21 1978-12-05 Morrow Otis L Drainage structure forming method
JPH08333763A (en) * 1995-06-06 1996-12-17 Ichisawa Concrete Kogyo Kk Manufacture of pipe mounting block of manhole
JP2006274655A (en) * 2005-03-29 2006-10-12 National Institute For Rural Engineering Drain structure of embankment and its construction method
JP2012237094A (en) * 2011-05-10 2012-12-06 Nit:Kk Manhole flotation preventing method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20240011237A1 (en) * 2022-07-11 2024-01-11 Hydro-Klean, Llc System and method for extending the height of a manhole
US12221760B2 (en) * 2022-07-11 2025-02-11 Hydro-Klean, Llc System and method for extending the height of a manhole

Also Published As

Publication number Publication date
US20200332488A1 (en) 2020-10-22

Similar Documents

Publication Publication Date Title
CN109339079B (en) Foundation pit water stopping system adjacent to river permeable stratum and construction process thereof
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN105442532A (en) Construction method for pile-head-expanded bored pile
US10947690B2 (en) Trenchless method of installing a monolithic manhole in a levee for pipe access
CN114086969B (en) Tunnel entering construction method
KR20140096731A (en) Underground water drainage system of excavated ground and pipeline construction method using the same
CN114606964B (en) Foundation pit dewatering method used under complex geological conditions
CN101319501B (en) Construction method of deep foundation ditch
CN111560964B (en) Construction method of rear anti-seepage system of foundation pit
CN102635126B (en) Method for constructing casting well for aluminum alloy hot-rolled sheet ingots
CN105714771B (en) Construction method of manual hole digging pile
JP2000008623A (en) Structural restoration method
CN217204058U (en) Foundation pit enclosure wall outside surface subsides or underground pipe deformation repair structure
CN113374936B (en) Underpinning protection system for top socket pipeline in bottom-through construction and construction method
CN113957880B (en) Construction method of steel-concrete underground continuous wall
CN204435321U (en) A kind of steam power station water intaking open channel
CN114198142B (en) Karst collapse treatment method
KR20150108342A (en) Underground water drainage system of excavated ground and pipeline construction method using the same
JP3002188B1 (en) Ground excavation method
CN221399292U (en) Inspection well for pipeline
US12221760B2 (en) System and method for extending the height of a manhole
JPS61254716A (en) Setting of in-place concrete pile
CN113293769B (en) Protection construction method for original structure of deep foundation pit excavation
CN217870574U (en) Structure for applying locking steel sheet pile to water-stop curtain between piles
CN213836704U (en) Drainage device falls in bottom plate

Legal Events

Date Code Title Description
AS Assignment

Owner name: HYDRO-KLEAN, LLC, IOWA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:HUSTON, MATT;INGHAM, MICHAEL;SIGNING DATES FROM 20200416 TO 20200417;REEL/FRAME:052429/0846

FEPP Fee payment procedure

Free format text: ENTITY STATUS SET TO UNDISCOUNTED (ORIGINAL EVENT CODE: BIG.); ENTITY STATUS OF PATENT OWNER: SMALL ENTITY

FEPP Fee payment procedure

Free format text: ENTITY STATUS SET TO SMALL (ORIGINAL EVENT CODE: SMAL); ENTITY STATUS OF PATENT OWNER: SMALL ENTITY

Free format text: ENTITY STATUS SET TO MICRO (ORIGINAL EVENT CODE: MICR); ENTITY STATUS OF PATENT OWNER: SMALL ENTITY

STCF Information on status: patent grant

Free format text: PATENTED CASE

AS Assignment

Owner name: NXT CAPITAL, LLC, AS AGENT, ILLINOIS

Free format text: SECURITY INTEREST;ASSIGNOR:HYDRO-KLEAN, LLC;REEL/FRAME:056795/0544

Effective date: 20210708

MAFP Maintenance fee payment

Free format text: PAYMENT OF MAINTENANCE FEE, 4TH YR, SMALL ENTITY (ORIGINAL EVENT CODE: M2551); ENTITY STATUS OF PATENT OWNER: SMALL ENTITY

Year of fee payment: 4