JPS61254716A - Setting of in-place concrete pile - Google Patents
Setting of in-place concrete pileInfo
- Publication number
- JPS61254716A JPS61254716A JP9502385A JP9502385A JPS61254716A JP S61254716 A JPS61254716 A JP S61254716A JP 9502385 A JP9502385 A JP 9502385A JP 9502385 A JP9502385 A JP 9502385A JP S61254716 A JPS61254716 A JP S61254716A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- pile
- site
- hole
- gap
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
この発明は、基礎造成に際してのコンクリートくいの設
置に関する分野に属する。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) This invention belongs to the field of installing concrete piles during foundation construction.
(従来の技術)
従来現場でコンクリートを打設して、コンクリートクい
を設置する場合には、くい設置予定地へ、くい穴を掘削
した後、このくい穴内へ、鉄筋篭を挿入し、然る後くい
穴内ヘコンクリートを打設していた。(Conventional technology) Conventionally, when concrete is poured on site and concrete piles are installed, a hole is drilled at the site where the pile is to be installed, and a reinforcing bar cage is inserted into the hole. After that, concrete was being poured into the pile hole.
(発明により解決すべき問題点)
前記従来の方法によれば、打設したコンクリ−トが鉄筋
篭を均一に埋設したか否か不明であるばかりでなく、く
い穴内の残留泥水、又は泥土が、打設コンクリートに混
入して、コンクリートの質を低下させるおそれがあった
。またくい穴壁の一部崩壊による造成コンクリートの不
整形化又は強度の不均一化など、設置くいの状態が予測
および探知困難であって、信頼度の向上がむつかしく、
よって必要以上のコンクリートを使用しなければならな
い(例えば従来の現場くいは中実くいとなる)などの問
題点があった。更に鉄筋篭の埋設は、当然コンクリート
の肉厚内になるので、鉄筋量に比し、曲げモーメントの
対抗力が小さいなどの問題もあった。(Problems to be Solved by the Invention) According to the conventional method, it is not only unclear whether the poured concrete has evenly buried the reinforcing bar cages, but also the residual mud or mud in the pile hole. , there was a risk that it would mix with the poured concrete and deteriorate the quality of the concrete. In addition, it is difficult to predict and detect the condition of the installed piles, such as irregular shapes or uneven strength of the prepared concrete due to partial collapse of the pile wall, making it difficult to improve reliability.
Therefore, there were problems such as having to use more concrete than necessary (for example, conventional site piles were solid piles). Furthermore, since the reinforcing bar cage is naturally buried within the thickness of the concrete, there is a problem that the resistance to bending moment is small compared to the amount of reinforcing bar.
(問題点解決の手段)
然るにこの発明は、くい穴内へ内外二重管を挿入し、内
外二重管の間隙部へ、コンクリートを打設したので、予
め設計した通りの肉厚のコンクリートくいを造成できる
のみならず、必要な鉄■を有効に使用し、しかもコンク
リート使用量は従来の既成くい打設の場合とほぼ同様に
なるなど、前記従来の問題点を悉く解決したのである。(Means for solving the problem) However, in this invention, the inner and outer double pipes are inserted into the pile hole, and concrete is poured into the gap between the inner and outer double pipes. Not only is it possible to construct a concrete structure, but it also uses the necessary iron effectively, and the amount of concrete used is almost the same as in the case of conventional prefabricated piles, all of the problems of the conventional method have been solved.
即らこの発明はくい設置予定地へ、所定外径のくい穴を
掘削した後、前記くい穴内へ、内外壁間に所定間隙を保
つようにして内外二重管を挿入し、前記内外二重管の間
隙部へ、コンクリートを打設して現場コンリートくいを
設置するものである。That is, in this invention, after drilling a hole with a predetermined outer diameter at a site where the pile is to be installed, an inner and outer double pipe is inserted into the hole while maintaining a predetermined gap between the inner and outer walls, and the inner and outer double pipe is Concrete is poured into the gap between the pipes and concrete piles are installed on site.
前記において、くい穴の掘削に際しては、オーガーによ
り掘削した泥の一部を、穴壁になすりつけつつ掘進する
ようにすることにより、穴壁を堅固にして、作業中(特
に二重管挿入時)の崩壊を有効に防止すると共に、掘削
土を大量には排出しないので、排土処理について、著し
く作業性を改善したものである。此の掘削方法について
は、くい穴の深さ、土質その他の理由により従来工法を
用いることもできる。前記における内外二重管は、地上
で予め形成し、底部を塞いだ後内外二重管を同時に挿入
するのが好ましいが、必要に応じ内管と外管とを別々に
挿入することも可能である。然し乍ら内管と外管とを別
々に挿入する場合には、内外二重管の間に入った泥水を
排除した後、又は排除しつつコンクリートを打設する必
要がある。In the above, when digging a pile hole, the hole wall is strengthened by rubbing some of the mud excavated by the auger on the hole wall as the hole is dug, and the hole is made solid during the work (especially when inserting a double pipe). This method effectively prevents the collapse of soil and does not discharge a large amount of excavated soil, which significantly improves the workability of soil disposal. Regarding this excavation method, conventional methods may be used depending on the depth of the hole, soil quality, and other reasons. It is preferable to form the inner and outer double pipes in advance on the ground and insert the inner and outer double pipes at the same time after closing the bottom, but it is also possible to insert the inner and outer pipes separately if necessary. be. However, when inserting the inner pipe and the outer pipe separately, it is necessary to pour concrete after or while removing muddy water that has entered between the inner and outer double pipes.
尤もくい穴掘削に際し、湧水がなく、しかも噴射水を多
足に使用しない場合などの理由により、空穴が掘削でき
れば、内外二重管の挿入状態は問わないことになる。When excavating a hole that is extremely difficult, if an empty hole can be excavated due to reasons such as the absence of spring water and the use of injected water in large numbers, it does not matter how the inner and outer double pipes are inserted.
また拡底工法を採用した際には、くい設置予定地へ、所
定外径のくい穴を掘削すると共に、くい穴の下部へ所定
の高さに亘って、拡底部を設け、該拡底部へセメントミ
ルクを注入してソイルセメントとした後、前記くい穴内
へ、内外壁間に所定間隙を保つようにして内外二重管を
挿入し、前記内外二重管の間隙部へコンクリートを打設
して、現場コンクリートくいを設置する。この工法にお
ける内外二重管底の挿入深さは、拡底部の中間位置、又
は拡底部の底面へ近接した位置となる。In addition, when the expanded bottom method is adopted, a hole with a specified outer diameter is excavated at the site where the pile is planned to be installed, an expanded bottom section is provided at a specified height below the hole, and cement is poured into the expanded bottom section. After injecting milk to make soil cement, insert the inner and outer double pipes into the hole so as to maintain a predetermined gap between the inner and outer walls, and pour concrete into the gap between the inner and outer double pipes. , install on-site concrete piles. In this construction method, the insertion depth of the inner and outer double pipe bottoms is at an intermediate position of the expanded bottom part or a position close to the bottom surface of the expanded bottom part.
この点についは、従来行われている拡底根固め工法の基
準によりコンクリートくいを設置する。Regarding this point, concrete piles will be installed according to the standard of the conventional wide-bottomed foundation construction method.
また拡底根固め用のソイルセメントと、打設コンクリー
トとを一体化させる為に、内外二重壁管底の塞板に孔を
設け、又は塞板を取り外すこともある。In addition, in order to integrate the soil cement for expanding the bottom with the poured concrete, holes may be made in the closing plate at the bottom of the inner and outer double-walled pipe, or the closing plate may be removed.
(発明の作用)
即ちこの発明によれば、内外二重管の間隙部へコンクリ
ートを打設するので、完成したくいの長さ、太さおよび
形状が設計通りであって、信頼度が高くなると共に、曲
げ抗力の大きいくいが出来ることになる。(Operation of the invention) That is, according to this invention, since concrete is poured into the gap between the inner and outer double pipes, the length, thickness and shape of the completed pile are as designed, and reliability is high. At the same time, piles with large bending resistance can be created.
またくい穴の崩壊がないので、作業性が頗る良好であり
、打設されたコンクリートは、予め地上で配合された通
りの質を保有させることができる。In addition, since there is no collapse of the pit, workability is extremely good, and the poured concrete can maintain the same quality as previously mixed on the ground.
(実施例1)
この発明は、くい設置予定地へ所定外径のくい穴1をオ
ーガー2により掘削する。この場合にオーガーロッド3
の先端から加圧水を噴射しつつオーガーロッド3を回転
すると、オーガーロッド3に固定した撹拌棒4によって
、掘削土を粉砕しつつ、前記オーガーロッド3に固定し
たドラム5によって、前記粉砕土を、前記くい穴壁1a
に練りつける。従ってくい穴壁は、堅固に整形されると
共に、掘削土の練りつけにより、排土量を少なくするこ
とができる。前記のようにして、オーガー2が支持地盤
12に到達し、該支持地盤12を適当の深さまで掘削し
たならば、オーガーロッド3をくい穴から抜き取る。つ
いでくい穴内径とほぼ等しい外径の鋼製外管6内へ、所
定の間隙Sを保って(間隙Sはコンクリートくいの肉厚
となる)鋼製内管7を挿入し、内管7と外管6の下端に
塞板8を固着すると共に、適宜のスペーサー9(例えば
トラス状に形成した鉄筋、又は内外管の間隙保持用駒片
)を間隙部の適所へ介装して、内外二重管10を形成す
る。前記くい穴1に前記二重管10を挿入し、二重管1
0の内外壁間へコンクリート11を充填する。この場合
に内外壁間は中空であるから(泥水又は泥などが入って
いない)充填したコンクリート11は地上での配合割合
を保つことになり、設計強度が保持されると共に、予定
時間で硬化するなど、信頼性を保持することができる。(Example 1) In the present invention, a pile hole 1 having a predetermined outer diameter is excavated at a site where a pile is to be installed using an auger 2. In this case, auger rod 3
When the auger rod 3 is rotated while injecting pressurized water from the tip of the auger rod 3, the excavated soil is crushed by the stirring rod 4 fixed to the auger rod 3, and the crushed soil is crushed by the drum 5 fixed to the auger rod 3. Hole wall 1a
Practice it. Therefore, the wall of the pit can be firmly shaped, and by kneading the excavated soil, the amount of soil removed can be reduced. As described above, when the auger 2 reaches the supporting ground 12 and excavates the supporting ground 12 to an appropriate depth, the auger rod 3 is removed from the hole. Insert the steel inner tube 7 into the steel outer tube 6, which has an outer diameter approximately equal to the inner diameter of the hole, while maintaining a predetermined gap S (the gap S is the thickness of the concrete pile). A closing plate 8 is fixed to the lower end of the outer tube 6, and an appropriate spacer 9 (for example, a reinforcing bar formed in a truss shape, or a piece for maintaining a gap between the inner and outer tubes) is inserted at an appropriate position in the gap to separate the inner and outer tubes. A heavy pipe 10 is formed. Insert the double pipe 10 into the hole 1, and
Concrete 11 is filled between the inner and outer walls of 0. In this case, since the space between the inner and outer walls is hollow (there is no muddy water or mud inside), the filled concrete 11 maintains the mixing ratio on the ground, maintains its design strength, and hardens within the scheduled time. etc., reliability can be maintained.
前記のようにして、内外壁面に鋼製内外管を装着したコ
ンクリートくい13を設置することができた。図中16
は地表である。As described above, the concrete piles 13 equipped with steel inner and outer tubes could be installed on the inner and outer walls. 16 in the diagram
is the surface of the earth.
(実施例2)
前記実施例1と同様にして、くい穴1を掘削成形したな
らば、オーガーロッド3を逆回転して、オーガーの補助
刃(図示してない)を拡開し、そのままオーガーロッド
3を回転すると共に、所定の上下範囲(例えば3m位)
に亘ってオーガーロッド3を昇降させると、前記くい穴
1の下部へ、支持地盤面の上下に、拡開穴14が掘削さ
れる。(Example 2) After drilling and forming the borehole 1 in the same manner as in Example 1, the auger rod 3 is rotated in the opposite direction, the auxiliary blade (not shown) of the auger is expanded, and the auger is directly inserted. While rotating the rod 3, the specified vertical range (for example, about 3 m)
When the auger rod 3 is moved up and down over this period, an enlarged hole 14 is drilled below the borehole 1 above and below the supporting ground surface.
そこでオーガーロッド3を正転させて、補助刃を収納さ
せた後、オーガーロッド3の先端からセメントミルクを
噴射させつつ、オーガーロッド3を回転し乍ら引き上げ
、拡開穴14内ヘソイルセメント15を充満させる。然
る後前記くい穴1内に鋼製の外管6と内管7よりなる二
重管10を挿入し、二重管10の内外壁間へコンクリー
ト11を充填する。この場合に二重管10の下端は、前
記拡開穴14のほぼ中間位置にあって、ソイルセメント
15に埋設されている。このにうにして、内外に鋼管を
装着したコンクリートくい13を設置することができた
。Therefore, after rotating the auger rod 3 in the normal direction and storing the auxiliary blade, the cement milk is injected from the tip of the auger rod 3, and the auger rod 3 is rotated and pulled up to fill the soil cement 15 inside the expanded hole 14. to fill up. Thereafter, a double pipe 10 consisting of an outer pipe 6 and an inner pipe 7 made of steel is inserted into the hole 1, and concrete 11 is filled between the inner and outer walls of the double pipe 10. In this case, the lower end of the double pipe 10 is located approximately in the middle of the expanded hole 14 and is buried in the soil cement 15. In this way, we were able to install concrete piles 13 with steel pipes attached inside and outside.
(発明の効果)
即ちこの発明によれば、くい穴内へ内外二重管を挿入し
、該二重管の間隙部へコンクリートを充填したので、内
外に鋼管を装着したコンクリートくいを埋設したのと同
様の効果がある。また二重管の空間部へコンクリートを
打設する為に、打設コンクリートが泥水又は泥と混合し
、コンクリートくいの品質を低下するおそれなく、設計
強度を確実に保有することができる効果がある。然して
鋼管くいの特質である抗曲げモーメントに対しては鋼管
の厚さに比例した強度を有する効果がある。(Effect of the invention) That is, according to the present invention, an inner and outer double pipe is inserted into a pile hole, and the gap between the double pipes is filled with concrete. It has a similar effect. In addition, since concrete is poured into the space of the double pipe, there is no risk that the poured concrete will mix with muddy water or mud and deteriorate the quality of the concrete piles, and the design strength can be reliably maintained. . However, with respect to bending moment resistance, which is a characteristic of steel pipe piles, it has the effect of having strength proportional to the thickness of the steel pipe.
更にこの発明の設置方法は、技術的に単純であって、こ
の方法を正しく行う限りにおいて、高熟練の作業員でな
くても、信頼度の高い基礎くいの設置ができる効果もあ
る。Furthermore, the installation method of the present invention is technically simple, and even non-skilled workers can install foundation piles with high reliability as long as the method is carried out correctly.
図はこの発明のくい設置順序を示すもので、第1図はオ
ーガーによる掘削開始図、第2図は予定掘削終了図、第
3図は二重管挿入流の図、第4図はコンクリート打設終
了図、第5図は他の実施例におけるコンクリート打設終
了図である。
1・・・くい穴 2・・・オーガー3・・・オ
ーガーロッド 4・・・撹拌棒5・・・ドラム
6・・・外管7・・・内管 10・・・二
重管13・・・コンクリートくいThe figures show the pile installation order of this invention. Figure 1 is a diagram of the start of excavation with an auger, Figure 2 is a diagram of the planned completion of excavation, Figure 3 is a diagram of the double pipe insertion flow, and Figure 4 is a diagram of concrete pouring. Figure 5 is a diagram showing the completion of concrete pouring in another embodiment. 1... Socket hole 2... Auger 3... Auger rod 4... Stirring rod 5... Drum
6...Outer pipe 7...Inner pipe 10...Double pipe 13...Concrete pile
Claims (1)
、前記くい穴内へ、内外壁間に所定間隙を保つようにし
て内外二重管を挿入し、前記内外二重管の間隙部へ、コ
ンクリートを打設することを特徴とした現場コンクリー
トくいの設置方法 2 くい穴の掘削は、オーガーにより掘削した泥を穴壁
になすりつけつつ掘進するようにした特許請求の範囲第
1項記載の現場コンクリートくいの設置方法 3 内外二重管は、予め形成し、かつ底を塞いだ二重管
とした特許請求の範囲第1項記載の現場コンクリートく
いの設置方法 4 くい設置予定地へ、所定外径のくい穴を掘削すると
共に、くい穴の下部へ所定の高さに亘って、拡底部を設
け、該拡底部へセメントミルクを注入してソイルセメン
トとした後、前記くい穴内へ、内外壁間に所定間隙を保
つようにして内外二重管を挿入し、前記内外二重管の間
隙部へコンクリートを打設することを特徴とした現場コ
ンクリートくいの設置方法 5 内外二重管底の挿入深さは、拡底部の中間部、又は
拡底部の底部に近接させた特許請求の範囲第4項記載の
現場コンクリートくいの設置方法[Scope of Claims] 1. After drilling a pile hole with a predetermined outer diameter at the site where the pile is to be installed, insert an inner and outer double pipe into the pile hole while maintaining a predetermined gap between the inner and outer walls, and A method for installing concrete piles on-site, characterized by pouring concrete into the gap between double pipes 2. A method of installing concrete piles on site, characterized by pouring concrete into the gap between double pipes. 2. A method of installing concrete piles on site, characterized by pouring concrete into the gap between double pipes. Method 3 for installing concrete piles on-site according to claim 1. Method 4 for installing concrete piles on-site according to claim 1, in which the inner and outer double pipes are double pipes that are formed in advance and have their bottoms closed. At the planned installation site, a hole with a predetermined outer diameter is excavated, an enlarged bottom section is provided at the bottom of the hole over a predetermined height, and cement milk is poured into the enlarged bottom section to form soil cement. On-site concrete pile installation method 5, characterized by inserting an inner and outer double pipe into the pile hole so as to maintain a predetermined gap between the inner and outer walls, and pouring concrete into the gap between the inner and outer double pipes. The method for installing on-site concrete piles according to claim 4, in which the insertion depth of the inner and outer double pipe bottoms is set at the middle part of the expanded bottom part or close to the bottom of the expanded bottom part.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9502385A JPS61254716A (en) | 1985-05-02 | 1985-05-02 | Setting of in-place concrete pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9502385A JPS61254716A (en) | 1985-05-02 | 1985-05-02 | Setting of in-place concrete pile |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS61254716A true JPS61254716A (en) | 1986-11-12 |
Family
ID=14126466
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9502385A Pending JPS61254716A (en) | 1985-05-02 | 1985-05-02 | Setting of in-place concrete pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS61254716A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63206570A (en) * | 1987-02-18 | 1988-08-25 | 東急建設株式会社 | Apparatus for producing spray concrete |
JPS6480621A (en) * | 1987-06-12 | 1989-03-27 | Mitani Sekisan Kk | Working method of in-situ pile |
JP2017223018A (en) * | 2016-06-14 | 2017-12-21 | 三谷セキサン株式会社 | Installation method of foundation pile, foundation pile structure, and double precast pile |
CN108867631A (en) * | 2018-08-06 | 2018-11-23 | 天津市盛世基建岩土工程有限公司 | A kind of construction method of rotary digging drilling hole bored concrete pile |
CN109537586A (en) * | 2018-12-31 | 2019-03-29 | 江苏兴厦建设工程集团有限公司 | A kind of pedestal pile |
-
1985
- 1985-05-02 JP JP9502385A patent/JPS61254716A/en active Pending
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63206570A (en) * | 1987-02-18 | 1988-08-25 | 東急建設株式会社 | Apparatus for producing spray concrete |
JPH0584787B2 (en) * | 1987-02-18 | 1993-12-03 | Tokyu Kensetsu Kk | |
JPS6480621A (en) * | 1987-06-12 | 1989-03-27 | Mitani Sekisan Kk | Working method of in-situ pile |
JP2017223018A (en) * | 2016-06-14 | 2017-12-21 | 三谷セキサン株式会社 | Installation method of foundation pile, foundation pile structure, and double precast pile |
CN108867631A (en) * | 2018-08-06 | 2018-11-23 | 天津市盛世基建岩土工程有限公司 | A kind of construction method of rotary digging drilling hole bored concrete pile |
CN109537586A (en) * | 2018-12-31 | 2019-03-29 | 江苏兴厦建设工程集团有限公司 | A kind of pedestal pile |
CN109537586B (en) * | 2018-12-31 | 2024-01-16 | 江苏兴厦建设工程集团有限公司 | Pile with large head |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101122131B (en) | Foundation pit supporting pile using pipe casting pile embedding in rock | |
KR100762991B1 (en) | Precast piling method injected with high-strength mortar | |
CN108842819A (en) | A kind of urban track traffic cable run method for tunnel construction | |
CN109736303A (en) | It is a kind of to press pour water soil static pressure pipe pile structure and construction method | |
CN206721870U (en) | A kind of long auger guncreting pile steel reinforcement cage | |
KR101021915B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
CN110777775A (en) | Foundation pit structure and construction method thereof | |
JP2003147782A (en) | Foundation structure for constructing new building on existing basement and its construction method | |
JPS61254716A (en) | Setting of in-place concrete pile | |
CN217053672U (en) | Large-diameter inspection well pile drilling method construction system | |
JP4485006B2 (en) | Construction method for underground structures | |
JP2008031772A (en) | Construction method of precast pile, and cover for use in the construction method | |
JPH02289718A (en) | Drilling method of expanded head pile hole, constructing method of expanded head pile and pile hole drill | |
CN112627188B (en) | Deep foundation pit supporting structure and construction method thereof | |
JP6730121B2 (en) | Underground wall construction method | |
JP4074198B2 (en) | How to remove existing piles | |
JP2942779B1 (en) | Underground wall construction method | |
JPH03257215A (en) | Pile constructing method | |
JPH0470422A (en) | Open caisson method | |
JP3810882B2 (en) | Construction method of cast-in-place pile in confined groundwater zone | |
KR200373276Y1 (en) | Steel pipe pile of support structure | |
CN221399292U (en) | Inspection well for pipeline | |
CN113737771B (en) | Pipe jacking well opening soil body reinforcing process for soft soil foundation | |
JP2881501B2 (en) | Construction method for high strength cast-in-place concrete piles | |
KR200375610Y1 (en) | Cast in place concrete pile using vibro magnetic shovel hammer |