Slope face block and slope face greening construction method

Info

Publication number
JPH09165750A
JPH09165750A JP33039995A JP33039995A JPH09165750A JP H09165750 A JPH09165750 A JP H09165750A JP 33039995 A JP33039995 A JP 33039995A JP 33039995 A JP33039995 A JP 33039995A JP H09165750 A JPH09165750 A JP H09165750A
Authority
JP
Japan
Prior art keywords
block
slope
concrete block
planted
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP33039995A
Other languages
Japanese (ja)
Inventor
Tamotsu Tsuchida
保 土田
Katsuro Mizukami
克朗 水上
Toru Ito
亨 伊藤
Hirofumi Mori
浩文 森
Kazuo Chikabayashi
和生 親林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taiheiyo Cement Corp
Maeta Concrete Industry Ltd
Original Assignee
Chichibu Onoda Cement Corp
Maeta Concrete Industry Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chichibu Onoda Cement Corp, Maeta Concrete Industry Ltd filed Critical Chichibu Onoda Cement Corp
Priority to JP33039995A priority Critical patent/JPH09165750A/en
Publication of JPH09165750A publication Critical patent/JPH09165750A/en
Pending legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Revetment (AREA)

Abstract

PROBLEM TO BE SOLVED: To make it possible to plant a slope face area with trees easily and definitely. SOLUTION: Planting concrete blocks 2 are freely fitted in a space area 11 of mold blocks 1 for slope protection. The planting concrete blocks 2 are movably connected to the mold blocks 1, thereby forming a slope face block 8. The slope face block 8 is positioned on the upper part of an intended slope face 30 to be planted with trees and opposed to the slope face. Then, the slope face is adapted to fall down toward the slope face so that each of both blocks may be joined with the slope face freely.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】この発明は、急勾配の法面等
を緑化すめための法面ブロック及び法面緑化施工方法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a slope block and a slope greening method for greening a steep slope or the like.

【0002】[0002]

【従来の技術】山などの整形斜面(法面)を緑化させる
方法として植物の生えるコンクリートブロック、即ち、
植栽コンクリートブロックを該斜面に配設する方法が採
用されている。このブロックを法面に配設する場合に
は、複数の空間部を有する法枠ブロックを法面に配設し
た後、各空間部に植栽コンクリートブロックを嵌着する
ことが知られている。
2. Description of the Related Art As a method of greening a shaped slope (slope) such as a mountain, a concrete block where plants grow, that is,
A method of arranging a planting concrete block on the slope is adopted. When arranging this block on the slope, it is known that a planting concrete block is fitted into each space after arranging a slope frame block having a plurality of spaces on the slope.

【0003】[0003]

【発明が解決しようとする課題】しかし、従来例には次
の様な問題がある。 (1)法枠ブロックは、傾斜して足場の良くない法面に
配設されているので、該法枠ブロックの各空間部に1個
づつ植栽コンクリートブロックを嵌着する作業は、重労
働で危険な上、作業能率も良くないので多くの作業時間
を要する。
However, the conventional example has the following problems. (1) Since the legal frame blocks are inclined and are arranged on the slopes where the scaffolding is not good, the work of fitting one planting concrete block into each space of the legal frame block is a heavy labor task. Since it is dangerous and the work efficiency is not good, much work time is required.

【0004】(2)植栽コンクリートブロックを法枠ブ
ロックの空間部に嵌着し固定する時には、両ブロックの
底面が同一面上に位置する様に固着される。そのため、
特に大型の該枠ブロックを用いた施工において、法面を
精度よく形成しないと植栽コンクリートブロックの底面
が法面と密着しないことがある。このように植栽コンク
リートブロックが法面に密着しないと、植栽コンクリー
トブロックに対して法面からの毛細管現象による水分の
供給ができなくなるので、植栽コンクリートブロックが
乾燥し易く、植物が生育できなくなる。
(2) When the planting concrete block is fitted and fixed in the space of the method frame block, the bottoms of both blocks are fixed so that they are located on the same plane. for that reason,
Particularly in the construction using the large frame block, the bottom surface of the planted concrete block may not adhere to the slope unless the slope is accurately formed. If the planting concrete block does not adhere to the slope in this way, water cannot be supplied to the planting concrete block by capillary action from the slope, so that the planting concrete block easily dries and plants can grow. Disappear.

【0005】この発明は上記事情に鑑み、簡単に、か
つ、確実に法面緑化することができるようにすることを
目的とする。
In view of the above circumstances, an object of the present invention is to make it possible to easily and surely perform slope greening.

【0006】[0006]

【課題を解決するための手段】この発明は、法枠ブロッ
クの空間部中の植栽コンクリートブロックを移動可能に
支持して、法面ブロックを形成する工程と;該法面ブロ
ックを緑化対象法面の上方に位置せしめて該法面と対向
せしめる工程と;該法面ブロックを該法面に向って降下
させ、法枠ブロックと植栽コンクリートブロックとを互
いに自由に該法面に圧着せしめる工程と;を備えたこと
を特徴とする法面緑化施工方法、である。この発明は、
空間部を有する法枠ブロックと;該空間部に遊嵌合され
た植栽コンクリートブロックと;該両ブロックを移動自
在に支持する支持手段と;を備えたことを特徴とする法
面ブロック、である。
SUMMARY OF THE INVENTION The present invention comprises a step of movably supporting a planting concrete block in a space of a slope frame block to form a slope block; A step of arranging above the surface so as to face the slope; a step of lowering the slope block toward the slope and freely crimping the slope frame block and the planted concrete block to the slope And a slope slope greening construction method. The present invention
A slope block having a space portion; a planting concrete block loosely fitted in the space portion; and a support means for movably supporting both blocks; is there.

【0007】[0007]

【発明の実施の形態】法枠ブロックの空間部の植栽コン
クリートブロックを支持手段、例えば、該植栽コンクリ
ートブロックと該法枠ブロックとを連結する連結部材、
を介して移動可動に支持することにより法面ブロックを
形成する。この植栽コンクリートブロックは植物が生え
ることの出来るブロックで、空隙を有するポーラスコン
クリートブロックが用いられる。
BEST MODE FOR CARRYING OUT THE INVENTION Supporting means for supporting a planting concrete block in a space portion of a law frame block, for example, a connecting member for connecting the planting concrete block and the law frame block,
A slope block is formed by movably supporting it through. This planted concrete block is a block on which plants can grow, and a porous concrete block having voids is used.

【0008】この連結部材は、法枠ブロックを吊り上げ
ることにより植栽コンクリートブロックを安全に吊り上
げることができるとともに、植栽コンクリートブロック
の底面が法枠の底面と比較して上下出来る構造となって
いる。
[0008] This connecting member has a structure in which the planting concrete block can be safely lifted by hoisting the method frame block, and the bottom of the planting concrete block can be moved up and down as compared with the bottom of the method frame. .

【0009】この法面ブロックを緑化対象斜面の培養土
層の上方に位置せしめ、該培養土層と対向させる。この
時、植栽コンクリートブロックは自重により法枠ブロッ
クの底面から突出した状態(張り出し状態)となる。
The slope block is located above the culture soil layer on the slope to be replanted and is opposed to the culture soil layer. At this time, the planted concrete block is in a state of being projected (overhanging state) from the bottom surface of the legal frame block by its own weight.

【0010】この法面ブロックを該斜面に向って降下さ
せると、両ブロックは互いに自由に培養土層に圧着する
が、初めに植栽コンクリートブロック、次に法枠ブロッ
クの順で培養土層に密着する。法面は盛り土の場合、比
較的精度良く整形できるが、予め低く整形し、土壌改良
材、肥料成分を含み、適当に湿った培養土を用いて整形
すると、仕上がりを向上させることができる。また、こ
の培養土を用いる方法は生育に必要な栄養を法面に多く
保持できるため植栽コンクリートに生育する植物にとっ
て良好な環境を提供する。
When the slope block is lowered toward the slope, both blocks freely press-bond to the culture soil layer, but first the planted concrete block and then the slope frame block are attached to the culture soil layer in this order. In close contact. When the slope is embankment, it can be shaped relatively accurately, but if it is shaped low in advance and is shaped using a soil-improving material and a fertilizer component and appropriately moist culture soil, the finish can be improved. In addition, the method using this culture soil provides a good environment for plants growing on planting concrete because it can retain a large amount of nutrients necessary for growth on the slope.

【0011】このような工程を繰り返し、緑化対象法面
全面にわたり、簡単に、かつ確実に植栽コンクリートブ
ロックを密着させる。
By repeating such steps, the planted concrete block is brought into close contact with the entire surface of the slope to be greened easily and surely.

【0012】[0012]

【実施例1】この発明の第1実施例を図1〜図4により
説明する。工場等で法枠ブロック1と植栽コンクリート
ブロック、即ち、ポーラスコンクリートブロック2とか
らなる法面ブロック8を形成する。該法枠ブロック1
は、図示しない型枠に、係合棒15を備えた鉄筋を配設
し、コンクリート原料、例えば、水191Kg/m3 、普
通ポルトランドセメント381Kg/m3 、細骨材836
Kg/m3 、粗骨材1030Kg/m3 、混和材(花王 商
品名「マイティー150」1.22Kg/m3 、を混練し
た生コンを法枠ブロック用型枠に打設して形成する。法
枠ブロック1には複数の空間部11が設けられており、
その空間部11には、植栽コンクリートブロック2が嵌
着されている。
Embodiment 1 A first embodiment of the present invention will be described with reference to FIGS. A slope block 8 composed of a slope frame block 1 and a planted concrete block, that is, a porous concrete block 2 is formed in a factory or the like. The legal framework block 1
Is provided with a reinforcing bar having an engaging rod 15 in a formwork (not shown), and a concrete raw material, for example, water 191 kg / m 3 , ordinary Portland cement 381 kg / m 3 , fine aggregate 836
Kg / m 3, coarse aggregate 1030 kg / m 3, formed by Da設in admixture (Kao trade name "Mighty 150" 1.22Kg / m 3, kneaded fresh concrete the Howaku block mold frame a. Method The frame block 1 is provided with a plurality of space portions 11,
The planting concrete block 2 is fitted in the space 11.

【0013】この法枠ブロック1は、例えば、縦2m、
横3m、厚さ20cm、に形成された大型連続タイプで
あり、その空間部11は一辺の長さmが85cmの正方
形状であり、その壁面11aは内方に傾斜している。
The law frame block 1 has, for example, a length of 2 m,
The space portion 11 is a large continuous type having a width of 3 m and a thickness of 20 cm, and the space portion 11 has a square shape with a side length m of 85 cm, and its wall surface 11a is inclined inward.

【0014】この空間部11の四隅は面とりされてお
り、その面取部11Sには連結部材15、即ち、前記係合
棒15が設けられている。この係合棒15は、径6〜8
mm程度の補強筋、例えば、アルミナイズド鋼棒が用い
られる。この係合棒15は先端部がL字状に形成され、
その後部15aは法枠ブロック1内に埋設され、その先
端部15bは空間部11に突出している。この突出量h
は、植栽コンクリートブロック2が変位しても、外れな
い程度の長さ、例えば10cm、に適宜選択される。
The four corners of the space 11 are chamfered, and the chamfered portion 11S is provided with the connecting member 15, that is, the engaging rod 15. The engagement rod 15 has a diameter of 6 to 8
A reinforcing bar of about mm, for example, an aluminized steel rod is used. The engaging rod 15 has an L-shaped tip,
The rear portion 15a is embedded in the legal frame block 1, and the tip portion 15b thereof projects into the space portion 11. This protrusion amount h
Is appropriately selected such that the planted concrete block 2 does not come off even if it is displaced, for example, 10 cm.

【0015】植栽コンクリートブロック2は、図示しな
い植栽ブロック用型枠内に不識布あるいは瀘紙等を敷
き、径が6〜10mm程度の補助筋、例えば、アルミナ
イズド鋼棒を組んで配する。この際、法枠ブロックの係
合棒15に係合するような位置にループ20を形成す
る。
The planting concrete block 2 is arranged by arranging an unknowing cloth or a paper filter in a planting block mold (not shown) and assembling an auxiliary bar having a diameter of about 6 to 10 mm, for example, an aluminized steel rod. To do. At this time, the loop 20 is formed at a position where it engages with the engagement rod 15 of the method frame block.

【0016】次に、水62.5Kg/m3 、普通ポルトラ
ンドセメント250.0Kg/m3 、骨材(砕石、粒径1
0〜20mm)1590Kg/m3 、混和剤(花王 商品
名「マイティー150」)1.5Kg/m3 、を強制ミキ
サーで混練して生コンを形成し、該生コンを前記型枠内
に打設し、ポーラスコンクリートブロック2を成形し
た。このブロック2は一辺の長さnが80cmの正方形
状体である。
Next, water 62.5 kg / m 3 , ordinary Portland cement 250.0 kg / m 3 , aggregate (crushed stone, particle size 1
0 to 20 mm) 1590 Kg / m 3 and an admixture (Kao's trade name “Mighty 150”) 1.5 Kg / m 3 were kneaded with a forced mixer to form green concrete, which was placed in the mold. The porous concrete block 2 was molded. This block 2 is a square body having a side length n of 80 cm.

【0017】このポーラスコンクリートブロックに振動
を与え、ポーラスコンクリートブロックの下方の空隙に
土壌粒子、土壌改良材、等からなる培地材を充填する。
Vibration is applied to the porous concrete block to fill the voids below the porous concrete block with a medium material composed of soil particles, a soil improving material, and the like.

【0018】前記ポーラスコンクリートブロックの上方
部空隙に前記植生蓄材、種子、を充填し、植栽コンクリ
ートブロック2を形成する。このブロック2は、一辺の
長さnが80cmの正方形状体であるが、その大きさは
法枠ブロックの空間部の形状に合わせて適宜変更され
る。
The planted concrete block 2 is formed by filling the voids in the upper portion of the porous concrete block with the vegetation storage material and seeds. The block 2 is a square body having a side length n of 80 cm, but its size is appropriately changed according to the shape of the space portion of the legal frame block.

【0019】また、植栽コンクリートブロック2の大き
さは、法枠ブロック1の空間部11に遊嵌合した時、互
いに自由に上下動できる大きさにする必要があり、空間
部11の寸法より若干小さくする。本実施例の場合、例
えば、両者間のスペースの大きさfは10mm、又、連
結部材15、20が設けられている隅部のスペースの大
きさgは、30〜50mmが選択される。又、植栽コン
クリートブロックの形状は法枠ブロックの空間部11の
形状に合わせて適宜変更される。
Further, the size of the planted concrete block 2 needs to be such that it can freely move up and down with each other when loosely fitted in the space portion 11 of the method frame block 1. Make it slightly smaller. In the case of the present embodiment, for example, the size f of the space between the two is selected to be 10 mm, and the size g of the space at the corner where the connecting members 15 and 20 are provided is selected to be 30 to 50 mm. Further, the shape of the planted concrete block is appropriately changed according to the shape of the space portion 11 of the method frame block.

【0020】次に法面ブロック8の施工方法について説
明する。前記法枠ブロック1の各空間部11に植栽コン
クリートブロック2を遊嵌合するとともに、連結部材1
5、20を係合せしめて両者1、2を移動可能に連結す
る。
Next, a method of constructing the slope block 8 will be described. The planting concrete block 2 is loosely fitted in each space 11 of the law frame block 1 and the connecting member 1
Engage 5 and 20 to movably connect both 1 and 2.

【0021】緑化対象法面Wを整形し、その上に培養土
を積層して培養土層30を形成する。この培養土層30
の厚さtは必要に応じて適宜選択されるが、例えば、厚
さt=60mm以上、が選ばれる。
The slope W to be greened is shaped, and the culture soil is laminated on the slope W to form a culture soil layer 30. This culture soil layer 30
The thickness t is appropriately selected according to need. For example, the thickness t = 60 mm or more is selected.

【0022】前記法面ブロック8を図示しないクレーン
により吊り上げ、該培養土層30上に位置せしめ、両者
を対向せしめる。この時、植栽コンクリートブロック2
は自重により下方に変位し該ブロックの底面2aは法枠
ブロック1の底面1aより下方に突出する。この突出
量、即ち、張り出し量Tは、例えば、植栽コンクリート
ブロックの厚さが10cmの時、8cmが選ばれる。
The slope block 8 is hoisted by a crane (not shown) to be positioned on the culture soil layer 30 so that they are opposed to each other. At this time, planting concrete block 2
Is displaced downward by its own weight, and the bottom surface 2a of the block projects below the bottom surface 1a of the method frame block 1. The protruding amount, that is, the protruding amount T is selected to be 8 cm when the thickness of the planted concrete block is 10 cm, for example.

【0023】この状態の法面ブロック8を培養土層30
に向ってゆっくり降下させると、初めに該植栽コンクリ
ートブロック2の底面2aが培養土層30に接着し、鎖
線の状態となる。この時、法枠ブロック1の底面1a
は、まだ培養土層30に当接していない。
The slope block 8 in this state is used as a culture soil layer 30.
When it is slowly lowered toward, the bottom surface 2a of the planted concrete block 2 first adheres to the culture soil layer 30 and becomes a chain line state. At this time, the bottom surface 1a of the legal frame block 1
Has not yet abutted on the culture soil layer 30.

【0024】更に法面ブロック8を降下させると、該植
栽コンクリートブロック2は培養土層30を押圧しなが
ら密着するとともに、法枠ブロック1の底面1aも培養
土層30に接着する。この法面ブロック8をアンカ等の
固定部材AKにより法面に固定してもよい。
When the slope block 8 is further lowered, the planted concrete block 2 adheres to the culture soil layer 30 while pressing it, and the bottom surface 1a of the slope frame block 1 also adheres to the culture soil layer 30. The slope block 8 may be fixed to the slope by a fixing member AK such as an anchor.

【0025】この様な工程を繰り返すことにより所望面
積の法面に植栽コンクリートブロック2を配設する。
By repeating these steps, the planting concrete block 2 is arranged on the slope of a desired area.

【0026】[0026]

【実施例2】この発明の第2実施例を図5、図6により
説明する。この実施例と第1実施例との相違点は植栽コ
ンクリートブロック2の支持手段として、連結部材の係
合棒15を法枠ブロック1に設ける代わりに植栽コンク
リートブロック2に設け、該係合棒15に係合するルー
プ20を植栽コンクリートブロック2に設ける代わり
に、法枠ブロック1に設けたことである。なお、この係
合棒15は、下向きに設けられる。
Second Embodiment A second embodiment of the present invention will be described with reference to FIGS. The difference between this embodiment and the first embodiment is that, as the support means for the planting concrete block 2, the engaging rod 15 of the connecting member is provided on the planting concrete block 2 instead of on the legal frame block 1, and the engagement is performed. Instead of providing the planting concrete block 2 with the loop 20 that engages with the rod 15, the law frame block 1 is provided. The engagement rod 15 is provided downward.

【0027】この発明の第3実施例を図7、図8により
説明する。この実施例と第1実施例との相違点は、植栽
コンクリートブロック2の支持手段として、載置具30
を用いることである。この載置具30は、例えば、鉄筋
により形成され、その先端部30aは法枠ブロック1内
に埋設され、後端部30bは空間部11に水平状に突出
している。
A third embodiment of the present invention will be described with reference to FIGS. The difference between this embodiment and the first embodiment is that the mounting tool 30 is used as a support means for the planting concrete block 2.
Is used. The mounting tool 30 is formed of, for example, a reinforcing bar, a front end portion 30 a thereof is embedded in the method frame block 1, and a rear end portion 30 b thereof horizontally projects into the space 11.

【0028】植栽コンクリートブロック2の外周面に
は、載置具30の後端部30bが引っかかる段部32が
形成されている。この段部32の深さは法枠ブロックの
底面1aからの植栽コンクリートブロック2の底面2a
の突出量、即ち、張り出し量Tを考慮して適宜選択され
る。この張り出し量Tとして、例えば、植栽コンクリー
トブロックの厚さが10cmの時、5cm以下が選ばれ
る。
On the outer peripheral surface of the planted concrete block 2, there is formed a step 32 on which the rear end 30b of the mounting tool 30 is caught. The depth of this step 32 is the bottom 2a of the planted concrete block 2 from the bottom 1a of the method frame block.
Is appropriately selected in consideration of the amount of protrusion, that is, the amount of protrusion T. As the protruding amount T, for example, 5 cm or less is selected when the thickness of the planted concrete block is 10 cm.

【0029】この発明の第4実施例を図9、図10によ
り説明する。この実施例と第1実施例との相違点は、支
持手段として法枠ブロック1の空間部11のテーパ内面
41と、該内面41に対向する植栽コンクリートブロッ
ク2のテーパ外周面42とを形成し、両面41、42を
当接せしめることにより支持することである。
A fourth embodiment of the present invention will be described with reference to FIGS. The difference between this embodiment and the first embodiment is that a tapered inner surface 41 of the space portion 11 of the method frame block 1 and a tapered outer peripheral surface 42 of the planted concrete block 2 facing the inner surface 41 are formed as the supporting means. Then, the both surfaces 41, 42 are supported by bringing them into contact with each other.

【0030】このテーパの内面41は底面1a側が、上
面1b側より広くなる様に傾斜しており、テーパ外周面
42は上面2b側が底面2a側より広くなる様に傾斜し
ている。なお、空間部11は逆台形状となる。
The tapered inner surface 41 is inclined so that the bottom surface 1a side is wider than the upper surface 1b side, and the tapered outer peripheral surface 42 is inclined so that the upper surface 2b side is wider than the bottom surface 2a side. The space 11 has an inverted trapezoidal shape.

【0031】この発明の第5実施例を図11、図12に
より説明する。この実施例と第1実施例との相違点は、
支持手段として、法枠ブロック1に植栽コンクリートブ
ロック2を載せる載置部材50を固定し、空間部11に
該載置部材50をたるませて張設したことである。
A fifth embodiment of the present invention will be described with reference to FIGS. The difference between this embodiment and the first embodiment is that
As the supporting means, the placing member 50 on which the planting concrete block 2 is placed is fixed to the method frame block 1, and the placing member 50 is slackened and stretched in the space 11.

【0032】この載置部材として、例えば、ひも、ワイ
ヤ、ネット等が用いられるが、その張り具合は植栽コン
クリートブロック2を載置した時に法枠ブロックの底面
1aから植栽コンクリートブロックの底面2aが所定範
囲の張り出し量T、例えば、植栽コンクリートブロック
の厚さが10cmの時、8cmとなる様に調整される。
As the placing member, for example, a string, a wire, a net or the like is used. The tension of the placing concrete block 2 from the bottom surface 1a of the legal frame block to the bottom surface 2a of the planting concrete block when the planting concrete block 2 is placed. Is adjusted to a predetermined range T, for example, 8 cm when the thickness of the planted concrete block is 10 cm.

【0033】この載置部材50は、複数本から構成さ
れ、例えば、植栽コンクリートブロックの一辺に平行な
二本のワイヤ50A、二本のX状に交差するひも51
A、菱形状に配設された4本のワイヤ52A、植栽コン
クリートブロックの一辺に略平行な三本のワイヤ53
A、植栽コンクリートブロックの隅部に略平行な二本の
ワイヤ54A、植栽コンクリートブロック2の略中央部
で十字状に交差する二本のワイヤ55A、等の様に構成
される。
The placing member 50 is composed of a plurality of pieces, and for example, two wires 50A parallel to one side of the planting concrete block and two strings 51 intersecting in an X shape.
A, four wires 52A arranged in a diamond shape, three wires 53 substantially parallel to one side of the planting concrete block
A, two wires 54A that are substantially parallel to the corners of the planting concrete block, two wires 55A that intersect in a cross shape at the approximately central portion of the planting concrete block 2, and the like.

【0034】この支持手段を用いると、植栽コンクリー
トブロック2の成形が容易となり、又、該植栽コンクリ
ートブロック2を支持手段上に載置するだけでセットで
きるので、作業が簡単である。
By using this supporting means, the planting concrete block 2 can be easily molded, and since the planting concrete block 2 can be set only by placing it on the supporting means, the work is simple.

【0035】この発明の第6実施例を図13により説明
する。この実施例と第5実施例との相違点は、支持手段
50と植栽コンクリートブロック2との間に空間部11
の底面を覆う如き不織布60を介在せしめたことであ
る。この不織布の介在により目地での流出を防止するこ
とができる。
A sixth embodiment of the present invention will be described with reference to FIG. The difference between this embodiment and the fifth embodiment is that a space 11 is provided between the support means 50 and the planting concrete block 2.
That is, the non-woven fabric 60 is interposed so as to cover the bottom surface of the. The interposition of this non-woven fabric can prevent the outflow at the joint.

【0036】この発明の第7実施例を図14、図15に
より説明する。この実施例と第1実施例との相違点は、
植栽コンクリートブロック2に埋設された補助筋70と
法枠ブロック1とをワイヤやロープなどで連結するか、
或いは植栽コンクリートブロックにワイヤやロープなど
の連結部材自体を埋設し、法枠ブロックを連結したこと
である。また、連結した補助筋を使用する場合には、突
出した部分を下方に曲げたり、穴を開けたり、つぶして
広げたりすることで、ワイヤ等との連結を確実にするこ
とができる。
A seventh embodiment of the present invention will be described with reference to FIGS. The difference between this embodiment and the first embodiment is that
Connect the auxiliary reinforcement 70 embedded in the planting concrete block 2 and the method frame block 1 with a wire or rope, or
Alternatively, the connection members themselves such as wires and ropes are embedded in the planted concrete block, and the method frame blocks are connected. Further, when using the connected auxiliary muscles, it is possible to ensure the connection with the wire or the like by bending the protruding portion downward, making a hole, or crushing and expanding.

【0037】この連結材70は、両ブロック1、2の隅
部1c、2cで連結されているが、この連結場所の配置
は必要に応じて適宜選択される。また、補強筋71は植
栽コンクリートブロックの中央部は菱形状に埋設されて
いるが、この補強筋71の配置も適宜選択される。
The connecting member 70 is connected at the corners 1c and 2c of both blocks 1 and 2, and the arrangement of the connecting place is appropriately selected as required. Further, the reinforcing bar 71 is embedded in a diamond shape in the center of the planted concrete block, but the arrangement of the reinforcing bar 71 is also selected appropriately.

【0038】なお、法枠ブロックの底面1aからの植栽
コンクリートブロックの底面2aの張り出し量Tは、必
要に応じて適宜選択されるが、最大でも植栽コンクリー
トブロックの厚さよりも小さいことが望ましい。例え
ば、該ブロックの厚さが10cmの時、張り出し量Tは
8cm以下が選ばれる。
The projecting amount T of the bottom 2a of the planting concrete block from the bottom 1a of the legal frame block is appropriately selected according to need, but it is desirable that it is at most smaller than the thickness of the planting concrete block. . For example, when the thickness of the block is 10 cm, the overhang amount T is selected to be 8 cm or less.

【0039】この発明の実施例は、上記に限定されるも
のではなく、例えば、法面ブロックの空間部11を複数
個設ける代わりに、一個設けても良い。又、空間部の形
状及び植栽コンクリートブロックの形状は必要に応じて
適宜変更しても良いことは勿論である。
The embodiment of the present invention is not limited to the above, and for example, instead of providing a plurality of space portions 11 of the slope block, one may be provided. Also, it goes without saying that the shape of the space and the shape of the planted concrete block may be changed as needed.

【0040】[0040]

【発明の効果】この発明は以上の様に構成したので法枠
ブロックと植栽コンクリートブロックとは互いに自由に
移動しながら、互いに独立に法面に着地する。そのた
め、法面に配設された植栽コンクリートブロックは法面
と密着し、植物の発芽、生育を確実に行なうことができ
る。又、何平方メートルもの面積を機械を用いて一度に
施工できるので、施工の効率化と省力化を実現すること
ができる。
Since the present invention is constructed as described above, the slope frame block and the planted concrete block can move freely while landing on the slope independently of each other. Therefore, the planting concrete block arranged on the slope is in close contact with the slope, and germination and growth of the plant can be reliably performed. Further, since an area of many square meters can be constructed at one time by using a machine, it is possible to realize the construction efficiency and labor saving.

【0041】更に、法面ブロックを吊り上げると、植栽
コンクリートブロックが該法面ブロックの底面から下方
に突出するので、植栽コンクリートブロックの接地の状
況が目視により簡単に確認できる。
Further, when the slope block is lifted, the planting concrete block projects downward from the bottom surface of the slope block, so that the grounding condition of the planting concrete block can be easily visually confirmed.

【0042】又、培養土を用いると、法面を精度良く整
形することができるとともに、植栽コンクリートブロッ
クの底面が法面に密着する。そのため、植物の生育に必
要な栄養素を法面に多く保持できるため、植栽コンクリ
ートブロックに生育する植物にとって良好な環境とな
る。
Further, when the culture soil is used, the slope can be accurately shaped, and the bottom surface of the planted concrete block adheres to the slope. Therefore, a large amount of nutrients necessary for plant growth can be retained on the slope, which provides a favorable environment for plants growing in planting concrete blocks.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第1実施例を示す平面図である。FIG. 1 is a plan view showing a first embodiment of the present invention.

【図2】図1の一部断面拡大図である。FIG. 2 is an enlarged view of a partial cross section of FIG.

【図3】図1の一部拡大平面図である。FIG. 3 is a partially enlarged plan view of FIG.

【図4】施工方法を示す図である。FIG. 4 is a diagram showing a construction method.

【図5】本発明の第2実施例を示す拡大図で図2に相当
する図である。
FIG. 5 is an enlarged view showing a second embodiment of the present invention and corresponds to FIG.

【図6】第2実施例の一部拡大平面図である。FIG. 6 is a partially enlarged plan view of the second embodiment.

【図7】本発明の第3実施例を示す図で、図8のVII−V
II線断面図である。
FIG. 7 is a view showing a third embodiment of the present invention, which is VII-V of FIG.
FIG. 2 is a sectional view taken along line II.

【図8】平面図である。FIG. 8 is a plan view.

【図9】本発明の第4実施例を示す図で、図10のVIII
I−VIIII線断面図である。
FIG. 9 is a view showing a fourth embodiment of the present invention, which is VIII in FIG.
It is a sectional view taken along the line I-VIIII.

【図10】平面図である。FIG. 10 is a plan view.

【図11】第5実施例を示す図で、平面図である。FIG. 11 is a view showing a fifth embodiment and is a plan view.

【図12】図11のXII−XII線断面図である。12 is a sectional view taken along line XII-XII in FIG.

【図13】第6実施例を示す図で、断面図である。FIG. 13 is a sectional view showing a sixth embodiment.

【図14】第7実施例を示す図で、図15のXIV−XIV線
断面図である。
14 is a view showing a seventh embodiment and is a cross-sectional view taken along line XIV-XIV of FIG.

【図15】平面図である。FIG. 15 is a plan view.

【符号の説明】[Explanation of symbols]

1 法枠ブロック 2 植栽コンクリートブロック 8 法面ブロック 11 空間部 15 連結部材 20 連結部材 30 培養土層 1 Slope block 2 Planted concrete block 8 Slope block 11 Space part 15 Connecting member 20 Connecting member 30 Culture soil layer

───────────────────────────────────────────────────── フロントページの続き (72)発明者 伊藤 亨 山形県酒田市上本町6番7号 株式会社前 田先端技術研究所内 (72)発明者 森 浩文 東京都港区西新橋2−14−1 秩父小野田 株式会社内 (72)発明者 親林 和生 東京都港区西新橋2−14−1 秩父小野田 株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Toru Ito 6-7 Uehonmachi, Sakata City, Yamagata Prefecture Maeda Institute of Advanced Technology Co., Ltd. (72) Inventor Hirofumi Mori 2-14-1, Nishishimbashi, Minato-ku, Tokyo Chichibu Onoda Co., Ltd. (72) Inventor Kazuo Obayashi 2-14-1, Nishishimbashi, Minato-ku, Tokyo Chichibu Onoda Co., Ltd.

Claims (11)

【特許請求の範囲】[Claims] 【請求項1】 法枠ブロックの空間部中の植栽コンクリ
ートブロックを移動可能に支持して法面ブロックを形成
する工程と;該法面ブロックを緑化対象法面の上方に位
置せしめて該法面と対向せしめる工程と;該法面ブロッ
クを該法面に向って降下させ、法枠ブロックと植栽コン
クリートブロックとを互いに自由に該法面に圧着せしめ
る工程と;を備えたことを特徴とする法面緑化施工方
法。
1. A step of movably supporting a planted concrete block in a space of a slope frame block to form a slope block; locating the slope block above a slope to be greened A step of causing the slope block to face the slope; a step of lowering the slope block toward the slope so that the slope frame block and the planted concrete block are freely crimped to the slope. Slope greening construction method.
【請求項2】 植栽コンクリートブロックが、法面ブロ
ックの吊り上げ時に法枠ブロックから張り出すことを特
徴とする請求項1記載の法面緑化施工方法。
2. The slope-vegetation construction method according to claim 1, wherein the planted concrete block projects from the slope frame block when the slope block is suspended.
【請求項3】 緑化対象法面が、培養土層を備えている
ことを特徴とする請求項1記載の法面緑化施工方法。
3. The slope revegetation construction method according to claim 1, wherein the slope to be planted has a culture soil layer.
【請求項4】 空間部を有する法枠ブロックと;該空間
部に遊嵌合された植栽コンクリートブロックと;該両ブ
ロックを移動自在に支持する支持手段と;を備えたこと
を特徴とする法面ブロック。
4. A law frame block having a space; a planting concrete block loosely fitted in the space; and a support means for movably supporting both blocks. Slope block.
【請求項5】 支持手段が、連結部材であることを特徴
とする請求項4記載の法面ブロック。
5. The slope block according to claim 4, wherein the supporting means is a connecting member.
【請求項6】 連結部材が、法枠ブロックに設けた係合
部材と、植栽コンクリートブロックに設けた係合部材
と、からなることを特徴とする請求項5記載の法面ブロ
ック。
6. The slope block according to claim 5, wherein the connecting member comprises an engagement member provided on the slope frame block and an engagement member provided on the planted concrete block.
【請求項7】 支持手段が、法枠ブロックに設けた係止
金具と、植栽コンクリートブロックに設けた係合段部
と、からなることを特徴とする請求項4記載の法面ブロ
ック。
7. The slope block according to claim 4, wherein the support means comprises a locking metal fitting provided on the slope frame block and an engagement step provided on the planting concrete block.
【請求項8】 支持手段が、法枠ブロックの空間部のテ
ーパ内面と、該テーパ内面と対向する植栽コンクリート
ブロックのテーパ外周面と、からなることを特徴とする
請求項4記載の法面ブロック。
8. The sloped surface according to claim 4, wherein the supporting means comprises a tapered inner surface of the space portion of the slope frame block and a tapered outer peripheral surface of the planted concrete block facing the tapered inner surface. block.
【請求項9】 支持手段が、法枠ブロックにより支持さ
れ、かつ、該法枠ブロックの空間部に張設され植栽コン
クリートブロックの載置部材であることを特徴とする請
求項4記載の法面ブロック。
9. The method according to claim 4, wherein the supporting means is a mounting member for the planting concrete block which is supported by the law frame block and is stretched in the space portion of the law frame block. Face block.
【請求項10】 植栽コンクリートブロックの載置部材
が、不織布を介して植栽コンクリートブロックを保持し
ていることを特徴とする請求項9記載の法面ブロック。
10. The slope block according to claim 9, wherein the placing member of the planting concrete block holds the planting concrete block through a nonwoven fabric.
【請求項11】 支持手段が、一端を法枠ブロックに固
定され、他端を植栽コンクリートブロックに固定された
ワイヤであることを特徴とする請求項4記載の法面ブロ
ック。
11. The slope block according to claim 4, wherein the supporting means is a wire having one end fixed to the slope frame block and the other end fixed to the planting concrete block.
JP33039995A 1995-12-19 1995-12-19 Slope face block and slope face greening construction method Pending JPH09165750A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33039995A JPH09165750A (en) 1995-12-19 1995-12-19 Slope face block and slope face greening construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33039995A JPH09165750A (en) 1995-12-19 1995-12-19 Slope face block and slope face greening construction method

Publications (1)

Publication Number Publication Date
JPH09165750A true JPH09165750A (en) 1997-06-24

Family

ID=18232173

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33039995A Pending JPH09165750A (en) 1995-12-19 1995-12-19 Slope face block and slope face greening construction method

Country Status (1)

Country Link
JP (1) JPH09165750A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101942819A (en) * 2010-09-01 2011-01-12 河南省水利勘测设计研究有限公司 Concrete plate roughening slope protection structure
JP2018184722A (en) * 2017-04-24 2018-11-22 旭化成アドバンス株式会社 Reinforcement construction of dike rear slope toe, reinforcement method of dike rear slope toe and block mat for reinforcing dike rear slope toe
CN109736266A (en) * 2018-12-27 2019-05-10 金华市恒通工程检测有限公司 Watch out for bank-protection works mold-bagged concrete protective slope structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101942819A (en) * 2010-09-01 2011-01-12 河南省水利勘测设计研究有限公司 Concrete plate roughening slope protection structure
JP2018184722A (en) * 2017-04-24 2018-11-22 旭化成アドバンス株式会社 Reinforcement construction of dike rear slope toe, reinforcement method of dike rear slope toe and block mat for reinforcing dike rear slope toe
CN109736266A (en) * 2018-12-27 2019-05-10 金华市恒通工程检测有限公司 Watch out for bank-protection works mold-bagged concrete protective slope structure

Similar Documents

Publication Publication Date Title
KR100947248B1 (en) A stone structure for the protection of slope and constructing method thereof
JPH09165750A (en) Slope face block and slope face greening construction method
JP2006169957A (en) Block for civil-engineering structure, and block component member for civil-engineering structure
JPS61183521A (en) Method of stabilizing vegetation foundation on face of slope
JP2007327274A (en) Construction method of vegetation slope frame
JPH05171652A (en) Slope stability method
JPH10292380A (en) Slope greening method
JP3004226B2 (en) Slope protection method and wire mesh used for the method
CN211523246U (en) Falling zone plants protection solid slope string bag of green planting
KR20090078315A (en) Construction work of net and plantland breast wall for plantland collapse prevention for cut-slope mode of life restoration
JPH11293678A (en) Slope protection construction method
JPH05295714A (en) Vegetation block
JPH09184145A (en) Greening block and its manufacture and the greening block execution method
JPH08105051A (en) Planting base and planing jig therefor
JP2003034938A (en) Block for retaining wall
JP2000248553A (en) Repairing scene seeding and planting construction method of face of slope
JP2006169860A (en) Method of producing block for civil-engineering structure
JP3117066B2 (en) Slope reinforcement and greening method and its fabric sheet
CN109339073B (en) Device and method for supporting soft rock and hard rock interbedded rock mass side slope and realizing surface layer greening
CN207567792U (en) A kind of deep stable rock slope greening mechanism
JPH1037199A (en) Greening work method for face of slope
KR20100064651A (en) Eco-friendly afforestation method
JPH0756331Y2 (en) Natural stone joint block
JPH0363316A (en) Block for plantation
JPH10147939A (en) Planting base board establishing method and planting block