JPH09158158A - Filling type concrete dam and construction method thereof - Google Patents

Filling type concrete dam and construction method thereof

Info

Publication number
JPH09158158A
JPH09158158A JP33986495A JP33986495A JPH09158158A JP H09158158 A JPH09158158 A JP H09158158A JP 33986495 A JP33986495 A JP 33986495A JP 33986495 A JP33986495 A JP 33986495A JP H09158158 A JPH09158158 A JP H09158158A
Authority
JP
Japan
Prior art keywords
concrete
dam
rock
filling
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP33986495A
Other languages
Japanese (ja)
Inventor
Eitaro Yoshitomi
英太郎 吉富
Shinji Fukushima
伸二 福島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP33986495A priority Critical patent/JPH09158158A/en
Publication of JPH09158158A publication Critical patent/JPH09158158A/en
Withdrawn legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To save the consumption of cement in the construction of a dam body. SOLUTION: A dam body D comprises a rock placed concrete area 1 cast on a foundation bedrock G, a large-sized mass of rock 21 and a core concrete area 2 comprising concrete or mortar 22 filled in a clearance between each mass of rock 21 and outside concrete areas 3 and 4 having a specified thickness, which are provided on a surface layer on the upstream side and the downstream side of this concrete area and whose lower end is joined with the upstream side of the placed rock concrete 1 and the top on the end on the downstream side.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、ダムの構築技術に
関するものである。
TECHNICAL FIELD The present invention relates to a dam construction technique.

【0002】[0002]

【従来の技術】従来、コンクリート重力ダムには、ケー
ブルクレーンあるいはジグクレーン等によって、コンク
リートバケットで運搬されたコンクリートを、柱状ブロ
ックで打ち込み、内部振動機で締め固めて堤体を構築し
て行く通常型のダムや、貧配合の超硬練りコンクリート
を用いてダンプトラック等で運搬し、これをブルドーザ
で敷き均して、振動目地切り機で目地を造成し、フィル
ダムの構築で用いられるような振動ローラで締め固めて
構築するRCDダムがある。
2. Description of the Related Art Conventionally, in concrete gravity dams, concrete transported in concrete buckets is driven by a cable bucket or jig crane into a columnar block and compacted by an internal vibrator to construct a dam body. Type dam, or a super-hard concrete containing poor mix, and then transporting it with a dump truck, etc., laying it with a bulldozer and leveling it, and creating joints with a vibrating joint cutting machine. There is an RCD dam that is constructed by compacting with rollers.

【0003】[0003]

【発明が解決しようとする課題】しかし、上記従来工法
によるコンクリートダムの構築においては、いずれも、
セメントに骨材を練り混ぜたコンクリートを打設するこ
とによって堤体を構築して行くので、大量のセメントが
必要であり、しかもこの大量のコンクリートの打ち込
み、敷き均し及び振動締め固め等の面倒な作業量が多い
という問題が指摘される。また、大量のコンクリートの
打ち込みを行うと、その硬化時の水和反応に伴う発熱量
が大きくなるため、1回あたりの打設量を制限せざるを
得ず、工期が長くなる問題もある。
However, in the construction of the concrete dam by the above-mentioned conventional construction method,
A large amount of cement is required because a levee body is constructed by placing concrete in which cement is mixed into aggregates, and moreover, a large amount of cement is required. It is pointed out that there is a large amount of work. In addition, when a large amount of concrete is poured, the amount of heat generated due to the hydration reaction at the time of hardening thereof becomes large, so that there is no choice but to limit the setting amount per time, and there is a problem that the construction period becomes long.

【0004】本発明は、上記のような事情のもとになさ
れたもので、その技術的課題とするところは、ダムの構
築におけるセメントの使用量を節減し、かつ作業量を軽
減して、工期を短縮することにある。
The present invention has been made under the above circumstances, and its technical problem is to reduce the amount of cement used in the construction of a dam and to reduce the work amount. It is to shorten the construction period.

【0005】[0005]

【課題を解決するための手段】上述した技術的課題は、
本発明によって有効に解決することができる。すなわ
ち、本発明に係る間詰め式コンクリートダムは、所定高
さに積み上げた岩塊群及びこの岩塊群の間隙に充填され
た間詰めコンクリートからなるコアコンクリート領域
と、このコアコンクリート領域の上流側及び下流側の表
層に設けられた水密コンクリートからなる外部コンクリ
ート領域とを有するものである。この間詰め式コンクリ
ートダムは、ダム堤体施工領域における上流側の端部上
及び下流側の端部上にそれぞれ型枠を組み立ててコンク
リートを打設することにより上流側及び下流側の外部コ
ンクリート領域を施工し、これら両外部コンクリート領
域間に岩塊を投入しこの岩塊群の隙間にモルタル又はコ
ンクリートを間詰めしてコアコンクリート領域を施工す
るといった工程を繰り返し行うことによって構築され
る。
The above-mentioned technical problems are as follows.
This can be effectively solved by the present invention. That is, the filling concrete dam according to the present invention includes a core concrete region composed of a group of rocks piled up at a predetermined height and a filling concrete filled in a gap of the group of rocks, and an upstream side of the core concrete region. And an external concrete region made of watertight concrete provided on the surface layer on the downstream side. This space-filling type concrete dam assembles a formwork on the upstream end and the downstream end of the dam body construction area, respectively, and places concrete to form the upstream and downstream external concrete areas. It is constructed by repeating the steps of constructing, injecting a rock mass between these two outer concrete regions, filling the gap between the rock masses with mortar or concrete, and constructing the core concrete region.

【0006】本発明において、コアコンクリート領域は
その強度及び重量によってダム堤体を安定させるもので
あるが、積み上げた岩塊群の間隙にコンクリート又はモ
ルタルを間詰めした構造であるため、岩塊相互の咬み合
わせ強度と、間詰めコンクリート又はモルタルによる岩
塊相互の結合力とが複合された十分な強度が得られ、か
つ間詰めによって十分な重量が得られる。また、岩塊群
の使用によって、コンクリート重力ダムに比較してセメ
ントの使用量が著しく少なくなり、コンクリート打設に
伴うコンクリートの敷き均しや振動締め固め等の作業も
不要である。コアコンクリート領域の上流側及び下流側
の表層に設けられた外部コンクリート領域は、水密性及
び耐久性の高いコンクリートからなるものであって、コ
アコンクリートの施工の際に積み上げた岩塊群の両側の
ガイドとしての機能と、この岩塊群の間隙に注入した未
硬化のコンクリート又はモルタルが流出してしまうのを
防止する堰としての機能を有し、更に施工後は、貯水に
対する遮水壁として機能するものである。
In the present invention, the core concrete region stabilizes the dam embankment by its strength and weight. However, since it has a structure in which concrete or mortar is packed in the gaps of the rock masses piled up, the rock mass mutual Sufficient strength is obtained by combining the bite strength of No. 3 and the interlocking force between the rock masses of the stuffed concrete or mortar, and a sufficient weight is obtained by the stuffing. In addition, the use of rock masses significantly reduces the amount of cement used compared to concrete gravity dams, eliminating the work such as leveling and vibration compaction of concrete when placing concrete. The outer concrete area provided on the surface layer on the upstream side and the downstream side of the core concrete area is made of concrete with high watertightness and durability, and is located on both sides of the rock masses piled up during the construction of the core concrete. It has a function as a guide and a weir that prevents the uncured concrete or mortar injected into the gaps of the rock mass from flowing out, and also functions as an impermeable wall against water storage after construction. To do.

【0007】なお、岩塊群を用いて構築されるダムとし
ては、一般に、ロックフィルダムが知られている。ロッ
クフィルダムは、透水性の低い粘性土等の土質材料から
なるコア領域の上流側及び下流側に岩塊群からなるロッ
ク領域が、コア材の流出を防止するためのフィルタ領域
を介して設けられたもので、この場合のロック領域は、
積み上げた岩塊の互いの咬み合いによってダム堤体全体
を安定させるものであるが、本発明の間詰め式コンクリ
ートダムにおけるコアコンクリート領域は、積み上げた
岩塊の互いの咬み合いと、各岩塊間の隙間を埋めている
間詰めコンクリートの結合力及び重量によってダム堤体
を安定させている。したがって、堤体断面は、ロックフ
ィルダムよりも小さくできるが、大型のダンプトラック
等で運搬して来た大粒径の岩塊群を積み上げるのに適し
た十分なスペースが確保できるように、通常のコンクリ
ート重力ダムよりは堤体断面を大きくすることが望まし
い。すなわち本発明は、堤体積の低減よりも、大型土木
機械による施工性の向上及び施工コストの低減を優先さ
せたものである。
Rock fill dams are generally known as dams constructed using rock masses. The rockfill dam is provided with rock regions composed of rock masses on the upstream side and the downstream side of a core region made of a soil material such as cohesive soil having low water permeability through a filter region for preventing the outflow of the core material. The lock area in this case is
Although the whole dam dam body is stabilized by the mutual engagement of the stacked rock masses, the core concrete region in the filling concrete dam of the present invention is such that the stacked rock masses are interlocked with each other and The dam embankment is stabilized by the bonding force and weight of the filling concrete that fills the gap between the dams. Therefore, the cross section of the dam body can be made smaller than that of the rockfill dam, but it is necessary to secure a sufficient space suitable for accumulating large-sized rock masses transported by a large dump truck. It is desirable to make the cross section of the dam body larger than that of the concrete gravity dam. That is, the present invention prioritizes improvement of workability and reduction of construction cost by a large-scale civil engineering machine rather than reduction of bank volume.

【0008】[0008]

【発明の実施の形態】図1は、本発明に係る間詰め式コ
ンクリートダムの好適な一実施形態を示す断面図で、図
中左側が貯水される上流側、右側が下流側である。参照
符号Dで総括して示すダム堤体は、基礎岩盤G上を、上
流側と下流側の間を横断する図示の断面と直交する方向
に横断するように延び、上流側及び下流側の面が所定の
安定勾配に形成されている。このダム堤体Dは、基礎岩
盤G上に打設された着岩コンクリート領域1と、大粒径
の岩塊21群及びその各岩塊21間の間隙に間詰めされ
たコンクリート又はモルタル22からなるコアコンクリ
ート領域2と、このコアコンクリート領域2の上流側及
び下流側の表層に設けられ下端が前記着岩コンクリート
1の上流側及び下流側の端部上面に接合された所定層厚
の外部コンクリート領域3,4とで構成される。
1 is a cross-sectional view showing a preferred embodiment of a filling concrete dam according to the present invention, in which the left side is the upstream side where water is stored and the right side is the downstream side. The dam levee body generally indicated by the reference symbol D extends on the foundation bedrock G so as to cross in a direction orthogonal to the illustrated cross section that crosses between the upstream side and the downstream side, and the upstream and downstream surfaces. Are formed in a predetermined stable gradient. This dam embankment D is composed of a landing concrete region 1 cast on a foundation bedrock G, a group of large-sized rock masses 21 and concrete or mortar 22 packed in the gaps between the rock masses 21. Core concrete area 2 and an outer concrete of a predetermined layer thickness, the lower end of which is provided on the surface layer on the upstream side and the downstream side of the core concrete area 2 and the lower end of which is joined to the upper surface of the end portion of the rock concrete 1 on the upstream side and the downstream side. It is composed of regions 3 and 4.

【0009】ダム堤体Dの下端部に相当する着岩コンク
リート領域1は、その上に構築される領域の全荷重を受
けるものであり、かつ十分な水密性を要求されることか
ら、富配合コンクリートで構築され、基礎岩盤Gの適当
な深さに半埋設状態に設けられる。これによって、貯水
圧によるダム堤体Dの水平変位や、貯水された水Wが基
礎岩盤Gとの境界に沿って下流側へ漏洩するのを防止し
ている。コアコンクリート領域2は、ダム堤体D全体の
安定を維持するものであるため、ここで使用される大粒
径の岩塊21は、積み上げられた状態での岩塊21相互
の咬み合わせ強度が十分に発揮されるように、風化して
いない新鮮かつ堅牢で十分な強度を有する岩質のものが
選択され、間詰めコンリート又はモルタル22は、積み
上げられた岩塊21群の間隙に完全に充填されるために
必要な十分な流動性と、岩塊21同士を固結させるのに
十分な強度を有するものが選択される。外部コンクリー
ト領域3,4は、十分な強度及び水密性を要求されるた
め、着岩コンクリート領域1と同様の富配合コンクリー
トの打設によって形成される。
The rock-bearing concrete region 1 corresponding to the lower end of the dam body D receives the entire load of the region constructed on it and is required to have sufficient watertightness. Constructed of concrete, it is semi-buried at an appropriate depth of the foundation bedrock G. This prevents horizontal displacement of the dam bank D due to the stored water pressure and leakage of the stored water W downstream along the boundary with the foundation bedrock G. Since the core concrete region 2 maintains the stability of the entire dam embankment D, the large-sized rock mass 21 used here has a biting strength of the rock masses 21 in the stacked state. Fresh, robust, and rock-strength that is not weathered and has sufficient strength is selected so that it can be fully exerted, and the filling consort or mortar 22 completely fills the gaps between the stacked blocks 21. A material having sufficient fluidity necessary to be worked and strength sufficient to consolidate the rock masses 21 is selected. Since the outer concrete regions 3 and 4 are required to have sufficient strength and watertightness, they are formed by pouring the rich mixed concrete as in the landing concrete region 1.

【0010】以下、本発明の構築方法を上記ダム堤体D
の構築に適用した実施形態を、図2を参照しながら工程
順に説明する。
The construction method of the present invention will be described below with reference to the dam body D
The embodiment applied to the construction will be described in the order of steps with reference to FIG.

【0011】まず図2(A)に示すように、ダム建設予
定地の基礎岩盤Gの表層部を適当な深さに根切りして整
地した後、図示の断面と直交する方向に延びるこの根切
り部に富配合のコンクリートを打設することによって、
所要の層厚の着岩コンクリート領域1を施工する。
First, as shown in FIG. 2 (A), the surface layer portion of the foundation rock mass G at the site where the dam is to be constructed is root-cut to an appropriate depth to level the ground, and then the root extending in a direction orthogonal to the cross section shown in the figure. By placing concrete with a rich mixture in the cut part,
The rock-bearing concrete area 1 having the required layer thickness is constructed.

【0012】着岩コンクリート領域1のコンクリートが
硬化したら、図2(B)に示すように、この着岩コンク
リート領域1の上流側及び下流側の端部に沿って、型枠
5,6を組み立てる。この型枠5,6は、それぞれ堰板
51a,61aの下端が着岩コンクリート領域1のコン
クリートの縁部に当接した外側型枠51,61と、前記
コンクリート上に組み立てられて堰板52a,62aが
前記外側型枠51,61の堰板51a,61aと対向し
た内側型枠52,62とからなるものである。またこの
型枠5,6は、第1層目の施工高さに対応した高さΔh
を有すると共に、堰板51a,52a及び61a,62
aは、施工しようとするダム堤体Dの両側面の法面勾配
に対応して内側へ所定角度で傾斜している。
When the concrete in the rock landing concrete area 1 is hardened, as shown in FIG. 2B, the molds 5 and 6 are assembled along the upstream and downstream ends of the rock landing concrete area 1. . These formwork 5 and 6 are outer formwork 51 and 61 in which the lower ends of the weir plates 51a and 61a are in contact with the edges of the concrete of the rock landing concrete area 1, and the weir plates 52a, which are assembled on the concrete. 62a is composed of the barrier plates 51a, 61a of the outer molds 51, 61 and the inner molds 52, 62 facing each other. The formwork 5, 6 has a height Δh corresponding to the construction height of the first layer.
And the weir plates 51a, 52a and 61a, 62
The angle a is inwardly inclined at a predetermined angle corresponding to the slope of both side surfaces of the dam body D to be constructed.

【0013】型枠5,6を組み立てたら、図2(C)に
示すように、その堰板51a,52aによって画成され
た打設空間及び堰板61a,62aによって画成された
打設空間に、それぞれ富配合のコンクリートを撒き出
し、振動機等で締め固めることによって上流側及び下流
側の第1層目の外部コンクリート領域31 ,41 を形成
する。
After the molds 5 and 6 are assembled, as shown in FIG. 2C, the placing space defined by the weir plates 51a and 52a and the placing space defined by the weir plates 61a and 62a. First, the concrete with a rich mixture is sprinkled out and compacted by a vibrator or the like to form the outer concrete regions 3 1 and 4 1 of the first layer on the upstream side and the downstream side.

【0014】外部コンクリート領域31 ,41 のコンク
リートに、所定時間の経過によって適当な硬度が発現さ
れたら、型枠5,6を撤去し、前記外部コンクリート領
域31 ,41 によって挟まれたコア形成空間に、図2
(D)に示すように、大型ダンプトラック等により搬入
された大粒径の岩塊21群を投入して、各岩塊11を互
いに咬み合うように、かつ前記第1層目の外部コンクリ
ート領域31 ,41 の上端とほぼ同等となる高さで前記
空間に積み上げる。この時、外部コンクリート領域3
1 ,41 は、積み上げた岩塊21群を両側から押さえて
ガイドする役割を奏する。
When a suitable hardness is developed in the concrete of the outer concrete regions 3 1 , 4 1 over a predetermined time, the molds 5, 6 are removed and sandwiched by the outer concrete regions 3 1 , 4 1 . In the core forming space,
As shown in (D), a large-sized rock mass 21 group carried in by a large-sized dump truck or the like is thrown in so that the rock masses 11 bite each other, and the outer concrete region of the first layer. The space is piled up in the space at a height almost equal to the upper ends of 3 1 and 4 1 . At this time, the external concrete area 3
1 and 4 1 play a role of pressing and guiding the stacked rock masses 21 from both sides.

【0015】コア形成空間への岩塊21群の積み上げが
完了したら、これら各岩塊21の間に形成された互いに
連続した間隙に、図2(E)に示すように、高流動性の
コンクリート又はモルタル22を注入して間詰めする。
このコンクリート又はモルタル22は、大型のダンプト
ラックあるいはクレーンとコンクリートバケット等によ
り運搬されて岩塊21群の上から注入され、前記間隙に
充填されるため、内部振動機による締め固めや、ブルド
ーザ等による敷き均し等の作業は行う必要がなく、岩塊
21群の両側は外部コンクリート領域31 ,41 で堰き
止められているため、間詰めされたコンクリート又はモ
ルタル22の流出が確実に防止される。間詰めされたコ
ンリート又はモルタル22は、時間の経過と共に硬化す
ることによって岩塊21同士を固結させて大きな靭性を
発現し、これによって、第1層目の外部コンクリート領
域31 ,41 と接合された第1層目のコアコンクリート
領域21 が形成される。
When the group of rock masses 21 has been piled up in the core forming space, high fluidity concrete is formed in the mutually continuous gaps formed between the rock masses 21 as shown in FIG. 2 (E). Alternatively, mortar 22 is injected to fill the space.
This concrete or mortar 22 is carried by a large dump truck or a crane and a concrete bucket, injected from above the rock mass 21 group, and filled in the gap, so that it is compacted by an internal vibrator or by a bulldozer or the like. Since it is not necessary to perform work such as spreading and leveling, both sides of the rock mass 21 group are dammed by the external concrete areas 3 1 and 4 1 , so that the outflow of the packed concrete or mortar 22 is reliably prevented. It The packed concrete or mortar 22 hardens with the passage of time to consolidate the rock masses 21 and develops a large toughness, whereby the outer concrete regions 3 1 and 4 1 of the first layer are formed. The joined first-layer core concrete region 2 1 is formed.

【0016】なお、岩塊21の粒径は特に限定するもの
ではないが、ある程度粒径が大きいものを用いることに
よって、コンクリート又はモルタル22の注入抵抗が小
さくなるので、確実に間詰めすることができ、例えば地
山の切土あるいは基礎岩盤Gの根切り等によって発生し
た粗粒岩塊を、破砕等の細粒化工程を施すことなくその
まま使用することができる。
The grain size of the rock mass 21 is not particularly limited, but the use of a grain size having a relatively large grain size reduces the injection resistance of the concrete or the mortar 22, so that the rock mass can be reliably packed. It is possible to use, for example, a coarse-grained rock mass generated by cutting the ground or cutting the foundation bedrock G, etc., without using a refining step such as crushing.

【0017】このようにして施工されたコアコンクリー
ト領域21 の体積の大部分は、岩塊21が占めるため、
使用されるコンクリート又はモルタル22の量、すなわ
ちセメントの使用量は、コンクリート重力ダムに比較し
て著しく少ないものとなる。またこのため、コンクリー
ト又はモルタル22の硬化時の水和反応に伴う発熱量も
少なく、1回の工程で大区画の施工が可能である。
Since most of the volume of the core concrete region 2 1 thus constructed is occupied by the rock mass 21,
The amount of concrete or mortar 22 used, that is, the amount of cement used, is significantly smaller than that of the concrete gravity dam. For this reason, the amount of heat generated by the hydration reaction during hardening of the concrete or mortar 22 is small, and a large section can be constructed in one step.

【0018】上述の一連の工程によって第1層目が施工
されたら、工事をその上段に移行させ、図2(B)から
の工程を再び実行して行く。すなわち、図3(A)に示
すように、まず第1層目の外部コンクリート領域31
1 の上面の両側縁に沿って図2(B)と同様の型枠
5’,6’を組み立て、これにコンクリートを打設する
ことによって、前記第1層目の外部コンクリート領域3
1 ,41 と連続した第2層目の外部コンクリート領域3
2 ,42 を施工し、次にこの外部コンクリート領域3
2 ,42 に挟まれたコア形成空間に、図3(B)及び
(C)に示すように岩塊21群を積み上げてその間隙に
コンクリート又はモルタル22を間詰めし、これによっ
て第2層目のコアコンクリート領域22 を施工する。以
下、このような工程をn回繰り返して、第n層目まで施
工することによって、図1に示すような高さhの間詰め
式コンクリートダムの堤体Dの構築が完了する。
When the first layer is constructed by the series of steps described above, the construction is shifted to the upper stage and the steps from FIG. 2B are executed again. That is, as shown in FIG. 3 (A), first, the first outer concrete region 3 1 ,
4 1 along the opposite side edges of the upper surface Figure 2 (B) and the same mold 5 ', 6' assembled, by pouring concrete into this, the first layer of the external concrete area 3
1, 4 1 second layer outer concrete area 3 continuous with
2 and 4 2 were constructed, then this external concrete area 3
As shown in FIGS. 3 (B) and 3 (C), a group of rock masses 21 are piled up in the core forming space sandwiched between 2 and 4 2 and concrete or mortar 22 is packed in the gap, whereby the second layer is formed. Construction of eye core concrete area 2 2 . Hereinafter, by repeating such a process n times and constructing up to the n-th layer, the construction of the dike D of the filling concrete dam of height h as shown in FIG. 1 is completed.

【0019】[0019]

【発明の効果】本発明によると、次の効果が実現され
る。 (1) コアコンクリート領域が、岩塊群の間隙をコンクリ
ート又はモルタルで間詰めすることによって施工され、
セメントの使用量が大幅に節減されるため、施工費用が
低減され、しかも通常のコンクリート重力ダムの施工に
おいて問題となるコンクリートの発熱量を低減すること
ができる。 (2) コアコンクリート領域の施工において、大量のコン
クリートの打ち込み、敷き均し及び振動締め固めといっ
た作業が不要であるため、作業量を減少させ、省力化が
可能である。 (3) 積み上げられた岩塊相互の咬み合わせ強度と、間詰
めコンクリート又はモルタルによる岩塊相互の結合力と
によってコアコンクリート領域の十分な強度が得られ、
かつ間詰めによって十分な重量が得られるので、ロック
フィルダムのような大きな堤体断面積を必要としない。 (4) 使用される岩塊の粒径に制限はなく、所定の強度を
有する堅牢な岩質のものであれば、大粒径のものをその
まま使用できるため、低コストで岩塊を調達することが
できる。
According to the present invention, the following effects are realized. (1) The core concrete area is constructed by filling the gaps of the rock mass with concrete or mortar,
Since the amount of cement used is greatly reduced, the construction cost can be reduced, and the heat generation amount of concrete, which is a problem in the construction of a normal concrete gravity dam, can be reduced. (2) In the construction of the core concrete area, it is possible to reduce the amount of work and save labor, because the work of placing a large amount of concrete, spreading and leveling, and vibration compaction is unnecessary. (3) Sufficient strength of the core concrete area is obtained by the biting strength of the stacked rock masses and the binding force of the rock masses by the packed concrete or mortar.
Moreover, since sufficient weight can be obtained by the space filling, a large levee cross-sectional area such as that of the rockfill dam is not required. (4) There is no limitation on the particle size of the rock mass used, and as long as it is a rocky material with a certain strength, it can be used as it is with a large particle size, so the rock mass can be procured at low cost. be able to.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る間詰め式コンクリートダムの好適
な一実施形態を示す断面図である。
FIG. 1 is a cross-sectional view showing a preferred embodiment of a filling concrete dam according to the present invention.

【図2】上記間詰め式コンクリートダムの第1層目の施
工工程を工程順に示す説明図である。
FIG. 2 is an explanatory view showing a step of constructing a first layer of the filling concrete dam in the order of steps.

【図3】上記間詰め式コンクリートダムの第2層目の施
工工程を工程順に示す説明図である。
FIG. 3 is an explanatory diagram showing a step of constructing a second layer of the filling concrete dam in the order of steps.

【符号の説明】[Explanation of symbols]

1 着岩コンクリート領域 2 コアコンクリート領域 21 岩塊 22 間詰めコンリート又はモルタル 3,4 外部コンクリート領域 1 Landed concrete area 2 Core concrete area 21 Rock mass 22 Filled concrete or mortar 3,4 External concrete area

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 所定高さに積み上げた岩塊群及びこの岩
塊群の間隙に充填された間詰めコンクリートからなるコ
アコンクリート領域と、 このコアコンクリート領域の上流側及び下流側の表層に
設けられた水密コンクリートからなる外部コンクリート
領域と、を有することを特徴とする間詰め式コンクリー
トダム。
1. A core concrete region composed of a group of rocks piled up to a predetermined height and a filling concrete filled in a gap of the group of rocks, and a surface layer on the upstream and downstream sides of the core concrete region. An outer concrete area made of watertight concrete, and a filling concrete dam.
【請求項2】 ダム堤体施工領域における上流側の端部
上及び下流側の端部上にそれぞれ型枠を組み立ててコン
クリートを打設することにより上流側及び下流側の外部
コンクリート領域を施工する工程と、 これら両外部コンクリート領域間に岩塊を投入してこの
岩塊群の隙間にモルタル又はコンクリートを間詰めする
ことによりコアコンクリート領域を施工する工程と、を
交互に繰り返すことにより所要高さのダム堤体を構築す
ることを特徴とする請求項1に記載の間詰め式コンクリ
ートダムの構築方法。
2. The upstream and downstream external concrete areas are constructed by assembling a formwork and placing concrete on the upstream end and the downstream end of the dam embankment construction area, respectively. The required height can be obtained by alternately repeating the steps and the step of constructing the core concrete area by putting rock mass between these two outer concrete areas and filling the space between the rock masses with mortar or concrete. The method for constructing a filling type concrete dam according to claim 1, wherein the dam dam body is constructed.
JP33986495A 1995-12-05 1995-12-05 Filling type concrete dam and construction method thereof Withdrawn JPH09158158A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33986495A JPH09158158A (en) 1995-12-05 1995-12-05 Filling type concrete dam and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33986495A JPH09158158A (en) 1995-12-05 1995-12-05 Filling type concrete dam and construction method thereof

Publications (1)

Publication Number Publication Date
JPH09158158A true JPH09158158A (en) 1997-06-17

Family

ID=18331555

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33986495A Withdrawn JPH09158158A (en) 1995-12-05 1995-12-05 Filling type concrete dam and construction method thereof

Country Status (1)

Country Link
JP (1) JPH09158158A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007297817A (en) * 2006-04-28 2007-11-15 Dam Gijutsu Center Form for top of slope
JP2008267044A (en) * 2007-04-23 2008-11-06 Takamura Sogyo Kk Method of constructing concrete structure with soil concrete used
CN105220654A (en) * 2015-10-12 2016-01-06 中国电建集团贵阳勘测设计研究院有限公司 A kind of ruggedized construction of earth and rockfill dam and construction method thereof
RU2593780C2 (en) * 2014-06-17 2016-08-10 ПАО "Укргидропроект" Method of making dam from rolled concrete
CN105926544A (en) * 2016-06-24 2016-09-07 中国电建集团华东勘测设计研究院有限公司 Economical debris flow blocking dam structure and construction method thereof
CN111088804A (en) * 2019-10-25 2020-05-01 中国水利水电第一工程局有限公司 Construction method of high-flow-state fine-aggregate concrete rock-fill dam in high-temperature area of equator
CN111636382A (en) * 2020-06-16 2020-09-08 中国电建集团贵阳勘测设计研究院有限公司 Transition layer structure of rock-fill concrete gravity dam and construction method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007297817A (en) * 2006-04-28 2007-11-15 Dam Gijutsu Center Form for top of slope
JP4537343B2 (en) * 2006-04-28 2010-09-01 財団法人ダム技術センター Form for shoulder
JP2008267044A (en) * 2007-04-23 2008-11-06 Takamura Sogyo Kk Method of constructing concrete structure with soil concrete used
RU2593780C2 (en) * 2014-06-17 2016-08-10 ПАО "Укргидропроект" Method of making dam from rolled concrete
CN105220654A (en) * 2015-10-12 2016-01-06 中国电建集团贵阳勘测设计研究院有限公司 A kind of ruggedized construction of earth and rockfill dam and construction method thereof
CN105926544A (en) * 2016-06-24 2016-09-07 中国电建集团华东勘测设计研究院有限公司 Economical debris flow blocking dam structure and construction method thereof
CN111088804A (en) * 2019-10-25 2020-05-01 中国水利水电第一工程局有限公司 Construction method of high-flow-state fine-aggregate concrete rock-fill dam in high-temperature area of equator
CN111636382A (en) * 2020-06-16 2020-09-08 中国电建集团贵阳勘测设计研究院有限公司 Transition layer structure of rock-fill concrete gravity dam and construction method

Similar Documents

Publication Publication Date Title
CN103958780B (en) The method for forming cementing retaining wall
CN107419630A (en) A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction
JP3010356B1 (en) How to build a tunnel
JP2007051517A (en) Construction method for forming inclined plane reinforced by external protection material
CN105604075B (en) It is easy to the interim dock entrance cofferdam construction method and cofferdam structure recovered
JP2933901B2 (en) Strengthening method for soft ground using slag
CA1185441A (en) Process of forming a continuous wall in the ground
JP2003020625A (en) Method for reinforcing soil structure bank body
JPH09158158A (en) Filling type concrete dam and construction method thereof
JP2004108142A (en) Method for construction of a control type revetment
CN110172979B (en) Roller compacted concrete damming method
JP2009293331A (en) Structure of retaining wall formed of soil improvement object and its construction method
JPH05230845A (en) L-shaped block retaining wall structure and construction method thereof
JP3528129B2 (en) Construction method for concrete structures and ground reinforcement
JP3583181B2 (en) Embankment construction method
JPH06228947A (en) Construction of landslide protection wall in ground filled up with wastes
JP2004225453A (en) Construction method of civil engineering structure
JP4170955B2 (en) Construction method of concrete structure using residual formwork and soil concrete
JP2004263490A (en) Underground composite wall
CN217870601U (en) Consolidate assembled retaining wall
JPS59170312A (en) Core construction of fill-type dam
JPH0978613A (en) Precast interlocking block member
TWI646239B (en) Stacking block for retaining wall and concrete structure using stacked block for retaining wall
JP3335593B2 (en) Underground structure construction structure
JP2022106058A (en) Construction method of headrace channel of dam and headrace channel of dam

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20030304