JP4537343B2 - Form for shoulder - Google Patents

Form for shoulder Download PDF

Info

Publication number
JP4537343B2
JP4537343B2 JP2006125622A JP2006125622A JP4537343B2 JP 4537343 B2 JP4537343 B2 JP 4537343B2 JP 2006125622 A JP2006125622 A JP 2006125622A JP 2006125622 A JP2006125622 A JP 2006125622A JP 4537343 B2 JP4537343 B2 JP 4537343B2
Authority
JP
Japan
Prior art keywords
shoulder
mold
csg
frame
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2006125622A
Other languages
Japanese (ja)
Other versions
JP2007297817A (en
Inventor
紀夫 滝口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2006125622A priority Critical patent/JP4537343B2/en
Publication of JP2007297817A publication Critical patent/JP2007297817A/en
Application granted granted Critical
Publication of JP4537343B2 publication Critical patent/JP4537343B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

本発明は、台形CSGダムなどの法肩の補強、締め固めを行うための型枠およびこの型枠を使用する法肩の締め固め方法に関するものである。   The present invention relates to a mold for reinforcing and compacting a shoulder such as a trapezoidal CSG dam and a method for compacting a shoulder using the mold.

台形ダム(堰、堤防、堤体)を構築する場合、CSG(Cemented Sand and Gravel 原位置コンクリート)工法と称せられる工法が骨材等の採取費や材料費の節減、省人化、工期短縮、環境負荷の軽減を目的として実施されている。   When constructing trapezoidal dams (weirs, dikes, levee bodies), the construction method called CSG (Cemented Sand and Gravel in-situ concrete) method reduces the cost of collecting aggregates and materials, saving labor, shortening the construction period It is implemented to reduce the environmental load.

このCSG工法は、ダム建設現場などにおいて、施工現場で採取した岩塊や土砂等を含む現地発生材を骨材に利用して、これにセメントおよび水を加えて混合し、本体工事の材料として使用することにより、骨材などの輸送費や材料費の節減、省人化、工期短縮、環境負荷の軽減を図るものである。   This CSG method uses locally generated materials including rock blocks and earth and sand collected at construction sites as the aggregates at dam construction sites, etc., and mixes them with cement and water. By using it, it is intended to reduce transportation costs and material costs such as aggregates, save labor, shorten the construction period, and reduce the environmental burden.

この工法では、前記のように現地発生材、セメントおよび水を所定の配合量で混合しCSGを製造し、施工現場に搬入するが、搬入後、CSGを敷き均すとともに、振動ローラなどを用いて転圧して締め固める。これらの工程を繰り返して階段的(層状)に積み重ねて高さを増していき、所望の台形状構造物を構築する。   In this construction method, as described above, locally generated materials, cement and water are mixed at a predetermined blending amount to produce CSG and carried to the construction site. After carrying in, CSG is spread and leveled using vibration rollers, etc. Compress and compact. These steps are repeated to build up a desired trapezoidal structure by stacking them stepwise (layered) to increase the height.

前記敷き均し工程は、運搬および搬入時に分離した混合材料をかき混ぜて均質な状態にすることと、平坦に敷き均すことで転圧作業を効果的に行うことを目的としている。すなわち、ダンプトラックによった型枠内に投入すると成分分離が生じ易く、敷き均し厚さを厚くすると、玉石など粗骨材に相当する成分だけが固まった箇所が発生して、転圧しても粗骨材の隙間にセメント系固化材が充填されなくなるおそれがある。このため、敷き均し試験を実施して適切な敷均厚を求め材料の分離を解消する。   The spread leveling step is intended to stir the mixed material separated during transportation and carry-in to make it into a homogeneous state and to perform the rolling work effectively by leveling the level. In other words, component separation tends to occur when it is put into a mold by a dump truck, and when the spreading thickness is increased, only a component corresponding to a coarse aggregate such as cobblestone is solidified and rolled. However, there is a possibility that the cement-based solidified material may not be filled in the gaps between the coarse aggregates. For this reason, a leveling test is performed to obtain an appropriate leveling thickness to eliminate material separation.

また、転圧工程では、振動ローラの自重による圧密と、振動による骨材間摩擦の減少およびセメント系固化材の流動作用によりCSGを締め固める。   In the rolling step, the CSG is compacted by compaction due to the weight of the vibration roller, reduction of friction between the aggregates due to vibration, and flow of the cement-based solidification material.

ところで、このように振動動作によって上面の締め固めを行うと法面が変形し崩れることがある。そこで、かかる不都合を解消するために、従来は、例えば金網型枠をセットし、その外側にH型鋼を設置して金網の変形抑制を図るようにしたり、または、H型鋼を型枠として積み重ねている(例えば特許文献1参照)。
特開2004−225453号公報
By the way, when the upper surface is compacted by the vibration operation in this way, the slope may be deformed and collapsed. Therefore, in order to eliminate such inconvenience, conventionally, for example, a wire mesh formwork is set and an H-shaped steel is installed outside thereof to suppress deformation of the wire mesh, or the H-shaped steel is stacked as a formwork. (For example, refer to Patent Document 1).
JP 2004-225453 A

法肩の崩壊を防止するため、H型鋼を積上げる方法では、重量の調整は積上げ数で行うしか方法がなく、その場合であっても積上げ可能な数は打設するCSGの層の厚さに規制され、例えば2段以上の積上げは出来ず、重量調整を自由に行うことが困難で、法肩を十分に支えることが難しい。   In order to prevent the shoulder from collapsing, in the method of stacking the H-shaped steel, the only way to adjust the weight is to adjust the number of stacks. For example, it is difficult to stack two or more stages, it is difficult to adjust the weight freely, and it is difficult to sufficiently support the shoulder.

また、H型鋼は1層毎に設置しているため、下層のコンクリートが完全に固化した後でなければ、上層にH型鋼を新たに設置することができず、時間を要する。   In addition, since the H-shaped steel is installed in each layer, the H-shaped steel cannot be newly installed in the upper layer unless the lower-layer concrete is completely solidified, which takes time.

本発明の目的は前記従来例の不都合を解消し、大型の振動ローラを使用して法肩部を締め固めても法肩部が崩れるおそれがなく、複数段の法肩を同時に支えることができるから法肩の補強や締め固めを効率よく行うことができ、施工性の向上を図れる法肩用の型枠およびそれを使用する法肩の締め固め方法を提供することにある。   The object of the present invention is to eliminate the inconvenience of the conventional example, and even if the shoulder portion is compacted using a large vibration roller, the shoulder portion does not collapse and can support a plurality of shoulders simultaneously. It is an object of the present invention to provide a shoulder-shoulder mold that can efficiently reinforce and compact a shoulder and to improve workability, and a method for compacting a shoulder using the same.

本発明は前記目的を達成するものとして、請求項1記載の発明は、階段状に法肩を構築する工法において使用する法肩用の型枠であって、断面方形状の複数の枠体を階段状に連結し、前記枠体の中空内部に重量調整用の水を充填したことを要旨とするものである。   The present invention achieves the above-mentioned object, and the invention according to claim 1 is a mold for a shoulder used in a construction method for constructing a shoulder in a step shape, and includes a plurality of frames having a square cross section. It is connected in a stepped manner, and the gist is that the hollow interior of the frame body is filled with water for weight adjustment.

請求項1記載の本発明によれば、複数の枠体を階段状に連結してあるから、複数段の法肩を同時に保護でき、施工性が向上する。また、枠体の内部に水を充填できるから、型枠の重量調整が容易に行えて大型の振動ローラなどを使用して締め固めを行っても型枠を重量の大きいものに形成しておけるから、法肩を確実に保護できる。そして、型枠を移動するときは内部の水を抜けば、重量が軽くなり移動が容易になる。   According to the first aspect of the present invention, since the plurality of frames are connected in a stepped manner, a plurality of shoulders can be protected at the same time, and workability is improved. In addition, because the inside of the frame can be filled with water, the weight of the mold can be easily adjusted, and even if it is compacted using a large vibration roller, the mold can be formed with a large weight. Therefore, the shoulder can be protected reliably. When moving the mold, if the water inside is removed, the weight becomes light and the movement becomes easy.

請求項2記載の発明は、前記枠体の上部に給水口と空気抜き孔を設け、側部に排水口を設けたことを要旨とするものである。   The gist of the invention described in claim 2 is that a water supply port and an air vent hole are provided in the upper portion of the frame body, and a drain port is provided in the side portion.

請求項2記載の本発明によれば、枠体の重量調整は、上部の給水口からの水の給水量、排水口からの排水量で自由に調整でき、施工現場に対応させて柔軟に対処できる。   According to the second aspect of the present invention, the weight adjustment of the frame can be freely adjusted by the amount of water supplied from the upper water supply port and the amount of water discharged from the water discharge port, and can be flexibly dealt with in accordance with the construction site. .

請求項3記載の発明は、上下の枠体はL字型の接続材で上段の側面部と下段の上面部を連結することを要旨とするものである。   The gist of the invention described in claim 3 is that the upper and lower frames are connected to the upper side surface portion and the lower upper surface portion by an L-shaped connecting material.

請求項3記載の本発明によれば、上下の枠体は、L字型の接続材で連結されるから、簡単な構造で型枠を階段状のものに形成できる。   According to the third aspect of the present invention, since the upper and lower frame bodies are coupled by the L-shaped connecting material, the mold frame can be formed in a stepped shape with a simple structure.

請求項4記載の発明は、階段状に連結した枠体を一体化した状態で吊上げ可能な吊具を枠体に設けたことを要旨とするものである。   The gist of the invention described in claim 4 is that the frame body is provided with a lifting tool that can be lifted in an integrated state of the frame bodies connected in a stepped shape.

請求項4記載の本発明によれば、吊具で吊あげるだけで、階段状の型枠を一体物として吊上げられるから、複数段の法肩の同時保護が容易に行え、階段状に立ち上げる工程の進行を早めることができ、施工性が向上する。   According to the fourth aspect of the present invention, since the staircase-shaped formwork can be lifted as a single object simply by lifting it with a lifting tool, simultaneous protection of multiple shoulders can be easily performed, and the staircase is raised in a staircase shape. The progress of the process can be accelerated and the workability is improved.

請求項5記載の発明は、工法として、複数の断面方形状の枠体を階段状に連結した型枠を複数段の法肩の箇所に設置し、最上段の法肩を締め固めた後、階段状の型枠を1段ずつ上方へ盛りかえることを要旨とするものである。   The invention according to claim 5 is a construction method in which a plurality of step-shaped frame bodies connected in a step-like manner are installed at a plurality of shoulder positions, and the upper shoulder is compacted. The gist is to fold up the step-like formwork one step at a time.

請求項5記載の本発明によれば、法肩を複数段同時に保護できると同時に、上方への型枠の移動ストロークは1段で行うから、法肩が保護される時間を長く確保できて保護が確実になる。また、型枠は複数段を1セットにして複数の枠体が移動するから移動が容易で効率的に行える。   According to the fifth aspect of the present invention, the shoulder can be protected simultaneously in a plurality of steps, and at the same time, the upward movement of the formwork is performed in one step, so that the time for protecting the shoulder can be secured for a long time. Is certain. In addition, the mold can be moved easily and efficiently because a plurality of frames are moved in a set of a plurality of stages.

以上述べたように本発明の法肩用の型枠およびこの型枠を使用する法肩の締め固め方法は、大型の振動ローラを使用して法肩部を締め固めても、現場の状況に対応する重量の大きい型枠の使用が可能となるから、法肩部を確実に保護できて崩れるおそれがなく、複数段の法肩を同時に支えることができるから法肩の補強や締め固めを効率よく行うことができ、施工性の向上を図れるものである。   As described above, the method for compacting the shoulder of the present invention and the method of compacting the shoulder using the mold according to the present invention is suitable for the situation in the field even if the shoulder is compacted using a large vibration roller. Corresponding heavy formwork can be used, so that the shoulder can be reliably protected and there is no risk of collapse, and multiple shoulders can be supported simultaneously, so the shoulder can be reinforced and compacted efficiently. It can be performed well and the workability can be improved.

以下、図面について本発明の実施形態を詳細に説明する。図1は本発明の法肩用の型枠の実施形態を示す斜視図、図2は台形CSGダムの側面図で、本発明の型枠1はCSG工法において階段状に形成する台形CSGダム8の法肩の補強、締め固めを行う時に使用するものとして、断面方形で中空の鋼製の枠体1aを複数本、図示の例では2本を階段状に配置し、上段の枠体1aの前面側の側面と下段の枠体1aの上面とを適宜間隔をもってL字形の接続材2で接続し、階段状に連結した。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a perspective view showing an embodiment of a mold for shoulders of the present invention, FIG. 2 is a side view of a trapezoidal CSG dam, and the mold 1 of the present invention is a trapezoidal CSG dam 8 formed in a staircase shape in the CSG method. In order to reinforce and compact the shoulders of the above, a plurality of square steel frames 1a having a square cross section, two in the illustrated example, are arranged in a step shape, and the upper frame 1a The side surface on the front side and the upper surface of the lower frame 1a were connected with an L-shaped connecting member 2 at an appropriate interval, and connected in a staircase pattern.

各枠体1には、例えば上面の一方の端部に給水口3を、他方の端に空気抜き孔4を設け、また、前面側の側部に排水口5を設ける。   Each frame 1 is provided with, for example, a water supply port 3 at one end portion of the upper surface, an air vent hole 4 at the other end, and a drain port 5 at a side portion on the front side.

さらに、枠体1aの上面にフック形状の吊具6を適宜間隔で複数取り付けた。   Further, a plurality of hook-shaped suspensions 6 were attached to the upper surface of the frame 1a at appropriate intervals.

次にかかる型枠1を使用してCSG工法により原位置コンクリートを層状の台形状に積み重ねて台形CSGダム(堰、堤防、堤体)を構築する方法を説明する。原位置コンクリートの投入場所の周囲に本発明の型枠1を設置し、内部にCSGおよびコンクリート等を投入して層状に積み重ねていくが、前回打設したCSGおよびコンクリート等の層と今回打設したCSGおよびコンクリート等の層とのそれぞれの法肩に型枠1が階段状に設置される。この階段状に設置される型枠1を水平の直線方向にさらに接続材11で所要長連結する。   Next, a method for constructing a trapezoidal CSG dam (weir, levee, levee body) by stacking in-situ concrete into a layered trapezoid by the CSG method using such a mold 1 will be described. The formwork 1 of the present invention is installed around the place where the concrete is put in-situ, and CSG and concrete etc. are thrown into the inside and stacked in layers. The formwork 1 is installed in a staircase shape on each shoulder with the CSG and concrete layers. The mold 1 installed in a staircase shape is further connected to the horizontal linear direction by a connecting material 11 for a required length.

このとき、設置する型枠1のCSGおよびコンクリート等が打設される側の内側と、この内側から内方にのびる水平方向とにわたってL字型の金網・エキスパンドメタル等10を同時に布設する。   At this time, an L-shaped wire mesh / expanded metal 10 and the like are laid simultaneously over the inside of the form 1 to be placed on the side where CSG and concrete are placed and the horizontal direction extending from the inside to the inside.

この状態で各枠体1aが上下段の法肩に位置し、枠体1aの中空内部には給水口3から水が注入されて内部には水9が充填されている。給水量は現場の条件に対応させて決定するが、例えば、2段の枠体1aと水との合計重量で800Kg以上あれば、対応できる。   In this state, each frame 1a is positioned on the upper and lower shoulders, and water is injected into the hollow interior of the frame 1a from the water supply port 3 and filled with water 9. The amount of water supply is determined according to the conditions at the site. For example, if the total weight of the two-stage frame 1a and water is 800 kg or more, it can be handled.

なお、内部に水9を注入するときは、空気抜き孔4を開放することで、水9の注入はスムーズに行える。   In addition, when water 9 is injected into the inside, the water 9 can be smoothly injected by opening the air vent hole 4.

そして、今回打設した上層のCSGおよびコンクリート等の上面を大型の振動ローラ7などで締め固める。このとき、大きな転圧が上層のCSGおよびコンクリート等に加わるが、法肩は型枠1で保護されているから、法肩部が崩れるおそれはない。   Then, the upper surface of the upper layer of CSG and concrete placed this time is compacted with a large vibration roller 7 or the like. At this time, a large rolling pressure is applied to the upper CSG, concrete, etc., but since the shoulder is protected by the mold 1, there is no possibility that the shoulder will collapse.

上層のCSGおよびコンクリート等の締め固めが終了すれば、型枠1を吊具6を使用してクレーンなどで一段吊上げ、上段の枠体1aを上層のCSGおよびコンクリート等の上面に設置し、下段の枠体1aをそれまで上段の枠体1aのあった位置に設置する。   When the upper layer CSG and concrete are compacted, the formwork 1 is lifted one stage with a crane or the like using the lifting tool 6, and the upper frame 1a is installed on the upper surface of the upper layer CSG and concrete. The frame 1a is installed at the position where the upper frame 1a has existed.

この型枠1の上方への移動時には、枠体1aの内部の水を排水口5から排水して全体の重量を軽減して移動し易くする。また、型枠1の移動は上下の枠体1aが接続材2で結合されているから、結合された階段状のまま同時に移動できる。   When the mold 1 is moved upward, the water inside the frame 1a is drained from the drain port 5 to reduce the overall weight and facilitate the movement. In addition, since the upper and lower frame bodies 1a are coupled by the connecting material 2, the mold 1 can be moved simultaneously in the coupled stepped shape.

この状態で上段の枠体1aと上段の金網・エキスパンドメタル等10が上層のCSGおよびコンクリート等の層の上に突出するから、この内側に次の層のCSGおよびコンクリート等を打設し、その上を転圧し、締め固める。   In this state, the upper frame 1a and the upper metal mesh / expanded metal 10 protrude on the upper layer of CSG and concrete, so the next layer of CSG and concrete is placed inside this, Roll up and compact.

この上層のCSGおよびコンクリート等の層の締め固めの際、法肩はつねにCSGおよびコンクリート等の層の2段分が型枠1で保護されているから、確実に保護でき、階段形状が崩れることはない。   When compacting the upper layer of CSG and concrete, etc., the shoulder is always protected by the mold 1 for the two steps of the layer of CSG and concrete, so that the shape of the staircase can be reliably protected. There is no.

なお、前記実施形態ではCSGおよびコンクリート等の層の2段分について型枠1で保護したが、これに限定されるものではなく、3段分について型枠1で保護することも可能であり、3段分の方がより確実に法肩を保護でき、望ましい。   In the above embodiment, the two stages of layers such as CSG and concrete are protected by the mold 1, but the present invention is not limited to this, and the three stages can be protected by the mold 1. Three steps are preferable because they can protect the shoulder more reliably.

また、型枠1が外されたさらに下方のCSGおよびコンクリート等の層については、法肩の垂直壁面から各CSGおよびコンクリート等の層の底部にわたってL字型に金網・エキスパンドメタル等10が布設されているから、型枠1が外されてCSGおよびコンクリート等の層が露出しても表面の劣化や骨材の肌落ちが防げる。   Further, for the CSG and concrete layers below the formwork 1, a wire mesh / expanded metal 10 is laid in an L shape from the vertical wall of the shoulder to the bottom of each CSG and concrete layer. Therefore, even if the mold 1 is removed and the layers such as CSG and concrete are exposed, the deterioration of the surface and the skin of the aggregate can be prevented.

本発明の法肩用の型枠およびこれを使用する法肩の締め固め方法の実施形態を示す斜視図である。It is a perspective view which shows embodiment of the form for shoulders of a shoulder of this invention, and the method of compacting the shoulder which uses this. 台形CSGダムの側面図である。It is a side view of trapezoid CSG dam.

符号の説明Explanation of symbols

1 型枠 1a 枠体
2 接続材 3 給水口
4 空気抜き孔 5 排水口
6 吊具 7 振動ローラ
8 台形ダム 9 水
10 金網・エキスパンドメタル等 11 接続材
DESCRIPTION OF SYMBOLS 1 Formwork 1a Frame 2 Connection material 3 Water supply port 4 Air vent hole 5 Drainage port 6 Lifting tool 7 Vibration roller 8 Trapezoid dam 9 Water 10 Metal mesh, expanded metal, etc. 11 Connection material

Claims (5)

階段状に法肩を構築する工法において使用する法肩用の型枠であって、断面方形状の複数の枠体を階段状に連結し、前記枠体の中空内部に重量調整用の水を充填したことを特徴とする法肩用の型枠。   It is a mold for a shoulder used in a method for constructing a shoulder in a staircase, and a plurality of frames having a square cross section are connected in a staircase shape, and water for adjusting the weight is provided in the hollow inside of the frame. A shoulder-shoulder formwork characterized by filling. 前記枠体の上部に給水口と空気抜き孔を設け、側部に排水口を設けた請求項1記載の法肩用の型枠。   The mold for a shoulder according to claim 1, wherein a water supply port and an air vent hole are provided at an upper portion of the frame body, and a drainage port is provided at a side portion. 上下の枠体はL字型の接続材で上段の側面部と下段の上面部を連結する請求項1または請求項2に記載の法肩用の型枠。   The formwork for the shoulder according to claim 1 or 2, wherein the upper and lower frames are L-shaped connecting members that connect the upper side surface portion and the lower upper surface portion. 階段状に連結した枠体を一体化した状態で吊上げ可能な吊具を枠体に設けた請求項1から請求項3のいずれかに記載の法肩用の型枠。   The formwork for the shoulder according to any one of claims 1 to 3, wherein the frame body is provided with a lifting tool that can be lifted in an integrated state of the frame bodies connected in a stepped manner. 複数の断面方形状の枠体を階段状に連結した型枠を複数段の法肩の箇所に設置し、最上段の法肩を締め固めた後、階段状の型枠を1段ずつ上方へ盛りかえることを特徴とする法肩の締め固め方法。   Install a form that connects multiple frames with a square cross section in a staircase shape at multiple shoulders, tighten the top shoulder, and then step up the staircase one by one A method of compacting shoulders, characterized by refilling.
JP2006125622A 2006-04-28 2006-04-28 Form for shoulder Expired - Fee Related JP4537343B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006125622A JP4537343B2 (en) 2006-04-28 2006-04-28 Form for shoulder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006125622A JP4537343B2 (en) 2006-04-28 2006-04-28 Form for shoulder

Publications (2)

Publication Number Publication Date
JP2007297817A JP2007297817A (en) 2007-11-15
JP4537343B2 true JP4537343B2 (en) 2010-09-01

Family

ID=38767534

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006125622A Expired - Fee Related JP4537343B2 (en) 2006-04-28 2006-04-28 Form for shoulder

Country Status (1)

Country Link
JP (1) JP4537343B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6253479B2 (en) * 2014-03-27 2017-12-27 株式会社熊谷組 Method for constructing concrete structure and formwork used for the method
JP6921771B2 (en) * 2018-03-05 2021-08-18 鹿島建設株式会社 Lifting device and construction method of concrete structure using the lifting device
JP7361576B2 (en) * 2019-11-13 2023-10-16 鹿島建設株式会社 Formwork system and method for constructing concrete structures using this formwork system

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61134413A (en) * 1984-12-03 1986-06-21 Bridgestone Corp Checkdam
JPS6327563U (en) * 1986-08-01 1988-02-23
JPH05248086A (en) * 1992-03-04 1993-09-24 Onoda Cement Co Ltd Laying of lightweight concrete
JPH0790867A (en) * 1993-09-20 1995-04-04 Kyokado Eng Co Ltd Reinforcing earth structure
JPH0868041A (en) * 1994-08-26 1996-03-12 Hazama Gumi Ltd Bank construction method
JPH09158158A (en) * 1995-12-05 1997-06-17 Fujita Corp Filling type concrete dam and construction method thereof
JPH10266168A (en) * 1997-03-21 1998-10-06 Fujita Corp Method of construction of check dam
JP2001032241A (en) * 1999-07-19 2001-02-06 Kansai Electric Power Co Inc:The Execution method for concrete structure and concrete placing mold
JP2001192254A (en) * 1999-10-19 2001-07-17 Inbakkusu:Kk Concrete, concrete structure, method for execution of concrete structure, debris barrier and method for execution of debris dam
JP2002180434A (en) * 2000-12-15 2002-06-26 Hokuriku Regional Development Bureau Ministry Land Infrastructure & Transport Construction method for concrete structure and ground reinforcement
JP2004176314A (en) * 2002-11-25 2004-06-24 Nippon Steel Metal Prod Co Ltd Civil-engineered structure equipped with planting sections, and method of constructing the same
JP2004183281A (en) * 2002-12-02 2004-07-02 Hokuriku Regional Development Bureau Ministry Land Infrastructure & Transport Construction method for concrete structure, form block used in the method, and form block manufacturing method
JP2004225453A (en) * 2003-01-27 2004-08-12 Inbakkusu:Kk Construction method of civil engineering structure
JP2004257189A (en) * 2003-02-27 2004-09-16 Sekisui Plastics Co Ltd Lightweight banking structure with wall surface member of multiple structure

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61134413A (en) * 1984-12-03 1986-06-21 Bridgestone Corp Checkdam
JPS6327563U (en) * 1986-08-01 1988-02-23
JPH05248086A (en) * 1992-03-04 1993-09-24 Onoda Cement Co Ltd Laying of lightweight concrete
JPH0790867A (en) * 1993-09-20 1995-04-04 Kyokado Eng Co Ltd Reinforcing earth structure
JPH0868041A (en) * 1994-08-26 1996-03-12 Hazama Gumi Ltd Bank construction method
JPH09158158A (en) * 1995-12-05 1997-06-17 Fujita Corp Filling type concrete dam and construction method thereof
JPH10266168A (en) * 1997-03-21 1998-10-06 Fujita Corp Method of construction of check dam
JP2001032241A (en) * 1999-07-19 2001-02-06 Kansai Electric Power Co Inc:The Execution method for concrete structure and concrete placing mold
JP2001192254A (en) * 1999-10-19 2001-07-17 Inbakkusu:Kk Concrete, concrete structure, method for execution of concrete structure, debris barrier and method for execution of debris dam
JP2002180434A (en) * 2000-12-15 2002-06-26 Hokuriku Regional Development Bureau Ministry Land Infrastructure & Transport Construction method for concrete structure and ground reinforcement
JP2004176314A (en) * 2002-11-25 2004-06-24 Nippon Steel Metal Prod Co Ltd Civil-engineered structure equipped with planting sections, and method of constructing the same
JP2004183281A (en) * 2002-12-02 2004-07-02 Hokuriku Regional Development Bureau Ministry Land Infrastructure & Transport Construction method for concrete structure, form block used in the method, and form block manufacturing method
JP2004225453A (en) * 2003-01-27 2004-08-12 Inbakkusu:Kk Construction method of civil engineering structure
JP2004257189A (en) * 2003-02-27 2004-09-16 Sekisui Plastics Co Ltd Lightweight banking structure with wall surface member of multiple structure

Also Published As

Publication number Publication date
JP2007297817A (en) 2007-11-15

Similar Documents

Publication Publication Date Title
CN104060631A (en) Road well lid opening elevation dynamic control structure and construction method thereof
KR101044441B1 (en) Slab top-down method of underground construction
JP3010356B1 (en) How to build a tunnel
IL188996A (en) Water retention system
JP4537343B2 (en) Form for shoulder
CN108396761A (en) The non-fully pile foundation cushion cap and production method under precipitation state inside a kind of foundation pit
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN211898390U (en) Pouring template system for concrete cushion layer of river levee dam
JP2020513075A (en) Field-placed reinforcement top type pile foundation and its construction method
KR20090097538A (en) Curb element concrete placing apparatus and the method of construction thereof
CN107059531A (en) A kind of anti-settling pervious surface and its laying method
CN111074893A (en) Construction system and construction method of concrete cushion layer of river levee dam
CN115961647A (en) Basement roof post-cast strip advanced sealing structure, construction structure and construction method
CN206512546U (en) A kind of anti-settling pervious surface
CN211849445U (en) Construction system of river levee dam concrete bed course
JP6475554B2 (en) Construction method of shaft and construction method of underground storage tank
JP6669435B2 (en) Construction method of dam and dam
KR102221486B1 (en) Manhole height adjustment repair work method
JP2002242165A (en) Work method for exterior wall units, concrete structure and work method for this structure
KR100967947B1 (en) Slab construction method depending on sand for lpg tank foundation
JP6402056B2 (en) Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method
JP4170955B2 (en) Construction method of concrete structure using residual formwork and soil concrete
JP4155519B2 (en) Construction method of concrete frame with underdrain
CN218933172U (en) Drainage water-stopping structure in pit under basement bottom plate
JP7361576B2 (en) Formwork system and method for constructing concrete structures using this formwork system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20081225

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100514

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100615

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100617

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130625

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4537343

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160625

Year of fee payment: 6

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees