JPH084021A - Method of constructing cylindrical structure - Google Patents

Method of constructing cylindrical structure

Info

Publication number
JPH084021A
JPH084021A JP13595894A JP13595894A JPH084021A JP H084021 A JPH084021 A JP H084021A JP 13595894 A JP13595894 A JP 13595894A JP 13595894 A JP13595894 A JP 13595894A JP H084021 A JPH084021 A JP H084021A
Authority
JP
Japan
Prior art keywords
block
ground
blocks
precast
insertion hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13595894A
Other languages
Japanese (ja)
Inventor
Munehito Abe
宗人 阿部
Masahiro Nakai
将博 中井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PS Co Ltd
Original Assignee
PS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PS Co Ltd filed Critical PS Co Ltd
Priority to JP13595894A priority Critical patent/JPH084021A/en
Publication of JPH084021A publication Critical patent/JPH084021A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To construct an underground structure and a ground structure as a united pressedressed reinforced concrete(PRC) structure without providing a pier, etc., with a footing, using a precast block. CONSTITUTION:Cylindrical precast blocks 5 provided with reinforcement insertion holes and PC steel bar insertion holes are stacked in order on a base block 2, and those are coupled with one another by PC steel bars 7, and the blocks 5 are press-fit in ground. Next, the stacking of the blocks 6 on ground part is repeated to form a ground structure, and it is passed into the block and reinforcements 8 are inserted from above, and those are fixed by grouting, thus a cylindrical structure consisting of PRC structure is constructed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、PRC(Prestressed
Reinforced Concrete :プレストレスト鉄筋コンクリー
ト)構造の下部構造を構築する筒状構造物の構築方法に
関する。例えば橋脚とか構造物の基礎等のような下部構
造を構築する方法に関し、さらに詳しくは、筒状のプレ
キャストコンクリートブロック(以下プレキャストブロ
ックという)を用いてプレストレスト鉄筋コンクリート
(PRC)構造で地中基礎と地上構造を一体に施工する
構築方法に関する。
The present invention relates to PRC (Prestressed)
Reinforced Concrete: A method of constructing a tubular structure for constructing a substructure of a prestressed reinforced concrete structure. For example, regarding the method of constructing a substructure such as a bridge pier or the foundation of a structure, in more detail, a prestressed reinforced concrete (PRC) structure using a tubular precast concrete block (hereinafter referred to as a precast block) The present invention relates to a construction method for constructing a structure integrally.

【0002】[0002]

【従来の技術】橋梁の橋脚などは、基礎杭、基礎(フー
チング)等を施工し、その上に柱状躯体を場所打ちコン
クリートで構築したり、又はフーチング上にプレキャス
トブロックを積重したり、さらには、基礎杭部分をウエ
ル等の沈設によって施工しその上にフーチングを構築す
る等の技術によって施工されていた。
2. Description of the Related Art For bridge piers and the like, foundation piles, foundations (footings), etc. are constructed, columnar frames are constructed on them by cast-in-place concrete, or precast blocks are piled on the footings. Was constructed by the technique of constructing foundation piles by sinking wells and building footings on them.

【0003】プレキャストブロックを積重してこのよう
な構造物を構築する場合、ブロック1個毎にブロック内
に埋設してある鉄筋を継手を用いて接合しながら積重し
ていたため、ブロック製作精度の維持、接合手間等に問
題があった。また、接合面に継手があるので、継手の剪
断に対して、剪断キー等を設ける必要がある。これに対
して、プレキャストブロックにあらかじめ鉄筋を埋設せ
ず、鉄筋を後挿入する技術は「土木施工8巻8号(東北
本線第8場淵川橋りょう工事におけるRCプレキャスト
ブロック式橋脚の施工)」に報告されている。この技術
では、鉄筋接続位置を特別なブロックを用いて集中させ
ていた。
In the case of constructing such a structure by stacking precast blocks, since the reinforcing bars embedded in each block are stacked by using joints, the block manufacturing accuracy is improved. There was a problem in maintenance, joining work, etc. Further, since there is a joint on the joint surface, it is necessary to provide a shear key or the like for shearing the joint. On the other hand, the technology to insert the reinforcing bar into the precast block without pre-embedding the reinforcing bar in advance is "Civil engineering construction Vol. It has been reported. In this technique, the connecting position of the reinforcing bar is concentrated by using a special block.

【0004】一方、プレキャストブロックを用いてPC
(プレストレストコンクリート)構造の下部構造を構築
する場合は、接合面にフルプレストレスが掛かり、プレ
キャストブロックの接合面に凹凸があると、凸部に大き
な局部応力が生じ破損する問題があるので、接合面は高
い平坦精度が要求され、例えば鏡面仕上げを行って施工
するか、又はマッチキャストのプレキャストブロックを
製作しなければならない。
On the other hand, a PC using a precast block
When constructing a substructure of a (prestressed concrete) structure, if the joint surface is subjected to full prestress and the joint surface of the precast block is uneven, there is a problem that a large local stress is generated in the convex portion and the joint surface is damaged. Requires a high level of flatness and must be applied, for example, with a mirror finish or a matchcast precast block must be manufactured.

【0005】[0005]

【発明が解決しようとする課題】本発明は、プレキャス
トブロックを用いて、フーチングを別に設けることな
く、地下構造物と地上構造物とを一体のプレストレスト
鉄筋コンクリート(PRC)構造とし短工期で橋脚等を
構築する構築方法を提供しようとするものである。本発
明のさらに具体的な目的は次のとおりである。
SUMMARY OF THE INVENTION According to the present invention, a precast block is used to form an integrated prestressed reinforced concrete (PRC) structure for an underground structure and an aboveground structure without separately providing footing, and a pier or the like can be constructed in a short period of time. It is intended to provide a building method for building. The more specific objects of the present invention are as follows.

【0006】(1)地下の基礎部分と地上の柱状物部分
との工程を分断することなく連続的に施工する。 (2)ブロック接合面の精度を鏡面仕上等の高精度を要
しない構造とする。 (3)鉄筋接合ブロック等を設けることなく、鉄筋接続
位置が集中するのを排除する。
(1) Construction is continuously performed without dividing the process of the underground foundation portion and the above-mentioned columnar portion portion. (2) The structure of the block joint surface does not require high precision such as mirror finishing. (3) Concentration of reinforcing bar connection positions is eliminated without providing a reinforcing bar joint block or the like.

【0007】[0007]

【課題を解決するための手段】本発明は、上記目的を達
成するため、次の技術手段を構成とする。すなわち、基
準ブロックに地中圧入刃口を取付け、鉄筋挿通孔及びP
C鋼棒挿通孔を設けた筒状プレキャストブロックを前記
基準ブロック上に順次積重してPC鋼棒で順次連結し、
ブロック内の排土と筒状プレキャストブロックの積重と
を繰り返しながらブロック積重体を地中に圧入し、前記
刃口が支持基盤に到達するまで地中に沈下し、ついで、
筒状プレキャストブロックの積重を繰り返して地上構造
体を形成し、積重したブロックの鉄筋挿通孔に通し鉄筋
を上方から挿通してグラウチング固定し、PRC構造体
を構築することを特徴とする筒状構造物の構築方法であ
る。この場合、前記通し鉄筋は継手位置を互いに異なる
レベルに設けることが好ましく、また、前記鉄筋を挿通
してグラウチング固定するとき、グラウト液を鉄筋挿通
孔に注入した後、鉄筋をグラウト液中に沈漬することと
すれば好適である。
In order to achieve the above object, the present invention comprises the following technical means. That is, the underground press-fitting blade opening is attached to the reference block, and the reinforcing bar insertion hole and P
Cylindrical precast blocks provided with C steel rod insertion holes are sequentially stacked on the reference block and sequentially connected with PC steel rods,
Pressing the block stack into the ground while repeating the earth removal in the block and the stacking of the tubular precast block, sinking into the ground until the blade edge reaches the support base, then,
A cylinder characterized by repeatedly stacking cylindrical precast blocks to form a ground structure, and inserting a reinforcing bar from above through a reinforcing bar insertion hole of the stacked blocks to fix a grouting structure to construct a PRC structure. It is a method of constructing a structure. In this case, it is preferable that the through-bars are provided at joint positions at different levels from each other.In addition, when the grouting liquid is inserted into the grouting liquid after the grouting liquid is injected into the grouting liquid when the grouting liquid is inserted and fixed by grouting. Pickling is preferable.

【0008】[0008]

【作用】本発明は、上記構成により次の作用を生じる。 (a)基礎部分と地上の柱状部を連続・一体施工するこ
とができる。 (b)PRC構造とすることによりプレキャストブロッ
クに過度のプレストレストを与えないようにする。従っ
て、プレキャストブロックは接合面の高い平坦精度を必
要とせず、鏡面仕上処理するとか、マッチキャストとす
ることを要せず、プレキャストブロックの製造工程を簡
易化することができる。
The present invention has the following effects due to the above configuration. (A) It is possible to continuously and integrally construct the foundation portion and the columnar portion on the ground. (B) The PRC structure prevents the precast block from being excessively prestressed. Therefore, the precast block does not require high flatness of the joint surface, and does not require mirror finishing treatment or match casting, and the manufacturing process of the precast block can be simplified.

【0009】(c)全てのブロック積重した後に、主構
造鉄筋を後挿入とすることにより、特別な接続ブロック
を用いる必要がない。予め余裕のある径の鉄筋挿通孔を
穿設しておくことにより、容易に挿入することができ
る。さらに、プレキャストブロック同士の接合面にはカ
ップラがなく、鉄筋自体が横断しているため、RC構造
のプレキャストブロックのように、プレキャストブロッ
クの接合面に剪断キーを設けるなどの対策が不要であ
る。
(C) Since all the blocks are stacked and the main structural rebar is post-inserted, it is not necessary to use a special connection block. It can be easily inserted by previously forming a reinforcing bar insertion hole having a sufficient diameter. Furthermore, since there is no coupler on the joint surface between the precast blocks and the rebar itself traverses, it is not necessary to take measures such as providing a shear key on the joint surface of the precast blocks, unlike the RC precast block.

【0010】(d)挿入鉄筋とブロックとの付着はグラ
ウトで行う。 (e)グラウト注入は、鉄筋挿入前に行い、グラウト液
中に鉄筋を沈設することによって、挿入孔と鉄筋の間に
空隙が生じない。この場合、予注入グラウトの液量は挿
入孔全容積と挿入鉄筋体積から決定する。
(D) Adhesion between the inserted rebar and the block is carried out with a grout. (E) The grout injection is performed before the rebar is inserted, and the rebar is submerged in the grout solution, so that no void is generated between the insertion hole and the rebar. In this case, the liquid volume of the pre-injection grout is determined from the total volume of the insertion hole and the volume of the inserted rebar.

【0011】[0011]

【実施例】図1に実施例の橋脚を示した。地面2より下
方の地中には、圧入刃口4を取付けた基準ブロック3の
上方に筒状プレキャストブロック5が積重されており、
さらに地上部に同じ筒状プレキャストブロック6が積重
されており、これらのブロック5、6はPC鋼棒7で連
結されていると共に、鉄筋8が挿入されて一体化し、P
RC構造物を形成している。その頂部には、上部構造
9、例えば橋桁が施工される。この橋脚を構成する筒状
プレキャストブロックの平面図を図2に示した。このブ
ロック5、6には、PC鋼棒挿通孔11と鉄筋挿通孔1
2が設けられている。図2は矩形断面のブロックを示し
ているが、本発明では断面形状は任意である。円形、台
形、多角形、その他いかなる断面のブロックでも同様に
使用可能である。
EXAMPLE FIG. 1 shows a pier of an example. In the ground below the ground 2, a cylindrical precast block 5 is stacked above the reference block 3 to which the press-fitting blade mouth 4 is attached,
Further, the same tubular precast block 6 is stacked on the ground part, and these blocks 5 and 6 are connected by a PC steel rod 7, and a reinforcing bar 8 is inserted and integrated,
It forms an RC structure. A superstructure 9, for example a bridge girder, is installed on its top. A plan view of the tubular precast block that constitutes this pier is shown in FIG. In the blocks 5 and 6, the PC steel rod insertion hole 11 and the reinforcing bar insertion hole 1
2 are provided. Although FIG. 2 shows a block having a rectangular cross section, the cross sectional shape is arbitrary in the present invention. A circular, trapezoidal, polygonal, or any other cross-section block can be used as well.

【0012】実施例の橋脚の仕様は次のとおりである。 地中部長さ:25m 地上部長さ:32m 断面寸法 :6m×4m×部材厚0.6m ブロック高さ寸法:2m 鉄筋 :φ35mm×148本(挿入孔φ70m
m) 組立PC鋼棒:φ32mm×24本(挿入孔φ70m
m) ブロック重量:約50t 実施例の橋脚を本発明方法により施工した。施工手順を
図3〜7を参照しながら説明する。
The specifications of the pier of the embodiment are as follows. Underground length: 25 m Aboveground length: 32 m Cross-sectional dimension: 6 m x 4 m x Member thickness 0.6 m Block height dimension: 2 m Reinforcing bar: φ35 mm x 148 (insertion hole φ70 m
m) Assembled PC steel rod: φ32 mm x 24 (insertion hole φ70 m
m) Block weight: about 50 tons The pier of the example was constructed by the method of the present invention. The construction procedure will be described with reference to FIGS.

【0013】(1)施工位置の地面2を測量整地し、圧
入反力をとるアースアンカー21を施工する。 (2)ブロック圧入位置に、鋼製圧入刃口4を据え付け
る。 (3)鋼製刃口4に、基準ブロック3を載せて、PC鋼
棒7を挿通し、鋼製刃口4を緊結固定する。
(1) The ground 2 at the construction position is surveyed and leveled, and an earth anchor 21 for producing a press-fit reaction force is constructed. (2) Install the steel press-fitting blade mouth 4 at the block press-fitting position. (3) Place the reference block 3 on the steel blade 4 and insert the PC steel rod 7 to fix the steel blade 4 tightly.

【0014】(4)筒状プレキャストブロック5の接合
面に樹脂系接着材を塗布し、ブロックをクレーン31で
吊り下げ、組立PC鋼棒7をガイドにして積み重ね、筒
状プレキャストブロックを4段積み重ねたらPC鋼棒7
を緊張しグラウトする。 (5)ブロック上部に載荷梁24を載せ、アースアンカ
ー21に連結した反力梁23からジャッキ25によりブ
ロックを地中に沈下させる。レベル、トランシットで水
平、垂直方向を確認しながら、慎重にアースアンカーに
ジャッキで載荷する。同時にバケットハンマーなどの掘
削機32でブロック内部の土砂を掘削排出しながら地中
に沈入させる。
(4) A resin-based adhesive is applied to the joint surface of the tubular precast block 5, the blocks are hung by a crane 31, and the assembled PC steel rods 7 are stacked as a guide to stack the tubular precast blocks in four stages. Cod PC steel rod 7
And grout. (5) The loading beam 24 is placed on the upper part of the block, and the block is sunk into the ground by the jack 25 from the reaction beam 23 connected to the earth anchor 21. Carefully jack on the ground anchor while checking the horizontal and vertical directions with the level and transit. At the same time, the excavator 32 such as a bucket hammer excavates and discharges the earth and sand inside the block to settle into the ground.

【0015】(6)筒状プレキャストブロック4段分の
沈設が完了したら、反力梁23、ジャッキ25、載荷梁
24を撤去し、次のブロックを組立てるためのPC鋼棒
7を、下部ブロック緊張端PC鋼棒7の頭部にカップラ
を用いて接続する。 (7)以後、(4)〜(6)の工程を2回繰り返し、地
中部分25mを構築する。
(6) When the four stages of the cylindrical precast block are completely sunk, the reaction beam 23, the jack 25, and the loading beam 24 are removed, and the PC steel rod 7 for assembling the next block is tightened in the lower block. The end PC steel rod 7 is connected to the head using a coupler. (7) After that, the steps (4) to (6) are repeated twice to construct the underground portion 25m.

【0016】(8)地中部分が完了したら、ブロック内
部に土砂を投入して埋め戻す。 (9)地上部を構築するブロックを組み立てるPC鋼棒
7を接続する。 (10)ブロック接合面に樹脂系接着材を塗布し、架設
作業足場35を取付けたブロックをクレーン31で吊り
下げ、組み立てPC鋼棒7をガイドにして積み重ね、筒
状プレキャストブロックを4段積み重ねたらPC鋼棒7
を緊張しグラウトする。
(8) When the underground portion is completed, earth and sand are put into the block to backfill it. (9) Connect the PC steel rods 7 that assemble the blocks that construct the above-ground portion. (10) Apply a resin adhesive to the block joint surface, hang the block with the erection work scaffold 35 attached by the crane 31, stack using the assembled PC steel rods 7 as guides, and stack the tubular precast blocks in four stages PC steel rod 7
And grout.

【0017】(11)(10)の工程を3回繰り返し地
上柱状部32mを構築する。 (12)最上部ブロック周囲に作業足場を設置する。 (13)鉄筋挿通孔に、超遅延凝固性グラウト液を注入
する。グラウト液は挿通孔容積、鉄筋体積を計算して注
入する。鉄筋挿入完了時に上部から若干あふれ出るよう
に量を決める。
The steps (11) and (10) are repeated three times to construct the ground columnar section 32m. (12) Install work scaffolds around the top block. (13) Inject a super delayed coagulable grout solution into the reinforcing bar insertion hole. The grout solution is injected by calculating the volume of the insertion hole and the volume of the reinforcing bar. Determine the amount so that it will overflow slightly from the top when the rebar insertion is completed.

【0018】(14)鉄筋を地上で櫛状に組立て、吊具
33を用いてクレーンで吊り下げグラウト液が注入され
ている挿入孔中に沈入させる。鉄筋の接続位置は、異な
る高さとなるようにする。このとき、全長にわたる鉄筋
を一時に挿通できない場合は、構造物頂部に仮受け治具
を設置し、分割挿入が可能なようにする。この場合も接
続位置が集中しないように計画する。
(14) Reinforcing bars are assembled on the ground in a comb shape, and are suspended by a crane using a suspending tool 33 to be sunk into an insertion hole into which grout liquid is injected. Reinforcing bars should be connected at different heights. At this time, if the reinforcing bars over the entire length cannot be inserted at one time, a temporary receiving jig is installed on the top of the structure to enable the split insertion. Also in this case, make a plan so that connection positions are not concentrated.

【0019】(15)グラウトの強度発現により、ブロ
ック本体と鉄筋が付着し一体化する。 実施例では、途中で作業を分断することなく、地中及び
地上の部分が一体化した筒状構造体を短工期で施工する
ことができた。また、プレキャストブロックの接合面を
鏡面仕上げする必要がなく、プレキャストブロックの製
造工程も簡単になり、プレキャストブロックの継目に弱
点がなく、優れた筒状構造物の構築を安全、安価、短工
期に施工することができる。
(15) Due to the strength development of the grout, the block body and the reinforcing bar are attached and integrated. In the example, the tubular structure in which the underground and above-ground portions were integrated could be constructed in a short period of time without dividing the work in the middle. In addition, the joining surface of the precast block does not need to be mirror-finished, the manufacturing process of the precast block is simple, there are no weak points in the joint of the precast block, and the construction of an excellent tubular structure is safe, inexpensive, and in a short construction period. Can be installed.

【0020】[0020]

【発明の効果】本発明の筒状構造物の構築方法は、主構
造鉄筋を後挿入としたこと及びPRC構造としたことに
よって、プレキャストブロックの接合面の製作精度を格
別のものとする必要がなく、マッチキャストや鏡面仕上
げ等を必要としないのでプレキャストブロックの製作順
序、製造精度も自由となる。また、地中基礎部と地上柱
状部とが連続一体となり、施工工程の分断もなく、施工
能率が向上し、またプレキャストブロックをあらかじめ
製作しておくことができるので工期に自由度が増し、無
駄なく効率的な工期設定が可能となり、高品質の筒状構
造物を安全、高能率、短工期に施工することができると
いう優れた効果を奏する。
According to the method for constructing the tubular structure of the present invention, the manufacturing accuracy of the joint surface of the precast block needs to be exceptional because the main structural rebar is post-inserted and the PRC structure is adopted. Since there is no need for match casting or mirror finishing, the precast block can be manufactured in any order and with no precision. In addition, the underground foundation part and the above-ground columnar part are continuously integrated, there is no division of the construction process, the construction efficiency is improved, and the precast block can be manufactured in advance, which increases the degree of freedom in the construction period and wastes. Therefore, it is possible to efficiently set the construction period, and it is possible to construct a high quality cylindrical structure safely, efficiently, and in a short construction period.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例の筒状構造物を示す説明図であ
る。
FIG. 1 is an explanatory view showing a tubular structure according to an embodiment of the present invention.

【図2】筒状プレキャストブロックの平面図である。FIG. 2 is a plan view of a tubular precast block.

【図3】実施例の構築工程の工程図である。FIG. 3 is a process drawing of a construction process of an example.

【図4】実施例の構築工程の工程図である。FIG. 4 is a process diagram of a construction process of an example.

【図5】実施例の構築工程の工程図である。FIG. 5 is a process drawing of the construction process of the example.

【図6】実施例の構築工程の工程図である。FIG. 6 is a process drawing of the construction process of the example.

【図7】実施例の構築工程の工程図である。FIG. 7 is a process drawing of the construction process of the example.

【符号の説明】[Explanation of symbols]

1 筒状構造物 2 地面 3 基準ブロック 4 刃口 5、6 プレキャストブロック 7 PC鋼棒 8 鉄筋 9 上部構造 11 PC鋼棒挿通孔 12 鉄筋挿通孔 21 アースアンカー 23 反力梁 24 載荷梁 25 ジャッキ 31 クレーン 32 掘削機 33 吊具 34 カップラ 35 足場 1 Tubular Structure 2 Ground 3 Reference Block 4 Blade 5, 6 Precast Block 7 PC Steel Bar 8 Reinforcing Bar 9 Upper Structure 11 PC Steel Bar Through Hole 12 Reinforcing Bar Through Hole 21 Earth Anchor 23 Reaction Beam 24 Loading Beam 25 Jack 31 Crane 32 Excavator 33 Lifting tool 34 Coupler 35 Scaffold

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 基準ブロックに地中圧入刃口を取付け、
鉄筋挿通孔及びPC鋼棒挿通孔を設けた筒状プレキャス
トブロックを前記基準ブロック上に順次積重して、PC
鋼棒で順次連結し、ブロック内の排土と筒状プレキャス
トブロックの積重とを繰り返しながらブロック積重体を
地中に圧入し、前記刃口が支持基盤に到達するまで地中
に沈下し、ついで、筒状プレキャストブロックの積重を
繰り返して地上構造体を形成し、積重したブロックの鉄
筋挿通孔に通し鉄筋を上方から挿通してグラウチング固
定し、PRC構造体を構築することを特徴とする筒状構
造物の構築方法。
1. An underground press-fitting blade opening is attached to a reference block,
A cylindrical precast block provided with a reinforcing bar insertion hole and a PC steel rod insertion hole is sequentially stacked on the reference block to form a PC.
Sequentially connected with steel bars, press the block stack into the ground while repeating the soil discharge in the block and the stacking of the cylindrical precast block, sinking into the ground until the blade edge reaches the support base, Then, the stacking of the cylindrical precast blocks is repeated to form a ground structure, and the reinforcing bars are inserted through the reinforcing bar insertion holes of the stacked blocks from above and fixed by grouting to construct a PRC structure. A method for constructing a tubular structure.
【請求項2】 前記通し鉄筋は継手位置を互いに異なる
レベルに設けることを特徴とする請求項1記載の筒状構
造物の構築方法。
2. The method for constructing a tubular structure according to claim 1, wherein the through bars are provided at joint positions at different levels.
【請求項3】 前記鉄筋を挿通してグラウチング固定す
るとき、グラウト液を鉄筋挿通孔に注入した後、鉄筋を
グラウト液中に沈漬することを特徴とする請求項1又は
2記載の筒状構造物の構築方法。
3. The tubular shape according to claim 1 or 2, wherein, when the rebar is inserted and fixed by grouting, the grout solution is injected into the rebar insertion hole, and then the rebar is immersed in the grout solution. How to build a structure.
JP13595894A 1994-06-17 1994-06-17 Method of constructing cylindrical structure Pending JPH084021A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13595894A JPH084021A (en) 1994-06-17 1994-06-17 Method of constructing cylindrical structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13595894A JPH084021A (en) 1994-06-17 1994-06-17 Method of constructing cylindrical structure

Publications (1)

Publication Number Publication Date
JPH084021A true JPH084021A (en) 1996-01-09

Family

ID=15163825

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13595894A Pending JPH084021A (en) 1994-06-17 1994-06-17 Method of constructing cylindrical structure

Country Status (1)

Country Link
JP (1) JPH084021A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007070894A (en) * 2005-09-07 2007-03-22 Ps Mitsubishi Construction Co Ltd Method of lifting down precast concrete skeleton joint body into ground, and jig for use in the method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6035191A (en) * 1983-08-05 1985-02-22 Kureha Chem Ind Co Ltd Pump
JPH0474489A (en) * 1990-07-17 1992-03-09 Nec Corp Printed circuit board

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6035191A (en) * 1983-08-05 1985-02-22 Kureha Chem Ind Co Ltd Pump
JPH0474489A (en) * 1990-07-17 1992-03-09 Nec Corp Printed circuit board

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007070894A (en) * 2005-09-07 2007-03-22 Ps Mitsubishi Construction Co Ltd Method of lifting down precast concrete skeleton joint body into ground, and jig for use in the method

Similar Documents

Publication Publication Date Title
CN104018518B (en) The method of prefabricated diaphragm wall and construction outer wall of basement and floor
WO2004033843A2 (en) Subterranean structures and methods for constructing subterranean structures
JPH1060817A (en) Constructing method of annexing structure
CN204000925U (en) Prefabricated diaphragm wall
JPH08296243A (en) Construction method for underground structure by precast concrete central pillar
JP2000352296A (en) Method o constructing passage just under underground structure
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR102482690B1 (en) Bridge foundation construction method using formwork integrated PC panels
JP2831934B2 (en) How to build substructure
JPH084021A (en) Method of constructing cylindrical structure
JP2021188354A (en) Precast prestressed concrete foundation structure and its construction method
KR960016755B1 (en) Working method and working apparatus of underground structure
JPH0525821A (en) Continuous underground wall and construction method thereof
JPS63280153A (en) Underground inverted lining method
CN217998366U (en) Permanent and temporary combined basement structure
CN115354739B (en) Permanent-face combined basement structure and construction method thereof
CN112900235B (en) Assembled support trestle and filling core bar concrete bracing beam
JPH04185816A (en) Construction of beam in underground wall
JP4159148B2 (en) Construction method of shaft
JP2838019B2 (en) Caisson blade framing method
JP2615344B2 (en) Foundation using expanded polystyrene and its construction method
JPH10131300A (en) Execution method for building by preceding erection of steel frame
JP3061934B2 (en) Retaining wall construction method
CN115717368A (en) Abutment deviation rectifying and reinforcing structure and construction method thereof
JPS6217233A (en) Foundation base column

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19980804