JPH08134845A - Erection method of bridge - Google Patents

Erection method of bridge

Info

Publication number
JPH08134845A
JPH08134845A JP6277681A JP27768194A JPH08134845A JP H08134845 A JPH08134845 A JP H08134845A JP 6277681 A JP6277681 A JP 6277681A JP 27768194 A JP27768194 A JP 27768194A JP H08134845 A JPH08134845 A JP H08134845A
Authority
JP
Japan
Prior art keywords
hanger
erection
girder
bridge
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6277681A
Other languages
Japanese (ja)
Other versions
JP2768282B2 (en
Inventor
Matsuo Tsuruoka
松生 鶴岡
Nobuhide Wada
信秀 和田
Seiji Tokuyama
清治 徳山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP6277681A priority Critical patent/JP2768282B2/en
Publication of JPH08134845A publication Critical patent/JPH08134845A/en
Application granted granted Critical
Publication of JP2768282B2 publication Critical patent/JP2768282B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: To improve workability and profitability by devising a hanging type by a hanger regarding the erection method of a bridge by a method of hanger type span-by-span precast block construction. CONSTITUTION: Blocks 3 transported on a bridge girder 2 are hung up by a crab trolley 16, and transported up to a place determined by turning the direction at 90 deg. and suspended successively by a B hanger 26 and an A hanger 25 hung down from an erection girder 11 again. The blocks 3 within a range required for the turn of the direction are suspended temporarily from the A hanger 25 in height lower than specified installation height once. Regarding the A hanger, the intervals of hanging materials are made larger than width in the bridge axial direction of the blocks 3, and the directions of the blocks 3 can be rotated in spaces among the hanging materials. The blocks 3 in number required in a single span are hung down, and the block 3 suspended from the A hanger 25 is pulled up to specified height and positioned. A working scaffold 23 is used from the front column head section side, and an adhesive is applied, drawn near and joined.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本願発明は、工場またはヤードで
製作された橋桁ブロックを1径間分ごと架設ガーダーに
吊り下げて架設するハンガー方式のスパンバイスパンプ
レキャストブロック工法による橋梁の架設方法の改良に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is an improvement of a bridge erection method by a hanger type span-by-span precast block construction method in which bridge girder blocks manufactured in a factory or a yard are hung and erected on erection girders for each span. It is about.

【0002】[0002]

【従来の技術】プレキャストブロック工法は、工場ある
いは製作ヤードで橋軸方向または橋軸直角方向に分割し
て構造物を製作し、架設現場に搬入し、プレストレスを
導入して一体構造物に作り上げる工法であり、橋梁の施
工等に用いられている。
2. Description of the Related Art In the precast block method, a structure is manufactured by dividing it into a bridge axis direction or a direction perpendicular to the bridge axis at a factory or a manufacturing yard, and then the structure is carried into the erection site, and prestress is introduced to form an integrated structure. It is a construction method and is used for construction of bridges.

【0003】プレキャストブロック工法を橋梁の架設に
適用した場合の利点としては、以下のようなものが挙げ
られる。
The following are some of the advantages of applying the precast block construction method to bridge construction.

【0004】 プレキャストブロックを下部工の施工
中に製作し、ストックできるので、製作工程と架設工程
を別々に設定でき、工期が大幅に短縮できる。
Since the precast block can be manufactured and stocked during the construction of the substructure, the manufacturing process and the erection process can be set separately, and the construction period can be significantly shortened.

【0005】 プレキャストブロックの製作は、工場
または製作ヤードでの繰り返し作業となり、品質の安定
した構造物を造ることができる。また、機械化施工を行
うことで合理化、省力化が可能である。
The production of the precast block is a repetitive operation in a factory or a production yard, and a structure having stable quality can be produced. Moreover, rationalization and labor saving can be achieved by performing mechanized construction.

【0006】 ストックヤードでブロックを保管する
ことにより、架設後の乾燥収縮、クリープによる変形が
小さくなる。
By storing the blocks in the stockyard, drying shrinkage after installation and deformation due to creep are reduced.

【0007】上述の点からして、プレキャストブロック
工法は、PC橋工事の分野で最も急速施工、省力化施工
が期待できる工法であるが、そのためにはブロックの製
作では型枠設備等の自動化、ブロックの架設では架設機
械の大型化を前提とし、大規模な橋梁工事において有利
な工法となる。
From the above point of view, the precast block construction method is the construction method which is expected to be the most rapid construction and labor-saving construction in the field of PC bridge construction. The block erection is an advantageous construction method for large-scale bridge construction, assuming that the erection machine is large.

【0008】なお、プレストレスの導入に関し、諸外国
では外ケーブルを使用する例が多く、それにより施工
性、経済性の向上が図られている。
With respect to the introduction of prestress, there are many cases in which foreign cables are used in other countries, which improves workability and economy.

【0009】また、プレキャストブロック工法の代表的
な架設方法としては、工場またはヤードで製作された1
径間分のブロックを架設ガーダー上に運搬して、所定の
位置決め後、接合し、プレストレスを与えながら1径間
ずつ架設して行くスパンバイスパン工法と、橋脚を中心
にバランスを取り、左右交互または同時にブロックを接
合してプレストレスを与えながら張り出して行く片持ち
架設工法があり、前者は支間40〜60m、後者は支間
60〜100m程度のPC桁橋に適している。
Further, as a typical erection method of the precast block construction method, it is manufactured in a factory or a yard.
The span-by-span construction method, in which blocks for spans are transported onto the erection girder, and after predetermined positioning, they are joined and erected one span at a time while prestressing, the balance is centered around the pier, There is a cantilever erection method in which blocks are alternately or simultaneously joined and overhanged while prestressing. The former is suitable for a PC girder bridge with a span of 40 to 60 m and the latter with a span of 60 to 100 m.

【0010】[0010]

【発明が解決しようとする課題】本願発明が対象とする
スパンバイスパンプレキャストブロック工法では、架設
ガーダーによるブロックの支持方法に関し、ブロックを
架設ガーダー上に載せて架設するサポート方式と、ブロ
ックを架設ガーダーに吊り下げて架設するハンガー方式
があり、前者は支点上の主桁(柱頭部)をプレキャスト
ブロックとする場合、後者は支点上の主桁を場所打ちす
る場合に適している。
The span-by-span precast block method, which is the subject of the present invention, relates to a method of supporting a block by a erection girder, including a support system for mounting the block on the erection girder and the erection girder. There is a hanger system that suspends and erects, the former is suitable when the main girder on the fulcrum (column head) is the precast block, and the latter is suitable for casting the main girder on the fulcrum in place.

【0011】スパンバイスパンプレキャストブロック工
法では、橋桁ブロックは、架設完了した橋桁上をトレー
ラーまたは自動搬送車などで、まず橋桁上の所定位置ま
で運搬する。
In the span-by-span precast block construction method, the bridge girder block is first transported to a predetermined position on the bridge girder by a trailer or an automatic carrier on the bridge girder that has been erected.

【0012】ハンガー方式の場合、そこから架設ガーダ
ー上を走行するクラブトロリー等の吊り装置で吊り上
げ、架設ガーダー上を架設位置まで橋軸方向に走行させ
る。
In the case of the hanger system, a hanging device such as a club trolley that runs on the erection girder is used to lift the hanger system, and the garment is moved on the erection girder to the installation position in the bridge axis direction.

【0013】この場合、橋軸方向に分割した形などに製
作されたプレキャストブロックは、横向きの状態で橋桁
上を搬送され、そのままクラブトロリーで吊り上げ、架
設ガーダーの支持脚としてのリアーレグを通過した位置
で90°回転させて、各ブロックの架設位置まで水平に
運搬され、吊り材を介して架設ガーダーから吊り下げら
れたハンガーに吊り替えられる。このとき、吊った状態
の多数のブロックを同時に水平移動させることは困難で
あるため、先方の橋脚側から順次手前にブロックを架設
して行くことになる。
In this case, the precast block manufactured in the form of being divided in the bridge axis direction is conveyed laterally on the bridge girder, hoisted by the club trolley as it is, and passed through the rear leg as the supporting leg of the erection girder. The product is rotated 90 ° to be transported horizontally to the erected position of each block, and is suspended from the erected girder and suspended by a hanger. At this time, since it is difficult to horizontally move a large number of suspended blocks at the same time, the blocks are sequentially erected from the pier side ahead.

【0014】その場合、先方からある程度までの区間に
ついては、吊り装置で支持したまま手前側の空間を利用
して90度方向転回させることができるが、手前側のブ
ロックについては、既に架設位置に到達しているブロッ
クやハンガー、吊り材などが障害となり、方向転回が不
能であるか、あるいは困難になる。
In this case, the section up to a certain extent can be turned by 90 degrees using the space on the front side while being supported by the suspension device, but the block on the front side is already in the erected position. Blocks, hangers, hangings, etc. that have reached reach obstacles, making it impossible or difficult to turn.

【0015】これに対処するため、一部のブロックを地
上から吊り上げるなどの手段も考えられるが、そのため
には、橋下のスペースが利用できることが前提であり、
また大型の機械設備、その他を要することになり、不経
済である。
In order to deal with this, it is conceivable to suspend some blocks from the ground, but for that purpose, it is premised that the space under the bridge can be used.
In addition, it is uneconomical because it requires large machinery and equipment.

【0016】本願発明は、このようなスパンバイスパン
プレキャストブロック工法による橋梁の架設方法におい
て、ハンガーによる吊り方式を工夫することにより、施
工性、経済性の向上を図ったものである。
The present invention is intended to improve the workability and the economical efficiency by devising the suspension method by the hanger in the bridge erection method by such a span-by-span precast block method.

【0017】[0017]

【課題を解決するための手段】本願発明は、工場または
ヤードで製作された1径間分の橋桁ブロックを、既設の
橋桁上より架設ガーダーに吊り下げて1径間ずつ架設す
るハンガー方式のスパンバイスパンプレキャストブロッ
ク工法による橋梁の架設方法において、橋軸方向に対し
90度回転した状態にあるブロックを、架設ガーダーに
沿って走行する吊り装置で順次吊り上げ、所定の転回位
置で90度方向転回させて、それぞれのブロックの架設
位置まで移動させ、架設ガーダーに吊り材を介して支持
されたハンガーに吊り替えるにあたり、少なくともブロ
ックの転回位置にあたる区間については、ハンガーを支
持する吊り材の間隔をブロックの橋軸方向の幅以上と
し、ブロックを吊り材間の空間で方向転回させて、各ブ
ロックの架設位置でハンガーに吊り替えるようにしたも
のである。
DISCLOSURE OF THE INVENTION The present invention is a span of a hanger type in which a bridge girder block for one span manufactured in a factory or a yard is suspended from an existing bridge girder on a erection girder and erected for each span. In the bridge erection method by the bi-span precast block method, the blocks in the state of being rotated 90 degrees with respect to the bridge axis direction are sequentially hung by a hoisting device that runs along the erection girder, and turned 90 degrees in the predetermined turning position. Then, when moving to the erection position of each block and suspending it on the hanger supported by the erection girder via the suspending material, at least the section corresponding to the turning position of the block, the interval of the suspending material supporting the hanger Make the width more than the width in the bridge axis direction, and turn the block in the space between the hanging materials to In which was set to replace suspended in Nga.

【0018】なお、ブロックの転回位置にあたる区間に
ついては、ハンガーに吊り替えたブロックを一旦橋桁架
設高さ以下に吊り降ろし、所要数のブロックをハンガー
に吊り替えた後、橋桁架設高さまで引き上げるようにす
れば、ブロックの転回のためのスペースを十分にとるこ
とができ、作業が容易となる。
In the section corresponding to the turning position of the block, the block suspended on the hanger is temporarily suspended below the bridge girder erection height, and after the required number of blocks are suspended on the hanger, the block is raised to the bridge girder erection height. If so, a sufficient space for turning the block can be secured, and the work becomes easy.

【0019】また、架設ガーダー上に屋根装置(天蓋)
を装備することで、全天候型の施工が可能となる他、屋
根装置をプレキャストブロックの養生を目的として利用
することもできる。このような屋根装置としては、例え
ば、架設ガーダーの外側にレールを敷設し、施工スパン
全長に渡りジャバラ式に開閉するようなものが考えられ
る。
A roof device (canopy) is mounted on the erection girder.
By installing the above, not only can all-weather construction be possible, but the roof device can also be used for the purpose of curing the precast block. As such a roof device, for example, one in which rails are laid outside the erection girder and opened / closed in a bellows manner over the entire length of the construction span can be considered.

【0020】[0020]

【実施例】次に、図示した実施例について説明する。な
お、以下に述べる実施例はあくまで一実施例であり、本
願発明は実施例に限定されるものではない。
EXAMPLES Next, the illustrated examples will be described. Note that the embodiment described below is merely an embodiment, and the present invention is not limited to the embodiment.

【0021】図1は、本願発明の対象となるハンガー方
式のスパンバイスパンプレキャストブロック工法におけ
る施工および機械構成の概要を示したものである。
FIG. 1 shows an outline of the construction and machine construction in the hanger type span-by-span precast block construction method which is the subject of the present invention.

【0022】(1) 本実施例における施工方針は以下の通
りである。
(1) The construction policy in this embodiment is as follows.

【0023】 施工支間は、40〜60m程度とす
る。
The construction span is about 40 to 60 m.

【0024】 ブロック3単体の重量は100t程度
までとする。
The weight of the block 3 alone is up to about 100 t.

【0025】 架設可能なブロック3単位長さ当たり
の重量は、30t/mを標準とする。
[0025] The standard weight of the unit block 3 that can be installed is 30 t / m.

【0026】 架設ガーダー11は、フロントレグ3
2、ランチングレグ33、リアーレグ34の3本の脚に
より支持され、平行かつ横断勾配、縦断勾配、平面線形
に合わせて設置される。また、これらの脚を使用し、手
延桁方式にて単スパンごとに架設し、移動する。
The erection girder 11 includes the front leg 3
2. It is supported by three legs of a launching leg 33 and a rear leg 34, and is installed in parallel and in a cross slope, a longitudinal slope and a plane alignment. In addition, these legs will be used to erect each single span by the hand-rolled girder system and move.

【0027】 ブロック3は、ブロック製作ヤードか
ら架設地点まで、架設完了した橋桁2上をトレーラー2
4または自動搬送車を用いて運搬することを原則とす
る。架設地点まで、仮設道路を使用し、架設地点直下よ
り架設ガーダー11のクラブトロリー16にて直接架設
することも可能である。
The block 3 is a trailer 2 on the completed bridge girder 2 from the block manufacturing yard to the erection point.
4 In principle, it should be transported using an automated guided vehicle. It is also possible to use a temporary road up to the erection point and to erect directly from below the erection point with the club trolley 16 of the erection girder 11.

【0028】 柱頭部の施工は、場所打ち、プレキャ
ストブロック双方の施工が可能である。
As for the construction of the column head, both cast in place and precast block can be constructed.

【0029】(2) 本実施例における機械構成は以下の通
りである。
(2) The mechanical structure of this embodiment is as follows.

【0030】 架設ガーダー11 2径間をまたぐ2本の桁で構成され、架設ブロック3を
支える。架設ガーダー11上部は、クラブトロリー16
の走行路として使用される。
The erection girder 11 is composed of two girders spanning two spans and supports the erection block 3. The upper part of the erection girder 11 is a club trolley 16
It is used as a road.

【0031】 クラブトロリー16(吊り装置) ブロック3を搬送車より吊り上げ、架設位置まで移動さ
せるためのクレーンで、橋軸方向に走行、横行が可能で
ある。
Club trolley 16 (suspension device) A crane for hoisting the block 3 from the carrier and moving it to the erection position, which can travel and traverse in the bridge axis direction.

【0032】 フロントレグ32 架設ガーダー11最前部の脚で、送り出し、高さ調整、
横移動の機能がある。
Front leg 32 The front leg of the erected girder 11 is used for feeding, height adjustment,
There is a function of lateral movement.

【0033】 ランチングレグ33 架設ガーダー11中間部の脚で、送り出し、高さ調整、
横移動の機能がある。
Launching leg 33 With the leg in the middle part of the erection girder 11, the feeding, height adjustment,
There is a function of lateral movement.

【0034】 リアーレグ34 架設ガーダー11最後部の脚で、高さ調整、横移動の機
能があり、架設完了した桁2上を走行する走行装置を装
備している。
Rear leg 34 This is the last leg of the erection girder 11 and has the functions of height adjustment and lateral movement, and is equipped with a traveling device that travels on the girder 2 that has been erected.

【0035】 Aハンガー25 吊ビーム27を介してブロック3を仮吊りするハンガー
で、ブロック3の幅より吊り材28による支持点間距離
が長い。
A hanger 25 A hanger for temporarily suspending the block 3 via the suspension beam 27, and the distance between the supporting points by the suspending member 28 is longer than the width of the block 3.

【0036】 Bハンガー26 標準のハンガーでブロック3の位置決め、架設支持を行
う。
B hanger 26 The block 3 is positioned and erected by a standard hanger.

【0037】 作業足場23(ワーキングステージ) ブロック3の位置決め、接合作業用の足場で架設ガーダ
ー11に沿い移動可能である。この作業足場23は中央
で左右に分離できるようになっており、分離した状態で
移動させることができる。
Working scaffold 23 (working stage) It is a scaffold for positioning and joining work of the block 3 and is movable along the erection girder 11. The work scaffold 23 can be separated into left and right parts at the center, and can be moved in a separated state.

【0038】(3) 本実施例におけるブロック3の架設作
業は、以下のように行う。
(3) The erection work of the block 3 in this embodiment is performed as follows.

【0039】先頭のブロック3から順次クラブトロリー
16を用いて架設位置まで移動させ、Bハンガー26ま
たはAハンガー25に所定数のブロック3を均等な位置
間隔で吊り下げる。
The first block 3 is sequentially moved to the erection position by using the club trolley 16, and a predetermined number of blocks 3 are hung on the B hanger 26 or the A hanger 25 at equal position intervals.

【0040】この際、クラブトロリー16により吊り下
げられたブロック3は、橋軸方向に運搬され、所定の位
置で90度方向転回し、ハンガー25,26に吊り替え
られる必要がある。
At this time, the block 3 suspended by the club trolley 16 needs to be transported in the bridge axis direction, turned 90 degrees at a predetermined position, and suspended by the hangers 25 and 26.

【0041】この方向転回に必要な範囲を残し、所定数
のブロック3をBハンガー26に吊り下げた後、残され
た範囲のブロック3全数を方向転回に必要な空間を残し
た状態(所定の設置高さより低く仮吊りする)でAハン
ガー25に吊り替える。この区間の全数のブロック3が
Aハンガー25に仮吊りされた後、Aハンガー25のブ
ロック3を所定の高さ、間隔に位置決めする。
A predetermined number of blocks 3 are hung on the B hanger 26 while leaving a range necessary for turning in this direction, and a space necessary for turning all the blocks 3 in the remaining range is left (predetermined). Temporarily suspend it below the installation height) and hang it on the A hanger 25. After all the blocks 3 in this section are temporarily suspended on the A hanger 25, the blocks 3 of the A hanger 25 are positioned at a predetermined height and at intervals.

【0042】間詰め部の位置や、単径間の長さにより異
なるが、架設範囲内の方向転回の範囲が重ならない場合
は、Aハンガー25を使用する必要はない。
The A hanger 25 need not be used if the direction turning ranges within the erection range do not overlap, although it depends on the position of the packing portion and the length of the single diameter.

【0043】ブロックに、作業足場23上から接着剤を
塗布した後、引き寄せ鋼棒によりブロック3を順次引き
寄せながら接合する。
After the adhesive is applied to the blocks from above the work scaffold 23, the blocks 3 are sequentially drawn and joined by a drawing steel rod.

【0044】外ケーブルの敷設完了後、間詰め部の打
設、緊張を行い、単径間の施工を完了する。
After the laying of the outer cable is completed, the stuffing portion is laid and tensioned to complete the construction of the single span.

【0045】(4) 本実施例における架設ガーダー11の
移動は、以下のように行う。
(4) The erection girder 11 in this embodiment is moved as follows.

【0046】単径間の緊張完了後、Aハンガー25、B
ハンガー26を格納し、作業足場23の格納等の架設ガ
ーダー11の移動準備を行う。
After the tension of the single span is completed, A hanger 25, B
The hanger 26 is stored, and the erection girder 11 is prepared for movement such as storage of the work scaffold 23.

【0047】架設ガーダー11の移動は、ランチングレ
グ33の支持を解放(移動時にせりが出ない高さまで引
き上げる)し、フロントレグ32、リアーレグ34で架
設ガーダー11を支持することから始まる。
The movement of the erection girder 11 is started by releasing the support of the launching leg 33 (pulling it up to a height where there is no curb during movement) and supporting the erection girder 11 by the front leg 32 and the rear leg 34.

【0048】フロントレグ32は、前方の橋脚1に固定
されており、架設ガーダー11とは移動装置32aを介
して接続されている。また、リアーレグ34の脚部は、
ガーダー走行装置34a(またはガーダー送り出し装
置)となっており、その上部で架設ガーダー11を支持
している。
The front leg 32 is fixed to the front pier 1 and is connected to the erection girder 11 via the moving device 32a. Also, the legs of the rear leg 34 are
It is a girder traveling device 34a (or a girder feeding device), and the erection girder 11 is supported by the upper part thereof.

【0049】リアーレグ34、フロントレグ32で支持
された状態で、走行装置34a、移動装置32aを駆動
し、架設ガーダー11を送り出して行く。
While being supported by the rear leg 34 and the front leg 32, the traveling device 34a and the moving device 32a are driven to send out the erected girder 11.

【0050】ランチングレグ33をフロントレグ32と
同位置まで送り出した後(ランチングレグ33は付属し
ている移動装置33aで、自力でフロントレグ32の位
置まで移動可能であり、架設ガーダー11のバランス、
作業性を考慮しながら送り出す)、ランチングレグ33
を橋脚1に支持固定し、フロントレグ32を解放し、架
設ガーダー11に沿い、前方の橋脚1位置までフロント
レグ32を自力移動させる。
After the launching leg 33 has been sent to the same position as the front leg 32 (the launching leg 33 can be moved to the position of the front leg 32 by the moving device 33a attached thereto, the balance of the erection girder 11,
Launching leg 33 while considering workability)
Is supported and fixed to the pier 1, the front leg 32 is released, and the front leg 32 is moved along the erection girder 11 to the position of the pier 1 in front.

【0051】(5) 次に、本実施例における施工手順を、
図2(a) 〜(d) および図3(e) 〜(h)に基づいて説明す
る。
(5) Next, the construction procedure in this embodiment is
2 (a) to 2 (d) and 3 (e) to 3 (h).

【0052】 ブロック3の架設開始(図2(a) 参
照) 事前に移動式クレーンにより架設された先方橋脚1上の
基準ブロック3c側から架設を開始する。橋桁2上を運
搬したブロック3は、クラブトロリー16により吊り上
げられ、90度方向転回し、決められた位置まで運搬さ
れた後、順次等間隔に架設ガーダー11より下げられた
ハンガー(前方の区間は標準のハンガーであるBハンガ
ー25)に吊り替える。
Start of erection of the block 3 (see FIG. 2 (a)) The erection starts from the side of the reference block 3c on the leading pier 1 previously erected by the mobile crane. The block 3 carried on the bridge girder 2 was lifted by the club trolley 16, turned 90 degrees, carried to a predetermined position, and then sequentially lowered at equal intervals from the hanger (the front section was Suspend to standard hanger B hanger 25).

【0053】 ブロック3の架設(図2(b) 参照) 方向転回に必要な範囲のブロック3は、いったんAハン
ガー25に所定の設置高さより低く仮吊りする。単径間
に必要数のブロック3がAハンガー25、Bハンガー2
6に吊り下がった状態で、Aハンガー25に吊り下がっ
たブロック3を所定の高さ、等間隔に引き上げて位置決
めする。同時に先方柱頭部側から作業足場23を使用
し、接着剤の塗布、引寄せ、接合を行う。
Construction of Block 3 (See FIG. 2B) The block 3 in the range necessary for turning in the direction is temporarily hung on the A hanger 25 at a height lower than a predetermined installation height. The required number of blocks 3 in a single diameter is A hanger 25, B hanger 2
In the state where the block 3 is hung on 6, the blocks 3 hung on the A hanger 25 are lifted at a predetermined height and at equal intervals to be positioned. At the same time, the working scaffold 23 is used from the side of the front stigma to apply, draw, and join the adhesive.

【0054】 外ケーブルの敷設、緊張(図2(c) 参
照) 単径間全数のブロック3の接合、引寄せ、仮緊張が完了
した後、間詰めコンクリートの施工を行う。その後、外
ケーブルの敷設、緊張を行い、単径間の施工を完了す
る。
Laying of the outer cable and tension (see FIG. 2 (c)) After the joining, drawing, and temporary tension of all the blocks 3 of the single span are completed, the filling concrete is applied. After that, the outer cable is laid and tensioned to complete the construction of the single span.

【0055】 架設ガーダー11の移動準備(図2
(d) 参照) リアーレグ34、フロントレグ32で架設ガーダー11
を支え、ランチングレグ33のアンカーを解放し、若干
浮いた状態にする。同時にクラブトロリー16の固定、
ハンガー25,26の格納固定、作業足場23の移動準
備を実施する。
Preparation for moving the erection girder 11 (see FIG. 2
(See (d)) Rear leg 34, front leg 32 with erection girder 11
To release the anchor of the launching leg 33 and bring it into a slightly floating state. Fix the club trolley 16 at the same time,
The hangers 25 and 26 are stored and fixed, and the work scaffold 23 is prepared for movement.

【0056】 架設ガーダー11の送り出し(図3
(e) 参照) リアーレグ34脚部に装備した走行装置34a(図1参
照)を用いて架設ガーダー11の送り出しを行う。フロ
ントレグ32脚部は、橋脚1にアンカーで固定され、フ
ロントレグ32と架設ガーダー11の接合部は移動装置
32aを介している。この移動装置32aをガイドとし
て架設ガーダー11が前進する。
Sending out the erection girder 11 (see FIG.
(See (e)) The erection girder 11 is sent out by using the traveling device 34a (see FIG. 1) mounted on the leg of the rear leg 34. The leg portion of the front leg 32 is fixed to the pier 1 by an anchor, and the joint portion between the front leg 32 and the erection girder 11 is via a moving device 32a. The erection girder 11 moves forward using the moving device 32a as a guide.

【0057】 架設ガーダー11の位置決め調整(図
3(f) 参照) 架設ガーダー11の送り出し、フロントレグ32、ラン
チングレグ33が同一の橋脚1上に位置し、架設ガーダ
ー11の先端部分が次の橋脚1に届いた状態で架設ガー
ダー11の位置決め、調整を行い、仮固定する。
Positioning adjustment of the erection girder 11 (see FIG. 3 (f)) The delivery of the erection girder 11, the front leg 32 and the launching leg 33 are located on the same pier 1, and the tip part of the erection girder 11 is the next pier. After reaching the position 1, the erection girder 11 is positioned and adjusted and temporarily fixed.

【0058】 架設ガーダー11の固定(図3(g) 参
照) 橋脚1上のフロントレグ32、ランチングレグ33の支
持を入れ替える。ランチングレグ33を橋脚1上の基準
ブロック3a上にあずけ、固定した後、フロントレグ3
2を解放する。フロントレグ32の移動装置32aを駆
動させ、先方の橋脚1位置に固定する。
Fixing the erection girder 11 (see FIG. 3 (g)) The front leg 32 and the launching leg 33 on the pier 1 are exchanged for support. After placing the launching leg 33 on the reference block 3a on the pier 1 and fixing it, the front leg 3
Release 2. The moving device 32a of the front leg 32 is driven and fixed at the position of the pier 1 on the front side.

【0059】 ブロック3の架設準備(図3(h) 参
照) 架設ガーダー11の移動完了後、芯出し、微調整、位置
決めを行い、固定する。各部の点検、調整後、ブロック
3架設の準備を行う。
Preparation for erection of block 3 (see FIG. 3 (h)) After the movement of the erection girder 11 is completed, centering, fine adjustment and positioning are performed and fixed. After inspecting and adjusting each part, prepare for building block 3.

【0060】[0060]

【発明の効果】本願発明は、ハンガー方式のスパンバイ
スパンプレキャストブロック工法による橋梁の架設方法
において、架設ガーダーに沿って走行する吊り装置で順
次吊り上げ、所定の転回位置で90度方向転回させて、
それぞれのブロックの架設位置まで移動させ、架設ガー
ダーに吊り材を介して支持されたハンガーに吊り替える
にあたり、少なくともブロックの転回位置にあたる区間
については、吊り間隔を広げたハンガーを用いること
で、ブロックを吊り材間の空間で方向転回できるように
したものであり、架設作業を原則として桁上のみで行う
ことができる。
EFFECT OF THE INVENTION The present invention is a method of erection of a bridge by a span-by-span precast block construction method of a hanger system, which is sequentially hoisted by a hoisting device which runs along a hoisting girder, and is turned by 90 degrees at a predetermined turning position,
When moving to the erection position of each block and suspending it on the hanger supported by the erection girder through the suspending material, at least the section that corresponds to the turning position of the block, use the hanger with a wider suspension interval to move the block. It is designed so that the direction can be turned in the space between the hanging materials, and in principle the erection work can be performed only on the girder.

【0061】従って、橋下に移動クレーン等の設置スペ
ースがとれない場合でも、プレキャストブロック工法に
よる大規模な橋梁の施工が可能である。
Therefore, even if a space for installing a mobile crane or the like cannot be provided under the bridge, a large-scale bridge can be constructed by the precast block method.

【0062】また、ブロックの転回位置にあたる区間に
ついては、ハンガーに吊り替えたブロックを一旦橋桁架
設高さ以下に吊り降ろし、所要数のブロックをハンガー
に吊り替えた後、橋桁架設高さまで引き上げるようにす
れば、ブロックの転回のためのスペースを十分にとるこ
とができ、作業が容易となる。
In the section corresponding to the turning position of the block, the block suspended on the hanger is temporarily suspended below the bridge girder erection height, the required number of blocks are suspended on the hanger, and then the block is raised to the bridge girder erection height. If so, a sufficient space for turning the block can be secured, and the work becomes easy.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本願発明の対象となるハンガー方式のスパン
バイスパンプレキャストブロック工法の概要を示したも
ので、(a) は架設中の橋梁の側面図、(b) はA−A線断
面図、(c) はB−B線断面図、(d) はC−C線断面図、
(e) はD−D線断面図である。
FIG. 1 shows an outline of a hanger type span-by-span precast block construction method, which is the subject of the present invention, in which (a) is a side view of a bridge being erected, (b) is a sectional view taken along line AA, (c) is a sectional view taken along line BB, (d) is a sectional view taken along line CC,
(e) is a DD sectional view.

【図2】 (a) 〜(d) は本願発明の対象となるサポート
方式のスパンバイスパンプレキャストブロック工法の一
実施例における施工手順を示す側面図である。
2 (a) to 2 (d) are side views showing a construction procedure in an embodiment of a span-by-span precast block construction method of a support system which is an object of the present invention.

【図3】 (e) 〜(h) は図2(d) に続く施工手順を示す
側面図である。
3 (e) to (h) are side views showing a construction procedure following FIG. 2 (d).

【符号の説明】[Explanation of symbols]

1…橋脚、2…橋桁、3…ブロック、3c…基準ブロッ
ク、11…架設ガーダー、16…クラブトロリー、23
…作業足場、24…トレーラー、25…Aハンガー、2
6…Bハンガー、27…吊ビーム、28…吊り材、32
…フロントレグ、33…ランチングレグ、34…リアー
レグ
1 ... Bridge pier, 2 ... Bridge girder, 3 ... Block, 3c ... Standard block, 11 ... Erection girder, 16 ... Club trolley, 23
… Work scaffolding, 24… Trailer, 25… A hanger, 2
6 ... B hanger, 27 ... hanging beam, 28 ... hanging material, 32
… Front leg, 33… Launching leg, 34… Rear leg

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 工場またはヤードで製作された1径間分
の橋桁ブロックを、既設の橋桁上より架設ガーダーに吊
り下げて1径間ずつ架設するハンガー方式のスパンバイ
スパンプレキャストブロック工法による橋梁の架設方法
において、橋軸方向に対し90度回転した状態にあるブ
ロックを、前記架設ガーダーに沿って走行する吊り装置
で順次吊り上げ、所定の転回位置で90度方向転回させ
て、それぞれのブロックの架設位置まで移動させ、前記
架設ガーダーに吊り材を介して支持されたハンガーに吊
り替えるにあたり、少なくとも前記転回位置にあたる区
間については、前記ハンガーを支持する吊り材の間隔を
ブロックの橋軸方向の幅以上とし、ブロックを前記吊り
材間の空間で方向転回させて、各ブロックの架設位置で
ハンガーに吊り替えることを特徴とする橋梁の架設方
法。
1. A bridge using a hanger type span-by-span precast block method in which a bridge girder block for one span manufactured in a factory or a yard is hung from an existing bridge girder on a erection girder and erected one span at a time. In the erection method, blocks in a state of being rotated by 90 degrees with respect to the bridge axis direction are sequentially hung by a hanging device that runs along the erection girder, and are laid at 90 degrees in a predetermined turning position to lay each block. When moving to a position and suspending the hanger supported by the erection girder through a suspending member, at least for the section corresponding to the turning position, the interval of the suspending member supporting the hanger is not less than the width of the block in the bridge axis direction. Then, the blocks are turned around in the space between the suspension members and suspended on the hangers at the installation position of each block. A method of constructing a bridge characterized by the following.
【請求項2】 前記転回位置にあたる区間については、
ハンガーに吊り替えたブロックを一旦橋桁架設高さ以下
に吊り降ろし、所要数のブロックをハンガーに吊り替え
た後、橋桁架設高さまで引き上げる請求項1記載の橋梁
の架設方法。
2. Regarding the section corresponding to the turning position,
The bridge erection method according to claim 1, wherein the block suspended on the hanger is temporarily suspended to a height below the bridge girder erection height, a required number of blocks are suspended on the hanger, and then raised to the bridge girder erection height.
JP6277681A 1994-11-11 1994-11-11 Bridge construction method Expired - Fee Related JP2768282B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6277681A JP2768282B2 (en) 1994-11-11 1994-11-11 Bridge construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6277681A JP2768282B2 (en) 1994-11-11 1994-11-11 Bridge construction method

Publications (2)

Publication Number Publication Date
JPH08134845A true JPH08134845A (en) 1996-05-28
JP2768282B2 JP2768282B2 (en) 1998-06-25

Family

ID=17586827

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6277681A Expired - Fee Related JP2768282B2 (en) 1994-11-11 1994-11-11 Bridge construction method

Country Status (1)

Country Link
JP (1) JP2768282B2 (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008297777A (en) * 2007-05-30 2008-12-11 Sumitomo Mitsui Construction Co Ltd Method of constructing bridge
JP2009127317A (en) * 2007-11-26 2009-06-11 Sanshin Kogyo Kk Bridge construction apparatus
CN101851898A (en) * 2010-06-09 2010-10-06 中铁科工集团有限公司 Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof
CN102009911A (en) * 2010-12-02 2011-04-13 秦皇岛天业通联重工股份有限公司 Horizontal hanging beam travelling crane
CN103194977A (en) * 2013-04-10 2013-07-10 中铁十七局集团第三工程有限公司 Placing method for girder guiding machine before first hole box girder erection by integrated transportation and erection type bridge girder erection machine
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge
CN109826097A (en) * 2019-02-18 2019-05-31 腾达建设集团股份有限公司 A kind of interim prestressing force implementation method in the section of bridge subsection
CN110397289A (en) * 2019-08-14 2019-11-01 武汉通联路桥机械技术有限公司 A kind of comprehensive setting up girder stood in house capital and have automatic traveling function
CN112195785A (en) * 2020-09-18 2021-01-08 浙江交工金筑交通建设有限公司 Rotatable ultra-low-altitude bridge construction method for underpass existing bridge small-radius curve bridge
CN113417671A (en) * 2021-08-06 2021-09-21 中交(广州)建设有限公司 Construction method for quickly assembling prefabricated parts in shield tunnel
CN113503176A (en) * 2021-08-06 2021-10-15 中交(广州)建设有限公司 Integrated intelligent assembling trolley for prefabricated parts in tunnel

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008297777A (en) * 2007-05-30 2008-12-11 Sumitomo Mitsui Construction Co Ltd Method of constructing bridge
JP2009127317A (en) * 2007-11-26 2009-06-11 Sanshin Kogyo Kk Bridge construction apparatus
CN101851898A (en) * 2010-06-09 2010-10-06 中铁科工集团有限公司 Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof
CN102009911A (en) * 2010-12-02 2011-04-13 秦皇岛天业通联重工股份有限公司 Horizontal hanging beam travelling crane
CN103194977A (en) * 2013-04-10 2013-07-10 中铁十七局集团第三工程有限公司 Placing method for girder guiding machine before first hole box girder erection by integrated transportation and erection type bridge girder erection machine
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge
CN109826097A (en) * 2019-02-18 2019-05-31 腾达建设集团股份有限公司 A kind of interim prestressing force implementation method in the section of bridge subsection
CN110397289A (en) * 2019-08-14 2019-11-01 武汉通联路桥机械技术有限公司 A kind of comprehensive setting up girder stood in house capital and have automatic traveling function
CN110397289B (en) * 2019-08-14 2021-09-17 武汉通联路桥机械技术有限公司 All-dimensional beam erecting equipment standing on top of house column and having automatic walking function
CN112195785A (en) * 2020-09-18 2021-01-08 浙江交工金筑交通建设有限公司 Rotatable ultra-low-altitude bridge construction method for underpass existing bridge small-radius curve bridge
CN112195785B (en) * 2020-09-18 2022-07-01 浙江交工金筑交通建设有限公司 Rotatable ultra-low-altitude bridge construction method for underpass existing bridge small-radius curve bridge
CN113417671A (en) * 2021-08-06 2021-09-21 中交(广州)建设有限公司 Construction method for quickly assembling prefabricated parts in shield tunnel
CN113503176A (en) * 2021-08-06 2021-10-15 中交(广州)建设有限公司 Integrated intelligent assembling trolley for prefabricated parts in tunnel

Also Published As

Publication number Publication date
JP2768282B2 (en) 1998-06-25

Similar Documents

Publication Publication Date Title
JP2768282B2 (en) Bridge construction method
JP2768283B2 (en) Bridge construction method
JP3671777B2 (en) Bridge construction method
CN208934425U (en) Self-propelled multifunctional material distributing machine
JP2894226B2 (en) Bridge construction method
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
JP5184248B2 (en) Construction method of level crossing
KR20070010449A (en) Construction method for arched bridge
CN106042173A (en) Bridge production system
JP3110985B2 (en) Construction method of column capital of overhang girder bridge
JP4104910B2 (en) How to build arch ribs for concrete arch bridges
JP2000045231A (en) Erection method for arch bridge
JP2539150B2 (en) Bridge erection equipment
JP2768280B2 (en) Bridge construction method
CN110453689A (en) Circular foundation pit lining wall formwork construction system and construction method
JP2768281B2 (en) Bridge construction method
JP2768279B2 (en) Construction girder for precast block method
JP3616894B2 (en) Steel pipe pile installation device
CN111893898A (en) Suspension splicing bridge building system with pier hoisting and transportation splicing separated and construction method thereof
CN108914717B (en) Method for in-situ overhead installation of auxiliary support by using reinforcing steel bars of integral ballast bed
JPH0833032B2 (en) Construction method of building frame
JP2000129633A (en) Erection method for bridge floor slab
CN105507160B (en) Method of operation platform for movable-type bailey beams for construction of cast-in-place box beams
CN110080278B (en) Method for embedding annular foundation frame of bale rotary table
JPH10204830A (en) Method for bridging bridge girder

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980310

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees