CN110453689A - Circular foundation pit lining wall formwork construction system and construction method - Google Patents

Circular foundation pit lining wall formwork construction system and construction method Download PDF

Info

Publication number
CN110453689A
CN110453689A CN201910828118.6A CN201910828118A CN110453689A CN 110453689 A CN110453689 A CN 110453689A CN 201910828118 A CN201910828118 A CN 201910828118A CN 110453689 A CN110453689 A CN 110453689A
Authority
CN
China
Prior art keywords
steel
side form
fixed
template
inwall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910828118.6A
Other languages
Chinese (zh)
Inventor
徐巍
申帅
乔传颉
周宇
童晶
李彦贺
王玲
王玉泽
王全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Bureau Group North China Construction Co Ltd
Original Assignee
China Construction First Group Corp Ltd
China Construction First Bureau Group North China Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, China Construction First Bureau Group North China Construction Co Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201910828118.6A priority Critical patent/CN110453689A/en
Publication of CN110453689A publication Critical patent/CN110453689A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/182Bulkheads or similar walls made solely of concrete in situ using formworks to separate sections
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Revetment (AREA)

Abstract

A circular foundation pit lining wall template construction system and a construction method comprise a mould hanging system and a template system, wherein the template system comprises an end mould, a bottom mould and a side mould, the mould hanging system is fixed on a crown beam of a circular deep foundation pit, the mould hanging system comprises vertical triangular trusses which are uniformly arranged along the crown beam at intervals, an annular track which is fixed on the vertical triangular trusses, and electric hoists with roadblocks which are fixed on the annular track and used for hoisting the side mould; the bottom die comprises a shaped hyperbolic steel bottom die and a bottom die cross plate supporting frame for supporting the shaped hyperbolic steel bottom die; the end mould comprises an end plate, a section steel supporting and reinforcing device, a woodwork I-beam, a horizontal steel bar sling of the inner lining wall and a screw rod; the side mold comprises a side mold body, a shaping large template lifting hook, a steel shaping pouring opening, an operation platform, a high-strength screw rod and a connecting rod. The electric hoist with the treadmill can be designed in number and moving position according to needs, and after the side die body is assembled, the electric hoist is hoisted to a preset position through the die hoisting system, so that the electric hoist with the treadmill is quick in construction and low in cost.

Description

A kind of physa hole inwall template construction system and construction method
Technical field
The invention belongs to the realm of building construction, a kind of physa hole inwall template construction system and construction method are particularly belonged to.
Background technique
In conventional mould construction technology, takes the big machineries such as tower crane or crane to carry out shaping formwork hoisting, installs and tear open Remove, typified form is larger heavier, can not manual operation, needed in installation and demolishing process for a long time occupy tower crane, will affect Inwall and other normal transports (reinforcing bar and other material horizontals and vertical transport).
Summary of the invention
The object of the present invention is to provide a kind of a kind of physa hole liner wall forms of physa hole inwall template construction system to apply The Worker's Stadium system and construction method will solve the low technical problem of prior art construction efficiency;And solve prior art labor intensive Problem.
To achieve the above object, the present invention adopts the following technical scheme:
A kind of physa cheats inwall template construction system, including hangs modular system and template system, the template system include end mould, Bed die and side form, the modular system that hangs are fixed in the crown beam of circular deep foundation ditch, it is characterised in that: the modular system that hangs includes edge The circular orbit for being fixed on and being stood on English truss to English truss is found in the setting of crown beam uniform intervals, and is fixed on annular Band sport car electric hoist on track, for lifting side form, it is described to stand to English truss one end and crown beam and outside concrete road surface Or basis is fixed, in foundation pit, at least one circle circular orbit is fixed on the overhanging end stood to English truss, several for other end overhanging Group band sport car electric hoist interval is fixed on circular orbit;
The bed die includes sizing hyperbolic steel bed die and the bed die cross plate support frame for being used to support sizing hyperbolic steel bed die; The end mould includes end plate, the type steel support bracing means for fixing end head plate, uniform intervals set on end plate and fashioned iron The fixed other end of wooden H-beam, one end and type steel support bracing means between bracing reinforcement device anchors into the liner of liner wall Wall horizontal reinforcement gets rid of muscle and for the screw rod that type steel support bracing means and diaphram wall is fixed;The side form includes side form Ontology, the behaviour for pouring mouth with the sizing large form suspension hook with the fixation of sport car electric hoist, steel sizing, being fixed on side form ontology Make platform, the high-strength bolt fixed with side form ontology and the connecting rod for being connected and fixed ground-connecting-wall reinforcing bar and high-strength bolt.
It is further preferred that described stand to English truss and foundation pit center line is located along the same line.
Further, described stand to English truss includes overhanging bottom girder steel, tripod chord member, web member and gusset plate.
Further, the circular orbit is formed by I-steel splicing fixation.
Further, the side form ontology includes arc formwork, the main back cord of channel steel and wooden H-beam time back cord, and the steel is fixed Type pours mouth and includes top surface opening, the gusseted frame that vertical cross-section is right angle trigonometry type and be fixed on gusseted outer frame edge Overturn cover board.
In addition, the operating platform includes horizontal support bar, the oblique branch between horizontal support bar and side form ontology It strut, the vertical supporting between horizontal support bar and skewed horizontal load bar, the pedal being laid on horizontal support bar and is set to Protective frame on horizontal support bar.
It is further preferred that each band sport car electric hoist passes through a fashioned iron shoulder pole and four wirerope liftings at least one Block side form ontology.
A kind of method of physa hole inwall template construction system inner lining construction wall, which is characterized in that include the following steps,
Step 1: installation bed die cross plate support frame: installation bed die cross plate support frame, and bind and install inwall reinforcing bar;
Step 2: installation bed die: adjustment bed die cross plate support frame absolute altitude, installation sizing hyperbolic steel bed die;
Step 3: installation side form: the prefabricated side form finished being lifted by hanging modular system to predetermined position, the installation of side form is completed And it reinforces;
Step 4: installation end mould: completing the installation and reinforcing of end mould in side form two sides;
Step 5: liner wall pours: a mouthful concrete perfusion completion liner wall is poured to steel sizing by expects pipe and is poured, demoulding Step 1 ~ five are repeated afterwards until inwall is poured and finished.
Compared with prior art the invention has the characteristics that and the utility model has the advantages that
The present invention uses circular orbit handling apparatus, dedicated for template construction, can save tower crane and hang time, accelerate construction progress, Facilitate template construction, the convention liner that compares wall construction method can be arranged according to inwall construction deployment and flowing water section, band sport car Electric hoist can design number and shift position as needed, can synchronous construction can cross construction, flexible and convenient operation;It can be according to interior Chemise radian is arranged different circular orbits and meets site operation requirement;And after side form ontology is completed, hung by hanging modular system It is filled to predetermined position, is constructed fast, at low cost.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the present invention for hanging modular system;
Fig. 2 is that of the present invention stand to the positional relationship of English truss and circular orbit illustrates;
Fig. 3 is that wirerope of the present invention and fashioned iron shoulder pole positional relationship illustrate;
Fig. 4 is the positional relationship diagram of liner wall of the present invention and diaphram wall;
Fig. 5 is the structural schematic diagram of side form of the present invention;
Fig. 6 is that steel of the present invention sizing pours mouth and the positional relationship of side form ontology illustrates;
Fig. 7 is end mould of the present invention diagram.
Appended drawing reference: 1- crown beam;2- is stood to English truss;21- overhangs bottom girder steel;22- tripod chord member;23- web member; 24- gusset plate;3- circular orbit;4- band sport car electric hoist;5- sizing hyperbolic steel bed die;6- bed die cross plate support frame;7- End plate;8- type steel support bracing means;9- wooden H-beam;10- liner wall;11- inwall horizontal reinforcement gets rid of muscle;12- Lower diaphragm wall;13- screw rod;14- side form ontology;The main back cord of 141- channel steel;142- wooden H-beam time back cord;143- arc formwork; 15- sizing large form suspension hook;The sizing of 16- steel pours mouth;161- gusseted frame;162- overturns cover board;17- operating platform; 171- horizontal support bar;172- skewed horizontal load bar;173- vertical supporting;174- pedal;175- protective frame;18- ground-connecting-wall reinforcing bar; 19- high-strength bolt;20- high-strength bolt;25- fashioned iron shoulder pole;26- wirerope;27- inwall reinforcing bar.
Specific embodiment
For realize the present invention technological means, character of innovation, reach purpose and effect is easy to understand, below to Invention further illustrates.
The embodiment recorded herein is specific specific embodiment of the invention, for illustrating design of the invention, Be it is explanatory and illustrative, should not be construed as the limitation to embodiment of the present invention and the scope of the invention.Except what is recorded herein Outside embodiment, those skilled in the art can also based on the claim of this application book and specification disclosure of that using aobvious and The other technical solutions being clear to, these technical solutions include using any obvious to making for the embodiment recorded herein The technical solution of substitutions and modifications.
A kind of physa hole inwall template construction system, as illustrated in fig. 1 and 2, including hangs modular system and template system, template System includes end mould, bed die and side form, hangs crown beam 1 and outside concrete road surface or basis that modular system is fixed on circular deep foundation ditch On, as illustrated in fig. 1 and 2, hanging modular system includes standing to English truss 2 along the setting of 1 uniform intervals of crown beam, is fixed on and stands to triangle Circular orbit 3 on truss 2, and be fixed on circular orbit 3, the band sport car electric hoist 4 for lifting side form, it stands to triangle 2 one end of truss and crown beam 1 are fixed, and other end overhanging is stood to English truss 2 in foundation pit, at least one circle circular orbit 3 is fixed on Overhanging end, several groups band sport car electric hoist 4 interval is fixed on circular orbit 3, convenient for horizontal flowing water section divide construction, to add Fast construction speed;It stands to English truss 2 and foundation pit center line and is located along the same line, overhang bottom girder steel 21, tripod chord member 22, web member 23 and gusset plate 24, circular orbit 3 is formed by I-steel splicing fixation, as shown in figure 3, each band sport car electric hoist 4 At least one piece of side form ontology 14 is lifted by crane by a fashioned iron shoulder pole 25 and four wirerope 26, one piece of side form ontology 14 nearly weighs 1T, Band sport car electric hoist 4 drives side form ontology 14 horizontally or vertically to move.
As shown in figure 5, bed die includes sizing hyperbolic steel bed die 5 and the bed die for being used to support sizing hyperbolic steel bed die 5 Cross plate support frame 6;The panel of sizing hyperbolic steel bed die 5 uses Double curved arc steel form, and standard block size is 4.8 × 3m, Primary and secondary back cord is combined as with square steel and channel steel and is fabricated to typified form use, and support system (bed die cross plate support frame 6) is 70 cross plate support frames cooperate arc girder 20# I-steel.Advantage: 1, flexible and convenient turntable connection: every 500mm in upright bar If a turntable connecting plate, each connecting plate can connect horizontal tube in four direction.2, the upright bar connection of novel and unique: each rule Lattice upright bar passes through upright bar connector in the height direction and upright bar connecting pin is attached.Upright bar connecting pin is new deisgn product, It is fixed without hair fastener, can effectively avoid gadgety loss problem.3, flexibly firm horizontal connection: each cross bar both ends respectively have One horizontal connection device, for being connect with upright bar turntable and brace.Horizontal connection device is by casting connector and two bolts Composition, three is by rivet combination at an entirety.Two bolts not only can be up and down, but also will not fall off, and both facilitating makes With in turn avoiding the loss problem of small bolt in use process.
As shown in fig. 7, end mould includes end plate 7, type steel support bracing means 8, uniform intervals for fixing end head plate 7 Wooden H-beam 9, one end and the fixation of type steel support bracing means 8 between end plate 7 and type steel support bracing means 8 is another The inwall horizontal reinforcement that end anchors into liner wall 10 gets rid of muscle 11 and is used for type steel support bracing means 8 and diaphram wall 1 Fixed screw rod 13;End plate 7 uses 18mm multi-layer board, and secondary back cord uses wooden H-beam 9, and main back cord uses shape steel bracket (type Bracing members bracing means 8 carries out fixed with the main back cord 141 of the channel steel of underground connection wall and side form.
As shown in figure 5, side form include side form ontology 14, for the sizing large form suspension hook fixed with sport car electric hoist 4 15, steel sizing pours mouth 16, the operating platform being fixed on side form ontology 14 17, the high-strength bolt 19 fixed with side form ontology 14 With the connecting rod 20 for being connected and fixed ground-connecting-wall reinforcing bar 18 and high-strength bolt 19, ground-connecting-wall reinforcing bar 18 is embedded in diaphram wall In 12, the horizontal and vertical spacing of ground-connecting-wall reinforcing bar 18 is 1000mm, is arranged in blossom type, and side form ontology 14 includes arc mould The main back cord 141 of plate 143, channel steel and wooden H-beam time back cord 142, as shown in fig. 6, steel sizing pour mouth 16 include top surface opening, Vertical cross-section is the gusseted frame 161 of right angle trigonometry type and the overturning cover board 162 for being fixed on 161 outer of gusseted frame, steel It further includes that socket joint blocks mouth that sizing, which pours mouth 16, and socket joint blocks mouth and blocked after pouring by steel plate insertion, socket joint Block mouth the prior art for being related to comparative maturity, arc formwork 143 use 21mm thickness Visa plate, meet turnover 20 times with On, wooden H-beam time back cord 142 uses 200 mm high wooden H-beam systems, and spacing is not more than 300mm, and the main back cord 141 of channel steel is adopted With 12# double flute steel, spacing is not more than 1200mm, and arc formwork 143 is connect with wooden H-beam time back cord 142 using corner brace, carpenter It is connected between word beam time back cord 142 and the main back cord 141 of channel steel with connection pawl, is connected between arc formwork 143 by bending core ribbon, Ensure that seam crossing pours not spillage;Large form about 60kg/ ㎡, operating platform 17 include horizontal support bar 171, set on horizontally-supported Skewed horizontal load bar 172 between bar 171 and side form ontology 14, erecting between horizontal support bar 171 and skewed horizontal load bar 172 To support 173, the pedal 174 being laid on horizontal support bar 171 and the protective frame 175 on horizontal support bar 171.
Side form and end mould are all made of wooden H-beam template system, and feature is main are as follows: back cord and wooden frame are using connection pawl mark Quasi- part connection is simple, convenient, rapid;Template is light-weight, and rigidity is big;Template reparation is convenient, when form surfacing damages, only Panel is needed to change, formwork reinforcement uses D20 high-strength bolt, includes the auxiliary products such as Screw arbor with nut at both-ends, water-stopping pull rod, taper joint.
A kind of method of physa hole inwall template construction system inner lining construction wall, which is characterized in that include the following steps,
Step 1: installation bed die cross plate support frame 6: installation bed die cross plate support frame 6, and bind and install inwall reinforcing bar 27;
Step 2: installation bed die: adjustment 6 absolute altitude of bed die cross plate support frame, installation sizing hyperbolic steel bed die 5;
Step 3: installation side form: the prefabricated side form finished being lifted by hanging modular system to predetermined position, the installation of side form is completed And it reinforces;
Step 4: installation end mould: completing the installation and reinforcing of end mould in side form two sides;
Step 5: liner wall 10 pours: pouring 16 concrete perfusion of mouth completion liner wall 10 to steel sizing by expects pipe and pour It builds, step 1 ~ five is repeated after demoulding until inwall is poured and finished.
Template installation procedure and requirement
(1) to prevent mouth running pulp under template, before installing side form, bed die should ensure that level, and in the bed die top surface that template is located in place Upper 401 gluing sponge strips, to reduce spillage;The template hanging for bottom, before installation template, to be arranged template support pad item or Band (such as pylon, double frame, flitch etc.), and its is straight for calibration.
(2) there must be the signalman of profession when side form lifts with professional knuckle man to complete lifting operation.
(3) side form lifting must carry out specific aim safe practice and tell somebody what one's real intentions are, and construction worker must fulfil signature formality.
(4) when side form lifts by crane, vertical lifting, steady rise surely to fall, forbid significantly to put, before lifting, it should be noted that check template The phenomenon that whether scraping pocket with surrounding;After decoupling device, tower crane hook and wirerope must be over template platform frame guardrail and other obstacles After can pivoted arm;Ground handling operator, in template lifting, it is necessary to leave other than template 2m.
(5) after template acceptance(check) should timely casting concrete, prevent building template is long-term from wet by the rain and burnt by the sun becoming Shape.
Mold casting concrete
(1) panel is cleaned before molding, cleaning panel preferably uses medium-hard hairbrush to scrub, and plate face will be wiped clean, otherwise in template Dust can be stained with the surface of concrete, it is necessary to ensure that this process carries out after concrete rushes hair.
(2) after template is dry, with brush or clean towel, template surface is painted into release agent (salad oil).It not brush too It is more, forbid to trickle, is best without oil trace to have glossy.Guarantee uniformly, to brush one times again after rain.
(3) check whether reinforcing bar mutually conflicts with form tie hole, embedded part system, have conflict must adjust reinforcement location.
(4) according to construction survey point, the positioning support that template spacing is controlled on reinforcing bar is welded, ground is added using reinforcing bar two sides Concrete cover does inner support.
(5) molding correction.First by the verticality of template edge instrument or line pendant calibration template, and yin-yang is adjusted with angle square The angle of Angle formwork, it is ensured that verticality and angle reach design requirement.Then casing, pull rod are put on, nut is tightened.Check mould Plate is adjusted to meeting pouring concrete requirement.Note that casing is unsuitable too long, stretches out template back surface 20mm and be preferred.
Points for attention in concreting process:
A. blanking uniformly, continuously must not will concentrate precipitate and cause jammed.It can be started the short time in reinforcing bar, duct dense part Poker vibrator assists blanking.
B. concrete mixes and stirs quality, the strict control ratio of mud, to guarantee the quality of concrete check at any time in casting process.
Form removable requirement
(1) demoulding can be carried out after concrete strength reaches quality requirement.Pull-rod nut is first unloaded when demoulding, extracts pull rod out, It stacks in place.Core ribbon is unloaded, template is moved back or hung away.
(2) it first tears piece template open, then removes circle curve template, forbid to be pounded with sledgehammer or crowbar prizes template firmly, in case damage is mixed Solidifying soil surface.
(3) stacking, cleaning and repairing of template.After form removable, the plate face of template and gap are carried out immediately comprehensively thorough Bottom cleaning guarantees that mold sticking does not occur in next use.Template will repair cleaning after, such as template cleaning, deformation Correction, replacement of template accessory etc..
(4) it surely to rise in formwork hoisting and surely fall, every piece of template must be placed on flitch.
(5) non-template operator must not arbitrarily enter formwork area, and operator must wear security protection articles. The commander of operation group leader is accepted, must not operate against regulations and give directions against regulations.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (8)

1. a kind of physa cheats inwall template construction system, including hangs modular system and template system, the template system includes end Mould, bed die and side form, the modular system that hangs are fixed in the crown beam (1) of circular deep foundation ditch, it is characterised in that: described to hang modular system The circular orbit for being fixed on and being stood on English truss (2) to English truss (2) is found including what is be arranged along crown beam (1) uniform intervals (3), it and is fixed on circular orbit (3), band sport car electric hoist (4) for lifting side form, it is described to stand to English truss (2) One end and crown beam (1) are fixed, and other end overhanging is stood to English truss (2) in foundation pit, at least one circle circular orbit (3) is fixed on Overhanging end, several groups band sport car electric hoist (4) interval be fixed on circular orbit (3);
The bed die includes sizing hyperbolic steel bed die (5) and the bed die cross plate for being used to support sizing hyperbolic steel bed die (5) Support frame (6);The end mould include end plate (7), for fixing end head plate (7) type steel support bracing means (8), uniformly between Every wooden H-beam (9), one end and the type steel support bracing means being set between end plate (7) and type steel support bracing means (8) (8) the inwall horizontal reinforcement that the fixed other end anchors into liner wall (10) gets rid of muscle (11) and is used for type steel support bracing means (8) screw rod (13) fixed with diaphram wall (12);The side form includes side form ontology (14), is used for and band sport car electric hoist (4) operating platform that fixed sizing large form suspension hook (15), steel sizing pour mouth (16), are fixed on side form ontology (14) (17), with high-strength bolt (19) of side form ontology (14) fixation and for being connected and fixed ground-connecting-wall reinforcing bar (18) and high-strength bolt (19) connecting rod (20).
2. a kind of physa as described in claim 1 cheats inwall template construction system, it is characterised in that: described to stand to triangle purlin Frame (2) is located along the same line with foundation pit center line.
3. a kind of physa as described in claim 1 cheats inwall template construction system, it is characterised in that: described to stand to triangle purlin Frame (2) includes overhanging bottom girder steel (21), tripod chord member (22), web member (23) and gusset plate (24).
4. a kind of physa as described in claim 1 cheats inwall template construction system, it is characterised in that: the circular orbit (3) it is formed by I-steel splicing fixation.
5. a kind of physa as described in claim 1 cheats inwall template construction system, it is characterised in that: the side form ontology It (14) include arc formwork (143), the main back cord of channel steel (141) and wooden H-beam time back cord (142), the steel sizing pours mouth (16) include top surface opening, vertical cross-section be right angle trigonometry type gusseted frame (161) and be fixed on gusseted frame (161) The overturning cover board (162) of outer.
6. a kind of physa as described in claim 1 cheats inwall template construction system, it is characterised in that: the operating platform It (17) include horizontal support bar (171), set on the skewed horizontal load bar between horizontal support bar (171) and side form ontology (14) (172), be set to vertical supporting (173) between horizontal support bar (171) and skewed horizontal load bar (172), be laid on it is horizontally-supported Pedal (174) on bar (171) and the protective frame (175) on horizontal support bar (171).
7. a kind of physa as described in claim 1 cheats inwall template construction system, it is characterised in that: each band sport car Electric hoist (4) lifts by crane at least one piece of side form ontology (14) by fashioned iron shoulder pole (25) He Sigen wirerope (26).
8. a kind of side of physa hole inwall template construction system inner lining construction wall as described in claim 1 ~ 7 any one Method, which is characterized in that include the following steps,
Step 1: installation bed die cross plate support frame (6): installation bed die cross plate support frame (6), and bind and install inwall Reinforcing bar (27);
Step 2: installation bed die: adjustment bed die cross plate support frame (6) absolute altitude, installation sizing hyperbolic steel bed die (5);
Step 3: installation side form: the prefabricated side form finished being lifted by hanging modular system to predetermined position, the installation of side form is completed And it reinforces;
Step 4: installation end mould: completing the installation and reinforcing of end mould in side form two sides;
Step 5: liner wall (10) pours: pouring mouth (16) concrete perfusion to steel sizing by expects pipe and complete liner wall (10) it pours, step 1 ~ five is repeated after demoulding until inwall is poured and finished.
CN201910828118.6A 2019-09-03 2019-09-03 Circular foundation pit lining wall formwork construction system and construction method Pending CN110453689A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910828118.6A CN110453689A (en) 2019-09-03 2019-09-03 Circular foundation pit lining wall formwork construction system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910828118.6A CN110453689A (en) 2019-09-03 2019-09-03 Circular foundation pit lining wall formwork construction system and construction method

Publications (1)

Publication Number Publication Date
CN110453689A true CN110453689A (en) 2019-11-15

Family

ID=68490557

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910828118.6A Pending CN110453689A (en) 2019-09-03 2019-09-03 Circular foundation pit lining wall formwork construction system and construction method

Country Status (1)

Country Link
CN (1) CN110453689A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113404057A (en) * 2021-07-16 2021-09-17 江苏通力建设集团有限公司 Integral pouring structure and construction method for foundation pit side wall cushion layer of elevator shaft
CN113585276A (en) * 2021-04-07 2021-11-02 中国建筑一局(集团)有限公司 Mounting and dismounting device and construction method for bottom membrane of reverse lining wall of deep foundation pit

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0953237A (en) * 1995-08-11 1997-02-25 Mitsui Home Co Ltd Pit and constructing method of basement utilizing the pit
CN102913248A (en) * 2012-11-13 2013-02-06 广汉金达隧道机械有限公司 Whole-circle whole invertedly-hanging template and mold-erecting and demolding methods of template
CN103912010A (en) * 2014-04-04 2014-07-09 北京城建设计发展集团股份有限公司 Construction method of open excavation prefabricated underground structure
CN204919531U (en) * 2015-08-04 2015-12-30 中交第二航务工程局有限公司 Hang mould supporting device what inside lining was pour to underground continuous wall body surface face
CN107503365A (en) * 2017-09-11 2017-12-22 上海宝冶集团有限公司 Super High elevator high and big die plate installation engineering method
CN207312994U (en) * 2017-09-19 2018-05-04 中国水利水电第十工程局有限公司 Power station major diameter surge shaft steel lining cantilevered annular track boom hoisting
CN109403354A (en) * 2018-11-27 2019-03-01 武汉钢铁集团鄂城钢铁有限责任公司 A kind of whirling well hangs upside down the construction method of retaining wall deep foundation pit support
CN210621713U (en) * 2019-09-03 2020-05-26 中国建筑一局(集团)有限公司 Circular foundation pit inside lining wall template construction system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0953237A (en) * 1995-08-11 1997-02-25 Mitsui Home Co Ltd Pit and constructing method of basement utilizing the pit
CN102913248A (en) * 2012-11-13 2013-02-06 广汉金达隧道机械有限公司 Whole-circle whole invertedly-hanging template and mold-erecting and demolding methods of template
CN103912010A (en) * 2014-04-04 2014-07-09 北京城建设计发展集团股份有限公司 Construction method of open excavation prefabricated underground structure
CN204919531U (en) * 2015-08-04 2015-12-30 中交第二航务工程局有限公司 Hang mould supporting device what inside lining was pour to underground continuous wall body surface face
CN107503365A (en) * 2017-09-11 2017-12-22 上海宝冶集团有限公司 Super High elevator high and big die plate installation engineering method
CN207312994U (en) * 2017-09-19 2018-05-04 中国水利水电第十工程局有限公司 Power station major diameter surge shaft steel lining cantilevered annular track boom hoisting
CN109403354A (en) * 2018-11-27 2019-03-01 武汉钢铁集团鄂城钢铁有限责任公司 A kind of whirling well hangs upside down the construction method of retaining wall deep foundation pit support
CN210621713U (en) * 2019-09-03 2020-05-26 中国建筑一局(集团)有限公司 Circular foundation pit inside lining wall template construction system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113585276A (en) * 2021-04-07 2021-11-02 中国建筑一局(集团)有限公司 Mounting and dismounting device and construction method for bottom membrane of reverse lining wall of deep foundation pit
CN113404057A (en) * 2021-07-16 2021-09-17 江苏通力建设集团有限公司 Integral pouring structure and construction method for foundation pit side wall cushion layer of elevator shaft

Similar Documents

Publication Publication Date Title
CN106677211B (en) Early-dismantling assembly type pipe gallery aluminum mould trolley system for integrally casting wall and top plate and construction method thereof
CN105736016B (en) Tunnel double-lining framework of steel reinforcement construction equipment and its application
CN206538787U (en) Early-dismantling assembly type pipe gallery aluminum mould trolley system for integrally pouring wall and top plate
CN106894639B (en) The hanging reverse construction method of installation of steel construction under a kind of
CN109577534A (en) Tool-based hanging die assembly type composite floor slab and construction method
CN100476076C (en) Mobile integral construction platform, construction method thereof and special sling for the same
CN106013781A (en) Slab supporting construction method and construction device by reversely suspending template
CN104975719A (en) Novel material distribution device and construction method for pouring floor concrete by using same
CN208934425U (en) Self-propelled multifunctional material distributing machine
CN107905111B (en) A kind of rigid frame-continuous girder end bay construction technology
CN107905124B (en) A kind of symmetrical expression rigid frame-continuous girder construction technology
CN106906841A (en) One kind is used for lateral wall form bracing system construction
CN108589535A (en) A kind of reinforced concrete box girder construction method
CN209799969U (en) A integrally lift up cantilever formwork device for quick construction shaft lining cutting
CN109183620A (en) Telescoping bracket, steel box-girder hanging device and hanging method
CN107227814A (en) Sectional construction method for large cantilever concrete structure
CN106703407A (en) Construction method of double-layered shape steel supporting rack of cantilever beam plate
CN106351439A (en) Aluminum alloy template construction technology and method
CN110453689A (en) Circular foundation pit lining wall formwork construction system and construction method
CN106042173A (en) Bridge production system
CN109869153A (en) The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN103758045A (en) Box girder wet joint formwork construction method under space limitation condition
CN109025275A (en) A kind of shear wall side regularization stair punching block and installation method
CN210621713U (en) Circular foundation pit inside lining wall template construction system
CN107587711A (en) A kind of regularization assembled overhanging protection canopy and its assembly method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination