JP2008297777A - Method of constructing bridge - Google Patents

Method of constructing bridge Download PDF

Info

Publication number
JP2008297777A
JP2008297777A JP2007144199A JP2007144199A JP2008297777A JP 2008297777 A JP2008297777 A JP 2008297777A JP 2007144199 A JP2007144199 A JP 2007144199A JP 2007144199 A JP2007144199 A JP 2007144199A JP 2008297777 A JP2008297777 A JP 2008297777A
Authority
JP
Japan
Prior art keywords
bridge
girder
span
box girder
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2007144199A
Other languages
Japanese (ja)
Other versions
JP4937838B2 (en
Inventor
Akio Kasuga
昭夫 春日
Akira Morohashi
明 諸橋
Toshibumi Ochi
俊文 越智
Takayuki Odagiri
隆幸 小田切
Shinichiro Kumagai
紳一郎 熊谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2007144199A priority Critical patent/JP4937838B2/en
Publication of JP2008297777A publication Critical patent/JP2008297777A/en
Application granted granted Critical
Publication of JP4937838B2 publication Critical patent/JP4937838B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To reduce construction period and construction cost in a method of constructing a bridge for constructing a multi-span continuous bridge by a span by span construction method. <P>SOLUTION: In the structure of a bridge 12 constructed between spans, a plurality of box beam core parts 14 are set in a multi-main box beam structure disposed at predetermined intervals in the directions perpendicular to the bridge axis. A plurality of core segments 24 forming the box beam core parts 14 for one bridge are disposed adjacent to each other in the bridge axis direction on an existing bridge positioned at the rear of the construction span S0. After the box beam core parts 14 are assembled by introducing the prestress in the bridge direction into these core segments, the box beam core parts 14 are moved to the construction span S0, and lifted to a construction girder 110 so installed as to straddle the construction span S0. The box beam core parts 14 lifted by the construction girder 110 are lowered onto a pair of pedestals 32 on both sides of the construction span S0 in the bridge axis direction, and, as required, moved to a predetermined position in the direction perpendicular to the bridge axis. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本願発明は、いわゆるスパンバイスパン工法により多径間連続橋を架設する、橋梁の架設方法に関するものである。   The present invention relates to a bridge construction method for constructing a multi-span continuous bridge by a so-called span-by-span construction method.

従来より、多径間連続橋を架設する方法の1つとして、スパンバイスパン工法が知られている。   Conventionally, the span-by-span construction method is known as one of the methods of constructing a multi-span continuous bridge.

このスパンバイスパン工法においては、例えば「特許文献1」に記載されているように、複数のプレキャストセグメントを橋軸方向に互いに隣接するように配置し、これら複数のプレキャストセグメントに橋軸方向のプレストレスを導入して一体化することにより、1径間分の橋桁を架設し、これを複数の径間に対して順次繰り返すことにより多径間連続橋を架設するようになっている。   In this span-by-span construction method, for example, as described in “Patent Document 1”, a plurality of precast segments are arranged adjacent to each other in the bridge axis direction, and the precast segments in the bridge axis direction are arranged on the plurality of precast segments. By integrating by introducing stress, a bridge girder for one span is constructed, and a multi-span continuous bridge is constructed by sequentially repeating this for a plurality of spans.

このようなスパンバイスパン工法を、多主桁箱桁構造を有する橋桁に適用する場合には、従来、図9に示すような施工手順で、その架設作業が行われている。   When such a span-by-span construction method is applied to a bridge girder having a multi-main girder box girder structure, the erection work has been conventionally performed according to a construction procedure as shown in FIG.

すなわち、まず、同図(a)に示すように、架設径間を跨ぐようにして設置された架設用ガーダ100に、複数の箱桁セグメント2を順次吊り下げて、これらを橋軸方向に互いに隣接するように配置し、そして、同図(b)に示すように、主桁1本分の箱桁セグメント2をすべて吊り下げて、これらを互いに密着させた状態で、同図(c)に示すように、橋軸方向両端部の目地4にコンクリートを打設した後、これら複数の箱桁セグメント2に橋軸方向のプレストレスを導入して一体化することにより、1つの主桁6について架設を完了させ、その後、同図(d)に示すように、架設用ガーダ100を橋軸直交方向に移動させて、他の主桁についても同様の手順で架設を行うようになっている。   That is, first, as shown in FIG. 2A, a plurality of box girder segments 2 are sequentially suspended from a girder for installation 100 so as to straddle between installation diameters, and these are connected to each other in the direction of the bridge axis. As shown in FIG. 4B, the box girder segments 2 for one main girder are all suspended and are in close contact with each other, as shown in FIG. As shown in the drawing, after placing concrete on joints 4 at both ends in the bridge axis direction, by introducing prestress in the bridge axis direction into the plurality of box girder segments 2 and integrating them, one main girder 6 After erection is completed, the erection girder 100 is moved in the direction orthogonal to the bridge axis as shown in FIG. 4D, and erection is performed in the same procedure for the other main girders.

特開平8−134845号公報JP-A-8-134845

しかしながら、上記従来のスパンバイスパン工法により多主桁箱桁構造を有する橋桁の架設を行う場合には、架設用ガーダが1基であれば、架設径間において、複数の主桁の各々について、複数の箱桁セグメントの吊下げ、目地打設およびプレストレス導入を行う必要があり、しかも、1つの主桁の施工が完了する度に架設用ガーダを橋軸直交方向に移動させる必要があり、このため架設工期が非常に長くなってしまう、という問題がある。   However, when constructing a bridge girder having a multi-main girder box girder structure by the conventional span-by-span construction method, if there is only one girder for erection, between each erection diameter, It is necessary to suspend a plurality of box girder segments, place joints and introduce prestress, and it is necessary to move the girder for construction in the direction perpendicular to the bridge axis every time construction of one main girder is completed. For this reason, there is a problem that the construction period becomes very long.

一方、この場合において、複数の架設用ガーダを用いるようにすれば、ある程度の工期短縮を図ることが可能となるが、大幅な工期短縮を図ることはできず、また施工コストが高くなってしまう、という問題がある。   On the other hand, in this case, if a plurality of construction girders are used, the construction period can be shortened to some extent, but the construction period cannot be significantly shortened and the construction cost becomes high. There is a problem.

本願発明は、このような事情に鑑みてなされたものであって、スパンバイスパン工法により多径間連続橋を架設する橋梁の架設方法において、工期短縮および施工コスト低減を図ることができる橋梁の架設方法を提供することを目的とするものである。   The present invention has been made in view of such circumstances, and in a bridge erection method in which a multi-span continuous bridge is erected by a span-by-span construction method, the construction period can be shortened and the construction cost can be reduced. The purpose is to provide a construction method.

本願発明は、橋桁の構造を、所定の多主桁箱桁構造に設定した上で、架設工程を複数の径間に分散させて同時進行で施工を行い得る構成とすることにより、上記目的達成を図るようにしたものである。   The present invention achieves the above object by setting the structure of the bridge girder to a predetermined multi-main girder box girder structure and dispersing the erection process between a plurality of diameters so that construction can be performed simultaneously. It is intended to plan.

すなわち、本願発明に係る橋梁の架設方法は、
複数のプレキャストセグメントを橋軸方向に互いに隣接するように配置し、これら複数のプレキャストセグメントに橋軸方向のプレストレスを導入して一体化することにより、1径間分の橋桁を架設し、これを複数の径間に対して順次繰り返すことにより多径間連続橋を架設する、橋梁の架設方法において、
上記各径間に架設される橋桁の構造を、複数の箱桁コア部が橋軸直交方向に所定間隔をおいて配置されてなる多主桁箱桁構造に設定しておき、
架設径間の後方に位置する既設橋桁上において、1本分の箱桁コア部を構成する複数のコアセグメントを橋軸方向に互いに隣接するように配置し、これら複数のコアセグメントに橋軸方向のプレストレスを導入することにより箱桁コア部を組み立てた後、
この箱桁コア部を、上記架設径間へ移動させて、該架設径間を跨ぐように設置された架設用ガーダに吊り込み、
この架設用ガーダに吊り込まれた箱桁コア部を、上記架設径間の橋軸方向両側に位置する1対の橋脚上に吊り下ろし、
その後、この吊り下ろされた箱桁コア部を、必要に応じて橋軸直交方向に所定位置まで移動させる、ことを特徴とするものである。
That is, the bridge erection method according to the present invention is:
A plurality of precast segments are arranged so as to be adjacent to each other in the bridge axis direction, and a bridge girder for one span is constructed by introducing prestress in the bridge axis direction and integrating these precast segments. In the bridge erection method, a multi-span continuous bridge is erected by sequentially repeating for a plurality of spans.
The structure of the bridge girder constructed between each of the above diameters is set to a multi-main girder box girder structure in which a plurality of box girder core portions are arranged at predetermined intervals in the direction orthogonal to the bridge axis,
On the existing bridge girder located behind the span of installation span, a plurality of core segments composing one box girder core are arranged adjacent to each other in the bridge axis direction, and these core segments are arranged in the bridge axis direction. After assembling the box girder core by introducing the prestress of
This box girder core part is moved between the installation diameters and suspended in the installation girder installed so as to straddle the installation diameters.
The box girder core part suspended in the erection girder is suspended on a pair of bridge piers located on both sides in the bridge axis direction between the erection diameters,
Then, the suspended box girder core is moved to a predetermined position in the direction perpendicular to the bridge axis as necessary.

上記「箱桁コア部」とは、箱桁において箱形断面を囲む部分(すなわち張出し床版を含まない部分)を意味するものである。   The “box girder core portion” means a portion surrounding the box cross section in the box girder (that is, a portion not including the overhanging slab).

上記「箱桁コア部を組み立て」る際に導入されるプレストレスは、架設用ガーダへの吊り込みから橋軸直交方向への移動までの間、箱桁コア部を組立状態に維持しておくことが可能な大きさのプレストレスであれば、その具体的な大きさは特に限定されるものではない。   Prestress introduced when assembling the box girder core part keeps the box girder core part in an assembled state from the suspension to the girder for construction to the movement in the direction perpendicular to the bridge axis. The specific size is not particularly limited as long as it can be prestressed.

上記「箱桁コア部」を架設径間へ移動させる際の具体的な移動方法は特に限定されるものではなく、また、この「箱桁コア部」を架設径間において橋軸直交方向に移動させる際の具体的な移動方法についても特に限定されるものではない。   The specific movement method for moving the “box girder core” between the installation diameters is not particularly limited, and the “box girder core” is moved in the direction perpendicular to the bridge axis between the installation diameters. There are no particular restrictions on the specific movement method used for the movement.

上記構成に示すように、本願発明に係る橋梁の架設方法は、スパンバイスパン工法により多径間連続橋を架設するようになっているが、各径間に架設される橋桁の構造を、複数の箱桁コア部が橋軸直交方向に所定間隔をおいて配置されてなる多主桁箱桁構造に設定した上で、架設径間の後方に位置する既設橋桁上において、1本分の箱桁コア部を構成する複数のコアセグメントを橋軸方向に互いに隣接するように配置し、これら複数のコアセグメントに橋軸方向のプレストレスを導入することにより箱桁コア部を組み立てた後、この箱桁コア部を架設径間へ移動させて、該架設径間を跨ぐように設置された架設用ガーダに吊り込み、この架設用ガーダに吊り込まれた箱桁コア部を、架設径間の橋軸方向両側に位置する1対の橋脚上に吊り下ろし、その後、この吊り下ろされた箱桁コア部を、必要に応じて橋軸直交方向に所定位置まで移動させるようになっているので、次のような作用効果を得ることができる。   As shown in the above configuration, the bridge erection method according to the present invention is such that a multi-span continuous bridge is constructed by a span-by-span construction method, but a plurality of bridge girder structures constructed between each diameter are provided. The box girder core is set to a multi-main girder box girder structure with a predetermined interval in the direction orthogonal to the bridge axis, and one box is placed on the existing bridge girder located behind the span of span. After assembling the box girder core portion by arranging a plurality of core segments constituting the girder core portion so as to be adjacent to each other in the bridge axis direction and introducing prestress in the bridge axis direction to the plurality of core segments. The box girder core part is moved to the span between the installation spans, suspended in the girder for installation installed so as to straddle the span of the installation span, and the box girder core part suspended in the construction girder is inserted between the installation spans. Hang on a pair of bridge piers located on both sides of the bridge axis , Then, the box girder core portion was lowered this suspension, because is adapted to move to a predetermined position as necessary to bridge axis orthogonal direction, it is possible to obtain the following effects.

すなわち、架設径間の後方に位置する既設橋桁上における箱桁コア部の組立作業と、この組立てが行われた箱桁コア部の架設径間における設置作業と、この架設径間の後方側の径間における床版施工作業とを、並行して行うことが可能となり、これにより従来のスパンバイスパン工法に比して工期を大幅に短縮することができる。   That is, the assembling work of the box girder core part on the existing bridge girder located behind the span of the installation diameter, the installation work between the installation diameters of the box girder core part where this assembly was performed, and the rear side between the installation diameters It is possible to carry out the floor slab construction work in the span in parallel, which can significantly shorten the construction period compared to the conventional span-by-span construction method.

しかも、本願発明において用いられる架設用ガーダは、従来のように多主桁箱桁構造を構成する各箱桁の全体ではなく、その箱桁コア部のみを吊り込むことができれば足りるので、従来のスパンバイスパン工法(図9参照)のように、架設径間の後方に位置する既設橋桁上から供給される箱桁セグメントを、架設用ガーダの支柱間を通すために横向きにする必要がなく、したがって架設用ガーダに吊り込んだ箱桁セグメントを90°回転させる必要もなくなる。このため、架設用ガーダの構成を簡素化することができるとともに施工性を一層向上させることができる。   Moreover, the girder for erection used in the invention of the present application is not limited to the whole of each box girder constituting the multi-main girder box girder structure as in the prior art. Like the span-by-span construction method (see Fig. 9), the box girder segment supplied from the existing bridge girder located behind the span of the span does not need to be turned sideways to pass between the struts of the girder for construction. Therefore, it is not necessary to rotate the box girder segment suspended in the erection girder by 90 °. For this reason, the construction of the girder for installation can be simplified and the workability can be further improved.

また本願発明においては、架設用ガーダを橋軸直交方向へ移動させる必要がないので、この点においても架設用ガーダの構成を簡素化することができ、これにより施工コスト低減を図ることができる。   In the present invention, since it is not necessary to move the girder for installation in the direction orthogonal to the bridge axis, the construction of the girder for installation can be simplified in this respect, and the construction cost can be reduced.

このように本願発明によれば、スパンバイスパン工法により多径間連続橋を架設する橋梁の架設方法において、工期短縮および施工コスト低減を図ることができる。   As described above, according to the present invention, the construction period can be shortened and the construction cost can be reduced in the bridge construction method for constructing the multi-span continuous bridge by the span-by-span construction method.

上述したように本願発明においては、橋桁における床版の施工を、架設径間よりも後方側の径間において行うことが可能となるが、その際、床版の箱桁コア部相互間に位置する部分の施工を、これら箱桁コア部間に複数のプレキャスト板を架け渡した状態で、これらプレキャスト板の上にコンクリートを打設することにより行うようにすれば、床版の施工を効率的に行うことができる。そしてこれにより、この床版施工作業を、既設橋桁上における箱桁コア部の組立作業および架設径間における箱桁コア部の設置作業の施工サイクルに適合させることが容易に可能となる。   As described above, in the present invention, the construction of the floor slab in the bridge girder can be performed between the rear-side spans rather than the spanning spans. If the construction of the part to be performed is carried out by placing concrete on these precast plates in a state where a plurality of precast plates are bridged between the box girder core portions, the construction of the floor slab is efficient. Can be done. This makes it possible to easily adapt the floor slab construction work to the construction cycle of the assembly work of the box girder core part on the existing bridge girder and the installation work of the box girder core part between the spans.

上記構成において、箱桁コア部の架設径間への移動方法が特に限定されないことは上述したとおりであるが、この移動を、既設の箱桁コア部の上面に敷設されたレール上を走行する台車に、箱桁コア部を載置した状態で行うようにすれば、箱桁コア部の移動を効率良くかつ確実に行うことができる。   In the above configuration, as described above, the method of moving the box girder core portion between the installation diameters is not particularly limited. However, this movement is performed on a rail laid on the upper surface of the existing box girder core portion. If the box girder core part is placed on the carriage, the box girder core part can be moved efficiently and reliably.

上記構成において、架設径間の橋軸方向両側に位置する1対の橋脚の各々の上面に、橋桁の橋軸方向端部を構成する柱頭部セグメントを、そのコアセグメント相互間に横桁が形成されるようにして、それぞれ先行施工しておき、そして、架設用ガーダのガーダ本体を支持する支持する複数対の支柱の各々を、各柱頭部セグメントにおいて互いに隣接する1対の横桁の上方に位置する床版部分に設置するようにすれば、新たな支持構造を設けなくても、架設用ガーダの支持を安定的に行うことが可能となる。また、このような構成を採用することにより、架設用ガーダにおける橋軸直交方向の支柱間隔を狭くすることができるので、箱桁コア部の吊り込みに必要な架設用ガーダの強度を容易に確保することができ、これにより架設用ガーダの構成を一層簡素化することができる。   In the above configuration, the column head segment that forms the bridge axial direction end of the bridge girder is formed on the upper surface of each of the pair of bridge piers located on both sides in the bridge axial direction between the spans of the span. Each of a plurality of pairs of supporting columns that support the girder body of the erection girder is placed above a pair of cross beams adjacent to each other in each column head segment. If it is installed on the floor slab portion positioned, it is possible to stably support the erection girder without providing a new support structure. Also, by adopting such a configuration, the strut spacing in the direction perpendicular to the bridge axis in the girder for construction can be narrowed, so the strength of the girder for construction necessary for hanging the box girder core can be easily secured. Thus, the construction of the girder for installation can be further simplified.

なお、このように架設用ガーダの支柱間隔を狭くしても、この架設用ガーダは箱桁全体ではなくその箱桁コア部のみを吊り込むことができれば足りるので、その吊込み作業を何ら支障なく行うことが可能である。   Even if the strut spacing of the girder for installation is reduced in this way, it is sufficient that the girder for construction can suspend only the box girder core part instead of the whole box girder, so that the hangering work is not hindered. Is possible.

以下、図面を用いて、本願発明の実施の形態について説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

図1は、本願発明の一実施形態に係る橋梁の架設方法の概要を示す工程図であって、架設途中の多径間連続橋10を橋軸直交方向から見て示す側面図である。   FIG. 1 is a process diagram showing an outline of a bridge erection method according to an embodiment of the present invention, and is a side view showing a multi-span continuous bridge 10 in the middle of erection as seen from the direction orthogonal to the bridge axis.

また、図2、3は、この架設途中の多径間連続橋10を橋軸直交断面で示す図であって、図2(a)が図1のIIa-IIa
線断面図、図2(b)が図1のIIb-IIb 線断面図、図2(c)が図1のIIc-IIc 線断面図であり、図3が、図1のIII-III 線断面図である。そして、図4は、図3のIV方向矢視図である。
2 and 3 are views showing the multi-span continuous bridge 10 in the middle of the construction in a cross-section perpendicular to the bridge axis, and FIG. 2 (a) is IIa-IIa of FIG.
2B is a sectional view taken along line IIb-IIb in FIG. 1, FIG. 2C is a sectional view taken along line IIc-IIc in FIG. 1, and FIG. 3 is a sectional view taken along line III-III in FIG. FIG. FIG. 4 is a view in the direction of arrows IV in FIG.

さらに、図5〜8は、図1の(a)〜(d)の各々の工程を示す斜視図である。   Further, FIGS. 5 to 8 are perspective views showing respective steps of FIGS. 1 (a) to (d).

これらの図に示すように、本実施形態においては、スパンバイスパン工法により多径間連続橋10を架設するようになっている。   As shown in these drawings, in this embodiment, the multi-span continuous bridge 10 is constructed by a span-by-span method.

本実施形態の架設方法について説明する前に、その架設対象となる多径間連続橋10の構成について説明する。   Before describing the erection method of the present embodiment, the configuration of the multi-span continuous bridge 10 to be erected will be described.

この多径間連続橋10は、各径間の支間長が40m程度の連続橋であって、その各径間に架設される橋桁12の構造として、複数(具体的には4つ)の箱桁コア部14が橋軸直交方向に所定間隔をおいて配置されてなる多主桁箱桁構造が採用されている。   The multi-span continuous bridge 10 is a continuous bridge having a span length of about 40 m between the spans. As a structure of the bridge girder 12 constructed between the spans, a plurality of (specifically, four) boxes are used. A multi-main girder box girder structure in which the girder core portions 14 are arranged at predetermined intervals in the direction perpendicular to the bridge axis is employed.

図2に示すように、この橋桁12においては、その4つの箱桁コア部14により床版の一部が構成されている。すなわち、これら各箱桁コア部14相互間の上端部に、中間床版16が各箱桁コア部14と面一で形成されるとともに、橋軸直交方向両側に位置する各箱桁コア部14の橋軸直交方向外側の上端部に、張出し床版18が各箱桁コア部14と面一で形成されている。その際、中間床版16の施工は、互いに隣接する1対の箱桁コア部14間に複数のプレキャスト板20を架け渡した状態で、これらプレキャスト板20の上にコンクリート22を打設することにより行われている。一方、張出し床版18は、場所打ちでコンクリートを打設することにより行われている。   As shown in FIG. 2, in the bridge girder 12, a part of the floor slab is constituted by the four box girder core portions 14. That is, the intermediate floor slab 16 is formed flush with the box girder core portions 14 at the upper end portions between the box girder core portions 14, and the box girder core portions 14 positioned on both sides of the bridge axis orthogonal direction. An overhanging slab 18 is formed flush with each box girder core portion 14 at the upper end portion on the outer side in the direction perpendicular to the bridge axis. At that time, the intermediate floor slab 16 is constructed by placing concrete 22 on the precast plates 20 in a state where a plurality of precast plates 20 are bridged between a pair of box girder core portions 14 adjacent to each other. It is done by. On the other hand, the overhanging slab 18 is formed by placing concrete by cast-in-place.

また、図3、4に示すように、多径間連続橋10における各橋脚30上には、橋桁12の橋軸方向端部を構成する柱頭部セグメント32が、支承50を介して配置されている。この柱頭部セグメント32は、4つの箱桁コア部14の各々に対応する位置に形成された箱形断面形状を有するコアセグメント34と、これら各コアセグメント34相互間に形成された横桁36と、これら各コアセグメント34相互間において横桁36の上端部に、これら各コアセグメント34と面一で形成された中間床版38と、橋軸直交方向両側に位置する各コアセグメント34の橋軸直交方向外側の上端部に、これら各コアセグメント34と面一で形成された張出し床版40とからなっている。   Further, as shown in FIGS. 3 and 4, a column head segment 32 constituting the bridge axial direction end portion of the bridge girder 12 is arranged via a support 50 on each pier 30 in the multi-span continuous bridge 10. Yes. The column head segment 32 includes a core segment 34 having a box-shaped cross-sectional shape formed at a position corresponding to each of the four box girder core portions 14, and a cross beam 36 formed between the core segments 34. The intermediate floor slab 38 formed flush with the core segments 34 at the upper ends of the cross beams 36 between the core segments 34 and the bridge shafts of the core segments 34 located on both sides of the bridge axis orthogonal direction. At the upper end portion on the outer side in the orthogonal direction, these core segments 34 and an extended floor slab 40 formed flush with each other are formed.

以下の説明において、4つの箱桁コア部14を区別する必要がある場合には、これら各箱桁コア部14を、図2において左側から順に、箱桁コア部14A、14B、14C、14Dと称することとする。   In the following description, when it is necessary to distinguish the four box girder core parts 14, these box girder core parts 14 are respectively arranged in order from the left side in FIG. 2 as box girder core parts 14A, 14B, 14C, 14D. I will call it.

本実施形態においては、これら4つの箱桁コア部14を、箱桁コア部14A、14B、14D、14Cの順で架設するようになっている。なお、箱桁コア部14Bと箱桁コア部14Dとの架設順序を入れ替えるようにしてもよい。   In this embodiment, these four box girder core parts 14 are constructed in the order of box girder core parts 14A, 14B, 14D, and 14C. In addition, you may make it replace the construction order of box girder core part 14B and box girder core part 14D.

まず、1番目に架設される箱桁コア部14Aについて、その架設工程の概要を説明する。   First, the outline of the erection process is demonstrated about the box girder core part 14A erected first.

図1(a)および図5に示すように、架設径間S0の後方に位置する既設橋桁上において、1本分の箱桁コア部14Aを構成する複数(具体的には12個)のコアセグメント24を橋軸方向に互いに隣接するように配置し、接着剤を介して互いに密着させた後、これら複数のコアセグメント24に橋軸方向のプレストレスを導入することにより箱桁コア部14Aを組み立てる。このプレストレス導入は、これら複数のコアセグメント24に対して、橋軸方向に延びる内ケーブル(図示せず)を配置し、この内ケーブルを緊張することにより行う。   As shown in FIGS. 1 (a) and 5, a plurality (specifically, twelve) of cores constituting one box girder core portion 14A on an existing bridge girder located behind the span S0. The segments 24 are arranged so as to be adjacent to each other in the bridge axis direction, are brought into close contact with each other via an adhesive, and then the prestress in the bridge axis direction is introduced into the plurality of core segments 24 to thereby form the box girder core portion 14A. assemble. The prestress is introduced by arranging an inner cable (not shown) extending in the bridge axis direction with respect to the plurality of core segments 24 and tensioning the inner cable.

そして、この箱桁コア部14Aを、架設径間S0へ移動させて、この架設径間S0を跨ぐように設置された架設用ガーダ110に吊り込む。その後、この架設用ガーダ110に吊り込まれた箱桁コア部14Aを、架設径間S0の橋軸方向両側に位置する1対の橋脚30上に吊り下ろし、この吊り下ろされた箱桁コア部14Aを、橋軸直交方向に所定位置(すなわち図3において左から1番目の位置)まで移動させる。   Then, the box girder core portion 14A is moved to the span between spans S0 and is hung on the span girder 110 installed so as to straddle the span between spans S0. Thereafter, the box girder core portion 14A suspended in the erection girder 110 is suspended on a pair of bridge piers 30 located on both sides of the span span S0 in the bridge axis direction, and the suspended girder core portion is suspended. 14A is moved to a predetermined position (that is, the first position from the left in FIG. 3) in the direction orthogonal to the bridge axis.

この箱桁コア部14Aの移動および架設を行うのと並行して、架設径間S0の後方に位置する既設橋桁上では、複数のコアセグメント24を配置して、2番目に架設される箱桁コア部14Bの組立てを行う。   In parallel with the movement and erection of the box girder core part 14A, a plurality of core segments 24 are arranged on the existing bridge girder located behind the erection span S0, and the box girder installed second. The core part 14B is assembled.

図1(b)および図6に示すように、この2番目に架設される箱桁コア部14Bについても、箱桁コア部14Aと同様にして、その組立て、移動および架設を行う。   As shown in FIG. 1B and FIG. 6, the second girder core portion 14B to be erected is assembled, moved and erected in the same manner as the box girder core portion 14A.

以下、同様にして、3番目、4番目に架設される箱桁コア部14D、14Cについても、箱桁コア部14Aと同様にして、その組立て、移動および架設を行う。   Similarly, the third, fourth box girder core portions 14D, 14C are assembled, moved, and installed in the same manner as the box girder core portion 14A.

上記架設工程において、各箱桁コア部14の架設径間S0への移動は、架設径間S0の後方側に敷設されたレール112上を走行する前後1対の台車114に箱桁コア部14を載置した状態で行う。その際、このレール112は、既設橋桁上における箱桁コア部14Cの位置から架設径間S0の後方側に隣接する後方側径間S−1に架設された箱桁コア部14Cの上面の前端位置まで延びるように敷設しておく。   In the above-described erection process, the box girder core portion 14 is moved to the pair of front and rear carriages 114 that run on the rail 112 laid on the rear side of the erection span S0. Is carried out with the At this time, the rail 112 is connected to the front end of the upper surface of the box girder core portion 14C installed in the rear span S-1 adjacent to the rear side of the span span S0 from the position of the box girder core portion 14C on the existing bridge girder. Lay it up to the position.

また、上記架設工程において、架設径間S0の後方に位置する既設橋桁上における箱桁コア部14の組立ては、レール112を覆うようにして既設橋桁上に固定設置された架台116上において行う。   In the erection process, the box girder core 14 is assembled on the existing bridge girder positioned on the rear side of the erection span S0 on the pedestal 116 fixedly installed on the existing bridge girder so as to cover the rail 112.

上記架設工程において、架設径間S0の橋軸方向両側に位置する1対の橋脚30上に吊り下ろされた箱桁コア部14の橋軸直交方向への移動を円滑に行い得るようにするため、図3、4に示すように、これら各橋脚30の上端面における架設径間S0側の端部に、橋軸直交方向に延びる仮受け架台118を設置しておき、この仮受け架台118に箱桁コア部14を吊り下ろして、この仮受け架台118の上面をスライドさせるようにして所定位置まで箱桁コア部14を移動させる。その際、仮受け架台118は、橋脚30の上端面に設置された橋桁12の支承50と略同じ高さになるように調整しておく。また、図5、6に示すように、架設径間S0における各橋脚30の近傍には、箱桁コア部14の吊り下ろしおよび横移動の作業を行うための足場130を設置しておく。   In the above erection process, the box girder core portion 14 suspended on the pair of bridge piers 30 located on both sides of the bridge span S0 in the bridge axis direction can be smoothly moved in the bridge axis orthogonal direction. As shown in FIGS. 3 and 4, a temporary support base 118 extending in a direction orthogonal to the bridge axis is installed at the end of the bridge span S0 side at the upper end surface of each pier 30, and the temporary support base 118 is attached to the temporary support base 118. The box girder core unit 14 is suspended, and the box girder core unit 14 is moved to a predetermined position by sliding the upper surface of the temporary support base 118. At that time, the temporary support base 118 is adjusted so as to be substantially the same height as the support 50 of the bridge girder 12 installed on the upper end surface of the pier 30. As shown in FIGS. 5 and 6, a scaffold 130 for performing the hanging and lateral movement work of the box girder core portion 14 is installed in the vicinity of each pier 30 in the span span S <b> 0.

なお、箱桁コア部14A以外に橋軸直交方向への移動が必要となる2つの箱桁コア部14B、14Dについては、仮受け架台118の上面をスライドさせて、所定位置(すなわち図3において左から2番目、4番目の位置)まで移動させるが、箱桁コア部14Cについては、仮受け架台118への吊り下ろしまでを行う。   In addition to the box girder core portion 14A, for the two box girder core portions 14B and 14D that require movement in the direction perpendicular to the bridge axis, the upper surface of the temporary support base 118 is slid to a predetermined position (that is, in FIG. 3). 2nd and 4th positions from the left), but the box girder core portion 14C is suspended from the temporary support base 118.

以上の架設工程により、4つの箱桁コア部14の架設が完了したら、図1(c)および図7に示すように、架設用ガーダ110を架設径間S0の前方側に隣接する前方側径間S+1へ移動させ、この前方側径間S+1を新たな架設径間として、4つの箱桁コア部14について同様の架設を行う。   When the installation of the four box girder core portions 14 is completed by the above installation process, as shown in FIG. 1 (c) and FIG. 7, the installation girder 110 has a front side diameter adjacent to the front side of the installation span S0. The four box girder cores 14 are installed in the same manner with the front side gap S + 1 as a new installation gap.

一方、架設用ガーダ110が前方側径間S+1へ移動した後の架設径間S0においては、各箱桁コア部14の橋軸方向両端部の目地42にコンクリートを打設した後、これら各箱桁コア部14を構成する複数のコアセグメント24に橋軸方向のプレストレスを導入して一体化することにより、各箱桁コア部14の架設を完了させる。このプレストレス導入は、各箱桁コア部14に沿って配置された橋軸方向に延びる外ケーブル44を緊張することにより行う。   On the other hand, in the construction span S0 after the construction girder 110 has moved to the front span S + 1, after placing concrete on the joints 42 at both ends in the bridge axis direction of each box girder core portion 14, each of these boxes Installation of each box girder core portion 14 is completed by introducing prestress in the bridge axis direction and integrating the plurality of core segments 24 constituting the girder core portion 14. This pre-stress is introduced by tensioning the outer cable 44 extending along the bridge axis direction disposed along each box girder core portion 14.

また、このとき、後方側径間S−1においては、中間床版16の施工の一部として、互いに隣接する1対の箱桁コア部14間に複数のプレキャスト板20を架け渡す。   At this time, in the rear side span S-1, as a part of the construction of the intermediate floor slab 16, a plurality of precast plates 20 are bridged between a pair of box girder core portions 14 adjacent to each other.

その後、図1(d)および図8に示すように、この後方側径間S−1において、中間床版16の施工の残部として、互いに隣接する1対の箱桁コア部14間に架け渡された複数のプレキャスト板20の上にコンクリート22を打設するとともに、橋軸直交方向両側に位置する各箱桁コア部14の橋軸直交方向外側において、場所打ちで張出し床版18の施工を行う。   Thereafter, as shown in FIGS. 1 (d) and 8, spanning between the pair of box girder core portions 14 adjacent to each other as the remainder of the construction of the intermediate floor slab 16 in the rear side span S-1. Concrete 22 is placed on the plurality of precast plates 20 formed, and the floor slab 18 is constructed by cast-in-place on the outside of each box girder core portion 14 located on both sides in the direction orthogonal to the bridge axis. Do.

上記架設工程において用いられる架設用ガーダ110は、図3に示すように、橋軸方向に延びる1対のガーダ本体120と、これら1対のガーダ本体120を橋軸方向の2箇所において支持する支柱122と、これら1対のガーダ本体120の先端部に取り付けられた先端支柱124と、橋軸方向の2箇所においてこれら1対のガーダ本体120に架け渡された可動梁126と、これら各可動梁126に上端部が支持された吊り具128とからなっている。   As shown in FIG. 3, the girder 110 for erection used in the erection process includes a pair of girder main bodies 120 extending in the bridge axis direction, and struts that support the pair of girder main bodies 120 at two locations in the bridge axis direction. 122, a tip post 124 attached to the tip of the pair of girder main bodies 120, a movable beam 126 laid over the pair of girder main bodies 120 at two locations in the bridge axis direction, and each of these movable beams A lifting tool 128 having an upper end supported by 126 is formed.

そして本実施形態においては、この架設用ガーダ110を架設径間S0を跨ぐように設置する際、その前後1対の支柱122の各々を、架設径間S0の橋軸方向両側に位置する各柱頭部セグメント32において、箱桁コア部14Cに対応する位置に形成されたコアセグメント34に隣接する1対の横桁36の上方に位置する中間床版38に設置するようにする。   And in this embodiment, when installing this installation girder 110 so that straddle span S0 may be straddled, each of the pair of pillars 122 before and after that is located on each side of the bridge span in the span span S0. In the part segment 32, it installs in the intermediate | middle floor slab 38 located above a pair of cross girder 36 adjacent to the core segment 34 formed in the position corresponding to the box girder core part 14C.

以上詳述したように、本実施形態に係る橋梁の架設方法は、スパンバイスパン工法により多径間連続橋10を架設するようになっているが、各径間に架設される橋桁12の構造を、複数の箱桁コア部14が橋軸直交方向に所定間隔をおいて配置されてなる多主桁箱桁構造に設定した上で、架設径間S0の後方に位置する既設橋桁上において、1本分の箱桁コア部14を構成する複数のコアセグメント24を橋軸方向に互いに隣接するように配置し、これら複数のコアセグメント24に橋軸方向のプレストレスを導入することにより箱桁コア部14を組み立てた後、この箱桁コア部14を架設径間S0へ移動させて、該架設径間S0を跨ぐように設置された架設用ガーダ110に吊り込み、この架設用ガーダ110に吊り込まれた箱桁コア部14を、架設径間S0の橋軸方向両側に位置する1対の橋脚上に吊り下ろし、その後、この吊り下ろされた箱桁コア部14を、必要に応じて橋軸直交方向に所定位置まで移動させるようになっているので、次のような作用効果を得ることができる。   As described in detail above, the bridge erection method according to the present embodiment is such that the multi-span continuous bridge 10 is erected by the span-by-span method, but the structure of the bridge girder 12 erected between the respective diameters. Is set on a multi-main girder box girder structure in which a plurality of box girder core portions 14 are arranged at a predetermined interval in the direction perpendicular to the bridge axis, and on the existing bridge girder located behind the span span S0, A plurality of core segments 24 constituting one box girder core portion 14 are arranged so as to be adjacent to each other in the bridge axis direction, and prestress in the bridge axis direction is introduced into the plurality of core segments 24 to thereby form a box girder. After assembling the core part 14, the box girder core part 14 is moved to the spanning span S <b> 0 and suspended on the spanning girder 110 that is installed across the spanning span S <b> 0. Suspended box girder core 1 Are suspended on a pair of bridge piers located on both sides in the bridge axis direction of the span span S0, and then the suspended box girder core portion 14 is moved to a predetermined position in the direction perpendicular to the bridge axis as necessary. Therefore, the following effects can be obtained.

すなわち、架設径間S0の後方に位置する既設橋桁上における箱桁コア部14の組立作業と、この組立てが行われた箱桁コア部14の架設径間S0における設置作業と、この架設径間S0の後方側に隣接する後方側径間S−1における床版施工作業とを、並行して行うことが可能となり、これにより従来のスパンバイスパン工法に比して工期を大幅に短縮することができる。   That is, the assembling work of the box girder core portion 14 on the existing bridge girder located behind the span of span S0, the installation work of the box girder core portion 14 having been assembled in the span of span S0, and this span of span It is possible to perform the floor slab construction work in the rear side span S-1 adjacent to the rear side of S0 in parallel, thereby significantly shortening the construction period compared to the conventional span-by-span construction method. Can do.

しかも、本実施形態において用いられる架設用ガーダ110は、従来のように多主桁箱桁構造を構成する各箱桁の全体ではなく、その箱桁コア部14のみを吊り込むことができれば足りるので、従来のスパンバイスパン工法(図9参照)のように、架設径間の後方に位置する既設橋桁上から供給される箱桁セグメントを、架設用ガーダの支柱間を通すために横向きにする必要がなく、したがって架設用ガーダに吊り込んだ箱桁セグメントを90°回転させる必要もなくなる。このため、架設用ガーダの構成を簡素化することができるとともに施工性を一層向上させることができる。   Moreover, the erection girder 110 used in the present embodiment only needs to be able to suspend only the box girder core portion 14 instead of the entire box girder constituting the multi-main girder box girder structure as in the prior art. As in the conventional span-by-span construction method (see Fig. 9), the box girder segment supplied from the existing bridge girder located behind the span of the span must be placed sideways to pass between the struts of the girder for construction. Therefore, it is not necessary to rotate the box girder segment suspended in the erection girder by 90 °. For this reason, the construction of the girder for installation can be simplified and the workability can be further improved.

また本実施形態においては、架設用ガーダ110を橋軸直交方向へ移動させる必要がないので、この点においても架設用ガーダ110の構成を簡素化することができ、これにより施工コスト低減を図ることができる。   Moreover, in this embodiment, since it is not necessary to move the construction girder 110 in the direction orthogonal to the bridge axis, the construction of the construction girder 110 can be simplified in this respect as well, thereby reducing the construction cost. Can do.

このように本実施形態によれば、スパンバイスパン工法により多径間連続橋10を架設する橋梁の架設方法において、工期短縮および施工コスト低減を図ることができる。   As described above, according to the present embodiment, the construction period can be shortened and the construction cost can be reduced in the bridge construction method for constructing the multi-span continuous bridge 10 by the span-by-span construction method.

本実施形態においては、橋桁12における中間床版16および張出し床版18の施工を、後方側径間S−1において行うようになっているが、その際、箱桁コア部14相互間に位置する中間床版16の施工を、これら箱桁コア部14間に複数のプレキャスト板20を架け渡した状態で、これらプレキャスト板20の上にコンクリート22を打設することにより行うようになっているので、中間床版16および張出し床版18の施工を効率的に行うことができる。そしてこれにより、この床版施工作業を、既設橋桁上における箱桁コア部14の組立作業および架設径間S0における箱桁コア部14の設置作業の施工サイクルに適合させることが容易に可能となる。   In the present embodiment, the construction of the intermediate floor slab 16 and the overhanging floor slab 18 in the bridge girder 12 is performed at the rear side span S-1, but at this time, the position between the box girder core portions 14 is determined. The intermediate floor slab 16 is constructed by placing concrete 22 on the precast plates 20 in a state where a plurality of precast plates 20 are bridged between the box girder core portions 14. Therefore, the construction of the intermediate floor slab 16 and the overhanging floor slab 18 can be performed efficiently. And it becomes possible easily to adapt this floor slab construction work to the construction cycle of the assembly work of the box girder core part 14 on the existing bridge girder and the installation work of the box girder core part 14 in the span span S0. .

また本実施形態においては、箱桁コア部14の架設径間S0への移動を、既設の箱桁コア部14Cの上面に敷設されたレール112上を走行する台車114に、箱桁コア部14を載置した状態で行うようになっているので、箱桁コア部14の移動を効率良くかつ確実に行うことができる。   Further, in this embodiment, the movement of the box girder core portion 14 to the span span S0 is transferred to the carriage 114 running on the rail 112 laid on the upper surface of the existing box girder core portion 14C. Since the box girder core portion 14 can be moved efficiently and reliably.

さらに本実施形態においては、架設径間S0の橋軸方向両側に位置する1対の橋脚30の各々の上面に、橋桁12の橋軸方向端部を構成する柱頭部セグメント32を、そのコアセグメント34相互間に横桁36が形成されるようにして、それぞれ先行施工しておき、そして、架設用ガーダ110を支持する複数対の支柱122の各々を、架設径間S0の橋軸方向両側に位置する各柱頭部セグメント32において、箱桁コア部14Cに対応する位置に形成されたコアセグメント34に隣接する1対の横桁36の上方に位置する中間床版38に設置するようになっているので、新たな支持構造を設けなくても、架設用ガーダ110の支持を安定的に行うことが可能となる。また、このような構成を採用することにより、架設用ガーダ110における橋軸直交方向の支柱間隔を狭くすることができるので、箱桁コア部14の吊り込みに必要な架設用ガーダ110の強度を容易に確保することができ、これにより架設用ガーダ110の構成を一層簡素化することができる。   Furthermore, in the present embodiment, the column head segment 32 constituting the bridge axial direction end portion of the bridge girder 12 is provided on the upper surface of each of the pair of bridge piers 30 positioned on both sides in the bridge axial direction of the span span S0. 34, each of the plurality of pairs of columns 122 supporting the girder 110 for installation is placed on both sides of the spanning span S0 in the bridge axis direction. In each column head segment 32 positioned, it is installed on an intermediate floor slab 38 positioned above a pair of cross beams 36 adjacent to a core segment 34 formed at a position corresponding to the box beam core portion 14C. Therefore, it is possible to stably support the erection girder 110 without providing a new support structure. Further, by adopting such a configuration, it is possible to reduce the interval between the columns in the bridge girder orthogonal direction in the erection girder 110, so that the strength of the erection girder 110 necessary for hanging the box girder core portion 14 is increased. This can be ensured easily, whereby the construction of the erection girder 110 can be further simplified.

なお、このように架設用ガーダ110の支柱間隔を狭くしても、この架設用ガーダ110は箱桁全体ではなくその箱桁コア部14のみを吊り込むことができれば足りるので、その吊込み作業を何ら支障なく行うことが可能である。   Even if the strut spacing of the erection girder 110 is reduced in this way, it is sufficient that the erection girder 110 can suspend only the box girder core portion 14 instead of the entire box girder. This can be done without any problem.

上記実施形態においては、架設対象となる多径間連続橋10が、その各径間に架設される橋桁12として、4つの箱桁コア部14を備えた構成となっているものとして説明したが、2つまたは3つの箱桁コア部14を備えた構成となっている場合、あるいは5つ以上の箱桁コア部14を備えた構成となっている場合においても、上記実施形態と同様の架設方法を採用することにより上記実施形態と同様の作用効果を得ることができる。ただし、箱桁コア部14が2つの場合には、柱頭部セグメント32における各コアセグメント34の両側に横桁36が形成された構成とはならないので、架設用ガーダ110の支柱122を設置するための構造を橋脚30上に新たに設けることが必要となる。   In the said embodiment, although the multi-span continuous bridge 10 used as construction object was demonstrated as what was equipped with the four box girder core parts 14 as the bridge girder 12 constructed between each diameter. The same construction as in the above embodiment also in the case of a configuration with two or three box girder core portions 14 or in the case of a configuration with five or more box girder core portions 14 By adopting the method, it is possible to obtain the same effects as those of the above embodiment. However, in the case where there are two box girder core portions 14, the structure is not formed in which the cross beams 36 are formed on both sides of each core segment 34 in the column head segment 32, so that the support column 122 of the erection girder 110 is installed. It is necessary to newly provide this structure on the pier 30.

なお、上記実施形態において諸元として示した数値は一例にすぎず、これらを適宜異なる値に設定してもよいことはもちろんである。   In addition, the numerical value shown as a specification in the said embodiment is only an example, and of course, you may set these to a different value suitably.

本願発明の一実施形態に係る橋梁の架設方法の概要を示す工程図であって、架設途中の多径間連続橋を橋軸直交方向から見て示す側面図BRIEF DESCRIPTION OF THE DRAWINGS It is process drawing which shows the outline | summary of the construction method of the bridge which concerns on one Embodiment of this invention, Comprising: The side view which sees the multi span continuous bridge in the middle of construction seen from a bridge axis orthogonal direction 上記架設途中の多径間連続橋を橋軸直交断面で示す図であって、同図(a)は図1のIIa-IIa線断面図、同図(b)は図1のIIb-IIb 線断面図、同図(c)は図1のIIc-IIc 線断面図FIG. 2 is a diagram showing a multi-span continuous bridge in the middle of the construction in a cross section perpendicular to the bridge axis, in which FIG. (A) is a sectional view taken along line IIa-IIa in FIG. 1, and FIG. Sectional view, (c) is a sectional view taken along line IIc-IIc in FIG. 上記架設途中の多径間連続橋を橋軸直交断面で示す、図1のIII-III 線断面図Sectional view taken along the line III-III in Fig. 1, showing the multi-span continuous bridge in the middle of the construction in a cross section perpendicular to the bridge axis 図3のIV方向矢視図IV direction arrow view of FIG. 図1(a)の工程を示す斜視図The perspective view which shows the process of Fig.1 (a) 図1(b)の工程を示す斜視図The perspective view which shows the process of FIG.1 (b). 図1(c)の工程を示す斜視図The perspective view which shows the process of FIG.1 (c). 図1(d)の工程を示す斜視図A perspective view showing the process of FIG. 従来例を示す、図1と同様の図Figure similar to Figure 1 showing a conventional example

符号の説明Explanation of symbols

10 多径間連続橋
12 橋桁
14、14A、14B、14C、14D 箱桁コア部
16、38 中間床版
18、40 張出し床版
20 プレキャスト板
22 コンクリート
24、34 コアセグメント
30 橋脚
32 柱頭部セグメント
36 横桁
42 目地
44 外ケーブル
50 支承
110 架設用ガーダ
112 レール
114 台車
116 架台
118 仮受け架台
120 ガーダ本体
122 支柱
124 先端支柱
126 可動梁
128 吊り具
130 足場
S0 架設径間
S+1 前方側径間
S−1 後方側径間
10 Multi-span continuous bridge 12 Bridge girder 14, 14A, 14B, 14C, 14D Box girder core part 16, 38 Intermediate floor slab 18, 40 Overhang slab 20 Precast plate 22 Concrete 24, 34 Core segment 30 Bridge pier 32 Column head segment 36 Cross girder 42 Joint 44 Outer cable 50 Bearing 110 Girder for installation 112 Rail 114 Dolly 116 Drawer 116 Pedestal 118 Temporary receiving stand 120 Girder main body 122 Support column 124 Tip column 126 Movable beam 128 Lifting tool 130 Scaffolding S0 Installation span S + 1 Front side span S- 1 Between rear side

Claims (4)

複数のプレキャストセグメントを橋軸方向に互いに隣接するように配置し、これら複数のプレキャストセグメントに橋軸方向のプレストレスを導入して一体化することにより、1径間分の橋桁を架設し、これを複数の径間に対して順次繰り返すことにより多径間連続橋を架設する、橋梁の架設方法において、
上記各径間に架設される橋桁の構造を、複数の箱桁コア部が橋軸直交方向に所定間隔をおいて配置されてなる多主桁箱桁構造に設定しておき、
架設径間の後方に位置する既設橋桁上において、1本分の箱桁コア部を構成する複数のコアセグメントを橋軸方向に互いに隣接するように配置し、これら複数のコアセグメントに橋軸方向のプレストレスを導入することにより箱桁コア部を組み立てた後、
この箱桁コア部を、上記架設径間へ移動させて、該架設径間を跨ぐように設置された架設用ガーダに吊り込み、
この架設用ガーダに吊り込まれた箱桁コア部を、上記架設径間の橋軸方向両側に位置する1対の橋脚上に吊り下ろし、
その後、この吊り下ろされた箱桁コア部を、必要に応じて橋軸直交方向に所定位置まで移動させる、ことを特徴とする橋梁の架設方法。
A plurality of precast segments are arranged so as to be adjacent to each other in the bridge axis direction, and a prestress in the bridge axis direction is introduced into and integrated with the plurality of precast segments to construct a bridge girder for one span. In the bridge erection method, a multi-span continuous bridge is erected by sequentially repeating for a plurality of spans.
The structure of the bridge girder constructed between the above-mentioned diameters is set to a multi-main girder box girder structure in which a plurality of box girder core parts are arranged at predetermined intervals in the direction orthogonal to the bridge axis,
On the existing bridge girder located behind the span of installation span, a plurality of core segments constituting one box girder core portion are arranged adjacent to each other in the bridge axis direction, and these core segments are arranged in the bridge axis direction. After assembling the box girder core by introducing the prestress of
This box girder core part is moved between the installation diameters and suspended in the installation girder installed so as to straddle the installation diameters.
The box girder core part suspended in the erection girder is suspended on a pair of bridge piers located on both sides in the bridge axis direction between the erection diameters,
Then, the suspended bridge girder core is moved to a predetermined position in the direction perpendicular to the bridge axis as necessary, and a bridge erection method is provided.
上記橋桁における床版の施工を、上記架設径間よりも後方側の径間において行い、
その際、上記床版の上記箱桁コア部相互間に位置する部分の施工を、これら箱桁コア部間に複数のプレキャスト板を架け渡した状態で、これらプレキャスト板の上にコンクリートを打設することにより行う、ことを特徴とする請求項1記載の橋梁の架設方法。
Construction of the floor slab in the bridge girder is performed between the rear spans rather than the span between the spans,
At that time, the construction of the part located between the box girder core parts of the floor slab is placed on the precast board with a plurality of precast boards laid between the box girder core parts. The bridge erection method according to claim 1, wherein the bridge erection method is performed.
上記箱桁コア部の上記架設径間への移動を、既設の箱桁コア部の上面に敷設されたレール上を走行する台車に、上記箱桁コア部を載置した状態で行う、ことを特徴とする請求項1または2記載の橋梁の架設方法。   The movement of the box girder core part between the installation diameters is performed in a state where the box girder core part is placed on a carriage that runs on a rail laid on the upper surface of the existing box girder core part. The method for laying a bridge according to claim 1 or 2, characterized in that: 上記架設径間の橋軸方向両側に位置する1対の橋脚の各々の上面に、上記橋桁の橋軸方向端部を構成する柱頭部セグメントを、該柱頭部セグメントにおけるコアセグメント相互間に横桁が形成されるようにして、それぞれ先行施工しておき、
上記架設用ガーダのガーダ本体を支持する複数対の支柱の各々を、上記各柱頭部セグメントにおいて互いに隣接する1対の横桁の上方に位置する床版部分に設置する、ことを特徴とする請求項1〜3いずれか記載の橋梁の架設方法。
A column head segment constituting a bridge axis direction end portion of the bridge girder is disposed on the upper surface of each of the pair of bridge piers positioned on both sides in the bridge axis direction between the installation spans. Are pre-constructed so that
The plurality of pairs of columns supporting the girder main body of the erection girder are installed on a floor slab portion located above a pair of cross beams adjacent to each other in each column head segment. Item 4. A method for laying a bridge according to any one of items 1 to 3.
JP2007144199A 2007-05-30 2007-05-30 How to build a bridge Active JP4937838B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007144199A JP4937838B2 (en) 2007-05-30 2007-05-30 How to build a bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007144199A JP4937838B2 (en) 2007-05-30 2007-05-30 How to build a bridge

Publications (2)

Publication Number Publication Date
JP2008297777A true JP2008297777A (en) 2008-12-11
JP4937838B2 JP4937838B2 (en) 2012-05-23

Family

ID=40171539

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007144199A Active JP4937838B2 (en) 2007-05-30 2007-05-30 How to build a bridge

Country Status (1)

Country Link
JP (1) JP4937838B2 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864734A (en) * 2010-06-28 2010-10-20 中铁二局股份有限公司 Cross sliding type erecting method for separated box girder of high speed railway
CN104594190A (en) * 2015-02-16 2015-05-06 西安公路研究院 Bridge seamless telescopic device and construction method of device
CN106480825A (en) * 2016-10-31 2017-03-08 中铁六局集团有限公司 Railway nonstandard Beams Erection Construction engineering method
CN108330842A (en) * 2018-04-19 2018-07-27 郑州新大方重工科技有限公司 A kind of Bridge Erector and construction method of large span steel reinforced concrete combination beam erection construction
CN110468714A (en) * 2019-08-09 2019-11-19 中铁七局集团有限公司 Overlength joins lateral closure construction method after unequal span asymmetric continuous bridge is first indulged
WO2020233501A1 (en) * 2019-05-23 2020-11-26 中铁二局集团有限公司 Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder
CN113373786A (en) * 2021-06-29 2021-09-10 保利长大工程有限公司 Novel UHPC simply supported box girder assembling method
CN114717973A (en) * 2022-03-04 2022-07-08 中建五局土木工程有限公司 Construction method for hoisting prefabricated small box girder under bridge girder erection machine in staggered height mode

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5841107A (en) * 1981-08-31 1983-03-10 名古屋高速道路公社 Traverse drawing constructing method of bridge beam
JPS5854107A (en) * 1981-09-26 1983-03-31 名古屋高速道路公社 Movement of bridge
JPH08134845A (en) * 1994-11-11 1996-05-28 Kajima Corp Erection method of bridge
JPH09156498A (en) * 1995-12-11 1997-06-17 Oriental Constr Co Ltd Single rail travel carriage
JP2001146716A (en) * 1999-11-22 2001-05-29 Shimizu Corp Erection method for bridge beam
JP2001336117A (en) * 2000-05-31 2001-12-07 Kajima Corp Cross section division type precast segment construction method
JP2004250986A (en) * 2003-02-20 2004-09-09 Sumitomo Mitsui Construction Co Ltd Erection method for grade separation viaduct
JP2007077630A (en) * 2005-09-13 2007-03-29 Oriental Construction Co Ltd Continuous girder using precast main-girder segment, and its erection method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5841107A (en) * 1981-08-31 1983-03-10 名古屋高速道路公社 Traverse drawing constructing method of bridge beam
JPS5854107A (en) * 1981-09-26 1983-03-31 名古屋高速道路公社 Movement of bridge
JPH08134845A (en) * 1994-11-11 1996-05-28 Kajima Corp Erection method of bridge
JPH09156498A (en) * 1995-12-11 1997-06-17 Oriental Constr Co Ltd Single rail travel carriage
JP2001146716A (en) * 1999-11-22 2001-05-29 Shimizu Corp Erection method for bridge beam
JP2001336117A (en) * 2000-05-31 2001-12-07 Kajima Corp Cross section division type precast segment construction method
JP2004250986A (en) * 2003-02-20 2004-09-09 Sumitomo Mitsui Construction Co Ltd Erection method for grade separation viaduct
JP2007077630A (en) * 2005-09-13 2007-03-29 Oriental Construction Co Ltd Continuous girder using precast main-girder segment, and its erection method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864734A (en) * 2010-06-28 2010-10-20 中铁二局股份有限公司 Cross sliding type erecting method for separated box girder of high speed railway
CN104594190A (en) * 2015-02-16 2015-05-06 西安公路研究院 Bridge seamless telescopic device and construction method of device
CN106480825A (en) * 2016-10-31 2017-03-08 中铁六局集团有限公司 Railway nonstandard Beams Erection Construction engineering method
CN108330842A (en) * 2018-04-19 2018-07-27 郑州新大方重工科技有限公司 A kind of Bridge Erector and construction method of large span steel reinforced concrete combination beam erection construction
CN108330842B (en) * 2018-04-19 2024-04-26 郑州新大方重工科技有限公司 Bridge girder erection machine for erection construction of large-span reinforced concrete composite girder and construction method
WO2020233501A1 (en) * 2019-05-23 2020-11-26 中铁二局集团有限公司 Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder
US11391004B1 (en) 2019-05-23 2022-07-19 China Railway No. 2 Engineering Group Co. LTD. Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder
CN110468714A (en) * 2019-08-09 2019-11-19 中铁七局集团有限公司 Overlength joins lateral closure construction method after unequal span asymmetric continuous bridge is first indulged
CN110468714B (en) * 2019-08-09 2021-04-30 中铁七局集团有限公司 Longitudinal and transverse closure construction method of ultra-long-connection unequal-span asymmetric continuous bridge
CN113373786A (en) * 2021-06-29 2021-09-10 保利长大工程有限公司 Novel UHPC simply supported box girder assembling method
CN114717973A (en) * 2022-03-04 2022-07-08 中建五局土木工程有限公司 Construction method for hoisting prefabricated small box girder under bridge girder erection machine in staggered height mode

Also Published As

Publication number Publication date
JP4937838B2 (en) 2012-05-23

Similar Documents

Publication Publication Date Title
JP4937838B2 (en) How to build a bridge
JP4777319B2 (en) Bridge erection method
JP6702835B2 (en) Bridge girder erection method for multi span span bridge
JP5319216B2 (en) Bridge girder erection device and bridge girder erection method
JP2008088782A (en) Cantilever overhang erection method of corrugated steel plate web bridge
JP4777922B2 (en) Mobile suspension support
JP6411970B2 (en) Method for dismantling and removing mobile work vehicle and mobile work vehicle
JP4336659B2 (en) Construction method of upper-floor type suspension floor slab bridge
JP4104910B2 (en) How to build arch ribs for concrete arch bridges
JPH05106210A (en) Erecting method for concrete skew bridge
JP4980257B2 (en) Construction method for column head construction, method for constructing mobile work vehicle using part thereof, and method for extending bridge
JP6839681B2 (en) How to dismantle a tower-supported chimney
JP4351523B2 (en) Column head construction method
JP5074260B2 (en) Bridge erection method
JP4849371B2 (en) Construction method of upper part of pier in cantilever erection method
JP2017096057A (en) Bridge construction method
CN214831975U (en) Pier construction device
JP4331005B2 (en) Construction method of precast segment bridge
JP2011208419A (en) Erection method of bridge girder
JP2018091093A (en) Bridge construction method
JP7012486B2 (en) Bridge construction method
JP2016108120A (en) Floor climbing-type tower crane and construction method for building
JP2015190122A (en) Beam-like member construction method
JP6411832B2 (en) Temporary beam connecting member and structure construction method
JP5973295B2 (en) Column head construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20091117

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110420

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20111122

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120113

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120221

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120222

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150302

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4937838

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250