JPH0765313B2 - Underground construction method - Google Patents

Underground construction method

Info

Publication number
JPH0765313B2
JPH0765313B2 JP1287359A JP28735989A JPH0765313B2 JP H0765313 B2 JPH0765313 B2 JP H0765313B2 JP 1287359 A JP1287359 A JP 1287359A JP 28735989 A JP28735989 A JP 28735989A JP H0765313 B2 JPH0765313 B2 JP H0765313B2
Authority
JP
Japan
Prior art keywords
construction
mountain
excavation
underground
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1287359A
Other languages
Japanese (ja)
Other versions
JPH03147927A (en
Inventor
浩一 杉本
英武 谷口
昌宏 浅田
郁男 石川
智 阿部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP1287359A priority Critical patent/JPH0765313B2/en
Publication of JPH03147927A publication Critical patent/JPH03147927A/en
Publication of JPH0765313B2 publication Critical patent/JPH0765313B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】 《産業上の利用分野》 本発明は、例えばビルディングの地下部分または地下駐
車場などの地下構造物の構築に適用される地下構築工法
に関する。
TECHNICAL FIELD The present invention relates to an underground construction method applied to the construction of an underground structure such as an underground portion of a building or an underground parking lot.

《従来の技術》 従来、この種の地下構築工法としては、切梁工法が多く
採用されている。切梁工法は、根切りに伴って浅段から
深段へ仮設鋼材またはRC部材を仮設し、これを支保工と
して山止壁を支えながら順次深く掘り下げた後、本設構
造物の柱,梁及び床について、各階毎に深段より切梁お
よび腹起しを解体撤去しながら、浅段へ工事を進めてい
く工法である。
<< Conventional Technology >> Conventionally, the beam construction method has been widely adopted as this type of underground construction method. The method of cutting beams is to temporarily construct a temporary steel material or RC member from shallow to deep with root cutting, and then use this as support work to dig deeper in sequence while supporting the retaining wall, and then the pillars and beams of the main structure. For floors and floors, the construction method is to proceed to the shallow steps while dismantling and removing the beams and upsets from the deep steps on each floor.

ところが、上記切梁工法では、躯体構築に際し、切梁の
腹起し材の搬入や取付け、さらに解体搬出などの仮設工
数が多く必要である。また、コンクリート打設後も切梁
等の解体までに一定期間の養生が必要であり、そのため
工期も比較的長くかかる。
However, the above-mentioned beam construction method requires a large number of temporary man-hours such as loading and mounting of the uprising material of the beam and disassembly and removal when constructing the skeleton. Further, even after pouring concrete, it is necessary to cure for a certain period of time until the dismantling of beams and the like, so that the construction period is relatively long.

そこで近年、切梁を本設構造物の一部として利用する工
法が開発されている(例えば特開昭52−135509号公報な
ど)。但し、複数の柱を必要とする広い床面積を有する
地下構造物の場合には、切梁を支持するために仮設され
る複数の支持杭を撤去するなどの手段が採用されてお
り、この面でまだ多くの工数が必要となっている。
Therefore, in recent years, a construction method has been developed in which a crossbeam is used as a part of the main structure (for example, Japanese Patent Laid-Open No. 52-135509). However, in the case of an underground structure with a large floor area that requires multiple columns, means such as removal of multiple support piles temporarily installed to support the girder is adopted. Therefore, a lot of man-hours are still required.

一方、例えば特開昭63−312439号公報に示されているよ
うに、地盤の所定箇所に地中壁を設け、この地中壁によ
って囲まれた箇所に対し根切りを行ないながら、その箇
所に鉄骨構造の躯体を構築し、この躯体を切梁に利用し
て地中壁を内側から支えながらさらに根切りを行ない、
上階から下階へ本設構造物を構築する工法も開発されて
いる。しかし、上記の工法はいわゆる逆打ち工法と呼ば
れ、下階から上階に本設構造物を構築する順打ち工法に
比べて掘削が面倒で、それだけ工期が長くかかり、高コ
ストとなる。
On the other hand, as shown in, for example, Japanese Patent Laid-Open No. 63-312439, a ground wall is provided at a predetermined location on the ground, and while cutting the root surrounded by this ground wall, Build a frame with a steel frame structure and use this frame as a cutting beam to further cut the root while supporting the underground wall from the inside.
A method of constructing a permanent structure from the upper floor to the lower floor has also been developed. However, the above-mentioned construction method is called a so-called reverse construction method, and excavation is more troublesome than the sequential construction method of constructing a permanent structure from the lower floor to the upper floor, which requires a longer construction period and becomes expensive.

《発明が解決しようとする課題》 従来では、躯体構築に際し、切梁や腹起し材の搬入や取
付け、さらに解体搬出など多くの仮設工数が必要であ
る。また、コンクリート打設後も切梁等の解体までに一
定期間の養生が必要であり、そのため工期も比較的長く
かかる。さらに切梁を支持するために仮設される複数の
支持杭の設置および撤去などについても多くの工数が必
要となる。また、逆打ち工法などによっても、下方掘削
が困難で、全体工期が長くかかり、それだけ高コストと
なる。
<< Problems to be Solved by the Invention >> Conventionally, in constructing a skeleton, a large number of temporary man-hours such as loading and mounting of a cutting beam and a waving material and dismantling and unloading are required. Further, even after pouring concrete, it is necessary to cure for a certain period of time until the dismantling of beams and the like, so that the construction period is relatively long. Furthermore, a large number of man-hours are required for installing and removing a plurality of support piles that are temporarily installed to support the beams. Moreover, even if the reverse construction method is used, it is difficult to dig down, and the whole construction period is long, resulting in higher costs.

本発明はこのような事情に鑑みてなされたもので、仮設
工事の省略とともに順打ち工法を取入れ、それにより一
層の工数低減,工期の短縮ならびにコストの低減などが
図れる地下構築工法を提供することを目的とする。
The present invention has been made in view of the above circumstances, and provides an underground construction method capable of further reducing the man-hours, shortening the construction period, and reducing the cost by omitting the temporary construction work and incorporating the progressive construction method. With the goal.

《課題を解決するための手段》 本発明に係る地下構築工法は、地盤に山止壁を形成し、
山止壁によって囲まれた区域内に構真柱を構築し、その
後上記区域に対して根切りを行ないながら本設構造物の
梁部分を構真柱に取り付け、これら構真柱及び梁部分を
山止支保工に利用して山止壁を内側から支えて掘削を行
なうと共に、掘削完了後本設構造物を下階から上階へ順
次構築することを特徴とする。
<< Means for Solving the Problem >> The underground construction method according to the present invention forms a retaining wall in the ground,
Constructing a true pillar in the area surrounded by the retaining wall, and then cutting the root of the above area and attaching the beam part of the main structure to the true pillar. It is characterized in that it is used for supporting the dam to support excavation from the inside of the dam and excavation is performed, and after completion of the excavation, the main structure is constructed sequentially from the lower floor to the upper floor.

《作 用》 本発明によれば、地盤に形成した山止壁で囲まれた区域
に構真柱を構築し、その後この区域に対して根切りを行
ないながら本設構造物の梁部分を構真柱に取り付け、こ
れら構真柱及び梁部分を山止支保工に利用するので、従
来の地下工事の山止支保工等の仮設部材がなくなって資
材の搬入出が大幅に減少し、仮設工事全体の省力化が図
れる。したがって、一層の工数低減、工期の短縮ならび
にコストの低減などが可能となる。
<< Operation >> According to the present invention, a structure pillar is constructed in an area surrounded by a moat wall formed in the ground, and thereafter, a beam portion of the main structure is constructed while root cutting is performed on this area. Since it is attached to the true pillar and these structural pillars and beams are used for the mountain shore support work, the temporary materials such as the mountain shore support work in the conventional underground construction are eliminated, and the loading and unloading of materials is greatly reduced. Overall labor saving can be achieved. Therefore, it is possible to further reduce the man-hours, the work period, and the cost.

また、本設構造物である構真柱及び梁部分による山止支
保工によって山止壁を内側から支え、掘削完了後、順打
ち工法によって本設構造物を下階から上階に順次構築す
るので、逆打ち工法に比べ、掘削が行ないやすい。した
がって、この面でも作業能率の向上、工期の短縮などが
図れる。
In addition, by supporting the mountain wall from the inside by retaining structures by the structure columns and beams, which is the main structure, after the excavation is completed, the main structure is constructed sequentially from the lower floor to the upper floor by the progressive construction method. Therefore, excavation is easier to perform than the reverse construction method. Therefore, also in this aspect, the work efficiency can be improved and the construction period can be shortened.

《実 施 例》 以下、本発明の一実施例を図面を参照して説明する。<< Examples >> One example of the present invention will be described below with reference to the drawings.

第1図〜第8図は工程を順次に示す平面図および側断面
図、第9図は完成した地下構築物の一部を拡大して示す
側断面図である。
1 to 8 are plan views and side sectional views sequentially showing the steps, and FIG. 9 is a side sectional view showing a part of the completed underground structure in an enlarged manner.

まず第1図〜第8図によって工程を順次に説明する。First, the steps will be sequentially described with reference to FIGS.

山止壁4の施工(第1図(A),(B)) 地盤1の所定箇所、すなわち地下構築物を建てようとす
る箇所の外周に、掘削機械2およびクローラクレーン3
などを用いて山止壁4を設ける。
Construction of mountain stop wall 4 (Figs. 1 (A) and (B)) The excavating machine 2 and the crawler crane 3 are provided on a predetermined portion of the ground 1, that is, on the outer periphery of a portion where an underground structure is to be built.
The mountain stop wall 4 is provided by using, for example.

構真柱(切梁支持、棚杭兼用)の施工(第2図
(A),(B)) 鋼管(Gコラム、STコラムなどの中空材)を使用して切
梁支持および棚杭兼用の構真柱5を設置する。この場
合、トレミ管を使用して、根入れ部、充填部のRC施工を
行なう。
Construction of structural columns (for both beam support and shelf pile) (Figs. 2 (A) and (B)) Using steel pipes (hollow materials such as G column and ST column) for both beam support and shelf pile A true pillar 5 is installed. In this case, use the Tremi tube to perform RC construction of the rooting and filling parts.

すき取りの施工(第3図(A),(B)) パワーショベル6などにより、山止壁4によって囲まれ
た区域に対し、地下1階の梁下端までのすき取りを行な
う。ここで地下1階の本設構造物の梁部分となる切梁7
および腹起し8を設置し、これらの躯体、具体的には構
真柱5,切梁7及び腹起し8を山止支保工に利用して、山
止壁4を内側から支える。そして、土間補強用の仮設ス
ラブの施工を行なう。梁材は、PC(SRC)またはS部材
とする。
Scraping work (Figs. 3 (A) and (B)) A power shovel 6 is used to scrape the area surrounded by the mountain stop wall 4 to the lower end of the beam on the first basement floor. Cut beam 7 that will be the beam part of the main structure on the first basement floor.
And, the abutment 8 is installed, and these skeletons, specifically, the concrete columns 5, the girders 7 and the abutment 8 are used for the mountain support, and the mountain wall 4 is supported from the inside. Then, the temporary slab for soil reinforcement is constructed. The beam is PC (SRC) or S member.

一次掘削、2段切梁の施工(第4図(A),(B)) 切梁7および腹起し8からなる躯体を山止支保工に利用
して、山止壁4を地下1階部分で内側から支え、一次掘
削つまり地下2階部分の掘削を行なう。ここで2段切梁
つまり地下2階部分の切梁施工を行なう。地下2階梁
は、PC(SRC)またはS部材とする。
Primary excavation, construction of two-level girder (Figs. 4 (A), (B)) The skeleton consisting of the girder 7 and the uprising 8 is used for the mountain shore support work, and the mountain dome 4 is on the first basement floor. Supporting the inside from the part, the primary excavation, that is, the excavation of the second basement. Here, the two-storied girder, that is, the girder construction on the second basement floor is performed. The beam on the second basement floor will be PC (SRC) or S member.

二次掘削、3段切梁の施工(第5図(A),(B)) ここではと同様、本設の構造物の躯体である地下2階
梁の切梁7および腹起し8を山止支保工に利用して、山
止壁4を地下2階部分で内側から支え、二次掘削つまり
地下3階部分の掘削を行なう。ここで3段切梁つまり地
下3階部分の切梁施工を行なう。地下3階梁は、PC(SR
C)またはS部材とする。
Secondary excavation, construction of three-level girder (Figs. 5 (A) and (B)) In the same manner as here, the girder 7 and the uprising 8 of the second-floor girder, which is the frame of the main structure, are installed. It is used for the mountain shore support work to support the mountain dome 4 from the inside on the second basement, and perform secondary excavation, that is, the third underground. Here, we will construct a three-level girder, that is, a girder for the basement floor. The beam on the 3rd basement floor is PC (SR
C) or S member.

三次掘削以降(第6図(A),(B)) ここでは前記同様、本設の構造物の躯体である地下3階
梁の切梁7および腹起し8を山止支保工に利用して、山
止壁4を地下3階部分で内側から支え、本設の構造物の
躯体を構築し、三次掘削および4段切梁の施工を行な
う。これにより地下4階の梁が形成される。ついで、同
様に四次掘削及び5段切梁等順次施工を行ない、地下5
階以降の梁が形成される(図示せず)。なお、地下4,5
階以降の梁も、PC(SRC)またはS部材とする。
After the third excavation (Figs. 6 (A) and (B)) Here, as before, the cut beams 7 and uprisings 8 of the beam on the 3rd floor of the basement, which is the frame of the main structure, were used for the mountain troop support work. Then, the mountain stop wall 4 is supported from the inside on the third basement, the structure of the main structure is constructed, and the third excavation and the construction of the four-level beam are performed. This will form a beam on the 4th basement floor. Then, similarly, quaternary excavation and 5 steps of beams, etc. are carried out in sequence, and 5 underground
Beams below the floor are formed (not shown). In addition, 4,5 underground
Beams on and after the floor will also be PC (SRC) or S members.

耐圧版、地中梁の配筋(第7図(A),(B)) 最終掘削後、耐圧版10下端の床付けならびに最終段切梁
の施工、構真柱5の下端部分間に地中梁11等の配筋9を
行ない、下記の耐圧版10および地中梁11の施工を行な
う。
Reinforcement plate, reinforcement of underground beam (Figs. 7 (A), (B)) After final excavation, flooring of pressure plate 10 at the lower end and construction of the final step beam, ground between the lower ends of construction columns 5 Reinforcement 9 such as middle beam 11 is performed, and pressure plate 10 and underground beam 11 described below are constructed.

耐圧版、地中梁の施工(第8図(A),(B)) 配筋9部分に対し、コンクリート打設を行ない、耐圧版
10および地中梁11の形成を行なう。
Construction of pressure plate and underground beam (Figs. 8 (A) and (B)) Concrete placement is performed on the 9 bar arrangements, and the pressure plate
10 and underground beam 11 are formed.

以下、順次に下階から上階に向かって、本設構造物の構
築、すなわちコンクリート打設により、山止支保工に利
用した切梁7および腹起し8ならびに構真柱5を本設構
造物とする構築を行なう。
Hereinafter, from the lower floor to the upper floor, the construction structure of the main structure, that is, concrete placing, is used to sequentially construct the girder 7 and the uprising 8 and the structure column 5 used for the mountain shore support work. Perform the actual construction.

以上説明したように第9図に示す如く、地盤1の所定箇
所に形成された山止壁4が、山止支保工としての構真柱
5,切梁7および腹起し8によって支持され、かつこれら
構真柱5,切梁7および腹起し8を本設構造物とする地下
構築物が構成される。
As described above, as shown in FIG. 9, the retaining wall 4 formed at a predetermined location of the ground 1 is a true column as a retaining structure.
5, an underground structure that is supported by the cut beams 7 and the uprisings 8 and that has the structural columns 5, the cut beams 7 and the uplifts 8 as the main structure is constructed.

本実施例によれば、地盤1に山止壁4を形成し、この山
止壁4によって囲まれた区域内に構真柱5を構築し、そ
の後上記区域に対して根切りを行ないながら本設構造物
の梁部分7,8を構真柱5に取り付け、これら構真柱5及
び梁部分7,8を山止支保工に利用して山止壁4を内側か
ら支えて掘削を行ない、掘削完了後本設構造物を下階か
ら上階に順次構築するので、従来の地下工事の山止支保
工等の架設部材が少なくなり、仮設工事全体の省略が図
れ、資材搬入出が大幅に減少し、省力化が図れる。した
がって、一層の工数低減、工期の短縮ならびにコストの
低減などが可能となる。
According to the present embodiment, the earth retaining wall 4 is formed in the ground 1, the structure pillars 5 are constructed in the area surrounded by the earth retaining wall 4, and then the root cutting is performed for the area. The beam portions 7 and 8 of the construction structure are attached to the true column 5, and the true column 5 and the beam portions 7 and 8 are utilized for the mountain shore support work to support the mountain cliff 4 from the inside for excavation. After the excavation is completed, the main structure is constructed sequentially from the lower floor to the upper floor.Therefore, the number of erection members for the conventional underground construction such as mountain shore support work is reduced, and the temporary construction work can be omitted altogether, and the material loading and unloading is significantly It can be reduced and labor can be saved. Therefore, it is possible to further reduce the man-hours, the work period, and the cost.

また、下階から上階に本設構造物の構築を行なう順打ち
工法によるから、逆打ち工法に比べ、掘削が行ないやす
い。したがって、この面でも作業能率の向上、工期の短
縮などが図れる。
Further, since the method of constructing the permanent structure from the lower floor to the upper floor is used, the excavation is easier to perform than the reverse construction method. Therefore, also in this aspect, the work efficiency can be improved and the construction period can be shortened.

《発明の効果》 以上のように本発明によれば、本設構造物となる構真柱
及び梁部分を山止支保工に利用して山止壁を内側から支
えつつ掘削を行ない、掘削完了後に本設構造物を下階か
ら上階に順次構築するので、従来に比して一層の工数低
減、工期の短縮ならびにコストの低減などを図ることが
できる。
<< Effects of the Invention >> As described above, according to the present invention, the structure columns and the beam portions that are the main structure are used for the mountain stop support work to perform the excavation while supporting the mountain stop wall from the inside and completing the excavation. Later, since the main structure is constructed sequentially from the lower floor to the upper floor, it is possible to further reduce the man-hour, the construction period, and the cost as compared with the conventional structure.

【図面の簡単な説明】[Brief description of drawings]

図は本発明の一実施例を示すもので、第1図(A),
(B)〜第8図(A),(B)は工程を順次に示す平面
図および側断面図、第9図は完成した地下構築物の一部
を拡大して示す側断面図である。 1……地盤、4……山止壁 5……構真柱 7,8……梁部分(切梁,腹起し)
FIG. 1 shows an embodiment of the present invention, which is shown in FIG.
(B) -FIGS. 8 (A) and (B) are plan views and side sectional views sequentially showing the steps, and FIG. 9 is a side sectional view showing a part of the completed underground structure in an enlarged manner. 1 …… Soil, 4 …… Mountain wall 5 …… Structural pillar 7,8 …… Beam (cut beam, upset)

───────────────────────────────────────────────────── フロントページの続き (72)発明者 石川 郁男 東京都千代田区神田司町2丁目3番地 株 式会社大林組東京本社内 (72)発明者 阿部 智 東京都千代田区神田司町2丁目3番地 株 式会社大林組東京本社内 (56)参考文献 特開 昭63−312439(JP,A) ─────────────────────────────────────────────────── --- Continuation of the front page (72) Inventor Ikuo Ishikawa 2-3 Kandaji-cho, Chiyoda-ku, Tokyo Obayashi Corporation Tokyo headquarters (72) Inventor Satoshi Abe 2-3 Kandaji-cho, Chiyoda-ku, Tokyo Obayashi Corporation Tokyo Head Office (56) References JP-A-63-312439 (JP, A)

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】地盤に山止壁を形成し、該山止壁によって
囲まれた区域内に構真柱を構築し、その後上記区域に対
して根切りを行ないながら本設構造物の梁部分を上記構
真柱に取り付け、これら構真柱及び梁部分を山止支保工
に利用して上記山止壁を内側から支えて掘削を行なうと
共に、掘削完了後本設構造物を下階から上階へ順次構築
することを特徴とする地下構築工法。
1. A foundation wall is formed by forming a retaining wall on the ground, constructing a structure pillar in an area surrounded by the retaining wall, and then cutting the root to the area. Are attached to the above-mentioned structure columns, and these structure columns and beam portions are used for the mountain shore support work to support the above-mentioned mountain walls from the inside for excavation, and after completion of digging, the main structure is moved up from the lower floor. An underground construction method characterized by sequentially building on the floors.
JP1287359A 1989-11-06 1989-11-06 Underground construction method Expired - Lifetime JPH0765313B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1287359A JPH0765313B2 (en) 1989-11-06 1989-11-06 Underground construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1287359A JPH0765313B2 (en) 1989-11-06 1989-11-06 Underground construction method

Publications (2)

Publication Number Publication Date
JPH03147927A JPH03147927A (en) 1991-06-24
JPH0765313B2 true JPH0765313B2 (en) 1995-07-19

Family

ID=17716348

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1287359A Expired - Lifetime JPH0765313B2 (en) 1989-11-06 1989-11-06 Underground construction method

Country Status (1)

Country Link
JP (1) JPH0765313B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5668971B2 (en) * 2010-10-29 2015-02-12 清水建設株式会社 Construction method for underground structures
CN108612129B (en) * 2018-05-03 2020-04-10 中国建筑第八工程局有限公司 Reverse construction method based on recyclable steel platform

Also Published As

Publication number Publication date
JPH03147927A (en) 1991-06-24

Similar Documents

Publication Publication Date Title
JP4558145B2 (en) Seismic isolation method for existing buildings
JP2000352296A (en) Method o constructing passage just under underground structure
JP4115095B2 (en) Reverse strike method
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JPH0684690B2 (en) Building basement extension method
JPS5829922A (en) Constructing method for underground outer wall
JPH0765313B2 (en) Underground construction method
JP2757026B2 (en) Reverse construction method of basement structure
JPH0559728A (en) Sheathing work above underground structure
JPH05179647A (en) Supporting structure for earth retaining wall
JP3109038B2 (en) Underground skeleton structure and construction method
JPS63280153A (en) Underground inverted lining method
JPH0759813B2 (en) Underground construction method
KR100593203B1 (en) a deck supportframe and a construction methed
JPH05255943A (en) Construction method for underground skeleton by slide down system
JP2894217B2 (en) Building structural frame
JP3809340B2 (en) Reverse strike method
JPH08291526A (en) Construction method for underground structure
JPH0742179A (en) Modified inversion placing construction method
JPH08105122A (en) Underground and aboveground simultaneous execution method of structure
JP2772397B2 (en) Underground building construction method
JPS63277342A (en) Reverse execution of underground story
JPS63312439A (en) Underground construction method
JP3061934B2 (en) Retaining wall construction method
JPS59233028A (en) Residential land formation work on sloped ground