JPH076169B2 - How to install and tension cable-stayed cables - Google Patents

How to install and tension cable-stayed cables

Info

Publication number
JPH076169B2
JPH076169B2 JP2122011A JP12201190A JPH076169B2 JP H076169 B2 JPH076169 B2 JP H076169B2 JP 2122011 A JP2122011 A JP 2122011A JP 12201190 A JP12201190 A JP 12201190A JP H076169 B2 JPH076169 B2 JP H076169B2
Authority
JP
Japan
Prior art keywords
cable
tension
strand
strands
stayed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2122011A
Other languages
Japanese (ja)
Other versions
JPH0416605A (en
Inventor
真一 近藤
優 瀬間
秀世 本間
雄治 金沢
Original Assignee
住友建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 住友建設株式会社 filed Critical 住友建設株式会社
Priority to JP2122011A priority Critical patent/JPH076169B2/en
Publication of JPH0416605A publication Critical patent/JPH0416605A/en
Publication of JPH076169B2 publication Critical patent/JPH076169B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は斜張橋で用いられる多数のストランドで構成
された斜張ケーブルをケーブル保護管内に挿入して架設
し、張力を導入する斜張ケーブルの架設緊張方法に関す
る。
The present invention relates to a cable-stayed cable used in a cable-stayed bridge, which is constructed by inserting a cable-stayed cable composed of a large number of strands into a cable protection tube and erected to introduce tension. Concerning the cable tension method.

〔従来の技術〕[Conventional technology]

長大斜張橋の斜張ケーブルは多数(37〜91本程度)のス
トランド(PC鋼より線)で構成される現場製作ケーブル
が多く用いられる。この斜張ケーブルの緊張は、本来1
本の斜張ケーブルを構成する全ストランドを同時に緊張
する一括緊張方式が基本である。
As for the cable-stayed cable of the long cable-stayed bridge, many on-site cables composed of many strands (37 to 91 strands) (PC steel stranded wire) are used. The tension of this cable-stayed cable is originally 1
The basic method is a collective tension method in which all the strands that make up a cable-stayed cable are tensioned at the same time.

ところが、斜張ケーブルを一括緊張するには、斜張ケー
ブルの保護管を足場支保工で支持したり、ハンガーワイ
ヤーで吊って空中に保持しておき、この中にストランド
を挿入するなどの方法で架設しなければならなかった。
しかし、張出し工法で施工する長大斜張橋では足場支保
工を組立てたり、太径のハンガーワイヤーを張ったりす
ることが非効率的であるため、ストランドの挿入に先だ
ち、前記の方法で保護管を保持することは一般的でな
く、斜張ケーブルの一括緊張は行なわれていなかった。
However, in order to tension the cable-stayed cables all together, a method such as supporting the protective tube of the cable-stayed cable with scaffolding support, or hanging it with a hanger wire and holding it in the air, and inserting a strand into it is possible. I had to erection.
However, it is inefficient to assemble the scaffolding support and to hang the hanger wire of large diameter on the long cable stayed bridge constructed by the overhanging method.Therefore, before inserting the strand, protect the protection tube with the above method. It was not common to hold and cable-stayed cables were not collectively tensioned.

一括緊張方式に代る方法としては、1本の斜張ケーブル
を構成する多数のストランドのうちの数本を先ず保護管
に挿入して緊張し、保護管を空中に保持しておき、この
状態で残りのストランドを1本ずつ挿入し1本ずつ緊張
するか、あるいは残りの全ストランドを挿入してから1
本ずつ緊張する分割緊張方式が採用されていた。
As an alternative to the collective tension method, first insert a few of the many strands that make up one cable-strand cable into the protective tube to tension it and keep the protective tube in the air. Insert the remaining strands one by one and tighten each one, or insert all the remaining strands and then
The split tension method, in which each book is tense, was adopted.

分割緊張方式では、ストランドを緊張すると主桁や主塔
が弾性変形し、先に緊張したストランドの張力が変化す
る。しかし、この変化量はコンクリートのヤング係数や
緊張作業時の温度変化の影響を受けることになる。従っ
て、分割緊張方式は1本の斜材を構成するすべてのスト
ランドの緊張が完了した時点における、斜張ケーブル1
本としての張力を把握しようとする場合、この張力は計
算値として算出しなければならないため、コンクリート
のヤング係数などの影響による誤差を含み精度が悪いと
いう大きな欠点があった。
In the split tension method, when the strand is tensioned, the main girder and the main tower are elastically deformed, and the tension of the previously tensioned strand changes. However, this amount of change is affected by Young's modulus of concrete and temperature change during tension work. Therefore, in the split tension system, the cable-stayed cable 1 at the time when the tension of all the strands constituting one diagonal member is completed.
When trying to grasp the tension as a book, this tension has to be calculated as a calculated value, so that there is a big drawback that the precision is poor because it includes an error due to the influence of the Young's modulus of concrete and the like.

〔発明の目的〕[Object of the Invention]

この発明は上記問題点に着目しなされたものである。そ
の目的は、斜張ケーブルの架設に足場支保工などを必要
とせず、1本の斜張ケーブルを構成する多数のストラン
ドを一括緊張して、張力導入の高精度化、作業の高能率
化を図り得る斜張ケーブルの架設、緊張方法を提案する
にある。
The present invention has been made in view of the above problems. The purpose is to increase the accuracy of tension introduction and work efficiency by collectively tensioning the many strands that make up one cable-stayed cable without the need for scaffolding support for the installation of the cable-stayed cable. The purpose is to propose a method of erection and tension of a cable-stayed cable that can be achieved.

〔発明の構成〕[Structure of Invention]

この斜張ケーブルの架設、緊張方法は、多数のストラン
ドで構成された斜張ケーブルを架設したケーブル保護管
内に挿入して緊張する方法において、前記多数のケーブ
ル中の数本を先行ストランドとしてケーブル保護管内に
挿入し、先行ストランドを仮緊張してケーブル保護管を
空中に保持し、この状態のケーブル保護管内に残りの多
数の後行ストランドを挿入し一括して緊張した後、先行
ストランドを緊張し所定張力を導入することを特徴とす
る。
This cable-stayed cable is laid and tensioned by inserting the cable-stayed cable composed of a large number of strands into a cable protection tube and then tensioning it. Insert the tube into the tube and temporarily tension the leading strand to hold the cable protection tube in the air.In this state, insert the remaining many trailing strands into the cable protection tube and tighten them in a lump, then tension the leading strand. It is characterized by introducing a predetermined tension.

〔作用〕[Action]

この方法は1〜3本程度の先行ストランドで保護管およ
び後行ストランドを空中に保持した状態で多数の後行ス
トランドをセンターホールジャッキで一括して緊張する
ので、導入した張力は油圧計で直接読取ることができ、
誤差を生じる様々な要因を除き、精度の高い緊張が可能
となり、かつ架設・緊張の作業性が向上する。多数のス
トランドを一括緊張した後、先行ストランドをあらため
て所定張力となるように緊張するが、その本数が1〜3
本程度で後行ストランドの本数に比べて少ないので後行
ストランドに与える影響は極めて微小な値となり、張力
管理上の問題とはならない。
With this method, many trailing strands are collectively tensioned by the center hole jack while the protective tube and trailing strands are held in the air by about 1 to 3 leading strands. Can read,
Except for various factors that cause errors, highly accurate tension is possible and workability of erection and tension is improved. After tensioning a large number of strands at once, the preceding strand is re-tensioned so as to have a predetermined tension.
Since the number of strands is less than the number of trailing strands, the influence on the trailing strands is extremely small and does not cause a problem in tension management.

〔実施例〕〔Example〕

以下、実施例の斜張ケーブルの架設、緊張方法を工程順
に図面を用い説明する。
Hereinafter, the method of constructing and tensioning the cable-stayed cable of the embodiment will be described in the order of steps with reference to the drawings.

第1図は斜張ケーブルを架設する斜張橋の主塔1と主桁
2である。ケーブルの架設に先だち、主桁2上でケーブ
ル保護管3(ポリエチレン製で所定長さの単位体)の中
に螺旋状のスペーサーワイヤーを挿入し、相互に溶着し
てケーブル架設長さとする。この保護管3内にパイロッ
トワイヤー4を挿通する。
Figure 1 shows the main tower 1 and main girder 2 of the cable-stayed bridge where the cable-stayed cable is erected. Prior to the cable installation, a spiral spacer wire is inserted into the cable protection tube 3 (unit made of polyethylene and having a predetermined length) on the main girder 2 and welded to each other to obtain the cable installation length. The pilot wire 4 is inserted into the protective tube 3.

第2図において、保護管3先端に吊上げ治具5を取付
け、主塔に取付けたタワークレーン6で吊上げる。続い
て第3図において、保護管3を先端治具5およびパイロ
ットワイヤー4を用いて主塔1に仮止めする。この際パ
イロットワイヤー4の下端は主桁に固定しておく。な
お、第3図において8は主塔に設けたケーブル定着孔,9
はレバーブロックである。
In FIG. 2, a hoisting jig 5 is attached to the tip of the protective tube 3 and hoisted by a tower crane 6 attached to the main tower. Subsequently, in FIG. 3, the protection tube 3 is temporarily fixed to the main tower 1 by using the tip jig 5 and the pilot wire 4. At this time, the lower end of the pilot wire 4 is fixed to the main girder. In FIG. 3, 8 is a cable fixing hole provided in the main tower, 9
Is a lever block.

第4図において、斜張ケーブルを構成する61本のストラ
ンド(15mm鋼より線)中の2本を先行ストランド10−1
となし、仮止めした保護管3内に上端部からプッシング
マシン11で押込み挿入する。このストランド10−1を第
5図において、その下端を主桁2に設置したケーブル定
着体に固定し、上端位置に配置したシングルストランド
ジャッキ12で仮緊張する。仮緊張の張力は9.8(t・
f)、ストランド1本当り4.9(t・f)となした。ケ
ーブルサグ(ストランド両端を結ぶ直線に対するストラ
ンドの最大たるみ距離)は500mmであった。
In Fig. 4, two of the 61 strands (15mm steel stranded wire) forming the cable-stayed cable are replaced by the preceding strand 10-1.
After that, the push-in machine 11 pushes and inserts the protective tube 3 temporarily fixed from the upper end. In FIG. 5, this strand 10-1 is fixed at its lower end to a cable fixing member installed on the main girder 2 and temporarily tensioned by a single-strand jack 12 arranged at the upper end position. The tension of temporary tension is 9.8 (t ・
f), 4.9 (t · f) per strand. The cable sag (the maximum slack distance of the strand with respect to the straight line connecting both ends of the strand) was 500 mm.

第6図において、パイロットワイヤー4を撤去し、保護
管3を先行ストランド10−1で主塔1と主桁2間の空中
に保持する。第7図において、空中に保持された保護管
3内に主塔1の定着孔8を挿通して後行となる59本のス
トランド10−2をプッシングマシン11で押込み挿入す
る。挿入後に、先行ストランド10−1にかかる張力は2
5.9(t・f)ストランド1本当り、12.95(t・f),
ケーブルサグは2.031mmであった。
In FIG. 6, the pilot wire 4 is removed, and the protection tube 3 is held in the air between the main tower 1 and the main girder 2 by the preceding strand 10-1. In FIG. 7, 59 strands 10-2 to be succeeding by inserting the fixing holes 8 of the main tower 1 into the protective tube 3 held in the air are pushed and inserted by the pushing machine 11. After insertion, the tension applied to the preceding strand 10-1 is 2
5.9 (tf) per strand, 12.95 (tf),
The cable sag was 2.031 mm.

第8図において挿入した後行のストランド10−2に緊張
管理用のマーキングをするとともに、その下端を主桁2
に設置したケーブル定着体に固定する。後行59本のの全
ストランド10−2をセンターホールジャッキ13で一括緊
張して所定の緊張力を導入し、上端部を主塔1の定着孔
8部分に定着する。この時の後行ストランド10−2の張
力は485.52(t・f)、1本当り8.2(t・f)、先行
ストランド10−1にかかる張力は8.0(t・f)、1本
当り4.0(t・f)であり、ケーブルサグは99mmであっ
た。
Marking for tension control is made on the following strand 10-2 inserted in Fig. 8 and the lower end of the main girder 2
It is fixed to the cable fixing body installed in. All of the 59 subsequent strands 10-2 are collectively tensioned by the center hole jack 13 to introduce a predetermined tension, and the upper end is fixed to the fixing hole 8 portion of the main tower 1. At this time, the tension of the trailing strand 10-2 is 485.52 (t · f), 8.2 (t · f) per strand, and the tension applied to the preceding strand 10-1 is 8.0 (t · f), 4.0 (per strand). tf) and the cable sag was 99 mm.

続いて先行のストランド10−1をあらためてシングルス
トランドジャッキで緊張し、所定の緊張力を導入した
後、定着孔8部分に定着する。この時の後行ストランド
10−2の張力は16.4(t・f)、1本当り8.2(t・
f)後行ストランド10−2にかかる張力は485.48(t・
f)、1本当り8.2(t・f)であり、ケーブルサグは9
7mmであった。最終の工程で先行ストランドを再緊張し
たが、一括緊張した後行ストランド張力は485.52(t・
f)から485.48(t・f)に僅か変化したのみで、スト
ランド1本としては無視できる値であった。
Then, the preceding strand 10-1 is re-tensioned with a single-strand jack to introduce a predetermined tension force, and then fixed to the fixing hole 8 portion. Trailing strand at this time
Tensile force of 10-2 is 16.4 (tf), and 8.2 (t
f) The tension applied to the trailing strand 10-2 is 485.48 (t.
f) It is 8.2 (tf) per cable, and cable sag is 9
It was 7 mm. In the final process, the preceding strand was re-tensioned, but the tension of the trailing strand after it was collectively tightened was 485.52 (t
It was a slight change from f) to 485.48 (t · f), which was a negligible value for one strand.

〔発明の効果〕〔The invention's effect〕

この発明は以上の通りであり、次の効果を奏する。 The present invention is as described above, and has the following effects.

この方法は1本の斜張ケーブルを構成するストラン
ドの大多数の張力をまとめて直接的に測定するので、従
来の分割緊張方式に 比べ高い精度で緊張力を導入できる。
Since this method directly measures the tensions of the majority of the strands constituting one cable-strand cable directly, it is possible to introduce the tension force with higher accuracy than the conventional split tension method.

従来の分割緊張方式ではケーブル緊張に2日間程度
を要したが、この一括緊張方式では緊張に要した時間は
半日程度であり、作業能率が著しく向上した。
The conventional split tension method required about two days for cable tension, but this collective tension method required about half a day for tension, resulting in a significant improvement in work efficiency.

足場支保工あるいはハンガーケーブルなどが不要で
あり、張出し工法の斜張橋にも適用できるので適用範囲
が広く、かつ工程の合理化が達成できる。
Since it does not require scaffolding support or hanger cables, and can be applied to cable-stayed bridges with overhanging methods, it has a wide range of applications and can streamline the process.

【図面の簡単な説明】[Brief description of drawings]

第1図〜8図は実施例の斜張ケーブルの架設、緊張方法
を工程順に示す斜張橋の側面図、第1,2,3,4,7図(b)
はそれぞれ、ケーブル保護管上端部の拡大図、第3図
(c)はケーブル保護管下端部の拡大図である。 1……主塔,2……主桁,3……ケーブル保護管,4……パイ
ロットワイヤー,5……吊上げ治具,6……タワークレー
ン,7……ウインチ,8……ケーブル定着孔,9……レバーブ
ロック,10−1……先行ストランド,10−2……後行スト
ランド,11……プッシングマシン,12……シングルストラ
ンドジャッキ,13……センターホールジャッキ
FIGS. 1 to 8 are side views of a cable-stayed bridge showing the cable-stayed cable installation and tensioning method in the order of steps, and FIGS. 1, 2, 3, 4, and 7 (b).
Is an enlarged view of the upper end of the cable protection tube, and FIG. 3 (c) is an enlarged view of the lower end of the cable protection tube. 1 …… Main tower, 2 …… Main girder, 3 …… Cable protection tube, 4 …… Pilot wire, 5 …… Hoisting jig, 6 …… Tower crane, 7 …… Winch, 8 …… Cable fixing hole, 9 …… Lever block, 10-1 …… Leading strand, 10-2 …… Trailing strand, 11 …… Pushing machine, 12 …… Single strand jack, 13 …… Center hole jack

───────────────────────────────────────────────────── フロントページの続き (72)発明者 金沢 雄治 東京都新宿区荒木町13番地の4 住友建設 株式会社内 (56)参考文献 特開 平1−142107(JP,A) 特開 平1−142108(JP,A) 特公 平1−15646(JP,B2) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Yuji Kanazawa 13-13 Arakicho, Shinjuku-ku, Tokyo Sumitomo Construction Co., Ltd. (56) References 142108 (JP, A) Japanese Patent Publication 1-15646 (JP, B2)

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】多数のストランドで構成された斜張橋の斜
張ケーブルを架設したケーブル保護管内に挿入して緊張
する方法において、前記多数のストランド中の数本を先
行ストランドとしてケーブル保護管内に挿入し、先行ス
トランドを仮緊張してケーブル保護管を空中に保持し、
この状態のケーブル保護管内に残りの多数の後行ストラ
ンドを挿入し一括して緊張した後、先行ストランドを緊
張し所定張力を導入することを特徴とする斜張ケーブル
の架設,緊張方法。
1. A method of inserting a cable-stayed cable of a cable-stayed bridge composed of a large number of strands into a cable protection tube in which the cable is laid and tensioning the same, wherein several of the plurality of strands are used as preceding strands in the cable protection tube. Insert and temporarily tension the leading strand to hold the cable protection tube in the air,
A method of constructing and tensioning a cable-stayed cable, characterized in that the remaining large number of trailing strands are inserted into the cable protection tube in this state and tensioned collectively, and then the preceding strand is tensioned to introduce a predetermined tension.
JP2122011A 1990-05-11 1990-05-11 How to install and tension cable-stayed cables Expired - Fee Related JPH076169B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2122011A JPH076169B2 (en) 1990-05-11 1990-05-11 How to install and tension cable-stayed cables

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2122011A JPH076169B2 (en) 1990-05-11 1990-05-11 How to install and tension cable-stayed cables

Publications (2)

Publication Number Publication Date
JPH0416605A JPH0416605A (en) 1992-01-21
JPH076169B2 true JPH076169B2 (en) 1995-01-30

Family

ID=14825363

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2122011A Expired - Fee Related JPH076169B2 (en) 1990-05-11 1990-05-11 How to install and tension cable-stayed cables

Country Status (1)

Country Link
JP (1) JPH076169B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2849070B1 (en) * 2002-12-18 2005-03-04 Freyssinet Int Stup METHOD FOR MOUNTING A HAUBAN
FR2858987B1 (en) * 2003-08-20 2006-02-17 Freyssinet Int Stup METHOD FOR MOUNTING A HAUBAN
JP4847805B2 (en) * 2006-06-28 2011-12-28 株式会社エスイー Cable laying method
JP5365834B2 (en) * 2008-09-18 2013-12-11 清水建設株式会社 Tension introduction method to cable

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0711123B2 (en) * 1987-11-26 1995-02-08 鹿島建設株式会社 Construction method of diagonal cable in cable-stayed bridge

Also Published As

Publication number Publication date
JPH0416605A (en) 1992-01-21

Similar Documents

Publication Publication Date Title
US4473915A (en) Tension member and a method of assembling and installing the tension member
JPH076169B2 (en) How to install and tension cable-stayed cables
JP2000054321A (en) Installation of oblique cable
JP3608751B2 (en) Temporary fixing method of block in PC precast block method by non-coupler
KR20160029277A (en) Construction Method to Create Multi-span Continuity in PSC Bridges
JP3108619B2 (en) Method of introducing prestress into concrete block for anchoring outer cable of concrete girder
JP2807845B2 (en) Construction method of diagonal material for Stypanel Bridge
JP2979297B2 (en) Suspended slab bridge using external cable and its construction method
CN114941288B (en) Construction method for suspension bridge loose cable sleeve
JP2810853B2 (en) How to install diagonal cable
JPH06101344A (en) Tightening material fixing structure and method of fixing
JPH01219203A (en) Manufacture of oblique cable for diagonal cable bridge
JP2725532B2 (en) Prestressed concrete double T-type slab with stringing material
JPH01142108A (en) Method of erecting diagonal brace cable in obliquely stretched bridge
JP5365834B2 (en) Tension introduction method to cable
CN116591053A (en) Cable system tensioning control method suitable for self-anchored cable-stayed suspension cooperative system
JPH09273119A (en) Suspension bridge construction method
Bondy Post-Tensioned Concrete in Buildings Past and Future: An Insider’s view
JP3175384B2 (en) Drum winding wire for prefabricated overhead wire
CN113481884A (en) Formwork erecting method for arched concrete beam
JPH0426002B2 (en)
JPS6370201A (en) Laying method for optical cable
JPH0827724A (en) Cable tensed fixing method
JPS62129404A (en) Construction of main cable of suspension bridge
JPS6310107A (en) Labor saving stringing construction method for optical fiber composite overhead ground wire

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080130

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090130

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090130

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100130

Year of fee payment: 15

LAPS Cancellation because of no payment of annual fees