JP2807845B2 - Construction method of diagonal material for Stypanel Bridge - Google Patents

Construction method of diagonal material for Stypanel Bridge

Info

Publication number
JP2807845B2
JP2807845B2 JP40983290A JP40983290A JP2807845B2 JP 2807845 B2 JP2807845 B2 JP 2807845B2 JP 40983290 A JP40983290 A JP 40983290A JP 40983290 A JP40983290 A JP 40983290A JP 2807845 B2 JP2807845 B2 JP 2807845B2
Authority
JP
Japan
Prior art keywords
cable
tower
girder
concrete
diagonal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP40983290A
Other languages
Japanese (ja)
Other versions
JPH04213605A (en
Inventor
義明 今井
壮次 金井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP40983290A priority Critical patent/JP2807845B2/en
Publication of JPH04213605A publication Critical patent/JPH04213605A/en
Application granted granted Critical
Publication of JP2807845B2 publication Critical patent/JP2807845B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、スティパネル橋の斜材
の施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for installing a diagonal member for a stypanel bridge.

【0002】[0002]

【従来の技術】斜張橋やスティパネル橋の施工におい
て、垂直の塔と水平の主桁間にPC鋼材などの斜材を連
結する方法としては、斜材の一端を主桁又は塔に埋設
し、斜材の他端を塔側又は桁側に貫通して緊張定着する
方法と、斜材の両端を塔と主桁にそれぞれ貫通させて主
桁側または塔側で緊張定着する方法である。
2. Description of the Related Art In the construction of a cable-stayed bridge or a stay panel bridge, as a method of connecting a diagonal member such as a PC steel material between a vertical tower and a horizontal main girder, one end of the diagonal member is embedded in the main girder or the tower. Then, the other end of the diagonal material is penetrated to the tower side or the girder side, and the tension is fixed. .

【0003】[0003]

【本発明が解決しようとする問題点】前記した従来の斜
材の施工技術には次のような問題点がある。 <イ>斜材の一端を桁に埋設し他端を塔側で緊張して定
着する方法にあっては、斜材の埋設端をコンクリート打
設時に同時に埋設しなければならず、しかも斜材の他端
側に斜材の全長を桁上または載置専用の支保工上に展開
しておく必要があり、施工が面倒である。 <ロ>桁の下面で斜材を定着する場合は、桁下に障害物
が存在すると施工が困難を極める。 <ハ>斜材を塔側で緊張定着する場合は、ジャッキの移
動に手数がかかる上に、大規模な設備が必要となる。
[Problems to be solved by the present invention] The above-mentioned conventional diagonal member construction techniques have the following problems. <B> In the method of embedding one end of the diagonal material in the spar and fixing the other end by tightening it on the tower side, the embedded end of the diagonal material must be buried at the same time as the concrete is cast. It is necessary to unfold the entire length of the diagonal material on the girder or on a support dedicated to mounting on the other end side of, and the construction is troublesome. <B> In the case where the diagonal material is fixed on the lower surface of the girder, the construction is extremely difficult if there is an obstacle below the girder. <C> When the diagonal material is settled on the tower side, it takes time and effort to move the jack, and large-scale equipment is required.

【0004】[0004]

【本発明の目的】本発明は以上の問題点を解決するため
に成されたもので、その目的とするところは施工性に優
れた、スティパネル橋の斜材の施工方法を提供すること
にある。
SUMMARY OF THE INVENTION The present invention has been made to solve the above problems, and an object of the present invention is to provide a method for installing a diagonal member of a stypan bridge which has excellent workability. is there.

【0005】[0005]

【課題を解決するための手段】本発明は、塔とこの塔に
一体に張り出す水平桁との間に斜めにコンクリート製の
斜材を連結するスティパネル橋の斜材の施工方法におい
て、塔から張り出した桁にPCケーブルの一端を埋設
し、塔頂部に別途のPCケーブルを摺動自在に挿通し、
前記両PCケーブルの端部間に定着具を介して連結し、
定着具を露出させたままコンクリートを打設して斜材を
形成し、コンクリートの硬化後定着具に定着した一方の
PCケーブルを緊張して斜材にプレストレスを導入する
ことを特徴とする。さらに本発明は、PCケーブルの一
端を塔頂部に定着し、塔頂部と水平桁との途上の定着具
を介して一方のPCケーブルを緊張して斜材にプレスト
レスを導入することを特徴とする。
SUMMARY OF THE INVENTION The present invention relates to a method for constructing a diagonal material for a stay panel bridge in which a diagonal concrete material is diagonally connected between a tower and a horizontal girder integrally projecting from the tower. One end of the PC cable is buried in the girder that overhangs, and another PC cable is slidably inserted into the top of the tower,
Connected between the ends of the two PC cables via a fixing device,
The method is characterized in that concrete is cast while exposing the fixing device to form a diagonal material, and after the concrete is hardened, one PC cable fixed to the fixing device is tensioned to introduce prestress into the diagonal material. Further, the present invention is characterized in that one end of the PC cable is fixed to the tower top, and one PC cable is tensioned through a fixing tool on the way between the tower top and the horizontal girder to introduce prestress into the diagonal member. I do.

【0006】[0006]

【本発明の構成】以下、図面を参照しながら本発明につ
いて説明する。尚、本例においてはPCケーブルを塔に
貫通させて配置するスルー方式を採用してスティパネル
橋を施工する場合について説明する。 <イ>塔、水平桁の施工 図1に示すように公知の施工法で塔1を施工する。この
際図7に示すように塔1の頂部に緩やかな曲率で湾曲し
たサドル管2を埋設しておく。サドル管2は例えば両端
を開放した鋼管などを使用できる。つぎに移動式作業車
3を使用して塔1の左右両側にコンクリートを打設して
水平桁4を順次張り出していく。 <ロ>斜材ステージの構築 水平桁4を一定長だけ張り出したら、図2のように水平
桁4の両側に斜材用のステージ7を構築する。ステージ
7はPCケーブルの架設予定線に沿って組み立てた支保
工などで構成する。 <ハ>桁側PCケーブルの分割配置 水平桁4の張り出し時において、桁用PCケーブル5a
の一端を水平桁4に埋設しておく。桁用PCケーブル5
aはPC鋼より線などで、その埋設端に抵抗板を固定し
て埋設する。桁用PCケーブルの自由端には図8に示す
ようなアンカーヘッド6の挿通孔61に挿通し、楔62
で定着する。アンカーヘッド6は同心円状に二重に挿通
孔61が開設してあり、各挿通孔61は楔62の挿通方
向が内側列と外側列単位でそれぞれ逆になっている。
尚、63は楔62の脱落を防止するセットプレートであ
る。 <ニ>塔側シースの配設 桁用PCケーブル5aのセットが完了したら図3に示す
ように塔1の各サドル管2に長尺のPCケーブル5bを
挿通し、各PCケーブル5bの両端を水平桁4の左右に
案内する。そして図9に示すように各PCケーブル5b
の端をアンカーヘッド6の内側の挿通孔61に挿通し、
両ケーブル5a、5b間を緊張した後コーン64を用い
て定着する。このときPCケーブル5bの定着端は後述
するアンカーヘッド6から緊張分だけ余分に突出させて
おく。これにより、塔1と水平桁4との間に連続したP
Cケーブル5a、5bが架設されたことになる。 <ホ>斜材コンクリートの打設 つぎに図4に示すようにPCケーブル5a、5b群の周
囲に型枠を組み立ててコンクリートを打設してスティパ
ネル8を構築する。この際、連続したPCケーブル5
a、5bのうち少なくとも片方のアンカーヘッド6の周
囲にボックスなどで包囲して、アンカーヘッド6がコン
クリートに埋没しないように配慮する。 <ヘ>PCケーブルの二次緊張 コンクリートの硬化後、図10に示すようにスティパネ
ル8に設けた切欠71内のアンカーヘッド6にカーブチ
ェア65を介してセンターホール型の緊張ジャキ9をセ
ットし、PCストランド5bを把持して緊張する。PC
ケーブル5bの緊張反力はアンカーヘッド6を介してP
Cケーブル5aで支持されるからスティパネル8の途上
において塔1を挟んで両PCケーブル5a、5bを同時
に緊張できる。これにより、スティパネル8に所定のプ
レストレスを導入することができる。また、アンカーヘ
ッド6が露出している間は適時再緊張作業が行える。最
後にスティパネル8の切欠部にコンクリートを充填して
ステージ7を解体して図5に示すスティパネル橋を得
る。尚、両PCケーブル5aに効果的に緊張するにはコ
ンクリートの打設前にシースを外装してアンボンドタイ
プに構成しておくと良い。また、両PCケーブル5a、
5bを緊張する時期は、水平桁4のカンチレバー施工
時、ステージ7上での施工時、或いは最終緊張時などで
行ない、各部の断面力の調整や水平桁4のレベル調整を
行う。
The present invention will be described below with reference to the drawings. In this example, a case will be described in which a stay panel bridge is constructed by employing a through system in which a PC cable is penetrated through a tower. <A> Construction of tower and horizontal girder As shown in FIG. 1, the tower 1 is constructed by a known construction method. At this time, as shown in FIG. 7, a saddle pipe 2 curved with a gentle curvature is buried at the top of the tower 1. As the saddle pipe 2, for example, a steel pipe having both ends opened can be used. Next, concrete is cast on the left and right sides of the tower 1 using the mobile work vehicle 3 and the horizontal girders 4 are sequentially extended. <B> Construction of diagonal material stage After the horizontal girder 4 has been extended by a certain length, stages 7 for diagonal material are constructed on both sides of the horizontal girder 4 as shown in FIG. The stage 7 is configured by a supporter or the like assembled along a planned installation line of the PC cable. <C> Divided arrangement of the girder side PC cable When the horizontal girder 4 projects, the girder PC cable 5a
Is buried in the horizontal girder 4. PC cable for girder 5
a is a PC steel stranded wire or the like, and a resistance plate is fixed and embedded at an embedded end thereof. The free end of the girder PC cable is inserted into an insertion hole 61 of the anchor head 6 as shown in FIG.
To settle. The anchor head 6 has double insertion holes 61 concentrically formed, and the insertion direction of the wedges 62 in each of the insertion holes 61 is reversed in the inner row and the outer row.
A set plate 63 prevents the wedge 62 from falling off. <D> Arrangement of tower side sheath When the setting of the girder PC cable 5a is completed, a long PC cable 5b is inserted into each saddle tube 2 of the tower 1 as shown in FIG. Guide to the left and right of the horizontal girder 4. Then, as shown in FIG. 9, each PC cable 5b
Into the insertion hole 61 inside the anchor head 6,
After tension is applied between the cables 5a and 5b, fixing is performed using the cone 64. At this time, the fixing end of the PC cable 5b is made to protrude from the anchor head 6, which will be described later, by an amount corresponding to the tension. Thereby, the continuous P between the tower 1 and the horizontal beam 4
This means that the C cables 5a and 5b have been installed. <E> Casting of diagonal concrete Next, as shown in FIG. 4, a formwork is assembled around the group of PC cables 5a and 5b, and concrete is cast to construct the stay panel 8. At this time, the continuous PC cable 5
a, 5b, at least one of the anchor heads 6 is surrounded by a box or the like so that the anchor heads 6 are not buried in concrete. <F> Secondary tension of PC cable After the concrete is hardened, a center hole type tension jack 9 is set via the curve chair 65 to the anchor head 6 in the notch 71 provided in the stay panel 8 as shown in FIG. Then, the PC strand 5b is gripped and tensioned. PC
The tension reaction force of the cable 5b is P via the anchor head 6.
Since the PC cables 5a and 5b are supported by the C cable 5a, the PC cables 5a and 5b can be simultaneously tensioned on the way of the stay panel 8 with the tower 1 interposed therebetween. Thereby, a predetermined prestress can be introduced into the stay panel 8. Further, while the anchor head 6 is exposed, the re-tensioning operation can be performed as needed. Finally, concrete is filled into the notch of the stay panel 8, and the stage 7 is dismantled to obtain the stay panel bridge shown in FIG. Note that, in order to effectively tension the two PC cables 5a, it is preferable to provide an unbonded type by sheathing the sheath before placing concrete. Also, both PC cables 5a,
The tension of 5b is performed at the time of cantilever construction of the horizontal girder 4, at the time of construction on the stage 7, or at the time of final tension, etc., to adjust the sectional force of each part and the level of the horizontal girder 4.

【0007】[0007]

【他の実施例】前記実施例はPCケーブルを塔に貫通さ
せたスルー方式について説明したが、PCケーブル5b
の一端を塔1の頂部に定着させる方式に採用しても良い
ことはもちろんである。
[Other Embodiments] In the above embodiment, the through system in which a PC cable is passed through a tower has been described.
Of course, one end of the column may be fixed to the top of the tower 1.

【0008】[0008]

【発明の効果】本発明は以上説明したようになるから次
の効果が得られる。<イ>PCケーブルの緊張作業を作
業環境の良好な桁上で簡易に行える。そのため、桁下に
障害物があっても施工できると共に、緊張用ジャッキの
移動が容易である。<ロ>適時PCケーブルの再緊張を
行える。<ハ>複数に分割したPCケーブル間で緊張す
る方式であるから、塔や桁のコンクリート打設時にPC
ケーブルの全長を配置しておく従来方法と比較してPC
ケーブルの載置が容易である。
As described above, the present invention has the following effects. <a> Tension work of a PC cable can be easily performed on a girder in a favorable work environment. Therefore, even if there is an obstacle under the girder, the work can be performed, and the tension jack can be easily moved. <B> The PC cable can be re-tensioned as needed. <C> Since the tension is applied between the PC cables divided into a plurality of pieces, the PC cable is used when placing concrete in towers and girders.
PC compared to the conventional method that arranges the entire length of the cable
Easy placement of cables.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 塔の左右に水平桁を張り出す施工方法を示し
た説明図
FIG. 1 is an explanatory view showing a construction method of extending a horizontal girder to the left and right of a tower.

【図2】 水平桁に桁用PCケーブルをセットしたとき
の説明図
FIG. 2 is an explanatory diagram when a girder PC cable is set on a horizontal girder.

【図3】 アンカーヘッドを介して各PCケーブルに連
続性を付与したときの説明図
FIG. 3 is an explanatory diagram when continuity is given to each PC cable via an anchor head.

【図4】 塔と水平桁間にスティパネルを施工するとき
の説明図
FIG. 4 is an explanatory view when constructing a stay panel between a tower and a horizontal girder.

【図5】 完成時の全体図[Figure 5] Overall view when completed

【図6】 PCケーブルの挿通前における塔頂部の部分
断面図
FIG. 6 is a partial cross-sectional view of a tower top before a PC cable is inserted.

【図7】 PCケーブルを挿通した状態の塔頂部の部分
断面図
FIG. 7 is a partial cross-sectional view of the tower top with a PC cable inserted.

【図8】 桁用PCケーブルを定着したアンカーヘッド
の断面図
FIG. 8 is a sectional view of an anchor head to which a girder PC cable is fixed.

【図9】 両PCケーブルを接続したアンカーヘッドの
断面図
FIG. 9 is a cross-sectional view of an anchor head to which both PC cables are connected.

【図10】 PCケーブル緊張時におけるスティパネル
の縦断面図
FIG. 10 is a longitudinal sectional view of a stay panel when a PC cable is tensioned.

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 塔とこの塔に一体に張り出す水平桁との
間に斜めにコンクリート製の斜材を連結するスティパネ
ル橋の斜材の施工方法において塔から張り出した桁にP
Cケーブルの一端を埋設し、塔頂部に別途のPCケーブ
ルを摺動自在に挿通し、前記両PCケーブルの端部間に
定着具を介して連結し、定着具を露出させたままコンク
リートを打設して斜材を形成し、コンクリートの硬化後
定着具に定着した一方のPCケーブルを緊張して斜材に
プレストレスを導入することを特徴とする、スティパネ
ル橋の斜材の施工方法。
1. A method for constructing a stay panel bridge in which a concrete diagonal member is diagonally connected between a tower and a horizontal girder extending integrally with the tower.
One end of the C cable is buried, a separate PC cable is slidably inserted into the tower top, connected between the ends of the two PC cables via a fixing device, and concrete is struck while exposing the fixing device. A method of constructing a diagonal material for a stay panel bridge, wherein a prestress is introduced into the diagonal material by tensioning one of the PC cables fixed to the fixing device after hardening of the concrete.
【請求項2】 請求項1のPCケーブルの一端を塔頂部
に定着し、塔頂部と水平桁との途上の定着具を介して一
方のPCケーブルを緊張して斜材にプレストレスを導入
することを特徴とする、請求項1のスティパネル橋の斜
材の施工方法。
2. The PC cable according to claim 1, wherein one end of the PC cable is fixed to the tower top, and one PC cable is tensioned through a fixing tool on the way between the tower top and the horizontal girder to introduce prestress into the diagonal member. The method for constructing a diagonal member for a stay panel bridge according to claim 1, wherein:
JP40983290A 1990-12-12 1990-12-12 Construction method of diagonal material for Stypanel Bridge Expired - Fee Related JP2807845B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP40983290A JP2807845B2 (en) 1990-12-12 1990-12-12 Construction method of diagonal material for Stypanel Bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP40983290A JP2807845B2 (en) 1990-12-12 1990-12-12 Construction method of diagonal material for Stypanel Bridge

Publications (2)

Publication Number Publication Date
JPH04213605A JPH04213605A (en) 1992-08-04
JP2807845B2 true JP2807845B2 (en) 1998-10-08

Family

ID=18519110

Family Applications (1)

Application Number Title Priority Date Filing Date
JP40983290A Expired - Fee Related JP2807845B2 (en) 1990-12-12 1990-12-12 Construction method of diagonal material for Stypanel Bridge

Country Status (1)

Country Link
JP (1) JP2807845B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110345890A (en) * 2019-06-24 2019-10-18 中铁大桥勘测设计院集团有限公司 A kind of bridge completion state dissipate saddle's position and anchor span it is linear combine the method for determination

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110886223A (en) * 2019-11-06 2020-03-17 中国铁路设计集团有限公司 Construction method for concreting steel-concrete combined tower and concrete box girder
CN111551088B (en) * 2020-05-12 2022-06-07 中钢集团武汉安全环保研究院有限公司 Accurate blasting demolition method for single-tower single-cable-plane prestressed cable-stayed bridge
CN112482239A (en) * 2020-12-17 2021-03-12 张家港保税区金港建设工程质量检测有限公司 Double-amplitude four-cable-plane cable-stayed bridge of single-blade hyperboloid single-column tower and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110345890A (en) * 2019-06-24 2019-10-18 中铁大桥勘测设计院集团有限公司 A kind of bridge completion state dissipate saddle's position and anchor span it is linear combine the method for determination

Also Published As

Publication number Publication date
JPH04213605A (en) 1992-08-04

Similar Documents

Publication Publication Date Title
JPS5869908A (en) Free tension material, method and apparatus for producing and assembling obliquely tentioned cable of bridge
KR100885663B1 (en) A prestressed concrete composite girder using cross-beam and constructing method thereof
KR20110111907A (en) Saddle assembly
JP2807845B2 (en) Construction method of diagonal material for Stypanel Bridge
JP3924192B2 (en) Bridge superstructure and substructure connection structure and its construction method
JP2709279B2 (en) Saddle structure for cable-stayed cable on main tower side of cable-stayed bridge
JP3877995B2 (en) How to build a string string bridge
KR100277606B1 (en) Structural reinforcement method using bidirectional truss
JP2000144637A (en) Support structure for bridge girder in extrusion method
JP3466136B2 (en) Method and apparatus for overhanging PC bridge
JP3797560B2 (en) Bridge segment and its construction method
KR20170091553A (en) Apparatus for introducing compressive force in slab of a bridge and method for constructing a bridge having the same
KR20060057233A (en) Prestressed concrete i-beam and maintenance repairing construction method of bridge for using prestressed concrete i-beam
US4319374A (en) Method of constructing a stayed girder bridge
JP2979297B2 (en) Suspended slab bridge using external cable and its construction method
JP2000104220A (en) Erection of combined truss bridge
JP2734985B2 (en) Cantilever shed and its construction method
JPH0771007A (en) Temporary fixation method on construction of capital of bridge
WO2016200083A1 (en) Prestressed concrete girder
JP2774066B2 (en) Floor slab made of PC version
KR100442969B1 (en) Method and its devices to strengthen a bridge by external prestressing cable
CN114941288B (en) Construction method for suspension bridge loose cable sleeve
KR200167491Y1 (en) Apparatus for connecting continuously upper slab concretes of multi-span preflex composite bridge and represtressed preflex composite bridge by P.C steel wire P.C steel bar.
KR200300029Y1 (en) Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon
JP2927671B2 (en) External cable installation method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees