JPH073809A - Construction method of cylindrical structure body - Google Patents

Construction method of cylindrical structure body

Info

Publication number
JPH073809A
JPH073809A JP16735693A JP16735693A JPH073809A JP H073809 A JPH073809 A JP H073809A JP 16735693 A JP16735693 A JP 16735693A JP 16735693 A JP16735693 A JP 16735693A JP H073809 A JPH073809 A JP H073809A
Authority
JP
Japan
Prior art keywords
steel
concrete
closed cell
unit closed
cylindrical structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP16735693A
Other languages
Japanese (ja)
Inventor
Masayuki Okimoto
真之 沖本
Noriyuki Hirozawa
規行 広沢
Hayao Yanagimoto
速雄 柳本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP16735693A priority Critical patent/JPH073809A/en
Publication of JPH073809A publication Critical patent/JPH073809A/en
Pending legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To enable the construction of a large-sized cylindrical structure body with high strength such as a caisson type pile, a bridge lower structure, etc., and to enable the construction of such a cylindrical structure body in the ground at a low cost. CONSTITUTION:Steel elements 3 forming double steel shells on lip hardwares 7 are subsequently fitted with joints to form cylindrical unit closing cells 2. The upper ends of the unit closing cells 2 are slipped in a zigzag shape for the adjacent steel elements 3 each other, so that horizontal connection sections 6 with the unit closing cells 2 are intermittent. The insides of the double steel shells of the steel elements 3 are filled with concrete, and a monolithic cylindrical structure body 1 of a steel and concrete composite structure is constructed. After the completion of the cylindrical structure body 1, underwater concrete is placed in the front end thereof, and the bottom concrete is placed thereon.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、土木、建築分野におい
て、深礎杭、橋梁下部工、立坑、地下タンク等として用
いられる筒状構造体の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a tubular structure used as a deep foundation pile, a bridge substructure, a shaft, an underground tank, etc. in the field of civil engineering and construction.

【0002】[0002]

【従来の技術】大型の構造物においても、施工の省力
化、高品質化、安全性の向上等を図るべく、プレキャス
ト化等による合理的な施工法の開発が望まれている。従
来知られている文献である「橋りょう下部工におけるプ
レキャスト化」(コンクリート工学、Vol.30,No.1
1, 1992年11月には、プレキャスト化の例とし
て、図14に示すような工場製作された円筒形のコンク
リート製単体ブロック21を施工地点で中掘り工法で沈
設させながら積み重ね、PC鋼棒22で接続し、ポスト
テンション方式によって鉛直方向にプレストレッシング
するPCウェル工法や、より口径の大きい筒状構造体に
ついて、図15に示すようにリング形状を分割したセグ
メント31形式の鉛直継手32および水平継手33を備
えた構造が示され、継手に関する検討が行われている。
また、特開平1−75710号公報には、貯液タンク、
その他の筒状構造体等の構築に適用するためのプレスト
レス構造体の製造法として、両端に継手を有する平行フ
ランジ鋼製エレメントを所定数継手嵌合して、二重鋼殻
構造の閉合セルを形成し、二重鋼殻内にコンクリートを
充填して鋼コンクリート合成構造とする方法が開示され
ている。
2. Description of the Related Art Even in a large structure, it is desired to develop a rational construction method by precasting in order to save construction work, improve quality, and improve safety. Previously known document "Precasting in bridge substructure" (Concrete Engineering, Vol.30, No.1)
1, In November 1992, as an example of precasting, a cylindrical concrete unit block 21 manufactured in a factory as shown in FIG. The vertical joint 32 and horizontal joint of the segment 31 type in which the ring shape is divided as shown in FIG. 15 for the PC well construction method in which the pre-tensioning method is used for prestressing in the vertical direction and the cylindrical structure having a larger diameter is connected. A construction with 33 is shown and a joint study is underway.
Further, Japanese Patent Laid-Open No. 1-75710 discloses a liquid storage tank,
As a method of manufacturing a prestressed structure for application to the construction of other tubular structures, etc., a predetermined number of parallel flange steel elements having joints at both ends are joint-fitted to form a closed cell with a double steel shell structure. Is disclosed and a method of forming a steel-concrete composite structure by filling concrete in a double steel shell is disclosed.

【0003】[0003]

【発明が解決しようとする課題】PCウェル工法は、上
記文献でも述べられているように、運搬上の制限や、施
工現場における種々の制約により、適用範囲が限られ
る。一方、リング形状を分割したセグメント形式のもの
は、地震力等に耐え得る信頼性の高い継手構造を実現す
るためには、継手構造が複雑となり、コストや施工製の
問題が生ずる。また、継手を減らすために、単位ブロッ
クあるいはセグメントを大きくすることも考えられる
が、ブロック等の単体重量が大きくなり、運搬やハンド
リングが困難になる。これに対し、特開平1−7571
0号公報記載の発明では、鋼管矢板形式の鋼製エレメン
トを用いているため、エレメント単体の重量は比較的小
さく、運搬性やハンドリングの面で有利であるが、現場
におけるコンクリートの充填を必要とし、構築される構
造体が大型化した場合の鉛直方向の上下端積み重ね接合
部での一体化、高強度化、さらに施工性等の面で改善の
余地がある。本発明は、大型で高強度の筒状構造体の構
築、さらにこのような筒状構造体の地中への構築を容易
に、かつ低コストで行う方法を提供することを目的とし
たものである。
The application range of the PC well method is limited due to transportation restrictions and various restrictions at the construction site, as described in the above-mentioned document. On the other hand, in the case of the segment type in which the ring shape is divided, in order to realize a highly reliable joint structure that can withstand seismic force, etc., the joint structure becomes complicated and problems of cost and construction arise. It is also possible to increase the size of the unit block or segment in order to reduce the number of joints, but the weight of the unit such as the block becomes large, which makes transportation and handling difficult. On the other hand, JP-A-1-7571
In the invention described in Japanese Patent Publication No. 0, since a steel pipe sheet pile type steel element is used, the weight of the element alone is relatively small, which is advantageous in terms of transportability and handling, but requires concrete filling on site. There is room for improvement in terms of integration at the vertically joined upper and lower ends of the structure, increased strength, and workability when the structure to be built becomes large. An object of the present invention is to provide a method for constructing a large-sized, high-strength tubular structure and further for constructing such a tubular structure in the ground easily and at low cost. is there.

【0004】[0004]

【課題を解決するための手段】本発明は、両端に継手3
Cを有する平行フランジ鋼製エレメント3を所定数継手
嵌合して、円筒形もしくは角筒形の二重鋼殻構造の閉合
セルの形成し、この二重鋼殻内にコンクリートを充填
し、コンクリートを固化させることにより鋼コンクリー
ト合成構造の筒状構造体を構築するに当り、隣接する所
定長の鋼製エレメント相互を上下方向に所定間隔千鳥状
にずらして継手嵌合することにより、上下端が鋸歯状の
単位閉合セル2を形成し、上下の単位閉合セル2どうし
を接合する継手位置が不連続となるようにして、順次、
上側に単位閉合セルを継ぎ足すことで、所定高さまたは
所定深さの筒状構造体を構築することを特徴とする。平
行フランジを有する鋼製エレメント3は、閉合セルの内
外面を形成する内外フランジと両フランジをつなぐ1ま
たは2以上のウェブ等から構成され、内外フランジの両
端に互いに嵌合する継手を設けたものである。鋼製エレ
メント3の本体は鋼板どうしを溶接したり、角形鋼管や
H形鋼等の形鋼を溶接したもの等を用いることができ
る。
According to the present invention, the joints 3 are provided at both ends.
A predetermined number of parallel flange steel elements 3 having C are joint-fitted to form a closed cell of a double steel shell structure of a cylindrical shape or a square tube shape, and the double steel shell is filled with concrete to form concrete. When constructing a tubular structure of a steel-concrete composite structure by solidifying, the adjacent upper and lower ends of the steel elements of predetermined lengths are staggered in a vertical direction at predetermined intervals to fit the joints. The sawtooth unit closed cells 2 are formed, and the joint positions for joining the upper and lower unit closed cells 2 are made discontinuous,
It is characterized in that a tubular structure having a predetermined height or a predetermined depth is constructed by adding unit closed cells to the upper side. The steel element 3 having parallel flanges is composed of an inner and outer flange forming the inner and outer surfaces of the closed cell and one or more webs connecting both flanges, etc., and joints are provided at both ends of the inner and outer flanges. Is. As the main body of the steel element 3, it is possible to use steel plates welded to each other, or a shape steel such as a square steel pipe or an H-shaped steel welded.

【0005】また、継手部分については、両端に継手を
有する鋼板矢板を半裁したものを溶接する等して製作す
ることができる。なお、継手形状は、鋼板矢板で多用さ
れている一体成形のものの他、鋼製エレメントの端部に
溶接したスリットパイプどうしを嵌合させる形式のも
の、スリットパイプを雌継手としてT形断面の雄継手を
嵌合する形式のもの等、特に限定されない。また、嵌合
部にはグラウト注入を行う等して、コンクリート等の流
出を防止する。筒状構造体が、深礎杭や立坑等、地下に
構築される場合は、下端に刃先金物を設置する等して、
単位閉合セルを、順次、地中に圧入しながら継ぎ足し、
内部の掘削等により所定深さまで沈設して行く。二重鋼
殻内へのコンクリートの打設は、施工条件等によって
は、複数の単位閉合セルを継ぎ足した後に行うこともで
きるが、単位閉合セルを形成する毎に、コンクリートの
充填、養生等を行い、ある程度強度を発現した状態で、
次の単位閉合セルを継ぎ足すようにすれば、施工時も構
造的に安定した状態での施工が可能となる。また、コン
クリートの養生と単位閉合セルどうしの接合を並行作業
とすることも可能である。特に、筒状構造体を地中に構
築する場合には、単位閉合セルを形成する毎に、コンク
リートの充填を行うのが好ましい。
Further, the joint portion can be manufactured by welding a half-cut steel sheet sheet pile having joints at both ends. In addition, the joint shape is not only the integrally formed one that is often used for steel sheet piles, but also the type in which slit pipes welded to the ends of steel elements are fitted together, and a male pipe with a T-shaped cross section using the slit pipe as a female joint. There is no particular limitation on the type in which a joint is fitted. Further, the fitting portion is subjected to grout injection or the like to prevent concrete or the like from flowing out. If the tubular structure is constructed underground, such as deep foundation piles or vertical shafts, install a cutting edge hardware at the lower end,
Unit-closed cells are successively added while being pressed into the ground,
It will be sunk to a specified depth by excavation inside. Depending on the construction conditions, etc., concrete can be poured into the double steel shell after adding multiple unit closing cells, but concrete filling and curing should be performed every time a unit closing cell is formed. Done, and with some strength developed,
If the following unit closed cells are added, construction can be performed in a structurally stable state during construction. It is also possible to perform concrete curing and joining of unit closed cells in parallel. In particular, when constructing the tubular structure in the ground, it is preferable to fill the concrete each time the unit closed cell is formed.

【0006】[0006]

【作用】本発明の構築方法は、両端に継手を有する平行
フランジ鋼製エレメントを千鳥状にずらして継手嵌合し
てなる単位閉合セルを、順次、継ぎ足して行くものであ
り、上下の単位閉合セルの接合位置を不連続とし、この
ようにして構成される円筒形もしくは角筒形の二重鋼殻
内にコンクリートを充填して結合一体化するため、高強
度、高剛性の筒状構造体を容易に構築することができ
る。
According to the construction method of the present invention, the parallel-flange steel elements having joints at both ends are staggered in a zigzag manner and the unit-closing cells formed by joint-fitting are successively added. A high-strength, high-rigidity cylindrical structure because the joining positions of cells are discontinuous and concrete is filled in the cylindrical or prismatic double steel shell constructed in this way to combine and integrate them. Can be easily constructed.

【0007】本発明の構築方法において使用する鋼製エ
レメントは、小分割されたものであり、ハンドリング性
に優れ、かつ従来の鋼矢板等と同様の継手嵌合式に接合
されるため、接合作業が容易で、信頼性に優れる。鋼製
エレメントは、運搬性にも優れ、工場製作された高強
度、高品質の鋼製エレメントを用い、コンクリートの充
填により鋼コンクリート合成構造として信頼性の高い筒
状構造体を構築することができる。鋼製エレメントを千
鳥状にずらして上下端を鋸歯状とした単位閉合セルを、
順次、地中に圧入しながら上側に単位閉合セルを継ぎ足
す工程を繰り返すことで、高強度、高剛性の筒状地中構
造体を構築することができる。また、コンクリートの充
填を単位閉合セルの形成毎行うことで、構造的に安定し
た状態での施工が可能である。
The steel element used in the construction method of the present invention is divided into small pieces, is excellent in handleability, and is joined in a joint fitting type similar to that of conventional steel sheet piles. Easy and reliable. The steel element has excellent transportability and uses a high-strength, high-quality steel element manufactured in the factory, and by filling concrete, a highly reliable tubular structure can be constructed as a steel-concrete composite structure. . A unit closed cell in which the steel elements are staggered and the upper and lower ends are serrated.
By sequentially repeating the process of adding the unit closed cells to the upper side while press-fitting into the ground, it is possible to construct a tubular underground structure having high strength and high rigidity. Further, by filling the concrete every time the unit closed cells are formed, it is possible to construct in a structurally stable state.

【0008】[0008]

【実施例】図1ないし図3は、本発明によって構築され
た筒状構造体の一実施例として、地中に設けられる立坑
の完成状態を示したものである。図中7は、構造体の地
中への圧入のための刃先金物であり、刃先金物7上に二
重鋼殻を構成する鋼製エレメント3を、順次、継手嵌合
して行くことにより単位閉合セル2を形成する。図中5
は継手3Cによる鉛直接合部を示す。単位閉合セル2の
上端は、隣接する鋼製エレメント3相互について千鳥状
にずらし、上側に継ぎ足す単位閉合セル2との水平接合
部6が不連続となるようにする。円筒形に閉合した鋼製
エレメント3による二重鋼殻内には、コンクリート4を
充填し、そのコンクリート4の固化により鋼コンクリー
ト合成構造の一体的な筒状構造体1が形成される。
1 to 3 show, as an example of a cylindrical structure constructed according to the present invention, a completed state of a shaft provided in the ground. Reference numeral 7 in the drawing denotes a cutting edge metal fitting for press-fitting the structure into the ground, and a steel element 3 forming a double steel shell is sequentially fitted onto the cutting edge metal fitting 7 to form a unit. The closed cell 2 is formed. 5 in the figure
Indicates a vertical joint by the joint 3C. The upper ends of the unit closed cells 2 are staggered with respect to the adjacent steel elements 3 so that the horizontal joint portion 6 with the unit closed cells 2 added to the upper side is discontinuous. Concrete 4 is filled in the double steel shell by the steel element 3 closed in a cylindrical shape, and by solidifying the concrete 4, an integral tubular structure 1 of a steel concrete composite structure is formed.

【0009】図4は、本発明で用いる鋼製エレメント3
の一例を示したもので、この例では鋼製エレメント3の
本体として角形鋼管3Aを用い、継手3Cを有する鋼矢
板の半裁体3bを角形鋼管3Aの4隅に平行に配置し溶
接している。
FIG. 4 shows a steel element 3 used in the present invention.
In this example, a rectangular steel pipe 3A is used as the main body of the steel element 3, and a half-cut body 3b of a steel sheet pile having a joint 3C is arranged parallel to the four corners of the rectangular steel pipe 3A and welded. .

【0010】図5は、図4の鋼製エレメント3を円筒形
に接続して二重鋼殻構造の単位閉合セル2を形成し、内
部にコンクリート4を充填した状態を部分的に示したも
のであり、継手3Cの隙間にグラウトを注入した後、コ
ンクリート4を充填する。
FIG. 5 partially shows a state in which the steel element 3 of FIG. 4 is connected in a cylindrical shape to form a unit closed cell 2 having a double steel shell structure and concrete 4 is filled inside. After pouring grout into the gap of the joint 3C, the concrete 4 is filled.

【0011】図6〜図13は、本発明の筒状構造体の構
築方法による施工手順の一例を示したもので、以下の工
程で施工を行う。 準備工(アースアンカー、刃先金物設置)〔図6参
照〕 立坑としての筒状構造体構築位置に、圧入の反力をとる
ためのアースアンカー11を施工する。地上部分には刃
先金物7を設置し、その上に仮設フレーム12を組み立
てる。
FIGS. 6 to 13 show an example of a construction procedure according to the method for constructing a tubular structure of the present invention. The construction is carried out in the following steps. Preparatory work (ground anchor, installation of cutting edge hardware) [Refer to FIG. 6] The ground anchor 11 for taking a reaction force of press-fitting is installed at a cylindrical structure building position as a vertical shaft. The cutting edge hardware 7 is installed on the ground portion, and the temporary frame 12 is assembled thereon.

【0012】 エレメント建込み、閉合、整形、仮付
溶接〔図7参照〕 仮設フレーム12を利用して、順次、鋼製エレメント3
を隣接する鋼製エレメント3と継手3Cどうしを嵌合さ
せながら建て込んで行く。鋼製エレメント3の上端が鋸
歯状になるよう千鳥状の配置を行う。なお、最下端と最
上端の閉合セル2については、長さの異なる鋼製エレメ
ント3を交互に配することで、千鳥状の配置とする。ま
た、継手3C部分は仮付溶接する。
Element installation, closing, shaping, temporary welding (see FIG. 7) Using the temporary frame 12, the steel element 3 is sequentially manufactured.
Are assembled while fitting the adjacent steel element 3 and the joints 3C. The steel elements 3 are arranged in a zigzag pattern so that the upper ends of the steel elements 3 are sawtooth. The closed cells 2 at the lowermost end and the uppermost end are staggered by alternately arranging steel elements 3 having different lengths. Further, the joint 3C portion is tack welded.

【0013】 継手部シール(グラウト充填)〔図8
参照〕 互いに嵌合させた継手3Cどうしの隙間にグラウト注入
を行い、継手部をシールする。
Joint seal (grouting) [Fig. 8
Reference] Grouting is performed in the gap between the fittings 3C fitted together, and the fitting is sealed.

【0014】 エレメント隔壁内コンクリート打設
〔図9参照〕 円筒形に閉合させた鋼製エレメント3による二重鋼殻内
にコンクリート4(図5参照)を打設し、コンクリート
4の養生(1日)後、仮設フレーム12(図1〜図3、
図4参照)を撤去する。
Concrete pouring in element partition wall (see FIG. 9) Concrete 4 (see FIG. 5) is placed in a double steel shell by steel elements 3 closed in a cylindrical shape, and curing of concrete 4 (1 day ) After that, the temporary frame 12 (FIGS. 1 to 3,
(See Fig. 4).

【0015】 圧入載荷装置設置〔図10参照〕 単位閉合セル2の上端に反力フレーム13を設置し、内
部を掘削しながら、アースアンカー11に反力をとった
センターホールジャッキ14により単位閉合セル2を地
盤中に圧入して行く。
Installation of press-fit loading device (see FIG. 10) A unit closing cell is installed by installing a reaction force frame 13 on the upper end of the unit closing cell 2 and excavating the inside thereof, and by using a center hole jack 14 which takes a reaction force to the earth anchor 11. Press 2 into the ground.

【0016】 エレメント建込み、閉合、整形、仮付
溶接(第2ステップ)〔図11参照〕 仮設フレーム12を組み立て、上記の工程と同様に鋼
製エレメント3を建て込み、地盤中に圧入した単位閉合
セル2の上側に新たな単位閉合セル2を接合して行く。
Element building, closing, shaping, temporary welding (second step) [see FIG. 11] A unit in which the temporary frame 12 is assembled and the steel element 3 is built in the same manner as the above process and press-fitted into the ground. A new unit closed cell 2 is joined to the upper side of the closed cell 2.

【0017】 前記工程の繰り返し〔図12参照〕 上記〜の工程を繰り返し、順次、筒状構造体を構築
しつつ、地盤中に圧入して行く。図中、15は内部掘削
用のバケットを示す。
Repeating the Steps (Refer to FIG. 12) The above steps (1) to (2) are repeated to sequentially form the cylindrical structure and press-fit it into the ground. In the figure, 15 indicates a bucket for internal excavation.

【0018】 底盤コンクリート打設、内装工事完成
〔図13参照〕 所定深さまで施工し、筒状構造体1を完成させた後、先
端部に水中コンクリート16を打設し、その上に底盤コ
ンクリート17を施工する。
Pouring of bottom concrete, completion of interior work (see FIG. 13) After the tubular structure 1 is completed by performing a predetermined depth, an underwater concrete 16 is placed at the tip, and the bottom concrete 17 is placed on it. Construct.

【0019】[0019]

【発明の効果】 本発明の構築方法によれば、鋼製エレメント3を千
鳥状にずらして継手3Cを嵌合してなる単位閉合セル2
を、順次、継ぎ足し、内部にコンクリート4を充填して
鋼コンクリート合成構造として結合一体化することによ
り、継手部が弱点とならない高強度、高剛性の筒状構造
体を容易に構築することができる。 小分割された鋼製エレメント3を用い、継手嵌合式
に接合するため、ハンドリング性に優れ、接合作業が容
易である。 地中構造体の場合にも、高強度、高剛性の筒状地中
構造体を施工性良く、低コストで構築することができ
る。 コンクリート4の充填を単位閉合セル2の形成毎に
行うことにより、構造的に安定した状態での施工が可能
である。
According to the construction method of the present invention, the unit closed cell 2 in which the steel elements 3 are staggered and the joints 3C are fitted thereinto
By sequentially adding and filling the interior with concrete 4 to join and integrate it as a steel-concrete composite structure, it is possible to easily construct a high-strength, high-rigidity tubular structure in which the joint portion does not become a weak point. . Since the steel elements 3 that are divided into small pieces are used for joining in a joint-fitting type, the handling is excellent and the joining work is easy. Also in the case of an underground structure, a high-strength, high-rigidity cylindrical underground structure can be constructed with good workability and at low cost. By filling the concrete 4 each time the unit closed cells 2 are formed, construction can be performed in a structurally stable state.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明を実施して構成された筒状構造体を示す
平面図である。
FIG. 1 is a plan view showing a tubular structure constructed by carrying out the present invention.

【図2】図1に示す筒状構造体の側面図である。FIG. 2 is a side view of the tubular structure shown in FIG.

【図3】図1に示す筒状構造体の鉛直断面図である。FIG. 3 is a vertical cross-sectional view of the tubular structure shown in FIG.

【図4】本発明で用いる鋼製エレメントの一例を示す平
面図である。
FIG. 4 is a plan view showing an example of a steel element used in the present invention.

【図5】図4の鋼製エレメントを用いて構築される筒状
構造体の一部を示す水平断面図である。
FIG. 5 is a horizontal cross-sectional view showing a part of a tubular structure constructed using the steel element of FIG.

【図6】本発明の一実施例における施工手順を示す鉛直
断面図である。
FIG. 6 is a vertical sectional view showing a construction procedure in one embodiment of the present invention.

【図7】図6に続く施工手順を示す鉛直断面図である。7 is a vertical cross-sectional view showing a construction procedure following FIG.

【図8】図7に続く施工手順を示す鉛直断面図である。FIG. 8 is a vertical cross-sectional view showing a construction procedure following FIG.

【図9】図8に続く施工手順を示す鉛直断面図である。9 is a vertical cross-sectional view showing a construction procedure following FIG.

【図10】図9に続く施工手順を示す鉛直断面図であ
る。
FIG. 10 is a vertical cross-sectional view showing a construction procedure subsequent to FIG.

【図11】図10に続く施工手順を示す鉛直断面図であ
る。
11 is a vertical cross-sectional view showing a construction procedure following FIG.

【図12】図11に続く施工手順を示す鉛直断面図であ
る。
12 is a vertical cross-sectional view showing a construction procedure following FIG.

【図13】図12に続く施工手順を示す鉛直断面図であ
る。
13 is a vertical cross-sectional view showing a construction procedure following FIG.

【図14】橋梁下部工に用いた従来の筒状構造体の一例
を示す正面図(一部断面図)である。
FIG. 14 is a front view (partially sectional view) showing an example of a conventional tubular structure used for a bridge substructure.

【図15】コンクリートセグメントによる筒状構造体の
従来例を示す斜視図である。
FIG. 15 is a perspective view showing a conventional example of a tubular structure made of concrete segments.

【符号の説明】[Explanation of symbols]

1 筒状構造体 2 単位閉合セル 3 鋼製エレメント 3A 角形鋼管 3B 鋼矢板半裁体 3C 継手 4 コンクリート 5 鉛直接合部 6 水平接合部 7 刃先金物 11 アースアンカー 12 仮設フレーム 13 反力フレーム 14 センターホールジャッキ 15 バケット 16 水中コンクリート 17 底盤コンクリート 1 Cylindrical structure 2 Unit closed cell 3 Steel element 3A Square steel pipe 3B Steel sheet pile half-cut body 3C Joint 4 Concrete 5 Vertical direct joint 6 Horizontal joint 7 Cutting edge hardware 11 Earth anchor 12 Temporary frame 13 Reaction frame 14 Center hole jack 15 Bucket 16 Underwater concrete 17 Bottom concrete

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 両端に継手3Cを有する平行フランジ鋼
製エレメント3を継手嵌合して、円筒形もしくは角筒形
の二重鋼殻構造の単位閉合セル2を形成し、前記二重鋼
殻内にコンクリート4を充填して鋼コンクリート合成構
造とする筒状構造体の構築方法において、隣接する鋼製
エレメント3の相互を上下方向に千鳥状にずらして継手
嵌合することにより、上下端が鋸歯状の単位閉合セル2
を形成し、順次、上側に単位閉合セル2を継ぎ足すこと
を特徴とする筒状構造体の構築方法。
1. A parallel flange steel element 3 having joints 3C at both ends is joint-fitted to form a unit closed cell 2 of a double steel shell structure of a cylindrical shape or a rectangular tube shape, and the double steel shell. In the method for constructing a tubular structure in which concrete 4 is filled into a steel-concrete composite structure, adjacent steel elements 3 are vertically staggered in a zigzag manner, and the joints are fitted to each other. Serrated unit closed cell 2
And a unitary closed cell 2 is added to the upper side one by one, and the cylindrical structure is constructed.
【請求項2】 上下端が鋸歯状の単位閉合セル2を、順
次、地中に圧入しながら上側に単位閉合セル2を継ぎ足
す請求項1の筒状構造体の構築方法。
2. The method for constructing a tubular structure according to claim 1, wherein the unit closed cells 2 having upper and lower ends having a serrated shape are successively inserted into the ground while the unit closed cells 2 are added to the upper side.
【請求項3】 単位閉合セル2を形成した後、該単位閉
合セル2の二重鋼殻内にコンクリート4を充填し、固化
させながら、順次、上側に単位閉合セル2を継ぎ足す請
求項1または2の筒状構造体の構築方法。
3. The unit closed cell 2 is formed, and then the double steel shell of the unit closed cell 2 is filled with concrete 4 and solidified, and the unit closed cell 2 is sequentially added to the upper side. Alternatively, the method of constructing the tubular structure of item 2.
JP16735693A 1993-06-15 1993-06-15 Construction method of cylindrical structure body Pending JPH073809A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16735693A JPH073809A (en) 1993-06-15 1993-06-15 Construction method of cylindrical structure body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16735693A JPH073809A (en) 1993-06-15 1993-06-15 Construction method of cylindrical structure body

Publications (1)

Publication Number Publication Date
JPH073809A true JPH073809A (en) 1995-01-06

Family

ID=15848208

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16735693A Pending JPH073809A (en) 1993-06-15 1993-06-15 Construction method of cylindrical structure body

Country Status (1)

Country Link
JP (1) JPH073809A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103422619A (en) * 2013-07-18 2013-12-04 杭州博数土木工程技术有限公司 Microwave shrinkage type connection structure of combined structure and construction technology

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103422619A (en) * 2013-07-18 2013-12-04 杭州博数土木工程技术有限公司 Microwave shrinkage type connection structure of combined structure and construction technology

Similar Documents

Publication Publication Date Title
JP4698491B2 (en) Temporary closing method and structure of underwater structure
JP4326908B2 (en) Retaining wall and method for constructing retaining wall
JP2008019608A (en) Steel pipe sheet pile, steel pipe sheet pile wall, steel pipe for pipe roof and pipe roof
JPH11117315A (en) Temporary cofferdam structure
JP2000265458A (en) Floor slab connecting structure for underground structure with precast pile underground wall
JP2001107319A (en) Aseismic reinforcing method of pier and aseismic reinforced structure
CN212801564U (en) Foundation ditch steel sheet pile supporting construction
JP2000265484A (en) CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL
JPH08284159A (en) Connection structure of pile head
JP4576067B2 (en) Joint structure of pile head and steel underground beam
JP3670240B2 (en) How to raise the earth wall
JPH073809A (en) Construction method of cylindrical structure body
CN211873023U (en) Foundation pit supporting device
JP2784317B2 (en) Open caisson structure
CN111119200A (en) Foundation pit supporting device
JP2933582B1 (en) Bridge pier reinforcement method
CN114059555B (en) Construction method of arc-shaped foundation pit supporting system based on anchoring structure
JP2007051500A (en) Joint structure of column and pile
JPS6026724A (en) Integration work of steel-framed building structure and composite underground beam
RU97140U1 (en) COMPOUND PILET JOINT
JPH09324418A (en) Foundation pile structure and construction method therefor
JPH01315520A (en) Underground outer wall constructing method for superstructure
CN210163934U (en) Cast-in-place pile formwork system
JP3082053B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JPH0790875B2 (en) Body structure of PC egg digester