CN108330952A - The manufacturing method of steel wall - Google Patents

The manufacturing method of steel wall Download PDF

Info

Publication number
CN108330952A
CN108330952A CN201810196043.XA CN201810196043A CN108330952A CN 108330952 A CN108330952 A CN 108330952A CN 201810196043 A CN201810196043 A CN 201810196043A CN 108330952 A CN108330952 A CN 108330952A
Authority
CN
China
Prior art keywords
wall
steel
steel pipe
wall body
sheet pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810196043.XA
Other languages
Chinese (zh)
Inventor
永尾直也
田中宏征
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to CN201810196043.XA priority Critical patent/CN108330952A/en
Publication of CN108330952A publication Critical patent/CN108330952A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/066Quays
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Composite Materials (AREA)
  • Chemical & Material Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明提供一种钢制墙,该钢制墙用钢管或者H型钢来加固墙体且施工容易,该墙体由能够容易地保持高止水性的钢板桩连结而成。设有利用接头连结多个帽型钢板桩而成的墙体。加固墙体的钢管沿着墙体的长度方向并列设置。在墙体和钢管之间设有间隔。墙体作为钢板桩墙并形成为在长度方向上反复凹凸的波板状。钢管以钢管的一部分进入墙体的凹部的方式配置。墙体的头部和钢管的头部相连结着。墙体和钢管之间利用混凝土进行连结。负载在墙体和钢管之间传递。由此,钢制墙能够形成由墙体和钢管分担承受钢制墙所受到的土压、水压的结构。

The present invention provides a steel wall, which uses steel pipes or H-shaped steel to reinforce the wall body and is easy to construct, and the wall body is connected by steel sheet piles that can easily maintain high water-tightness. There is a wall formed by connecting multiple hat-shaped steel sheet piles with joints. The steel pipes that reinforce the wall are arranged side by side along the length of the wall. A spacer is provided between the wall and the steel pipe. The wall body is a steel sheet pile wall and is formed in a corrugated plate shape in which unevenness is repeated in the longitudinal direction. The steel pipes are arranged so that a part of the steel pipes enters the concave portion of the wall. The head of the body of wall is connected with the head of the steel pipe. Concrete is used to connect the walls and steel pipes. The load is transferred between the wall and the steel pipe. Thus, the steel wall can form a structure in which the wall body and the steel pipe share the earth pressure and water pressure suffered by the steel wall.

Description

钢制墙的制造方法How to make steel walls

本申请是国际申请日为2012年5月1日(进入中国国家阶段日期:2014年10月31日)、国际申请号为PCT/JP2012/061574(中国国家申请号为201280072877.0)、发明名称为“钢制墙”的申请的分案申请。This application has an international filing date of May 1, 2012 (date of entering the Chinese national phase: October 31, 2014), an international application number of PCT/JP2012/061574 (Chinese national application number of 201280072877.0), and an invention title of " A divisional application of the application for "Steel Wall".

技术领域technical field

本发明涉及一种用于水土保持、围堰、护岸、填筑、堤坝等的钢制墙的制造方法。The invention relates to a method for manufacturing steel walls used for soil and water conservation, cofferdams, revetment, filling, embankments and the like.

背景技术Background technique

以往,钢板桩、钢管板桩用于水土保持、围堰、护岸、填筑、堤坝等的各种工事。钢板桩和钢管板桩根据所要求的刚性而分别使用。通常,钢板桩在即使刚性较低也可以的情况下使用,钢管板桩在刚性要求较高的情况下使用。Conventionally, steel sheet piles and steel pipe sheet piles have been used for various constructions such as soil and water conservation, cofferdams, bank revetments, landfills, and embankments. Steel sheet piles and steel pipe sheet piles are used according to the required rigidity. Generally, steel sheet piles are used when low rigidity is acceptable, and steel pipe sheet piles are used when high rigidity is required.

在此,钢管板桩的接头的宽余量比钢板桩的接头的宽余量大。因而,在当建造围堰、护岸等时要求止水性的情况下,通常采用在接头空间填充袋装的水泥砂浆的方法。该方法在用于河流·港湾等的水边环境的情况下,有可能导致当装满砂浆的袋破损时砂浆流出。另外,由于袋彼此之间的间隙能变成充满水,因此不一定适合于严格要求止水性的用途。Here, the margin of the joint of the steel pipe sheet pile is larger than the margin of the joint of the steel sheet pile. Therefore, when water-tightness is required when constructing cofferdams, bank revetments, etc., a method of filling the joint space with bagged cement mortar is generally employed. When this method is used in waterside environments such as rivers and harbors, there is a possibility that mortar will flow out when a bag filled with mortar is damaged. In addition, since the gap between the bags may become filled with water, it is not necessarily suitable for applications that strictly require water-tightness.

因此,作为在如海面废弃物处理场等的挡水性护岸等那样严格要求防止处理场内部的水泄漏的情况下的对策,提出有以下的方案。即,提出有对钢管板桩的接头空间实施防止泄漏措施而将砂浆等的填充剂直接填充于该接头空间的结构的方案(例如,参照专利文献1)。在如此填充砂浆的情况下,将钢管板桩打入地下后,需要进行通过高压水喷射等来排出接头内部的土沙从而将砂浆、袋状的砂浆填充在接头内的工作。因而,存在钢管板桩的现场工作费时费力的缺点。Therefore, the following proposals have been proposed as countermeasures when it is strictly required to prevent water leakage inside the disposal site, such as water-blocking bank revetments in marine waste disposal sites. That is, there has been proposed a structure in which leakage prevention measures are taken for joint spaces of steel pipe sheet piles, and fillers such as mortar are directly filled in the joint spaces (for example, refer to Patent Document 1). In the case of filling mortar in this way, after the steel pipe sheet pile is driven into the ground, it is necessary to discharge soil and sand inside the joint by high-pressure water jets, etc., and to fill the joint with mortar or bag-shaped mortar. Therefore, there is a disadvantage that the on-site work of the steel pipe sheet pile is time-consuming and laborious.

对此,虽然钢板桩的刚性比钢管板桩的刚性低,但是止水性优异,接头部分的游隙小,即使在不实施任何措施的状态下止水性也比钢管板桩的高。另外,通过事先对接头涂装膨润性止水材料,也能够进一步提高钢板桩的止水性。通过该方法,除了能够发挥与实施了上述措施的钢管板桩同等以上的止水性能之外,还能够节约现场工作的劳力。On the other hand, although the rigidity of the steel sheet pile is lower than that of the steel pipe sheet pile, it is excellent in water stop performance, and the play of the joint part is small, and the water stop performance is higher than that of the steel pipe sheet pile even in the state where no measures are taken. In addition, the water-stopping properties of the steel sheet pile can be further improved by coating the joints with a swelling water-stopping material in advance. According to this method, in addition to exhibiting a water-tight performance equivalent to or higher than that of the steel pipe sheet pile implemented above, it is also possible to save the labor of on-site work.

因此,作为提高钢板桩的刚性的技术,公知有利用拉杆连结作为护岸的钢板桩墙和设于比护岸靠陆地侧的位置的支柱的拉杆式钢板桩护岸等拉杆式的钢板桩墙。Therefore, as a technique for improving the rigidity of the steel sheet pile, tie-type steel sheet pile walls such as a tie-type steel sheet pile revetment in which a steel sheet pile wall serving as a revetment and a pillar provided on the land side of the revetment are connected by tie rods are known.

在拉杆式的钢板桩墙中,为了将钢板桩墙和支柱用较长的拉杆连结,需要较大的施工空间。In the tie-rod type steel sheet pile wall, in order to connect the steel sheet pile wall and the pillar with a long tie rod, a large construction space is required.

另外,同样在拉杆式的钢板桩墙中,由于用较长的拉杆将钢板桩墙和支柱连结,拉杆只能够传递拉力而不能够传递压缩力。In addition, also in the steel sheet pile wall of the tie rod type, since the steel sheet pile wall and the pillar are connected by a long tie rod, the tie rod can only transmit the tension force but not the compressive force.

而且,作为提高钢板桩的刚性的技术,提出有采用将H型钢与构成墙体的U形(帽型)钢板桩一体化而加强了刚性的组合钢板桩的方案(例如,参照专利文献2)。由于这样结构的组合钢板桩的截面面积变大且打设时的阻力变大,因此施工方法受到限定。特别地,在硬质地基上的施工变难。Furthermore, as a technique for improving the rigidity of the steel sheet pile, it has been proposed to adopt a combined steel sheet pile in which H-shaped steel is integrated with a U-shaped (hat-shaped) steel sheet pile constituting the wall to enhance rigidity (for example, refer to Patent Document 2). . Since the cross-sectional area of the combination steel sheet pile of such a structure becomes large and the resistance at the time of driving becomes large, the construction method is limited. In particular, construction on hard ground becomes difficult.

因此,为了在硬质地基上施工,考虑采用使用了挖掘地基的地螺钻(挖掘装置)的施工方法。但是,由于组合钢板桩的截面形状跨越范围广,因此需要研究对策。作为该对策的一例,在紧密架设类似于专利文献2的组合钢板桩的结构的组合钢板桩的情况下,提出有采用以下所示的施工方法的方案(例如,参照专利文献3)。即,提出有以跨越当打设上述组合钢板桩时用地螺钻挖掘的范围和当紧密架设在该组合钢板桩之前被打设了的组合钢板桩时用地螺钻挖掘成的范围的方式打设上述组合钢板桩的施工方法的方案。Therefore, in order to construct on a hard ground, a construction method using a ground auger (excavation device) for excavating the ground is considered. However, since the cross-sectional shape of the combined steel sheet pile spans a wide range, it is necessary to study countermeasures. As an example of this measure, when erecting the combination steel sheet pile of the structure similar to the combination steel sheet pile of patent document 2 closely, it proposes to adopt the construction method shown below (for example, refer patent document 3). That is, it is proposed to drive in a manner that spans the range excavated with a ground auger when driving the above-mentioned combined steel sheet pile and the range excavated with a ground auger when the combined steel sheet pile that was driven before the combined steel sheet pile is erected closely The proposal of the construction method of the said combination steel sheet pile.

现有技术文献prior art literature

专利文献patent documents

专利文献1:日本专利第3756755号公报Patent Document 1: Japanese Patent No. 3756755

专利文献2:日本特开2002-212943号公报Patent Document 2: Japanese Unexamined Patent Publication No. 2002-212943

专利文献3:日本专利第4074241号公报Patent Document 3: Japanese Patent No. 4074241

发明内容Contents of the invention

发明要解决的问题The problem to be solved by the invention

如上所述,作为钢制墙的刚性,钢管板桩墙的刚性高于钢板桩墙的刚性。然而,钢板桩墙的接头的止水性能比钢管板桩墙的接头的止水性能容易提高。As described above, as the rigidity of the steel wall, the rigidity of the steel pipe sheet pile wall is higher than that of the steel sheet pile wall. However, the watertight performance of the joint of the steel sheet pile wall is easier to improve than the watertight performance of the joint of the steel pipe sheet pile wall.

因此,如上述专利文献2所示,通过将型钢组合在容易提高止水性能的钢板桩墙,能够建造兼备刚性和较高的止水性能的钢制墙。Therefore, as shown in the above-mentioned Patent Document 2, by combining section steel with the steel sheet pile wall which is easy to improve waterproof performance, it is possible to construct a steel wall having both rigidity and high waterproof performance.

但是,通过组合钢板桩和型钢,截面面积变大。因而,如上所述,能够使用的施工方法受到限制。However, the cross-sectional area becomes larger by combining the steel sheet pile and the section steel. Therefore, as described above, usable construction methods are limited.

在此,考虑使钢板桩和型钢成为接触的状态,并用型钢加固由钢板桩形成的钢板桩墙(墙体),而不成为将钢板桩和型钢等的加固件接合成为一体。在这种情况下,也能够分别对型钢等的加固件和钢板桩单独地进行施工。但是,在分别对钢板桩和加固件单独地进行施工的情况下,对于在先施工的构件,当在使在后施工的构件与在先施工的构件接触的状态下打设在后施工的构件时产生以下的问题。即,由于钢板桩和加固件的滑动阻力,在打设时需要较大的力,另外,有可能产生噪音、振动。根据施工精度,这些钢板桩和加固件的任意一个都有产生变形的可能性。另外,为了在使在后施工的构件与在先施工的构件接触的状态下打设在后施工的构件,在后打设的构件的施工方法受到限制。例如,难以将作为加固件的钢管旋转压入,并且难以采用使构件振动而打设的振动式的施工方法。Here, it is considered that the steel sheet pile and the section steel are brought into contact, and the steel sheet pile wall (wall body) formed of the steel sheet pile is reinforced with the section steel, instead of integrally joining the steel sheet pile and the reinforcement such as the section steel. In this case, reinforcement materials, such as a section steel, and a steel sheet pile can also be constructed individually, respectively. However, when the steel sheet piles and reinforcements are separately constructed, for the member constructed earlier, the member constructed later shall be driven in a state where the member constructed later is in contact with the member constructed earlier. The following problems arise. That is, due to the sliding resistance of the steel sheet pile and the reinforcing material, a large force is required at the time of driving, and noise and vibration may be generated. Either of these steel sheet piles and reinforcements may be deformed depending on construction accuracy. In addition, in order to drive the member to be constructed later in a state in which the member to be constructed later is brought into contact with the member to be constructed earlier, the construction method of the member to be constructed later is limited. For example, it is difficult to rotationally press-fit a steel pipe as a reinforcement, and it is difficult to employ a vibratory construction method in which members are vibrated and drilled.

本发明是鉴于上述情况而完成的,其目的在于提供一种钢制墙,该钢制墙用钢管或者H型钢来加固墙体且施工容易,该墙体由能够容易地保持高止水性的钢板桩连结而成。The present invention has been accomplished in view of the above circumstances, and its object is to provide a steel wall that is reinforced with steel pipes or H-shaped steel and that is easy to construct. The wall is made of steel plates that can easily maintain high water-tightness. The piles are connected.

用于解决问题的方案solutions to problems

为了解决上述课题,本发明的钢制墙的特征在于,利用接头连结多根钢板桩而设置在长度方向上反复凹凸的波板状的墙体,用于加固上述墙体的由钢管或者H型钢形成的多个加固件沿着上述墙体的长度方向、与上述墙体隔开间隔地并列设置,形成为上述加固件的一部分进入上述墙体的凹部内的状态,上述墙体和上述加固件在头部相连结。In order to solve the above-mentioned problems, the steel wall of the present invention is characterized in that a plurality of steel sheet piles are connected by joints to form a corrugated wall with repeated unevenness in the longitudinal direction, and steel pipes or H-shaped steel for reinforcing the above-mentioned walls A plurality of reinforcing members formed are arranged side by side at a distance from the wall along the longitudinal direction of the wall, and are formed in a state where a part of the reinforcing member enters a recess of the wall, and the wall and the reinforcing member Join at the head.

在本发明中,因为墙体和加固件分离,所以对施工方法的限制较少,能够根据状况选择采用能够将作为加固件的钢管、H型钢打设于地基的各种施工方法。In the present invention, because the wall body and the reinforcement are separated, there are few restrictions on the construction method, and various construction methods that can be used as the reinforcement steel pipe and H-shaped steel to be drilled into the foundation can be selected according to the situation.

即,因为墙体和加固件分离着,所以能够分别单独地进行将钢板桩打设于地基并且对钢板桩之间进行连结来构筑墙体的施工和将加固件打设于地基的施工。除此之外,因为这些墙体和加固件之间未接触,所示施工变得容易。例如,通过在墙体和加固件之间设置间隔,能够通过振动打设锤施工方法来进行施工。另外,加固件为钢管的情况下也能够通过旋转压入的施工方法进行施工。另外,不言而喻,也能够实施油压压入施工方法等的静态压入施工方法。这样,因为施工方法的限制较少,所以能够根据状况选择采用能够将钢管、H型钢打设于地基的各种施工方法。That is, since the wall and the reinforcement are separated, the construction of driving the steel sheet piles to the foundation and connecting the steel sheet piles to construct the wall and the construction of driving the reinforcement to the foundation can be performed separately. In addition, the construction shown is facilitated because there is no contact between these walls and reinforcements. For example, by providing a space between the wall body and the reinforcement, construction can be performed by a vibrating hammer construction method. In addition, when the reinforcing material is a steel pipe, it can also be constructed by the construction method of rotary press fitting. In addition, it goes without saying that a static press-fit construction method such as a hydraulic press-fit construction method can also be implemented. In this way, since there are few restrictions on the construction method, various construction methods capable of driving steel pipes and H-shaped steel into the foundation can be selected and adopted according to the situation.

另外,能够获得与以往的钢板桩墙相同的高止水性能。In addition, it is possible to obtain the same high waterproof performance as the conventional steel sheet pile wall.

另外,不需要像拉杆式的墙体结构那样的宽广的施工空间。特别是,由于加固件进入墙体的凹部侧,因此能够形成小于钢板桩高度和钢管径之和的墙的宽度,能够节省施工空间地建造钢制墙。In addition, there is no need for a wide construction space like a tie-rod wall structure. In particular, since the reinforcing member enters the concave portion side of the wall body, the width of the wall can be formed smaller than the sum of the height of the steel sheet pile and the diameter of the steel pipe, and a steel wall can be constructed with a space-saving construction.

另外,能够形成如下结构,由于加固件进入墙体的凹部侧使加固件和墙体的距离变短,与拉杆式的钢板桩墙不同,在加固件和墙体在头部相连结的情况下,能够传递拉伸力和压缩力的双方。In addition, it is possible to form a structure in which the distance between the reinforcing member and the wall is shortened because the reinforcing member enters the concave portion side of the wall. Unlike the tie-rod type steel sheet pile wall, when the reinforcing member and the wall are connected at the head , capable of transmitting both tensile and compressive forces.

即,在土压、水压作用于钢制墙的情况下,因为墙体的头部和加固件的头部相连结着,所以能够进行负载在墙体和加固件之间的传递。由此,钢制墙能够形成由墙体和钢管分担承受钢制墙所受到的土压、水压的结构。另外,通过将墙体的头部和加固件的头部连结并进行固定,能够限制墙体和加固件的垂直方向的错位,并传递剪切力。That is, when earth pressure and water pressure act on the steel wall, since the head of the wall and the head of the reinforcement are connected, load can be transmitted between the wall and the reinforcement. Thus, the steel wall can form a structure in which the wall body and the steel pipe share the earth pressure and water pressure suffered by the steel wall. In addition, by connecting and fixing the head portion of the wall body and the head portion of the reinforcing member, vertical misalignment between the wall body and the reinforcing member can be restricted, and shear force can be transmitted.

另外,如果是拉杆式钢板桩结构,则为了使作用于在墙体延长方向上离散配置的拉杆的力分散而使墙体动作一致,需要横撑件。但是,在本发明中,加固件进入凹部侧,并在短距离传递力,因此不需要横撑件。In addition, in the tie-rod type steel sheet pile structure, a cross brace is required in order to disperse the force acting on the tie rods arranged discretely in the wall extending direction and to make the wall move uniformly. However, in the present invention, the reinforcement enters the side of the recess and transmits the force over a short distance, so the cross brace is not required.

特别是在每隔开一个或者隔开多个钢板桩地相对钢板桩配置加固件的情况下,若加固件和钢板桩之间空出间隔,则加固件产生部分效果,因此需要横撑件等的在延长方向上分散力的构件。但是,由于加固件进入墙体的凹部,因此即使对于未设置有加固件的钢板桩,加固件也能够产生效果,不需要横撑件等。In particular, when a reinforcing member is placed against the steel sheet piles at intervals of one or several steel sheet piles, if there is a gap between the reinforcing member and the steel sheet pile, the reinforcing member will have a partial effect, so cross braces, etc. are required A member that distributes forces in the direction of elongation. However, since the reinforcing material enters the recessed part of the wall body, the reinforcing material can produce an effect even for the steel sheet pile that is not provided with the reinforcing material, and a cross brace or the like is unnecessary.

此外,实施了如下室内试验,在宽度1957mm×高度1000mm×进深940mm的坚固的土槽内的中央,利用粘接剂将模拟了钢板桩墙的波形的丙烯酸板和模拟了钢管的丙烯管的下端固定,利用空中落下法在波形的丙烯酸板左右设置了硅砂5号(干燥沙),从该状态将丙烯酸板的单侧深挖到下端为止,确认墙体的变化。通过该实验,确认到,如果钢管的节距为墙高的4/7以下,通过将加固件以进入墙体的凹部的方式配置且连结加固件的头部和墙体的头部,则对于跳过的加固件的间隔的部分也产生加固件的效果。因而,优选的是,加固件的节距L和墙高H满足L≤4H/7。In addition, an indoor test was carried out. In the center of a solid soil tank with a width of 1957 mm x a height of 1000 mm x a depth of 940 mm, an acrylic plate imitating the corrugation of a steel sheet pile wall and the lower end of an acrylic pipe imitating a steel pipe were bonded with an adhesive. Fix it, and set silica sand No. 5 (dry sand) on the left and right sides of the corrugated acrylic board by the air drop method, and from this state, dig deep from one side of the acrylic board to the lower end to check the change of the wall. Through this experiment, it was confirmed that if the pitch of the steel pipes is 4/7 or less of the wall height, by arranging the reinforcing member so as to enter the concave portion of the wall and connecting the head of the reinforcing member and the head of the wall, the Spacing parts of the reinforcement that are skipped also produce the effect of the reinforcement. Therefore, it is preferable that the pitch L of the reinforcement and the wall height H satisfy L≦4H/7.

在本发明的上述结构中,优选的是,上述墙体和上述加固件利用跨越上述墙体的头部和上述加固件的头部而打设成的混凝土在头部相连结。In the above structure of the present invention, it is preferable that the wall body and the reinforcement member are connected at the head portion by concrete laid across the head portion of the wall body and the head portion of the reinforcement member.

根据这样的结构,因为形成由跨越加固件的头部和墙体的头部而打设的混凝土连结加固件的头部和墙体的头部的结构,所以能够形成不暴露钢管的头部(上端部)、钢板桩的头部(上端部)而由混凝土覆盖的结构。由此,能够提高钢制墙的美观。另外,因为以跨越加固件和墙体的方式打设混凝土,所以钢管和墙体之间的顶端倒塌等的危险性较少。According to such a structure, since the head of the reinforcing member and the head of the wall are connected by the concrete laid across the head of the reinforcing member and the head of the wall, it is possible to form the head without exposing the steel pipe ( upper end), and the head (upper end) of the steel sheet pile is covered with concrete. Thereby, the appearance of a steel wall can be improved. In addition, since the concrete is drilled so as to straddle the reinforcing member and the wall, there is less risk of collapse of the tip between the steel pipe and the wall.

另外,在本发明的上述结构中,优选的是,上述墙体和上述加固件通过将设置于上述墙体和上述加固件之间的钢板分别焊接接合于上述墙体和上述加固件而在头部相连结。In addition, in the above-mentioned structure of the present invention, it is preferable that the above-mentioned wall body and the above-mentioned reinforcing member are welded and joined to the above-mentioned wall body and the above-mentioned reinforcing member respectively by the steel plates provided between the above-mentioned wall body and the above-mentioned reinforcing member. The parts are connected.

根据这样的结构,因为钢板和加固件在头部的连结是将钢板焊接于加固件和墙体而进行的,所以施工轻松且施工花费的时间和劳力较少。例如,不需要像拉杆式的情况那样在钢板桩、钢管板桩开使拉杆穿过的孔并使拉杆穿过该孔所花费的时间和劳力。另外,在与打设上述的混凝土的情况相比较的情况下,不需要混凝土的养护期,能够实现施工期的缩短。According to such a structure, since the connection of the steel plate and the reinforcement at the head is performed by welding the steel plate to the reinforcement and the wall, construction is easy and requires less time and labor for construction. For example, the time and labor required to open a hole through which a tie rod is inserted in a steel sheet pile or a steel pipe sheet pile and to pass the tie rod through the hole are unnecessary like in the case of the tie rod type. In addition, when compared with the case of placing the above-mentioned concrete, the curing period of the concrete is unnecessary, and the construction period can be shortened.

另外,在本发明的上述结构中,除了通过将设置于上述墙体和上述加固件之间的钢板分别焊接接合于上述墙体和上述加固件来将上述墙体和上述加固件在头部相连结之外,还可以利用跨越上述墙体和上述加固件的头部而打设成的混凝土将上述墙体和上述加固件在头部连结。In addition, in the above-mentioned structure of the present invention, in addition to welding the steel plates provided between the above-mentioned wall body and the above-mentioned reinforcement member to the above-mentioned wall body and the above-mentioned reinforcement member respectively, the above-mentioned wall body and the above-mentioned reinforcement member are connected at the head. In addition to the connection, the wall and the reinforcing member may be connected at the head using concrete laid across the head of the wall and the reinforcing member.

根据这样的结构,因为组合利用焊接钢板进行的连结和利用混凝土进行的连结,所以可以互补美观和强度。例如,混凝土在传递连结部分的压缩力的方面优异,被焊接的钢板在传递连结部分的拉伸力的方面优异,因此能够互补强度。另外,能够对钢板引起的拉伸力的传递的提高和混凝土引起的景观美化(环境布置)以及安全措施(例如,防止顶端塌落)进行互补。According to such a structure, since the connection by the welded steel plate and the connection by concrete are combined, beauty and strength can complement each other. For example, concrete is excellent in transmitting the compressive force of the connecting portion, and welded steel plates are excellent in transmitting the tensile force of the connecting portion, so they can complement each other in strength. In addition, enhancement of transmission of tensile force by steel plates and landscaping (environmental arrangement) and safety measures (eg, prevention of tip collapse) by concrete can be complemented.

另外,在本发明的上述结构中,优选的是,上述加固件为上述钢管。Moreover, in the said structure of this invention, it is preferable that the said reinforcing material is the said steel pipe.

根据这样的结构,能够通过采用钢管作为加固件来获得较高的刚性,并且能够采用旋转压入施工方法、中掘施工方法,并容易进行抑制了噪音、振动的施工。According to such a structure, high rigidity can be obtained by using a steel pipe as a reinforcement, and the rotary press-fitting construction method and the mid-piercing construction method can be used, and the construction which suppressed noise and vibration can be performed easily.

另外,在本发明的上述结构中,优选的是,上述墙体和上述加固件之间设定有使上述墙体的上述钢板桩和上述加固件在施工中不会接触的间隔。Moreover, in the said structure of this invention, it is preferable that the space|interval which prevents the said steel sheet pile of the said wall body and the said reinforcement material from contacting during construction is set between the said wall body and the said reinforcement material.

根据这样的结构,在对墙体和加固件进行施工时,墙体的钢板桩和加固件在施工中不会接触,能够防止上述的墙体和加固件在施工中由于接触产生的问题。According to such a structure, when constructing a wall body and a reinforcement, the steel sheet pile of a wall and a reinforcement do not contact during construction, and can prevent the above-mentioned problem which arises from the contact of a wall and reinforcement during construction.

另外,在本发明的上述结构中,可以是,上述加固件设于上述墙体的承受相对较大的压力的侧。Moreover, in the said structure of this invention, the said reinforcing material may be provided in the side which receives relatively large pressure of the said wall body.

根据这样的结构,由于在承受相对较大的压力(土压、水压)的面的侧设置有加固件,因此墙体和加固件均承受压力。在这种情况下,负载向自加固件分离的方向作用于墙体。在此,由于是墙体的头部和加固件的头部相连结,负载在墙体和加固件之间传递(拉伸力的传递)的结构,因此能够由墙体和加固件分担承受负载。因而,即使将加固件配置于墙体的承受相对较大的压力的侧,也能够通过将加固件组合于墙体,充分实现强度的提高。另外,在将钢制墙用作例如护岸、水土保持墙等的情况下,加固件配置于背面侧。因而,在钢制墙上部的暴露侧,因为形成只有墙体的侧面露出而加固件被隐藏的状态,所以形成外观不复杂、美观性优异的钢制墙。According to such a structure, since the reinforcement is provided on the side of the surface receiving relatively large pressure (earth pressure, water pressure), both the wall body and the reinforcement receive pressure. In this case, the load acts on the wall in the direction of separation from the reinforcement. Here, since the head of the wall and the head of the reinforcement are connected, the load is transmitted between the wall and the reinforcement (transmission of tensile force), so the load can be shared by the wall and the reinforcement. . Therefore, even if the reinforcement is arranged on the side of the wall body that receives relatively high pressure, it is possible to sufficiently improve the strength by combining the reinforcement with the wall. Moreover, when using a steel wall as a revetment, a soil and water conservation wall, etc., for example, a reinforcing material is arrange|positioned on the back side. Therefore, on the exposed side of the upper part of the steel wall, only the side surface of the wall body is exposed and the reinforcement is hidden, so that a steel wall with an uncomplicated appearance and excellent aesthetics is formed.

另外,在本发明的上述结构中,也可以是,上述加固件设于上述墙体的与承受相对较大的压力的侧相反的侧。Moreover, in the said structure of this invention, the said reinforcing material may be provided in the side opposite to the side which receives relatively large pressure of the said wall body.

根据这样的结构,由于上述加固件设于墙体的与承受相对较大的压力的侧相反的侧,因此土压、水压作用于墙体。在这种情况下,负载在墙体和加固件的连结部分自墙体传递(传递压缩力)至加固件,能够由墙体和加固件分担承受土压、水压。另外,在用作护岸、水土保持墙等的情况下,加固件配置于墙体的前面侧即上部暴露侧。因而,例如,在施工时不需要为了露出加固件的头部而进行挖掘,能够容易地补修露出状态的加固件、以及加固件和墙体的连结部分。According to such a structure, since the said reinforcing material is provided in the side of the wall body opposite to the side receiving relatively large pressure, earth pressure and water pressure act on the wall body. In this case, the load is transmitted from the wall (transmits compressive force) to the reinforcement at the connecting portion of the wall and the reinforcement, and the wall and reinforcement can bear the earth pressure and water pressure in a shared manner. In addition, when using as a revetment, a soil and water conservation wall, etc., the reinforcement is arrange|positioned at the front side of a wall body, ie, the upper part exposure side. Therefore, for example, excavation is not required to expose the head of the reinforcing member during construction, and the exposed reinforcing member and the connection portion between the reinforcing member and the wall can be easily repaired.

发明的效果The effect of the invention

根据本发明,能够获得与以往的钢板桩墙相同的高止水性能,并且能够通过使负载传递到加固件来减小在墙体上产生的弯曲力矩。另外,虽然是组合了钢板桩和钢管或者H型钢的结构,但是能够分别对钢板桩和钢管或者H型钢单独地进行施工,因此能够容易地施工。According to the present invention, the same high waterproof performance as that of the conventional steel sheet pile wall can be obtained, and the bending moment generated in the wall body can be reduced by transmitting the load to the reinforcement. Moreover, although it is the structure which combined a steel sheet pile, a steel pipe, or an H-shaped steel, since the steel sheet pile, a steel pipe, or an H-shaped steel can be constructed individually, construction can be performed easily.

附图说明Description of drawings

图1是表示本发明的第1实施方式的钢制墙的概略俯视图。Fig. 1 is a schematic plan view showing a steel wall according to a first embodiment of the present invention.

图2是表示第1实施方式的上述钢制墙的要部概略俯视图。Fig. 2 is a schematic plan view showing a main part of the steel wall according to the first embodiment.

图3是表示地基中的第1实施方式的上述钢制墙的概略剖视图。Fig. 3 is a schematic cross-sectional view showing the steel wall according to the first embodiment in the foundation.

图4是表示本发明的第1实施方式的变形例的钢制墙的概略俯视图。Fig. 4 is a schematic plan view showing a steel wall according to a modified example of the first embodiment of the present invention.

图5是表示本发明的第2实施方式的钢制墙的要部概略俯视图。Fig. 5 is a schematic plan view showing a main part of a steel wall according to a second embodiment of the present invention.

图6是表示地基中的第2实施方式的上述钢制墙的概略剖视图。Fig. 6 is a schematic cross-sectional view showing the steel wall according to the second embodiment in the foundation.

图7是表示本发明的第3实施方式的钢制墙的要部概略俯视图。Fig. 7 is a schematic plan view of main parts showing a steel wall according to a third embodiment of the present invention.

图8是表示地基中的第3实施方式的上述钢制墙的概略剖视图。Fig. 8 is a schematic cross-sectional view showing the steel wall according to the third embodiment in the foundation.

图9是表示本发明的第4实施方式的钢制墙的要部概略俯视图。Fig. 9 is a schematic plan view showing a main part of a steel wall according to a fourth embodiment of the present invention.

图10是表示本发明的第5实施方式的钢制墙的要部概略俯视图。Fig. 10 is a schematic plan view of main parts showing a steel wall according to a fifth embodiment of the present invention.

图11是表示本发明的第5实施方式的变形例的钢制墙的概略俯视图。Fig. 11 is a schematic plan view showing a steel wall according to a modified example of the fifth embodiment of the present invention.

图12是表示本发明的第5实施方式的其他的变形例的钢制墙的要部概略俯视图。12 is a schematic plan view of main parts of a steel wall showing another modified example of the fifth embodiment of the present invention.

附图标记说明Explanation of reference signs

1、帽型钢板桩(钢板桩);1d、接头;2、钢管(加固件);3、钢制墙;5、盖;8、钢板;9、H型钢(加固件);31、钢制墙;32、钢制墙;33、钢制墙;34、钢制墙;34A、钢制墙。1. Hat-type steel sheet pile (steel sheet pile); 1d, joint; 2. Steel pipe (reinforcement); 3. Steel wall; 5. Cover; 8. Steel plate; 9. H-shaped steel (reinforcement); 31. Steel Wall; 32, steel wall; 33, steel wall; 34, steel wall; 34A, steel wall.

具体实施方式Detailed ways

以下,参照附图说明本发明的实施方式。Hereinafter, embodiments of the present invention will be described with reference to the drawings.

如图1至图3所示,本发明的第1实施方式的钢制墙3是组合作为钢板桩的帽型钢板桩1和钢管(加固件)2而构成的。多根钢管2沿着连结多个帽型钢板桩1而成的墙体(板桩墙)4的长度方向相互隔开间隔并列地配置成1列。As shown in FIGS. 1 to 3 , steel wall 3 according to the first embodiment of the present invention is configured by combining hat-shaped steel sheet pile 1 and steel pipe (reinforcing material) 2 which are steel sheet piles. A plurality of steel pipes 2 are arranged in parallel at intervals along the longitudinal direction of a wall (sheet pile wall) 4 formed by connecting a plurality of hat-shaped steel sheet piles 1 .

帽型钢板桩1具备:腹板1a;一对凸缘1b,分别自腹板1a的两侧缘以相互之间扩开的方式倾斜地延伸;一对臂1c,自左右的凸缘1b的顶端与腹板1a平行地向左右延伸;以及接头1d,设于臂1c的顶端。The hat-shaped steel sheet pile 1 includes: a web 1a; a pair of flanges 1b extending obliquely from both side edges of the web 1a so as to expand from each other; a pair of arms 1c extending from the top ends of the left and right flanges 1b. Extending left and right parallel to the web 1a; and a joint 1d provided at the top end of the arm 1c.

另外,帽型钢板桩1与钢管2不接触,形成为在帽型钢板桩1和钢管2之间隔有间隔的状态。另外,钢管2的直径小于帽型钢板桩1的宽度(有效宽度)。该钢管2成为其一部分进入凹部的状态,该凹部为由帽型钢板桩1构成的墙体的一侧面的谷部分。In addition, the hat-shaped steel sheet pile 1 and the steel pipe 2 are not in contact, and are in a state where a gap is provided between the hat-shaped steel sheet pile 1 and the steel pipe 2 . Moreover, the diameter of the steel pipe 2 is smaller than the width (effective width) of the hat-shaped steel sheet pile 1. This steel pipe 2 is in a state in which a part of the steel pipe 2 has entered a recess that is a valley portion on one side surface of the wall body constituted by the hat-shaped steel sheet pile 1 .

多个帽型钢板桩1将其接头1d相互连结排列成一列从而建造作为钢板桩墙的上述的墙体4。另外,帽型钢板桩1和钢管2被打设于地基。A plurality of hat-shaped steel sheet piles 1 are arranged in a row by connecting joints 1d to each other, and the above-mentioned wall body 4 as a steel sheet pile wall is constructed. In addition, the hat-shaped steel sheet pile 1 and the steel pipe 2 are driven into the foundation.

如图2和图3所示,该钢制墙3利用盖5连结由帽型钢板桩1形成的墙体4的头部和钢管2的头部。即,利用包裹墙体4的头部和钢管2的头部而被打设的混凝土设置盖5。通过墙体4的头部和钢管2的头部进入成为该盖5的混凝土内,墙体4的头部和钢管2的头部被连结固定。As shown in FIGS. 2 and 3 , in this steel wall 3 , the head of the wall body 4 formed by the hat-shaped steel sheet pile 1 and the head of the steel pipe 2 are connected by a cover 5 . That is, the cover 5 is provided with concrete laid to cover the head of the wall body 4 and the head of the steel pipe 2 . When the head of the wall body 4 and the head of the steel pipe 2 penetrate into the concrete that becomes the cover 5, the head of the wall body 4 and the head of the steel pipe 2 are connected and fixed.

另外,钢管2的上端开口被盖5的混凝土封闭。盖5沿着墙体4的长度方向设置,利用与一个墙体4的长度相同长度的盖5将所有的钢管2连结于墙体4。In addition, the upper end opening of the steel pipe 2 is closed by the concrete of the cover 5 . The cover 5 is provided along the longitudinal direction of the wall body 4 , and all the steel pipes 2 are connected to the wall body 4 by the cover 5 having the same length as the length of one wall body 4 .

另外,相对于墙体4,钢管2配置于施加土压侧的相反侧、即配置于未施加土压侧的前面侧。In addition, the steel pipe 2 is arranged on the side opposite to the side where the earth pressure is applied with respect to the wall body 4 , that is, on the front side of the side where the earth pressure is not applied.

另外,该例的钢制墙3例如成为护岸,其中,低侧的地基面b相对于高侧的地基面a是海、湖、河流等的水侧。此外,钢制墙3并不限定于护岸,能够用于水土保持、围堰、填筑、堤坝等。In addition, the steel wall 3 of this example serves as a revetment, for example, in which the foundation surface b on the lower side is the water side of a sea, a lake, a river, or the like with respect to the foundation surface a on the higher side. In addition, the steel wall 3 is not limited to bank protection, and can be used for soil and water conservation, cofferdams, filling, embankments, and the like.

在钢管2和由帽型钢板桩1形成的墙体4之间设有当分别单独地对墙体4(帽型钢板桩1)和钢管2进行施工时使墙体4和钢管2在施工中不会接触的程度的间隔。即,设有如下程度的间隔,使在后施工的墙体4在施工过程中不与在先施工的钢管2接触,或者在后施工的钢管2在施工过程中不与在先施工的墙体4接触。具体地,优选的是,在施工时墙体4和钢管2的彼此最接近的部分的间隔为50mm以上。另外,上述间隔也可以为60mm以上、70mm以上、80mm以上。但是,考虑到用于连结墙体4的头部和钢管2的头部的成本、钢制墙体的整体的厚度等,构成为钢管2的至少一部分进入作为墙体4的反复凹凸(峰和谷)的波板状的板桩墙的谷侧的凹部内。Between the steel pipe 2 and the wall 4 formed by the hat-shaped steel sheet pile 1, when the wall 4 (hat-shaped steel sheet pile 1) and the steel pipe 2 are separately constructed, the wall 4 and the steel pipe 2 are constructed. Intervals of the degree not to touch. That is, there is an interval of the following degree, so that the wall body 4 constructed later does not contact the steel pipe 2 constructed earlier during construction, or the steel pipe 2 constructed later does not contact the wall body constructed earlier. 4 contacts. Specifically, it is preferable that the distance between the parts of the wall body 4 and the steel pipe 2 closest to each other during construction is 50 mm or more. In addition, the above interval may be 60 mm or more, 70 mm or more, or 80 mm or more. However, in consideration of the cost for connecting the head of the wall 4 and the head of the steel pipe 2, the overall thickness of the steel wall, etc., at least a part of the steel pipe 2 enters into the repeated concavities and convexities of the wall 4 (peaks and Valley) in the concave portion of the valley side of the corrugated sheet pile wall.

通过形成钢管进入墙体的凹部内的结构,能够把持已经建造成的钢板桩墙的钢板桩4、已经打设的钢管从而油压压入或者旋转压入钢管2。在自已经建造成的钢板桩墙、钢管获得反作用力进行油压压入或者旋转压入钢管时,为了稳定地施工,优选的是,钢管配置为尽可能靠近已经建造成的钢板桩墙、钢管。By forming a structure in which the steel pipe enters the concave portion of the wall, the steel sheet pile 4 of the steel sheet pile wall already built and the steel pipe that has been driven can be held and the steel pipe 2 can be hydraulically pressed or rotated. In order to obtain a reaction force from the steel sheet pile wall or steel pipe that has already been built, and press in hydraulic pressure or rotationally press in the steel pipe, it is preferable that the steel pipe is placed as close as possible to the steel sheet pile wall or steel pipe that has already been built for stable construction. .

这种情况下,例如,凹部的深度(腹板1a与臂1c之间的沿着与腹板1a和臂1c垂直的方向的距离)根据帽型钢板桩1的型号等而不同,例如,在900mm宽度的帽型钢板桩的情况下,凹部的深度为200mm~300mm左右,因此,优选的是,将墙体4的帽型钢板桩1的腹板1a和钢管2之间的间隔设为其凹部的深度以下。In this case, for example, the depth of the recess (the distance between the web 1a and the arm 1c in the direction perpendicular to the web 1a and the arm 1c) varies depending on the model of the hat-shaped steel sheet pile 1, for example, in In the case of a hat-shaped steel sheet pile with a width of 900 mm, the depth of the concave portion is about 200 mm to 300 mm. Therefore, it is preferable to set the distance between the web 1 a of the hat-shaped steel sheet pile 1 of the wall 4 and the steel pipe 2 to its below the depth of the recess.

接着,说明钢制墙3的施工方法。Next, a construction method of the steel wall 3 will be described.

在钢制墙3的施工中,将构成墙体4的帽型钢板桩1和成为加固件的钢管2分别单独地打设于地基。In the construction of the steel wall 3, the hat-shaped steel sheet pile 1 which comprises the wall body 4, and the steel pipe 2 which becomes a reinforcing material are each driven individually in a foundation.

此时,既可以先将帽型钢板桩1打设于地基,也可以先将钢管2打设于地基。另外,也可以是这种情况,墙体4是原打设成的钢板桩墙,出于加固墙体4的目的等来打设钢管。At this time, the hat-shaped steel sheet pile 1 may be firstly driven into the foundation, or the steel pipe 2 may be firstly driven into the foundation. In addition, it may be the case that the wall body 4 is a steel sheet pile wall that was originally drilled, and steel pipes are drilled for the purpose of reinforcing the wall body 4 or the like.

另外,也可以并行地进行将帽型钢板桩1依次连结于在先打设的帽型钢板桩1的同时打设帽型钢板桩1的工程和将钢管2排成一列而依次打设钢管2的工程。In addition, the process of driving the hat-shaped steel sheet pile 1 while sequentially connecting the hat-shaped steel sheet pile 1 to the previously installed hat-shaped steel sheet pile 1 and sequentially driving the steel pipes 2 by arranging the steel pipes 2 may be performed in parallel. engineering.

另外,在帽型钢板桩1的打设过程中,既可以采用自在先压入的帽型钢板桩1获取反作用力来压入帽型钢板桩1的油压压入施工方法,也可以采用振动打设锤施工方法,也可以在打设时利用地螺钻进行挖掘。In addition, in the process of driving the hat-shaped steel sheet pile 1, the hydraulic press-fitting construction method that obtains the reaction force from the hat-shaped steel sheet pile 1 pressed in earlier to press the hat-shaped steel sheet pile 1 may be used, or vibration may be used. The hammer construction method can also be excavated with an auger when drilling.

在压入钢管2的过程中,也能够采用与帽型钢板桩1相同的施工方法。而且,在钢管2的情况下,也可以采用旋转压入施工方法、从钢管2内挖掘地基从而压入钢管2的中掘施工方法。In the process of press-fitting the steel pipe 2, the same construction method as that of the hat-shaped steel sheet pile 1 can be adopted. In addition, in the case of the steel pipe 2, a rotary press-fit construction method and a mid-cut construction method in which the foundation is excavated from the steel pipe 2 and the steel pipe 2 is pressed in can also be employed.

另外,也可以把持已经建造好的钢板桩墙的钢板桩1、已经打设好的钢管来油压压入或者旋转压入钢管2。此时,由于钢管进入墙体的凹部,因此用于获取反作用力的钢板桩墙、钢管与进行施工的钢管的位置变近,能够稳定地进行施工。In addition, it is also possible to hold the steel sheet pile 1 of the steel sheet pile wall that has already been built and the steel pipe that has already been laid, and press in the steel pipe 2 with oil pressure or rotary pressure. At this time, since the steel pipe enters the concave portion of the wall, the position of the steel sheet pile wall for obtaining the reaction force, the steel pipe, and the steel pipe to be constructed become close, and stable construction can be performed.

在该钢制墙3的情况,因为作为板桩墙的墙体4和作为加固件的钢管2在施工中隔开不会接触的间隔,例如隔开50mm以上的间隔被打设于地基,因此能够抑制墙体4和钢管2在施工中滑动而产生振动、噪音、变形。In the case of the steel wall 3, since the wall 4 as the sheet pile wall and the steel pipe 2 as the reinforcing member are separated from each other during construction, for example, they are laid on the foundation at a distance of 50 mm or more. Vibration, noise and deformation caused by sliding of the wall body 4 and the steel pipe 2 during construction can be suppressed.

另外,在墙体4和钢管2在施工中接触的情况下,例如,若采用在打设时使打设的构件振动的振动式的施工方法、旋转压入施工方法,则上述的噪音、振动、变形的可能性变高。由此,能够使用的施工方法受限制。与此相对,在该本实施方式中,因为施工中墙体4和钢管2之间分离着,所以施工方法的选择较广。In addition, when the wall body 4 and the steel pipe 2 are in contact during construction, for example, if a vibratory construction method or a rotary press-fit construction method is adopted to vibrate the members to be installed during construction, the above-mentioned noise and vibration will , the possibility of deformation becomes high. Therefore, usable construction methods are limited. On the other hand, in this embodiment, since the wall body 4 and the steel pipe 2 are separated during construction, the selection of construction methods is wide.

另外,在接合钢板桩和加固件而使其一体化了的情况下,被打设于地基的构件的截面面积变大,难以打设。与此相对,因为本实施方式的钢制墙3是墙体4和钢管2分别单独地打设,所以能够容易地施工。另外,因为墙体4和钢管2在施工中以不接触的方式分离着,所以与如上所述墙体4和钢管2相接触的情况相比,进一步使施工变容易。Moreover, when a steel sheet pile and a reinforcing material were joined and integrated, the cross-sectional area of the member driven into the foundation becomes large, and it becomes difficult to drive. On the other hand, the steel wall 3 of this embodiment can be easily constructed because the wall body 4 and the steel pipes 2 are installed separately. In addition, since the wall body 4 and the steel pipe 2 are separated during construction without contact, construction is further facilitated compared to the case where the wall body 4 and the steel pipe 2 are in contact as described above.

在打设了钢板桩1(墙体4)和钢管2后,以跨越墙体4和钢管2的方式打设成为盖5的混凝土。由此,墙体4的头部和钢管2的头部相连结。After the steel sheet pile 1 (wall body 4 ) and the steel pipe 2 have been driven, concrete to be the cover 5 is driven so as to straddle the wall body 4 and the steel pipe 2 . Thus, the head of the wall body 4 and the head of the steel pipe 2 are connected.

在该钢制墙3中,因为墙体4的头部和钢管2的头部相连结,所以通过连结部分能够使负载在墙体4和钢管2之间传递,并使墙体4和钢管2分担承受钢制墙3所受到的土压、水压。另外,因为墙体4的头部和钢管2的头部相连结着,所以能够防止钢管2和墙体4之间在铅垂方向的错位。如上所述,钢制墙3与单独的钢板桩墙相比,能够减少在由钢管2加固的墙体4上产生的弯曲力矩。另外,钢制墙3的止水性能够与钢板桩墙相同,即使不进行向接头1d填充砂浆等,也能够获得和在接头部分填充有砂浆的钢管板桩墙相同水平的止水性。In this steel wall 3, since the head of the wall 4 and the head of the steel pipe 2 are connected, the load can be transmitted between the wall 4 and the steel pipe 2 through the connecting portion, and the wall 4 and the steel pipe 2 can be connected together. Share the earth pressure and water pressure that the steel wall 3 is subjected to. In addition, since the head of the wall body 4 and the head portion of the steel pipe 2 are connected, displacement in the vertical direction between the steel pipe 2 and the wall body 4 can be prevented. As described above, the steel wall 3 can reduce the bending moment generated in the wall body 4 reinforced with the steel pipe 2 compared with a single steel sheet pile wall. In addition, the watertightness of the steel wall 3 can be the same as that of the steel sheet pile wall, and the same level of watertightness as that of the steel pipe sheet pile wall filled with mortar at the joint portion can be obtained without filling the joint 1d with mortar.

在本实施方式中,如图3所示,在钢制墙3中,钢管2配置于墙体4的被施加土压侧的相反侧、即配置于未施加土压侧的前面侧。因而,在作为加固原有的钢板桩墙的目的的情况下,即使在背面侧的地上部或者地中部存在障碍物,也能够在前面侧设置钢管从而进行加固。而且,即使在用相同的长度的钢管进行加固的情况下,与设置于背面的情况相比,打入土中的长度变短,能够削减施工劳力、时间和成本。In this embodiment, as shown in FIG. 3 , in the steel wall 3 , the steel pipe 2 is arranged on the opposite side of the wall body 4 to which the earth pressure is applied, that is, on the front side of the side to which the earth pressure is not applied. Therefore, in the case of reinforcing the existing steel sheet pile wall, even if there is an obstacle in the ground part or the middle part of the back side, steel pipes can be installed on the front side and reinforced. Furthermore, even in the case of reinforcing with steel pipes of the same length, compared with the case of installing on the back side, the length to be driven into the soil becomes shorter, and construction labor, time, and cost can be reduced.

在本实施方式中,钢制墙3用作护岸,钢管2的头部和墙体4的头部被盖5连结着。因而,盖5是钢管2的头部和墙体4的头部的连结件,并且也具有封闭钢管2的开口部的功能。该方式中,由于不一定需要像拉杆那样的专用的连结构件,因此能够实现成本降低。In this embodiment, the steel wall 3 is used as a revetment, and the head of the steel pipe 2 and the head of the wall body 4 are connected by a cover 5 . Therefore, the cover 5 is a link between the head of the steel pipe 2 and the head of the wall 4 , and also has a function of closing the opening of the steel pipe 2 . In this form, since a dedicated connecting member such as a tie rod is not necessarily required, cost reduction can be achieved.

在本实施方式的钢制墙3中,钢管2的长度比墙体4的上下长度(帽型钢板桩1的长度)长。通过将相对刚性较高的钢管2的长度变长,能够进行由钢管2承受土压、由墙体4发挥防止土砂流出的作用这样的自由的设计。由此,能够降低钢重、施工成本。例如,也可以形成如下方式,使钢管2比墙体4长,且只将钢管2打入支承层。In the steel wall 3 of this embodiment, the length of the steel pipe 2 is longer than the vertical length of the wall body 4 (the length of the hat-shaped steel sheet pile 1). By increasing the length of the relatively rigid steel pipe 2 , a free design can be performed in which the steel pipe 2 bears the earth pressure and the wall 4 functions to prevent the outflow of soil and sand. Thereby, steel weight and construction cost can be reduced. For example, it is also possible to make the steel pipe 2 longer than the wall body 4 and only drive the steel pipe 2 into the supporting layer.

此外,如后所述,既可以使钢管2的长度比墙体4的上下长度短,也可以使钢管2的长度和墙体4的上下长度相同。钢管2的长度根据刚性和地基条件来决定。另外,在当墙体4的上下长度与钢管2的长度相同程度时担心发生流砂、隆起、圆弧滑动的情况下,将墙体4的上下长度形成为比钢管2的长度长即可。另外,为了对地下水进行止水,也可以使墙体4比钢管2长。In addition, as will be described later, the length of the steel pipe 2 may be shorter than the vertical length of the wall body 4 , or the length of the steel pipe 2 may be equal to the vertical length of the wall body 4 . The length of the steel pipe 2 is determined according to rigidity and foundation conditions. In addition, if the vertical length of the wall body 4 is about the same as the length of the steel pipe 2, quicksand, bumps, and arc sliding may occur, the vertical length of the wall body 4 may be formed longer than the length of the steel pipe 2. In addition, the wall body 4 may be longer than the steel pipe 2 in order to stop groundwater.

在本实施方式中,如图1所示,在墙体4的各帽型钢板桩1(墙体4的每个凹部)均配置有钢管2。但是,根据所要求的强度,并不是全部的帽型钢板桩1都需要配置钢管2。例如,既可以如图4所示每隔开一个帽型钢板桩1(每隔开一个凹部)配置钢管2,也可以每隔开两个帽型钢板桩1(每隔开两个凹部)进行配置。由于加固件进入墙体的凹部,因此即使不在全部的帽型钢板桩1都配置钢管,也能够对相邻的钢板桩产生加固件的效果。但是,优选的是,在钢管2沿着墙体4的长度方向排列的状态下,大致均匀配置钢管2。In this embodiment, as shown in FIG. 1, the steel pipe 2 is arrange|positioned for each hat-shaped steel sheet pile 1 of the wall body 4 (every recessed part of the wall body 4). However, depending on the required strength, it is not necessary to arrange the steel pipe 2 for all the hat-shaped steel sheet piles 1 . For example, steel pipes 2 may be arranged every other hat-shaped steel sheet pile 1 (every two recesses) as shown in FIG. configuration. Since the reinforcing material enters the concave portion of the wall body, even if the steel pipes are not arranged in all the hat-shaped steel sheet piles 1, the effect of the reinforcing material can be produced on the adjacent steel sheet piles. However, it is preferable that the steel pipes 2 are arranged substantially uniformly in a state where the steel pipes 2 are arranged along the longitudinal direction of the wall body 4 .

构成墙体4的钢板桩并不限定于帽型钢板桩1,能够采用U型钢板桩、Z型钢板桩等的各种钢板桩。The steel sheet pile which comprises the wall body 4 is not limited to the hat-shaped steel sheet pile 1, Various steel sheet piles, such as a U-shaped steel sheet pile and a Z-shaped steel sheet pile, can be employ|adopted.

接着,说明本发明的第2实施方式。Next, a second embodiment of the present invention will be described.

如图5和图6所示,第2实施方式的钢制墙31利用作为连结构件的钢制的支承件(例如,切断成规定长度的钢板、型钢)6与盖5共同将钢管2的头部和墙体4的头部连结。另外,使钢管2的长度和墙体4的上下长度相同。除此以外,具有与第1实施方式的钢制墙3相同的结构。因此,对与第1实施方式相同的构成要素标注相同的附图标记并且省略其说明。As shown in FIGS. 5 and 6 , the steel wall 31 of the second embodiment uses a steel support member (for example, a steel plate cut to a predetermined length, shaped steel) 6 as a connecting member and a cover 5 to hold the steel pipe 2 together. The head link of head and body of wall 4. In addition, the length of the steel pipe 2 and the vertical length of the wall body 4 are made the same. Other than that, it has the same structure as the steel wall 3 of 1st Embodiment. Therefore, the same reference numerals are assigned to the same constituent elements as those of the first embodiment, and description thereof will be omitted.

在第2实施方式中,作为连结构件的钢制的支承件6(钢材)设置为夹在钢管2的头部和墙体4的头部之间的状态。该支承件6通过例如焊接、螺栓、自钻螺钉等固定于钢管2和墙体4。由此,在钢管2和墙体4分离的状态下,钢管2的头部和墙体4的头部被连结着。In 2nd Embodiment, the support material 6 (steel material) made of steel which is a connection member is provided in the state sandwiched between the head part of the steel pipe 2 and the head part of the wall body 4. As shown in FIG. The supporting member 6 is fixed to the steel pipe 2 and the wall 4 by, for example, welding, bolts, self-drilling screws and the like. As a result, the head of the steel pipe 2 and the head of the wall 4 are connected in a state where the steel pipe 2 and the wall 4 are separated.

另外,在第2实施方式中,如上所述钢管2的长度和墙体4的上下长度(帽型钢板桩1的长度)大致相同。In addition, in 2nd Embodiment, the length of the steel pipe 2 and the up-and-down length of the wall body 4 (the length of the hat-shaped steel sheet pile 1) are substantially the same as mentioned above.

第2实施方式的钢制墙31的施工方法如下所示。The construction method of the steel wall 31 of 2nd Embodiment is as follows.

首先,将钢板桩1以及钢管2与第1实施方式相同地进行打设。接着,将成为支承件6的钢材设置于钢板桩1(墙体4)与钢管2之间,并通过焊接、螺栓、自钻螺钉等分别固定于钢板桩1(墙体4)与钢管2。然后,与第1实施方式相同地跨越墙体4和钢管2地打设盖。First, the steel sheet pile 1 and the steel pipe 2 are driven in the same manner as in the first embodiment. Next, the steel material to be the support 6 is placed between the steel sheet pile 1 (wall 4 ) and the steel pipe 2 , and fixed to the steel sheet pile 1 (wall 4 ) and steel pipe 2 by welding, bolts, self-drilling screws, and the like. Then, similar to the first embodiment, a cover is drilled across the wall body 4 and the steel pipe 2 .

在第2实施方式的钢制墙31中,钢管2的头部和墙体4的头部通过盖5和支承件6两者连结着。由此,能够更可靠地将墙体4所承受的负载传递于钢管2。除了能够获得该效果和基于钢管2和帽型钢板桩1为相同长度所产生的效果以外,还能够获得与第1实施方式的钢制墙3相同的作用效果。In the steel wall 31 of the second embodiment, the head of the steel pipe 2 and the head of the wall body 4 are connected by both the cover 5 and the support 6 . Thereby, the load borne by the wall body 4 can be more reliably transmitted to the steel pipe 2 . In addition to obtaining this effect and the effect based on the steel pipe 2 and the hat-shaped steel sheet pile 1 having the same length, the same operation and effect as the steel wall 3 of the first embodiment can be obtained.

接着,说明本发明的第3实施方式。Next, a third embodiment of the present invention will be described.

如图7和图8所示,第3实施方式的钢制墙32不仅采用盖5连结钢管2的头部和墙体4的头部,还采用作为连结构件的一对板材7来连结钢管2的头部和墙体4的头部。而且,墙体4的上下长度比钢管2的长度长。另外,将钢管2配置于墙体4的被施加土压的背面侧。除此以外,具有与第1实施方式的钢制墙3相同的结构。因此,对与第1实施方式相同的构成要素标注相同的标记并省略其说明。As shown in Fig. 7 and Fig. 8, the steel wall 32 of the third embodiment not only uses the cover 5 to connect the head of the steel pipe 2 and the head of the wall 4, but also uses a pair of plate materials 7 as connecting members to connect the steel pipes. 2 head and wall 4 head. Moreover, the vertical length of the wall body 4 is longer than the length of the steel pipe 2 . In addition, the steel pipe 2 is disposed on the back side of the wall body 4 to which earth pressure is applied. Other than that, it has the same structure as the steel wall 3 of 1st Embodiment. Therefore, the same symbols are assigned to the same constituent elements as those of the first embodiment, and description thereof will be omitted.

在第3实施方式中,钢制的板材7设置为夹在钢管2的头部和墙体4的头部之间的状态。另外,板材7通过焊接、螺栓等分别固定于钢管2和墙体4。另外,在钢管2和墙体4分离的状态下,钢管2的头部和墙体4的头部被连结着。而且,跨越由板材7连结的钢管2的头部和墙体4的头部,用混凝土包入钢管2的头部和墙体4的头部来设置盖5,由此钢管2的头部和墙体4的头部也被盖5连结着。In the third embodiment, the steel plate 7 is provided in a state of being sandwiched between the head of the steel pipe 2 and the head of the wall body 4 . In addition, the plates 7 are respectively fixed to the steel pipe 2 and the wall 4 by welding, bolts or the like. In addition, in the state where the steel pipe 2 and the wall body 4 are separated, the head of the steel pipe 2 and the head of the wall body 4 are connected. And straddle the head of the steel pipe 2 connected by the plate 7 and the head of the wall 4, wrap the head of the steel pipe 2 and the head of the wall 4 with concrete to set the cover 5, thus the head of the steel pipe 2 and the head of the wall 4 The head of the body of wall 4 is also connected by a cover 5 .

另外,在第3实施方式中,如上所述墙体4的上下长度(帽型钢板桩1的长度)比钢管2的长度长。由此,能够实现防止流砂、隆起、圆弧滑动或者实现对地下水进行止水。另外,除了利用盖5进行连结之外,还利用板材7进行连结,由此能够提高钢管2的头部和墙体4的头部之间的连结部分的强度。特别是,在该结构中,因为拉伸负载作用于墙体4和钢管2之间,所以利用钢制的板材7进行的连结更有效。In addition, in the third embodiment, the vertical length (the length of the hat-shaped steel sheet pile 1 ) of the wall body 4 is longer than the length of the steel pipe 2 as described above. Thereby, it is possible to prevent quicksand, uplift, arc sliding or to stop groundwater. In addition, the strength of the connection portion between the head of the steel pipe 2 and the head of the wall body 4 can be increased by connecting with the plate material 7 in addition to the connection by the cover 5 . In particular, in this structure, since a tensile load acts between the wall body 4 and the steel pipe 2, the connection by the steel plates 7 is more effective.

另外,由于通过在墙体4的背面侧设置钢管2,能够使钢管2不暴露于墙体4的前侧而隐藏起来,因此能够提高钢制墙32的美观。Moreover, since the steel pipe 2 can be hidden without being exposed to the front side of the wall 4 by providing the steel pipe 2 on the back side of the wall body 4, the appearance of the steel wall 32 can be improved.

第3实施方式的钢制墙32,除了具有基于连结部分的结构、钢管2和墙体4的长度、以及钢管2相对于墙体4的配置的作用效果之外,还能够获得与第1实施方式相同的作用效果。The steel wall 32 of the third embodiment can achieve the same effect as that of the first embodiment in addition to the effects based on the structure of the connecting portion, the length of the steel pipe 2 and the wall 4, and the arrangement of the steel pipe 2 with respect to the wall 4. same effect.

接着,说明本发明的第4实施方式。Next, a fourth embodiment of the present invention will be described.

如图9所示,第4实施方式的钢制墙33为H型钢9代替钢管2作为加固件的结构,其以外的结构成为与第1实施方式的钢制墙3相同的结构。因此,对与第1实施方式相同的构成要素标注相同的标记并省略其说明。As shown in FIG. 9 , the steel wall 33 of the fourth embodiment has H-shaped steel 9 instead of the steel pipe 2 as a reinforcing member, and the other structures are the same as those of the steel wall 3 of the first embodiment. Therefore, the same symbols are assigned to the same constituent elements as those of the first embodiment, and description thereof will be omitted.

第4实施方式的钢制墙33采用H型钢9作为加固件。H型钢9沿着连接帽型钢板桩1而成的墙体4的长度方向、与第1实施方式的钢管2的情况相同地隔开间隔并排成一列而配置。另外,在H型钢9与墙体4之间,与第1实施方式的钢管2的情况相同地设置有间隔。The steel wall 33 of the fourth embodiment employs the H-shaped steel 9 as a reinforcement. The H-shaped steel 9 is arranged in a row at intervals along the longitudinal direction of the wall body 4 formed by connecting the hat-shaped steel sheet piles 1 , as in the case of the steel pipes 2 of the first embodiment. In addition, a gap is provided between the H-shaped steel 9 and the wall body 4 in the same manner as in the case of the steel pipe 2 of the first embodiment.

另外,H型钢9成为其一部分进入由帽型钢板桩1构成的为墙体的一侧面的谷部分的凹部的状态。另外,H型钢9配置为腹板9a正交于墙体4的长度方向。因而,凸缘9b平行于墙体4的长度方向。Moreover, the H-shaped steel 9 is the state which entered the recessed part of the valley part which is one side surface of the wall body comprised with the hat-shaped steel sheet pile 1 partly. In addition, the H-shaped steel 9 is arranged so that the web 9 a is perpendicular to the longitudinal direction of the wall body 4 . Thus, the flange 9b is parallel to the length direction of the wall 4 .

该墙体4的头部和H型钢9的头部连结着。钢制墙33和作为加固件的H型钢9的连结方法能够采用与第1实施方式至第3实施方式相同的方法。即,利用盖5连结墙体4和H型钢9。此外,也可以借助钢材通过焊接、螺栓的连结来连结墙体4和H型钢9。另外,还能够组合这些连结方法来连结墙体4的头部和H型钢9的头部。The head of this body of wall 4 is connected with the head of H-shaped steel 9. The connection method of the steel wall 33 and the H-shaped steel 9 as a reinforcing material can be the same as that of the first to third embodiments. That is, the wall body 4 and the H-shaped steel 9 are connected by the cover 5 . In addition, the wall body 4 and the H-shaped steel 9 may also be connected by welding or bolt connection by means of steel materials. In addition, it is also possible to connect the head of the wall body 4 and the head of the H-shaped steel 9 by combining these connection methods.

除了H型钢9代替钢管2作为加固件以外,墙体4的长度和H型钢9的长度的关系、H型钢9相对于墙体4的配置(包括墙体4和H型钢9的间隔)等的结构能够与第1实施方式至第3实施方式相同。In addition to the H-shaped steel 9 replacing the steel pipe 2 as a reinforcement, the relationship between the length of the wall 4 and the length of the H-shaped steel 9, the configuration of the H-shaped steel 9 relative to the wall 4 (including the interval between the wall 4 and the H-shaped steel 9), etc. The structure can be the same as that of the first to third embodiments.

在钢制墙33的施工方法中,除了不能够用中掘施工方法、旋转压入施工方法对H型钢9进行施工之外,能够采用与第1实施方式至第3实施方式的钢制墙的施工方法相同的施工方法。In the construction method of the steel wall 33, except that the H-shaped steel 9 cannot be constructed by the mid-cut construction method or the rotary press-in construction method, it is possible to adopt the same method as the steel wall of the first embodiment to the third embodiment. The same construction method as the construction method.

第4实施方式的钢制墙33除了由钢管2产生的作用效果以外,能够获得与第1实施方式至第3实施方式的钢制墙3相同的作用效果。The steel wall 33 of the fourth embodiment can obtain the same function and effect as the steel wall 3 of the first to third embodiments, except for the function and effect of the steel pipe 2 .

接着,说明本发明的第5实施方式。Next, a fifth embodiment of the present invention will be described.

如图10所示,第5实施方式的钢制墙34在上述的各实施方式中,通过焊接钢板8来进行钢管2的头部和墙体4的头部之间的连结。对于钢管2的头部和墙体4的头部的连结未使用混凝土。除该钢管2的头部和墙体4的头部之间的连结结构以外的结构成为与第1实施方式的钢制墙3相同的结构。因此,对相同的构成要素标注相同的标记并省略其说明。As shown in FIG. 10 , in the steel wall 34 according to the fifth embodiment, in each of the above-mentioned embodiments, the head of the steel pipe 2 and the head of the wall body 4 are connected by welding the steel plate 8 . Concrete is not used for the connection between the head of the steel pipe 2 and the head of the wall 4 . The structure other than the connection structure between the head part of this steel pipe 2 and the head part of the wall body 4 is the same structure as the steel wall 3 of 1st Embodiment. Therefore, the same symbols are assigned to the same components, and descriptions thereof are omitted.

与第1实施方式相同地,在第5实施方式的钢制墙34中,多根钢管2沿着连结多个帽型钢板桩1而成的墙体(板桩墙)4的长度方向相互隔开间隔排成1列而配置。另外,钢管2配置为钢管2的一部分进入反复凹凸的波状的钢板桩1的凹部的状态。Similar to the first embodiment, in the steel wall 34 of the fifth embodiment, a plurality of steel pipes 2 are separated from each other along the longitudinal direction of a wall (sheet pile wall) 4 formed by connecting a plurality of hat-shaped steel sheet piles 1 . They are arranged in a row at intervals. Moreover, the steel pipe 2 is arrange|positioned in the state which entered the recessed part of the wave-shaped steel sheet pile 1 which repeats unevenness|corrugation partly.

在墙体4的帽型钢板桩1与钢管2之间配置有钢板8。在本实施方式中,钢板8配置于帽型钢板桩1的臂1c与钢管2的外周之间。钢板8对应于左右的臂1c,分别相对于1个帽型钢板桩1和1个钢管2在左右各设置一个。The steel plate 8 is arrange|positioned between the hat-shaped steel sheet pile 1 of the wall body 4, and the steel pipe 2. In this embodiment, the steel plate 8 is arrange|positioned between the arm 1c of the hat-shaped steel sheet pile 1, and the outer periphery of the steel pipe 2. As shown in FIG. The steel plate 8 is corresponded to the arm 1c on either side, and is provided one each on the left and right with respect to one hat-shaped steel sheet pile 1 and one steel pipe 2, respectively.

另外,钢板8的一个端部焊接于帽型钢板桩1的臂1c,另一个端部焊接于钢管2的外周。Moreover, one end part of the steel plate 8 is welded to the arm 1c of the hat-shaped steel sheet pile 1, and the other end part is welded to the outer periphery of the steel pipe 2. As shown in FIG.

在钢制墙34的施工中,墙体4的建造和钢管2的打设与第1实施方式相同地进行。在墙体4的建造与钢管2的打设结束后,将钢板8焊接于墙体4的帽型钢板桩1和钢管2。In the construction of the steel wall 34, the construction of the wall body 4 and the drilling of the steel pipe 2 are performed in the same manner as in the first embodiment. After the construction of the wall body 4 and the laying of the steel pipe 2 are completed, the steel plate 8 is welded to the hat-shaped steel sheet pile 1 and the steel pipe 2 of the wall body 4 .

在第5实施方式的钢制墙34中,因为墙体4和钢管2的头部彼此间的连结利用焊接钢板8来进行,所以施工变得容易。另外,不像由混凝土连结的情况需要养护期,因此工期较短。In the steel wall 34 of the fifth embodiment, since the wall body 4 and the heads of the steel pipes 2 are connected by the welded steel plate 8, construction becomes easy. In addition, unlike the case of concrete connection, a curing period is not required, so the construction period is short.

另外,在本实施方式中,如图11所示,既可以将钢板8配置于帽型钢板桩1的腹板1a与钢管2的外周面之间,也可以配置于凸缘1b与钢管2的外周面之间。In addition, in this embodiment, as shown in FIG. 11, the steel plate 8 may be arranged between the web 1a of the hat-shaped steel sheet pile 1 and the outer peripheral surface of the steel pipe 2, or may be arranged between the flange 1b and the steel pipe 2. between the peripheral surfaces.

另外,也可以以跳过钢管2的间距(例如,每隔开一个或者多个帽型钢板桩1配置钢管2)的方式相对于帽型钢板桩1配置钢管2,并采用直径大于帽型钢板桩1的有效宽度的钢管2。In addition, the steel pipes 2 may be arranged relative to the hat-shaped steel sheet piles 1 by skipping the distance between the steel pipes 2 (for example, the steel pipes 2 are arranged every one or more hat-shaped steel sheet piles 1). Steel pipe 2 of effective width of pile 1.

另外,既可以将钢管2配置于墙体4的受到相对较大压力的一侧,也可以配置于其相反侧。In addition, the steel pipe 2 may be arranged on the side of the wall body 4 that receives a relatively high pressure, or may be arranged on the opposite side.

另外,如图12所示的钢制墙34A所示,除了通过焊接钢板8进行连结之外,还可以与第1实施方式相同地利用包入墙体4的头部和钢管2的头部地被打设的混凝土来设置盖5。在这种情况下,在焊接钢板8之后打设混凝土。In addition, as shown in the steel wall 34A shown in FIG. 12, in addition to connecting by welding the steel plate 8, it is also possible to use the head of the wall body 4 and the head of the steel pipe 2 to enclose the head of the wall 4 and the head of the steel pipe 2 similarly to the first embodiment. The concrete that is set is used to set the cover 5 . In this case, the concrete is laid after the steel plate 8 is welded.

另外,墙体4和钢管2除了利用焊接钢板8来连接之外,还利用混凝土进行连结。In addition, the wall body 4 and the steel pipe 2 are not only connected by the welded steel plate 8 but also connected by concrete.

在这种情况下,例如,能够以混凝土主要进行墙体4和钢管2之间的压缩力的传递、钢板8主要进行拉伸力的传递的方式形成互补结构。另外,能够实现上述的利用混凝土封堵钢管2的上端开口、防止顶端的倒塌等。In this case, for example, a complementary structure can be formed such that concrete mainly transmits compressive force between wall body 4 and steel pipe 2 , and steel plate 8 mainly transmits tensile force. In addition, the above-mentioned sealing of the upper end opening of the steel pipe 2 with concrete, the prevention of the collapse of the tip, and the like can be realized.

此外,也可以是,以原有的钢板桩墙为墙体4,通过相对于该墙体4,打设钢管2、H型钢9来建造钢制墙3、31、32、33、34、34A。Alternatively, the existing steel sheet pile wall may be used as the wall body 4, and the steel wall 3, 31, 32, 33, 34, 34A may be constructed by laying steel pipes 2 and H-shaped steel 9 on the wall body 4. .

Claims (6)

1.一种钢制墙的制造方法,所述钢制墙包括:利用接头连接多个钢板桩而在长度方向上反复凹凸呈波板状的墙体;用于加固上述墙体的、由不具有嵌合用接头的钢管形成的多个加固件,该制造方法的特征在于,1. A method for manufacturing a steel wall, the steel wall comprising: a wall body that is repeatedly concave-convex in the length direction in the shape of a corrugated plate by connecting a plurality of steel sheet piles with joints; A plurality of reinforcing members formed of steel pipes having joints for fitting, the manufacturing method is characterized in that, 所述制造方法包括:The manufacturing method includes: 以上述加固件的一部分进入上述墙体的凹部,且上述墙体和上述加固件在施工中不会接触的方式,将上述加固件沿着上述墙体的长度方向与上述墙体隔开间隔地并列设置;The reinforcing member is spaced apart from the wall along the length direction of the wall so that a part of the reinforcing member enters the recess of the wall and the wall and the reinforcing member are not in contact during construction. Parallel setting; 通过使得上述墙体和上述加固件只在头部相连结,在上述墙体和上述加固件之间传递负载,并且限制上述墙体和上述加固件在铅垂方向上的错位。By connecting the wall body and the reinforcement member only at the head portion, the load is transmitted between the wall body and the reinforcement member, and vertical misalignment of the wall body and the reinforcement member is restricted. 2.根据权利要求1所述的制造方法,其特征在于,2. The manufacturing method according to claim 1, characterized in that, 上述墙体和上述钢管之间在彼此最接近的情况下的间隔是70mm以上且300mm以下。The distance between the wall body and the steel pipe when they are closest to each other is 70 mm or more and 300 mm or less. 3.根据权利要求1所述的制造方法,其特征在于,3. The manufacturing method according to claim 1, characterized in that, 每隔开一个或者隔开多个上述钢板桩设置有上述加固件。The said reinforcing material is provided every one or several said steel sheet piles every other. 4.根据权利要求1所述的制造方法,其特征在于,4. The manufacturing method according to claim 1, characterized in that, 上述墙体和上述加固件利用跨越上述墙体和上述加固件的头部而打设成的混凝土在头部相连结。The wall body and the reinforcement member are connected at the head portion by concrete laid across the head portion of the wall body and the reinforcement member. 5.根据权利要求1所述的制造方法,其特征在于,5. The manufacturing method according to claim 1, characterized in that, 上述墙体和上述加固件通过将设置于上述墙体和上述加固件之间的钢板分别焊接于上述墙体和上述加固件而在头部相连结。The wall body and the reinforcement member are connected at the head by welding steel plates provided between the wall body and the reinforcement member to the wall body and the reinforcement member, respectively. 6.根据权利要求1所述的制造方法,其特征在于,6. The manufacturing method according to claim 1, characterized in that, 上述加固件的节距L和上述墙体的墙高H满足:L≤4H/7。The pitch L of the reinforcements and the wall height H of the wall satisfy: L≦4H/7.
CN201810196043.XA 2012-05-01 2012-05-01 The manufacturing method of steel wall Pending CN108330952A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810196043.XA CN108330952A (en) 2012-05-01 2012-05-01 The manufacturing method of steel wall

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201810196043.XA CN108330952A (en) 2012-05-01 2012-05-01 The manufacturing method of steel wall
CN201280072877.0A CN104271841A (en) 2012-05-01 2012-05-01 steel wall
PCT/JP2012/061574 WO2013164885A1 (en) 2012-05-01 2012-05-01 Steel wall

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201280072877.0A Division CN104271841A (en) 2012-05-01 2012-05-01 steel wall

Publications (1)

Publication Number Publication Date
CN108330952A true CN108330952A (en) 2018-07-27

Family

ID=49514295

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201280072877.0A Pending CN104271841A (en) 2012-05-01 2012-05-01 steel wall
CN201810196043.XA Pending CN108330952A (en) 2012-05-01 2012-05-01 The manufacturing method of steel wall

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201280072877.0A Pending CN104271841A (en) 2012-05-01 2012-05-01 steel wall

Country Status (7)

Country Link
EP (1) EP2848739A4 (en)
JP (1) JP6015751B2 (en)
CN (2) CN104271841A (en)
HK (1) HK1203580A1 (en)
IN (1) IN2014DN08915A (en)
SG (1) SG11201407027YA (en)
WO (1) WO2013164885A1 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017089144A (en) * 2015-11-05 2017-05-25 株式会社琉球技研 Revetment structure by steel sheet pile
JP2020076285A (en) 2018-11-02 2020-05-21 日本製鉄株式会社 Quay wall structure and construction method for quay wall structure
CN110863473B (en) * 2019-11-27 2024-06-25 中国电建集团贵阳勘测设计研究院有限公司 A combined water-blocking structure for buried pressure steel pipe
JP7516197B2 (en) 2020-02-27 2024-07-16 日本製鉄株式会社 Quay structure and method for constructing the quay structure
JP2021167523A (en) * 2020-04-10 2021-10-21 日本製鉄株式会社 Quay reinforcement structure and reinforcement method of quay structure
JP7364526B2 (en) * 2020-04-10 2023-10-18 日本製鉄株式会社 Quay wall structure and construction method of quay wall structure
CN114991187B (en) * 2022-06-28 2023-09-26 安徽省公路桥梁工程有限公司 Deepwater steel sheet pile and steel pipe pile combined cofferdam structure and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005299202A (en) * 2004-04-12 2005-10-27 Nippon Steel Corp Steel sheet pile, retaining structure using the sheet pile, and construction method of retaining structure
JP2009249959A (en) * 2008-04-09 2009-10-29 Nippon Steel Corp Continuous underground wall and its construction method
CN102116031A (en) * 2011-01-17 2011-07-06 东南大学 Steel sheet pile and tubular pile combined base pit supporting structure and supporting method thereof
CN202164596U (en) * 2011-06-30 2012-03-14 董荣进 Steel pipe sheet pile composite structure

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH074241B2 (en) 1987-05-07 1995-01-25 三菱重工業株式会社 Immobilization method of microbial cells
JP3756755B2 (en) 2000-11-29 2006-03-15 新日本製鐵株式会社 Steel sheet pile joint structure and water stop method
JP3603793B2 (en) * 2001-01-19 2004-12-22 住友金属工業株式会社 Steel wall for underground diaphragm wall and diaphragm wall
CN100537904C (en) * 2002-10-31 2009-09-09 住友金属工业株式会社 Steel plate wall and manufacture method thereof
JP4074241B2 (en) * 2003-12-15 2008-04-09 住友金属工業株式会社 How to build steel
WO2011142047A1 (en) * 2010-05-10 2011-11-17 住友金属工業株式会社 Steel wall and method for constructing steel wall

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005299202A (en) * 2004-04-12 2005-10-27 Nippon Steel Corp Steel sheet pile, retaining structure using the sheet pile, and construction method of retaining structure
JP2009249959A (en) * 2008-04-09 2009-10-29 Nippon Steel Corp Continuous underground wall and its construction method
CN102116031A (en) * 2011-01-17 2011-07-06 东南大学 Steel sheet pile and tubular pile combined base pit supporting structure and supporting method thereof
CN202164596U (en) * 2011-06-30 2012-03-14 董荣进 Steel pipe sheet pile composite structure

Also Published As

Publication number Publication date
CN104271841A (en) 2015-01-07
IN2014DN08915A (en) 2015-05-22
HK1203580A1 (en) 2015-10-30
EP2848739A1 (en) 2015-03-18
WO2013164885A1 (en) 2013-11-07
JP6015751B2 (en) 2016-10-26
EP2848739A4 (en) 2016-04-13
SG11201407027YA (en) 2014-12-30
JPWO2013164885A1 (en) 2015-12-24

Similar Documents

Publication Publication Date Title
CN108330952A (en) The manufacturing method of steel wall
JP5464370B2 (en) Filling reinforcement structure
CN102782219B (en) Steel wall and construction method for steel wall
JP3747198B2 (en) Steel pipe sheet pile foundation
KR102011321B1 (en) Construction method of foundation using rectangular pipe and its foundation
KR20100068597A (en) A shoring method using arch plate pile and h-pile
KR20090093556A (en) Panel , Wall Structure with panels and Construction Method using the Same
JP7149919B2 (en) Improvement structure and improvement method of existing wharf
TW200536994A (en) Steel-pipe sheet pile and coupling structure of steel-pipe sheet piles
CN100336980C (en) Supporting article for preventing sand from subsiding
CN112523265A (en) Protective structure for excavating foundation pit and spanning existing tunnel and construction method thereof
JP2015183453A (en) Dam body
JP2012007465A (en) Retaining wall device
JP3905776B2 (en) Revetment structure
JP2012102497A (en) Steel wall and method for constructing the same
JP3689835B2 (en) Civil engineering structure
JP2004052277A (en) Construction method for double closing levee
JP4088871B2 (en) Impermeable wall structure and impermeable wall structure using the impermeable wall
JP2004308328A (en) Seawall structure
JP2548634B2 (en) Underwater structure using underwater ground driving member
JP6298688B2 (en) Embankment
TWI554665B (en) Steel wall
JP2005256571A (en) Continuous wall and its construction method
JPH0971951A (en) Deep foundation structure using pipe pile, etc., and execution method thereof
JP4231194B2 (en) Revetment structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
REG Reference to a national code

Ref country code: HK

Ref legal event code: DE

Ref document number: 1251273

Country of ref document: HK

CB02 Change of applicant information
CB02 Change of applicant information

Address after: Tokyo, Japan, Japan

Applicant after: Nippon Iron & Steel Corporation

Address before: Tokyo, Japan, Japan

Applicant before: Nippon Steel Corporation

WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180727

REG Reference to a national code

Ref country code: HK

Ref legal event code: WD

Ref document number: 1251273

Country of ref document: HK