JPH07279428A - Constructing method of continuous frame by prestressed reinforced concrete construction - Google Patents

Constructing method of continuous frame by prestressed reinforced concrete construction

Info

Publication number
JPH07279428A
JPH07279428A JP6743294A JP6743294A JPH07279428A JP H07279428 A JPH07279428 A JP H07279428A JP 6743294 A JP6743294 A JP 6743294A JP 6743294 A JP6743294 A JP 6743294A JP H07279428 A JPH07279428 A JP H07279428A
Authority
JP
Japan
Prior art keywords
steel wire
concrete
prestressed reinforced
half precast
continuous frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6743294A
Other languages
Japanese (ja)
Inventor
Isao Hachiri
勲 八里
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP6743294A priority Critical patent/JPH07279428A/en
Publication of JPH07279428A publication Critical patent/JPH07279428A/en
Pending legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To solve trouble on processes until strength is displayed at a time when a method of post-tensioning construction is applied while omitting cost required for a grouting. CONSTITUTION:Half PCa beams 2 formed in U-shaped cross sections are arranged continuously among a plurality of columns 1, the half PCa beams are joined mutually by primary concrete or a joining means such as the welding of steel sheets in zones surrounded by the columns 1 and panels 1a, and PC steel wires 6 are disposed in the cavity sections of the half PCa beams 2 and stretched. Concrete is placed in the cavity sections.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、ハーフプレキャスト
コンクリート(以下ハーフPCaと称する)で構成され
るプレストレスト鉄筋コンクリート造の連続架構の構築
方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a continuous prestressed reinforced concrete frame composed of half precast concrete (hereinafter referred to as half PCa).

【0002】[0002]

【従来の技術】プレストレスト鉄筋コンクリート構造で
は、一般に鉄筋の組立時にPC(プレストレスト鉄筋コ
ンクリート)用シース管を配管してコンクリートを打設
し、コンクリートの強度発現後PC鋼線をシース管内に
挿入して緊張、定着及びグラウトを行なうポストテンシ
ョニング工法と、PC用シースに替えてグラウトの不要
なアンボンドPC工法がある。
2. Description of the Related Art In a prestressed reinforced concrete structure, a sheath pipe for PC (prestressed reinforced concrete) is generally piped to pour concrete at the time of assembling the rebar, and after the strength of the concrete is manifested, a PC steel wire is inserted into the sheath pipe for tensioning, There are a post-tensioning method for fixing and grout, and an unbonded PC method that does not require grout instead of a PC sheath.

【0003】これらはいずれも梁のように、引っ張り応
力が加わり易い部材の引っ張り抵抗を増加させ、曲げ抵
抗を増大させるため、大スパンの架構が容易になる利点
がある。
All of these have an advantage that a frame with a large span is easy because the tensile resistance of a member, such as a beam, to which tensile stress is easily applied increases, and the bending resistance increases.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、前者の
工法を柱梁の連続架構の構築に適用した場合には、梁を
構成するコンクリートの強度発現を待ってから緊張作業
に着手するため、工程上の問題があり、またグラウト費
用が嵩む欠点があった。
However, when the former construction method is applied to the construction of a continuous frame-column structure, tension work is started after waiting for the strength of the concrete forming the beam to start. There was a problem that the grout cost was increased.

【0005】また後者のアンボンドPC工法を架構に適
用した場合には、PC鋼線とコンクリートとの付着力は
本質的に弱いため、地震力を負担する大梁のような主要
部材に用いるのは困難であり、用途が限定されていた。
When the latter unbonded PC construction method is applied to a frame, the adhesive force between PC steel wire and concrete is essentially weak, so that it is difficult to use it for a main member such as a girder that bears an earthquake force. Therefore, the application was limited.

【0006】この発明は、以上の欠点に鑑みなされたも
のであって、その目的は、ポストテンショニング工法を
適用した場合における強度発現までの工程的問題を解決
するとともに、グラウトにかかる費用を省略できるよう
にしたPCコンクリート造による連続架構の構築方法を
提供するものである。
The present invention has been made in view of the above-mentioned drawbacks, and an object thereof is to solve the process problem until the strength is exerted when the post-tensioning method is applied and to reduce the cost for grout. The present invention provides a method for constructing a continuous frame made of PC concrete that is made possible.

【0007】またこの発明の他の目的は、ハーフPCa
梁の緊張端及び定着端に、直接PC鋼線を緊張定着でき
るようにすることにある。
Another object of the present invention is a half PCa.
The purpose is to enable the PC steel wire to be tensioned and anchored directly to the tensioned and anchored ends of the beam.

【0008】この発明のさらに他の目的は、柱を挟んで
連続する複数のハーフPCa梁間に導入プレストレス力
を伝達できるようにすることにある。
Still another object of the present invention is to enable the introduction prestressing force to be transmitted between a plurality of half PCa beams which are continuous with a column interposed therebetween.

【0009】この発明のまたさらなる他の目的は、配置
されるPC鋼線のハーフPCa内での正確な高さを確保
できるようにすることにある。
Still another object of the present invention is to ensure the accurate height of the PC steel wire to be placed in the half PCa.

【0010】[0010]

【課題を解決するための手段】前記目的を達成するため
この発明は、断面U字形をなしたハーフPCa梁を複数
の柱間に連続配置し、柱パネルゾーン内で前記ハーフP
Ca梁同士を接合手段により接合した後、PC鋼線をハ
ーフPCa梁の空洞部に配置して緊張し、その後該空洞
部にコンクリートを打設することを特徴とする。
In order to achieve the above-mentioned object, the present invention is to dispose a half PCa beam having a U-shaped cross section continuously between a plurality of columns, and to form the half P in a column panel zone.
After joining the Ca beams to each other by a joining means, a PC steel wire is placed in the hollow portion of the half PCa beam and tensioned, and then concrete is placed in the hollow portion.

【0011】またこの発明では、前記ハーフPCa梁の
緊張端及び定着端の部分のみを前記PC鋼線が挿入され
るシースとコーンまたはキャスティングを打込んだフル
プレキャスト梁とすることができる。
Further, according to the present invention, only the portions of the half PCa beam at the tension end and the fixing end can be a full precast beam in which a sheath into which the PC steel wire is inserted and a cone or casting is driven.

【0012】さらにこの発明では、前記接合手段が前記
ハーフPCa梁が交叉する柱パネルゾーンで前記PC鋼
線が配置される高さより下の位置に一次コンクリートを
打設し、その後PC鋼線を配置し、プレストレス力を前
記各ハーフPCa梁間に伝達させることができる。
Further, according to the present invention, the joining means places primary concrete at a position lower than the height at which the PC steel wire is arranged in the column panel zone where the half PCa beams intersect, and then the PC steel wire is arranged. However, the prestressing force can be transmitted between the half PCa beams.

【0013】また、前記一次コンクリートの打設作業に
替えてハーフPCa梁の端部に打込んだ鋼板を溶接によ
り接合することもできる。
Further, instead of the operation of placing the primary concrete, it is also possible to join the steel plates punched at the ends of the half PCa beams by welding.

【0014】さらにこの発明は、前記ハーフPCa梁の
空洞内部には前記PC鋼線の挿通方向に沿って該PC鋼
線を所定の高さ位置に保持するための支持手段が設けら
れている構成も採用できる。
Further, according to the present invention, a supporting means for holding the PC steel wire at a predetermined height position is provided inside the cavity of the half PCa beam along the insertion direction of the PC steel wire. Can also be adopted.

【0015】[0015]

【作用】以上の構成によるこの発明方法では、柱に結合
した各ハーフPCa梁そのものでPC鋼線に導入される
プレストレス力を支え、その後の空洞内へのコンクリー
ト打設によりPC鋼線の定着ととともに、連続架構が完
成する(請求項1)。
In the method of the present invention having the above construction, each half PCa beam itself connected to the column supports the prestressing force introduced into the PC steel wire, and the concrete is then cast into the cavity to fix the PC steel wire. Together with, the continuous frame is completed (Claim 1).

【0016】請求項2の構成とした場合にはPC鋼線の
緊張及び定着を一般的PC工法により行うことができ
る。
When the construction of claim 2 is adopted, the tension and fixing of the PC steel wire can be carried out by a general PC construction method.

【0017】請求項3,4の構成とした場合、各ハーフ
PCaの柱に対する定着後、柱を挾んで連続する複数の
ハーフPCa内に支障なくPC鋼線を配線できる。プレ
ストレス導入後の柱梁間の変形も防止される。
According to the third and fourth aspects, after the fixing of each half PCa to the pillar, the PC steel wire can be wired in the plurality of continuous half PCa by sandwiching the pillar without any trouble. Deformation between columns and beams after the introduction of prestress is also prevented.

【0018】請求項5の構成とした場合、PC鋼線の各
ハーフPCa内での正確な高さを確保でき、PC鋼線の
緊張とともに発生する鉛直方向の力をハーフPCa梁に
伝達できる。
In the case of the fifth aspect, the accurate height of the PC steel wire in each half PCa can be secured, and the vertical force generated with the tension of the PC steel wire can be transmitted to the half PCa beam.

【0019】[0019]

【実施例】以下、この発明の一実施例を手順を追って詳
細に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described in detail below step by step.

【0020】図1(a)〜(c)はこの発明方法の施工
手順を示すもので、まず図1(a)において、各柱1の
上部にこの発明による各ハーフPCa梁2が十字形に交
差して架設され、柱1の上部に設けられたパネル1a内
にその端部が設置される。
FIGS. 1 (a) to 1 (c) show a construction procedure of the method of the present invention. First, in FIG. 1 (a), each half PCa beam 2 according to the present invention is formed in a cross shape on an upper portion of each pillar 1. The ends are installed in the panel 1a provided on the upper part of the pillar 1 so as to cross each other.

【0021】各ハーフPCa梁2は、図2、及び図3
(a),(b)に示すように、梁主筋2a及びこれと直
交して配置され上部に突出する多数のU字形のスターラ
ップ筋2bを一体に埋設した状態で断面U字形に成形さ
れたPCa梁躯体3からなるもので、梁躯体3の空洞内
部には下端および両端を梁躯体3に接合した高さの異な
る一対のT字形保持金物4,5を所定間隔をおいて配列
している。
Each half PCa beam 2 is shown in FIG. 2 and FIG.
As shown in (a) and (b), the beam main reinforcement 2a and a large number of U-shaped stirrup reinforcements 2b arranged orthogonal to the main reinforcement 2a are molded in a U-shaped cross section in a state where they are integrally embedded. It is composed of PCa beam skeleton 3, and inside the cavity of beam skeleton 3, a pair of T-shaped holding hardwares 4 and 5 having different heights whose lower end and both ends are joined to beam skeleton 3 are arranged at predetermined intervals. .

【0022】各保持金物4,5はそれぞれの上部にシー
ス短管4a,5aを一体に溶接したもので、この各シー
ス短管4a,5aにPC鋼線6を通し、緊張することに
よって、各PC鋼線6の高さを正確に保持するものであ
る。
Each of the holding hardwares 4 and 5 is obtained by integrally welding sheath short pipes 4a and 5a on the upper part thereof, and by passing the PC steel wire 6 through each of the sheath short pipes 4a and 5a and tensioning the sheath short pipes 4a and 5a, The height of the PC steel wire 6 is accurately maintained.

【0023】なお、図1(c)の両側に示される前記各
ハーフPCa梁2による連続架構の終端部における前記
PC鋼線6の緊張及び定着部位は、図4,5に示すよう
に前記梁躯体3の空洞部から斜めに立ち上がるフルプレ
キャスト充填構造であり、この定着部位3aから端面に
向けて一対のロ―ト状シース3bを開口形成し、前記各
PC鋼線6の端部をこれに挿通し、定着部位3aの端面
でウエッジ7により緊張定着するようにしている。
The tension and fixing portions of the PC steel wire 6 at the end of the continuous frame composed of the half PCa beams 2 shown on both sides of FIG. 1 (c) are as shown in FIGS. It is a full precast filling structure that rises diagonally from the hollow portion of the skeleton 3, and a pair of funnel-shaped sheaths 3b are opened from this fixing portion 3a toward the end face, and the end portion of each PC steel wire 6 is formed in this. Through insertion, the wedge 7 is used for tension fixing at the end surface of the fixing portion 3a.

【0024】前記シース3bには、これと連通する空気
抜き孔3cを端面に開口しており、後述するコンクリー
ト打設工程において、シース3b内に流動コンクリート
が充填されてグラウト効果が発揮されるようにしてい
る。
An air vent hole 3c communicating with the sheath 3b is opened on the end face so that fluid concrete is filled in the sheath 3b in the concrete pouring step to be described later so that the grout effect is exerted. ing.

【0025】次に各ハーフPCa梁2の架設終了後に図
1(b)に示すように、ハーフPCa梁2で囲われる平
面内に合板型枠、デッキプレートなどのスラブ型枠8あ
るいはPC版を一面に敷設し、在来の床型枠工法により
スラブを施工する。
After the half PCa beams 2 have been erected, a slab form 8 such as a plywood form or a deck plate or a PC plate is placed in a plane surrounded by the half PCa beams 2 as shown in FIG. 1 (b). It will be laid on one side and a slab will be constructed using the conventional floor formwork method.

【0026】これと同時に各ハーフPCa梁2を柱1に
接合する。この接合方法としては導入されるプレストレ
スト力が連続して伝達できるように、例えば図6(a)
に示すように、柱1とパネル1aで囲われるゾーン内で
PC鋼線6が張設される下端より下部に無収縮早強コン
クリートからなる一次コンクリート9を打設し、対面す
るハーフPCa梁2を連結する方法と、図6(b)に示
すように、前記柱1とパネル1aで囲われたゾーン内に
おいて、ハーフPCa梁2の端部に打ち込まれた鋼板1
0を井桁状にして現場溶接する方法の二通りの方法があ
り、現場において最も適宜な接合方法を選択できる。
At the same time, each half PCa beam 2 is joined to the pillar 1. As this joining method, the introduced prestressing force can be continuously transmitted, for example, as shown in FIG.
As shown in Fig. 1, a primary concrete 9 made of non-shrink fast early concrete is placed below the lower end where the PC steel wire 6 is stretched in the zone surrounded by the pillar 1 and the panel 1a, and the facing half PCa beam 2 As shown in FIG. 6 (b), the steel plate 1 driven into the end of the half PCa beam 2 in the zone surrounded by the pillar 1 and the panel 1 a.
There are two methods of in-situ welding with 0 as a cross beam, and the most appropriate joining method can be selected in the field.

【0027】以上の連結作業終了後、図6(a),
(b)、および図1(c)に示すように各PC鋼線6を
柱1を挾んで連続する各ハーフPCa梁2のシース管4
b,5bに通して配線し、その両端を一般に採用されて
いるPC工法に適合する方法、例えばジャッキで引っ張
りウエッジ方式によって止めるなどして緊張および定着
し、プレストレスを導入する。
After the above connecting work is completed, as shown in FIG.
As shown in (b) and FIG. 1 (c), the sheath tube 4 of each half-PCa beam 2 that is continuous with each PC steel wire 6 across the column 1.
Wiring is carried out through b and 5b, and both ends thereof are tensioned and fixed by a method adapted to a generally adopted PC construction method, for example, pulled by a jack and stopped by a wedge method to introduce prestress.

【0028】プレストレスの導入によってPC鋼線6の
緊張とともに発生する鉛直方向の力を保持金物4,5を
介して各ハーフPCa梁2に伝達できる。
By introducing the prestress, the vertical force generated together with the tension of the PC steel wire 6 can be transmitted to each half PCa beam 2 through the holding hardware 4 and 5.

【0029】プレストレスの導入後は、図1(c)に示
すように、各ハーフPCa梁2の上部に突出するスター
ラップ筋2bと梁の上端主筋11aあるいはスラブ筋1
1bを組立てた後、ハーフPCa梁2の空洞部とスラブ
に現場打ちコンクリートCを打設する。
After the pre-stress is introduced, as shown in FIG. 1 (c), the stirrup ribs 2b protruding above the half PCa beams 2 and the upper main ribs 11a of the beams or the slab ribs 1 are formed.
After assembling 1b, cast-in-place concrete C is poured into the cavity and slab of the half PCa beam 2.

【0030】コンクリートCの固化によって、梁躯体3
の空洞部は完全に充填され、一体化した梁が形成される
と同時にPC鋼線6はコンクリートCのグラウト効果に
より定着し、プレストレスト鉄筋コンクリート作りの連
続架構を完成することになる。
By solidifying the concrete C, the beam frame 3
At the same time, the cavity is completely filled and an integrated beam is formed, and at the same time, the PC steel wire 6 is settled by the grout effect of the concrete C, and a continuous frame structure for prestressed reinforced concrete is completed.

【0031】なお、定着部位3aでは、空気抜き孔3c
を通じて空気を追い出しつつシース3b内に流動するコ
ンクリートCが充填され、完全な定着状態となる。
In the fixing portion 3a, the air vent hole 3c
The concrete C flowing into the sheath 3b is filled while expelling air through it, and a complete fixing state is achieved.

【0032】[0032]

【発明の効果】以上実施例によって詳細に説明したよう
に、柱に結合した各ハーフPCa梁そのものでPC鋼線
に導入されるプレストレス力を支え、その後の空洞内へ
のコンクリート打設によりPC鋼線の定着と同時に連続
架構が完成するため、工程上の問題を解決できるととも
に、打設コンクリートがグラウトの機能も兼用し、グラ
ウト注入の手間も省略されるため、安価にでき、構造上
からも柱を挾んで連続する複数の梁間に歪みを生ずるこ
となく連続してプレストレス力を伝達できるため個々の
梁にプレストレスを導入する場合に比べてプレトレス力
が均一化し、作業自体も簡略化する利点がある。したが
って、この発明は、地震力を負担する大梁のような主要
部の構築方法として好適であるほか、PC鋼線自体も錆
びにくいものとなる利点がある。
As described above in detail with reference to the embodiments, the half PCa beams themselves connected to the columns support the prestressing force introduced into the PC steel wire, and the concrete is then poured into the cavity to form the PC. Since the continuous frame is completed at the same time as the steel wire is fixed, problems in the process can be solved, and the pouring concrete also serves the function of grout, and the labor of grout injection is omitted, so it can be made cheaper and structurally Also, since the prestressing force can be transmitted continuously without distorting between the multiple beams across the column, the prettress force becomes more uniform than when prestressing is applied to each beam, and the work itself is also simplified. There is an advantage to Therefore, the present invention is suitable as a method for constructing a main part such as a girder that bears seismic force, and also has an advantage that the PC steel wire itself is less likely to rust.

【0033】また、この発明の請求項2の構成とするこ
とにより、PC鋼線の緊張及び定着を一般的PC工法で
行うことができ、作業を簡略化できる。
Further, according to the second aspect of the present invention, the tension and fixing of the PC steel wire can be performed by the general PC construction method, and the work can be simplified.

【0034】この発明の請求項3,4の構成とすること
により、PC鋼線の配線に支障がなく、しかもプレスト
レス導入時における柱梁の接合部に変形を生じない利点
がある。
The structure of claims 3 and 4 of the present invention has an advantage that the wiring of the PC steel wire is not hindered and the joint portion of the column and beam is not deformed when the prestress is introduced.

【0035】さらにこの発明の請求項5の構成とするこ
とにより、PC鋼線の各ハーフPCa内での正確な高さ
を確保できるとともに、PC鋼線の緊張とともに発生す
る鉛直方向のプレストレス力も梁に伝達できる利点があ
る。
Further, according to the fifth aspect of the present invention, the accurate height of the PC steel wire in each half PCa can be ensured, and the vertical prestressing force generated with the tension of the PC steel wire can be secured. There is an advantage that it can be transmitted to the beam.

【図面の簡単な説明】[Brief description of drawings]

【図1】(a)〜(c)はこの発明による連続架構の構
築手順を示す説明図である。
1A to 1C are explanatory views showing a procedure for constructing a continuous frame according to the present invention.

【図2】ハーフPCaと柱との接合部分を示す拡大斜視
図である。
FIG. 2 is an enlarged perspective view showing a joint portion between a half PCa and a column.

【図3】(a)は同ハーフPCa梁の断面図である。
(b)は(a)のA−A線断面図である。
FIG. 3A is a sectional view of the half PCa beam.
(B) is the sectional view on the AA line of (a).

【図4】ハーフPCaの緊張および定着部位の拡大断面
図である。
FIG. 4 is an enlarged cross-sectional view of a tension and fixing portion of the half PCa.

【図5】同斜視図である。FIG. 5 is a perspective view of the same.

【図6】(a)はハーフPCaの柱に対する接合方法の
一例を示す部分断面図である。(b)同接合方法の他の
例を示す部分拡大断面図である。
FIG. 6A is a partial cross-sectional view showing an example of a method of joining half PCa to a column. (B) It is a partial expanded sectional view showing another example of the joining method.

【符号の説明】[Explanation of symbols]

1 柱 1a パネル 2 ハーフPCa梁 3 PCa梁躯体 4,5 保持金物 6 PC 鋼線 9 一次コンクリート 10 鋼板 C コンクリート 1 Pillar 1a Panel 2 Half PCa Beam 3 PCa Beam Frame 4,5 Holding Hardware 6 PC Steel Wire 9 Primary Concrete 10 Steel Plate C Concrete

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 断面U字形をなしたハーフプレキャスト
コンクリート梁を複数の柱間に連続配置し、柱パネルゾ
ーン内で前記ハーフプレキャストコンクリート同士を接
合手段により接合した後、PC鋼線をハーフプレキャス
トコンクリート梁の空洞部に配置して緊張し、その後該
空洞部にコンクリートを打設することを特徴とするプレ
ストレスト鉄筋コンクリート造による連続架構の構築方
法。
1. A half precast concrete beam having a U-shaped cross section is continuously arranged between a plurality of columns, and the half precast concrete is joined by a joining means in a column panel zone, and then a PC steel wire is half precast concrete. A method for constructing a continuous frame by prestressed reinforced concrete construction, which comprises arranging in a hollow portion of a beam and tensioning it, and then placing concrete in the hollow portion.
【請求項2】 前記ハーフプレキャストコンクリート梁
の緊張端及び定着端の部分のみを前記PC鋼線が挿入さ
れるシースとコーンまたはキャスティングを打込んだフ
ルプレキャスト梁とすることを特徴とする請求項1記載
のプレストレスト鉄筋コンクリート造による連続架構の
構築方法。
2. A full precast beam in which a sheath and a cone into which the PC steel wire is inserted and a cone or a casting are cast only in the portions of the tensioned end and the anchored end of the half precast concrete beam. A method for constructing a continuous frame by the prestressed reinforced concrete construction described.
【請求項3】 前記接合手段は、前記ハーフプレキャス
トコンクリート梁が交叉する柱パネルゾーンで前記PC
鋼線が配置される高さより下の位置に一次コンクリート
を打設し、その後PC鋼線を配置し、プレストレス力を
前記各ハーフプレキャストコンクリート梁間に伝達させ
ることを特徴とする請求項1または2記載のプレストレ
スト鉄筋コンクリート造による連続架構の構築方法。
3. The joining means comprises a pillar panel zone where the half precast concrete beams intersect with each other,
The primary concrete is placed at a position lower than the height at which the steel wire is arranged, and then the PC steel wire is arranged to transfer a prestressing force between the respective half precast concrete beams. A method for constructing a continuous frame by the prestressed reinforced concrete construction described.
【請求項4】 前記一次コンクリートの打設作業に替え
て前記ハーフプレキャストコンクリート梁の端部に打込
んだ鋼板を溶接により接合することを特徴とする請求項
1または2記載のプレストレスト鉄筋コンクリート造に
よる連続架構の構築方法。
4. The prestressed reinforced concrete construction according to claim 1 or 2, characterized in that, instead of the operation of placing the primary concrete, the steel plates driven into the ends of the half precast concrete beams are joined by welding. How to build a frame.
【請求項5】 前記ハーフプレキャストコンクリートの
空洞内部には前記PC鋼線の挿通方向に沿って該PC鋼
線を所定の高さ位置に保持するための支持手段が設けら
れていることを特徴とする請求項1〜4のいずれかに記
載のプレストレスト鉄筋コンクリート造による連続架構
の構築方法。
5. A supporting means for holding the PC steel wire at a predetermined height position along the insertion direction of the PC steel wire is provided inside the cavity of the half precast concrete. The method for constructing a continuous frame by prestressed reinforced concrete construction according to any one of claims 1 to 4.
JP6743294A 1994-04-05 1994-04-05 Constructing method of continuous frame by prestressed reinforced concrete construction Pending JPH07279428A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6743294A JPH07279428A (en) 1994-04-05 1994-04-05 Constructing method of continuous frame by prestressed reinforced concrete construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6743294A JPH07279428A (en) 1994-04-05 1994-04-05 Constructing method of continuous frame by prestressed reinforced concrete construction

Publications (1)

Publication Number Publication Date
JPH07279428A true JPH07279428A (en) 1995-10-27

Family

ID=13344754

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6743294A Pending JPH07279428A (en) 1994-04-05 1994-04-05 Constructing method of continuous frame by prestressed reinforced concrete construction

Country Status (1)

Country Link
JP (1) JPH07279428A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155095A (en) * 2011-03-22 2011-08-17 中国十九冶集团有限公司 Arrangement method of steel rib concrete steel bars of large metallurgical industry factory building
JP2014237951A (en) * 2013-06-07 2014-12-18 鹿島建設株式会社 Precast member set and press method for precast member
CN113652969A (en) * 2021-08-13 2021-11-16 中交第一航务工程局有限公司 Prefabricated construction method for tie beam between road bridge piers of various levels

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155095A (en) * 2011-03-22 2011-08-17 中国十九冶集团有限公司 Arrangement method of steel rib concrete steel bars of large metallurgical industry factory building
JP2014237951A (en) * 2013-06-07 2014-12-18 鹿島建設株式会社 Precast member set and press method for precast member
CN113652969A (en) * 2021-08-13 2021-11-16 中交第一航务工程局有限公司 Prefabricated construction method for tie beam between road bridge piers of various levels

Similar Documents

Publication Publication Date Title
JPH1096263A (en) Precast concrete support and assembling method of slab
JPH0711710A (en) Reinforced concrete column and steel frame beam jointing structure and building constructing method
JPH07279428A (en) Constructing method of continuous frame by prestressed reinforced concrete construction
JPH07292773A (en) Construction method of framework with steel pipe concrete column
JP2001295404A (en) Method for driving hollow pipe into reinforced permanent form
JP3004242B2 (en) Building material for vibration control, vibration control structure and construction method
JPH10227010A (en) Steel form with main reinforcement for bridge floor panel and bridge floor panel construction method using it
JPH06158716A (en) Construction method of building with precast concrete member
JP2002332691A (en) Joint construction between column and beam
JPH06185111A (en) Precast concrete beam and column and construction method of earthquake-proof wall using them
JP3319709B2 (en) Construction method of prestressed concrete steel beam
JP2641836B2 (en) Precast prestressed concrete U-beam
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JP2568987B2 (en) Support member for reinforcing steel assembly and bridge construction method using the same
JPH06306931A (en) Construction of steel frame reinforced concrete structure
JPS61169559A (en) Semi-existing concrete panel using assembled reinforcement
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JP4184538B2 (en) Column base semi-fixed joint structure, building and building design method
JP3010355B1 (en) Construction method of joint of prestressed concrete floor
JPH07252882A (en) Connecting method for building frame
JP3041754U (en) Half precast slab
JPH02120446A (en) Precast concrete panel
JPH06306935A (en) Connection structure of column and beam of rc structure and its construction
JPH03132544A (en) Setting of precast beam
JPH0588331B2 (en)