JP3004242B2 - Building material for vibration control, vibration control structure and construction method - Google Patents
Building material for vibration control, vibration control structure and construction methodInfo
- Publication number
- JP3004242B2 JP3004242B2 JP9361755A JP36175597A JP3004242B2 JP 3004242 B2 JP3004242 B2 JP 3004242B2 JP 9361755 A JP9361755 A JP 9361755A JP 36175597 A JP36175597 A JP 36175597A JP 3004242 B2 JP3004242 B2 JP 3004242B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- building material
- vibration control
- cast
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Rod-Shaped Construction Members (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は、制震用建築材料、
制震構造及びその構築方法に関し、特に、ある程度強度
部材としての強度を有し、かつ、必要時に十分な制震力
を発揮できる制震用建築材料、制震構造及びその構築方
法に関する。The present invention relates to a building material for vibration control,
The present invention relates to a damping structure and a method of constructing the same, and more particularly to a damping building material, a damping structure and a method of constructing the same, which have a certain strength as a strength member and can exert a sufficient damping force when necessary.
【0002】[0002]
【背景技術および発明が解決しようとする課題】建築物
の制震構造は、従来より種々開発され、かつ、使用され
てきている。BACKGROUND ART Various types of vibration control structures for buildings have been developed and used in the past.
【0003】その一例として、例えば、柱や壁の途中に
制震装置を組み込み、地震時に建築物に層間変形が生
じ、せん断変形力を受けたた場合に、制震装置によりそ
の入力エネルギーを吸収するようにしたものがある。[0003] As one example, for example, a vibration damping device is installed in the middle of a column or a wall, and when a building undergoes interlayer deformation during an earthquake and receives a shearing deformation force, the input energy is absorbed by the vibration damping device. There are things that I try to do.
【0004】このように柱や壁の途中に制震装置を組み
込む場合、柱や壁を制震装置の組み込み部分をあけた状
態で構築した後、そのあいている部分に制震装置を挿入
して固定するようにしている。[0004] When a vibration control device is installed in the middle of a column or a wall in this manner, the column or wall is constructed with the built-in portion of the vibration control device opened, and then the vibration control device is inserted into the open portion. To fix it.
【0005】また、このような柱や壁を、例えば、鉄筋
コンクリートで構築する場合、柱や壁にスタッドを打ち
込んで制震装置を固定するようにしている。[0005] When such columns and walls are constructed of, for example, reinforced concrete, studs are driven into the columns and walls to fix the vibration damping device.
【0006】しかし、このような固定状態では、地震時
に建築物に層間変形が生じてせん断変形力を受けた場合
に、スタッドが柱や壁から抜け出してしまい、地震入力
エネルギーを吸収できないような事態が生じやすいもの
である。However, in such a fixed state, when a building undergoes interlayer deformation during an earthquake and is subjected to a shearing deformation force, the studs fall out of columns and walls, and the earthquake input energy cannot be absorbed. Is likely to occur.
【0007】また、鉄筋コンクリートで柱や梁を構築す
る場合には、コンクリート型枠を組んで、このコンクリ
ート型枠を支保工等で支持する作業が必要となり、作業
に手間がかかるものであった。In addition, when columns and beams are constructed of reinforced concrete, it is necessary to construct a concrete formwork and to support the concrete formwork by supporting works or the like, which is troublesome.
【0008】さらに、制震装置として、低降伏点パネル
鋼を用い、地震時のエネルギーを材料の降伏によって吸
収するようにしたものも知られているが、このような制
震装置にあっては、鉄筋コンクリートの柱や壁に取り付
けると、上部の柱や壁の自重が制震装置にかかって、変
形が生じ、地震時に良好なエネルギー吸収能力を発揮す
ることができない場合が生じることがある。Further, as a vibration control device, a device using low yield point panel steel to absorb energy at the time of an earthquake by yielding a material is also known. When mounted on a reinforced concrete column or wall, the weight of the upper column or wall may be applied to the vibration damping device, causing deformation, and failing to exhibit good energy absorption capacity during an earthquake.
【0009】本発明は、このような点に着目してなされ
たもので、その目的は、鉄筋コンクリート製の柱や壁に
制震装置を組み込む場合に、地震時に建築物に層間変形
が生じて、せん断力が加わった場合にも、制震装置の取
付部分が容易に破損することがなく、十分な取り付け強
度を有し、地震入力エネルギーを確実に吸収でき、しか
も製造の容易な制震用建築材料、制震構造及びその構築
方法を提供することにある。The present invention has been made in view of such a point. An object of the present invention is to incorporate a vibration control device into a reinforced concrete column or wall, and to cause interlayer deformation in a building during an earthquake, Even if a shear force is applied, the mounting part of the vibration control device is not easily damaged, has sufficient mounting strength, can reliably absorb the earthquake input energy, and is easy to manufacture. An object of the present invention is to provide a material, a vibration control structure, and a method of constructing the same.
【0010】本発明の他の目的は、制震装置として、低
降伏点パネル鋼を用いた場合にも、上部の柱や壁の自重
によって変形が生じることなく、地震時に良好なエネル
ギー吸収能力を発揮することのできる制震用建築材料、
制震構造及びその構築方法を提供することにある。Another object of the present invention is to provide a good energy absorption capacity at the time of an earthquake without deformation due to the weight of upper columns and walls even when a low yield point panel steel is used as a vibration control device. Building materials for vibration control that can be demonstrated
An object of the present invention is to provide a vibration control structure and a method of constructing the same.
【0011】本発明のさらに他の目的は、鉄筋コンクリ
ートで柱や梁を構築する場合に、コンクリート型枠を支
保工等で支持する作業を不要とし、作業の手間を省略す
ることのできる制震用建築材料、制震構造及びその構築
方法を提供することにある。Still another object of the present invention is to provide a seismic control system for constructing columns and beams made of reinforced concrete, which eliminates the need to support a concrete formwork by shoring or the like, and saves time and effort. It is an object of the present invention to provide a building material, a vibration control structure, and a method for constructing the same.
【0012】[0012]
【課題を解決するための手段】本発明は前記目的を達成
するためになしたもので、請求項1記載の発明に係る制
震用建築材料は、建築物の強度部材を貫通して上下方向
に複数接続される制震用建築材料であって、少なくとも
複数の主筋を埋設して形成され前記建築物の強度部材上
に設置可能にされたプレキャストコンクリート部と、前
記プレキャストコンクリート部より前記主筋を延出させ
て前記建築物の強度部材を貫通して前記強度部材下方に
突出されると共に、現場打ちコンクリートの打設により
前記強度部材と一体化される現場打ちコンクリート打設
部と、一方で前記プレキャストコンクリート部の前記現
場打ちコンクリート打設部と反対側で前記プレキャスト
コンクリート部の主筋に固定され、他方で上方に接続さ
れる制震用建築材料の現場打ちコンクリート打設部先端
の前記主筋と連結固定可能にされる制震装置とを備える
ことを特徴とする。SUMMARY OF THE INVENTION The present invention has been made to achieve the above object, and a building material for vibration damping according to the first aspect of the present invention penetrates a strength member of a building in a vertical direction. A plurality of seismic control building materials connected to a precast concrete part formed by burying at least a plurality of main reinforcements and capable of being installed on a strength member of the building, and the main reinforcements from the precast concrete parts. A cast-in-place concrete casting part that extends and penetrates through the strength member of the building and projects downwardly from the strength member, and is integrated with the strength member by casting cast-in-place concrete; A seismic control building material fixed to the main reinforcement of the precast concrete part on the opposite side of the precast concrete part from the cast-in-place concrete placement part, and connected on the other side upward Characterized in that it comprises a and a cast-in-place concrete portion the tip of the main reinforcement and connection fixable to be the vibration control device.
【0013】本発明によれば、プレキャストコンクリー
ト部の主筋に予め固定された制震装置に、上方に接続さ
れる制震用建築材料の現場打ちコンクリート打設部先端
の主筋を連結固定し、現場打ちコンクリート打設部にコ
ンクリートを打設することで、強度部材と一体化するこ
とができ、構築が容易に行えると共に、制震装置は、主
筋と一体にされているため、十分な強度を有し、地震時
に建築物に層間変形が生じて、せん断力が加わった場合
でも、制震装置の取付部分が容易に破損することがな
く、地震入力エネルギーを確実に吸収できる。According to the present invention, the main reinforcement at the tip of the cast-in-place concrete casting portion of the building material for vibration control connected upward is connected and fixed to the vibration control device fixed in advance to the main reinforcement of the precast concrete portion. Casting concrete into the cast-in-concrete casting section can be integrated with the strength members, facilitating construction. In addition, the vibration control device has sufficient strength because it is integrated with the main reinforcement. However, even if the building undergoes interlayer deformation during an earthquake and a shear force is applied, the mounting portion of the vibration damping device is not easily damaged, and the earthquake input energy can be reliably absorbed.
【0014】請求項2記載の発明は、請求項1におい
て、前記制震装置は、前記プレキャストコンクリート部
の主筋または前記現場打ちコンクリート打設部の主筋と
固定される対向する一対のベースプレートと、前記一対
のベースプレートとの間に取り付けられた少なくとも2
つのフランジプレートと、前記ベースプレートと前記フ
ランジプレートとに囲まれる部分に取り付けられた低降
伏点パネル鋼とを備えることを特徴とする。According to a second aspect of the present invention, in the first aspect, the vibration control device comprises a pair of opposed base plates fixed to a main reinforcement of the precast concrete portion or a main reinforcement of the cast-in-place concrete placing portion. At least two attached between a pair of base plates
And a flange plate, and a low yield point panel steel attached to a portion surrounded by the base plate and the flange plate.
【0015】本発明によれば、請求項1の状態に加え、
制震装置に低降伏点パネル鋼を用いる場合であっても、
フランジプレートによって補強することで、低降伏点パ
ネル鋼にかかる軸力をフランジプレートによって負担
し、低降伏点パネル鋼にかかる軸力を軽減して、良好な
地震時の入力エネルギーの吸収能力を発揮させることが
できる。According to the present invention, in addition to the first aspect,
Even if low yield point panel steel is used for the damping device,
By reinforcing with a flange plate, the axial force applied to the low yield point panel steel is borne by the flange plate, and the axial force applied to the low yield point panel steel is reduced, demonstrating a good ability to absorb input energy during earthquakes. Can be done.
【0016】また、このように、制震装置を補強するこ
とで、制震部材を上方の制震建築材料の現場打ちコンク
リート打設部に対するコンクリート打設時のコンクリー
ト型枠の支保工として使用することができ、支保工設置
に要する手間を省略することができる。Further, by reinforcing the vibration damping device in this way, the vibration damping member is used as a support for the concrete formwork at the time of placing concrete in the cast-in-place concrete placing portion of the upper vibration damping building material. And the labor required for the installation of the shoring can be omitted.
【0017】請求項3記載の発明は、請求項2におい
て、前記フランジプレート間には、リブプレートが取り
付けられることを特徴とする。According to a third aspect of the present invention, in the second aspect, a rib plate is attached between the flange plates.
【0018】本発明によれば、請求項2の状態に加え、
低降伏点パネル鋼全体に生じる面外座屈を防止して、よ
り良好なエネルギー吸収能力を発揮させることができ
る。According to the present invention, in addition to the state of claim 2,
Out-of-plane buckling occurring in the entire low yield point panel steel can be prevented, and a better energy absorbing ability can be exhibited.
【0019】請求項4記載の発明は、請求項1〜3のい
ずれかにおいて、前記プレキャストコンクリート部の前
記現場打ちコンクリート打設部側に位置する面には、前
記現場打ちコンクリート打設部への打設コンクリートと
の接合度を高めるコッタが形成されていることを特徴と
する。According to a fourth aspect of the present invention, in any one of the first to third aspects, the surface of the precast concrete portion which is located on the side of the cast-in-place concrete placing portion is provided with the cast-in-place concrete placing portion. It is characterized in that a cotter for increasing the degree of connection with the cast concrete is formed.
【0020】本発明によれば、請求項1〜3のいずれか
の状態に加え、コッタにより現場打ちコンクリート打設
部との接合強度を高めて、地震時のせん断力を現場打ち
コンクリート打設部から強度部材に確実に伝達させるこ
とができる。According to the present invention, in addition to any one of the first to third aspects, the joining strength with the cast-in-place concrete placing part is increased by a cotter, and the shear force during an earthquake is reduced by the cast-in-place concrete placing part. Can be reliably transmitted to the strength member.
【0021】請求項5記載の発明は、請求項4におい
て、前記コッタは、前記現場打ちコンクリート打設部に
向けて外側から内側に傾斜するテーパ部を有することを
特徴とする。According to a fifth aspect of the present invention, in the fourth aspect, the cotter has a tapered portion inclined from outside to inside toward the cast-in-place concrete placing portion.
【0022】本発明によれば、請求項4の状態に加え、
テーパ部により、打設したコンクリートがコッタ部分に
隙間なく確実に入り込んで、より接合強度を高めること
ができる。According to the present invention, in addition to the fourth aspect,
Due to the tapered portion, the poured concrete surely enters the cotter portion without any gap, and the joining strength can be further increased.
【0023】請求項6記載の制震構造は、請求項1〜5
のいずれかに記載の制震用建築材料を用いて構築される
制震構造であって、現場打ちコンクリート打設部へのコ
ンクリート打設にて階下の強度部材に一体化され、か
つ、プレキャストコンクリート部及びこのプレキャスト
コンクリート部の主筋に固定された制震装置を上方に突
出させた階下の制震用建築材料と、階上の強度部材を貫
通して現場打ちコンクリート打設部下端の主筋が前記階
下の制震用建築材料の制震装置と連結固定され、かつ、
現場打ちコンクリート打設部へのコンクリート打設にて
階上の強度部材に一体化された階上の制震用建築材料
と、を備えることを特徴とする。[0023] The vibration damping structure according to the sixth aspect is the first to fifth aspects.
A seismic control structure constructed using the building material for seismic control according to any one of the above, wherein the concrete is cast into a cast-in-place concrete casting section, and integrated with a strength member downstairs, and a precast concrete And the building material for seismic control of the downstairs with the damping device fixed to the main reinforcement of this precast concrete part protruding upward, and the main reinforcement at the lower end of the cast-in-place concrete casting part penetrating the strength member on the floor. It is connected and fixed to the vibration control device of building materials for vibration control downstairs, and
And a building material for seismic control on the floor integrated with the strength member on the floor by casting concrete in the cast-in-place concrete placing part.
【0024】本発明によれば、階下の強度部材から階上
の強度部材へと、主筋により一体化された強度の高い制
震構造を容易に得ることができ、しかも、地震時に良好
なエネルギー吸収能力を発揮させることができる。According to the present invention, it is possible to easily obtain a high-strength damping structure integrated by a main reinforcement from a lower-strength strength member to a higher-strength strength member. We can show ability.
【0025】請求項7記載の発明は、請求項6におい
て、前記階下の制震用建築材料と前記階上の制震用建築
材料との間に、中間制震用建築材料が設けられ、前記中
間制震用建築材料は、中間制震装置と、この中間制震装
置よりも剛性の高い支持部材とが予め一体的に固定さ
れ、前記支持部材が前記階下の制震用建築材料の制震装
置と連結固定されると共に、前記中間制震装置が前記階
上の制震用建築材料を構成する現場打ちコンクリート打
設部の主筋と連結固定されることを特徴とする。According to a seventh aspect of the present invention, in the sixth aspect, an intermediate vibration damping building material is provided between the vibration damping building material below the floor and the vibration damping building material above the floor. The building material for intermediate vibration damping includes an intermediate vibration damping device and a support member having a higher rigidity than the intermediate vibration damping device are integrally fixed in advance, and the support member is configured to control the vibration of the building material for vibration damping below the floor. The intermediate damping device is connected and fixed to a device, and the intermediate vibration damping device is connected and fixed to a main reinforcement of a cast-in-place concrete placing part constituting the building material for vibration control on the floor.
【0026】本発明によれば、請求項6の状態に加え、
階下の制震用建築材料の制震装置と、中間制震用建築材
料の中間制震装置との2箇所で、地震時のせん断力を吸
収することにより、1箇所あたりのせん断変形量を少な
くして、制震装置の損傷を抑えることができる。According to the present invention, in addition to the state of claim 6,
Reduces the amount of shear deformation per location by absorbing the shear force during an earthquake at two locations: the vibration control device for building materials for vibration control downstairs and the intermediate vibration control device for building materials for intermediate vibration control. Thus, damage to the vibration control device can be suppressed.
【0027】また、この中間制震用建築材料を用いるこ
とで、階高の建築物にも容易に対処することが可能とな
る。Also, by using this building material for intermediate vibration control, it is possible to easily cope with a building having a high floor.
【0028】請求項8記載の制震構造の構築方法は、請
求項1〜5のいずれかに記載の制震用建築材料を用いて
構築される制震構造の構築方法であって、階下の強度部
材を貫通させて階下の制震用建築材料を設置し、この階
下の制震用建築材料のプレキャストコンクリート部及び
制震装置を前記強度部材上に突出させた状態で、現場打
ちコンクリート打設部にコンクリートを打設して階下の
制震用建築材料を前記階下の強度部材と一体化させる工
程と、階上の強度部材上から前記階上の強度部材を貫通
させて階上の制震用建築材料の現場打ちコンクリート打
設部を前記階上の強度部材下方に突出させ、前記階上の
現場打ちコンクリート打設部の主筋下端を前記階下の制
震用建築材料の制震装置と連結固定する工程と、前記階
上の制震用建築材料の前記階上の強度部材下面より突出
する現場打ちコンクリート打設部の周囲にコンクリート
型枠を取り付ける工程と、前記階上の強度部材上から前
記階上の制震用建築材料の現場打ちコンクリート打設部
にコンクリートを打設する工程と、前記打設したコンク
リートが固化して階上の制震用建築材料と前記階上の強
度部材とが一体化した後、前記コンクリート型枠を取り
外す工程と、を含むことを特徴とする。According to a eighth aspect of the present invention, there is provided a method of constructing a vibration control structure using the building material for vibration control according to any one of the first to fifth aspects. The building material for seismic control under the floor is installed by penetrating the strength member, and the precast concrete part and the vibration control device of the building material for seismic control under the floor are protruded above the strength member, and cast-in-place concrete is cast. A step of casting concrete in the part to integrate the building material for vibration control on the lower floor with the strength member on the lower floor; and The cast-in-place concrete casting portion of the building material is projected below the strength member on the floor, and the lower end of the main bar of the cast-in-place concrete placement portion on the floor is connected to the vibration control device of the building material for vibration control below the floor. Fixing step and building material for vibration control on the floor Mounting a concrete formwork around the cast-in-place concrete casting portion projecting from the lower surface of the strength member on the floor, and casting the concrete material on the floor from the strength member on the floor. Removing the concrete formwork after the poured concrete has solidified and the building material for vibration control on the floor and the strength member on the floor have been integrated, and , Is included.
【0029】本発明によれば、簡単な作業で、階下の強
度部材から階上の強度部材へと、主筋により一体化され
た強度の高い制震構造を得ることができ、しかも、地震
時に良好なエネルギー吸収能力を発揮させることができ
る。According to the present invention, it is possible to obtain a high-strength vibration damping structure integrated by a main bar from a strength member downstairs to a strength member upstairs, with a simple operation. A high energy absorption capacity.
【0030】請求項9記載の発明は、請求項8におい
て、前記階下及び階上の強度部材として、柱上に掛け渡
された梁が用いられ、前記コンクリートの打設工程で
は、前記梁上に敷設された床版上に床用コンクリートを
打設する際に、その床用コンクリートを前記現場打ちコ
ンクリート打設部に打設することを特徴とする。According to a ninth aspect of the present invention, in the eighth aspect, as the downstairs and the upstairs strength members, a beam laid on a pillar is used, and in the concrete placing step, the beam is laid on the beam. When the concrete for floor is cast on the laid floor slab, the concrete for floor is poured into the cast-in-place concrete casting section.
【0031】本発明によれば、請求項8の状態に加え、
床用コンクリートの打設時に、そのコンクリートを現場
打ちコンクリート打設部に打設することで、容易に床及
び梁と一体化した制震構造を得ることができる。According to the present invention, in addition to the state of claim 8,
When the concrete for the floor is cast, the concrete is cast into the cast-in-place concrete placing portion, whereby a vibration control structure integrated with the floor and the beam can be easily obtained.
【0032】請求項10記載の発明は、請求項8におい
て、前記階下の制震用建築材料の制震装置上に、中間制
震装置と、この中間制震装置よりも剛性の高い支持部材
とが予め一体的に固定された中間制震用建築材料の前記
支持部材を連結固定した後、前記中間制震装置に前記階
上の制震用建築材料を構成する現場打ちコンクリート打
設部の主筋と連結固定する工程を含むことを特徴とす
る。According to a tenth aspect of the present invention, in accordance with the eighth aspect, an intermediate vibration damping device and a supporting member having higher rigidity than the intermediate vibration damping device are provided on the vibration damping device of the building material for vibration damping downstairs. After connecting and fixing the support member of the building material for intermediate vibration damping which has been previously fixed integrally, the main reinforcement of the cast-in-place concrete placing part constituting the building material for vibration damping on the floor is attached to the intermediate vibration damping device. And a step of connecting and fixing with.
【0033】本発明によれば、請求項8の状態に加え、
階下の制震用建築材料の制震装置と、中間制震用建築材
料の中間制震装置との上下2箇所に制震装置を有する制
震構造を容易に形成することができ、しかも、2箇所で
分割して地震時のせん断力を吸収することにより、1箇
所あたりのせん断変形量を少なくして、制震装置の損傷
を抑えることができる。According to the present invention, in addition to the state of claim 8,
It is possible to easily form a vibration control structure having a vibration control device at two places above and below a vibration control device for building materials for vibration control downstairs and an intermediate vibration control device for building materials for intermediate vibration control. By dividing at a location and absorbing the shearing force during an earthquake, the amount of shear deformation per location can be reduced, and damage to the damping device can be suppressed.
【0034】[0034]
【発明の実施の形態】以下、本発明の実施の形態につい
て図面を参照して詳細に説明する。Embodiments of the present invention will be described below in detail with reference to the drawings.
【0035】図1〜図9は、本発明の制震構造を用いた
一実施の形態にかかる制震柱を示す図である。FIGS. 1 to 9 are views showing a vibration control column according to an embodiment using the vibration control structure of the present invention.
【0036】この制震柱10は、図1に示すように、制
震用建築材料12を用い、建築物の強度部材である梁1
4を貫通して上下方向に連続して構築されるようになっ
ている。As shown in FIG. 1, the damping column 10 uses a building material 12 for damping, and a beam 1 as a strength member of a building.
4 and is constructed continuously in the vertical direction.
【0037】制震用建築材料12は、図2に示すよう
に、プレキャストコンクリート部20と、現場打ちコン
クリート打設部22と、制震装置24とを備える。As shown in FIG. 2, the building material 12 for vibration damping includes a precast concrete part 20, a cast-in-place concrete placing part 22, and a vibration damping device 24.
【0038】プレキャストコンクリート部20は、複
数、例えば12本の主筋26の上部をプレキャストコン
クリート部材28内に上下方向に埋設して形成され、梁
14上に設置可能にされている。The precast concrete portion 20 is formed by embedding the upper portions of a plurality of, for example, twelve main reinforcements 26 in a precast concrete member 28 in the vertical direction, and can be installed on the beam 14.
【0039】各主筋26の上端部30は、プレキャスト
コンクリート部材28の上面32から若干突出させた状
態となっており、この突出部分には図示せぬねじが形成
されている。The upper end 30 of each main bar 26 is slightly protruded from the upper surface 32 of the precast concrete member 28, and a screw (not shown) is formed at the protruding portion.
【0040】また、プレキャストコンクリート部材28
内の主筋26には、適宜帯筋33が周囲に掛け回されて
いる。The precast concrete member 28
A band 33 is looped around the main line 26 as needed.
【0041】さらに、プレキャストコンクリート部材2
8の下面34には、コッタ36が形成された状態となっ
ている。Further, the precast concrete member 2
8 is in a state where a cotter 36 is formed on the lower surface 34.
【0042】現場打ちコンクリート打設部22は、プレ
キャストコンクリート部20よりプレキャストコンクリ
ート部20内の主筋26を下方に延出させて形成され、
上方より梁14を貫通して梁14の下方に突出されるよ
うになっている。The cast-in-place concrete casting section 22 is formed by extending the main reinforcement 26 in the precast concrete section 20 downward from the precast concrete section 20.
It penetrates the beam 14 from above and projects below the beam 14.
【0043】また、この現場打ちコンクリート打設部2
2は、現場打ちコンクリートである床用コンクリート4
0(図1参照)の打設によって床42及び梁14と一体
化されるようになっている。この床用コンクリート40
は、プレキャストコンクリート部20のコッタ36に入
り込んでプレキャストコンクリート部20との接合強度
が高められるようになっている。このコッタ36は、図
5に示すように、現場打ちコンクリート打設部22に向
けて外側から内側に傾斜するテーパ部38が形成される
と、床用コンクリート40が隙間なくコッタ36に入り
込んでより一層接合強度が高められることとなる。な
お、床用コンクリート40の打設時には、図1に示すよ
うに、現場打ちコンクリート打設部22の梁14より下
方に突出する主筋26の周囲に適宜帯筋44が掛け回さ
れるようになっている。The cast-in-place concrete placing section 2
2 is cast-in-place concrete for flooring 4
0 (see FIG. 1) is integrated with the floor 42 and the beam 14. This floor concrete 40
Is inserted into the cotter 36 of the precast concrete section 20 to increase the bonding strength with the precast concrete section 20. As shown in FIG. 5, when the taper portion 38 which inclines from the outside to the inside toward the cast-in-place concrete placing portion 22 is formed, as shown in FIG. The joining strength is further increased. At the time of placing the concrete 40 for the floor, as shown in FIG. 1, the stirrup 44 is appropriately wound around the main reinforcement 26 projecting downward from the beam 14 of the cast-in-place concrete 22. ing.
【0044】さらに、この現場打ちコンクリート打設部
22の主筋26の下端部46には、ねじ48が形成され
ている。Further, a screw 48 is formed at the lower end 46 of the main bar 26 of the cast-in-place concrete casting section 22.
【0045】制震装置24は、図4に示すように、一対
の上下ベースプレート52、54と、フランジプレート
56と、低降伏点パネル鋼58と、リブプレート60と
を備えている。As shown in FIG. 4, the vibration damping device 24 includes a pair of upper and lower base plates 52, 54, a flange plate 56, a low yield point panel steel 58, and a rib plate 60.
【0046】上下ベースプレート52、54は、プレキ
ャストコンクリート部20の上面32に相応した大きさ
で、上下に対向して配置されており、この上下ベースプ
レート52、54には、各主筋26と対応した位置に複
数、例えば12個の連結孔62を有している。The upper and lower base plates 52 and 54 have a size corresponding to the upper surface 32 of the precast concrete section 20 and are arranged vertically opposite to each other. Has a plurality of, for example, twelve connection holes 62.
【0047】フランジプレート56は、上下ベースプレ
ート52、54間に、適宜間隔で4枚設けられて、制震
装置24にかかる軸力を支持できるようにされている。
このフランジプレート56は、4枚設けられているが、
設けられる枚数は低降伏点パネル鋼58の厚さや大きさ
によって設定されるもので、制震装置24にかかる軸力
を支持できるよう少なくとも2枚設けられる必要があ
る。Four flange plates 56 are provided at appropriate intervals between the upper and lower base plates 52 and 54 so as to support the axial force applied to the vibration damping device 24.
Although four flange plates 56 are provided,
The number of sheets to be provided is determined by the thickness and size of the low yield point panel steel 58, and it is necessary to provide at least two sheets to support the axial force applied to the vibration damping device 24.
【0048】低降伏点パネル鋼58は、いわゆる極軟鋼
と称されるものを採用しており、上下ベースプレート5
2、54及び各フランジプレート56に囲まれた部分に
3枚取り付けられている。また、この低降伏点パネル鋼
58は、地震時に建築物に層間変形が生じて、せん断力
が加わったときに降伏して入力エネルギーを吸収するよ
うになっている。As the low yield point panel steel 58, what is called extremely mild steel is adopted, and the upper and lower base plates 5 are used.
Three pieces are attached to portions surrounded by 2, 54 and each flange plate 56. The low-yield-point panel steel 58 undergoes interlayer deformation in a building during an earthquake, yields when shearing force is applied, and absorbs input energy.
【0049】リブプレート60は、低降伏点パネル鋼5
8の両面側上下方向ほぼ中央位置で、各フランジプレー
ト56間に取り付けられ、低降伏点パネル鋼58全体に
生じる面外座屈を防止して、低降伏点パネル58がより
良好なエネルギー吸収能力を発揮できるようにしてい
る。The rib plate 60 is made of panel steel 5 having a low yield point.
8 is mounted between the flange plates 56 at substantially the center in the vertical direction on both sides, to prevent the out-of-plane buckling occurring in the entire low yield point panel steel 58, and to provide the low yield point panel 58 with a better energy absorbing capacity. Can be demonstrated.
【0050】そして、この制震装置24が、下ベースプ
レート54の連結孔62に、プレキャストコンクリート
部20の上面32より突出する主筋26の上端部30挿
通してナット50にて締め付けることで、プレキャスト
コンクリート部20上面32に固定される用になってい
る。Then, the vibration damping device 24 is inserted into the connection hole 62 of the lower base plate 54 and the upper end 30 of the main reinforcing bar 26 protruding from the upper surface 32 of the precast concrete portion 20 and tightened by the nut 50, thereby forming the precast concrete. It is intended to be fixed to the upper surface 32 of the part 20.
【0051】また、この制震装置24は、上ベースプレ
ート54の連結孔62に、上方に接続される制震用建築
材料12の現場打ちコンクリート打設部22の主筋26
下端を挿通してナット50にて締め付けることで上方の
制震用建築材料12の主筋26とと連結固定可能にされ
ている。In addition, the vibration control device 24 is provided with a main reinforcement 26 of the cast-in-place concrete placing portion 22 of the building material 12 for vibration control connected upward to the connection hole 62 of the upper base plate 54.
By inserting the lower end and tightening it with a nut 50, it can be connected and fixed to the main reinforcement 26 of the building material 12 for vibration control above.
【0052】次に、この制震用建築材料12を用いた制
震柱10の構築方法について、図6から図9を参照して
説明する。Next, a method of constructing the damping column 10 using the damping building material 12 will be described with reference to FIGS.
【0053】まず、階下の柱を立設して、この柱上に梁
を掛け渡し、梁上に床版を敷設した状態で、図6に示す
ように、階下の梁14を貫通させて階下の制震用建築材
料12を梁14上に設置し、この階下の制震用建築材料
12のプレキャストコンクリート部20及び制震装置2
4を梁14上に突出させた状態で、床版上に床用コンク
リート40を打設して、この床用コンクリート40を階
下の制震用建築材料12の現場打ちコンクリート打設部
22に打設し、階下の制震用建築材料12を階下の梁1
4と一体化させた状態としておく。First, a pillar is set up downstairs, a beam is hung over the pillar, and a floor slab is laid on the beam, and as shown in FIG. Is installed on the beam 14, and the precast concrete part 20 and the vibration control device 2 of the vibration control
4 is projected on the beam 14 and a concrete 40 for floor is cast on the floor slab, and the concrete 40 for floor is poured into the cast-in-place concrete casting section 22 of the building material 12 for vibration control below the floor. The building material 12 for vibration control under the floor is installed and the beam 1 under the floor is installed.
4 and integrated.
【0054】次に、階下の梁14上に、階上の柱を立設
して、この柱上に階上の梁14を掛け渡し、この階上の
梁14上に階上の床版を敷設する(図6参照)。Next, an upstairs pillar is erected on the downstairs beam 14, and the upstairs beam 14 is bridged over this pillar. Lay it (see Fig. 6).
【0055】次いで、図7に示すように、階上の梁14
上から階上の梁14を貫通させて、階上の制震用建築材
料12の現場打ちコンクリート打設部22を階上の梁1
4下方に突出させ、受け筋64を用いて、プレキャスト
コンクリート部20及び制震装置24を階上の梁14に
設置する。Next, as shown in FIG.
The beam 14 on the floor is pierced from the top, and the cast-in-place concrete placing portion 22 of the building material 12 for vibration control on the floor is put on the beam 1 on the floor.
4 Protrude downward, and install the precast concrete portion 20 and the vibration control device 24 on the beam 14 on the floor using the receiving streaks 64.
【0056】この状態で、階上の現場打ちコンクリート
打設部22の主筋26の下端部46を階下の制震用建築
材料12の制震装置24の上ベースプレート52と連結
固定する。In this state, the lower end portion 46 of the main reinforcement 26 of the cast-in-place concrete casting section 22 on the floor is connected and fixed to the upper base plate 52 of the vibration control device 24 of the building material 12 for vibration control below the floor.
【0057】次に、図8に示すように、階上の制震用建
築材料12の階上の梁14より下方に突出する現場打ち
コンクリート打設部22の主筋26の周囲に、帯筋44
を掛け回し、補強を行う。Next, as shown in FIG. 8, around the main reinforcement 26 of the cast-in-place concrete casting part 22 projecting below the upper beam 14 of the building material 12 for vibration control on the floor, a band 44 is provided.
Around to reinforce.
【0058】次いで、図9に示すように、階上の制震用
建築材料12の階上の梁14より下方に突出する現場打
ちコンクリート打設部22の主筋26の周囲にコンクリ
ート型枠66を取り付ける。Next, as shown in FIG. 9, a concrete form 66 is placed around the main reinforcement 26 of the cast-in-place concrete casting portion 22 projecting below the upper beam 14 of the building material 12 for vibration control on the floor. Attach.
【0059】この場合、階上の制震用建築材料12は、
主筋26を介して、階下の制震用建築材料12の制震装
置24によって支持され、しかも、制震装置24は、フ
ランジプレート56によって補強されているので、階下
の制震装置24を支保工として用いることができ、コン
クリート型枠66の支保工設置に要する手間を省略する
ことができる。In this case, the building material 12 for vibration control on the floor is
It is supported by the vibration damping device 24 of the building material 12 for downstairs via the main reinforcement 26, and the damping device 24 is reinforced by the flange plate 56. And the labor required for installing the concrete formwork 66 can be omitted.
【0060】次に、階上の床版上に床用コンクリート4
0を打設し、この床用コンクリート40を、階上の制震
用建築材料12の現場打ちコンクリート打設部22に打
設する。Next, the concrete 4 for the floor is placed on the floor slab on the floor.
0, and the floor concrete 40 is cast into the cast-in-place concrete casting section 22 of the building material 12 for vibration control on the floor.
【0061】この場合、床用コンクリート40は、階上
のプレキャストコンクリート部20の下面34を飲み込
む位置まで打設して、下面34のコッタ36内に入り込
ませて接合強度を高める。この場合、図5に示すよう
に、コッタ36にテーパ部38を形成することで、コン
クリート打設時のプレキャストコンクリート部20の下
面34に空気溜まりが生じて隙間が発生するのを防止で
きる。In this case, the floor concrete 40 is cast to a position where the lower surface 34 of the precast concrete portion 20 on the floor is swallowed, and enters the cotter 36 on the lower surface 34 to increase the bonding strength. In this case, as shown in FIG. 5, by forming the tapered portion 38 on the cotter 36, it is possible to prevent the formation of a gap due to the formation of air pockets on the lower surface 34 of the precast concrete portion 20 during concrete casting.
【0062】次いで、打設した床用コンクリート40が
固化して、階上の制震用建築材料12と階上の梁14及
び床42が一体化した後、コンクリート型枠66を取り
外す。Next, after the cast floor concrete 40 is solidified and the building material 12 for floor control on the floor is integrated with the beam 14 on the floor and the floor 42, the concrete form 66 is removed.
【0063】これによって、階下の制震用建築材料12
と階上の制震用建築材料12とが主筋26を介して一体
化した状態を容易に得ることができる。In this way, the building material 12 for vibration control downstairs can be obtained.
It is possible to easily obtain a state in which the building material for vibration control 12 on the floor is integrated with the building material 12 via the main reinforcement 26.
【0064】そして、この階上の制震用建築材料12上
に、階上の制震用建築材料12と同様の工程により、繰
り返し階上の制震用建築材料12を接続していけば、梁
14を貫通して上下方向に連続する制震柱10を容易に
得ることが可能である。If the building material 12 for the upper floor is repeatedly connected to the building material 12 for the upper floor by the same process as that of the building material 12 for the upper floor, It is possible to easily obtain the damping column 10 that penetrates the beam 14 and is continuous in the vertical direction.
【0065】図10には、他の実施の形態にかかる制震
柱を示す。FIG. 10 shows a damping column according to another embodiment.
【0066】この制震柱70は、前記実施の形態におけ
る階下の梁14を貫通させて一体形成した階下の制震用
建築材料12と、階上の梁14を貫通させて一体形成し
た階上の制震用建築材料12との間に、中間制震用建築
材料72を設けるようにしている。The damping column 70 is composed of a building material 12 for damping downstairs integrally formed by penetrating the beam 14 downstairs in the above embodiment, and an upstairs integrally formed by penetrating the beam 14 upstairs. An intermediate vibration control building material 72 is provided between the vibration control material 12 and the vibration control building material 12.
【0067】この中間制震用建築材料72は、中間制震
装置74と、この中間制震装置74よりも剛性の高い支
持部材76とが予め一体的に固定された状態となってい
る。The building material 72 for intermediate vibration damping is in a state in which an intermediate vibration damping device 74 and a support member 76 having a higher rigidity than the intermediate vibration damping device 74 are integrally fixed in advance.
【0068】中間制震装置74は、制震装置24と同様
に、上下ベースプレート52、54と、フランジプレー
ト56と、低降伏点パネル鋼58と、リブプレート60
とから構成されている。Similarly to the vibration control device 24, the intermediate vibration control device 74 includes upper and lower base plates 52 and 54, a flange plate 56, a low yield point panel steel 58, and a rib plate 60.
It is composed of
【0069】支持部材76は、プレキャストコンクリー
ト製のもので、内部に少なくとも主筋を埋設してあり、
その主筋の上下端部を突出させ、この主筋の上端部を中
間制震装置74の下ベースプレート54と連結固定して
いる。The support member 76 is made of precast concrete, and has at least main reinforcement embedded therein.
The upper and lower ends of the main bars are projected, and the upper ends of the main bars are connected and fixed to the lower base plate 54 of the intermediate vibration control device 74.
【0070】そして、支持部材76の主筋の下端部を階
下の制震用建築材料12の制震装置24の上ベースプレ
ート52と連結固定し、中間制震装置74の上ベースプ
レート52を階上の制震用建築材料12の現場打ちコン
クリート打設部22の主筋下端部と連結固定している。Then, the lower end of the main reinforcement of the support member 76 is connected and fixed to the upper base plate 52 of the vibration control device 24 of the building material 12 for vibration control under the floor, and the upper base plate 52 of the intermediate vibration control device 74 is controlled to the upper floor. It is connected and fixed to the lower end of the main reinforcing bar of the cast-in-place concrete placing section 22 of the building material 12 for earthquake.
【0071】この制震柱70を構築するに際しては、階
下の制震用建築材料12を階下の梁14と一体化させた
後、階下の制震用建築材料12の制震装置24上に中間
制震用建築材料72の支持部材76を載置し、支持部材
76と制震装置24の上ベースプレート52とを連結固
定する。In constructing the vibration control column 70, the building material 12 for the vibration control below the floor is integrated with the beam 14 below the floor, and then the intermediate material is placed on the vibration control device 24 of the building material 12 for the vibration below the floor. The support member 76 of the building material 72 for vibration control is placed, and the support member 76 and the upper base plate 52 of the vibration control device 24 are connected and fixed.
【0072】次いで、階上の柱及び梁14を組み立てて
床版を敷設した状態で、階上の制震用建築材料12の現
場打ちコンクリート打設部22を、梁14を貫通させ
て、その下端部を中間制震用建築材料72の中間制震装
置74上に載置した後、現場打ちコンクリート打設部2
2の主筋の下端部と中間制震装置74の上ベースプレー
ト52とを連結固定する。Next, in a state where the columns and beams 14 on the floor are assembled and the floor slab is laid, the cast-in-place concrete placing portion 22 of the building material 12 for vibration control on the floor is passed through the beams 14, and After placing the lower end on the intermediate vibration control device 74 of the building material 72 for intermediate vibration control, the cast-in-place concrete placement unit 2
The lower end of the main bar 2 and the upper base plate 52 of the intermediate vibration control device 74 are connected and fixed.
【0073】そして、この状態で、階上の制震用建築材
料12の現場打ちコンクリート打設部22にコンクリー
ト型枠を取り付け、内部にコンクリートを打設すればよ
い。Then, in this state, a concrete formwork may be attached to the cast-in-place concrete placing portion 22 of the building material 12 for vibration control on the floor, and concrete may be poured inside.
【0074】このようにすることで、階上及び階下の制
震用建築材料12と、中間制震用建築材料72とを主筋
が連続した状態の制震柱70を容易に得ることができ
る。In this way, it is possible to easily obtain the damping column 70 in which the main reinforcement of the building material 12 for damping above and below the floor and the building material 72 for intermediate damping are continuous.
【0075】また、このように、制震装置24と、中間
制震装置74の2箇所で、エネルギーを吸収させること
により、各制震装置24、中間制震装置74のエネルギ
ー吸収量を半減させて、損傷を少なくすることができ
る。As described above, by absorbing energy at the two locations of the vibration damping device 24 and the intermediate vibration damping device 74, the energy absorption of each vibration damping device 24 and the intermediate vibration damping device 74 is reduced by half. Damage can be reduced.
【0076】さらに、この中間制震用建築材料72を用
いることで、階高の建築物にも容易に対処することが可
能となる。Further, by using the building material 72 for intermediate vibration control, it is possible to easily cope with a building having a floor height.
【0077】本発明は、前記各実施の形態に限られるも
のではなく、本発明の要旨の範囲内において種々の形態
に変形可能である。The present invention is not limited to the above embodiments, but can be modified into various forms within the scope of the present invention.
【0078】例えば、前記各実施の形態においては、制
震構造として、制震柱を示したが、この例に限らず、制
震壁を構築する場合にも適用できるものである。For example, in each of the above-described embodiments, a damping column is shown as the damping structure. However, the present invention is not limited to this example, and can be applied to a case where a damping wall is constructed.
【0079】また、建築物の強度部材として梁を示した
が、梁に限定されるものではなく、建築物の強度をにな
う部材であれば種々適用できる。Although the beam is shown as the strength member of the building, the invention is not limited to the beam, and various members can be applied as long as the member has strength of the building.
【0080】さらに、制震装置及び中間制震装置は、3
枚の低降伏点パネル鋼を用いているが、この使用枚数や
大きさは自由に設定することができるものである。Further, the vibration control device and the intermediate vibration control device are:
Although the number of low yield point panel steels is used, the number and size of the sheets used can be freely set.
【0081】また、中間制震用建築材料の支持部材とし
て、プレキャストコンクリートを示したが、これに限ら
ず、例えば鉄骨を用いることも可能である。Although the precast concrete is shown as a support member of the building material for intermediate vibration control, it is not limited to this, and for example, a steel frame can be used.
【0082】[0082]
【図1】本発明の一実施の形態にかかる制震柱を示す断
面図である。FIG. 1 is a cross-sectional view illustrating a damping column according to an embodiment of the present invention.
【図2】図1の制震柱を構築するための制震用建築材料
を示す断面図である。FIG. 2 is a sectional view showing a building material for vibration control for constructing the vibration control column of FIG. 1;
【図3】図2の制震用建築材料を、階上及び階下で連結
固定した状態を示す斜視図である。FIG. 3 is a perspective view showing a state in which the building material for vibration damping of FIG. 2 is connected and fixed above and below the floor.
【図4】制震用建築材料の制震装置の斜視図である。FIG. 4 is a perspective view of a vibration control device of a building material for vibration control.
【図5】プレキャストコンクリート部のコッタの状態を
示す部分断面図である。FIG. 5 is a partial sectional view showing a state of a cotter in a precast concrete part.
【図6】階下の制震用建築材料を固定した状態を示す断
面図である。FIG. 6 is a cross-sectional view showing a state in which a building material for vibration control below the floor is fixed.
【図7】階上の制震用建築材料の現場打ちコンクリート
打設部と階下の制震用建築材料の制震装置を連結固定し
た状態を示す断面図である。FIG. 7 is a cross-sectional view showing a state in which a cast-in-place concrete damping section for building materials for vibration control on the floor is connected and fixed to a vibration control device for building materials for vibration control on the floor below.
【図8】階上の現場打ちコンクリート打設部の主筋に帯
筋を取り付けた状態を示す断面図である。FIG. 8 is a cross-sectional view showing a state where a reinforcing bar is attached to a main reinforcing bar of a cast-in-place concrete placing part on the floor.
【図9】階上の現場打ちコンクリート打設部周囲にコン
クリート型枠を取り付けてコンクリートを打設する状態
を示す断面図である。FIG. 9 is a cross-sectional view showing a state in which a concrete formwork is attached around a cast-in-place concrete pouring portion on the floor and concrete is poured.
【図10】本発明の他の実施の形態に係る制震柱を示す
断面図である。FIG. 10 is a cross-sectional view illustrating a damping column according to another embodiment of the present invention.
10、70 制震柱 12 制震用建築材料 14 強度部材としての梁 20 プレキャストコンクリート部 22 現場打ちコンクリート打設部 24 制震装置 26 主筋 30 主筋の上端部 36 コッタ 38 テーパ部 40 現場打ちコンクリートとしての床用コンクリート 46 主筋の下端部 52 上ベースプレート 54 下ベースプレート 56 フランジプレート 58 低降伏点パネル鋼 60 リブプレート 66 コンクリート型枠 72 中間制震用建築材料 74 中間制震装置 76 支持部材 10, 70 Vibration control column 12 Building material for vibration control 14 Beam as strength member 20 Precast concrete part 22 Cast-in-place concrete placement part 24 Vibration control device 26 Main reinforcement 30 Upper end of main reinforcement 36 Cotta 38 Taper part 40 As cast-in-place concrete Concrete for floor 46 Lower end of main bar 52 Upper base plate 54 Lower base plate 56 Flange plate 58 Low yield point panel steel 60 Rib plate 66 Concrete formwork 72 Intermediate vibration control building material 74 Intermediate vibration control device 76 Support member
───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E04B 1/16 E04C 3/34 E04H 9/02 301 ──────────────────────────────────────────────────続 き Continued on the front page (58) Fields surveyed (Int. Cl. 7 , DB name) E04B 1/16 E04C 3/34 E04H 9/02 301
Claims (10)
複数接続される制震用建築材料であって、 少なくとも複数の主筋を埋設して形成され前記建築物の
強度部材上に設置可能にされたプレキャストコンクリー
ト部と、 前記プレキャストコンクリート部より前記主筋を延出さ
せて前記建築物の強度部材を貫通して前記強度部材下方
に突出されると共に、現場打ちコンクリートの打設によ
り前記強度部材と一体化される現場打ちコンクリート打
設部と、 一方で前記プレキャストコンクリート部の前記現場打ち
コンクリート打設部と反対側で前記プレキャストコンク
リート部の主筋に固定され、他方で上方に接続される制
震用建築材料の現場打ちコンクリート打設部先端の前記
主筋と連結固定可能にされる制震装置とを備えることを
特徴とする制震用建築材料。1. A building material for seismic control connected to a plurality of members in a vertical direction through a strength member of a building, wherein the building material is formed by burying at least a plurality of main reinforcing bars and can be installed on the strength member of the building. A precast concrete part, and the main reinforcement extends from the precast concrete part, penetrates through the strength member of the building, and projects below the strength member. A cast-in-place concrete casting portion integrated with the main body of the precast concrete portion on the other side of the precast concrete portion on the side opposite to the cast-in-place concrete casting portion, and on the other hand connected upward. And a seismic damping device that can be connected and fixed to the main bar at the tip of the cast-in-place concrete casting part of building materials. Building materials for earthquakes.
筋または前記現場打ちコンクリート打設部の主筋と固定
される対向する一対のベースプレートと、 前記一対のベースプレートとの間に取り付けられた少な
くとも2つのフランジプレートと、 前記ベースプレートと前記フランジプレートとに囲まれ
る部分に取り付けられた低降伏点パネル鋼とを備えるこ
とを特徴とする制震用建築材料。2. The vibration control device according to claim 1, wherein the vibration control device comprises: a pair of opposed base plates fixed to a main reinforcement of the precast concrete portion or a main reinforcement of the cast-in-place concrete placing portion; A building material for seismic control, comprising: at least two flange plates attached to the base plate; and a low yield point panel steel attached to a portion surrounded by the base plate and the flange plate.
られることを特徴とする制震用建築材料。3. The building material for vibration damping according to claim 2, wherein a rib plate is attached between the flange plates.
リート打設部側に位置する面には、前記現場打ちコンク
リート打設部への打設コンクリートとの接合度を高める
コッタが形成されていることを特徴とする制震用建築材
料。4. The method according to claim 1, wherein a surface of the precast concrete portion located on the side of the cast-in-place concrete placing portion is joined to the cast-in-place concrete in the cast-in-place concrete placing portion. A building material for seismic control characterized by forming a cotter to increase the degree.
て外側から内側に傾斜するテーパ部を有することを特徴
とする制震用建築材料。5. The building material for seismic control according to claim 4, wherein the cotter has a tapered portion inclined from outside to inside toward the cast-in-place concrete placing portion.
建築材料を用いて構築される制震構造であって、 現場打ちコンクリート打設部へのコンクリート打設にて
階下の強度部材に一体化され、かつ、プレキャストコン
クリート部及びこのプレキャストコンクリート部の主筋
に固定された制震装置を上方に突出させた階下の制震用
建築材料と、 階上の強度部材を貫通して現場打ちコンクリート打設部
下端の主筋が前記階下の制震用建築材料の制震装置と連
結固定され、かつ、現場打ちコンクリート打設部へのコ
ンクリート打設にて階上の強度部材に一体化された階上
の制震用建築材料と、 を備えることを特徴とする制震構造。6. A vibration damping structure constructed using the building material for vibration damping according to any one of claims 1 to 5, wherein the concrete is cast into a cast-in-place concrete pouring part, and the strength of the downstairs is obtained. The building material for seismic control below downstairs, in which the precast concrete part and the seismic control device fixed to the main reinforcement of this precast concrete part protrude upward, The main reinforcement at the lower end of the cast-in-place concrete casting section is fixedly connected to the vibration control device of the building material for vibration control below the floor, and is integrated with the strength member on the floor by casting concrete into the cast-in-place concrete placement section. And a building material for vibration control on the upper floor.
との間に、中間制震用建築材料が設けられ、 前記中間制震用建築材料は、中間制震装置と、この中間
制震装置よりも剛性の高い支持部材とが予め一体的に固
定され、前記支持部材が前記階下の制震用建築材料の制
震装置と連結固定されると共に、前記中間制震装置が前
記階上の制震用建築材料を構成する現場打ちコンクリー
ト打設部の主筋と連結固定されることを特徴とする制震
構造。7. The building material for intermediate damping according to claim 6, wherein a building material for intermediate damping is provided between the building material for damping below the floor and the building material for damping above the floor. The intermediate vibration damping device and a supporting member having higher rigidity than the intermediate vibration damping device are integrally fixed in advance, and the supporting member is connected and fixed to the vibration damping device of the building material for vibration damping downstairs. A vibration control structure, wherein the intermediate vibration control device is connected and fixed to a main reinforcement of a cast-in-place concrete casting section constituting the building material for vibration control on the floor.
建築材料を用いて構築される制震構造の構築方法であっ
て、 階下の強度部材を貫通させて階下の制震用建築材料を設
置し、この階下の制震用建築材料のプレキャストコンク
リート部及び制震装置を前記強度部材上に突出させた状
態で、現場打ちコンクリート打設部にコンクリートを打
設して階下の制震用建築材料を前記階下の強度部材と一
体化させる工程と、 階上の強度部材上から前記階上の強度部材を貫通させて
階上の制震用建築材料の現場打ちコンクリート打設部を
前記階上の強度部材下方に突出させ、前記階上の現場打
ちコンクリート打設部の主筋下端を前記階下の制震用建
築材料の制震装置と連結固定する工程と、 前記階上の制震用建築材料の前記階上の強度部材下面よ
り突出する現場打ちコンクリート打設部の周囲にコンク
リート型枠を取り付ける工程と、 前記階上の強度部材上から前記階上の制震用建築材料の
現場打ちコンクリート打設部にコンクリートを打設する
工程と、 前記打設したコンクリートが固化して階上の制震用建築
材料と前記階上の強度部材とが一体化した後、前記コン
クリート型枠を取り外す工程と、 を含むことを特徴とする制震構造の構築方法。8. A method for constructing a vibration control structure constructed using the building material for vibration control according to claim 1, wherein the structural member is used for vibration control in a lower floor. The building material is installed, and the precast concrete section of the building material for vibration control under the floor and the vibration control device are protruded above the strength member, and concrete is poured into the cast-in-place concrete casting section to control the floor below. A step of integrating the seismic building material with the strength member on the lower floor, and forming a cast-in-place concrete casting part of the building material for seismic control on the floor by penetrating the strength member on the floor from above the strength member on the floor. Protruding below the strength member on the floor, connecting and fixing the lower end of the main reinforcement of the cast-in-place concrete placing portion on the floor with the vibration control device of the building material for vibration control on the floor, From the lower surface of the strength member on the floor of the building material Attaching a concrete formwork around the cast-in-place concrete casting section to be cast; and casting concrete from the strength member on the floor to the cast-in-place concrete casting section of the building material for vibration control on the floor. Removing the concrete formwork after the cast concrete is solidified and the building material for vibration control on the floor is integrated with the strength member on the floor. How to build the structure.
た梁が用いられ、 前記コンクリートの打設工程では、前記梁上に敷設され
た床版上に床用コンクリートを打設する際に、その床用
コンクリートを前記現場打ちコンクリート打設部に打設
することを特徴とする制震構造の構築方法。9. The floor according to claim 8, wherein a beam laid on a pillar is used as the strength member on the lower floor and the upper floor, and in the concrete placing step, a floor slab laid on the beam is used. A method for constructing a vibration control structure, comprising: when placing concrete for flooring, placing the concrete for flooring into the cast-in-place concrete placing portion.
置と、この中間制震装置よりも剛性の高い支持部材とが
予め一体的に固定された中間制震用建築材料の前記支持
部材を連結固定した後、前記中間制震装置に前記階上の
制震用建築材料を構成する現場打ちコンクリート打設部
の主筋と連結固定する工程を含むことを特徴とする制震
構造の構築方法。10. The vibration control device according to claim 8, wherein an intermediate vibration control device and a support member having higher rigidity than the intermediate vibration control device are integrally fixed on the vibration control device of the building material for vibration control under the floor. After connecting and fixing the supporting member of the building material for intermediate vibration damping, and connecting and fixing the intermediate vibration damping device to the main reinforcement of the cast-in-place concrete placing section constituting the building material for vibration damping on the floor. A method of constructing a vibration control structure characterized by including:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9361755A JP3004242B2 (en) | 1997-12-10 | 1997-12-10 | Building material for vibration control, vibration control structure and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9361755A JP3004242B2 (en) | 1997-12-10 | 1997-12-10 | Building material for vibration control, vibration control structure and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11172759A JPH11172759A (en) | 1999-06-29 |
JP3004242B2 true JP3004242B2 (en) | 2000-01-31 |
Family
ID=18474761
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9361755A Expired - Fee Related JP3004242B2 (en) | 1997-12-10 | 1997-12-10 | Building material for vibration control, vibration control structure and construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3004242B2 (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001329715A (en) * | 2000-05-24 | 2001-11-30 | Taisei Corp | Method of constructing base-isolated structure |
KR100623676B1 (en) | 2004-08-18 | 2006-09-19 | 삼성물산 주식회사 | A pc members for multi-layer soft frame and construction method of join part in building make using its |
JP5207078B2 (en) * | 2009-08-17 | 2013-06-12 | 清水建設株式会社 | Construction method for seismic control columns |
KR101968598B1 (en) * | 2018-08-28 | 2019-04-15 | 주식회사 에이이 | Seismic Retrofitting Structure of Reinforced Concrete Column Using Reinforcing Plate and Wire Cable |
CN112942682B (en) * | 2021-01-27 | 2022-06-14 | 上海绿地建设(集团)有限公司 | Multicavity steel core concrete column |
-
1997
- 1997-12-10 JP JP9361755A patent/JP3004242B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH11172759A (en) | 1999-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100742577B1 (en) | Composite structural framing system | |
JP2522714B2 (en) | Construction method of building frame | |
JP3004242B2 (en) | Building material for vibration control, vibration control structure and construction method | |
JP3384785B2 (en) | Construction method of damping wall | |
JP2000226952A (en) | Attaching structure of hysteresis damping member in concrete building frame structure, attaching method and vibration control concrete building frame structure | |
JP2002357009A (en) | Vibration-control beam and method for building it | |
JPH1181737A (en) | Vibration control construction for reinforced concrete building and constructing method therefor | |
JP3418681B2 (en) | Installation method of ultra mild steel panel damper in precast RC building structure | |
JPH10252187A (en) | Earthquake resistant construction of building structure and construction method thereof | |
JP4660810B2 (en) | Boundary beam damper | |
JP3233260B2 (en) | Anchoring structure of anchor material on steel column base | |
JP3608130B2 (en) | Out-of-plane fall prevention structure for expanded seismic walls | |
JP2600961B2 (en) | Connection structure between reinforced concrete columns and steel beams | |
JP3306226B2 (en) | Attached column base structure of multi-story shear wall | |
JP3043938B2 (en) | Joint structure between reinforced concrete columns and steel beams | |
JP3760609B2 (en) | Leg anchorage of steel columns | |
JP2620118B2 (en) | Net formwork method for walls and floors | |
JP3020021B2 (en) | Building seismic retrofitting method | |
JPH06299718A (en) | Construction of wall, floor in atomic power plant and wall slab thereof | |
JP3830062B2 (en) | Seismic reinforcement method for reinforced concrete buildings | |
JP3245824B2 (en) | Column and beam joint structure of RC structure and its construction method | |
JP3888988B2 (en) | Construction method of vibration control pillar | |
JPH1121984A (en) | Reinforced box culvert | |
JP2540314B2 (en) | Steel rebar concrete columns and beams | |
JPH10159350A (en) | Reinforcement wall for existing building, and its constructing method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19991102 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081119 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091119 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091119 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101119 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131119 Year of fee payment: 14 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |