JPH07270578A - Acceptance inspection method for new fuel - Google Patents

Acceptance inspection method for new fuel

Info

Publication number
JPH07270578A
JPH07270578A JP6087753A JP8775394A JPH07270578A JP H07270578 A JPH07270578 A JP H07270578A JP 6087753 A JP6087753 A JP 6087753A JP 8775394 A JP8775394 A JP 8775394A JP H07270578 A JPH07270578 A JP H07270578A
Authority
JP
Japan
Prior art keywords
fuel
container
inspection
new fuel
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6087753A
Other languages
Japanese (ja)
Other versions
JP2736735B2 (en
Inventor
Shingo Koike
伸吾 小池
Yoshimasa Sakai
義政 坂井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nuclear Fuel Industries Ltd
Original Assignee
Nuclear Fuel Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nuclear Fuel Industries Ltd filed Critical Nuclear Fuel Industries Ltd
Priority to JP6087753A priority Critical patent/JP2736735B2/en
Publication of JPH07270578A publication Critical patent/JPH07270578A/en
Application granted granted Critical
Publication of JP2736735B2 publication Critical patent/JP2736735B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Monitoring And Testing Of Nuclear Reactors (AREA)

Abstract

PURPOSE:To enhance the work efficiency while ensuring the safety by transferring a fuel container from a temporary stock yard to a detecting position using a truck equipped with a suspension gantry crane and then standing the fuel rods on an inspection table integrally with each truck. CONSTITUTION:A fuel container carried by means of a carrying work tool is mounted on a truck 41 in front of a container stand 18 and secured in place. It is then hoisted by means of a jib crane 42 fixed to the upper stage of the container stand 18. Subsequently, the fuel container is raised by rolling the wheels 43 of the truck upward along the rail 44 of the container stand 18 and the fuel container is secured before a suspender 17 is removed. Finally, a new fuel O is then hoisted by means an overhead crane and fixed to an inspection table. Dedicated work tools are employed, respectively, in the process for transferring the fuel container from a temporary stock yard to an inspecting position and in the process for standing the new fuel 0 on the container stand 18. Consequently, the work is carried out without operating the overhead crane after transfer of the fuel container before fixing thereof to the container stand 18.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、例えば沸騰水型原子力
発電所に搬入された新燃料の原子炉に装荷する前に行わ
れる輸送時の損傷の有無を確認するための外観,寸法等
の検査である所謂「新燃料搬入検査作業方法」の工夫に
関するものである。
BACKGROUND OF THE INVENTION The present invention relates to the appearance, dimensions, etc. for confirming the presence or absence of damage during transportation, for example, before loading a new fuel introduced into a boiling water nuclear power plant into a nuclear reactor. The present invention relates to a so-called "new fuel carry-in inspection work method" which is an inspection.

【0002】[0002]

【従来の技術】図5は搬送状態の新燃料を内部に収容す
る搬送容器の搬入作業を説明する説明図である。沸騰水
型原子力発電所に搬入される新燃料は、輸送容器(1) に
収納されて原子炉発電所まで輸送される。この輸送容器
(1) は、チャンネルボックスを被覆していない新燃料を
2体密閉収納する燃料容器(5) と、この燃料容器(5) を
梱包して保護する保護容器(4) とからなる。
2. Description of the Related Art FIG. 5 is an explanatory view for explaining a loading operation of a transport container for containing fresh fuel in a transport state. The new fuel carried into the boiling water nuclear power plant is stored in the transport container (1) and transported to the reactor power plant. This shipping container
(1) consists of a fuel container (5) for sealingly accommodating two new fuels that do not cover the channel box, and a protective container (4) for packing and protecting the fuel container (5).

【0003】図5に示す通り、輸送容器(1) を積んだ輸
送車(2) が原子力発電所に到着後、クレーン車(3) によ
って発電所構内の指定された場所に降ろされる。そこで
保護容器(4) を開梱され、内部の燃料容器(5) が取出さ
れて専用トラック(6) に載せられて、原子炉建屋(7) の
大物搬入口(8) より搬入される。
As shown in FIG. 5, after a transport vehicle (2) loaded with a transport container (1) arrives at a nuclear power plant, it is unloaded at a designated place on the premises of a power plant by a crane vehicle (3). Therefore, the protective container (4) is unpacked, the internal fuel container (5) is taken out, placed on a dedicated truck (6), and carried in from the large-sized cargo inlet (8) of the reactor building (7).

【0004】原子炉建屋内に搬入後、燃料容器(5) は4
個積みの燃料容器吊上用治具(9) と原子炉建屋内の天井
クレーン(10)とで吊下げられ、最上階の指定された仮置
き場所(11)に仮置きされる。即ち、燃料容器(5) は、平
行に渡された一対の枕木(12)に直交するように並べら
れ、その上に更に一対の枕木(12)を平行に渡し、更に燃
料容器(5) を載せるように仮置きされる。
After loading into the reactor building, the fuel container (5)
It is hung by a jig (9) for lifting individual fuel containers and an overhead crane (10) in the reactor building, and temporarily placed in a designated temporary storage location (11) on the top floor. That is, the fuel container (5) is arranged so as to be orthogonal to the pair of sleepers (12) passed in parallel, and the pair of sleepers (12) is further passed in parallel on the fuel container (5). It is temporarily placed so that it can be placed.

【0005】図6は燃料容器の開梱の手順を示す説明図
であり、a図〜d図は個々の手順を示す説明図である。
図7は新燃料の保管作業を示す説明図であり、e図〜g
図は個々の手順を示す説明図である。
FIG. 6 is an explanatory diagram showing a procedure for unpacking a fuel container, and FIGS. 6A to 6D are explanatory diagrams showing individual procedures.
FIG. 7 is an explanatory view showing the storage operation of the new fuel, and is shown in FIGS.
The figure is an explanatory view showing the individual steps.

【0006】図6のa図に示す通り、仮置き場所(11)に
仮置きされた燃料容器(5) は天井クレーン(10)のフック
(13)で横倒状態で吊下げられて燃料容器開梱場所(14)ま
で移送される。次に、燃料容器(5) の上蓋(15)と頭蓋(1
6)とを天井クレーン(10)を用いて取外して開梱が行われ
る。即ち、燃料容器(5) の頭蓋(16)をずらして外し、更
に上蓋(15)の両側面にフック(13)を介して天井クレーン
(10)と繋げ、天井クレーン(10)を引上げて取外す。
As shown in FIG. 6a, the fuel container (5) temporarily placed in the temporary placement location (11) is the hook of the overhead crane (10).
It is hung sideways at (13) and transferred to the fuel container unpacking location (14). Next, cover the top (15) and skull (1) of the fuel container (5).
6) and are removed using the overhead crane (10) and unpacking is performed. That is, the skull (16) of the fuel container (5) is displaced and removed, and the overhead crane is attached to both sides of the upper lid (15) via the hooks (13).
Connect to (10) and pull up the overhead crane (10) to remove.

【0007】次に、図6のb図に示されるように、開梱
された燃料容器(5) は、該容器(5)の両側部に設けられ
た2つの吊環に竪吊り治具(17)を取付け、天井クレーン
(10)を引上げて竪吊りして、図6のc図に示す通り、コ
ンテナスタンド(18)に燃料容器(5) を立て掛けた状態で
取付ける。燃料容器(5) 取付け後、新燃料(0) を吊下
げ、燃料容器(5) より取出して、d図に示されるように
新燃料(0) の上部の把手(20)をフック(13)を介して吊下
げながら検査台(19)に取付ける。
Next, as shown in FIG. 6 (b), the unpacked fuel container (5) is mounted on a vertical hanging jig (17) on two hanging rings provided on both sides of the container (5). ) Is installed and the overhead crane
(10) is pulled up and vertically suspended, and the fuel container (5) is attached to the container stand (18) while leaning against it, as shown in FIG. After installing the fuel container (5), suspend the new fuel (0), take it out from the fuel container (5), and hook the handle (20) on the upper part of the new fuel (0) into the hook (13) as shown in Fig. D. Attach it to the inspection table (19) while suspending it via.

【0008】この検査台(19)に取付けた後、新燃料(0)
の取出し、新燃料(0) の検査の順で作業が行なわれる。
検査台(19)に取付けられた新燃料(0) は外観,寸法検査
等の検査が行わる。
After mounting on this inspection table (19), fresh fuel (0)
The work is done in the order of taking out the fuel and inspecting the new fuel (0).
The new fuel (0) mounted on the inspection table (19) is inspected for appearance and dimensions.

【0009】検査終了後、検査台に取り付けられている
手巻きウィンチ(図示せず)によって、図7のe図に示
したように、チャンネルボックス(21)が装着される。更
に、f図に示すように、チャンネルボックス付き新燃料
(0a)を天井クレーン(10)で吊下げて移送し、g図に示す
ように、使用済燃料貯蔵プール(22)の燃料収納機(23)に
取付け、プール(22)に保管する。尚、チャンネルボック
ス付き新燃料(0a)を使用済燃料貯蔵プール(22)内に保管
しない場合は、新燃料貯蔵ラック(図示せず)に収納す
る。
After the inspection is completed, a channel box (21) is mounted by a manual winch (not shown) attached to the inspection table, as shown in FIG. Furthermore, as shown in Fig. F, new fuel with channel box
(0a) is hung by an overhead crane (10) and transferred, and is attached to the fuel storage unit (23) of the spent fuel storage pool (22) and stored in the pool (22) as shown in FIG. When the new fuel with channel box (0a) is not stored in the spent fuel storage pool (22), it is stored in a new fuel storage rack (not shown).

【0010】最後に空の燃料容器(5) を天井クレーン(1
0)で吊下げ、蓋を付けて、もとの仮置き場(11)の指定場
所へ置く。
Finally, empty the fuel container (5) with the overhead crane (1
Suspend at 0), attach the lid, and place it in the designated place of the original temporary storage area (11).

【0011】以上の作業を新燃料搬入検査作業と称す
る。図8はこの従来の新燃料搬入検査作業のタイムスケ
ジュールを示す説明図である。図において、各工程の黒
塗四角は天井クレーンの動作を示し、斜線四角は、燃料
検査台に取り付けられている手巻きウィンチの動作を示
す。また、各々の四角の幅はその作業に係る時間(分)
を示す。
The above work is called a new fuel carry-in inspection work. FIG. 8 is an explanatory view showing a time schedule of the conventional new fuel carry-in inspection work. In the figure, the black squares in each process show the operation of the overhead crane, and the shaded squares show the operation of the manual winch attached to the fuel inspection table. The width of each square is the time (minutes) related to the work.
Indicates.

【0012】図に示す通り、天井クレーン(10)は休みな
く、(a) 燃料容器移動、(b) 燃料容器開梱、(c) 燃料容
器竪吊り移動、(d) 燃料容器スタンド取付、(e) 新燃料
移動、(f) 新燃料検査、(g) チャンネルボックス装着、
(h) チャンネルボックス(C/B) 付き新燃料移動、(i) 空
燃料容器竪吊り移動、(j) 空燃料蓋取付移動の工程をほ
ぼ連続運転している。
As shown in the figure, the overhead crane (10) does not rest, (a) fuel container movement, (b) fuel container unpacking, (c) fuel container vertical suspension movement, (d) fuel container stand attachment, ( e) New fuel transfer, (f) New fuel inspection, (g) Channel box installation,
The processes of (h) moving new fuel with channel box (C / B), (i) vertically moving empty fuel container, and (j) moving empty fuel lid are operating almost continuously.

【0013】[0013]

【発明が解決しようとする課題】以上のように、クレー
ン運転者は緊張の連続でかなりの疲労となる。万一誤操
作等によりトラブルが生じると社会的影響が大きい。一
方、最近では原子炉建屋内での他の点検作業等も増加
し、新燃料搬入検査作業に要する工期も充分確保できず
短縮化傾向にある。一方、放射線取扱い作業に従事する
作業員の作業時間は1日最大10時間の規制がある。
As described above, the crane operator is considerably tired due to continuous tension. Should trouble occur due to incorrect operation, social impact will be great. On the other hand, recently, other inspection work etc. inside the reactor building has increased, and the construction period required for the new fuel loading inspection work cannot be sufficiently secured, and it tends to be shortened. On the other hand, the working hours of workers engaged in radiation handling work are regulated to a maximum of 10 hours per day.

【0014】このような制約の中で1日当たりの新燃料
検査数量を増加させるためには、天井クレーン(10)のス
ピードをアップさせるものも一案ではあるが、先に述べ
た通り、安全作業確保の観点から好ましいことではな
い。各原子力発電所の仕様が異なるため、1日当たりの
新燃料検査数量は一定ではないが、現状では16体/日
から24体/日程度である。
In order to increase the number of new fuel inspections per day under such restrictions, it is possible to increase the speed of the overhead crane (10), but as mentioned above, safety work is required. It is not preferable from the viewpoint of securing. The number of new fuel inspections per day is not constant because the specifications of each nuclear power plant are different, but currently it is about 16 to 24 units / day.

【0015】この間、天井クレーン(10)は休みなく連続
運転となり、クレーン運転者は緊張の連続でかなりの疲
労となる。何故なら、万一誤操作等によりトラブルが生
じた場合には社会的影響が大きいためである。また、最
近では原子炉建屋内での他の点検作業等も増加し、新燃
料搬入検査作業に要する工期も充分に取れず、短縮化傾
向にある。
During this time, the overhead crane 10 is continuously operated without any breaks, and the crane operator is tired due to continuous tension. This is because if a trouble should occur due to an erroneous operation, the social impact will be great. Further, recently, other inspection work and the like inside the reactor building has increased, and the construction period required for the new fuel carry-in inspection work cannot be sufficiently taken, and it tends to be shortened.

【0016】本発明は、このような状況下で、新燃料搬
入検査作業の安全作業を確保し、尚且作業の効率化を達
成するための新燃料搬入検査作業方法を得ることを目的
とする。
Under such circumstances, it is an object of the present invention to obtain a new fuel carry-in inspection work method for ensuring the safety work of the new fuel carry-in inspection work and achieving the efficiency of the work.

【0017】[0017]

【課題を解決するための手段】本請求項1に記載の発明
に係る新燃料搬入検査作業方法では、原子炉建屋内の仮
置き場所に積まれた新燃料入り燃料容器を同じく原子炉
建屋内の検査場所まで搬送し、前記燃料容器から内部の
新燃料を取出して検査台に立設状態で装着し、前記新燃
料の検査を行うと共に該新燃料にチャンネルボックスを
装着する新燃料搬入検査作業方法において、前記仮置き
場所に積まれた燃料容器の前記検査場所までの搬送を、
前記新燃料入り燃料容器を吊持する門型クレーン付きの
台車で行い、前記検査場所で取出した新燃料を別の台車
に移し替え、前記検査台への前記新燃料の立設装着を前
記別の台車ごと行うものである。
In the new fuel carry-in inspection work method according to the invention described in claim 1, a fuel container containing new fuel loaded in a temporary storage location in the reactor building is also used in the reactor building. New fuel carry-in inspection work of transporting the new fuel from the fuel container to the inspection stand, mounting it on the inspection stand in an upright state, inspecting the new fuel, and mounting a channel box on the new fuel. In the method, the transportation of the fuel container loaded in the temporary storage location to the inspection location,
Carrying on a trolley-equipped trolley that suspends the fuel container containing the new fuel, transfer the new fuel taken out at the inspection place to another trolley, and install the new fuel upright on the inspection base separately from the above. This is done for each carriage.

【0018】[0018]

【作用】本発明においては、仮置き場所に積まれた燃料
容器の前記検査場所までの搬送を、前記新燃料入り燃料
容器を吊持する門型クレーン付きの台車で行い、前記検
査場所で取出した新燃料を別の台車に移し替え、前記検
査台への前記新燃料の立設装着を前記別の台車ごと行う
ものであるため、原子炉建屋内に設置された天井クレー
ンは、少なくとも検査場所までの搬送と、検査台への新
燃料の立設を行う必要がなくなり、クレーン運転者の運
転への負担が軽くなる。従って、安全作業を確保し、尚
且作業の効率化を達成することができる。
In the present invention, the fuel container loaded in the temporary storage location is transported to the inspection location by the carriage with the gate type crane that suspends the fuel container containing the new fuel, and is taken out at the inspection location. Since the new fuel is transferred to another trolley, and the new fuel is erected on the inspection table upright for each of the other trolleys, the overhead crane installed in the reactor building must be at least the inspection location. There is no need to transport the new fuel to the inspection table and to set up new fuel on the inspection table, which reduces the burden on the crane operator's operation. Therefore, it is possible to secure the safe work and achieve the work efficiency.

【0019】ところで、仮置き場所と検査場所とは一般
に互いに離れた所にあるものではなく、同じ階上にあ
る。そこで、従来の天井クレーンで燃料容器を搬送する
のではなく、仮置き場所に積まれた燃料容器の検査場所
までの搬送を行う門型クレーン付きの台車で、燃料容器
を持ち上げ、持ち上げた燃料容器を搬送させるようにす
るものである。
By the way, the temporary storage location and the inspection location are not generally separated from each other, but on the same floor. Therefore, instead of transporting the fuel container with a conventional overhead crane, the carrier with a gate-type crane that transports the fuel container loaded in the temporary storage location to the inspection location lifts the fuel container and lifts the fuel container. Is to be transported.

【0020】即ち、具体的には、燃料容器を横倒状態で
上方に牽引する牽引手段と、該牽引手段と上方に牽引さ
れた燃料容器とを横方向に移送する台車とを備えた門型
クレーン付きの台車で行う。この門型クレーン付きの台
車は、構成が簡単であり、作業具が安価に作成でき、操
作も単純である。
That is, specifically, a gate type provided with a traction means for pulling the fuel container upward in a sideways state and a carriage for laterally transferring the traction means and the fuel container pulled upward. Carry with a crane. The dolly-mounted trolley has a simple structure, work tools can be manufactured at low cost, and operation is simple.

【0021】尚、牽引手段の駆動源としては、作業員が
ウインチを巻き上げるような人力によるものでも良い
し、電動モータ等の機械力を用いたものでも良い。更
に、台車の移送も作業員が人力によっておすものでも良
いし、別の電動モータ等の機械力で移送させる構成とし
ても良い。尚、機械力を用いる場合には、操作盤を作業
具に付属させてもよいし、遠隔操作ができるようにして
もよい。
The drive source of the traction means may be human power such as an operator hoisting a winch, or mechanical power such as an electric motor. Further, the trolley may be transferred manually by an operator, or may be configured to be transferred by a mechanical force such as another electric motor. When mechanical force is used, the operation panel may be attached to the work tool or may be remotely operated.

【0022】また、検査場所で取出した新燃料を別の台
車に移し替え、前記検査台への前記新燃料の立設装着を
前記別の台車ごと行うものとしては、具体的には、燃料
容器を横倒状態で支持する台車と、前記燃料容器を支持
した台車を立設状態で保持する立設台と、前記立設台上
に設置された前記台車の一端を上方に牽引する牽引手段
と、前記立設台の側面に設けられた前記台車の一方の車
輪を載せる軌条とを備え、台車の一端を牽引させて、一
方の車輪を軌条に載せて、軌条を外れることなく持ち上
げて、台車ごと立設させるものがある。
Further, the new fuel taken out at the inspection place is transferred to another trolley, and the new fuel is erected on the inspection pedestal together with the other trolley. A trolley for supporting the trolley in a sideways state, an erection stand for holding the trolley supporting the fuel container in an erected state, and a traction means for pulling one end of the trolley installed on the erection platform upward. A rail for mounting one wheel of the carriage provided on a side surface of the upright table, one end of the carriage being pulled, one wheel being placed on the rail, and being lifted without leaving the rail, There is a thing to make each stand stand.

【0023】この検査場所で取出した新燃料を別の台車
に移し替え、前記検査台への前記新燃料の立設装着を前
記別の台車ごと行うものは、構成が簡単であり、作業具
が安価に作成でき、操作も単純である。
The new fuel taken out at this inspection place is transferred to another trolley, and the new fuel is erected and mounted on the inspection base for each of the other trolleys. It is inexpensive to create and simple to operate.

【0024】尚、同様に、牽引手段の駆動源としては、
作業員がウインチを巻き上げるような人力によるもので
も良いし、電動モータ等の機械力を用いたものでも良
い。機械力を用いる場合には、操作盤を作業具に付属さ
せてもよいし、遠隔操作ができるようにしてもよい。
Similarly, as the drive source of the traction means,
It may be manually operated by a worker to wind up a winch, or may be mechanically operated by an electric motor or the like. When mechanical force is used, the operation panel may be attached to the work implement or may be remotely operated.

【0025】[0025]

【実施例】図1は本発明の新燃料搬入検査作業のタイム
スケジュールを示す説明図である。図2は本発明の方法
で用いる作業具の一実施例の構成を示す説明図である。
図3は図2の作業具の使用を示す説明図である。図4は
本発明の方法で用いる別の作業具の一実施例の構成を示
す説明図であり、a図は上面図,b図は平面図,c図は
側面図である。尚、図において、従来例と同一の符号は
同一又は相当部分を示す。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 is an explanatory view showing a time schedule of a new fuel carry-in inspection work of the present invention. FIG. 2 is an explanatory view showing the configuration of an embodiment of a work tool used in the method of the present invention.
FIG. 3 is an explanatory view showing the use of the work implement of FIG. 4A and 4B are explanatory views showing the structure of an embodiment of another working tool used in the method of the present invention. FIG. 4A is a top view, FIG. 4B is a plan view, and FIG. 4C is a side view. In the drawings, the same reference numerals as those in the conventional example indicate the same or corresponding portions.

【0026】図1において、各工程の白抜四角は本発明
の方法で用いる作業具の動作を示し、黒塗四角は天井ク
レーンの動作を示し、斜線四角は、燃料検査台に取り付
けられている手巻きウィンチの動作を示す。また、各々
の四角の幅はその作業に係る時間(分)を示す。
In FIG. 1, the white squares in each step show the operation of the work implement used in the method of the present invention, the black squares show the operation of the overhead crane, and the shaded squares are attached to the fuel inspection table. The operation of the manual winch is shown. The width of each square indicates the time (minutes) involved in the work.

【0027】図1に示す通り、本発明では、仮置き場所
(11)に積まれた燃料容器(5) を検査場所まで搬送する工
程と、新燃料をコンテナスタンド(立設台)に立設する
工程とを専用の作業具で行うものである。
In the present invention, as shown in FIG.
The process of transporting the fuel container (5) loaded in (11) to the inspection place and the process of standing the new fuel on the container stand (standing table) are performed by dedicated work tools.

【0028】即ち、天井クレーン(10)は、この2つの工
程には関与せず、コンテナスタンド(18)に燃料容器(5)
と共に立設された新燃料(0) を竪吊りして検査台(19)に
移動する工程と、外観,寸法検査等が行なわれ、装着さ
れたチャンネルボックス付き新燃料(0a)を移送して使用
済燃料貯蔵プール(22)の燃料収納機(23)に取付け、プー
ル(22)に保管するか、新燃料貯蔵ラックに収納する工程
とを行う。
That is, the overhead crane (10) does not participate in these two steps, and the fuel container (5) is attached to the container stand (18).
The process of vertically suspending the new fuel (0) installed together with it and moving it to the inspection table (19), and the appearance and dimension inspections were performed, and the installed new fuel (0a) with a channel box was transferred. The process of attaching the spent fuel storage pool (22) to the fuel storage unit (23) and storing it in the pool (22) or storing it in a new fuel storage rack is performed.

【0029】従って、クレーン運転者の運転への負担が
軽くなり、安全作業を確保し、尚且作業の効率化を達成
することができる。
Therefore, the burden on the crane operator for driving is lightened, safe work can be secured, and work efficiency can be improved.

【0030】仮置き場所(11)に積まれた燃料容器(5) の
吊下げ、移動、開梱及びコンテナスタンド(18)までの移
動の作業には、図2に示した搬送作業具(30)で行う。こ
の搬送作業具(30)は、回転方向が自在に変わる車輪(31)
が装着された4本の支柱(32)を互いに桁(33)で組んだ門
型様の外観を有している。長手方向の長さ及び幅は燃料
容器の長さ及び幅よりも大きな外観を有している。尚、
長手方向の長さ又は幅の一方が燃料容器よりも大きけれ
ば使用可能であるが、双方が大きい方が持ち上げた時に
安定がある。
The operations of suspending, moving, unpacking and moving the fuel containers (5) loaded in the temporary storage location (11) to the container stand (18) are performed by the transfer work tools (30) shown in FIG. ). This transfer work tool (30) has wheels (31) whose direction of rotation can change freely.
It has a gate-like appearance in which four columns (32) to which are mounted are assembled with each other by girders (33). The length and width in the longitudinal direction have a larger appearance than the length and width of the fuel container. still,
It can be used if one of the length or width in the longitudinal direction is larger than the fuel container, but the larger one is stable when lifted.

【0031】搬送作業具(30)の中心位置には、滑車(34)
が取りつけてあり、この滑車(34)には支柱(32)の一本に
燃料容器(5) を吊下げるウィンチ(35)からワイヤ(36)が
延びている。このウィンチ(35)を巻上げることにより、
燃料容器(5) の側面の4か所の吊環にフックを引っ掛
け、横倒状態で吊り上げる。
At the central position of the transfer work tool (30), the pulley (34)
The pulley (34) has a wire (36) extending from a winch (35) for suspending the fuel container (5) on one of the columns (32). By winding up this winch (35),
Hook the four hanging rings on the side of the fuel container (5) and hang it upside down.

【0032】作業員は、前述の図5で示す燃料容器仮置
き場(11)まで手押しにより搬送作業具(30)を移動させ、
ウィンチ(13)を巻上げて燃料容器(5) を吊り上げ、同じ
く手押しにより、燃料容器(5) を吊り上げた搬送作業具
(30)を押して、コンテナスタンド(18)の近傍の検査場所
まで移動させる。この搬送作業具における移動作業は従
来の天井クレーンで行うものと比べて、燃料容器(5) の
近くで操作を行うことができるため、操作時間が約半分
に短縮できる。
The worker moves the transfer work tool (30) by hand to the fuel container temporary storage place (11) shown in FIG.
Transport work tool in which the winch (13) is rolled up to lift the fuel container (5), and the fuel container (5) is also lifted by pushing it by hand.
Press (30) to move to the inspection location near the container stand (18). Compared with the conventional overhead crane, the transfer work of the transfer work tool can be performed near the fuel container (5), so the operation time can be reduced to about half.

【0033】更に、図3に示すように、コンテナスタン
ド(18)まで、移動させたなら、燃料容器(5) を台車(41)
に載せ、燃料容器(5) の上蓋(15)及び頭蓋(16)を取外し
て燃料容器(5) を開梱する。次に、開梱された燃料容器
(5) は立設させるため、図4に示す竪吊り治具(17)を台
車(41)の一端側の側面に設けられた2つの吊環(34)に取
付ける。
Further, as shown in FIG. 3, if the fuel container (5) is moved to the container stand (18), the truck (41) is moved.
Then, remove the upper lid (15) and skull (16) of the fuel container (5) and unpack the fuel container (5). Next, the unpacked fuel container
Since (5) is erected, the vertical suspension jig (17) shown in FIG. 4 is attached to the two suspension rings (34) provided on the side surface on one end side of the carriage (41).

【0034】図4に示す通り、コンテナスタンド(18)に
は、従来天井クレーン(10)で燃料容器(5) を竪吊りして
いたものを、天井クレーン(10)を使わずに、燃料容器
(5) を竪吊りし、コンテナスタンド(18)に立て掛ける機
能を備える。
As shown in FIG. 4, in the container stand (18), the one in which the fuel container (5) was vertically suspended by the overhead crane (10) is used instead of the overhead crane (10).
It has the function of vertically hanging (5) and leaning it against the container stand (18).

【0035】即ち、搬送作業具(30)で移動してきた燃料
容器(5) をコンテナスタンド(18)の手前で台車(41)に載
せて固定する。次にコンテナスタンド(18)の上段に取付
けたジブクレーン(42)で巻上げ、台車(41)の車輪(43)を
コンテナスタンド(18)のレール(軌条)(44)に沿って燃
料容器(5) を立て起す。
That is, the fuel container (5) moved by the transfer work tool (30) is placed and fixed on the carriage (41) in front of the container stand (18). Next, hoist it with the jib crane (42) attached to the upper stage of the container stand (18), and then move the wheels (43) of the truck (41) along the rails (rail) (44) of the container stand (18) to the fuel container (5). Raise up.

【0036】立て起し後、コンテナスタンド(18)に燃料
容器(5) を固定し、竪吊り治具(17)を外す。以降は、天
井クレーン(10)で新燃料(0) を吊り上げ、前述の図6に
示した検査台(19)に取付ける。
After standing upright, the fuel container (5) is fixed to the container stand (18) and the vertical hanging jig (17) is removed. After that, the new fuel (0) is lifted by the overhead crane (10) and attached to the inspection table (19) shown in FIG. 6 described above.

【0037】以上のように、仮置き場所に積まれた燃料
容器を検査場所まで搬送する工程と、新燃料をコンテナ
スタンド(立設台)に立設する工程とを専用の作業具で
行うことにより、燃料容器(5) の移動からコンテナスタ
ンド(18)への取付けまで天井クレーンを施用することな
く作業を進めることができる。
As described above, the step of transporting the fuel container loaded in the temporary storage location to the inspection location and the step of erection of the new fuel on the container stand (standing table) should be carried out by dedicated work tools. This allows the work to proceed from moving the fuel container (5) to mounting it on the container stand (18) without applying an overhead crane.

【0038】図1に示す本実施例のタイムスケジュール
と、図8に示す従来のタイムスケジュールとを比較する
と、 (1) 作業効率については、従来法では、新燃料検査数量
はA〜Hまで、8本、本法では新燃料検査数量はA〜N
まで、14本となり、作業効率は75%向上する。 (2) クレーン運転状況 従来法では、クレーン運転時間;180分連続運転 本法では、クレーン運転時間;70分運転 従来比の40%弱となり、大幅に軽減される。
Comparing the time schedule of this embodiment shown in FIG. 1 with the conventional time schedule shown in FIG. 8, (1) Regarding work efficiency, in the conventional method, the new fuel inspection quantity is from A to H, Eight, new fuel inspection quantity is A to N in this method
Up to 14, the work efficiency is improved by 75%. (2) Crane operating status In the conventional method, the crane operating time is 180 minutes continuous operation. In this method, the crane operating time is 70 minutes operating.

【0039】以上のように、図1のタイムスケジュール
に示す通り、天井クレーンの運転状況は、従来法の図8
と比較しても明らかな通り、大幅に軽減される。同時
に、作業の効率化を図ることができ、大きな効果を得る
ことができる。従来は、クレーンの運転に制約され、例
えば、新燃料(0) の移動と燃料容器(5) の同時移動は不
可能であったが、本方法を採用することにより移動作業
が同時進行可能となり、作業の効率化を図ることができ
る。また、クレーン運転者は新燃料(0) 及びチャンネル
ボックス付き新燃料(9) の移動にのみ集中すればよく、
疲労度は大幅に軽減される。
As described above, as shown in the time schedule of FIG. 1, the operating condition of the overhead crane is as shown in FIG.
As you can see from the comparison, it is significantly reduced. At the same time, work efficiency can be improved and a great effect can be obtained. Conventionally, it was impossible to move the new fuel (0) and the fuel container (5) at the same time due to the constraint of the crane operation, but by adopting this method, the moving work can proceed at the same time. Therefore, the work efficiency can be improved. Also, the crane operator need only concentrate on the movement of fresh fuel (0) and fresh fuel with channel box (9),
Fatigue is greatly reduced.

【0040】[0040]

【発明の効果】本発明は以上説明した通り、仮置き場所
に積まれた燃料容器の前記検査場所までの搬送を、前記
新燃料入り燃料容器を吊持する門型クレーン付きの台車
で行い、前記検査場所で取出した新燃料を別の台車に移
し替え、前記検査台への前記新燃料の立設装着を前記別
の台車ごと行うものであるため、原子炉建屋内に設置さ
れた天井クレーンは、少なくとも検査場所までの搬送
と、検査台への新燃料の立設を行う必要がなくなり、ク
レーン運転者の運転への負担が軽くなる。従って、安全
作業を確保し、尚且作業の効率化の達成が可能であると
いう効果がある。
As described above, according to the present invention, the transportation of the fuel container loaded in the temporary storage location to the inspection location is performed by the carriage with the gate type crane for suspending the fuel container containing the new fuel, Since the new fuel taken out at the inspection place is transferred to another trolley, and the new fuel is erected on the inspection pedestal together with the other trolley, an overhead crane installed in the reactor building Eliminates the need to carry at least to the inspection place and to set up new fuel on the inspection table, which reduces the burden on the crane operator's operation. Therefore, there is an effect that it is possible to secure the safe work and achieve the work efficiency.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の新燃料搬入検査作業のタイムスケジュ
ールを示す説明図である。
FIG. 1 is an explanatory view showing a time schedule of a new fuel carry-in inspection work of the present invention.

【図2】本発明の方法で用いる作業具の一実施例の構成
を示す説明図である。
FIG. 2 is an explanatory diagram showing a configuration of an embodiment of a work tool used in the method of the present invention.

【図3】図2の作業具の使用を示す説明図である。FIG. 3 is an explanatory view showing the use of the work implement of FIG. 2.

【図4】本発明の方法で用いる別の作業具の一実施例の
構成を示す説明図であり、a図は上面図,b図は平面
図,c図は側面図である。
4A and 4B are explanatory views showing the configuration of an embodiment of another working tool used in the method of the present invention, wherein FIG. 4A is a top view, FIG. 4B is a plan view, and FIG. 4C is a side view.

【図5】搬送状態の新燃料を内部に収容する搬送容器の
搬入作業を説明する説明図である。
FIG. 5 is an explanatory diagram for explaining a carrying-in operation of a carrier container that accommodates fresh fuel in a carrier state.

【図6】燃料容器の開梱の手順を示す説明図である。FIG. 6 is an explanatory diagram showing a procedure for unpacking a fuel container.

【図7】新燃料の保管作業を示す説明図である。FIG. 7 is an explanatory diagram showing a storage operation of new fuel.

【図8】従来の新燃料搬入検査作業のタイムスケジュー
ルを示す説明図である。
FIG. 8 is an explanatory diagram showing a time schedule of a conventional new fuel carry-in inspection work.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 原子炉建屋内の仮置き場所に積まれた新
燃料入り燃料容器を同じく原子炉建屋内の検査場所まで
搬送し、前記燃料容器から内部の新燃料を取出して検査
台に立設状態で装着し、前記新燃料の検査を行うと共に
該新燃料にチャンネルボックスを装着する新燃料搬入検
査作業方法において、 前記仮置き場所に積まれた燃料容器の前記検査場所まで
の搬送を、前記新燃料入り燃料容器を吊持する門型クレ
ーン付きの台車で行い、 前記検査場所で取出した新燃料を別の台車に移し替え、
前記検査台への前記新燃料の立設装着を前記別の台車ご
と行うことを特徴とする新燃料搬入検査作業方法。
1. A fuel container containing new fuel loaded in a temporary storage location in the reactor building is also transported to an inspection location in the reactor building, and new fuel inside is taken out from the fuel container and set up on an inspection table. Installed in the installed state, inspecting the new fuel and at the same time, in the new fuel carry-in inspection work method of mounting the channel box on the new fuel, transporting the fuel container loaded in the temporary storage location to the inspection location, Carrying with a carriage with a gate crane that suspends the fuel container containing the new fuel, transfer the new fuel taken out at the inspection place to another carriage,
A new fuel carry-in inspection work method characterized in that the new fuel is vertically installed on the inspection table together with the other carriage.
JP6087753A 1994-03-31 1994-03-31 New fuel loading inspection work method Expired - Lifetime JP2736735B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6087753A JP2736735B2 (en) 1994-03-31 1994-03-31 New fuel loading inspection work method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6087753A JP2736735B2 (en) 1994-03-31 1994-03-31 New fuel loading inspection work method

Publications (2)

Publication Number Publication Date
JPH07270578A true JPH07270578A (en) 1995-10-20
JP2736735B2 JP2736735B2 (en) 1998-04-02

Family

ID=13923708

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6087753A Expired - Lifetime JP2736735B2 (en) 1994-03-31 1994-03-31 New fuel loading inspection work method

Country Status (1)

Country Link
JP (1) JP2736735B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016023932A (en) * 2014-07-16 2016-02-08 原子燃料工業株式会社 Processing system of unused nuclear fuel and processing method of unused nuclear fuel
JP2017211188A (en) * 2016-05-23 2017-11-30 三菱重工業株式会社 Cask facility and cask handling method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102097140B (en) * 2009-12-11 2013-02-13 上海核工程研究设计院 Underwater fuel conveying trolley and tipping-over device for pressurized water reactor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016023932A (en) * 2014-07-16 2016-02-08 原子燃料工業株式会社 Processing system of unused nuclear fuel and processing method of unused nuclear fuel
JP2017211188A (en) * 2016-05-23 2017-11-30 三菱重工業株式会社 Cask facility and cask handling method

Also Published As

Publication number Publication date
JP2736735B2 (en) 1998-04-02

Similar Documents

Publication Publication Date Title
JPH07270578A (en) Acceptance inspection method for new fuel
CN106639287B (en) Stone Vertical transportation resources in exterior wall scaffold
JPH01294121A (en) Container transferrer
JP3180203B2 (en) Material lifting assembly equipment used for construction of high-rise structures
JP2000204764A (en) Carrying-in hanger
JP6828951B2 (en) Cargo handling method by container crane and container crane
JP2017211188A (en) Cask facility and cask handling method
JP5138413B2 (en) Crane lifter carrier
JP4514277B2 (en) Product coil shipping method
JPH0891770A (en) Long member suspending device
JPH0818648B2 (en) Temporary storage / import facility for tunnel segment
CN108899105A (en) The production method of heavy water reactor spent fuel dry-type storage
JPH07172380A (en) Method for dismantling scaffolding in lng ship tank
JP3038323B2 (en) New fuel inspection device
CN209293852U (en) A kind of tunnel cable trench cover transporting and hoisting trolley
JP3298488B2 (en) Container crane
JP2560184B2 (en) Equipment for automatic storage and transportation of materials and equipment for the shield construction method
JPH10297841A (en) Carrying-in method for hoist of elevator
JPS6234943Y2 (en)
JP3576399B2 (en) Inspection method and inspection device for fuel control valve for gas turbine
JPH05107392A (en) Facility for handling container
JP2009145173A (en) Inspection equipment for cask for transporting and storing radioactive material
JPS637651Y2 (en)
JPH09328289A (en) Vertical heavy-load lift of overhead crane and conveying method using it
JPS6090292A (en) Coke conveying apparatus for facility for dry quenching of coke

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19971202