JPH10297841A - Carrying-in method for hoist of elevator - Google Patents

Carrying-in method for hoist of elevator

Info

Publication number
JPH10297841A
JPH10297841A JP9107491A JP10749197A JPH10297841A JP H10297841 A JPH10297841 A JP H10297841A JP 9107491 A JP9107491 A JP 9107491A JP 10749197 A JP10749197 A JP 10749197A JP H10297841 A JPH10297841 A JP H10297841A
Authority
JP
Japan
Prior art keywords
hoist
hoistway
guide rail
floor
elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP9107491A
Other languages
Japanese (ja)
Inventor
Nobuaki Yagi
伸明 八木
Toshiyuki Tadokoro
俊之 田所
Hidekazu Toyoda
秀和 豊田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP9107491A priority Critical patent/JPH10297841A/en
Publication of JPH10297841A publication Critical patent/JPH10297841A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PROBLEM TO BE SOLVED: To prevent a flaw on building floor and also reduce the worker's labor. SOLUTION: An upper part of a hoistway is provided with a hoist 4, and a guide rail 10 is laid on a building floor face 9 on the first floor, and a truck 11 having the loaded hoist machine 12 is set on the upper face of the guide rail 10. A drawing wire body 5 and the truck 11 are mutually connected, and the hoist 4 is driven to move the truck 11 to an entrance door 8. After that, the drawing wire body 5 is re-attached to the hanger bolt 13 of the hoist machine 12 to drive the hoist 4 again, and the hoist machine 12 is therefore suspended into the hoistway 1 and installed in a hoistway pit 7.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はホームエレベータ等
の小型エレベータの巻上機を昇降路内に搬入するエレベ
ータの巻上機搬入方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of loading a hoist of a small elevator such as a home elevator into a hoistway.

【0002】[0002]

【従来の技術】従来、ホームエレベータ等の小型エレベ
ータにおいて、巻上機を昇降路内に搬入するには、2人
の作業員が手持ち、搬入していた。しかし、近時、巻上
機の重量が増す傾向にあり、台車にのせて運搬するよう
になった。
2. Description of the Related Art Conventionally, in a small elevator such as a home elevator, two workers carry and carry in a hoist into a hoistway. However, recently, the weight of the hoist has tended to increase, and the hoist has been transported on a bogie.

【0003】[0003]

【発明が解決しようとする課題】上記従来技術において
は、台車が家の床面上を走行する結果、床面に傷をつけ
るという問題があった。又、巻上機は多大の重量があ
り、これを作業員が運搬するには相当の力を必要として
いた。
In the above-mentioned prior art, there is a problem that the bogie travels on the floor of the house, thereby damaging the floor. Further, the hoisting machine has a large weight, and requires a considerable amount of force to transport it.

【0004】本発明の目的は、床に傷をつけることな
く、又、作業員の労力を軽減することのできるエレベー
タの巻上機搬入方法を提供するにある。
It is an object of the present invention to provide a method for carrying an elevator hoisting machine which does not damage the floor and can reduce the labor of an operator.

【0005】[0005]

【課題を解決するための手段】上記目的は、昇降路ピッ
ト内に巻上機を搬入するエレベータの巻上機搬入方法に
おいて、前記昇降路内ピット上部にホイストを取付け、
一方1階建屋床面にガイドレールを敷設し、他方、この
ガイドレール上に前記巻上機を載置した台車を走行可能
に取付け、しかる後、前記ホイストと台車とを索条体に
より連絡し、そして、前記ホイストを駆動しながら索条
体を介して台車を昇降路出入口側に移動させ、その後、
索条体を巻上機に連絡し、しかる後、ホイストを再度駆
動して巻上機を吊上げつつ昇降路内に搬入するようにし
たことにより達成される。
The object of the present invention is to provide an elevator hoisting machine loading method for loading a hoisting machine into a hoistway pit, wherein a hoist is mounted above the hoistway pit.
On the other hand, a guide rail is laid on the floor of the first-floor building. On the other hand, a bogie on which the hoist is mounted is mounted on the guide rail so as to be able to travel, and thereafter, the hoist and the bogie are connected by a cord. And, while driving the hoist, move the bogie to the hoistway entrance / exit side via the cord body,
This is achieved by connecting the cord to the hoist, and then driving the hoist again to carry the hoist up into the hoistway while lifting the hoist.

【0006】[0006]

【発明の実施の形態】以下、図面を参照して本発明の一
実施の形態を説明する。図1は昇降路ピット内に巻上機
を搬入する昇降路全体の斜視図、図2は図1の巻上機部
分の側面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. FIG. 1 is a perspective view of the entire hoistway for carrying the hoist into the hoistway pit, and FIG. 2 is a side view of the hoist part of FIG.

【0007】図において、1は昇降路であり、この昇降
路1の上部には揚重梁2が設けられており、この揚重梁
2にホイスト4が玉掛けワイヤーロープ3を介して取付
けられている。5はホイスト4により巻上げられる索条
体、6は昇降路1の下部に設けられた滑車で、この滑車
6により垂直に降りている索条体5を出入口8、建屋床
9へと水平に移行させる。そして、索条体5の一端は台
車11の吊り穴14と連結している。10は建屋床面9
に出入口8に向かって敷設された本設の乗りかごガイド
レールで、このガイドレール10上を台車11に設けら
れたキャスター15が走行する。12は台車に載置され
た巻上機であり、吊りボルト13が設けられている。
In FIG. 1, reference numeral 1 denotes a hoistway. A hoisting beam 2 is provided on the hoistway 1. A hoist 4 is attached to the hoisting beam 2 via a sling wire rope 3. I have. 5 is a rope that is hoisted by the hoist 4, and 6 is a pulley provided at the lower part of the hoistway 1. The rope 5 that is vertically descended by the pulley 6 is horizontally transferred to an entrance 8 and a building floor 9. Let it. One end of the cable body 5 is connected to the suspension hole 14 of the carriage 11. 10 is the building floor 9
A caster 15 provided on a trolley 11 runs on the guide rail 10 on a main car guide rail laid toward the entrance 8. Reference numeral 12 denotes a hoisting machine mounted on a carriage, on which a suspension bolt 13 is provided.

【0008】次に巻上機12の搬入方法を説明する。巻
上機12を昇降路ピット7に搬入するにあたり、図2に
示すように建屋床面9に2本の本設乗りかごガイドレー
ル10を敷設し、このガイドレール10上面に巻上機1
2を載置した台車11をキャスター15が走行できるよ
うに設置する。次に、図1に示すように索条体5の一端
を台車11の吊り穴14に取付け、ホイスト4を駆動し
ながら索条体5を介して台車11を移動させ、出入口8
まで移動させる。その後、索条体5の一端を吊り穴14
から外し、この一端を巻上機10に設けられている吊り
ボルト13に連結し、しかる後、ホイスト4を再度駆動
して巻上機12を昇降路1に吊り込み、昇降路ピット7
に設置する。
Next, a method of loading the hoisting machine 12 will be described. In loading the hoisting machine 12 into the hoistway pit 7, two permanent car guide rails 10 are laid on the floor 9 of the building as shown in FIG.
The cart 11 on which the caster 2 is mounted is installed so that the casters 15 can travel. Next, as shown in FIG. 1, one end of the cable body 5 is attached to the hanging hole 14 of the carriage 11, and the carriage 11 is moved through the cable body 5 while driving the hoist 4, and
Move up to Thereafter, one end of the cord body 5 is connected to the hanging hole 14.
And one end thereof is connected to a suspension bolt 13 provided on the hoisting machine 10. Thereafter, the hoist 4 is driven again to suspend the hoisting machine 12 in the hoistway 1, and the hoistway pit 7
Installed in

【0009】このように、巻上機12の運搬は全てホイ
スト4の駆動により行うことができ、従って、作業者の
労力を大巾に軽減することができる。又、ガイドレール
10を使用することにより建屋床面8を傷つけることな
く巻上機12を搬入することができる。更にガイドレー
ル10として、本設のガイドレールを用いるなり、この
搬入作業のために、特別のガイドレールを持ち込んだ
り、持ち出したりする必要がなく、費用を易くすること
ができる。
As described above, all the transport of the hoisting machine 12 can be carried out by driving the hoist 4, so that the labor of the operator can be greatly reduced. Further, by using the guide rail 10, the hoisting machine 12 can be carried in without damaging the building floor surface 8. Further, since a permanent guide rail is used as the guide rail 10, there is no need to bring in or take out a special guide rail for the carrying-in operation, and the cost can be reduced.

【0010】[0010]

【発明の効果】本発明によれば、建屋床に傷をつけるこ
となく、又、作業者に多大の労力をかけさせることな
く、巻上機をピット内に搬入できる。更に、ガイドレー
ルとして、本設のガイドレールを用いるなり、特別にガ
イドレールを持ち込んだり、持ち出したりする必要がな
く、費用を安くすることができる。
According to the present invention, the hoist can be carried into the pit without damaging the floor of the building and without requiring a great deal of labor by the operator. Further, since the guide rails provided in the present embodiment are used as the guide rails, there is no need to carry in or take out the guide rails, and the cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】昇降路ピット内に巻上機を搬入する昇降路全体
の斜視図である。
FIG. 1 is a perspective view of an entire hoistway for loading a hoist into a hoistway pit.

【図2】図1の巻上機部分の側面図である。FIG. 2 is a side view of a hoist portion of FIG.

【符号の説明】[Explanation of symbols]

1 昇降路 2 揚重梁 3 玉掛けワイヤーロープ 4 ホイスト 5 索条体 6 滑車 7 昇降路ピット 8 出入口 9 建屋床面 10 ガイドレール 11 台車 12 巻上機 13 吊りボルト 14 吊り穴 15 キャスター DESCRIPTION OF SYMBOLS 1 Hoistway 2 Lifting beam 3 Sling wire rope 4 Hoist 5 Cord line 6 Pulley 7 Hoistway pit 8 Entrance 9 Building floor surface 10 Guide rail 11 Bogie 12 Hoisting machine 13 Hanging bolt 14 Hanging hole 15 Caster

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 昇降路ピット内に巻上機を搬入するエレ
ベータの巻上機搬入方法において、前記昇降路内ピット
上部にホイストを取付け、一方1階建屋床面にガイドレ
ールを敷設し、他方、このガイドレール上に前記巻上機
を載置した台車を走行可能に取付け、しかる後、前記ホ
イストと台車とを索条体により連絡し、そして、前記ホ
イストを駆動しながら索条体を介して台車を昇降路出入
口側に移動させ、その後、索条体を巻上機に連絡し、し
かる後、ホイストを再度駆動して巻上機を吊上げつつ昇
降路内に搬入するようにしたことを特徴とするエレベー
タの巻上機搬入方法。
An elevator hoist loading method for loading a hoist into a hoistway pit, wherein a hoist is mounted on an upper part of the hoistway pit, and a guide rail is laid on the floor of the first-floor building. A carriage on which the hoist is mounted is mounted on the guide rail so as to be able to run, and thereafter, the hoist and the carriage are connected by a cord, and the hoist is driven through the cord while being driven. To move the bogie to the hoistway entrance side, and then connect the cable to the hoist, and then drive the hoist again to lift the hoist and carry it into the hoistway. Characteristic method of loading elevator hoist.
【請求項2】 前記ガイドレールとして、本設の乗かご
ガイドレールを用いたことを特徴とする請求項1記載の
エレベータの巻上機搬入方法。
2. The method according to claim 1, wherein a permanent car guide rail is used as the guide rail.
JP9107491A 1997-04-24 1997-04-24 Carrying-in method for hoist of elevator Pending JPH10297841A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9107491A JPH10297841A (en) 1997-04-24 1997-04-24 Carrying-in method for hoist of elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9107491A JPH10297841A (en) 1997-04-24 1997-04-24 Carrying-in method for hoist of elevator

Publications (1)

Publication Number Publication Date
JPH10297841A true JPH10297841A (en) 1998-11-10

Family

ID=14460564

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9107491A Pending JPH10297841A (en) 1997-04-24 1997-04-24 Carrying-in method for hoist of elevator

Country Status (1)

Country Link
JP (1) JPH10297841A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001335255A (en) * 2000-05-24 2001-12-04 Toshiba Corp Elevator installation construction method, and elevator installation unit
US6364067B1 (en) * 2000-09-20 2002-04-02 Otis Elevator Company Method and apparatus for installing elevator components
JP2004509032A (en) * 2000-07-19 2004-03-25 オーチス エレベータ カンパニー Lifting tool for integrated elevator installation
CN101934994A (en) * 2010-08-30 2011-01-05 广东省第四建筑工程公司 Building high-altitude vertical hoisting double-guide cable system and assisting method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001335255A (en) * 2000-05-24 2001-12-04 Toshiba Corp Elevator installation construction method, and elevator installation unit
JP2004509032A (en) * 2000-07-19 2004-03-25 オーチス エレベータ カンパニー Lifting tool for integrated elevator installation
US6364067B1 (en) * 2000-09-20 2002-04-02 Otis Elevator Company Method and apparatus for installing elevator components
CN101934994A (en) * 2010-08-30 2011-01-05 广东省第四建筑工程公司 Building high-altitude vertical hoisting double-guide cable system and assisting method

Similar Documents

Publication Publication Date Title
JPH10297841A (en) Carrying-in method for hoist of elevator
JP2015016941A (en) Elevator heavy substance lifting method, and elevator hoist lifting method
JP4929045B2 (en) Guide rail installation method for machine room-less elevator
CN214141300U (en) Special double-beam bridge crane for metallurgy
JP2001114484A (en) Construction method for suspending elevator main rope
JP2006348692A (en) Material conveyance system for construction of exterior wall part of building
JP4597595B2 (en) Hoisting machine installation equipment
JPH0628548Y2 (en) Lifting device for self-propelled work platform
JPH0920480A (en) Heavy object carrying method of utilizing rope type elevator and heavy object carrier device used in this heavy object carrying method
JPH05330758A (en) Elevator guide rail installation assist device and guide rail installation method
JPH0681481A (en) Material hoisting/lowering equipment
JP2512196B2 (en) Construction material hoisting device and hoisting method
CN218058063U (en) Lifting car for high-rise building well
CN221116788U (en) Elevator well material transportation equipment
CN212655333U (en) Crane mounting and transporting device
JPS6234943Y2 (en)
JP3298488B2 (en) Container crane
JP4115823B2 (en) Elevator equipment
JPH0734076Y2 (en) Lifting equipment for construction material carrier
JPH0949334A (en) Traveling carriage to carry building member and carrying method of building member
JPH11325405A (en) Fixing tool for feed water heater and fixing method therefor
JPH10167668A (en) Vertical and horizontal transporting device and its operation
JP4239464B2 (en) Elevator equipment
JPH07304582A (en) Carrying-in and carrying-out method for escalator truss and device therefor
JPH04129981A (en) Method of installing construction for hydraulic elevator

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071117

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071117

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081117

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081117

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081117

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081117

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 9

Free format text: PAYMENT UNTIL: 20091117

LAPS Cancellation because of no payment of annual fees