JPH0718675A - Sc pile and executing method thereof - Google Patents

Sc pile and executing method thereof

Info

Publication number
JPH0718675A
JPH0718675A JP5183299A JP18329993A JPH0718675A JP H0718675 A JPH0718675 A JP H0718675A JP 5183299 A JP5183299 A JP 5183299A JP 18329993 A JP18329993 A JP 18329993A JP H0718675 A JPH0718675 A JP H0718675A
Authority
JP
Japan
Prior art keywords
concrete
pile
steel pipe
tubular body
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5183299A
Other languages
Japanese (ja)
Inventor
Koichi Kujirai
孝一 鯨井
Takaaki Ohara
卓明 尾原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP5183299A priority Critical patent/JPH0718675A/en
Publication of JPH0718675A publication Critical patent/JPH0718675A/en
Pending legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

PURPOSE:To dispense with the anchor reinforcing bar welding work at the site and improve the connecting strength to a footing and reliability by burying a plurality of anchor reinforcing bars in a concrete cylindrical body constituting an SC pile in advance. CONSTITUTION:An SC pile 1 is driven into the ground until the distance from the end face of the SC pile 1 to the upper face of the flattening concrete B on the ground becomes the prescribed length. Flattening cobble stones A are laid on the ground to surround the outer periphery of tone SC pile 1, then the flattening concrete B is placed on them. Filler concrete C is filled in the SC pile 1 to the same height as that of the flattening concrete B. A steel pipe 1a is melted and removed from slightly above the flattening concrete B to the end face of the SC pile 1. The concrete at this portion is demolished to expose anchor reinforcing bars 3. A foundation beam main reinforcement is bonded to the exposed anchor reinforcing bars 3 to form a footing D.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は建築構造物その土木構造
物の基礎となるフーチングを支持固定するSC杭及びそ
の施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an SC pile for supporting and fixing a footing which is a basis of a building structure and a civil engineering structure, and a construction method thereof.

【0002】[0002]

【従来の技術】従来、例えば図6で示す如くフーチング
Dを支持固定するSC杭aとしてコンクリートの筒状体
bの外周に鋼管cを被覆したものが知られている。
2. Description of the Related Art Conventionally, as shown in FIG. 6, for example, an SC pile a for supporting and fixing a footing D is known in which a steel pipe c is coated on the outer periphery of a concrete tubular body b.

【0003】[0003]

【発明が解決しようとする課題】しかし上記従来のSC
杭aを使った施工方法によると、地中に打設した当該S
C杭aが地上の均しコンクリートBの上面から少許露出
したその周面の鋼管cに、フーチングを支持固定するた
めに別個にアンカー鉄筋dを垂直に溶着しなければなら
ず、この溶着のための溶接姿勢が悪くなるために溶接が
十分に行いにくく溶接の信頼度が低くなる等の問題点を
有していた。
However, the conventional SC described above is used.
According to the construction method using the pile a, the S that has been placed underground
In order to support and fix the footing, the anchor bar d must be separately welded vertically to the steel pipe c on the peripheral surface of which the C pile a is slightly exposed from the upper surface of the leveling concrete B on the ground. However, there is a problem in that the welding posture is poor and it is difficult to perform welding sufficiently, and the reliability of welding is reduced.

【0004】本発明は上記の問題点を解決し、簡単な構
造でしかも施工上の信頼性が高いSC杭とその施工方法
を提供することを目的とする。
It is an object of the present invention to solve the above problems and provide an SC pile having a simple structure and high reliability in construction, and a construction method thereof.

【0005】[0005]

【課題を解決するための手段】上記の目的を達成するた
め本発明は、鋼管と、該鋼管の内周面に打設したコンク
リートの筒状体と、該コンクリート筒状体内に軸方向に
埋設した複数のアンカー鉄筋とからなることを特徴とす
る。
To achieve the above object, the present invention provides a steel pipe, a concrete tubular body cast on the inner peripheral surface of the steel pipe, and an axially embedded concrete tubular body. It is characterized by comprising a plurality of anchor rebars.

【0006】[0006]

【作用】SC杭を地中に打設する。[Operation] An SC pile is driven into the ground.

【0007】そして地上の均しコンクリートから少許上
方までの鋼管部分を残して、その少許上方から該SC杭
の端面までに被覆された鋼管を溶断して除去し、更にそ
の鋼管を取り除いた個所にあたるコンクリート筒状体の
コンクリートの露出部分を解体する。
Then, the steel pipe portion from the leveled concrete to the upper part of the ground is left, and the steel pipe covered from the upper part of the concrete to the end face of the SC pile is melted and removed, and the steel pipe is removed. Dismantle the exposed part of the concrete in the concrete tubular body.

【0008】一方、予め地上の均しコンクリートから少
許上方までの鋼管部分を残して、その少許上方から該S
C杭の端面までの鋼管部分が取り除いてあるSC杭にお
いては、当該SC杭のコンクリート筒状体の露出部分を
上方として、該SC杭を地中に打設し、該コンクリート
筒状体の露出部分を解体する。
On the other hand, the steel pipe portion from the leveled concrete on the ground to the upper side of the small area is left in advance, and the S pipe is formed from the upper side of the small area.
In the SC pile in which the steel pipe portion up to the end surface of the C pile is removed, the exposed portion of the concrete tubular body of the SC pile is placed above and the SC pile is driven into the ground to expose the concrete tubular body. Dismantle parts.

【0009】かくてコンクリート筒状体の軸方向に埋め
込まれたアンカー鉄筋が露出することにより、フーチン
グを支承して固定するために当該アンカー鉄筋をそのま
ま使用することができる。
Thus, by exposing the anchor rebar embedded in the axial direction of the concrete tubular body, the anchor rebar can be used as it is for supporting and fixing the footing.

【0010】[0010]

【実施例】以下、本発明の1実施例を図1及び図2によ
り説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to FIGS.

【0011】1はSC杭を示し、該SC杭1はその全長
にわたり被覆した鋼管1aと、該鋼管1aの内周面のコ
ンクリートの筒状体2と、該コンクリート筒状体2の軸
方向に埋め込まれた複数のアンカー鉄筋3とからなる。
Reference numeral 1 denotes an SC pile, which is a steel pipe 1a covering the entire length thereof, a concrete tubular body 2 on the inner peripheral surface of the steel pipe 1a, and an axial direction of the concrete tubular body 2. It consists of a plurality of anchor rebars 3 embedded.

【0012】次にこの実施例の施工方法について図3に
より説明する。
Next, the construction method of this embodiment will be described with reference to FIG.

【0013】先づ予め、当該SC杭1を杭打ち機等でそ
の端面から地上の均しコンクリートBの上面までの距離
が所定の長さになるまで地中に打設する。
First, the SC pile 1 is first driven into the ground by a pile driving machine or the like until the distance from its end face to the upper surface of the leveling concrete B on the ground becomes a predetermined length.

【0014】次に該SC杭1の外周を囲繞するように地
面に均しぐり石Aと、更にその上に均しコンクリートB
を敷設すると共に、該SC杭1内に中埋コンクリートC
を該均しコンクリートBと同一の高さになるまで中埋め
する。
Next, a leveling stone A is leveled on the ground so as to surround the outer periphery of the SC pile 1, and leveling concrete B is further placed on the leveling stone A.
And laying concrete in the SC pile 1
Is filled to the same height as the leveled concrete B.

【0015】次に該均しコンクリートBの少許上方から
SC杭1の端面までの鋼管1aを溶断して除去し、更に
該鋼管1aが除去された個所にあたるコンクリートの筒
状体2のコンクリートを解体して該コンクリート筒状体
2の軸方向に埋め込まれた複数のアンカー鉄筋3を露出
させる。
Next, the steel pipe 1a from a little above the leveled concrete B to the end face of the SC pile 1 is melted and removed, and the concrete of the concrete tubular body 2 corresponding to the portion where the steel pipe 1a is removed is dismantled. Then, the plurality of anchor rebars 3 embedded in the axial direction of the concrete tubular body 2 are exposed.

【0016】そしてこの露出したアンカー鉄筋3に図示
していない基礎梁主筋を結着させ型枠を嵌めて生コンを
流し込みフーチングDを造る。
Then, a main beam (not shown) is attached to the exposed anchor reinforcing bar 3 and a mold is fitted into the anchor reinforcing bar 3, so that fresh concrete is poured into the footing D.

【0017】かくて当該アンカー鉄筋3をSC杭1に溶
着することなく直接にフーチングDを支持して固定する
ことができるのでSC杭1の施工上の信頼性が向上す
る。
Thus, the anchor rebar 3 can be directly supported and fixed to the footing D without being welded to the SC pile 1, so that the construction reliability of the SC pile 1 is improved.

【0018】図4及び図5は本発明の他の実施例を示
し、前記コンクリート筒状体2をその端面から所定の長
さにわたって露出させて該コンクリート筒状体2の残余
の部分を鋼管1aにて被覆しているSC杭1であり、前
記複数のアンカー鉄筋3を露出させるに際し、被覆され
た鋼管1aを溶断して除去する作業上の手間が省略でき
るという効果を有する。
FIGS. 4 and 5 show another embodiment of the present invention, in which the concrete tubular body 2 is exposed from its end face for a predetermined length, and the remaining portion of the concrete tubular body 2 is steel pipe 1a. It is an SC pile 1 covered with 1., and has an effect that it is possible to omit the work time for fusing and removing the covered steel pipe 1a when exposing the plurality of anchor rebars 3.

【0019】[0019]

【発明の効果】上記のように本発明のSC杭によると、
鋼管と、該鋼管内のコンクリートの筒状体と、該コンク
リート筒状体の軸方向に埋め込んだ複数のアンカー鉄筋
とにより構成したので、地中に打設したSC杭において
端面から所定の長さまでの鋼管の切断除去及び又はコン
クリート筒状体のコンクリートを解体してアンカー鉄筋
を露出し、該アンカー鉄筋を利用してフーチングを支持
固定でき、かくて施工上の信頼性が向上する効果を有す
る。
As described above, according to the SC pile of the present invention,
Since it is composed of a steel pipe, a concrete tubular body in the steel pipe, and a plurality of anchor reinforcing bars embedded in the axial direction of the concrete tubular body, in the SC pile driven underground, from the end face to a predetermined length. The steel pipe can be removed by cutting and / or the concrete of the concrete tubular body can be disassembled to expose the anchor reinforcing bar, and the footing can be supported and fixed by using the anchor reinforcing bar, thus improving the reliability in construction.

【図面な簡単な説明】[Brief description of drawings]

【図1】本発明の1実施例の断面図である。FIG. 1 is a sectional view of an embodiment of the present invention.

【図2】そのII-II 截断面図である。FIG. 2 is a sectional view taken along the line II-II.

【図3】その一施工状態を示す断面図である。FIG. 3 is a cross-sectional view showing one construction state thereof.

【図4】本発明の他の実施例の断面図である。FIG. 4 is a sectional view of another embodiment of the present invention.

【図5】そのV−V截断面図である。FIG. 5 is a sectional view taken along line VV.

【図6】従来のSC杭の施工状態を示す断面図である。FIG. 6 is a cross-sectional view showing a construction state of a conventional SC pile.

【符号の説明】[Explanation of symbols]

1 SC杭 1a 鋼管 2 コンクリートの筒状体 3 アンカー鉄筋 1 SC pile 1a Steel pipe 2 Concrete tubular body 3 Anchor rebar

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 鋼管と、該鋼管の内周面に打設したコン
クリートの筒状体と、該コンクリート筒状体内に軸方向
に埋設した複数のアンカー鉄筋とからなることを特徴と
するSC杭。
1. An SC pile comprising a steel pipe, a concrete tubular body cast on the inner peripheral surface of the steel pipe, and a plurality of anchor rebars axially embedded in the concrete tubular body. .
【請求項2】 前記鋼管が前記コンクリート筒状体の全
長にわたり被覆されていることを特徴とする請求項1に
記載の鋼管杭。
2. The steel pipe pile according to claim 1, wherein the steel pipe is covered over the entire length of the concrete tubular body.
【請求項3】 前記鋼管は、前記コンクリート筒状体を
その端面から所定の長さにわたって露出させて該コンク
リート筒状体の残余の部分を被覆していることを特徴と
する請求項1に記載のSC杭。
3. The steel pipe covers the remaining portion of the concrete tubular body by exposing the concrete tubular body from its end surface over a predetermined length. SC pile.
【請求項4】 前記請求項2に記載のSC杭を、その端
面から地上の均しコンクリートの上面までの距離が所定
の長さになるまで地中に打設し、該均しコンクリートの
少許上方から前記端面までの前記鋼管を切断して除去
し、該鋼管の除去された個所の前記コンクリート筒状体
のコンクリートを解体して前記複数のアンカー鉄筋を露
出することを特徴とする鋼管杭の施工方法。
4. The SC pile according to claim 2 is driven into the ground until the distance from the end face to the upper surface of the leveling concrete on the ground reaches a predetermined length, and the leveling of the leveling concrete is reduced. The steel pipe from the upper side to the end surface is cut and removed, and the concrete of the concrete tubular body at the removed portion of the steel pipe is dismantled to expose the plurality of anchor rebars. Construction method.
【請求項5】 前記請求項3に記載のSC杭のコンクリ
ート筒状体の露出部を上方として該SC杭を、前記鋼管
の端部が地上の均しコンクリートの上面より少許上方の
位置になるまで地中に打設し、前記露出部のコンクリー
トを解体して前記複数のアンカー鉄筋を露出することを
特徴とするSC杭の施工方法。
5. The SC pile according to claim 3, wherein the exposed portion of the concrete tubular body is upward, and the end of the steel pipe is located slightly above the upper surface of the leveling concrete on the ground. A method for constructing an SC pile, which is characterized in that the concrete of the exposed portion is disassembled to expose the plurality of anchor rebars.
JP5183299A 1993-06-30 1993-06-30 Sc pile and executing method thereof Pending JPH0718675A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5183299A JPH0718675A (en) 1993-06-30 1993-06-30 Sc pile and executing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5183299A JPH0718675A (en) 1993-06-30 1993-06-30 Sc pile and executing method thereof

Publications (1)

Publication Number Publication Date
JPH0718675A true JPH0718675A (en) 1995-01-20

Family

ID=16133245

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5183299A Pending JPH0718675A (en) 1993-06-30 1993-06-30 Sc pile and executing method thereof

Country Status (1)

Country Link
JP (1) JPH0718675A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010196251A (en) * 2009-02-23 2010-09-09 Nippon Concrete Ind Co Ltd Existing concrete pile
JP2010255394A (en) * 2009-03-31 2010-11-11 Japan Pile Corp Sc pile, manufacturing method therefor, and pile head treatment method
JP2017503101A (en) * 2014-01-15 2017-01-26 シービージェイ(香港) オーシャン エンジニアリング リミテッドCbj(Hong Kong) Ocean Engineering Limited Water structure fixing roll and its construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010196251A (en) * 2009-02-23 2010-09-09 Nippon Concrete Ind Co Ltd Existing concrete pile
JP2010255394A (en) * 2009-03-31 2010-11-11 Japan Pile Corp Sc pile, manufacturing method therefor, and pile head treatment method
JP2017503101A (en) * 2014-01-15 2017-01-26 シービージェイ(香港) オーシャン エンジニアリング リミテッドCbj(Hong Kong) Ocean Engineering Limited Water structure fixing roll and its construction method

Similar Documents

Publication Publication Date Title
JPH09242067A (en) Building method for cast-in-place concrete pile
JP4611113B2 (en) Integrated construction method of pile and column
JP3728653B2 (en) Bonding structure between flat slab and concrete-filled steel pipe column and flat slab construction method
JPH0718675A (en) Sc pile and executing method thereof
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
JP3122850B2 (en) Construction method of building with basement floor with steel pipe pile foundation
JP3057466B2 (en) How to build underground structures
JPH0517955A (en) Execution method for direct foundation and form panel for direct foundation
JPH0337603B2 (en)
KR100694762B1 (en) Method for constructing underground slabs and walls without preliminary wall-attached supports
JPH0892970A (en) Foundation structure
JP2693027B2 (en) Pile head treatment method for cast-in-place concrete pile
JPH0467533B2 (en)
JP3567387B2 (en) How to build an underground skeleton
JPH10266227A (en) Method of connecting ready made pile and foundation slab
JPH07103583B2 (en) Construction method for large span underground structure
JP2000144757A (en) Preparation of foundation for building
JP3360234B2 (en) Construction method of underground skeleton
JP2004108091A (en) Composite structure building and construction method therefor
JPS5841118A (en) Sheathing and protecting method for long-sized slope
JP3289163B2 (en) How to build underground structures
JP2000144756A (en) Preparation of foundation for building
JPS61134441A (en) Method of reinforcing foundation ground of building
JP2003003500A (en) PCa UNDERGROUND STEEL COLUMN INSERTION METHOD FOR CAST- IN-PLACE PILE
JPH0441817A (en) Sheathing method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040902

RD02 Notification of acceptance of power of attorney

Effective date: 20040930

Free format text: JAPANESE INTERMEDIATE CODE: A7422

A131 Notification of reasons for refusal

Effective date: 20070417

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070601

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070925

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070927

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101005

Year of fee payment: 3

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111005

Year of fee payment: 4

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121005

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131005

Year of fee payment: 6