JPH0711140B2 - Formwork construction method in reverse construction method - Google Patents

Formwork construction method in reverse construction method

Info

Publication number
JPH0711140B2
JPH0711140B2 JP62226920A JP22692087A JPH0711140B2 JP H0711140 B2 JPH0711140 B2 JP H0711140B2 JP 62226920 A JP62226920 A JP 62226920A JP 22692087 A JP22692087 A JP 22692087A JP H0711140 B2 JPH0711140 B2 JP H0711140B2
Authority
JP
Japan
Prior art keywords
concrete
sand
formwork
pillar
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP62226920A
Other languages
Japanese (ja)
Other versions
JPS6471942A (en
Inventor
英策 垣田
幸一 高木
正剛 山口
有宏 牟田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP62226920A priority Critical patent/JPH0711140B2/en
Publication of JPS6471942A publication Critical patent/JPS6471942A/en
Publication of JPH0711140B2 publication Critical patent/JPH0711140B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、建物の地下構造躯体を地表部分から地盤を
根切りしながら下階に向って施工する逆打ち工法におい
て、特にコンクリート造の本設柱の側型枠を組立てる型
枠施工法に関する。
Description: TECHNICAL FIELD The present invention relates to a reverse striking method for constructing an underground structural body of a building from the ground surface portion toward the lower floor while rooting the ground, particularly a concrete construction pillar. Formwork construction method for assembling side molds of

従来の技術 従来、逆打ち工法における柱の型枠施工法としては、第
3図に例示したように、根切り底面1上に立てたサポー
ト2…でコンクリートパネル3を支持せしめ、該コンク
リートパネル3の上に柱の側型枠4を組立てた構成で実
施されている。図中5は柱主筋、8は該主筋5に巻装さ
れたフープ筋、6は本設柱鉄骨(構真柱)、7は前記鉄
骨を支える仮設鉄骨である。
2. Description of the Related Art Conventionally, as a pillar formwork construction method in the upside-down construction method, as shown in FIG. 3, a concrete panel 3 is supported by a support 2 ... Standing on a root cutting bottom surface 1. It is carried out in a configuration in which the side frame 4 of the pillar is assembled on the above. In the figure, 5 is a pillar main bar, 8 is a hoop bar wound around the main bar 5, 6 is a main column steel frame (structured column), and 7 is a temporary steel frame that supports the steel frame.

本発明が解決しようとする問題点 上記第3図に例示したような従来の型枠施工法によれ
ば、柱主筋5…がコンクリートパネル3を貫通して下方
に突出されるので、コンクリートパネル3には柱主筋5
…を通す孔あけ加工が不可欠であり、この孔あけ加工が
面倒である。その上、前記の孔に柱主筋5を通しながら
コンクリートパネル3を取付け、柱の側型枠4を建込む
作業、あるいはコンクリート打設後の脱型作業が非常に
面倒で困難である。しかも、柱の側型枠4の位置決め固
定が難しく、型枠精度の確保が困難という問題点があっ
た。
Problems to be Solved by the Present Invention According to the conventional formwork construction method as illustrated in FIG. 3, the pillar main bars 5 penetrate the concrete panel 3 and are projected downward. There are 5 pillars
It is indispensable to make a hole to drill through, and this hole is troublesome. In addition, it is very troublesome and difficult to mount the concrete panel 3 while passing the pillar main bar 5 through the hole and erection of the side mold 4 of the pillar, or the demolding work after placing concrete. Moreover, there is a problem that it is difficult to position and fix the side mold 4 of the column, and it is difficult to secure the accuracy of the mold.

問題点を解決するための手段 上記従来技術の問題点を解決するための手段として、こ
の発明に係る逆打ち工法における型枠施工法は、図面の
第1図と第2図に好適な実施例を示したとおり、 建物の地下構造躯体を地盤の根切り工事の進捗にしたが
い順次下階に向って施工を進める逆打ち工法において、 施工単位の深さまで地盤の根切りを進め、その根切り底
面1上に砂型枠10を設置し、この砂型枠10の中に砂11を
柱底の高さまで充填する段階と、前記充填砂11の面上に
おける柱主筋位置の外側部分に捨コンクリート(又は捨
モルタル、以下同じ)12を打設し、同柱主筋位置の内側
部分にはコンクリートパネル13を敷設し、前記捨コンク
リート12及びコンクリートパネル13の面上にプラスチッ
クシートを敷き、前記充填砂11を利用してコンクリート
パネル13の外周に柱主筋5を配筋する段階と、前記捨コ
ンクリート12の面上に墨出しをして柱の側型枠4を組立
て、コンクリート15を打設する段階と、前記打設コンク
リート15の硬化後に砂型枠10及び柱の側型枠4を解体
し、充填砂11を崩壊させて捨コンクリート12及びコンク
リートパネル13を解体し、再び地盤の根切りを進める段
階と、より成る構成とした。
Means for Solving the Problems As means for solving the problems of the above-mentioned prior art, the formwork construction method in the reverse construction method according to the present invention is a preferred embodiment shown in FIGS. 1 and 2 of the drawings. As shown in the figure, in the reverse construction method, in which the construction of the underground structure of the building is carried out sequentially toward the lower floor according to the progress of the root cutting work, the root cutting of the ground is advanced to the depth of the construction unit, and the root cutting bottom 1. A sand formwork 10 is installed on the sand mold 10 and the sand formwork 10 is filled with sand 11 up to the height of the bottom of the pillar. Mortar, the same applies below) 12 is laid, a concrete panel 13 is laid inside the main reinforcement of the same column, a plastic sheet is laid on the surfaces of the waste concrete 12 and the concrete panel 13, and the filling sand 11 is used. Then concrete The steps of arranging the column main bars 5 on the outer periphery of the flannel 13, the steps of marking on the surface of the waste concrete 12 to assemble the side mold 4 of the pillar, and placing the concrete 15; After the hardening of 15, the sand mold 10 and the side mold 4 of the pillar are dismantled, the filling sand 11 is disintegrated to dismantle the waste concrete 12 and the concrete panel 13, and the root cutting of the ground is promoted again. did.

作 用 柱の側型枠4は、砂型枠10に充填した砂11の締固め効果
でしっかりと支持される。
The side formwork 4 of the working column is firmly supported by the compaction effect of the sand 11 filled in the sand formwork 10.

柱主筋5は砂型枠10内の充填砂11中に突き刺した状態で
配筋され、柱主筋5の外側部分は捨コンクリート12が、
内側部分はコンクリートパネル13がそれぞれ型枠代用と
されるので、コンクリートパネル13に孔あけ加工するこ
とは一切不要であり、柱の側型枠4の組立て施工が極め
て簡単に行える。
The column main bars 5 are arranged in a state of being pierced into the filling sand 11 in the sand formwork 10, and the outer portion of the column main bars 5 is a waste concrete 12,
Since the concrete panels 13 are used as mold substitutes for the inner parts, it is not necessary to make holes in the concrete panels 13 and the assembling construction of the pillar side mold 4 can be performed very easily.

また、柱の側型枠4は捨コンクリート12上に墨出しをし
て組立て施工ができるので、その位置決め固定が容易で
精度を得やすい。
Further, since the side mold 4 of the pillar can be marked out on the waste concrete 12 and assembled, the positioning and fixing thereof can be easily performed and the accuracy can be easily obtained.

コンクリート打設後の脱型に際しては、肌ばなれを容易
にするプラスチックシート(ポリエチレンフィルム9)
が敷込まれているので、捨コンクリート12及びコンクリ
ートパネル13は、砂型枠10を解体し、充填砂11に崩壊さ
せることにより極めて容易に解体することができる。
A plastic sheet (polyethylene film 9) that makes it easy for the skin to come out when releasing from the mold after placing concrete
Since the waste concrete 12 and the concrete panel 13 are laid, the sand formwork 10 can be disassembled very easily by dismantling the sand formwork 10 and collapsing it into the filling sand 11.

実施例 次に、図面の第1図と第2図に示した実施例を説明す
る。
Example Next, an example shown in FIGS. 1 and 2 of the drawings will be described.

図面は逆打ち工法による鉄骨鉄筋コンクリート造建物の
地下構造躯体の柱等を地盤の根切り工事を進めながら下
階に向って施工していく過程において、特に柱型枠の施
工法について示したものである。図示例では、地下1階
分の施工単位の深さまで地盤の根切りが進められた段階
を示している。図中1が根切り底面であり、その上に高
さ900mm程度の砂型枠10を組立て、砂11が柱底の高さレ
ベル(根切り底面1から約700mm位の高さ)まで充填さ
れている。
The drawing shows the construction method of the pillar formwork in the process of constructing the pillars of the underground structure of the steel reinforced concrete building by the upside down construction method toward the lower floor while proceeding with the root cutting work of the ground. is there. The illustrated example shows a stage where the ground root cutting has been advanced to the depth of the construction unit for the first basement floor. In the figure, 1 is the root cutting bottom, on which a sand formwork 10 having a height of about 900 mm is assembled, and sand 11 is filled up to the height level of the pillar bottom (height of about 700 mm from the root cutting bottom 1). There is.

砂型枠10内の充填砂11の上面において特に柱主筋5(後
述)の位置の外側部分には、型枠代用とされる捨コンク
リート(又は捨モルタル)12を厚さ50mmぐらい打設し、
柱主筋位置の内側部分にはコンクリートパネル13が敷設
されている。コンクリートパネル13としては厚さが12mm
位で仮設鉄骨7の横断面形状に沿って2分割された鉄板
が使用され、この2枚の鉄板を突き合わせることにより
柱主筋5の内側部分の全面に及ぶ大きさ、形状に形成さ
れているから、仮設鉄骨7の両側から楽に挟み込むこと
ができ、もって充填砂11の上面に載置されている。当該
コンクリートパネル13及び捨てコンクリート12は砂型枠
10内で拘束され締固められた充填砂11によって支持され
る。このため、充填砂11に関しては、締固め易く支持力
が安定化しやすい水しめ土が使用されている。
On the upper surface of the filling sand 11 in the sand mold 10, especially on the outer side of the position of the column main bar 5 (described later), a waste concrete (or waste mortar) 12, which is used as a substitute for the form, is placed with a thickness of about 50 mm,
A concrete panel 13 is laid inside the main pillar position. 12mm thick for concrete panel 13
An iron plate divided into two along the transverse cross-sectional shape of the temporary steel frame 7 is used at the position, and by butting these two iron plates together, the size and shape are formed so as to cover the entire inner surface of the column main bar 5. Therefore, it can be easily sandwiched from both sides of the temporary steel frame 7, and is thus placed on the upper surface of the filling sand 11. The concrete panel 13 and the discarded concrete 12 are sand formwork.
It is supported by packed sand 11 which is constrained and compacted within 10. For this reason, for the filling sand 11, hydrating soil is used that is easy to compact and has a stable supporting force.

前記捨コンクリート12及びコンクリートパネル13の面上
には、打設コンクリート15との肌ばなれを確実にする薄
いポリエチレンフィルム9等のプラスチックシートが敷
込まれている。そして、柱主筋5が、当該ポリエチレン
フィルム9の上からコンクリートパネル13の外周に沿っ
て、柱底から所定長さ突き出され前記充填砂11の中に突
き刺して配筋され、上部にはフープ筋8が巻装されてい
る。コンクリートパネル13については、当該柱主筋5を
通す孔の加工が一切不要なのである。
On the surfaces of the waste concrete 12 and the concrete panel 13, a plastic sheet such as a thin polyethylene film 9 for ensuring smooth contact with the cast concrete 15 is laid. Then, the pillar main bar 5 is projected from the polyethylene film 9 along the outer periphery of the concrete panel 13 by a predetermined length from the bottom of the pillar and pierced into the filling sand 11 to be arranged, and the hoop bar 8 is arranged on the upper part. Is wrapped around. Regarding the concrete panel 13, it is not necessary to process the holes through which the pillar main bars 5 pass.

柱の側型枠4は、上記捨コンクリート12(ポリエチレン
フィルム9)の面上に支持された形で組立てられてい
る。この側型枠4の組立施工に際しては、予め捨コンク
リート12の面上に墨出しをして型枠4の正確な位置決め
固定が行なわれる。型枠4はやはりコラムクランプ14に
より強固に締付けて組立てられている。
The side mold 4 of the pillar is assembled so as to be supported on the surface of the waste concrete 12 (polyethylene film 9). In assembling and constructing the side mold 4, the surface of the waste concrete 12 is marked in advance to accurately position and fix the mold 4. The frame 4 is also tightly assembled by the column clamp 14.

コンクリート15の打設及びその養生期間を経た後の脱型
に際しては、まず、砂型枠10及び柱の側型枠4の解体を
行なう。砂型枠10を解体すると、その中の充填砂11は簡
単に崩壊させることができる。捨コンクリート12とコン
クリートパネル13の面上には上記の通りポリエチレンフ
ィルム9が敷込まれているので、砂型枠10を解体する
と、充填砂11の崩壊と共に捨コンクリート12及びコンク
リートパネル13も柱型の打設コンクリート15と肌わかれ
して容易に解体される。その結果、柱底からは柱主筋5
…が次の打継ぎ用として突出した形の打継ぎ部が容易に
得られるのである。すなわち、以後、更に地盤の根切り
工事を進めながら前記柱主筋5を打継いで効率よく本設
柱6を地下階に向かって施工していくことができる。
When the concrete 15 is poured and the mold is removed after the curing period, the sand mold 10 and the pillar side mold 4 are disassembled. When the sand mold 10 is dismantled, the filling sand 11 therein can be easily collapsed. Since the polyethylene film 9 is laid on the surfaces of the waste concrete 12 and the concrete panel 13 as described above, when the sand formwork 10 is dismantled, the waste concrete 12 and the concrete panel 13 are also pillar-shaped as the filling sand 11 collapses. It is easily dismantled as it is disentangled with the cast concrete 15. As a result, the pillar main bar 5
It is easy to obtain a projecting splicing part for the next splicing. That is, thereafter, while continuing the ground cutting work, the main pillars 5 can be continuously spliced to efficiently construct the main pillars 6 toward the basement floor.

本発明が奏する効果 この発明に係る逆打ち工法における型枠施工法によれ
ば、充填砂11及び同充填砂11上に設けられる捨コンクリ
ート12とコンクリートパネル13並びにその上に敷込まれ
るプラスチックシートを使用するから、柱の側型枠4の
建込み、又は脱型の作業が容易、迅速にできると共に、
捨コンクリート12上で柱の側型枠4の位置決め固定を正
確にでき、型枠精度の確保が容易にできることになるの
である。
Effect of the present invention According to the formwork construction method in the reverse construction method according to the present invention, the filling sand 11 and the waste concrete 12 and the concrete panel 13 provided on the filling sand 11 and the plastic sheet laid on it Since it is used, the work of building or removing the side frame 4 of the pillar can be performed easily and quickly, and
It is possible to accurately position and fix the side mold 4 of the pillar on the waste concrete 12 and easily secure the mold accuracy.

【図面の簡単な説明】[Brief description of drawings]

第1図と第2図はこの発明に係る型枠施工法を柱底部に
実施した場合の垂直断面図と水平断面図、第3図は同じ
柱底部に関する従来の型枠施工法を示した垂直断面図で
ある。 1……根切り底面、4……柱の側型枠、5……柱主筋 10……砂型枠、11……充填砂、12……捨コンクリート 13……コンクリートパネル、15……打設コンクリート
1 and 2 are a vertical sectional view and a horizontal sectional view when the formwork construction method according to the present invention is applied to a column bottom, and FIG. 3 is a vertical section showing a conventional formwork construction method for the same column bottom. FIG. 1 …… Root cutting bottom, 4 …… Column side form, 5 …… Column main bar 10 …… Sand form, 11 …… Filled sand, 12 …… Scrap concrete 13 …… Concrete panel, 15 …… Pasting concrete

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 庁内整理番号 FI 技術表示箇所 E21D 13/00 ─────────────────────────────────────────────────── ─── Continuation of the front page (51) Int.Cl. 6 Identification code Internal reference number FI technical display location E21D 13/00

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】建物の地下構造躯体を地盤の根切り工事の
進捗にしたがい順次下階に向って施工を進める逆打ち工
法において、 施工単位の深さまで地盤の根切りを進め、その根切り底
面(1)上に砂型枠(10)を設置し、この砂型枠(10)
の中に砂(11)を柱底の高さまで充填する段階と、前記
充填砂(11)の面上における柱主筋位置の外側部分に捨
コンクリート(12)を打設し、同柱主筋位置の内側部分
にはコンクリートパネル(13)を敷設し、前記捨コンク
リート(12)及びコンクリートパネル(13)の面上にプ
ラスチックシートを敷き、前記充填砂(11)を利用して
コンクリートパネル(13)の外周に柱主筋(5)を配筋
する段階と、前記捨コンクリート(12)の面上に墨出し
をして柱の側型枠(4)を組立て、コンクリート(15)
を打設する段階と、前記打設コンクリート(15)の硬化
後に砂型枠(10)及び柱の側型枠(4)を解体し、充填
砂(11)を崩壊させて捨コンクリート(12)及びコンク
リートパネル(13)を解体し、再び地盤の根切りを進め
る段階と、より成ることを特徴とする、逆打ち工法にお
ける型枠施工法。
1. In the reverse construction method in which the construction of the underground structure of the building is performed toward the lower floor in accordance with the progress of the root cutting work, the root cutting of the ground is advanced to the depth of the construction unit, and the root cutting bottom (1) Install sand formwork (10) on the sand formwork (10)
Filling sand (11) up to the height of the bottom of the pillar, and placing concrete (12) on the outside of the pillar main bar position on the surface of the filling sand (11), A concrete panel (13) is laid in the inner part, a plastic sheet is laid on the surfaces of the waste concrete (12) and the concrete panel (13), and the filled sand (11) is used to remove the concrete panel (13). At the stage of arranging the column main bars (5) on the outer periphery, and marking out on the surface of the waste concrete (12) to assemble the side formwork (4) of the column, and then concrete (15)
And after the setting concrete (15) is hardened, the sand formwork (10) and the side formwork (4) of the pillar are dismantled, and the filling sand (11) is disintegrated and the waste concrete (12) and A method of constructing a formwork in a reverse construction method, which comprises the steps of dismantling a concrete panel (13) and advancing root cutting again.
JP62226920A 1987-09-10 1987-09-10 Formwork construction method in reverse construction method Expired - Lifetime JPH0711140B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62226920A JPH0711140B2 (en) 1987-09-10 1987-09-10 Formwork construction method in reverse construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62226920A JPH0711140B2 (en) 1987-09-10 1987-09-10 Formwork construction method in reverse construction method

Publications (2)

Publication Number Publication Date
JPS6471942A JPS6471942A (en) 1989-03-16
JPH0711140B2 true JPH0711140B2 (en) 1995-02-08

Family

ID=16852672

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62226920A Expired - Lifetime JPH0711140B2 (en) 1987-09-10 1987-09-10 Formwork construction method in reverse construction method

Country Status (1)

Country Link
JP (1) JPH0711140B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851584A (en) * 2020-07-31 2020-10-30 山东建筑大学 Construction method of reinforced concrete frame structure column foundation enclosure beam in reverse construction method

Also Published As

Publication number Publication date
JPS6471942A (en) 1989-03-16

Similar Documents

Publication Publication Date Title
US4434600A (en) Method for fixing the ends of concrete columns in concrete bases and device for carrying out said method
JPH0711140B2 (en) Formwork construction method in reverse construction method
JP3342891B2 (en) Construction method of horizontal beam erected on columnar structure
KR101880813B1 (en) A sandwitch pc pannel structure and construction method of structure using thereof
JPH09296565A (en) Precast concrete column, its manufacture, and execution method
JPH0523155B2 (en)
JPS6131261B2 (en)
JP2504578B2 (en) Steel frame construction method
JPH10299003A (en) Foundation work using precast concrete member
CN116357161A (en) Construction method of enclosure column
JPH02147768A (en) Formwork for forming concrete foundation
JP2616207B2 (en) Building construction method using reinforced concrete columns and steel beams
JP3179321B2 (en) Precast member manufacturing method, manufacturing apparatus, and precast member
JPS63130838A (en) Hollow pillar made of precast concrete
JP2520364B2 (en) Construction method of underground structure
CN114888952A (en) Manufacturing method of rectangular prefabricated cover plate
JPS6254945B2 (en)
JPS61109825A (en) Foundation construction for foundation beam and the like
JP2827808B2 (en) Half PC pillar
JPH05272256A (en) Constructing method of sidewall of tank made of concrete
JPS5841118A (en) Sheathing and protecting method for long-sized slope
JPH06155431A (en) Production of form object made of precast concrete
JPH11323963A (en) Execution work method of concrete footing
JPH0610359A (en) Construction method for foundation structure
JPH054219A (en) Method and apparatus for manufacturing hollow concrete molding member