JP2616207B2 - Building construction method using reinforced concrete columns and steel beams - Google Patents

Building construction method using reinforced concrete columns and steel beams

Info

Publication number
JP2616207B2
JP2616207B2 JP28735090A JP28735090A JP2616207B2 JP 2616207 B2 JP2616207 B2 JP 2616207B2 JP 28735090 A JP28735090 A JP 28735090A JP 28735090 A JP28735090 A JP 28735090A JP 2616207 B2 JP2616207 B2 JP 2616207B2
Authority
JP
Japan
Prior art keywords
concrete
column
hollow
steel
column member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP28735090A
Other languages
Japanese (ja)
Other versions
JPH04161628A (en
Inventor
勝尚 西村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP28735090A priority Critical patent/JP2616207B2/en
Publication of JPH04161628A publication Critical patent/JPH04161628A/en
Application granted granted Critical
Publication of JP2616207B2 publication Critical patent/JP2616207B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Description

【発明の詳細な説明】 《産業上の利用分野》 本発明、柱を鉄筋コンクリートで形成し、梁の方を鉄
骨で構成する鉄骨鉄筋複合化の柱・梁仕口部を具える鉄
筋コンクリート柱と鉄骨梁を用いた建築構法に関する。
DETAILED DESCRIPTION OF THE INVENTION << Industrial application field >> The present invention, a reinforced concrete column and a steel frame provided with a steel-reinforced composite column / beam joint in which the column is formed of reinforced concrete and the beam is formed of steel frame It relates to the construction method using beams.

《従来の技術》 柱を鉄筋コンクリート造りにした場合には、これに接
続する梁も鉄筋コンクリート造りにするのが一般的であ
る。
<< Conventional Technology >> When a pillar is made of reinforced concrete, a beam connected to the pillar is generally made of reinforced concrete.

しかし、特に梁の施工に際して型枠工事や、型枠撤去
工事などに時間と手間を要し、また建物躯体全体の重量
が重くなり、梁成に高さを取られる結果、天井が低くな
る欠点があった。さらに型枠脱型後の残材の処理が煩雑
であると共に、これらの作業に従事する作業人員数を確
保することも困難である。
However, it takes time and effort to construct the formwork and remove the formwork, especially when constructing the beams.In addition, the weight of the entire building frame increases, and the height of the beams is increased, resulting in a lower ceiling. was there. Further, the processing of the remaining material after the mold is released is complicated, and it is also difficult to secure the number of workers engaged in these operations.

このため最近では梁部分を純粋な鉄骨材によって構成
することで、重量の軽減と梁成の縮小,スパン長さの長
大化を図ると共に、作業の効率化,省力化を図ってい
る。
For this reason, recently, the beam portion is made of pure steel frame material, thereby reducing the weight, reducing the beam length, increasing the span length, and improving the work efficiency and labor saving.

《発明が解決しようとする課題》 ところで、柱を鉄筋コンクリート製とし、梁を鉄骨製
とした場合、その接続箇所となる柱・梁の仕口部におい
ては梁として使用するH形鋼のフランジに柱の主筋を接
合して継手を構成し、然る後に型枠を組んでコンクリー
トを打設していた。
<< Problems to be Solved by the Invention >> By the way, when the column is made of reinforced concrete and the beam is made of steel frame, the joint of the column and the beam, which is the connection point, is connected to the H-shaped steel flange used as the beam. Were joined together to form a joint, and then concrete was cast in a formwork.

そのために、柱・梁仕口部には鉄筋と鉄骨が交差接合
してあり、コンクリートの流動性を阻害し、コンクリー
トの付着強度に問題を残していた。
For this reason, the reinforcing steel and the steel frame are cross-joined at the column / beam joints, impeding the fluidity of the concrete, and leaving a problem in the adhesive strength of the concrete.

本発明は上記事情に鑑みてなされたものであって、そ
の目的は鉄筋コンクリート柱と鉄骨梁とを確実に接合で
きるようにした鉄筋コンクリート柱と鉄骨梁を用いた建
築構法を提供することにある。
The present invention has been made in view of the above circumstances, and an object of the present invention is to provide an architectural construction method using a reinforced concrete column and a steel beam capable of securely connecting the reinforced concrete column and the steel beam.

《課題を解決するための手段》 上記目的を達成するために、本発明の鉄筋コンクリー
ト柱と鉄骨梁を用いた建築構法は、建て込んだ中空プレ
キャストコンクリート柱部材内に柱主筋およびフープ筋
を配筋した上で、該柱部材の上端部に該柱主筋に被せ
て、該柱部材の中空部に連通する中空なコンクリート打
設領域を有しかつ鉄骨梁に接続するための梁端部を一体
に構成して成る捨て型枠兼用の柱・梁仕口部を載置し、
次いで上記柱部材下部に形成した注入開口を介して該柱
部材の内部へその下方から上方の該柱・梁仕口部のコン
クリート打設領域の中程まで生コンクリートを注入充填
し、その後上記柱・梁仕口部の梁端部に鉄骨梁を接続
し、さらに該鉄骨梁上に上階のデッキプレートを装着し
その上にコンクリートの打設を行って上階の床スラブを
構築するとともに、上記柱・梁仕口部上に上階の中空プ
レキャストコンクリート柱部材を建て込み、柱主筋同士
を接続する工程を繰り返して構築していくのである。
<< Means for Solving the Problems >> In order to achieve the above object, a building construction method using a reinforced concrete column and a steel beam of the present invention is a method of arranging a column main reinforcing bar and a hoop reinforcing bar in a built hollow precast concrete column member. Then, the upper end of the pillar member is covered with the pillar main reinforcement, has a hollow concrete casting area communicating with the hollow portion of the pillar member, and integrally has a beam end for connecting to a steel beam. Place the pillar / beam joint that also serves as a disposal form
Then, through the pouring opening formed in the lower part of the pillar member, the inside of the pillar member is filled with ready-mixed concrete from below to the middle of the concrete casting area of the pillar / beam connection part above, and then the pillar is filled.・ A steel beam is connected to the beam end of the beam connection, and an upper deck plate is mounted on the steel beam, and concrete is cast on the steel plate to construct an upper floor slab, A hollow precast concrete column member on the upper floor is erected on the column / beam connection part, and the process of connecting the column main reinforcements is repeated to construct the column.

《作 用》 中空プレキャストコンクリート柱部材の中空部から柱
・梁仕口部の中空なコンクリート打設領域内に柱主筋を
通して、更に柱部材の内部へその下方から上方の柱・梁
仕口部のコンクリート打設領域の中程まで生コンクリー
トを上昇させるように注入充填したとき、鉄筋が交差す
る他、鉄骨が接続される当該柱・梁仕口部とその直下の
柱部材との継ぎ目にコンクリートが連続的に打ち込ま
れ、次に柱・梁仕口部の梁端部に鉄骨梁を接続し、さら
に鉄骨梁上にデッキプレートを装着してその上にコンク
リートの打設を行って床スラブを構築するとともに、更
に上階用の中空プレキャストコンクリート柱部材を装着
し、この上階用の柱部材も同じく上端部に柱・梁仕口部
を連結したならば、当該柱部材の下方から生コンクリー
トを加圧しながら充填する。このとき、下の方に位置す
る柱・梁仕口部の上部から下へもコンクリートが流入
し、上階用の柱部材とその床スラブを支える柱・梁仕口
部との継ぎ目においてもコンクリートが断層にならず一
体的に連続することになる。
<< Operation >> The hollow precast concrete column member passes from the hollow portion of the column member into the hollow concrete casting area of the column / beam connection portion, and further into the column member. When the ready-mixed concrete is poured and filled to the middle of the concrete casting area, the reinforcing steel crosses and concrete is added to the joint between the column / beam connection to which the steel frame is connected and the column member immediately below. Continuously driven, then steel beams are connected to the beam ends of the columns and beam connections, and a deck plate is mounted on the steel beams and concrete is cast on it to build a floor slab And, furthermore, if a hollow precast concrete column member for the upper floor is installed, and the column member for the upper floor is also connected to the column / beam connection at the upper end, the fresh concrete is poured from below the column member. Pressurize I want to fill. At this time, concrete also flows in from the upper part of the pillar / beam joint located below, and also at the seam between the pillar member for the upper floor and the pillar / beam joint supporting the floor slab. Will not be a fault but will be continuous continuously.

しかも、柱部材内へのコンクリートスラリーは注入充
填時に下から入るためにモルタル部分を形成せず、均質
なコンクリートを形成しながら硬化する。
Moreover, since the concrete slurry in the column member enters from below at the time of filling and filling, it does not form a mortar portion and hardens while forming a homogeneous concrete.

柱部材および柱・梁仕口部は型枠を必要としないの
で、脱型作業は要らない。
Since the column members and the column / beam joints do not require a formwork, no demolding work is required.

《実 施 例》 以下、本発明の好適な実施例について、図面を参照に
して詳細に説明する。本実施例は基本的には、建て込ん
だ中空プレキャストコンクリート柱部材1内に柱主筋7
およびフープ筋8を配筋した上で、柱部材1の上端部に
柱主筋7に被せて、柱部材1の中空部分11に連通する中
空なコンクリート打設領域14を有しかつ鉄骨梁20に接続
するための梁端部13を一体に構成して成る捨て型枠兼用
の柱・梁仕口部10を載置し、次いで柱部材1下部に形成
した注入開口4を介して柱部材1の内部へその下方から
上方の柱・梁仕口部10のコンクリート打設領域14の中程
まで生コンクリート3を注入充填し、その後柱・梁仕口
部10の梁端部13に鉄骨梁20を接続し、さらに鉄骨梁20上
に上階のデッキプレート22を装着しその上にコンクリー
トの打設を行って上階の床スラブ6を構築するととも
に、柱・梁仕口部10上に上階の中空プレキャストコンク
リート柱部材を建て込み、柱主筋7同士を接続する工程
を繰り返して構築していくようになっている。
<< Embodiment >> Hereinafter, a preferred embodiment of the present invention will be described in detail with reference to the drawings. In this embodiment, basically, the column main reinforcement 7 is provided in the hollow precast concrete column member 1 which has been erected.
After the hoop bars 8 are arranged, the column main bar 7 is covered on the upper end portion of the column member 1 to have a hollow concrete placing area 14 communicating with the hollow portion 11 of the column member 1. A column / beam joint 10 which is also used as a throw-out frame and integrally formed with a beam end portion 13 for connection is placed thereon, and then the column member 1 is inserted through an injection opening 4 formed below the column member 1. The fresh concrete 3 is injected into the inside from the lower part to the middle of the concrete placing area 14 of the column / beam joint 10 above, and then the steel beam 20 is inserted into the beam end 13 of the column / beam joint 10. The upper floor deck slab 6 is constructed by connecting the deck plate 22 on the upper floor on the steel beam 20 and placing concrete thereon, and the upper floor is placed on the column / beam connection 10. Build the hollow precast concrete column members and repeat the process of connecting the column main reinforcements 7 It has become.

第1図は中空プレキャストコンクリート柱部材1の内
部にコンクリートを打設した中実コンクリート柱2を示
す。
FIG. 1 shows a solid concrete column 2 in which concrete is cast inside a hollow precast concrete column member 1.

中空筒体状に形成したプレキャストコンクリートを型
枠にしてコンクリートを内部に現場打ちするための中空
プレキャストコンクリート柱部材(以下、中空PC柱部
材)1の下部には、ここから生コンクリート3を注入し
て下方から上方へ向って生コンクリート3を充填するた
めの注入開口4を具え、注入開口4の周りにはコンクリ
ートを注入するための口金5のボルト止めを設け、現場
にて床スラブ6の上に柱主筋7およびワープ筋8による
組鉄筋を被覆するように、立設している。
Using a precast concrete formed into a hollow cylindrical body as a formwork, a fresh concrete 3 is poured into a lower portion of a hollow precast concrete column member (hereinafter, hollow PC column member) 1 for casting concrete into the inside thereof. And a pouring opening 4 for filling the ready-mixed concrete 3 from the lower side to the upper side. A bolt 5 of a mouthpiece 5 for pouring concrete is provided around the pouring opening 4 so that the floor slab 6 can be placed on site. The bar main bar 7 and the warp bar 8 are erected so as to cover the reinforcing bar.

そして、口金5を注入開口4にボルト止めし、中空PC
柱部材1内にコンクリートを打ち、中実コンクリート柱
2を得ている。
Then, the base 5 is bolted to the injection opening 4 to form a hollow PC.
Concrete is poured into the column member 1 to obtain a solid concrete column 2.

注入開口4にはモルタル等を充填して後処理する。 The injection opening 4 is filled with mortar or the like, and is post-processed.

以上、第1図には中実コンクリート柱2の説明のため
に、その下部のみを示したが、中実コンクリート柱2の
上端部には柱・梁仕口部10を設ける。
Although only the lower portion of the solid concrete column 2 is shown in FIG. 1 for the purpose of explanation, the column / beam connection portion 10 is provided at the upper end of the solid concrete column 2.

この柱・梁仕口部10は中空PC柱部材1(プレカラムと
も称する)内にコンクリートを打設する前に連結する。
The column / beam connection 10 is connected before concrete is poured into the hollow PC column member 1 (also referred to as a precolumn).

すなわち、第2図(a)〜(c)に示すように、先ず
(a)において既に構築が完了した床スラブ6の上に中
空PC柱部材1を建込む。
That is, as shown in FIGS. 2 (a) to 2 (c), first, the hollow PC column member 1 is built on the floor slab 6 which has already been constructed in (a).

この中空PC柱部材1の上端部に、第2図(b)の如
く、中空PC柱部材1の中空部分11の軸心方向に収まるH
形鋼による縦骨12の中央外周面において水平、かつ90度
の間隔で四方に延びる同じH形鋼からなる鉄骨梁接合用
の梁端部13を具え、更に縦骨12と梁端部13との交差隅角
部にL字形をなして溶接により一体化した矩形状の枠体
で、上記交差隅角部にコンクリート打設領域14および捨
て型枠15を形成兼用する補強材を有した柱・梁仕口部10
を連結している。
As shown in FIG. 2 (b), H which fits in the axial direction of the hollow portion 11 of the hollow PC column member 1 is located at the upper end of the hollow PC column member 1.
A beam end 13 for joining steel beams made of the same H-shaped steel extending horizontally and at 90 ° intervals on the central outer peripheral surface of the longitudinal bone 12 made of a shaped steel, and further comprising the longitudinal bone 12 and the beam end 13. A rectangular frame formed by welding in an L-shape at the intersection corner portion, and having a reinforcing material that also serves as a concrete casting area 14 and a dumping form 15 at the intersection corner portion. Beam connection 10
Are linked.

捨て型枠15は梁端部13の補強材を兼ねながら中空PC柱
部材1との連結用コンクリート打設領域14を画成し、か
つ等価的に鉄板フープ相当を形成している。
The discarding formwork 15 also serves as a reinforcing material for the beam end portion 13 and defines a concrete placing area 14 for connection with the hollow PC column member 1, and equivalently forms an iron plate hoop equivalent.

中空部分11の四隅近くを貫通する柱主筋7の上方突出
端部を捨て型枠15で囲むコンクリート打設領域14内に挿
通しながら柱・梁仕口部10を中空PC柱部材1の上端部に
セットする。
The upper end of the hollow PC column member 1 is formed by inserting the column / beam connection portion 10 into the concrete casting region 14 surrounding the upper protruding end of the column main reinforcing bar 7 penetrating the four corners of the hollow portion 11 with the formwork 15. Set to.

次に、同図(c)の如く、また第1図に基づいて説明
したように、注入開口4からコンクリートを打ち、この
打設コンクリートは柱・梁仕口部10のコンクリート打設
領域14内の真中近くのレベルまで上昇した処で止める。
Next, as shown in FIG. 1C and as described with reference to FIG. 1, concrete is poured from the pouring opening 4, and the poured concrete is placed in the concrete placing area 14 of the column / beam joint 10. Stop where it rises to a level near the middle of the.

そして更に、柱・梁仕口部10の上端部に上階の床スラ
ブおよび上階用の中空PC柱部材を建てるものである。
Further, a floor slab on the upper floor and a hollow PC column member for the upper floor are erected at the upper end of the column / beam connection portion 10.

柱・梁仕口部10の構造は別構造のものでもよいので、
それを第3図に例示説明しながら上階層との施工手順を
以下に説明する。
Since the structure of the column / beam joint 10 may be different,
The construction procedure with the upper floor will be described below while exemplifying and explaining this in FIG.

第3図の柱・梁仕口部18は叙述の柱・梁仕口部10より
も簡易な構造をもち、縦骨12がなく、H形鋼を十字形に
組み、その交差中心部にプレキャストコンクリートによ
る四角形なコンクリート枠19を一体に構成したもので、
内部にコンクリート打設領域14aを持つ。
The column / beam connection 18 in FIG. 3 has a simpler structure than the column / beam connection 10 described above, has no vertical bones 12, and is made of H-shaped steel in a cross shape, and is precast at the center of the intersection. It consists of a square concrete frame 19 made of concrete,
It has a concrete casting area 14a inside.

コンクリート枠19の外部に突出したH形鋼は接続固定
する鉄骨梁20の梁端部13aに該当する。
The H-shaped steel projecting outside the concrete frame 19 corresponds to the beam end 13a of the steel beam 20 to be connected and fixed.

階下の中空PC柱部材1aの上端部に柱・梁仕口部18を載
せ、その上に上階用の中空PC柱部材1を立設固定する。
The column / beam connection 18 is placed on the upper end of the hollow PC column member 1a downstairs, and the hollow PC column member 1 for the upper floor is erected and fixed thereon.

すなわち、コンクリート枠19の中に柱主筋7を通しな
がらそのまま柱・梁仕口部18を中空PC柱部材1の上端部
に載せる。コンクリート枠19がPC柱部材1の上端部に載
置された状態になる。
That is, the column / beam connection portion 18 is placed on the upper end of the hollow PC column member 1 as it is while passing the column main reinforcement 7 through the concrete frame 19. The concrete frame 19 is placed on the upper end of the PC column member 1.

然して、注入開口4から生コンクリートを注入し、中
空PC柱部材1の内部を下から上へ向ってコンクリートが
充満しつつ、そのコンクリートがコンクリート枠19の半
分程度のレベルまで埋まったなら、コンクリートの硬化
を待ちながら、ある程度の強度、即ち中空PC柱部材1の
垂直度が維持できる段階で梁端部13aに鉄骨梁20を接続
する。
However, if the concrete is filled from the filling opening 4 and the inside of the hollow PC column member 1 is filled with concrete from the bottom to the top and the concrete is buried to about half the level of the concrete frame 19, the concrete While waiting for hardening, the steel beam 20 is connected to the beam end 13a at a stage where the strength, that is, the verticality of the hollow PC column member 1 can be maintained.

それからデッキプレート22を鉄骨梁20から梁端部13a
に渡って敷設し、このプレート22上にコンクリートを打
って床スラブ6を形成している。
Then the deck plate 22 is moved from the steel beam 20 to the beam end 13a.
And concrete is put on the plate 22 to form the floor slab 6.

次いで、同様に上階用の中空PC柱部材1を建て込ん
で、これの注入開口4からコンクリートを打設したと
き、柱・梁仕口部18の上部にもコンクリートが充満しな
がら漸次に充填コンクリート打設のレベルが上階の柱部
材内の上の方へ上昇するものである。
Next, similarly, when the hollow PC column member 1 for the upper floor is erected and concrete is poured from the pouring opening 4, the upper part of the column / beam connection portion 18 is gradually filled with concrete while filling. The level of concrete placement rises upward within the column members on the upper floor.

このようにして、順次に下の階から上の階へ施工する
ものである。
In this way, construction is performed sequentially from the lower floor to the upper floor.

《効 果》 以上、詳細に説明したように、本発明の鉄筋コンクリ
ート柱と鉄骨梁を用いた建築構法によれば、中空プレキ
ャストコンクリート柱部材に柱・梁仕口部を連結し、中
空プレキャストコンクリート柱部材の内部下方から上方
の柱・梁仕口部へ向ってコンクリートを注入充填してい
るので、コンクリートの骨材が分離することなく、均質
なコンクリートを密実に打設できるとともに、柱・梁仕
口部と柱部材との境にコンクリートを一体連続的に継目
なく打てるので、鉄筋とコンクリートとの付着強度の点
でも断層のない均一な施工品質を得る効果がある。
<Effects> As described above in detail, according to the building method using the reinforced concrete columns and the steel beams of the present invention, the hollow precast concrete columns are connected to the hollow precast concrete column members by connecting the column / beam connections. Concrete is injected and filled from the inside of the member from the lower part to the upper column / beam connection, so that concrete aggregate can be poured without separating concrete aggregate and the column / beam connection. Since concrete can be continuously and seamlessly struck at the boundary between the mouth and the column member, there is an effect of obtaining a uniform construction quality without a fault in terms of the bonding strength between the reinforcing steel and the concrete.

また、デッキプレートを使用しているので、床スラブ
を打ちながら上階へ中空PC柱部材を継ぎ、下方へ位置す
る柱・梁仕口部の方へもそのコンクリート打設領域へコ
ンクリートを充填しながら柱脚部分を打設コンクリート
で汚すことなく上階用のPC柱部材内部にコンクリートを
充填注入し、上階の柱部材と柱・梁仕口部との境目につ
いても継目のないコンクリートを形成できる効果があ
る。
In addition, since a deck plate is used, the hollow PC column member is connected to the upper floor while striking the floor slab, and concrete is filled into the concrete casting area toward the column / beam connection located below. The concrete is filled into the inside of the PC column for the upper floor without filling the column pedestal with cast concrete while forming the seamless concrete at the boundary between the column member on the upper floor and the column / beam joint. There is an effect that can be done.

しかも、柱・梁仕口部はコンクリート打設領域を形成
する部材が捨て型枠兼用のものを使用しているので、柱
と梁に関しては脱型作業が伴わず、PC柱部材だけにコン
クリートを打設して上階の施工に進捗できるので、省力
化及び工期短縮の点で極めて有利である。
Moreover, since the joints for the columns and beams use a material that also serves as a discarded formwork, the concrete forming area is not used for the columns and beams. Since it is possible to progress the construction on the upper floor by casting, it is extremely advantageous in terms of labor saving and shortening the construction period.

【図面の簡単な説明】[Brief description of the drawings]

第1図は中空プレキャストコンクリート柱部材を説明す
るための断面図、第2図(a)乃至(c)は施工の手順
を示す斜視図、第3図は別の柱・梁仕口部を使用した場
合を例示する側面図である。 1……中空プレキャストコンクリート柱部材 2……中実コンクリート柱 4……注入開口、5……口金 6……床スラブ、7……柱主筋 8……フープ筋、10……柱・梁仕口部 11……中空部分、12……縦骨 13……梁端部 14……コンクリート打設領域 15……捨て型枠、18……柱・梁仕口部 19……コンクリート枠、20……鉄骨梁 22……デッキプレート
FIG. 1 is a sectional view for explaining a hollow precast concrete column member, FIGS. 2 (a) to 2 (c) are perspective views showing a construction procedure, and FIG. 3 uses another column / beam joint. It is a side view which illustrates the case where it did. 1. Hollow precast concrete column member 2. Solid concrete column 4. Injection opening 5, ... Base 6 ... Floor slab, 7. Column main reinforcement 8. Hoop reinforcement, 10 Column / beam connection Part 11: Hollow part, 12: Vertical bone 13: Beam end 14: Concrete casting area 15: Discarded formwork, 18: Column / beam joint 19: Concrete frame, 20 ... Steel beam 22 ... Deck plate

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】建て込んだ中空プレキャストコンクリート
柱部材内に柱主筋およびフープ筋を配筋した上で、該柱
部材の上端部に該柱主筋に被せて、該柱部材の中空部に
連通する中空なコンクリート打設領域を有しかつ鉄骨梁
に接続するための梁端部を一体に構成して成る捨て型枠
兼用の柱・梁仕口部を載置し、次いで上記柱部材下部に
形成した注入開口を介して該柱部材の内部へその下方か
ら上方の該柱・梁仕口部のコンクリート打設領域の中程
まで生コンクリートを注入充填し、その後上記柱・梁仕
口部の梁端部に鉄骨梁を接続し、さらに該鉄骨梁上に上
階のデッキプレートを装着しその上にコンクリートの打
設を行って上階の床スラブを構築するとともに、上記柱
・梁仕口部上に上階の中空プレキャストコンクリート柱
部材を建て込み、柱主筋同士を接続する工程を繰り返し
て構築していくことを特徴とする鉄筋コンクリート柱と
鉄骨梁を用いた建築構法。
1. A pillar main bar and a hoop bar are arranged inside a built-in hollow precast concrete column member, and the upper end portion of the column member is covered with the column main bar to communicate with the hollow portion of the column member. A column / beam connection part having a hollow concrete casting area and integrally forming a beam end for connecting to a steel beam is also placed on the lower part of the column member. The fresh concrete is injected and filled into the interior of the pillar member from the lower part thereof to the middle of the concrete placing area of the pillar / beam connection part through the filling opening, and then the beam of the pillar / beam connection part is filled. A steel beam is connected to the end, a deck plate on the upper floor is mounted on the steel beam, concrete is poured on the steel plate to construct a floor slab on the upper floor, and the column / beam connection section A hollow precast concrete column member on the upper floor is built on top, Building construction method using reinforced concrete columns and steel beams, characterized in that by repeating the step of connecting the main reinforcement together continue to build.
JP28735090A 1990-10-26 1990-10-26 Building construction method using reinforced concrete columns and steel beams Expired - Lifetime JP2616207B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28735090A JP2616207B2 (en) 1990-10-26 1990-10-26 Building construction method using reinforced concrete columns and steel beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28735090A JP2616207B2 (en) 1990-10-26 1990-10-26 Building construction method using reinforced concrete columns and steel beams

Publications (2)

Publication Number Publication Date
JPH04161628A JPH04161628A (en) 1992-06-05
JP2616207B2 true JP2616207B2 (en) 1997-06-04

Family

ID=17716233

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28735090A Expired - Lifetime JP2616207B2 (en) 1990-10-26 1990-10-26 Building construction method using reinforced concrete columns and steel beams

Country Status (1)

Country Link
JP (1) JP2616207B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6792329B2 (en) * 2015-12-14 2020-11-25 大成建設株式会社 Construction method of column beam frame using precast concrete columns
CN107938835B (en) * 2017-06-12 2024-06-18 重庆大学 Prefabricated assembled frame adopting steel reinforced concrete column and steel beam combination

Also Published As

Publication number Publication date
JPH04161628A (en) 1992-06-05

Similar Documents

Publication Publication Date Title
JPH09209451A (en) Joint construction of up and down columns with beam and joint method
JP2616207B2 (en) Building construction method using reinforced concrete columns and steel beams
JPH04261934A (en) Building frame construction method using form member made of pre-cast concrete
JP2883898B2 (en) PC pillar and PC pillar construction method
JPH0790933A (en) Construction method of structure
JPH04222742A (en) Composite beam
JPH02300439A (en) Prefabricating method
JPH0325103A (en) Joint work for pc pillar and pc cap beam
JPH08144425A (en) Prefabricated member of mixed structure and construction method of mixed structure
JPH07324376A (en) Method for constructing reinforced concrete structure
JPH0893137A (en) Precast post serving as form and construction method therefor
JP2757032B2 (en) Construction method of underground building with pillars with capital by reverse hitting method
JPH03279533A (en) Constructing method for rigid-frame type rc super-high building
JPH02274938A (en) Combining method for src column
JPS5830459B2 (en) Construction method of precast reinforced concrete structure
JPH0453223B2 (en)
JPH02282538A (en) Construction method of reinforced concrete-made building frame
JPH02229337A (en) Constructing technique for concrete column
JPH0688342A (en) Constructing method of post
JPH09256631A (en) Construction method of building reinforced concrete wall
JPH11343665A (en) Hollow precast concrete column and construction method thereof
JPH0448134B2 (en)
JPH04216782A (en) Square silo and construction method thereof
JPH0327690B2 (en)
JPS62182329A (en) Construction of concrete structure