JPH04261934A - Building frame construction method using form member made of pre-cast concrete - Google Patents

Building frame construction method using form member made of pre-cast concrete

Info

Publication number
JPH04261934A
JPH04261934A JP4240591A JP4240591A JPH04261934A JP H04261934 A JPH04261934 A JP H04261934A JP 4240591 A JP4240591 A JP 4240591A JP 4240591 A JP4240591 A JP 4240591A JP H04261934 A JPH04261934 A JP H04261934A
Authority
JP
Japan
Prior art keywords
column
formwork
concrete
block body
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4240591A
Other languages
Japanese (ja)
Other versions
JP2586224B2 (en
Inventor
Kenzo Yoshioka
吉岡 研三
Masataka Sekine
関根 正孝
Yasuhiko Masuda
安彦 増田
Hiroya Hagio
浩也 萩尾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP3042405A priority Critical patent/JP2586224B2/en
Publication of JPH04261934A publication Critical patent/JPH04261934A/en
Application granted granted Critical
Publication of JP2586224B2 publication Critical patent/JP2586224B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To construct a reinforced concrete building high in quality. CONSTITUTION:The columnar main reinforcements 34 of a block body 3O are inserted into the hollow section S of a precast columnar form member 10 so as to be piled up together with sliced reinforcements 14. In addition, the connecting beam main reinforcements 36 of the block body 30 are piled up together with beam reinforcements 18 and 22 which are projected out of a precast beam form member 12, and the outside of the aforesaid piled-up section is covered with a steel plate form 38. Concrete is then injected into the inside of the hollow section S with pressure from an injection port located at the lower section of the precast columnar form member 10, and concrete is concurrently placed in the precast beam form member 12 and steel plate form 38.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は、プレキャストコンクリ
ート製柱型枠部材,プレキャストコンクリート製梁型枠
部材並びにプレキャストコンクリート製柱・梁仕口部ブ
ロック体を利用して施工するようにしたプレキャストコ
ンクリート製型枠部材を使用した躯体構築方法に関する
[Industrial Application Field] The present invention relates to precast concrete column formwork members, precast concrete beam formwork members, and precast concrete column/beam joint blocks that are constructed using precast concrete column formwork members and precast concrete beam formwork members. The present invention relates to a method of constructing a frame using formwork members.

【0002】0002

【従来の技術】従来では、鉄筋コンクリート建造物を構
築するにあたっては、まず柱構築用に先組みした柱鉄筋
を施工場所に取り付けると共に、この柱鉄筋を覆うよう
に柱型枠をセットし、その後柱コンクリートを打設して
柱を構築し、そしてその後半プレキャスト製の梁部材を
、構築した柱間に掛け渡すように配設し、この梁部材の
内部に梁鉄筋を設置し、その後梁コンクリートを打設す
るようにしていた。そして、このような作業を各階毎に
進めることで建造物を構築するようにしていた。殊に、
パネルゾーンにおける下階の柱鉄筋と上階の柱鉄筋相互
の接合や水平方向に交錯する梁鉄筋相互の接合は、ガス
圧接によるのが一般的であった。
[Prior Art] Conventionally, when constructing a reinforced concrete building, the pre-assembled column reinforcing bars for column construction were first attached to the construction site, a column formwork was set to cover the column reinforcing bars, and then the column Concrete is poured to construct columns, and in the second half, precast beam members are placed so as to span between the constructed columns, beam reinforcing bars are installed inside these beam members, and then beam concrete is placed. I was about to start pouring. The building was then constructed by performing such work on each floor. Especially,
Gas pressure welding was generally used to connect the column reinforcing bars on the lower floor and the column reinforcing bars on the upper floor in the panel zone, and to join the horizontally intersecting beam reinforcing bars.

【0003】0003

【発明が解決しようとする課題】しかしながら、かかる
従来の工法は、各種鉄筋相互を圧接により接合するよう
にしているため、複数の鉄筋を1本づつ圧接しなければ
ならず、この圧接作業に多大の時間を要することから工
期が長くなってしまうと共に、火気を使用することから
安全面に問題があった。また、この圧接作業に熟練を必
要とすると共に、雨中では圧接ができないことから接合
作業が天候に左右され、この点からも工期が長くかかっ
てしまう。
[Problems to be Solved by the Invention] However, in this conventional construction method, various types of reinforcing bars are joined together by pressure welding, so a plurality of reinforcing bars must be pressure welded one by one, and this pressure welding work requires a lot of effort. This lengthened the construction period, and the use of open flames posed safety concerns. In addition, this pressure welding process requires skill, and since pressure welding cannot be performed in the rain, the welding process is affected by the weather, which also lengthens the construction period.

【0004】またベニヤ板等の型枠を使用するため、廃
材が発生すると共に、型枠工も必要であった。
[0004] Furthermore, since a formwork such as a plywood board is used, waste materials are generated and formwork work is also required.

【0005】更に、柱構築に際しては、柱型枠内に上方
からコンクリートを打設するため、柱の底部から上部に
亘ってムラなくコンクリートを打設するのが困難であり
、内部にジャンカができて強度が低下してしまうという
課題があった。他方、この点に鑑みて柱部材を中実のプ
レキャストコンクリート部材で構成して品質を確保する
ことも考えられるが、現場施工において大型の揚重機等
が必要となり、好ましいものではなかった。
Furthermore, when constructing columns, since concrete is poured into the column formwork from above, it is difficult to pour concrete evenly from the bottom to the top of the column, and junkers may form inside the column. However, there was a problem in that the strength decreased. On the other hand, in view of this point, it is conceivable to construct the column members with solid precast concrete members to ensure quality, but this is not preferable because it requires a large lifting machine etc. for on-site construction.

【0006】そこで、本発明はかかる従来の課題に鑑み
て、効率良く、且つ高品質な鉄筋コンクリート建造物を
構築することができるプレキャストコンクリート製型枠
部材を使用した躯体構築方法を提供することを目的とす
る。
[0006] In view of such conventional problems, the present invention aims to provide a method of constructing a frame using precast concrete formwork members, which can efficiently construct a high-quality reinforced concrete building. shall be.

【0007】[0007]

【課題を解決するための手段】かかる目的を達成するた
めに本発明は、中空筒体状に形成され、肉厚部に添え筋
及びフープ筋が埋設されると共に下端部にコンクリート
注入口が形成されたプレキャストコンクリート製柱型枠
部材と、上方が開放された断面U字形状に形成され、柱
・梁仕口部へ突出される梁主筋が肉厚部に埋設されたプ
レキャストコンクリート製梁型枠部材と、上記柱型枠部
材の中空部に挿入される柱主筋及び上記梁型枠部材のU
字溝へ挿入される接続梁主筋とを有するプレキャストコ
ンクリート製柱・梁仕口部ブロック体とを予め製造し、
次いで、既設の柱主筋に被せて上記柱型枠部材を建て込
み、次いで、上記ブロック体を、その柱主筋を上記既設
の柱主筋に突き合わせるように上記柱型枠部材の中空部
に挿入しつつ、該柱型枠部材の上部に載置し、次いで、
上記ブロック体の側方に、その接続梁主筋に梁主筋を重
ね合わせつつ上記梁型枠部材を配設し、次いで、該梁型
枠部材と上記ブロック体との間に捨て型枠を配設し、そ
の後、上記柱型枠部材の注入口からその中空部にコンク
リートを圧入すると共に、上記梁型枠部材及び捨て型枠
内にコンクリートを打設することを特徴とする。
[Means for Solving the Problems] In order to achieve the above object, the present invention is formed into a hollow cylindrical body, in which splice reinforcements and hoop reinforcements are embedded in the thick part, and a concrete injection port is formed in the lower end. precast concrete column formwork members, and precast concrete beam formworks with a U-shaped cross section that is open at the top, and where beam main reinforcements that protrude toward the column/beam joint are buried in the thick part. member, a column main reinforcement inserted into the hollow part of the column formwork member, and the U of the beam formwork member.
A precast concrete column/beam joint block body having a connecting beam main reinforcement inserted into the groove is manufactured in advance,
Next, the column form frame member is built over the existing column main reinforcement, and then the block body is inserted into the hollow part of the column form frame member so that the column main reinforcement butts against the existing column main reinforcement. while placing it on the top of the column frame member, and then
The beam form member is arranged on the side of the block body, with the main beam reinforcement overlapping the connecting beam main reinforcement, and then the sacrificial formwork is arranged between the beam form member and the block body. Then, concrete is press-fitted into the hollow portion of the column formwork member through the injection port thereof, and concrete is poured into the beam formwork member and the sacrificial formwork.

【0008】また本発明は、上記プレキャストコンクリ
ート製柱・梁仕口部ブロック体が、上記接続梁主筋に替
えて、上記梁型枠部材のU字溝へ挿入される鉄骨材を備
えていることを特徴とする。
[0008] The present invention also provides that the precast concrete column/beam joint block body includes a steel frame material inserted into the U-shaped groove of the beam form member in place of the connecting beam main reinforcement. It is characterized by

【0009】さらに本発明は、上記捨て型枠が鋼板材で
形成されていることを特徴とする。
Further, the present invention is characterized in that the above-mentioned disposable formwork is formed of a steel plate material.

【0010】0010

【作用】本発明の作用について述べると、鉄筋コンクリ
ート建造物を構成する柱,梁及び柱・梁仕口部分を構成
する部材を、そのまま構造材として適用できるプレキャ
ストコンクリート製の型枠部材及びプレキャストコンク
リート製のユニットとして予め工場生産等するようにし
、これらを施工現場に搬入して構築作業を行えるように
したので、効率良く施工することができる。殊に、ベニ
ヤ板で型枠を構築する場合のように廃材が発生しないと
共に、型枠工を必要としないので、省資源,省力化を達
成することができ、かつまた脱型作業を省略することも
できる。また、外形の大きな柱型枠部材や梁型枠部材は
ほぼ半プレキャスト部材で軽量であるので、施工現場で
のこれら部材の搬入や建込みに際して大能力の揚重機等
を必要とすることもない。
[Function] Describing the function of the present invention, precast concrete formwork members and precast concrete formwork members can be used as structural materials for columns, beams, and pillar/beam joints that make up reinforced concrete buildings. Since these units are pre-produced in a factory and transported to the construction site for construction work, construction can be carried out efficiently. In particular, unlike when constructing a formwork using plywood, no waste material is generated and there is no need for formwork, so resource and labor savings can be achieved, and demolding work can be omitted. You can also do it. In addition, large-sized column formwork members and beam formwork members are almost semi-precast and lightweight, so there is no need for large-capacity lifting equipment when transporting and erecting these members at the construction site. .

【0011】また、鉄筋相互の接合に関しても、柱主筋
については、柱型枠部材に添え筋を埋設してこの添え筋
と柱主筋とで重ね継手構造を構成させるようにしたので
、柱主筋相互間の応力伝達をこの重ね継手構造によるこ
とができ、従ってこれら柱主筋相互間の接合を、単なる
突き合わせ構造とすることができる。そしてこのような
構成により、圧接接合部分を削減して効率良く短期に施
工を完了することができる。また、火気を使用する箇所
を削減できて安全であると共に、天候の影響を受けるこ
とも少なくなる。
[0011] Also, regarding the connection of the reinforcing bars to each other, for the main column reinforcements, the splice reinforcements are embedded in the column form frame members and the splint reinforcements and the main column reinforcements form a lap joint structure. Stress transmission between the pillars can be achieved by this lap joint structure, and therefore the joints between these column main reinforcements can be made into a mere butt structure. With this configuration, the number of press-welded parts can be reduced and construction can be completed efficiently and in a short period of time. In addition, it is safer because the number of places where fire is used can be reduced, and it is less affected by the weather.

【0012】また、柱型枠部材へのコンクリートの打設
は、柱型枠部材の下端部に形成した注入口からコンクリ
ートを圧入するようにしたため、柱型枠部材の中空部に
コンクリートをムラなく充填することができ、ジャンカ
ができるのを防止して構造材としての強度を十分に確保
することができる。
[0012] Furthermore, when pouring concrete into the column formwork members, the concrete is press-fitted from the injection hole formed at the lower end of the column formwork members, so that the concrete is evenly poured into the hollow parts of the column formwork members. It is possible to prevent the formation of junkers and ensure sufficient strength as a structural material.

【0013】さらに、本発明によって構築される建造物
は所謂ラーメン構造であり、この場合、地震等の短期応
力は梁の両端部に大きく加わることになるが、この梁の
両端部とブロック体との接続に鉄骨材を採用したので、
このような短期応力に対して優れた耐力を発揮させるこ
とができる。
Furthermore, the building constructed according to the present invention has a so-called rigid-frame structure, and in this case, short-term stresses such as those caused by earthquakes are largely applied to both ends of the beam. Since we adopted steel frame materials for the connections,
Excellent yield strength can be exhibited against such short-term stress.

【0014】また、ブロック体と梁型枠部材との間に配
設すべき型枠を捨て型枠とすることにより、脱型作業を
廃止して施工効率を向上させることができると共に、殊
に捨て型枠として鋼板材を採用しているので、上述した
短期応力、ひいては構造強度を十分強固なものとするこ
とができる。
[0014] Furthermore, by using a disposable formwork as the formwork to be placed between the block body and the beam formwork member, demolding work can be abolished and construction efficiency can be improved, and in particular, Since a steel plate material is used as the sacrificial formwork, the above-mentioned short-term stress and, as a result, the structural strength can be made sufficiently strong.

【0015】[0015]

【実施例】以下、本発明の実施例を図に基づいて詳細に
説明する。即ち、図1から図5は本発明にかかる躯体構
築方法の一実施例を示し、図1は本発明にかかる構築工
程を示す説明図、図2は柱と柱梁仕口部との接続状態を
示す拡大断面図、図3は図1中B−B線からの拡大断面
図、図4は図1中A−A線からの拡大断面図、図5は柱
梁仕口部の拡大斜視図である。
Embodiments Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. That is, FIGS. 1 to 5 show an example of the method for constructing a frame according to the present invention, FIG. 1 is an explanatory diagram showing the construction process according to the present invention, and FIG. 2 shows a state of connection between columns and beam joints. 3 is an enlarged sectional view taken from line B-B in FIG. 1, FIG. 4 is an enlarged sectional view taken from line AA in FIG. 1, and FIG. 5 is an enlarged perspective view of the column and beam joints. It is.

【0016】図1はプレキャストコンクリート(以下、
略してPCと称する。)製柱型枠部材10とPC製梁型
枠部材12とPC製柱・梁仕口部ブロック体30との建
て込み工程を示す。前記PC製柱型枠部材10は、図2
及び図3に示すように例えば、遠心成形法により断面が
矩形状の中空筒体として製作し、その肉厚内には、長さ
方向に配置される複数の添え筋14、および、この添え
筋14の外側を囲って長さ方向に等間隔に配置される複
数のフープ筋16を埋設してある。また、前記PC製柱
型枠部材10の下部側面には、コンクリートの注入口1
7を形成してある。
FIG. 1 shows precast concrete (hereinafter referred to as
It is abbreviated as PC. ) The construction process of the column formwork member 10, the PC beam formwork member 12, and the PC column/beam joint block body 30 is shown. The PC column frame member 10 is shown in FIG.
As shown in FIG. 3, for example, a hollow cylinder with a rectangular cross section is manufactured by centrifugal molding, and within its wall thickness are a plurality of splints 14 arranged in the length direction, and a plurality of splints 14 disposed in the length direction. A plurality of hoop muscles 16 are embedded around the outside of the hoop 14 and arranged at equal intervals in the length direction. In addition, a concrete injection port 1 is provided on the lower side of the PC column form member 10.
7 is formed.

【0017】また、前記PC製梁型枠部材12は、例え
ば、遠心成形型枠装置を用いて製作したものを用いる。 このPC製梁型枠部材12は図4に示すように、上方が
開放された断面U字状に形成され、その長さは掛け渡そ
うとする一対の柱間のスパンより短く形成してある。前
記PC製梁型枠部材12の肉厚内には、複数の下部梁主
筋18を長さ方向に埋設すると共に、複数のスターラッ
プ20を、その上端部を肉厚部分から上方に一部突出し
て埋設する。また、前記PC製梁型枠部材12の上側に
は、前記スターラップ20の内側に接して上部梁主筋2
2を配置し、これら上部梁主筋22および下部梁主筋1
8をPC製梁型枠部材12の両端から突出する。尚、こ
の上部梁主筋22は、PC製梁型枠部材12の成形後に
、現場において取り付けるようにしてもよい。
Furthermore, the PC beam form member 12 is manufactured using, for example, a centrifugal forming form apparatus. As shown in Fig. 4, this PC beam form member 12 is formed into a U-shaped cross section with an open upper part, and its length is made shorter than the span between the pair of columns to be spanned. . A plurality of lower beam main reinforcements 18 are buried in the length direction within the wall thickness of the PC beam form member 12, and a plurality of stirrups 20 are partially protruded upward from the thick wall portion at their upper ends. and bury it. Further, on the upper side of the PC beam form member 12, an upper beam main reinforcement 2 is provided in contact with the inner side of the stirrup 20.
2, and these upper beam main reinforcements 22 and lower beam main reinforcements 1
8 project from both ends of the PC beam form member 12. Incidentally, the upper beam main reinforcing bars 22 may be attached at the site after the PC beam form member 12 is formed.

【0018】そして、前記PC製柱型枠部材10および
PC製梁型枠部材12は、工場等で予め製作したものを
現場に搬入し、クレーン等で吊り下げて建て込む。まず
、前記PC製柱型枠部材10を建て込むが、この建て込
み位置には床スラブ24から複数の柱主筋26が立設さ
れており、この既設の柱主筋26の外側に被せてPC製
柱型枠部材10を建て込む。尚、前記床スラブ24から
立設した柱主筋26の長さは、PC製柱型枠部材10の
長さのおおよそ半分として形成してある。また、前記P
C製柱型枠部材10の建て込みでは一般に行われるよう
に、最後のコンクリート打設工程が完了してこれが硬化
するまで、このPC製柱型枠部材10は図外の支保工等
の支持部材により保持される。
The PC column frame member 10 and the PC beam frame member 12 are manufactured in advance at a factory or the like, and then transported to the site and suspended using a crane or the like to be erected. First, the PC column form frame member 10 is erected. At this erecting position, a plurality of column main reinforcements 26 are erected from the floor slab 24. The column frame member 10 is erected. The length of the column main reinforcing bars 26 erected from the floor slab 24 is approximately half the length of the PC column frame member 10. In addition, the P
As is generally done when constructing the C column form member 10, the PC column form member 10 is used as a supporting member such as a shoring (not shown) until the final concrete pouring process is completed and the concrete hardens. is maintained by

【0019】さらに、ブロック体30は図5に示すよう
に、コンクリートブロック32に、上下方向に突出して
PC製柱型枠部材10の中空部Sに挿入される複数の柱
主筋34、および梁の配置方向に突出してPC製梁型枠
部材12のU字溝へ挿入される複数の接続梁主筋36を
打ち込むことにより構成する。このブロック体30も予
め工場等で製作したものを用いる。
Furthermore, as shown in FIG. 5, the block body 30 includes a plurality of column main reinforcements 34 that protrude vertically from the concrete block 32 and are inserted into the hollow portion S of the PC column form member 10, and a beam. It is constructed by driving a plurality of connection beam main reinforcements 36 that protrude in the arrangement direction and are inserted into the U-shaped groove of the PC beam form member 12. This block body 30 is also manufactured in advance at a factory or the like.

【0020】そして、前記ブロック体30はクレーン等
で吊り下げて、柱主筋34の下部34aをPC製柱型枠
部材10の中空部S内に上方から挿入し、この柱主筋下
部34aとPC製柱型枠部材10内に埋設した添え筋1
4とを互いに重合するように、ブロック体30をPC製
柱型枠部材10の上部に載置する。尚、前記柱主筋34
の下部34aおよび上部34bの突出量は、それぞれP
C製柱型枠部材10の半分の長さに形成してあり、前記
柱主筋下部34aを前記中空部S内に挿入した際、この
柱主筋下部34aは床スラブ24から立設する柱主筋2
6と突き合わせ関係に配置される。
Then, the block body 30 is suspended by a crane or the like, and the lower part 34a of the column main reinforcement 34 is inserted into the hollow part S of the PC column form member 10 from above, and this column main reinforcement lower part 34a and the PC Splinter reinforcement 1 embedded in column formwork member 10
The block body 30 is placed on the top of the PC column frame member 10 so that the blocks 4 and 4 overlap each other. In addition, the column main reinforcement 34
The protrusion amounts of the lower part 34a and the upper part 34b are respectively P
It is formed to have half the length of the column form frame member 10 made of C, and when the column main reinforcement lower part 34a is inserted into the hollow part S, the column main reinforcement lower part 34a is connected to the column main reinforcement 2 that is erected from the floor slab 24.
It is placed in butt relation with 6.

【0021】一方、前記PC製梁型枠部材12を一対の
前記PC製柱型枠部材10間に配置し、支保工Hを用い
てブロック体30の側方に配設する。このとき、PC製
梁型枠部材12とPC製柱型枠部材10との間には間隔
Lが設けられ、この間隔LにはPC製梁型枠部材12か
ら突出した上部,下部梁主筋22,18が露出される。 尚、PC製梁型枠部材12から突出したそれぞれの梁主
筋22,18には、これらを囲ってスパイラル筋28を
巻回してあり、このPC製梁型枠部材12の配設時には
、このスパイラル筋28を、突出したそれぞれの梁主筋
22,18の基部側に束ねてある。
On the other hand, the PC beam form member 12 is placed between the pair of PC column form members 10, and is placed on the side of the block body 30 using the shoring H. At this time, a gap L is provided between the PC beam form member 12 and the PC column form member 10, and this gap L includes the upper and lower beam main bars 22 protruding from the PC beam form member 12. , 18 are exposed. Incidentally, each of the beam main reinforcements 22 and 18 protruding from the PC beam form member 12 has a spiral reinforcement 28 wound around them, and when this PC beam form member 12 is installed, this spiral The reinforcements 28 are bundled at the base side of each of the protruding beam main reinforcements 22, 18.

【0022】そしてこのようなPC製梁型枠部材12の
配設に際しては、前記ブロック体30の接続梁主筋36
は、前記PC製梁部材12から突出する下部,上部梁主
筋18,22に重合され、このように接続梁主筋36と
梁主筋18,22とを重合した段階でスパイラル筋28
を引き伸ばして、この重合部分全体を略均一に覆う。そ
して、PC製梁型枠部材12とブロック体30との間の
、この重合部分の外側に前記PC製梁型枠部材12の外
側形状に沿った捨て型枠としての鋼板型枠38を設置す
る。
When installing such a PC beam formwork member 12, the connection beam main reinforcement 36 of the block body 30 is
are superimposed on the lower and upper beam main reinforcements 18 and 22 protruding from the PC beam member 12, and at the stage where the connecting beam main reinforcements 36 and the beam main reinforcements 18 and 22 are superposed in this way, the spiral reinforcements 28
is stretched to almost uniformly cover the entire polymerized area. Then, a steel plate formwork 38 is installed as a waste formwork along the outer shape of the PC beam form member 12 on the outside of this overlapping portion between the PC beam form member 12 and the block body 30. .

【0023】このように、PC製柱型枠部材10,PC
製梁型枠部材12,PC製ブロック体30および鋼板型
枠38を設置した状態で、PC製柱型枠部材10の下端
部に形成した注入口17に図外のコンクリートポンプを
接続し、この注入口17からPC製柱型枠部材10の中
空部S内にコンクリートを圧入により注入する。また、
前記PC製梁型枠部材12内および前記鋼板型枠38内
に、上方の開放部からコンクリートを打設する。
[0023] In this way, the PC column frame member 10, PC
With the beam formwork member 12, PC block body 30, and steel plate formwork 38 installed, a concrete pump (not shown) is connected to the injection port 17 formed at the lower end of the PC column formwork member 10. Concrete is injected into the hollow part S of the PC column form member 10 through the injection port 17 by press-fitting. Also,
Concrete is poured into the PC beam form member 12 and the steel plate form 38 from the upper opening.

【0024】従って、前記PC製柱型枠部材10内に注
入したコンクリートが硬化することにより、互いに重合
した柱主筋下部34aと添え筋14とは重ね継手を構成
し、また同様に、添え筋14と床スラブ24から立設し
た柱主筋26とは重ね継手を構成する。このため、この
柱主筋26と前記柱主筋下部34aとは、それぞれ重ね
継手を介して強固に結合することができる。
Therefore, as the concrete poured into the PC column form member 10 hardens, the column main reinforcement lower part 34a and the splint reinforcement 14 overlap each other and form a lap joint, and similarly, the splint reinforcement 14 and the column main reinforcing bars 26 erected from the floor slab 24 constitute a lap joint. Therefore, the column main reinforcement 26 and the column main reinforcement lower part 34a can be firmly connected via lap joints.

【0025】一方、前記鋼板型枠38に打設したコンク
リートが硬化することにより、互いに重合した梁主筋下
部,上部18,22と接続梁主筋36とは重ね継手を構
成し、梁40となるPC製梁型枠部材12と前記ブロッ
ク体30との結合を強固にし、延いては、この梁40を
柱50となるPC製柱型枠部材10に確実に結合するこ
とができる。その後、床スラブ24の型枠を敷いてスラ
ブ配筋をし、その上にスラブコンクリートを打設する。 従って、前記ブロック体30の柱主筋34の上部34b
は床スラブ24から立設することになり、この柱主筋3
4bにPC製柱型枠部材10を被せることにより、上方
階の柱の建て込みが行われる。そして、前記各工程を施
工していくことにより順次上層階の構築を行うことがで
きる。
On the other hand, as the concrete poured into the steel plate formwork 38 hardens, the lower and upper beam main reinforcements 18 and 22 and the connecting beam main reinforcement 36, which overlap with each other, form a lap joint, and the PC which becomes the beam 40 is formed. The connection between the beam form member 12 and the block body 30 is strengthened, and in turn, the beam 40 can be reliably connected to the PC column form member 10 that becomes the column 50. Thereafter, a formwork for the floor slab 24 is laid, slab reinforcement is placed, and slab concrete is placed on top of it. Therefore, the upper part 34b of the column main reinforcement 34 of the block body 30
will be erected from the floor slab 24, and this column main reinforcement 3
By covering 4b with the PC column frame member 10, the columns of the upper floor are built. Then, by carrying out each of the above steps, the upper floors can be constructed in sequence.

【0026】従って、本実施例にあっては、鉄筋コンク
リート建造物を構成する柱,梁及び柱・梁仕口部分を構
成する部材を、そのまま構造材として適用できるプレキ
ャストコンクリート製の型枠部材10,12及びプレキ
ャストコンクリート製のユニット30として予め工場生
産等するようにし、これらを施工現場に搬入して構築作
業を行えるようにしたので、効率良く施工することがで
きる。殊に、ベニヤ板で型枠を構築する場合のように廃
材が発生しないと共に、型枠工を必要としないので、省
資源,省力化を達成することができ、かつまた脱型作業
を省略することもできる。また、外形の大きな柱型枠部
材10や梁型枠部材12はほぼ半プレキャスト部材で軽
量であるので、施工現場でのこれら部材の搬入や建込み
に際して大能力の揚重機等を必要とすることもない。
Therefore, in this embodiment, the precast concrete formwork members 10, which can be used as structural members as they are, are used as members that make up columns, beams, and column/beam joints that make up a reinforced concrete building. 12 and precast concrete units 30 are manufactured in advance at a factory, and these can be transported to the construction site for construction work, so construction can be carried out efficiently. In particular, unlike when constructing a formwork using plywood, no waste material is generated and there is no need for formwork, so resource and labor savings can be achieved, and demolding work can be omitted. You can also do it. In addition, since the column formwork members 10 and the beam formwork members 12, which have large external dimensions, are almost semi-precast members and are lightweight, a large-capacity lifting machine or the like is required when transporting and erecting these members at the construction site. Nor.

【0027】また、鉄筋相互の接合に関しても、柱主筋
34については、柱型枠部材10に添え筋14を埋設し
てこの添え筋14と柱主筋34とで重ね継手構造を構成
させるようにしたので、柱主筋26,34相互間の応力
伝達をこの重ね継手構造によることができ、従ってこれ
ら柱主筋26,34相互間の接合を、単なる突き合わせ
構造とすることができる。そしてこのような構成により
、圧接接合部分を削減して効率良く短期に施工を完了す
ることができる。また、火気を使用する箇所を削減でき
て安全であると共に、天候の影響を受けることも少なく
なる。
[0027] Also, regarding the mutual connection of reinforcing bars, for the column main reinforcements 34, splice reinforcements 14 are embedded in the column form frame member 10, and the splint reinforcements 14 and the column main reinforcements 34 constitute a lap joint structure. Therefore, the stress transmission between the column main reinforcements 26 and 34 can be achieved by this lap joint structure, and therefore the connection between the column main reinforcements 26 and 34 can be made into a mere butt structure. With this configuration, the number of press-welded parts can be reduced and construction can be completed efficiently and in a short period of time. In addition, it is safer because the number of places where fire is used can be reduced, and it is less affected by the weather.

【0028】また、柱型枠部材10へのコンクリートの
打設は、柱型枠部材10の下端部に形成した注入口17
からコンクリートを圧入するようにしたため、柱型枠部
材10の中空部Sにコンクリートをムラなく充填するこ
とができ、ジャンカができるのを防止して構造材として
の強度を十分に確保することができる。
Concrete is poured into the column form member 10 through an injection port 17 formed at the lower end of the column form member 10.
Since the concrete is press-fitted from the column frame member 10, the hollow part S of the column formwork member 10 can be evenly filled with concrete, and the formation of junkers can be prevented and sufficient strength as a structural material can be ensured. .

【0029】また、ブロック体30と梁型枠部材12と
の間に配設すべき型枠を捨て型枠としたので、脱型作業
を廃止して施工効率を向上させることができると共に、
殊に捨て型枠として鋼板材を採用しているので、上述し
た短期応力、ひいては構造強度を十分強固なものとする
ことができる。
Furthermore, since the formwork to be disposed between the block body 30 and the beam formwork member 12 is a waste formwork, demolding work can be abolished and construction efficiency can be improved.
In particular, since a steel plate material is used as the sacrificial formwork, the above-mentioned short-term stress and, as a result, the structural strength can be made sufficiently strong.

【0030】ところで、前記ブロック体30は接続梁主
筋36として棒状の鉄筋を用いた鉄筋コンクリートブロ
ックとして形成したものを開示したが、これに限ること
なく図6に示すように鉄骨材42を用いた鉄骨鉄筋コン
クリートブロックとして形成したものを用いることがで
きる。このようにすれば、本実施例によって構築される
建造物は所謂ラーメン構造であって地震等の短期応力は
梁40の両端部に大きく加わることになるが、この梁4
0の両端部とブロック体30との接続に鉄骨材42を採
用したので、このような短期応力に対して優れた耐力を
発揮させることができる。
By the way, the block body 30 has been disclosed as being formed as a reinforced concrete block using rod-shaped reinforcing bars as the connecting beam main reinforcements 36, but the present invention is not limited to this, and as shown in FIG. Those formed as reinforced concrete blocks can be used. In this way, the building constructed according to this embodiment has a so-called rigid-frame structure, and short-term stresses such as those caused by earthquakes are largely applied to both ends of the beam 40.
Since the steel frame material 42 is used to connect both ends of the block body 30 to the block body 30, it is possible to exhibit excellent resistance against such short-term stress.

【0031】[0031]

【発明の効果】以上要するに本発明にあっては、次のよ
うな優れた効果を発揮する。 (1)鉄筋コンクリート建造物を構成する柱,梁及び柱
・梁仕口部分を構成する部材を、そのまま構造材として
適用できるプレキャストコンクリート製の型枠部材及び
プレキャストコンクリート製のユニットとして予め工場
生産等するようにし、これらを施工現場に搬入して構築
作業を行えるようにしたので、効率良く施工することが
できる。殊に、ベニヤ板で型枠を構築する場合のように
廃材が発生しないと共に、型枠工を必要としないので、
省資源,省力化を達成することができ、かつまた脱型作
業を省略することもできる。また、外形の大きな柱型枠
部材や梁型枠部材はほぼ半プレキャスト部材で軽量であ
るので、施工現場でのこれら部材の搬入や建込みに際し
て大能力の揚重機等を必要とすることもない。 (2)また、鉄筋相互の接合に関しても、柱主筋につい
ては、柱型枠部材に添え筋を埋設してこの添え筋と柱主
筋とで重ね継手構造を構成させるようにしたので、柱主
筋相互間の応力伝達をこの重ね継手構造によることがで
き、従ってこれら柱主筋相互間の接合を、単なる突き合
わせ構造とすることができる。そしてこのような構成に
より、圧接接合部分を削減して効率良く短期に施工を完
了することができる。また、火気を使用する箇所を削減
できて安全であると共に、天候の影響を受けることも少
なくなる。 (3)また、柱型枠部材へのコンクリートの打設は、柱
型枠部材の下端部に形成した注入口からコンクリートを
圧入するようにしたため、柱型枠部材の中空部にコンク
リートをムラなく充填することができ、ジャンカができ
るのを防止して構造材としての強度を十分に確保するこ
とができる。 (4)さらに、本発明によって構築される建造物は所謂
ラーメン構造であり、この場合、地震等の短期応力は梁
の両端部に大きく加わることになるが、この梁の両端部
とブロック体との接続に鉄骨材を採用したので、このよ
うな短期応力に対して優れた耐力を発揮させることがで
きる。 (5)また、ブロック体と梁型枠部材との間に配設すべ
き型枠を捨て型枠としたので、脱型作業を廃止して施工
効率を向上させることができると共に、殊に捨て型枠と
して鋼板材を採用しているので、上述した短期応力、ひ
いては構造強度を十分強固なものとすることができる。
[Effects of the Invention] In summary, the present invention exhibits the following excellent effects. (1) Columns, beams, and members constituting the column/beam joints that make up a reinforced concrete building are manufactured in advance in a factory as precast concrete formwork members and precast concrete units that can be used as structural materials as they are. Since these items can be transported to the construction site and construction work can be carried out, construction can be carried out efficiently. In particular, unlike when constructing formwork with plywood, no waste material is generated, and no formwork is required.
Resource and labor savings can be achieved, and demolding work can also be omitted. In addition, large-sized column formwork members and beam formwork members are almost semi-precast and lightweight, so there is no need for large-capacity lifting equipment when transporting and erecting these members at the construction site. . (2) Also, regarding the connection of reinforcing bars to each other, for the main column reinforcements, we have embedded splint reinforcements in the column form frame members and configured a lap joint structure with the splint reinforcements and the main column reinforcements. Stress transmission between the pillars can be achieved by this lap joint structure, and therefore the joints between these column main reinforcements can be made into a mere butt structure. With this configuration, the number of press-welded parts can be reduced and construction can be completed efficiently and in a short period of time. In addition, it is safer because the number of places where fire is used can be reduced, and it is less affected by the weather. (3) In addition, when pouring concrete into the column formwork, the concrete is press-fitted through the injection hole formed at the bottom end of the column formwork, so that the concrete is evenly poured into the hollow part of the column formwork. It is possible to prevent the formation of junkers and ensure sufficient strength as a structural material. (4) Furthermore, the building constructed according to the present invention is a so-called rigid-frame structure, and in this case, short-term stress such as an earthquake will be applied to both ends of the beam, but the structure between both ends of the beam and the block body will be large. Since steel frames are used for the connections, it can exhibit excellent resistance to such short-term stress. (5) In addition, since the formwork to be installed between the block body and the beam formwork member is a waste formwork, it is possible to eliminate demolding work and improve construction efficiency. Since a steel plate material is used as the formwork, the above-mentioned short-term stress and, as a result, the structural strength can be made sufficiently strong.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】本発明工程の一実施例を示す説明図である。FIG. 1 is an explanatory diagram showing one embodiment of the process of the present invention.

【図2】本発明において、柱型枠部材とブロック体との
接続状態を示す拡大断面図である。
FIG. 2 is an enlarged sectional view showing a connection state between a column frame member and a block body in the present invention.

【図3】図1中のB−B線からの拡大断面図である。3 is an enlarged sectional view taken along line BB in FIG. 1. FIG.

【図4】図1中のA−A線からの拡大断面図である。4 is an enlarged sectional view taken along line AA in FIG. 1. FIG.

【図5】本発明に用いられるブロック体の拡大斜視図で
ある。
FIG. 5 is an enlarged perspective view of a block body used in the present invention.

【図6】本発明の他の実施例を示すブロック体の正面図
である。
FIG. 6 is a front view of a block body showing another embodiment of the present invention.

【符号の説明】[Explanation of symbols]

10  プレキャストコンクリート製柱型枠部材12 
 プレキャストコンクリート製梁型枠部材14  添え
筋                        
17  注入口18  下部梁主筋         
           20  スターラップ 22  上部梁主筋                
    24  床スラブ26  柱主筋      
                  30  ブロッ
ク体 34  柱主筋                  
      34a  柱主筋下部 34b  柱主筋上部               
   36  接続梁主筋
10 Precast concrete column formwork member 12
Precast concrete beam formwork member 14 Splice reinforcement
17 Inlet 18 Lower beam main reinforcement
20 Stirrup 22 Upper beam main reinforcement
24 Floor slab 26 Column main reinforcement
30 Block body 34 Column main reinforcement
34a Lower column main reinforcement 34b Upper column main reinforcement
36 Connecting beam main reinforcement

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】  中空筒体状に形成され、肉厚部に添え
筋及びフープ筋が埋設されると共に下端部にコンクリー
ト注入口が形成されたプレキャストコンクリート製柱型
枠部材と、上方が開放された断面U字形状に形成され、
柱・梁仕口部へ突出される梁主筋が肉厚部に埋設された
プレキャストコンクリート製梁型枠部材と、上記柱型枠
部材の中空部に挿入される柱主筋及び上記梁型枠部材の
U字溝へ挿入される接続梁主筋とを有するプレキャスト
コンクリート製柱・梁仕口部ブロック体とを予め製造し
、次いで、既設の柱主筋に被せて上記柱型枠部材を建て
込み、次いで、上記ブロック体を、その柱主筋を上記既
設の柱主筋に突き合わせるように上記柱型枠部材の中空
部に挿入しつつ、該柱型枠部材の上部に載置し、次いで
、上記ブロック体の側方に、その接続梁主筋に梁主筋を
重ね合わせつつ上記梁型枠部材を配設し、次いで、該梁
型枠部材と上記ブロック体との間に捨て型枠を配設し、
その後、上記柱型枠部材の注入口からその中空部にコン
クリートを圧入すると共に、上記梁型枠部材及び捨て型
枠内にコンクリートを打設する、ことを特徴とするプレ
キャストコンクリート製型枠部材を使用した躯体構築方
法。
Claim 1: A precast concrete column formwork member formed into a hollow cylindrical shape, with splint reinforcements and hoop reinforcements embedded in the thick wall part, and a concrete injection port formed in the lower end, and an open upper part. It is formed into a U-shaped cross section,
A precast concrete beam formwork member in which the main beam reinforcement that protrudes to the column/beam joint part is buried in the thick part, and the main column reinforcement and the beam formwork member that are inserted into the hollow part of the column formwork member. A precast concrete column/beam joint block body having a connecting beam main reinforcement to be inserted into the U-shaped groove is manufactured in advance, and then the column form frame member is erected by covering the existing column main reinforcement, and then, The block body is inserted into the hollow part of the column form member so that its main column reinforcement butts against the existing column main reinforcement, and is placed on top of the column form member, and then the block body is placed on top of the column form member. Laterally, the beam form member is arranged while superimposing the beam main reinforcement on the connecting beam main reinforcement, and then a sacrificial form is arranged between the beam form member and the block body,
Thereafter, concrete is press-fitted into the hollow part of the column formwork member through the injection port, and concrete is poured into the beam formwork member and the sacrificial formwork. The framework construction method used.
【請求項2】  上記プレキャストコンクリート製柱・
梁仕口部ブロック体が、上記接続梁主筋に替えて、上記
梁型枠部材のU字溝へ挿入される鉄骨材を備えているこ
とを特徴とする請求項1記載のプレキャストコンクリー
ト製型枠部材を使用した躯体構築方法。
[Claim 2] The above precast concrete pillar/
The precast concrete formwork according to claim 1, wherein the beam joint block body includes a steel frame material inserted into the U-shaped groove of the beam formwork member in place of the connection beam main reinforcement. A method of building a frame using members.
【請求項3】  上記捨て型枠が鋼板材で形成されてい
ることを特徴とする請求項1または2いずれかの項に記
載のプレキャストコンクリート製型枠部材を使用した躯
体構築方法。
3. The method of constructing a frame using a precast concrete formwork member according to claim 1 or 2, wherein the sacrificial formwork is made of a steel plate material.
JP3042405A 1991-02-15 1991-02-15 Building method using precast concrete formwork Expired - Lifetime JP2586224B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3042405A JP2586224B2 (en) 1991-02-15 1991-02-15 Building method using precast concrete formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3042405A JP2586224B2 (en) 1991-02-15 1991-02-15 Building method using precast concrete formwork

Publications (2)

Publication Number Publication Date
JPH04261934A true JPH04261934A (en) 1992-09-17
JP2586224B2 JP2586224B2 (en) 1997-02-26

Family

ID=12635162

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3042405A Expired - Lifetime JP2586224B2 (en) 1991-02-15 1991-02-15 Building method using precast concrete formwork

Country Status (1)

Country Link
JP (1) JP2586224B2 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003166286A (en) * 2001-11-29 2003-06-13 Isobe Miho Building skeleton construction method
JP2007132158A (en) * 2005-11-14 2007-05-31 Shimizu Corp Joint structure of column main reinforcement
JP2009144399A (en) * 2007-12-13 2009-07-02 Ohbayashi Corp Connection method for prestressed concrete member and reinforced concrete building
JP2011080358A (en) * 2011-01-05 2011-04-21 Sumitomo Mitsui Construction Co Ltd Column-beam joint structure of building, building, and joining method
JP2014055517A (en) * 2013-12-25 2014-03-27 Takenaka Komuten Co Ltd Precast beam-column joint structure
CN104631619A (en) * 2014-12-19 2015-05-20 东南大学 U-shaped steel vertical connection assembled integral type frame and construction method thereof
CN104727440A (en) * 2014-11-17 2015-06-24 马恒忠 Novel industrialized production efficiently-assembled type building frame column beam and manufacturing method
CN106499053A (en) * 2016-11-30 2017-03-15 东北林业大学 A kind of assembled integral pre-stressed concrete frame structure connection member

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1674410B1 (en) 2003-10-16 2017-04-05 Kyoritsu Seiyaku Corporation Trash can

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003166286A (en) * 2001-11-29 2003-06-13 Isobe Miho Building skeleton construction method
JP2007132158A (en) * 2005-11-14 2007-05-31 Shimizu Corp Joint structure of column main reinforcement
JP2009144399A (en) * 2007-12-13 2009-07-02 Ohbayashi Corp Connection method for prestressed concrete member and reinforced concrete building
JP2011080358A (en) * 2011-01-05 2011-04-21 Sumitomo Mitsui Construction Co Ltd Column-beam joint structure of building, building, and joining method
JP2014055517A (en) * 2013-12-25 2014-03-27 Takenaka Komuten Co Ltd Precast beam-column joint structure
CN104727440A (en) * 2014-11-17 2015-06-24 马恒忠 Novel industrialized production efficiently-assembled type building frame column beam and manufacturing method
CN104631619A (en) * 2014-12-19 2015-05-20 东南大学 U-shaped steel vertical connection assembled integral type frame and construction method thereof
CN106499053A (en) * 2016-11-30 2017-03-15 东北林业大学 A kind of assembled integral pre-stressed concrete frame structure connection member
CN106499053B (en) * 2016-11-30 2019-07-16 东北林业大学 A kind of assembled integral pre-stressed concrete frame structure connecting component

Also Published As

Publication number Publication date
JP2586224B2 (en) 1997-02-26

Similar Documents

Publication Publication Date Title
JPH04261934A (en) Building frame construction method using form member made of pre-cast concrete
JPH0518003A (en) Joining method of steel pipe concrete column and half-precast reinforced concrete column
JPH09209451A (en) Joint construction of up and down columns with beam and joint method
JPH0754396A (en) Column-beam jointing construction method
JP3039295B2 (en) Manufacturing method of prefabricated member of mixed structure
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
JPH0718734A (en) Constructing method for reinforced concrete building structure
JP2643641B2 (en) Building method using PC members
JPH1150538A (en) Building and method for constructing the same
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JP2003013493A (en) Beam-column connection joint and beam-column connection method
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH02120441A (en) Precast concrete wall panel and constructing wall therewith
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH0375704B2 (en)
JPH0673785A (en) Steel framed reinforced concrete column and construction of this column and steel skeleton beam
JPH02274938A (en) Combining method for src column
JPH04149365A (en) Construction method of beam
JPH05311748A (en) Connecting execution method of pole and beam
JPH03293445A (en) Structure of building and construction
JPH02282538A (en) Construction method of reinforced concrete-made building frame
JPH0327690B2 (en)
JPH0588331B2 (en)
JPH05125761A (en) Constructing method of composite structure
JPH01182432A (en) Compound structure of pillar and side beam