JPH0518003A - Joining method of steel pipe concrete column and half-precast reinforced concrete column - Google Patents

Joining method of steel pipe concrete column and half-precast reinforced concrete column

Info

Publication number
JPH0518003A
JPH0518003A JP19486491A JP19486491A JPH0518003A JP H0518003 A JPH0518003 A JP H0518003A JP 19486491 A JP19486491 A JP 19486491A JP 19486491 A JP19486491 A JP 19486491A JP H0518003 A JPH0518003 A JP H0518003A
Authority
JP
Japan
Prior art keywords
steel pipe
concrete column
column
concrete
precast reinforced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP19486491A
Other languages
Japanese (ja)
Inventor
Yoshiaki Imazu
賀昭 今津
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
OKI KENSETSU KK
OOKI KENSETSU KK
Original Assignee
OKI KENSETSU KK
OOKI KENSETSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by OKI KENSETSU KK, OOKI KENSETSU KK filed Critical OKI KENSETSU KK
Priority to JP19486491A priority Critical patent/JPH0518003A/en
Publication of JPH0518003A publication Critical patent/JPH0518003A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To offer an energy saving method applicable to a high-rise building consisting of lower sections of steel pipe concrete column construction and upper sections of half-precast reinforced concrete column construction in the high-rise building having 8 to 15 floors. CONSTITUTION:Lower sections of a structure are constructed of a steel pipe concrete column, and then, a plurality of connection reinforcing bars 3 inserting parts necessary for longitudinal anchorage of them into the steel pipe column and projecting remaining parts having proper lengths to the outside thereof are arranged to the inside of the steel pipe in the highest part of the steel pipe concrete column construction. After that, the steel pipe column is filled with concrete 6 to form the steel pipe concrete column 1. Then, the connection reinforcing bars 3...3 projected from the steel pipe concrete column 1 are fitted with a half-precast reinforced concrete column 2, and the steel pipe concrete column 1 is combined with the half-precast reinforced concrete column 2 by placing concrete to the inside of the half-precast reinforced concrete column 2. After that, upper sections are constructed of the half-precast reinforced concrete column, etc.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本願発明は8階乃至15階程度の
高層建築物の構築方法おいて、下部低層部を鋼管コンク
リート柱構造とし、上部高層部をハーフプレキャスト鉄
筋コンクリート柱構造とする際の鋼管コンクリート柱と
ハーフプレキャスト鉄筋コンクリート柱の接合方法に関
するものである。
BACKGROUND OF THE INVENTION The present invention relates to a method for constructing a high-rise building on the 8th to 15th floors, in which a lower low-rise part has a steel pipe concrete column structure and an upper high-rise part has a half precast reinforced concrete column structure. The present invention relates to a method for joining a concrete column and a half precast reinforced concrete column.

【0002】[0002]

【従来の技術】近年建築現場では、型枠・支保工など仮
設材の大量投入、労働作業員の集中配備、型枠組立、解
体時の安全性、熟練した作業員不足下における大量のく
体部に対する一定品質の確保など施工性における解決す
べき諸問題があり、安全かつ省力化しながらも一定品質
を保持することができる工法の開発が急務となってい
る。
2. Description of the Related Art In recent years, in construction sites, a large amount of temporary materials such as formwork and supporting work, concentrated deployment of labor workers, formwork assembly, safety at the time of dismantling, a large amount of bodywork under lack of skilled workers There are various problems in workability to be solved, such as ensuring a certain quality for parts, and it is an urgent task to develop a construction method that can maintain a certain quality while maintaining safety and labor saving.

【0003】これらの諸問題を解決する手段として、型
枠兼用のハーフプレキャスト鉄筋コンクリート柱を工場
生産しておき、これを施工現場にて柱主筋に被嵌し、そ
の内部にコンクリートを打設することにより建築物の鉄
筋コンクリート柱を構築する複合工法がある。
As a means for solving these various problems, a half-precast reinforced concrete column which also serves as a formwork is manufactured in a factory, and the main column bar is fitted at the construction site and concrete is placed therein. There is a composite construction method for constructing reinforced concrete columns for buildings.

【0004】ハーフプレキャスト鉄筋コンクリート柱と
は薄肉の中空プレキャストコンクリートに現場で鉄筋と
コンクリートを充填することによって形成する鉄筋コン
クリート柱をいう。
A half precast reinforced concrete column is a reinforced concrete column formed by filling thin-walled hollow precast concrete with reinforcement and concrete on site.

【0005】また、他の手段としては、施工現場におい
て鋼管柱を立設し、次いで該鋼管柱内にコンクリートを
打設することにより、鋼管柱自体をコンクリート打設の
際の型枠として用いると共にコンクリートと鋼管とが合
成されて耐力の大きい構造物を構築する鋼管コンクリー
ト柱工法、もしくは、予め工場にて鋼管柱内にコンクリ
ートを充填し鋼管コンクリート柱としておき、これを施
工現場にて組立てることにより構造物を構築する鋼管コ
ンクリート柱工法がある。
As another means, a steel pipe column is erected at a construction site, and concrete is then placed in the steel pipe column to use the steel pipe column itself as a formwork for concrete placing. By constructing a structure with high yield strength by synthesizing concrete and steel pipes, or by pre-filling the steel pipe columns with concrete at the factory to make concrete concrete pipes and then assembling this at the construction site. There is a steel pipe concrete pillar construction method for constructing structures.

【0006】[0006]

【解決しようとする課題】しかし、ハーフプレキャスト
鉄筋コンクリート柱を用いた鉄筋コンクリート柱の構築
工法は、型枠が不要であることから省力化した工法であ
るといえるが、通常用いられる200kgf/cm2
300kgf/cm2 程度のコンクリートを用いただけ
では大きな負荷をかけることができないためせいぜい7
階乃至8階建程度の中層の建築物向きの工法であり、こ
れを超える高層の建築物に適するものではない。
[SUMMARY] However, the construction method of the pillars reinforced concrete using a half precast reinforced concrete pillar, mold but is said to be a method that is labor saving because it is unnecessary, 200kgf / cm 2 ~ commonly used
Since a large load cannot be applied only by using concrete of about 300 kgf / cm 2, it is at most 7
This method is suitable for medium-rise buildings with one to eight floors and is not suitable for higher-rise buildings that exceed this level.

【0007】また、鋼管コンクリート柱を用いた工法
は、ハーフプレキャスト鉄筋コンクリート柱を用いた工
法と同様、型枠が不要であるとともに、鋼管柱とその内
部のコンクリートが、コンクリートは鋼管に拘束されて
十分な強度を発揮し、鋼管はコンクリートが充填されて
いることにより座屈が起こりにくいというように互いに
補完するように力を負担するため耐力・変形能力が向上
することから高層及び超高層の大規模構造に適した省力
化工法であるといえる。しかし、柱となる鋼管柱内にコ
ンクリートを打設するには一般に上端からコンクリート
を流し込むようにした場合、コンクリートの落下距離が
大きく途中でコンクリートが分離してしまうおそれがあ
ったり、下部の空気の逃げ場がなくなり内部に空隙が生
じてしまうことがあった。そのため、トレミー管を使用
してコンクリートを打設したり、下部からコンクリート
を圧入したりする方法が行われている。
[0007] Further, the construction method using steel pipe concrete columns does not require a formwork like the construction method using half precast reinforced concrete columns, and the steel pipe columns and the concrete inside thereof are sufficiently restrained by the steel pipe. The steel pipe is filled with concrete and buckles are less likely to occur, so the steel pipes bear forces so as to complement each other, improving the yield strength and deformation capacity. It can be said that this is a labor-saving construction method suitable for the structure. However, when pouring concrete into the steel pipe pillar that is to be the pillar, if the concrete is poured from the upper end, the concrete may fall greatly and the concrete may be separated in the middle, or the air in the lower part There was a case where there was no escape and a void was created inside. Therefore, a method of pouring concrete using a tremie pipe or press-fitting concrete from the lower part is performed.

【0008】また、鋼管柱の柱梁接合部に内ダイアフラ
ムを用いたタイプのものにおいては、これらの方法では
ブリージングによってダイアフラムの下側にコンクリー
トの水分がたまり空隙が生ずることがあるので、予め工
場で鋼管内にコンクリートを充填しプレキャスト鉄筋コ
ンクリート柱とする方法及びそのような鋼管コンクリー
ト柱を用いた構造物の構築方法も提案されている(特願
平3−49124号、特願平3−49125号)。この
鋼管コンクリート柱はハーフプレキャスト鉄筋コンクリ
ート柱に比して、その工事費が高額である。従って、高
層の建築物においては下部低層部分に鋼管コンクリート
柱を用い、上部高層部分にハーフプレキャスト鉄筋コン
クリート柱を用いれば非常に経済的とすることができ
る。
Further, in the type using the inner diaphragm at the beam-column joint portion of the steel pipe column, in these methods, the moisture of the concrete may accumulate on the lower side of the diaphragm due to breathing, so that a void may be generated beforehand. Japanese Patent Application No. 3-49124 and Japanese Patent Application No. 3-49125 propose a method of filling a steel pipe with concrete to form a precast reinforced concrete column and a method of constructing a structure using such a steel pipe concrete column. ). The construction cost of this steel pipe concrete column is higher than that of the half precast reinforced concrete column. Therefore, in a high-rise building, it is very economical to use steel pipe concrete columns in the lower low-rise portion and half precast reinforced concrete columns in the upper high-rise portion.

【0009】本願発明は上記課題に対処しようとするも
のであり、以下の記載の発明の完成によりその目的を達
成することができたものである。
The present invention is intended to address the above-mentioned problems, and has achieved the object by completing the invention described below.

【0010】[0010]

【課題を解決するための手段】本願発明は同一発明者が
発明した特願平3−49124号、“鋼管コンクリート
柱の製造方法”及び特願平3−49125号、“鋼管コ
ンクリート構造物の構築方法”に基づいて、さらに熟考
した結果発明したものである。
DISCLOSURE OF THE INVENTION The present invention is made by the same inventor in Japanese Patent Application No. 3-49124, “Method for manufacturing steel pipe concrete column” and Japanese Patent Application No. 3-49125, “Construction of steel pipe concrete structure”. It was invented as a result of further consideration based on the “method”.

【0011】本願発明は、下部低層部を鋼管コンクリー
ト柱を用いて構築し、上部高層部をハーフプレキャスト
鉄筋コンクリート柱を用いて構築するものであり、その
際の柱の接合手段として、鋼管コンクリート柱構造物の
最上部にある鋼管柱内に、その長さ方向の定着に必要な
部分が鋼管柱内に挿入されかつ適宜長さを有した残余部
分が鋼管柱外へ突出するようにした接続鉄筋を複数配置
し、その後鋼管柱内コンクリートを充填して鋼管コンク
リート柱とし、次いで該鋼管コンクリート柱より突出さ
せた接続鉄筋にハーフプレキャスト鉄筋コンクリート柱
を該接続鉄筋が内側になるように被嵌し、該ハーフプレ
キャスト鉄筋コンクリート柱の内部へコンクリートを充
填することにより、鋼管コンクリート柱とハーフプレキ
ャスト鉄筋コンクリート柱を接合して双方を一体とする
ことを特徴とする鋼管コンクリート柱とハーフプレキャ
スト鉄筋コンクリート柱の接合方法である。
According to the present invention, the lower low-rise portion is constructed by using a steel pipe concrete column, and the upper high-rise portion is constructed by using a half precast reinforced concrete column, and the steel pipe concrete column structure is used as a joining means of the columns at that time. In the steel pipe column at the top of the object, the connecting rebars are inserted so that the part necessary for fixing in the length direction is inserted into the steel pipe column and the remaining part with an appropriate length projects outside the steel pipe column. After arranging a plurality of steel pipe columns, concrete is filled with the steel pipe columns to form steel pipe concrete columns, and then half-precast reinforced concrete columns are fitted to the connecting rebars protruding from the steel pipe concrete columns so that the connecting rebars are inside, By filling the interior of precast reinforced concrete columns with concrete, steel pipe concrete columns and half precast reinforced concrete columns A method of joining steel concrete column and Precast reinforced concrete column, characterized in that an integral both to join the over preparative column.

【0012】また、鋼管コンクリート柱より突出させた
接続鉄筋にハーフプレキャスト鉄筋コンクリート柱を被
嵌した後、コンクリートの充填前に予め該鋼管コンクリ
ート柱と該ハーフプレキャスト鉄筋コンクリート柱の接
合部分に、流動性の高い高強度無収縮モルタルをグラウ
チングすることをも特徴とするものである。
Further, after fitting the half-precast reinforced concrete column to the connecting rebar projecting from the steel-tube concrete column, and before filling the concrete, the joint between the steel-tube concrete column and the half-precast reinforced concrete column has a high fluidity. It is also characterized by grouting high-strength non-shrink mortar.

【0013】なお、この際の鋼管柱とは、鋼管内に何も
充填されていない中空の鋼管とともに、鋼管の開口部、
すなわちハーフプレキャスト鉄筋コンクリート柱との接
合部付近を除く中間部分にだけ予めコンクリートを充填
した鋼管(鋼管と鋼管コンクリート柱の中間体)を含む
ものとし、鋼管コンクリート柱とは、前記の要領にて施
工現場にてコンクリートを充填し製造するもののほか、
予め工場内にて製造したプレキャスト部材の双方を含む
ものとする。
In this case, the steel pipe column means a hollow steel pipe in which nothing is filled in the steel pipe, an opening of the steel pipe,
That is, the steel pipe (intermediate between steel pipe and steel pipe concrete column) pre-filled with concrete shall be included only in the intermediate part except the vicinity of the joint with the half precast reinforced concrete column. In addition to those manufactured by filling concrete with
It shall include both precast members manufactured in advance in the factory.

【0014】[0014]

【作用】鋼管柱に該鋼管開口端部より突出するように接
続鉄筋を設けて鋼管コンクリート柱としたことにより、
ハーフプレキャスト鉄筋コンクリート柱との接合が可能
となるとともに、ハーフプレキャスト鉄筋コンクリート
柱の内側面が接続鉄筋と接して案内されるように摺動し
接続鉄筋を被嵌することにより、簡単かつ位置ずれする
ことなく接続固定することができる。
[Operation] By providing a connecting rebar on the steel pipe column so as to project from the steel pipe opening end to form a steel pipe concrete column,
It becomes possible to join with half precast reinforced concrete columns, and by sliding so that the inner surface of the half precast reinforced concrete columns is guided in contact with the connecting rebars and fitting the connecting rebars, it is easy and without displacement. The connection can be fixed.

【0015】[0015]

【実施例】以下、本願発明の一実施例を図面に基づいて
説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings.

【0016】本願発明は、まず、鋼管コンクリート柱を
用いて構造物の下部低層部を構築する。その手段として
は、例えば、本願発明者が発明した特願平3ー4912
5号に記載された手段、すなわち、工場内等で鋼管内に
予めコンクリートを充填し鋼管コンクリート柱とし、そ
の後、該鋼管コンクリート柱を施工現場へ搬入し、通常
の鉄骨と同様に立設していき、その際に鋼管コンクリー
ト柱と鋼管コンクリート柱の間にグラフト噴射器を挾入
し該グラフト噴射器の注入口よりグラウト材をグラウチ
ングすることにより該二つの鋼管コンクリート柱を接合
するという方法により下部低層部を構築する。
According to the present invention, first, a lower lower layer portion of a structure is constructed by using a steel pipe concrete column. As the means, for example, Japanese Patent Application No. 3-4912 invented by the present inventor
The means described in No. 5, that is, the steel pipe is preliminarily filled with concrete in a factory or the like to form a steel pipe concrete pillar, and then the steel pipe concrete pillar is carried into a construction site and erected in the same manner as a normal steel frame. At that time, a graft injector is inserted between the steel tube concrete column and the steel tube concrete column, and the two steel tube concrete columns are joined together by grouting a grout material from the inlet of the graft injector. Build the lower part.

【0017】この時、ハーフプレキャスト鉄筋コンクリ
ート柱と接合される鋼管コンクリート柱である接続鉄筋
を有した鋼管コンクリート柱を工場内等に製造してお
き、これを鋼管コンクリート柱構造物の最上部に配置し
ておく。この鋼管コンクリート柱は鋼管柱内に、その長
さ方向の定着に必要な部分が鋼管柱内に挿入されかつ適
宜長さを有した残余部分が鋼管柱外へ突出するようにし
た接続鉄筋(3)を複数配置し、その後該鋼管柱内へコ
ンクリートを充填することにより鋼管コンクリート柱と
するものである。そして、必要に応じて該鋼管コンクリ
ート柱より突出した接続鉄筋(3・・・3)に、別の接
続鉄筋(3b)を、溶接継手又は重ね継手等の方法によ
り継ぎ足し、十分な長さとする。接続鉄筋(3)の配置
場所及び数は任意であり、ハーフプレキャスト鉄筋コン
クリート柱と鋼管コンクリート柱が確実に接合でき、か
つ強度が保てれば良い。
At this time, a steel pipe concrete column having connecting rebars, which is a steel pipe concrete column to be joined to the half precast reinforced concrete column, is manufactured in a factory or the like, and is placed at the top of the steel pipe concrete column structure. Keep it. This steel pipe concrete column has a connecting rebar (3) in which a portion necessary for fixing in the longitudinal direction is inserted into the steel pipe column and the remaining portion having an appropriate length is projected outside the steel pipe column. ) Are arranged, and then concrete is filled into the steel pipe pillar to form a steel pipe concrete pillar. Then, if necessary, another connecting reinforcing bar (3b) is added to the connecting reinforcing bar (3 ... 3) protruding from the steel pipe concrete column by a method such as a welding joint or a lap joint to make a sufficient length. The location and number of the connecting reinforcing bars (3) are arbitrary, and it is sufficient that the half precast reinforced concrete columns and the steel pipe concrete columns can be reliably joined and the strength can be maintained.

【0018】その後、接続鉄筋(3・・・3)の上方よ
りハーフプレキャスト鉄筋コンクリート柱(2)を該接
続鉄筋(3・・・3)が内側になるように被嵌し、被嵌
したハーフプレキャスト鉄筋コンクリート柱(2)の内
部へコンクリートを充填することにより、鋼管コンクリ
ート柱(1)とハーフプレキャスト鉄筋コンクリート柱
(2)を接合して双方を一体とする。
Thereafter, a half precast reinforced concrete column (2) is fitted from above the connecting rebars (3 ... 3) so that the connecting rebars (3 ... 3) are on the inside, and the half precast fitted. By filling the inside of the reinforced concrete column (2) with concrete, the steel pipe concrete column (1) and the half precast reinforced concrete column (2) are joined to integrate them.

【0019】鋼管コンクリート柱は上記のように予め工
場内等にて製造して置くものの他、施工現場にて充填を
行う方法によって製造しても差し支えない。また、柱の
形状も図面に示された角柱にかかわらず円柱としても差
し支えない。
The steel tube concrete column may be manufactured by a method of filling at the construction site in addition to the one prepared and placed in the factory in advance as described above. Further, the shape of the pillar may be a cylinder regardless of the prismatic shape shown in the drawing.

【0020】さらに、鋼管コンクリート柱(1)より突
出させた接続鉄筋(3・・・3)にハーフプレキャスト
鉄筋コンクリート柱(2)を被嵌した後、コンクリート
充填前に該鋼管コンクリート柱(1)と該ハーフプレキ
ャスト鉄筋コンクリート柱(2)の接合部分に型枠を設
け、該接合部分の隙間を埋塞するために流動性の高い高
強度無収縮モルタル(7)をグラウチングすると良い。
Further, after connecting the half-precast reinforced concrete columns (2) to the connecting rebars (3 ... 3) protruding from the steel tubular concrete columns (1), the steel pipe concrete columns (1) and It is advisable to provide a mold at the joint portion of the half precast reinforced concrete column (2) and grout a high-strength non-shrink mortar (7) having high fluidity in order to fill the gap between the joint portions.

【0021】なお、図面においては、ハーフプレキャス
ト鉄筋コンクリート柱(2)が接続鉄筋(3・・・3)
を被嵌し鋼管コンクリート柱(1)の内側の寸法と同じ
大きさをしたものとなっているが、鋼管コンクリート柱
(1)よりも太くなければ図面に示したものより大きく
ても差し支えないし、又接続鉄筋(3・・・3)を被嵌
することができれば図面に示したものより小さくても差
し支えない。
In the drawing, the half precast reinforced concrete columns (2) are connected to the reinforcing bars (3 ... 3).
It has the same size as the inner dimension of the steel pipe concrete column (1), but if it is not thicker than the steel pipe concrete column (1), it may be larger than that shown in the drawing, Further, if the connecting reinforcing bars (3 ... 3) can be fitted, the size may be smaller than that shown in the drawings.

【0022】その後はハーフプレキャスト鉄筋コンクリ
ート柱を用いて上部高層部を構築する。構築方法として
は、柱用のハーフプレキャスト鉄筋コンクリート柱
(2)を接続鉄筋(3・・・3)を用いて接続固定す
る。次いで、梁用のコンクリート部材を型枠及び止め具
を用いて適宜位置に固定し、その後、柱用のハーフプレ
キャスト鉄筋コンクリート柱(2)及び梁用のコンクリ
ート部材の内部へコンクリートを充填し一体とする。こ
れを順次くり返し行う。この際、予め梁用のコンクリー
ト部材にフープ筋等の剪断補強筋を適宜間隔に配置して
おき、その後コンクリートを充填するようにしても良
い。
After that, the upper high-rise portion is constructed using the half precast reinforced concrete columns. As a construction method, the half precast reinforced concrete columns (2) for columns are connected and fixed using the connecting rebars (3 ... 3). Then, the concrete member for the beam is fixed at an appropriate position by using a formwork and a stopper, and then the inside of the half precast reinforced concrete column (2) for the column and the concrete member for the beam is filled with concrete to be integrated. . This is repeated repeatedly. At this time, shear reinforcements such as hoop reinforcements may be previously arranged at appropriate intervals on the concrete member for the beam, and then concrete may be filled.

【0023】[0023]

【効果】以上のように、下部低層部は耐力、変形能力な
どが非常に大きい鋼管コンクリート柱による構造体と
し、上部高層部は鋼管コンクリート柱に比べて安価なハ
ーフプレキャスト鉄筋コンクリート柱を用いた構造体と
することにより、夫々の部材を適材適所に用いた全体と
して経済的な構造物とすることができるとともに、一貫
して型枠工や鉄筋工などの熟練工が極めて省力化された
工法であるといえる。
[Effect] As described above, the lower low-rise part is a structure made of steel pipe concrete columns with extremely high proof strength and deformation capacity, and the upper high-rise part is a structure made of half-precast reinforced concrete columns, which is cheaper than steel pipe concrete columns. By doing so, it is possible to make an economical structure as a whole by using each member in the right material in the right place, and at the same time, it is a construction method in which skilled workers such as formwork and reinforcing bar work are extremely labor-saving. I can say.

【0024】また、構造物全体をプレハブ形式で構築す
るものであることにより、比較的短期間で計画通りに構
造物を構築することができ、この点からも極めて優れた
工法であるといえる。
Further, since the entire structure is constructed in the prefabricated form, the structure can be constructed as planned in a relatively short period of time, and it can be said that this is also an excellent construction method.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本願発明である鋼管コンクリート柱と中空コ
ンクリート部材を接合する手段を示す斜視図。
FIG. 1 is a perspective view showing a means for joining a steel pipe concrete column and a hollow concrete member according to the present invention.

【図2】 本願発明である鋼管コンクリート柱と中空コ
ンクリート部材を接合する手段を示す側面図。
FIG. 2 is a side view showing a means for joining a steel pipe concrete column and a hollow concrete member according to the present invention.

【図3】 〔図2〕のX−X線に沿う断面図。FIG. 3 is a sectional view taken along line XX of FIG.

【図4】 〔図2〕のY−Y線に沿う断面図。FIG. 4 is a sectional view taken along the line YY of FIG.

【図5】 〔図2〕のZ−Z線に沿う断面図。FIG. 5 is a sectional view taken along line ZZ of FIG.

【符号の説明】[Explanation of symbols]

1・・・鋼管コンクリート柱 2・・・ハーフプレキャスト鉄筋コンクリート柱 3,3b・・接続鉄筋 4・・・梁用主骨 5・・・鉄筋接続部 6,6b・・コンクリート 7・・・高強度無収縮モルタル 8・・・床材(コンクリート) 9・・・補強用鉄筋 1 ... Steel tube concrete pillar 2 ... Half precast reinforced concrete columns 3,3b ... Connecting rebar 4 ... Beam main frame 5 ... Reinforcing bar connection 6,6b ... Concrete 7: High strength non-shrink mortar 8: Floor material (concrete) 9 ... Reinforcing steel bars

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 鋼管柱内に、その長さ方向の定着に必要
な部分が鋼管柱内に挿入され、かつ適宜長さを有した残
余部分が鋼管柱外へ突出するように接続鉄筋を配置し、
その後該鋼管柱内にコンクリートを充填して鋼管コンク
リート柱とし、次いで鋼管コンクリート柱より突出させ
た接続鉄筋にハーフプレキャスト鉄筋コンクリート柱を
被嵌し、該ハーフプレキャスト鉄筋コンクリート柱の内
部へコンクリートを充填することにより双方を一体化す
ることを特徴とする鋼管コンクリート柱とハーフプレキ
ャスト鉄筋コンクリート柱の接合方法。
1. A connection reinforcing bar is arranged in a steel pipe column so that a portion necessary for fixing in the lengthwise direction is inserted into the steel pipe column and a remaining portion having an appropriate length projects outside the steel pipe column. Then
After that, the concrete is filled with concrete in the steel pipe column to form a steel pipe concrete column, and then a half precast reinforced concrete column is fitted to the connecting rebar protruding from the steel pipe concrete column, by filling the inside of the half precast reinforced concrete column with concrete. A method for joining steel pipe concrete columns and half precast reinforced concrete columns, characterized by integrating both.
【請求項2】 鋼管コンクリート柱より突出した接続鉄
筋にハーフプレキャスト鉄筋コンクリート柱を被嵌した
後、該鋼管コンクリート柱と該ハーフプレキャスト鉄筋
コンクリート柱の接合部分に流動性の高い高強度無収縮
モルタルをグランチングすることを特徴とする請求項1
に記載の鋼管コンクリート柱とハーフプレキャスト鉄筋
コンクリート柱の接合方法。
2. A high-strength non-shrink mortar having high fluidity is ground at the joint between the steel pipe concrete column and the half precast reinforced concrete column after fitting the half precast reinforced concrete column to the connecting rebar protruding from the steel pipe concrete column. Claim 1 characterized by the above.
Method for joining steel pipe concrete columns and half precast reinforced concrete columns as described in.
JP19486491A 1991-07-09 1991-07-09 Joining method of steel pipe concrete column and half-precast reinforced concrete column Pending JPH0518003A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19486491A JPH0518003A (en) 1991-07-09 1991-07-09 Joining method of steel pipe concrete column and half-precast reinforced concrete column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19486491A JPH0518003A (en) 1991-07-09 1991-07-09 Joining method of steel pipe concrete column and half-precast reinforced concrete column

Publications (1)

Publication Number Publication Date
JPH0518003A true JPH0518003A (en) 1993-01-26

Family

ID=16331570

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19486491A Pending JPH0518003A (en) 1991-07-09 1991-07-09 Joining method of steel pipe concrete column and half-precast reinforced concrete column

Country Status (1)

Country Link
JP (1) JPH0518003A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0711709A (en) * 1993-06-24 1995-01-13 Toda Constr Co Ltd Steel pipe column jointing method and building constructing method
JP2000282578A (en) * 1999-01-27 2000-10-10 Maeda Corp Structure of column
CN103306378A (en) * 2013-06-19 2013-09-18 泰兴市第一建筑安装工程有限公司 Construction method of multidirectional through concrete filled steel tubular column beam joint provided with steel corbels and ring beam
CN103806672A (en) * 2014-01-21 2014-05-21 浙江天地环保工程有限公司 Reinforcing method for touched nodes of existing beam and lacing bar type lattice steel column
KR101511172B1 (en) * 2013-05-16 2015-04-10 (주)한국건설공법 A joint structure of a CFT composite column and RC wide girder
JP2016132948A (en) * 2015-01-21 2016-07-25 株式会社竹中工務店 Connection structure
CN106638989A (en) * 2017-02-16 2017-05-10 中国建筑设计院有限公司 Steel pipe column and reinforced concrete column reinforced beam switching node and building comprising same
JP2018096071A (en) * 2016-12-12 2018-06-21 大成建設株式会社 Composite building
JP2019138137A (en) * 2018-02-05 2019-08-22 清水建設株式会社 Junction structure of cft column and rc column
JP2020204257A (en) * 2020-09-15 2020-12-24 大成建設株式会社 Composite building
JP2021046732A (en) * 2019-09-19 2021-03-25 戸田建設株式会社 Building with opening
JP2022176858A (en) * 2021-05-17 2022-11-30 三一筑工科技股▲ふん▼有限公司 Precast column and precast column connection structure

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0711709A (en) * 1993-06-24 1995-01-13 Toda Constr Co Ltd Steel pipe column jointing method and building constructing method
JP2000282578A (en) * 1999-01-27 2000-10-10 Maeda Corp Structure of column
JP4491099B2 (en) * 1999-01-27 2010-06-30 前田建設工業株式会社 Column structure
KR101511172B1 (en) * 2013-05-16 2015-04-10 (주)한국건설공법 A joint structure of a CFT composite column and RC wide girder
CN103306378A (en) * 2013-06-19 2013-09-18 泰兴市第一建筑安装工程有限公司 Construction method of multidirectional through concrete filled steel tubular column beam joint provided with steel corbels and ring beam
CN103306378B (en) * 2013-06-19 2015-04-01 泰兴市第一建筑安装工程有限公司 Construction method of multidirectional through concrete filled steel tubular column beam joint provided with steel corbels and ring beam
CN103806672A (en) * 2014-01-21 2014-05-21 浙江天地环保工程有限公司 Reinforcing method for touched nodes of existing beam and lacing bar type lattice steel column
JP2016132948A (en) * 2015-01-21 2016-07-25 株式会社竹中工務店 Connection structure
JP2018096071A (en) * 2016-12-12 2018-06-21 大成建設株式会社 Composite building
CN106638989A (en) * 2017-02-16 2017-05-10 中国建筑设计院有限公司 Steel pipe column and reinforced concrete column reinforced beam switching node and building comprising same
JP2019138137A (en) * 2018-02-05 2019-08-22 清水建設株式会社 Junction structure of cft column and rc column
JP2021046732A (en) * 2019-09-19 2021-03-25 戸田建設株式会社 Building with opening
JP2020204257A (en) * 2020-09-15 2020-12-24 大成建設株式会社 Composite building
JP2022176858A (en) * 2021-05-17 2022-11-30 三一筑工科技股▲ふん▼有限公司 Precast column and precast column connection structure

Similar Documents

Publication Publication Date Title
JPH0518003A (en) Joining method of steel pipe concrete column and half-precast reinforced concrete column
JP3700102B2 (en) Building basic structure
JPH08302892A (en) Precast structural member comprising reinforced concrete column and steel beam, and method for constructing structure using the same
JPH05311747A (en) Pole-beam structure
JP2005155036A (en) Column of building and rigid-frame structure using this column
JP3424842B2 (en) Joining method of steel reinforced concrete columns in precast method
KR20020063779A (en) Prefabricated Enclosed Steel Concrete Structures
JPH0536587B2 (en)
JPH0699963B2 (en) Prestressed RPC method and prestressed PC columns with beams
JP2762906B2 (en) RC frame
JPH02221535A (en) Connecting structure for pillar and beam
JPH0960194A (en) Precast concrete structure
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JPH0732706Y2 (en) Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams
JP2656175B2 (en) Column-beam joint structure
JPH1150538A (en) Building and method for constructing the same
JPH06306931A (en) Construction of steel frame reinforced concrete structure
JPH06316964A (en) Method for constructing joint of precast reinforced concrete column and beam
JP2005002585A (en) Capital member and rcft pole construction method using the same
JP2984626B2 (en) PC pillar construction method and its PC pillar
JP3094198B2 (en) Precast reinforced concrete member and method of constructing structure using the same
JPH04169625A (en) Joint structure
JPH0762740A (en) Joint method for precast steel framed reinforced concrete construction pillar and beam
JPH03290543A (en) Frame body of structure consisting of precast steel pipe column and precast steel beam or prestressed steel beam, joint structure with pc steel pipe column and pc steel beam or ps steel beam, and pc steel pipe column and ps steel beam