JPH06212644A - Foundation construction method - Google Patents

Foundation construction method

Info

Publication number
JPH06212644A
JPH06212644A JP662393A JP662393A JPH06212644A JP H06212644 A JPH06212644 A JP H06212644A JP 662393 A JP662393 A JP 662393A JP 662393 A JP662393 A JP 662393A JP H06212644 A JPH06212644 A JP H06212644A
Authority
JP
Japan
Prior art keywords
grooves
plates
ground
groove
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP662393A
Other languages
Japanese (ja)
Inventor
Hidemori Tanaka
英守 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP662393A priority Critical patent/JPH06212644A/en
Publication of JPH06212644A publication Critical patent/JPH06212644A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE:To shorten the construction period by doubling plates on both sides of a groove so as to stop the collapse of the groove and burying the doubled plates in place and omitting back-filling work. CONSTITUTION:Grooves 12 whose sides are parallel are excavated underground from the ground 11 in parallel. Then, the ground between the both grooves 12 is excavated to a specified depth where an excavator 13 is installed. Plates 14 are doubled on both sides of each of the grooves 12. The upper edges of the plates 14 are aligned with the excavation bottom of the excavator 13 or it is arranged to project slightly above the ground 11. The lower parts of the plates 14 are fixed by means of an angle 17 while the upper parts of the plates 14 are fixed by means of a separator 19, thereby maintaining the plates 14 on the sides of the grooves. Then, after reinforcing bats are placed, concrete is simultaneously cast on the grooves 12 and the excavator 13. Since the plates 14 are buried in place, it is possible to shorten the construct period accordingly.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、建築用基礎の構築方
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a building foundation.

【0002】[0002]

【従来の技術】従来の建築基礎の構築方法は、図5に示
すように、地面1から地中に向け溝2を掘削する。
2. Description of the Related Art As shown in FIG. 5, a conventional method for constructing a building foundation excavates a groove 2 from the ground 1 toward the ground.

【0003】上記溝2の両側の対向間隔は、地面1から
根切り底3に向け小さく(倒立台形)なっている。
The opposing distance between both sides of the groove 2 is small (inverted trapezoid) from the ground 1 to the root cutting bottom 3.

【0004】次に、溝2内の両側に対向状に型枠4を配
置する。上記型枠4の対向間隔は、各部において均等に
なっている。
Next, the molds 4 are arranged on both sides in the groove 2 so as to face each other. The facing intervals of the mold 4 are equal in each part.

【0005】しかして、型枠4内に鉄筋5を配筋したの
ち、図6に示すように、コンクリート6を打設する。
After the reinforcing bars 5 have been arranged in the form 4, concrete 6 is placed as shown in FIG.

【0006】打設コンクリート6の硬化後に図6に示す
ように、型枠4を撤去すると共に、形成した地中梁7と
溝2の側面との空隙に土壌8を埋め戻す。
After the cast concrete 6 is hardened, as shown in FIG. 6, the form 4 is removed and the soil 8 is backfilled in the gap between the formed underground beam 7 and the side surface of the groove 2.

【0007】しかるのち、土間用コンクリート9を打設
する。
After that, concrete 9 for soil is poured.

【0008】[0008]

【発明が解決しようとする課題】上記のような構築方法
を採用すると、地中梁よりも大きな幅で、しかも倒立台
形の溝を掘削するので、土壌の排出量が著しく多くな
り、搬出コストが上昇する問題があった。
When the construction method as described above is adopted, since an inverted trapezoidal groove having a width larger than that of an underground beam is excavated, the amount of soil discharged is significantly increased, and the cost of unloading is increased. There was a rising problem.

【0009】また、地中梁の構築後に型枠を撤去し、そ
して溝の空隙に排出した土壌を埋め戻すので、手間がか
かると共に、特に現場に一度搬出した土壌を搬入するた
めさらに手数がかかり、施工費が著しく上昇する。
[0009] Further, since the formwork is removed after the underground beam is constructed and the soil discharged to the void of the groove is backfilled, it takes time and labor, especially because the soil once transported to the site is brought in. , Construction costs will rise significantly.

【0010】さらに、地中梁の構築後に土間用コンクリ
ートを打設するので、工期が長くなると共に、地中梁と
土間用コンクリートを別々に搬入しなければならない問
題もあった。
Further, since the concrete for soil is placed after the construction of the underground girder, the construction period becomes long and there is a problem that the underground girder and the concrete for soil are required to be carried in separately.

【0011】そこで、この発明の課題は、溝の埋め戻し
が不要になると共に、地中梁と土間とのコンクリート打
設を同時に行なうようにした基礎の構築方法を提供する
ことである。
Therefore, an object of the present invention is to provide a method of constructing a foundation which eliminates the need for backfilling of grooves and simultaneously performs concrete pouring between an underground beam and a soil.

【0012】[0012]

【課題を解決するための手段】上記の課題を解決するた
めに、この発明は、地面から地中に向け両側面が平行す
る溝を並列状に掘削すると共に、この両溝間の地面を所
定の深さ迄掘り下げたのち、上記各溝の側面に板状体を
重ね合わせると共に、適宜の手段を用いて上記板状体の
重ね状態を維持し、次いで、上記各溝内に鉄筋を配筋し
たのち、上記各溝内及び前記溝間の掘り下げ部分にコン
クリートを打設する方法を採用したものである。
In order to solve the above-mentioned problems, the present invention excavates grooves whose both side surfaces are parallel to each other from the ground surface to the ground, and at the same time, defines the ground surface between the both grooves. After digging up to the depth of the above, the plate-like body is overlapped on the side surface of each groove, and the overlapped state of the plate-like body is maintained by using an appropriate means, and then a reinforcing bar is laid in each groove. After that, a method of placing concrete in each of the grooves and in the dug portion between the grooves is adopted.

【0013】[0013]

【作用】溝の両側面に重ね合わせた板状体により溝の側
面の崩壊を止めると共に、板状体を埋め殺して溝の埋め
戻し作業を省略する。
The plate-like members superposed on both side surfaces of the groove prevent the side surfaces of the groove from collapsing, and the plate-like members are buried to omit the backfilling work of the groove.

【0014】また、溝内と溝間の掘り下げ部分とに一度
にコンクリートを打設して、溝と土間とに別々にコンク
リートを打設する作業をなくする。
Further, it is possible to eliminate the work of placing concrete at the same time in the trench and in the dug portion between the trenches and separately placing concrete in the trench and the soil.

【0015】[0015]

【実施例】以下、この発明の実施例を添付図面に基づい
て説明する。
Embodiments of the present invention will be described below with reference to the accompanying drawings.

【0016】図1に示すように、地面11から地中に向
け両側面が平行(各部の対向間隔が均一な)する溝12
を並列状に掘削する。
As shown in FIG. 1, a groove 12 whose both side surfaces are parallel to each other from the ground surface 11 to the ground (the facing intervals of the respective parts are uniform).
Are drilled in parallel.

【0017】また、この並列する両溝12間の地面11
から所定の深さ迄掘削して掘り下げ部13を設ける。
Further, the ground surface 11 between the two grooves 12 arranged in parallel.
To a predetermined depth, and a dug portion 13 is provided.

【0018】次に、各溝12の両側面に板状体14を重
ね合わすと共に、板状体14の重ね合わせ状態を維持す
る。
Next, the plate-shaped bodies 14 are superposed on both side surfaces of each groove 12, and the superposed state of the plate-shaped bodies 14 is maintained.

【0019】上記並列する溝12の対向側の側面に重ね
合わせる板状体14の上縁は、掘り下げ部13の根切り
底と同レベルになり、並列する溝12の相反する側の側
面に重ね合わせた板状体14の上縁は、地面11から若
干上方に突出させてある。なお、板状体14には、鉄板
や硬質合成樹脂板などを用いる。
The upper edge of the plate-like member 14 superposed on the opposite side surfaces of the parallel grooves 12 is at the same level as the root cutting bottom of the dug portion 13, and is superposed on the opposite side surfaces of the parallel grooves 12. The upper edge of the combined plate-like bodies 14 is projected slightly above the ground 11. An iron plate, a hard synthetic resin plate, or the like is used for the plate-shaped body 14.

【0020】また、板状体14の重ね合わせ状態の維持
は、図3に示すように、溝12の根切り底にコンクリー
トを打設してベース15を形成すると共に、ベース15
のアンカーボルト16をベース15上に載置したアング
ル17の片側片に貫通させ、そして、アンカーボルト1
6にナット18をねじ込みながら、ベース15上にアン
グル17を固定し、アングル17のもう片側片と溝12
の側面とに間に板状体14の下縁を落し込んで支持し、
並列板状体14の上部は、図2に示すように、前もって
セパレータ19の両端にねじ込んである木コン20を板
状体14の内面に当接し、板状体14に外側から挿通す
るボルト21を木コン20にねじ込んで対向間隔を維持
するようにしたが、上記以外の方法で板状体14の対向
間隔を維持するようにしてもよい。
To maintain the stacked state of the plate-like bodies 14, as shown in FIG. 3, concrete is placed on the roots of the grooves 12 to form the base 15 and the base 15
The anchor bolt 16 of the above is passed through one side of the angle 17 placed on the base 15, and the anchor bolt 1
While screwing the nut 18 into 6, fix the angle 17 on the base 15, and fix the other side piece of the angle 17 and the groove 12
The lower edge of the plate-shaped body 14 is dropped between and supported on the side of
As shown in FIG. 2, the upper portion of the parallel plate-shaped body 14 abuts on the inner surface of the plate-shaped body 14 with the wooden contacts 20 which are previously screwed into both ends of the separator 19 and is inserted into the plate-shaped body 14 from the outside. Although the above is screwed into the wooden container 20 to maintain the facing distance, the facing distance of the plate-shaped body 14 may be maintained by a method other than the above.

【0021】次いで、それぞれの溝12内に力学的に要
求される量の鉄筋22を配筋したのち、図4に示すよう
に、それぞれの溝12及び掘り下げ部13にコンクリー
トを同時打設して、地中梁23及び土間24を設ける。
Then, after reinforcing the reinforcing bars 22 in the respective grooves 12 in a mechanically required amount, concrete is simultaneously poured into the respective grooves 12 and the dug portion 13, as shown in FIG. An underground beam 23 and a soil floor 24 are provided.

【0022】[0022]

【効果】この発明は、以上のようにして地中梁と土間と
をコンクリートの同時打設により構築するので、著しく
工期を短縮すると共に、施工費が安価になる。
[Effect] According to the present invention, since the underground girder and the soil are constructed by the simultaneous pouring of concrete as described above, the construction period can be remarkably shortened and the construction cost can be reduced.

【0023】また、地中梁構築用の溝は、側面が平行す
るよう掘削し、溝の両側面に重ね合わせた板状体を埋め
殺しにするため、溝の埋め戻し作業や型枠の撤去作業が
不要になると共に、倒立台形状溝の掘削にともない発生
した土壌の搬出量が増大するような問題を解消すること
ができる。
In addition, the trench for constructing the underground beam is excavated so that the side surfaces are parallel to each other, and the plate-like bodies superposed on both sides of the trench are buried, so that the trench is backfilled and the formwork is removed. This eliminates the need for work and solves the problem that the amount of soil carried out due to excavation of the inverted trapezoidal groove increases.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の実施例を示す縦断正面図FIG. 1 is a vertical sectional front view showing an embodiment of the present invention.

【図2】板状体の上部間隔維持を示す縦断拡大正面図FIG. 2 is an enlarged vertical cross-sectional front view showing maintaining the upper space of the plate-like bodies.

【図3】板状体の下縁支持を示す縦断拡大正面図FIG. 3 is an enlarged vertical sectional front view showing the lower edge support of the plate-shaped body.

【図4】地中梁と土間とを構築した縦断正面図[Fig. 4] Front view in vertical section of underground beam and soil floor

【図5】従来例の縦断正面図FIG. 5 is a vertical sectional front view of a conventional example.

【図6】地中梁と土間とを構築した縦断正面図FIG. 6 is a vertical sectional front view of an underground beam and an earth floor.

【符号の説明】[Explanation of symbols]

11 地面 12 溝 13 掘り下げ部 14 板状体 15 ベース 16 アンカーボルト 17 アングル 18 ナット 19 セパレータ 20 木コン 21 ボルト 22 鉄筋 23 地中梁 24 土間 11 Ground 12 Groove 13 Digging Part 14 Plate 15 Base 16 Anchor Bolt 17 Angle 18 Nut 19 Separator 20 Wood Con 21 Bolt 22 Reinforcing Bar 23 Underground Beam 24 Dirt

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 地面から地中に向け両側面が平行する溝
を並列状に掘削すると共に、この両溝間の地面を所定の
深さ迄掘り下げたのち、上記各溝の側面に板状体を重ね
合わせると共に、適宜の手段を用いて上記板状体の重ね
状態を維持し、次いで、上記各溝内に鉄筋を配筋したの
ち、上記各溝内及び前記溝間の掘り下げ部分にコンクリ
ートを打設することを特徴とする基礎の構築方法。
1. Grooves having both sides parallel to each other from the ground to the ground are excavated in parallel, and the ground between the grooves is dug down to a predetermined depth, and then a plate-like body is formed on the side surface of each groove. While superposing, maintain the stacked state of the plate-like body by using an appropriate means, then, after reinforcing bars in each of the grooves, concrete in the dug portion in each of the grooves and between the grooves. A method of constructing a foundation characterized by casting.
JP662393A 1993-01-19 1993-01-19 Foundation construction method Pending JPH06212644A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP662393A JPH06212644A (en) 1993-01-19 1993-01-19 Foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP662393A JPH06212644A (en) 1993-01-19 1993-01-19 Foundation construction method

Publications (1)

Publication Number Publication Date
JPH06212644A true JPH06212644A (en) 1994-08-02

Family

ID=11643491

Family Applications (1)

Application Number Title Priority Date Filing Date
JP662393A Pending JPH06212644A (en) 1993-01-19 1993-01-19 Foundation construction method

Country Status (1)

Country Link
JP (1) JPH06212644A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002285562A (en) * 2001-03-22 2002-10-03 Asahi Kasei Corp Foundation construction for building

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57116833A (en) * 1981-01-12 1982-07-21 Hitoshi Mori Setting of foundation
JPH03228921A (en) * 1990-02-05 1991-10-09 Achilles Corp Execution method for concrete foundation work

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57116833A (en) * 1981-01-12 1982-07-21 Hitoshi Mori Setting of foundation
JPH03228921A (en) * 1990-02-05 1991-10-09 Achilles Corp Execution method for concrete foundation work

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002285562A (en) * 2001-03-22 2002-10-03 Asahi Kasei Corp Foundation construction for building

Similar Documents

Publication Publication Date Title
US3195312A (en) Method for erecting precast retaining wall
KR102159832B1 (en) Construction method of basic construction of buildings
KR20190083466A (en) Retaining wall and construction method thereof
JP3893056B2 (en) Construction method of underground structure
JP2020197015A (en) Construction method of foundation
KR200183206Y1 (en) Block for breastwall
JPH06212644A (en) Foundation construction method
JP7115923B2 (en) Foundation structure reinforcement method and foundation structure reinforcement structure
JPH06306853A (en) Construction of underground structure
JPH0721196B2 (en) Reverse construction method of underground structure
JP3138129B2 (en) Reverse beam construction method and driving beam side formwork
JPS5851092B2 (en) Earth retaining installation method using advance shoring frame
KR100386696B1 (en) Foundation concrete pouring method of building structure
JPH0641993A (en) Learned retaining wall
JPH11158891A (en) Construction of basement for residence
JPH01210521A (en) Building method and framing board of buried concrete structure
JPS61261528A (en) Retaining wall with sheathing plate
JP2761531B2 (en) Construction method of guide for underground diaphragm wall
JP2933546B2 (en) Basement construction method and lower frame material used in the construction method
JPS6178927A (en) Construction of retaining wall
JP4195215B2 (en) Mountain retaining method and foundation construction method
JP2001323485A (en) Method of constructing underground structure
JPH05230842A (en) Construction method of underground structure
JPH03158527A (en) Creation method of concrete retaining wall and concrete block for retaining wall
JPH025843B2 (en)