JPH05156649A - Execution method for constructing structural stud - Google Patents

Execution method for constructing structural stud

Info

Publication number
JPH05156649A
JPH05156649A JP3327445A JP32744591A JPH05156649A JP H05156649 A JPH05156649 A JP H05156649A JP 3327445 A JP3327445 A JP 3327445A JP 32744591 A JP32744591 A JP 32744591A JP H05156649 A JPH05156649 A JP H05156649A
Authority
JP
Japan
Prior art keywords
structural stud
root
construction
vertical hole
foundation consolidation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3327445A
Other languages
Japanese (ja)
Other versions
JP2594724B2 (en
Inventor
Hiroshi Fujimura
博 藤村
Yukihiro Omika
侑弘 五十殿
Masachika Osada
正至 長田
Hiroshi Yoshida
宏 吉田
Hikari Sasao
光 笹尾
Minoru Kobayashi
小林  実
Hiroaki Kubo
弘明 久保
Minoru Yamamoto
稔 山本
Shunji Jinbo
俊次 神保
Shigetaka Suzuki
重孝 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHEM GURAUTO KK
Kajima Corp
Chemical Grouting Co Ltd
Original Assignee
CHEM GURAUTO KK
Kajima Corp
Chemical Grouting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHEM GURAUTO KK, Kajima Corp, Chemical Grouting Co Ltd filed Critical CHEM GURAUTO KK
Priority to JP3327445A priority Critical patent/JP2594724B2/en
Publication of JPH05156649A publication Critical patent/JPH05156649A/en
Application granted granted Critical
Publication of JP2594724B2 publication Critical patent/JP2594724B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To enhance the efficiency of construction work and to secure high accuracy in building a structural stud into a foundation consolidation portion by inserting a pipe into a vertical hole drilled in the ground, and injecting a jet to the foundation consolidation portion of the and building the structural stud into the foundation consolidation portion. CONSTITUTION:A vertical hole 2 is bored by rotation of a triple pipe 1 and a jet is injected from the end of the triple pipe 1 to cut the bent root portion of a structural stud 5. Then a stiffener is injected from the triple pipe 1 and substitues for and mixes with drilled earth and sand to form the foundation consolidation portion 3 of the structural stud 5 and form a mix 4 of earth, water and the stiffener. After the triple pipe 3 has been pulled, the structural stud 5 made by an H-steel is suspended down to build its end portion into the unhardended foundation consolidation portion 3. The structural stud 5 is fixed by jigs until the foundation consolidation portion 3 hardens enough to provide strength. Thereby junction of columns and beams can easily and surely be adjusted and the columns and the beams can be directly used, whereby economicity can be enhanced.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は地下階構造物の構築に
際し、柱・梁架構の山留め用の切梁等をつくるため、構
築に先立ち建込まれる構真柱の施工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a structure column to be built prior to the construction, in order to construct a girder or the like for retaining the pillar / beam frame when constructing a basement structure.

【0002】[0002]

【従来の技術】地下構造物を施工するには、従来仮設ま
たは本設としての鉄骨柱を建込み、仮設としての山留め
用の切梁や腹起材を架設し、地盤を掘削している。そし
て根切りの進行とともに、この切梁を下方へ、2段、3
段と順次増やすことで、深くまで地盤を掘削することが
可能となる。
2. Description of the Related Art In order to construct an underground structure, steel pillars have been conventionally constructed as temporary construction or permanent construction, and a girder for retaining a mountain and a ventilating material as temporary construction are installed to excavate the ground. Then, as the root cutting progresses, the beam is moved downwards in two steps, 3
By gradually increasing the number of steps, it becomes possible to dig deep into the ground.

【0003】鉄骨柱は構真柱と呼ばれ構造物の構築に先
立ち、杭工事時に建込み、続いて切梁や腹起材を架設し
て山留め壁の支持架構を構築し、次の掘削工事に移行す
る。
Steel columns are called structural columns, and they are built during the construction of piles prior to the construction of the structure, and then the beams and ponders are erected to construct the support frame for the mountain retaining wall and the next excavation work. Move to.

【0004】[0004]

【発明が解決しようとする課題】このような従来の工法
では、構真柱は杭工事の掘削が終了した後に建込み、続
いて杭のコンクリートを打ち込むことになる。そのた
め、掘削が終了した後に精度よく建込まれた構真柱は、
杭のコンクリートを打設する時に移動し、精度を保持す
ることが非常に困難であり、また、杭の直上部の構真柱
は地盤面まで、杭直径と同じ直径で掘削されているため
に、埋め戻しすることが必要となるなどの不都合があっ
た。
In such a conventional construction method, the structure columns are built after the excavation of the pile work is completed, and then the concrete of the pile is driven. Therefore, the structure pillars that were built accurately after the excavation was completed,
It is very difficult to move and maintain the accuracy when placing concrete for piles, and the structural columns directly above the piles are excavated to the ground surface with the same diameter as the pile diameter. However, there was an inconvenience that it was necessary to backfill.

【0005】この発明は上記問題点の解消を図ったもの
である。その目的は、施工作業の能率がよく、かつ、高
い建込み精度を確保できる構真柱の施工法を提案するに
ある。
The present invention is intended to solve the above problems. The purpose is to propose a construction method for a construction pillar that is highly efficient in construction work and that can secure high installation accuracy.

【0006】[0006]

【課題を解決するための手段】この発明は地下階構造物
の構築に先だち地中に建込む構真柱の施工法であって、
構真柱を建込むべき地盤に竪孔を削孔し、この竪孔にパ
イプを挿入し、構真柱の根固め部分に硬化材を含む超高
圧のジェット噴流を噴射し、周囲地盤を切削し、硬化材
が混入した大径柱状の根固め部を形成し、構真柱を前記
竪孔から吊込み、その先端部を未硬化の前記根固め部に
建入れ、根固め部の硬化により根固めすることを特徴と
する構真柱の施工法にある。
[Means for Solving the Problems] The present invention relates to a construction method for a structural pillar to be built underground before the construction of a basement structure,
A vertical hole is drilled in the ground where the structure column should be built, a pipe is inserted into this hole, and an ultra-high-pressure jet jet containing hardening material is injected to the root consolidation part of the structure column to cut the surrounding ground. Then, a large-diameter columnar root consolidation section mixed with a hardening material is formed, and the true column is hung from the vertical hole, and its tip is placed in the uncured root consolidation section, and the root consolidation section is hardened. This is a method of constructing a true pillar that is characterized by hardening.

【0007】[0007]

【作用】仮設用として構築した柱や梁を本設として使用
するには、柱の建入れ寸法、精度を可能な限りよくし、
梁は本設として柱に合理的に接合できる長さのものであ
ることが要求される。
[Operation] In order to use the pillars and beams constructed for temporary construction as main construction, the installation dimensions and accuracy of the pillars should be as good as possible,
The beam is required to have a length that can be reasonably joined to the column as a permanent installation.

【0008】この施工法では、構真柱を挿通して建込む
竪孔内には、地盤の比重とほぼ同等の混合体(土、水お
よび硬化材の混合物)が充満し、その下端部には硬化材
が混入した構真柱の根固め部がある。従って、竪孔内の
混合体および根固め部が柔らかいうちに、構真柱を吊込
み、垂直を保ち静置し根固め部が硬化するだけで、高精
度の建入れ寸法を確保することができる。従来のよう
に、コンクリートの打設による移動などで建込み精度の
低下を招くこともない。また、根固め部を超高圧のジェ
ット噴流を用い切削し、硬化材を混入し形成し、その上
の竪孔は構真柱を挿通する細径でよいので、従来の杭工
事に比べ作業能率を著しく高めることができる。
In this construction method, a mixture (soil, water and hardener mixture) having almost the same specific gravity as the ground is filled in the vertical hole inserted through the true structure column, and the lower end portion thereof is filled with the mixture. Has a solidified part of the structure pillar mixed with hardening material. Therefore, while the mixture in the pit and the root consolidation part are soft, the structure columns can be hung up and kept vertical and the root consolidation part can be hardened to ensure highly accurate installation dimensions. it can. Unlike in the past, the accuracy of construction will not be reduced due to movement such as placing concrete. In addition, the root consolidation part is cut by using an ultra-high pressure jet jet, mixed with hardened material to form it, and the vertical hole above it can be a small diameter to insert the true column, so work efficiency is higher than that of conventional pile construction. Can be significantly increased.

【0009】[0009]

【実施例】以下、図示する実施例により説明する。図1
〜5は実施例の施工を工程順に示すものである。図1に
おいて、所定の地盤位置にスーパージェット工法によ
り、先端から超高圧のジェット噴流を噴射するスーパー
ジェット用の三重管1を回転させ、所定深さの竪孔2を
穿設する。
Embodiments will be described below with reference to illustrated embodiments. Figure 1
5 to 5 show the construction of the example in the order of steps. In FIG. 1, a triple jet 1 for a super jet that jets a jet jet of ultra-high pressure is rotated from a tip end to a vertical hole 2 having a predetermined depth by a super jet method at a predetermined ground position.

【0010】つぎに図2において、三重管1の先端から
放射方向にジェット噴流を噴射しつつ、所定の回転数、
繰り返し回数および引上げピッチで構真柱の根固め部分
を切削する。図3において、必要な径、長さ切削し、同
時に切削土砂を竪孔2から地上に排出し、三重管1から
噴射した硬化材と切削土砂とを置換混合し大径柱状の構
真柱の根固め部3を形成する。根固め部3を形成したら
三重管1を地上に引き抜く。竪孔2内には地盤の比重と
ほぼ同等の土、水および硬化材の混合体4が残り充満さ
れる。
Next, referring to FIG. 2, while jetting a jet jet from the tip of the triple pipe 1 in a radial direction,
Cut the root consolidation part of the true column with the number of repetitions and the pulling pitch. In FIG. 3, cutting the required diameter and length, simultaneously discharging the cutting earth and sand from the pit 2 to the ground, replacing and mixing the hardened material injected from the triple pipe 1 and the cutting earth and sand The root consolidation part 3 is formed. After forming the root consolidation part 3, the triple pipe 1 is pulled out to the ground. The vertical hole 2 is filled with a mixture 4 of soil, water, and a hardening material, which has almost the same specific gravity as the ground.

【0011】図4,5において、H形鋼からなる構真柱
5を柔らかい混合体4が充満した竪孔2を挿通して吊込
み、その先端部を未硬化の根固め部3に建入れ、垂直に
保ち、根固め部3が硬化し、強度が発現まで、治具6で
仮固定し、静置する。根固め部3が硬化することで構真
柱5は固定され、施工は終了する。
In FIGS. 4 and 5, an H-shaped structural column 5 is hung through a vertical hole 2 filled with a soft mixture 4 and the tip end thereof is erected in an uncured root consolidation part 3. Then, it is kept vertical, and the root fixing portion 3 is hardened and temporarily fixed by the jig 6 until the strength is developed, and then left still. When the root-hardening part 3 hardens, the true column 5 is fixed and the construction is completed.

【0012】図6は地下構造物を構築すべき地盤7に、
この施工法により4本の構真柱5が建込んであり、その
周囲に山留めとなる連続壁8が設けられる。構真柱5の
地上部分に、図7のように従来の構築法と同様に梁9を
架設し、その柱・梁架構を地盤掘削のための山留め用の
切梁とする。
FIG. 6 shows a ground 7 on which an underground structure is to be constructed,
With this construction method, four structural columns 5 are built, and a continuous wall 8 serving as a mountain retaining is provided around it. As shown in FIG. 7, a beam 9 is erected on the ground portion of the structure column 5 as in the conventional construction method, and the column / beam structure is used as a retaining beam for earth excavation.

【0013】根切りの深さに応じて図8のごとく順次下
方へ2段目以下の梁9を架設し、地盤を掘削し地下構造
物の構築が進められる。
According to the depth of root cutting, as shown in FIG. 8, a beam 9 of the second stage or lower is sequentially installed downward, and the ground is excavated to construct an underground structure.

【0014】この実施例は、竪孔2の削孔と硬化材を混
入した大径柱状の根固め部の形成を、超高圧のジェット
噴流を利用するスーパージェット工法により、一つの装
置を用い施工し、一層の施工能率の向上を図ることがで
きた。
In this embodiment, the formation of a large-diameter column-shaped root-hardening portion mixed with a hardened material and the drilling of the vertical hole 2 is carried out by a super jet method utilizing an ultra-high pressure jet jet using one device. However, it was possible to further improve the construction efficiency.

【0015】[0015]

【発明の効果】この構真柱の施工法は以上の通りであ
り、次の効果を奏する。
The construction method of this structural pillar is as described above, and has the following effects.

【0016】 従来、山留め用の仮設として用いた構
真柱が高精度の建入れ寸法を確保することが可能となっ
たために、柱・梁接合の調整が簡単、確実となり、その
まま本設の柱・梁として利用可能となり、経済性が向上
した。
[0016] Because it has become possible to secure a highly accurate installation dimension for the true-tooth column that has been used as a temporary structure for mountain retaining, the adjustment of the column-beam joint becomes simple and reliable, and the column of the main structure is maintained as it is.・ Because it can be used as a beam, the economy has improved.

【0017】 従来の杭工事を伴なう構真柱の施工に
比べ、構真柱建込みの作業性が著しく向上した。
The workability of erection of a true pillar is significantly improved as compared with the conventional construction of a true pillar with a pile work.

【0018】 地下構造物の施工と同時に地上部の工
事も同時進行可能となり、生産性が向上した。
At the same time as the construction of the underground structure, the construction of the above-ground portion can proceed at the same time, and the productivity is improved.

【図面の簡単な説明】[Brief description of drawings]

図面は実施例の構真柱の施工工程および地下構造物の構
築の工程を順に示すものである。
The drawings show, in order, the construction process of the structural columns and the process of constructing the underground structure of the embodiment.

【図1】スーパージェット工法により地盤を削孔する工
程の一部断面で示す斜視図である。
FIG. 1 is a perspective view showing a partial cross section of a step of boring ground by a super jet method.

【図2】根固め部分を切削する工程の一部断面で示す斜
視図である。
FIG. 2 is a perspective view showing a partial cross section of a step of cutting a root consolidation portion.

【図3】硬化材を混入し根固め部を形成する工程の一部
断面で示す斜視図である。
FIG. 3 is a perspective view showing a partial cross section of a step of forming a root-hardening portion by mixing a hardening material.

【図4】構真柱を建込む工程の一部断面で示す斜視図で
ある。
FIG. 4 is a perspective view showing a partial cross section of a process of erection of a true column.

【図5】構真柱を建込み、根固めする工程の一部断面で
示す斜視図である。
FIG. 5 is a perspective view showing a partial cross section of the step of erection and consolidation of the true column.

【図6】建込んだ4本の構真柱の周囲に連続壁を設けた
工程の断面図であ。
FIG. 6 is a cross-sectional view of a process in which continuous walls are provided around four built-up false columns.

【図7】構真柱に梁を架設し柱・梁架構となした工程の
断面図である。
FIG. 7 is a cross-sectional view of a process in which a beam is erected on a true column to form a column / beam frame.

【図8】2段目に梁を架設し柱・梁架構となした工程の
断面図である。
FIG. 8 is a cross-sectional view of a step in which a beam is installed in the second stage to form a pillar / beam structure.

【符号の説明】[Explanation of symbols]

1…スーパージェット用の三重管、2…竪孔、3…根固
め部、4…混合体、5…構真柱、6…治具、7…地盤、
8…連続壁、9…梁。
DESCRIPTION OF SYMBOLS 1 ... Triple tube for super jets, 2 ... Vertical holes, 3 ... Root fixing part, 4 ... Mixing body, 5 ... Structural pillar, 6 ... Jig, 7 ... Ground,
8 ... Continuous wall, 9 ... Beam.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 長田 正至 東京都港区元赤坂1丁目2番7号 鹿島建 設株式会社内 (72)発明者 吉田 宏 東京都調布市飛田給2丁目19番1号 鹿島 建設株式会社技術研究所内 (72)発明者 笹尾 光 東京都調布市飛田給2丁目19番1号 鹿島 建設株式会社技術研究所内 (72)発明者 小林 実 東京都港区元赤坂1丁目2番7号 鹿島建 設株式会社内 (72)発明者 久保 弘明 東京都港区元赤坂1丁目6番4号安全ビル ケミカルグラウト株式会社内 (72)発明者 山本 稔 東京都港区元赤坂1丁目6番4号安全ビル ケミカルグラウト株式会社内 (72)発明者 神保 俊次 東京都港区元赤坂1丁目6番4号安全ビル ケミカルグラウト株式会社内 (72)発明者 鈴木 重孝 東京都港区元赤坂1丁目6番4号安全ビル ケミカルグラウト株式会社内 ─────────────────────────────────────────────────── ─── Continued Front Page (72) Inventor Masatoshi Nagata 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Hiroshi Yoshida 2--19-1, Tobita, Chofu-shi, Tokyo No. Kashima Construction Co., Ltd. Technical Research Institute (72) Inventor Hikaru Sasao 2-19-1, Tobita-cho, Chofu-shi, Tokyo Kashima Construction Co., Ltd. Technical Research Laboratory (72) Inventor Minoru Kobayashi 1-2-2 Moto-Akasaka, Minato-ku, Tokyo 7 Kashima Construction Co., Ltd. (72) Inventor Hiroaki Kubo 1-6-4 Moto-Akasaka, Minato-ku, Tokyo Safety Building in Chemical Grout Co., Ltd. (72) Minoru Yamamoto 1-6, Moto-Akasaka, Minato-ku, Tokyo No. 4 Safety Building in Chemical Grout Co., Ltd. (72) Inventor Shunji Jimbo 1-6-4 Moto-Akasaka, Minato-ku, Tokyo Safety Building Chemical Grout Co., Ltd. (72) Inventor Shigetaka Suzuki 1-6-4 Moto-Akasaka, Minato-ku, Tokyo Safety Building, inside Chemical Grout Co., Ltd.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 地下階構造物の構築に先だち地中に建込
む構真柱の施工法であって、構真柱を建込むべき地盤に
竪孔を削孔し、この竪孔にパイプを挿入し、構真柱の根
固め部分に硬化材を含む超高圧のジェット噴流を噴射
し、周囲地盤を切削し、硬化材が混入した大径柱状の根
固め部を形成し、構真柱を前記竪孔から吊込み、その先
端部を未硬化の前記根固め部に建入れ、根固め部の硬化
により根固めすることを特徴とする構真柱の施工法。
1. A method of constructing a structure pillar to be built underground before the construction of a basement structure, in which a vertical hole is drilled in the ground where the structure pillar is to be built, and a pipe is installed in this vertical hole. Insert, inject a super-high pressure jet jet containing hardening material into the root consolidation portion of the structure column, cut the surrounding ground, form a large diameter columnar root consolidation part mixed with the curing material, and A method for constructing a structure pillar, which comprises suspending from a vertical hole, building a tip portion thereof into the uncured root-hardening portion, and hardening the root-hardening portion to harden the root.
JP3327445A 1991-12-11 1991-12-11 Construction method of trussed pillar Expired - Fee Related JP2594724B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3327445A JP2594724B2 (en) 1991-12-11 1991-12-11 Construction method of trussed pillar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3327445A JP2594724B2 (en) 1991-12-11 1991-12-11 Construction method of trussed pillar

Publications (2)

Publication Number Publication Date
JPH05156649A true JPH05156649A (en) 1993-06-22
JP2594724B2 JP2594724B2 (en) 1997-03-26

Family

ID=18199250

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3327445A Expired - Fee Related JP2594724B2 (en) 1991-12-11 1991-12-11 Construction method of trussed pillar

Country Status (1)

Country Link
JP (1) JP2594724B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60119818A (en) * 1983-11-30 1985-06-27 Asahi Chem Ind Co Ltd Construction work of custom-made pile
JPH01295913A (en) * 1988-05-24 1989-11-29 Tousen Asano Paul Kk Constructing method for enlarged bulb of large caliber pile, and its apparatus

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60119818A (en) * 1983-11-30 1985-06-27 Asahi Chem Ind Co Ltd Construction work of custom-made pile
JPH01295913A (en) * 1988-05-24 1989-11-29 Tousen Asano Paul Kk Constructing method for enlarged bulb of large caliber pile, and its apparatus

Also Published As

Publication number Publication date
JP2594724B2 (en) 1997-03-26

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
JP3211673B2 (en) Simple temporary bridge temporary pier construction method
US3412562A (en) Structural wall and method
JP2874561B2 (en) Fore piling method with stiffening of the leading leg using a shaft
CN218934444U (en) High-pressure horizontal jet grouting pile tunnel reinforcing structure in frozen soil area
JP3129676B2 (en) Piling columns in building structures using piles as pillars
JP2868651B2 (en) Earth retaining method above existing underground structure
JPS59126821A (en) Erection work of foundation pile
JPH05156649A (en) Execution method for constructing structural stud
CN109235453B (en) Deep foundation pit PRC pipe pile assembled supporting method
GB2261891A (en) Installing columns e.g. below ground
CN210564379U (en) Rock wall beam excavation sample frame
JP2001146739A (en) Construction method for impervious wall
JPH0559215B2 (en)
JP4314681B2 (en) Reverse strut construction method
JPH07197469A (en) Structure of earth retaining wall and earth retaining method
JPS59145822A (en) Construction work of underground continuous wall
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPS6128774B2 (en)
JPS5869924A (en) Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
JP2991736B2 (en) Basement wall installation method
JPH0461129B2 (en)
CN116163739A (en) High-pressure horizontal jet grouting pile tunnel reinforcing structure and method in frozen soil area
JPS6138015A (en) Sheathing work

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19961112

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees