JP2594724B2 - Construction method of trussed pillar - Google Patents

Construction method of trussed pillar

Info

Publication number
JP2594724B2
JP2594724B2 JP3327445A JP32744591A JP2594724B2 JP 2594724 B2 JP2594724 B2 JP 2594724B2 JP 3327445 A JP3327445 A JP 3327445A JP 32744591 A JP32744591 A JP 32744591A JP 2594724 B2 JP2594724 B2 JP 2594724B2
Authority
JP
Japan
Prior art keywords
ground
pillar
construction
jet
triple pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP3327445A
Other languages
Japanese (ja)
Other versions
JPH05156649A (en
Inventor
博 藤村
侑弘 五十殿
正至 長田
宏 吉田
光 笹尾
小林  実
弘明 久保
稔 山本
俊次 神保
重孝 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Chemical Grouting Co Ltd
Original Assignee
Kajima Corp
Chemical Grouting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Chemical Grouting Co Ltd filed Critical Kajima Corp
Priority to JP3327445A priority Critical patent/JP2594724B2/en
Publication of JPH05156649A publication Critical patent/JPH05156649A/en
Application granted granted Critical
Publication of JP2594724B2 publication Critical patent/JP2594724B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は地下階構造物の構築に
際し、柱・梁架構の山留め用の切梁等をつくるため、構
築に先立ち建込まれる構真柱の施工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a prefabricated pillar to be constructed prior to construction in order to form a beam for retaining a pillar or a beam frame when constructing a basement structure.

【0002】[0002]

【従来の技術】地下構造物を施工するには、従来仮設ま
たは本設としての鉄骨柱を建込み、仮設としての山留め
用の切梁や腹起材を架設し、地盤を掘削している。そし
て根切りの進行とともに、この切梁を下方へ、2段、3
段と順次増やすことで、深くまで地盤を掘削することが
可能となる。
2. Description of the Related Art Conventionally, in order to construct an underground structure, a steel column as a temporary or permanent construction is erected, and a cut-off girder or a raised material is temporarily provided as a temporary construction, and the ground is excavated. Then, as the root cutting progresses, the cutting beam is moved downward in two steps, 3
By gradually increasing the steps, it becomes possible to excavate the ground deeply.

【0003】鉄骨柱は構真柱と呼ばれ構造物の構築に先
立ち、杭工事時に建込み、続いて切梁や腹起材を架設し
て山留め壁の支持架構を構築し、次の掘削工事に移行す
る。
Prior to the construction of a structure, a steel column is called a timber column, and is built during pile construction, followed by cutting beams and erection materials to construct a support frame for a retaining wall, and then performing the next excavation work Move to

【0004】[0004]

【発明が解決しようとする課題】このような従来の工法
では、構真柱は杭工事の掘削が終了した後に建込み、続
いて杭のコンクリートを打ち込むことになる。そのた
め、掘削が終了した後に精度よく建込まれた構真柱は、
杭のコンクリートを打設する時に移動し、精度を保持す
ることが非常に困難であり、また、杭の直上部の構真柱
は地盤面まで、杭直径と同じ直径で掘削されているため
に、埋め戻しすることが必要となるなどの不都合があっ
た。
In such a conventional construction method, the timber pillar is built after the excavation of the pile work is completed, and then the concrete of the pile is driven. Therefore, the timber pillars that were accurately built after the excavation was completed,
It is very difficult to move the pile when placing the concrete, and it is very difficult to maintain the accuracy.In addition, the straight column directly above the pile is excavated to the ground surface with the same diameter as the pile diameter. However, there is an inconvenience that backfilling is required.

【0005】この発明は上記問題点の解消を図ったもの
である。その目的は、施工作業の能率がよく、かつ、高
い建込み精度を確保できる構真柱の施工法を提案するに
ある。
The present invention has been made to solve the above problems. An object of the present invention is to propose a method of constructing a straight pillar that is efficient in construction work and can ensure high installation accuracy.

【0006】[0006]

【課題を解決するための手段】 この発明の構真柱の施工
方法は、地下階構造物の構築に先だち地中に建込む構真
柱の施工法であり、まず先端から超高圧のジェット噴流
を噴射するスーパージェット用の三重管を回転させて
真柱を建込むべき地盤に竪孔を削孔する。 次いで、上記
三重管の先端から放射方向にジェット噴流を噴射しつつ
所定の回転数、繰り返し回数、および引上げピッチで、
構真柱の根固め部分を切削するとともに、切削土砂を竪
孔から地上に排出し、三重管からは硬化材を噴射し、こ
の硬化材と切削土砂とを置換交換し大径柱状の根固め部
分を形成する。 続いて、三重管を地上に引き抜きなが
ら、竪孔内に地盤の比率とほぼ同等の土、水および硬化
材の混合体を充満させる。 その上で、構真柱を掘削した
上記竪孔から吊込み、その先端部を未硬化の根固め部に
建入れし、根固め部の硬化により根固めする。
SUMMARY OF THE INVENTION Construction of a straight pillar according to the present invention
Method, construction methods der of構真columns Ken writes in the area prior to the construction of the basement floor structure is, first, from the tip of the ultra-high pressure jet stream
The triple pipe for the super jet that injects water is rotated to drill a vertical hole in the ground where the trussed pillar is to be built . Then,
Injecting a jet jet radially from the tip of the triple tube
At a given number of revolutions, number of repetitions, and pulling pitch,
While cutting the solidified part of the trussed pillar, the ground
Exhaust to the ground through the hole, spray hardener from the triple pipe,
Replacement of hardened material with cutting earth and sand to replace large-diameter columnar
Form a minute. Then, pull out the triple tube to the ground
Soil, water, and hardening in the pit
Fill the mixture of materials. On top of that, a shaft was excavated
Suspended from the above-mentioned pit, the tip of which is uncured
Ken put in, and you root hardened by the hardening of the root hardened part.

【0007】[0007]

【作用】仮設用として構築した柱や梁を本設として使用
するには、柱の建入れ寸法、精度を可能な限りよくし、
梁は本設として柱に合理的に接合できる長さのものであ
ることが要求される。
[Function] In order to use pillars and beams built for temporary construction as main construction, make the pillar dimensions and accuracy as good as possible,
The beam is required to be of a length that can be reasonably joined to the pillar as a permanent construction.

【0008】この施工法では、構真柱を挿通して建込む
竪孔内には、地盤の比重とほぼ同等の混合体(土、水お
よび硬化材の混合物)が充満し、その下端部には硬化材
が混入した構真柱の根固め部がある。従って、竪孔内の
混合体および根固め部が柔らかいうちに、構真柱を吊込
み、垂直を保ち静置し根固め部が硬化するだけで、高精
度の建入れ寸法を確保することができる。従来のよう
に、コンクリートの打設による移動などで建込み精度の
低下を招くこともない。また、根固め部を超高圧のジェ
ット噴流を用い切削し、硬化材を混入し形成し、その上
の竪孔は構真柱を挿通する細径でよいので、従来の杭工
事に比べ作業能率を著しく高めることができる。
In this construction method, a mixture (a mixture of soil, water and hardening material) substantially equal to the specific gravity of the ground is filled in a pit which is built by inserting a timber column, and the lower end portion is filled with the mixture. There is a rooted portion of a pillar made of hardened material mixed. Therefore, while the mixture in the pit and the consolidation part are soft, it is possible to secure a high-precision installation dimension only by suspending the straight pillar, standing vertically and allowing the consolidation part to harden. it can. Unlike the prior art, there is no possibility of lowering the installation accuracy due to movement due to concrete placement. In addition, the root consolidation part is cut using an ultra-high pressure jet jet, a hardening material is mixed and formed, and the vertical hole above it can be a small diameter that can be inserted through a straight column, so work efficiency can be reduced compared to conventional pile construction. Can be significantly increased.

【0009】[0009]

【実施例】以下、図示する実施例により説明する。図1
〜5は実施例の施工を工程順に示すものである。図1に
おいて、所定の地盤位置にスーパージェット工法によ
り、先端から超高圧のジェット噴流を噴射するスーパー
ジェット用の三重管1を回転させ、所定深さの竪孔2を
穿設する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a description will be given with reference to the illustrated embodiment. FIG.
5 show the construction of the embodiment in the order of steps. In FIG. 1, a triple pipe 1 for a super jet for jetting a super high pressure jet jet from a tip is rotated by a super jet method at a predetermined ground position, and a vertical hole 2 having a predetermined depth is formed.

【0010】つぎに図2において、三重管1の先端から
放射方向にジェット噴流を噴射しつつ、所定の回転数、
繰り返し回数および引上げピッチで構真柱の根固め部分
を切削する。図3において、必要な径、長さ切削し、同
時に切削土砂を竪孔2から地上に排出し、三重管1から
噴射した硬化材と切削土砂とを置換混合した大径柱状の
構真柱の根固め部3を形成する。根固め部3を形成した
前記三重管1を地上に引き抜きながら竪孔2内には地盤
の比重とほぼ同等の土、水および硬化材の混合体4が残
り充満される。
Next, referring to FIG. 2, while jetting a jet stream in a radial direction from the tip of the triple tube 1, a predetermined rotation speed,
The rooted part of the pillar is cut with the number of repetitions and the pulling pitch. In FIG. 3, the required diameter and length are cut, and at the same time, the cut soil is discharged from the pit 2 to the ground, and the hardened material injected from the triple pipe 1 is mixed with the cut sand to form a large-diameter pillar-shaped straight pillar. The root consolidation part 3 is formed. While pulling out the triple pipe 1 on which the root consolidation portion 3 has been formed to the ground, a mixture 4 of soil, water and hardening material having substantially the same specific gravity as the ground remains in the vertical hole 2.

【0011】図4,5において、H形鋼からなる構真柱
5を柔らかい混合体4が充満した竪孔2を挿通して吊込
み、その先端部を未硬化の根固め部3に建入れ、垂直に
保ち、根固め部3が硬化し、強度が発現まで、治具6で
仮固定し、静置する。根固め部3が硬化することで構真
柱5は固定され、施工は終了する。
In FIGS. 4 and 5, a straight pillar 5 made of an H-shaped steel is suspended by passing through a vertical hole 2 filled with a soft mixture 4 and its tip is erected in an unhardened rooting part 3. Then, it is temporarily fixed with the jig 6 and left standing until the root stiffening portion 3 is hardened and the strength is developed. The trussed pillar 5 is fixed by the hardening of the root consolidation part 3, and the construction is completed.

【0012】図6は地下構造物を構築すべき地盤7に、
この施工法により4本の構真柱5が建込んであり、その
周囲に山留めとなる連続壁8が設けられる。構真柱5の
地上部分に、図7のように従来の構築法と同様に梁9を
架設し、その柱・梁架構を地盤掘削のための山留め用の
切梁とする。
FIG. 6 shows a ground 7 on which an underground structure is to be constructed.
By this construction method, four straight pillars 5 are built, and a continuous wall 8 serving as a mountain retaining is provided therearound. As shown in FIG. 7, a beam 9 is erected on the ground portion of the trussed pillar 5 in the same manner as in the conventional construction method, and the column / beam framing is used as a cutting beam for digging for excavating the ground.

【0013】根切りの深さに応じて図8のごとく順次下
方へ2段目以下の梁9を架設し、地盤を掘削し地下構造
物の構築が進められる。
According to the depth of the root cutting, as shown in FIG. 8, the beams 9 of the second stage or less are sequentially erected, and the ground is excavated to construct the underground structure.

【0014】この実施例は、竪孔2の削孔と硬化材を混
入した大径柱状の根固め部の形成を、超高圧のジェット
噴流を利用するスーパージェット工法により、一つの装
置を用い施工し、一層の施工能率の向上を図ることがで
きた。
In this embodiment, the drilling of the pit 2 and the formation of a large-diameter columnar root consolidation part mixed with a hardening material are carried out using a single apparatus by a super jet method utilizing an ultra-high pressure jet jet. The construction efficiency was further improved.

【0015】[0015]

【発明の効果】この構真柱の施工法は以上の通りであ
り、次の効果を奏する。
The construction method of this straight pillar is as described above, and has the following effects.

【0016】 従来、山留め用の仮設として用いた構
真柱が高精度の建入れ寸法を確保することが可能となっ
たために、柱・梁接合の調整が簡単、確実となり、その
まま本設の柱・梁として利用可能となり、経済性が向上
した。
Conventionally, since a timber column used as a temporary mounting for a mountain retaining structure can secure high-precision installation dimensions, the adjustment of the column-beam connection is simple and reliable, and the main column is installed as it is. -It can be used as a beam, improving economic efficiency.

【0017】 従来の杭工事を伴なう構真柱の施工に
比べ、構真柱建込みの作業性が著しく向上した。また地
下構造物の施工と同時に地上部の工事も同時進行可能と
なり、生産性が向上した。
[0017] The workability of building a timber column is significantly improved as compared with the conventional timber column construction with pile work. In addition, the construction of the above-ground part can proceed at the same time as the construction of the underground structure, improving productivity.

【0018】 構真材は地下構造物の本設の柱として
精度よく建込まれ、支持されるため、掘削のための山留
め用切梁を構真柱に取付けることができる。また根固め
部は直径5m以上の大口径体を形成して、建物の基礎を
その上に載せて支持することができる。
Since the timber is accurately built and supported as a permanent pillar of an underground structure, a girder cut beam for excavation can be attached to the timber pillar. In addition, the bolster portion forms a large-diameter body having a diameter of 5 m or more, and the foundation of the building can be placed thereon and supported.

【図面の簡単な説明】[Brief description of the drawings]

図面は実施例の構真柱の施工工程および地下構造物の構
築の工程を順に示すものである。
The drawings show, in order, the construction process of the timber pillar and the construction process of the underground structure of the embodiment.

【図1】スーパージェット工法により地盤を削孔する工
程の一部断面で示す斜視図である。
FIG. 1 is a perspective view showing a partial cross section of a step of drilling a ground by a super jet method.

【図2】根固め部分を切削する工程の一部断面で示す斜
視図である。
FIG. 2 is a perspective view showing a partial cross section of a step of cutting a root compaction portion.

【図3】硬化材を混入し根固め部を形成する工程の一部
断面で示す斜視図である。
FIG. 3 is a perspective view showing a partial cross section of a step of mixing a hardening material to form a root compaction portion.

【図4】構真柱を建込む工程の一部断面で示す斜視図で
ある。
FIG. 4 is a perspective view showing a partial cross section of a process of erection of a straight pillar.

【図5】構真柱を建込み、根固めする工程の一部断面で
示す斜視図である。
FIG. 5 is a perspective view showing a partial cross section of a process of building and buckling a timber pillar.

【図6】建込んだ4本の構真柱の周囲に連続壁を設けた
工程の断面図であ。
FIG. 6 is a cross-sectional view of a process in which a continuous wall is provided around four built-in straight pillars.

【図7】構真柱に梁を架設し柱・梁架構となした工程の
断面図である。
FIG. 7 is a sectional view of a process in which a beam is erected on a straight pillar to form a pillar / beam frame.

【図8】2段目に梁を架設し柱・梁架構となした工程の
断面図である。
FIG. 8 is a cross-sectional view of a process in which a beam is erected on the second stage to form a column / beam frame.

【符号の説明】[Explanation of symbols]

1…スーパージェット用の三重管、2…竪孔、3…根固
め部、4…混合体、5…構真柱、6…治具、7…地盤、
8…連続壁、9…梁。
DESCRIPTION OF SYMBOLS 1 ... Triple pipe for super jets, 2 ... Vertical hole, 3 ... Root consolidation part, 4 ... Mixed body, 5 ... Straight pillar, 6 ... Jig, 7 ... Ground,
8 ... continuous wall, 9 ... beam.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 長田 正至 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (72)発明者 吉田 宏 東京都調布市飛田給2丁目19番1号 鹿 島建設株式会社技術研究所内 (72)発明者 笹尾 光 東京都調布市飛田給2丁目19番1号 鹿 島建設株式会社技術研究所内 (72)発明者 小林 実 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (72)発明者 久保 弘明 東京都港区元赤坂1丁目6番4号安全ビ ル ケミカルグラウト株式会社内 (72)発明者 山本 稔 東京都港区元赤坂1丁目6番4号安全ビ ル ケミカルグラウト株式会社内 (72)発明者 神保 俊次 東京都港区元赤坂1丁目6番4号安全ビ ル ケミカルグラウト株式会社内 (72)発明者 鈴木 重孝 東京都港区元赤坂1丁目6番4号安全ビ ル ケミカルグラウト株式会社内 (56)参考文献 特開 昭60−119818(JP,A) 特開 平1−295913(JP,A) ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Masayoshi Nagata 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Hiroshi Yoshida 2-9-1-1 Tobita-Shi, Chofu-shi, Tokyo Kashima Construction Co., Ltd. (72) Inventor Hikaru Sasao 2-9-1-1, Tobita-Shi, Chofu-shi, Tokyo Kashima Construction Co., Ltd. (72) Inventor Minoru Kobayashi 1-2-2 Moto-Akasaka, Minato-ku, Tokyo No. 7 Kashima Construction Co., Ltd. (72) Inventor Hiroaki Kubo 1-6-4 Moto-Akasaka, Minato-ku, Tokyo Inside safety building Chemical Grout Co., Ltd. (72) Inventor Minoru Yamamoto 1-chome Moto-Akasaka, Minato-ku, Tokyo No. 6-4 Safety Bill Chemical Grout Co., Ltd. (72) Inventor Shunji Jimbo 1-6-4 Moto-Akasaka Minato-ku, Tokyo Safety Bill Chemical Grout Co., Ltd. In-house (72) Inventor Shigetaka Suzuki 1-6-4 Moto-Akasaka, Minato-ku, Tokyo Safety Building Chemical Grout Co., Ltd. (56) References JP-A-60-119818 (JP, A) JP-A-1-295913 (JP, A)

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地下構造物の構築に先だち地中に建込
む構真柱の施工法であって、先端から超高圧のジェット
噴流を噴射するスーパージェット用の三重管を回転させ
構真柱を建込むべき地盤に竪孔を削孔し、次いで前記
三重管の先端から放射方向にジェット噴流を噴射しつつ
所定の回転数、繰り返し回数、および引上げピッチで構
真柱の根固め部分を切削するとともに、切削土砂を竪孔
から地上に排出し、三重管から硬化材を噴射し、この硬
化材と切削土砂とを置換交換し大径柱状の根固め部分を
形成し、前記三重管を地上に引き抜きながら、前記竪孔
内には地盤の比率とほぼ同等の土、水および硬化材の混
合体を充満させ、さらに構真柱を前記竪孔から吊込み、
その先端部を未硬化の前記根固め部に建入れ、根固め
部の硬化により根固めすることを特徴とする構真柱の施
工法。
1. A method for constructing a timber pillar to be built in the ground prior to the construction of an underground floor structure, comprising: rotating a triple pipe for a super jet for jetting an ultra-high pressure jet jet from the tip.
Configuration Te and drilling the Tateana the ground to writing denominated the構真column, then a predetermined speed while injecting jet flow radially from the tip of the <br/> triple pipe, in number of repetitions, and pulling the pitch Along with cutting the solidified part of the true pillar, the cut soil is discharged from the pit into the ground, the hardening material is injected from the triple pipe, and this hardened material is replaced with the cut sand to replace the large-diameter columnar solidified part. formed, while pulling the triple pipe on the ground, said in Tateana is filled with mixture of approximately equal soil, water and a curing material as the ratio of the ground, further Tsukomi the構真column from the Tateana,
Construction methods of構真pillar, characterized in that the tip is placed denominated in the root consolidated portion of the uncured and roots solidified by curing of the root hardened portion.
JP3327445A 1991-12-11 1991-12-11 Construction method of trussed pillar Expired - Fee Related JP2594724B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3327445A JP2594724B2 (en) 1991-12-11 1991-12-11 Construction method of trussed pillar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3327445A JP2594724B2 (en) 1991-12-11 1991-12-11 Construction method of trussed pillar

Publications (2)

Publication Number Publication Date
JPH05156649A JPH05156649A (en) 1993-06-22
JP2594724B2 true JP2594724B2 (en) 1997-03-26

Family

ID=18199250

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3327445A Expired - Fee Related JP2594724B2 (en) 1991-12-11 1991-12-11 Construction method of trussed pillar

Country Status (1)

Country Link
JP (1) JP2594724B2 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0627405B2 (en) * 1983-11-30 1994-04-13 旭化成工業株式会社 Ready-made pile burying method
JPH0786231B2 (en) * 1988-05-24 1995-09-20 東扇アサノポール株式会社 How to build an enlarged bulb for large diameter piles

Also Published As

Publication number Publication date
JPH05156649A (en) 1993-06-22

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
JP3211673B2 (en) Simple temporary bridge temporary pier construction method
CN105909262B (en) A kind of bored tunnel driving method
JP2874561B2 (en) Fore piling method with stiffening of the leading leg using a shaft
CN218934444U (en) High-pressure horizontal jet grouting pile tunnel reinforcing structure in frozen soil area
JP4115095B2 (en) Reverse strike method
JP2594724B2 (en) Construction method of trussed pillar
JP2868651B2 (en) Earth retaining method above existing underground structure
CN109235453B (en) Deep foundation pit PRC pipe pile assembled supporting method
CN115419076A (en) Construction method for high-pressure rotary spraying recoverable anchor cable support of deep foundation pit
CN110410082B (en) Tunnel excavation advance support method
CN110924985A (en) Long rock pillar construction method suitable for overlying thin rock stratum
JP2858997B2 (en) Temporary support column used for reverse driving method
JP2958426B2 (en) Differential settlement correction method
JPH0280710A (en) Preparing cast-in-place concrete pile
JP4314681B2 (en) Reverse strut construction method
CN217352449U (en) Manual hole digging pile advance support system and conveying device
JPH0559215B2 (en)
JPH09125405A (en) Deep foundation for inclined tower leg
JPS6128774B2 (en)
JPS6124491B2 (en)
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JP2567990B2 (en) Reverse construction method for underground construction
JPS615118A (en) Formation work of over-all friction pile
JP2700700B2 (en) Construction method of underground continuous wall based on underground tunnel

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19961112

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees