CN116163739A - High-pressure horizontal jet grouting pile tunnel reinforcing structure and method in frozen soil area - Google Patents

High-pressure horizontal jet grouting pile tunnel reinforcing structure and method in frozen soil area Download PDF

Info

Publication number
CN116163739A
CN116163739A CN202211666570.5A CN202211666570A CN116163739A CN 116163739 A CN116163739 A CN 116163739A CN 202211666570 A CN202211666570 A CN 202211666570A CN 116163739 A CN116163739 A CN 116163739A
Authority
CN
China
Prior art keywords
pile
tunnel
vault
pile body
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211666570.5A
Other languages
Chinese (zh)
Inventor
乔志兵
张牛
申旭明
杨帆
陈稳干
李栋
李晓雨
缪鞍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 10 Engineering Group Co Ltd
Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
China Railway No 10 Engineering Group Co Ltd
Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 10 Engineering Group Co Ltd, Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd filed Critical China Railway No 10 Engineering Group Co Ltd
Priority to CN202211666570.5A priority Critical patent/CN116163739A/en
Publication of CN116163739A publication Critical patent/CN116163739A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/35Foundations formed in frozen ground, e.g. in permafrost soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to the technical field of tunnel reinforcement, in particular to a high-pressure horizontal jet grouting pile tunnel reinforcement structure and method in a frozen soil area. The reinforcement structure comprises a vault reinforcement body which is circumferentially arranged at the tunnel face along the side wall of the tunnel, wherein two sides of the vault reinforcement body respectively extend to the anchoring structures of the lower slopes at two sides of the tunnel; the vault reinforcing body is provided with a plurality of pile bodies which are sequentially in a snap-in arrangement, and the pile bodies are formed by adopting rotary spraying slurry through a horizontal rotary spraying machine. The reinforcement method is used for realizing the reinforcement structure. The invention has multiple functions of improving the strength of the composite soil body, preventing seepage, resisting skidding, pre-supporting and the like, so the comprehensive effect is better.

Description

High-pressure horizontal jet grouting pile tunnel reinforcing structure and method in frozen soil area
Technical Field
The invention relates to the technical field of tunnel reinforcement, in particular to a high-pressure horizontal jet grouting pile tunnel reinforcement structure and method in a frozen soil area.
Background
In recent years, the railway construction in China is developed at a high speed, and tunnel engineering related to the railway construction is also increasing. The tunnel engineering is used as one of underground engineering, and the construction of the tunnel engineering can cause surrounding rock disturbance, and macroscopic appearance is shown in tunnel deformation and earth surface subsidence. Especially, the surrounding rock has poor stability and is rich in groundwater, water burst, mud burst and even collapse can be caused, and the tunnel construction safety accident is caused, so that the soil in front of the tunnel face needs to be supported in advance before the tunnel construction.
The existing tunnel reinforcement structure and method for the frozen soil area still have the defects of poor efficiency, long construction period and the like.
Disclosure of Invention
The invention provides a high-pressure horizontal jet grouting pile tunnel reinforcing structure in a frozen soil area, which can overcome certain or certain defects in the prior art.
The invention relates to a high-pressure horizontal jet grouting pile tunnel reinforcing structure in a frozen soil area, which comprises a vault reinforcing body arranged at a tunnel face along the circumferential direction of the side wall of a tunnel, wherein two sides of the vault reinforcing body respectively extend to anchoring structures of lower slopes at two sides of the tunnel; the vault reinforcing body is provided with a plurality of pile bodies which are sequentially in a snap-in arrangement, and the pile bodies are formed by adopting rotary spraying slurry through a horizontal rotary spraying machine.
The reinforcing structure has multiple functions of improving the strength of a composite soil body, preventing seepage, resisting skidding, pre-supporting and the like, so that the comprehensive effect is better. Because the soil body and the cement slurry can be well mixed in the high-pressure rotary spraying process of the pile body, a concrete-like consolidated body can be formed, and the overall strength of the vault reinforcing body can be superior to that of a conventional cement structure. In addition, because the cement slurry injected at high pressure can crush larger blocky soil bodies in the rotary spraying process of the horizontal rotary spraying machine, the cement slurry can be fully mixed with the soil bodies, and the uniformity of the vault reinforcing body is good. In addition, the rotary spraying slurry of the horizontal rotary spraying machine only acts on the pile body area, so that the control of the design requirements on the range, the strength and the like of the arch top reinforcing body can be preferably realized.
Preferably, the pile body has a diameter of 500mm and a length of 15m, and the circumferential spacing between adjacent pile bodies is 35cm. So that the pile body can have better strength.
Preferably, the external insertion angle of the pile body is 3 °. So that the pile body can have better strength.
Preferably, grouting steel pipes are arranged in the middle of the pile body positioned in the 120-degree range of the tunnel arch part, and are used for forming a grouting reinforcement structure at the arch crown reinforcing body through grouting. So the reinforcement strength of the vault reinforcement body to the tunnel vault area can be further improved.
Preferably, the length of the grouting steel pipe is identical to the length of the pile body. So that the subsequent grouting step can be preferably realized.
Preferably, the hydraulic pile further comprises a face reinforcement body arranged at the upper part of the face, wherein the face reinforcement body comprises a plurality of face reinforcement piles formed by adopting horizontal rotary cement slurry through a high-pressure rotary cement slurry spraying machine. Therefore, the reinforcement of the face can be better realized.
The invention also provides a method for reinforcing the high-pressure horizontal jet grouting pile tunnel in the frozen soil area, which comprises the following steps:
forming a single pile body by rotary spraying, namely forming horizontal hole positions corresponding to the pile body through a horizontal rotary spraying machine, and after the corresponding horizontal hole positions are formed, withdrawing a drill rod of the horizontal rotary spraying machine and spraying cement slurry by rotary spraying;
forming a vault reinforcing body, namely forming a vault pile body by rotary spraying, wherein the vault pile body is a pile body positioned at a vault of a tunnel; then, forming a first group of piles in a rotary spraying mode from top to bottom and alternately left to right with the previous formed piles at intervals of 1 pile; and then, performing spin-spraying forming on the position of the 1 pile body at intervals to form a second group of pile bodies.
By the method of the embodiment, the collapse of the tunnel can be effectively prevented, the safety of construction in the tunnel, road driving and pipelines is ensured, and other relevant reinforcement measures and cost are avoided for the tunnel; and the progress is greatly improved, the mechanized operation is facilitated, the mechanical utilization rate is improved, and the energy waste is reduced.
Preferably, the cement slurry has a mud to water ratio of 1:1.
Drawings
FIG. 1 is a schematic view of the reinforcing structure in embodiment 1;
fig. 2 is a schematic diagram of the reinforcement method in example 1.
Detailed Description
For a further understanding of the present invention, the present invention will be described in detail with reference to examples. It is to be understood that the examples are illustrative of the present invention and are not intended to be limiting.
Example 1
Referring to fig. 1, the present embodiment provides a high-pressure horizontal jet grouting pile tunnel reinforcement structure in a frozen soil area, which includes a vault reinforcement body 100 circumferentially arranged at a tunnel face along a tunnel sidewall, wherein two sides of the vault reinforcement body 100 extend to anchor structures 30 of lower slopes at two sides of the tunnel respectively; the vault stiffener 100 has a plurality of sequentially snap-in piles 110, the piles 110 being formed by a horizontal rotary sprayer using a rotary cement slurry.
The reinforcing structure of the embodiment has multiple functions of improving the strength of a composite soil body, preventing seepage, resisting skidding, pre-supporting and the like, so that the comprehensive effect is better. Because the soil body and the cement slurry can be well mixed in the high-pressure rotary spraying process of the pile body 110, a concrete-like consolidated body can be formed, and the overall strength of the vault reinforcing body 100 can be superior to that of a conventional cement structure. In addition, in the rotary spraying process of the horizontal rotary spraying machine, the cement slurry injected at high pressure can crush larger massive soil bodies, so that the cement slurry can be fully mixed with the soil bodies, and the uniformity of the vault reinforcing body 100 is good. In addition, since the rotary cement slurry of the horizontal rotary jetting machine acts only on the pile body 110 region, the control of the design requirements such as the range and strength of the arch reinforcing body 100 can be preferably realized.
It will be appreciated that the horizontal rotary jetting machine employed in this embodiment is an existing apparatus, and the principle of high pressure horizontal rotary jetting slurry is also an existing principle. The method comprises the following steps: adopting horizontal directional drilling, stirring a drill rod and spraying slurry into soil after drilling to a designed depth, cutting a soil layer by means of the impact force of fluid, and changing the soil structure; in the pile body 110 forming process, the drill rod can be kept to rotate at a low speed and be pulled out slowly, meanwhile, cement slurry can be sprayed to the soil body in a horizontal rotary mode, and after the cement slurry is cemented and hardened, the pile body 110 with uniform diameter and certain strength can be formed, so that the vault reinforcing body 100 is obtained.
In addition, the pile body 110 in this embodiment can form a closed horizontal jet grouting curtain body, i.e., the vault reinforcing body 100, on the vault and the periphery of the tunnel in a concentric circle-like manner by sequentially snap-fitting. The vault reinforcement 100 can have beam effect, arch effect and soil body improvement reinforcement effect at the same time, so that the vault reinforcement 100 can better play roles in preventing drift sand from slipping and ensuring tunneling safety; meanwhile, in the process of spraying cement slurry in a rotary mode, the cement slurry can permeate and diffuse along gaps of the stratum, and particularly in the stratum with larger water inflow, the cement slurry can fill the gaps through diffusion, so that a better water stopping effect can be achieved.
In this embodiment, the diameter of the pile body 110 is 500mm, the length is 15m, and the circumferential spacing between the adjacent pile bodies 110 is 35cm (i.e. 15cm of engagement between the adjacent pile bodies 110). So that the pile body 110 can have better strength.
In this embodiment, the external insertion angle of the pile body 110 is 3 ° (the inclination angle from the horizontal plane and the upward inclination). So that the pile body 110 can have better strength.
The reinforcing structure in this embodiment can be preferably applied to the reinforcing scenes of weak strata such as various railways, highway tunnels and the like, and the reinforcing range can be set 50cm below the soil-stone boundary.
In this embodiment, grouting steel pipes 120 are disposed in the middle of the pile body 110 located in the 120 ° range of the tunnel arch portion, and the grouting steel pipes 120 are used to form a grouting reinforcement structure at the arch crown reinforcement body 100 through grouting. The reinforcement strength of the dome reinforcement body 100 to the tunnel dome area can be further improved.
In this embodiment, the grouting pipe 120 can be a pipe having a diameter of 76mm and a length of 15 m.
In this embodiment, the length of the grouting steel pipe 120 is identical to the length of the pile body 110. So that the subsequent grouting step can be preferably realized.
The reinforcing structure in this embodiment further includes a face reinforcing body disposed on an upper portion of the face, where the face reinforcing body includes a plurality of face reinforcing piles 130 formed by horizontal rotary cement slurry spraying through a high pressure rotary cement spraying machine. Therefore, the reinforcement of the face can be better realized.
In this embodiment, the number of the face reinforcing piles 130 is 5, the length is 10m, and the diameter is 500mm.
In this embodiment, the lower slopes on two sides of the tunnel refer to two sides of the lower step when the existing three-step temporary transverse bracing construction method is adopted for pit excavation. Wherein, the face reinforcement can be located the step department of going up. Wherein the anchoring structure 30 can be a cartridge anchor.
Based on the reinforcing structure of the embodiment, when the high-pressure horizontal jet grouting pile tunnel in the frozen soil area is reinforced, the following steps can be specifically performed:
the rotary spraying forming of the single pile body 110 is carried out, a horizontal hole site corresponding to the pile body 110 is formed through a horizontal rotary spraying machine, and after the corresponding horizontal hole site is formed, a drill rod of the horizontal rotary spraying machine is retracted and cement slurry is sprayed in a rotary mode;
forming a vault reinforcing body 100, namely, forming a vault pile body by rotary spraying, wherein the vault pile body is a pile body 110 positioned at a vault of a tunnel; then, the first group of piles (left 2, right 2, left 4 and right 4 … …) are formed by spin-spraying from top to bottom and alternately from left to right with the previous formed pile 110 at intervals of 1 pile 110; thereafter, a second set of piles (left 1, right 1, left 3, right 3, … …) were spin-molded at the positions spaced by 1 pile 110.
By the method of the embodiment, the collapse of the tunnel can be effectively prevented, the safety of construction in the tunnel, road driving and pipelines is ensured, and other relevant reinforcement measures and cost are avoided for the tunnel; and the progress is greatly improved, the mechanized operation is facilitated, the mechanical utilization rate is improved, and the energy waste is reduced.
In the practical application of a specific project, the construction period is shortened by 50 days, the work efficiency is improved by 0.5 times, and the number of times of operators is saved by about 1000 times.
In this example, the slurry ratio of the slurry was 1:1. The cement can be P.O42.5 ordinary Portland cement, and the cement slurry can be configured in a tunnel and conveyed to the face.
In this embodiment, the horizontal rotary jetting machine can employ a PG185-T horizontal rotary jetting machine.
In this embodiment, the horizontal hole position of each pile 110 can be measured first, and then the drill rod can be guided by the guide rail orientation.
In this embodiment, after each horizontal hole site exits the drill bit, a plug is used to plug the hole, and a grouting steel pipe 120 is inserted into the pile body 110 that is not completely cured, and grouting can be performed through the grouting steel pipe 120 after the pile body 110 is initially set to form a grouting reinforcement structure.
It is to be understood that, based on one or several embodiments provided herein, those skilled in the art may combine, split, reorganize, etc. the embodiments of the present application to obtain other embodiments, which do not exceed the protection scope of the present application.
The invention and its embodiments have been described above by way of illustration and not limitation, and the examples are merely illustrative of embodiments of the invention and the actual construction is not limited thereto. Therefore, if one of ordinary skill in the art is informed by this disclosure, the structural mode and the embodiments similar to the technical scheme are not creatively designed without departing from the gist of the present invention.

Claims (8)

1. High-pressure horizontal jet grouting pile tunnel reinforcing structure in frozen soil area, its characterized in that: the tunnel comprises a vault reinforcing body (100) which is circumferentially arranged at the tunnel face along the side wall of the tunnel, wherein two sides of the vault reinforcing body (100) respectively extend to anchoring structures (30) of lower slopes at two sides of the tunnel; the vault reinforcing body (100) is provided with a plurality of pile bodies (110) which are sequentially in a snap-in arrangement, and the pile bodies (110) are formed by adopting rotary spraying slurry through a horizontal rotary spraying machine.
2. The frozen soil area high pressure horizontal jet grouting pile tunnel reinforcing structure of claim 1, wherein: the diameter of the pile body (110) is 500mm, the length is 15m, and the circumferential spacing between the adjacent pile bodies (110) is 35cm.
3. The high-pressure horizontal jet grouting pile tunnel reinforcing structure in a frozen soil area according to claim 1 or 2, wherein: the external insertion angle of the pile body (110) is 3 degrees.
4. The high-pressure horizontal jet grouting pile tunnel reinforcing structure in a frozen soil area according to claim 1 or 2, wherein: grouting steel pipes (120) are arranged in the middle of the pile body (110) in the range of 120 degrees of the tunnel arch part, and the grouting steel pipes (120) are used for forming a grouting reinforcement structure at the arch crown reinforcement body (100) through grouting.
5. The frozen soil area high pressure horizontal jet grouting pile tunnel reinforcing structure of claim 1, wherein: the length of the grouting steel pipe (120) is consistent with the length of the pile body (110).
6. The frozen soil area high pressure horizontal jet grouting pile tunnel reinforcing structure of claim 1, wherein: the hydraulic pile comprises a hydraulic pile body, and is characterized by further comprising a hydraulic pile reinforcement body arranged at the upper part of the hydraulic pile body, wherein the hydraulic pile body comprises a plurality of hydraulic pile reinforcement piles (130) formed by adopting horizontal rotary cement slurry through a high-pressure rotary cement slurry spraying machine.
7. The method for reinforcing the high-pressure horizontal jet grouting pile tunnel in the frozen soil area comprises the following steps:
forming a single pile body (110) by rotary spraying, namely forming horizontal hole positions corresponding to the pile body (110) through a horizontal rotary spraying machine, and after the corresponding horizontal hole positions are formed, withdrawing a drill rod of the horizontal rotary spraying machine and spraying cement slurry in a rotary way;
forming a vault reinforcing body (100), namely, forming a vault pile body by rotary spraying, wherein the vault pile body is a pile body (110) positioned at a tunnel vault; then, the first group of pile bodies are formed by spin spraying from top to bottom and alternately from left to right with the previous formed pile body (110) at intervals of 1 pile body (110); and then, forming a second group of piles in a rotary spraying mode at the position of 1 pile body (110) at intervals.
8. The method for reinforcing the high-pressure horizontal jet grouting pile tunnel in the frozen soil area, which is characterized by comprising the following steps of: the mud-water ratio of the cement slurry is 1:1.
CN202211666570.5A 2022-12-23 2022-12-23 High-pressure horizontal jet grouting pile tunnel reinforcing structure and method in frozen soil area Pending CN116163739A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211666570.5A CN116163739A (en) 2022-12-23 2022-12-23 High-pressure horizontal jet grouting pile tunnel reinforcing structure and method in frozen soil area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211666570.5A CN116163739A (en) 2022-12-23 2022-12-23 High-pressure horizontal jet grouting pile tunnel reinforcing structure and method in frozen soil area

Publications (1)

Publication Number Publication Date
CN116163739A true CN116163739A (en) 2023-05-26

Family

ID=86421125

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211666570.5A Pending CN116163739A (en) 2022-12-23 2022-12-23 High-pressure horizontal jet grouting pile tunnel reinforcing structure and method in frozen soil area

Country Status (1)

Country Link
CN (1) CN116163739A (en)

Similar Documents

Publication Publication Date Title
CN109538216B (en) Tunnel construction process for crossing mining and subsidence areas
CN110130927A (en) A kind of carbonaceous slate serious deformation control construction method
CN105525619B (en) A kind of water rich strata bored tunnel occlusion pipe curtain
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN109931077B (en) Support system for tunnel repair and construction method thereof
CN111677520B (en) Construction method for excavating station structure by tunnel-first station-later station pipe curtain hole-pile method
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN108265706A (en) Engineering pile in karst cave geology and pile forming process
CN105464685A (en) Cave-pile method bored tunnel waterproof curtain and construction method thereof
CN102660955A (en) Quick construction method for foundation pit slope support
CN110284885A (en) Shield inspection-pit construction method
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN113803074A (en) Construction method of tunnel structure for artificial and mechanical combined obstacle removal of water-rich sand layer
CN218934444U (en) High-pressure horizontal jet grouting pile tunnel reinforcing structure in frozen soil area
CN108457670B (en) Construction method for large-section tunnel to penetrate through upper-hard lower-soft water-rich stratum
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
CN112012746A (en) Construction method of railway tunnel deep and large vertical shaft under condition of thick-layer water-rich broken zone
CN110566236A (en) Pipe shed and steel support combined supporting device and supporting method
CN112031801B (en) Settlement control method for underground tunnel to pass through existing operation line
CN101338567B (en) Construction method for underground buildings by rotary-spray shaft digging method cooperating with semi-inverse method
CN103615265B (en) Soft rock tunnel horizontal jet grouting construction method
CN109695453B (en) Auxiliary excavation construction method for vertical shaft main tunnel three-dimensional intersection
CN116398165A (en) New tunnel penetrating through existing station at zero distance and construction method thereof
CN217438921U (en) Anchor rod and isolation pile combined reinforcing structure for protecting excavation of side tunnel of foundation pit
CN109751056A (en) A kind of water rich strata shield-tunneling construction active well end processing method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination