JPH05112928A - Steel pipe pile column construction method - Google Patents
Steel pipe pile column construction methodInfo
- Publication number
- JPH05112928A JPH05112928A JP30690991A JP30690991A JPH05112928A JP H05112928 A JPH05112928 A JP H05112928A JP 30690991 A JP30690991 A JP 30690991A JP 30690991 A JP30690991 A JP 30690991A JP H05112928 A JPH05112928 A JP H05112928A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pipe piles
- press
- pipe pile
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Revetment (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、土留め壁や護岸、或い
は建築物の基礎等に利用される鋼管杭柱列の構築工法に
関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a steel pipe pile column array used for earth retaining walls, revetments, foundations of buildings and the like.
【0002】[0002]
【従来の技術】従来の鋼管杭柱列は、外周面の直径方向
2か所にC形断面又はT形断面の連結部材を軸心方向に
沿って固着突設された特殊な連結部材付き鋼管杭、即ち
鋼管杭矢板を使用し、この鋼管杭矢板を、隣接する連結
部材どうしが互いに嵌合するように、柱列状に近接圧入
することにより構築していた。2. Description of the Related Art A conventional steel pipe pile column is a steel pipe with a special connecting member in which two connecting members having a C-shaped section or a T-shaped section are fixedly projecting along the axial direction at two radial positions on the outer peripheral surface. A pile, that is, a steel pipe pile sheet pile is used, and the steel pipe pile sheet pile is constructed by press-fitting in a column shape so that adjacent connecting members fit to each other.
【0003】[0003]
【発明が解決しようとする課題】上記のような鋼管杭矢
板を使用する従来の工法では、鋼管周面から大きく張り
出した連結部材が邪魔になって、鋼管杭そのものを回転
させながら圧入させることが出来ないので、圧入する鋼
管杭矢板の内部で地盤を掘削する中堀り用アースオーガ
ーが必要であり、しかも鋼管杭矢板の上端を把持して圧
入する、長尺リーダー付きの大型杭打機が必要であるた
め、施工コストが高くつくばかりでなく、河川の護岸補
修工事のように柱列構築場所の上方空間が高速道路の橋
脚等によって制限されるような場所では、実施不可能に
なる欠点もあった。更に、所要口径の鋼管に連結部材を
溶接する加工作業が必要であり、鋼管そのままを活用出
来ない不便があった。In the conventional method of using the steel pipe pile sheet pile as described above, the connecting member that largely protrudes from the peripheral surface of the steel pipe interferes and the steel pipe pile itself can be press-fitted while rotating. Since it is not possible, a grounding auger for excavating the ground inside the steel pipe pile sheet pile to be press-fitted is required, and a large pile driver with a long leader that grips the upper end of the steel pipe pile sheet pile and press-fits is required. Therefore, not only is the construction cost high, but there is also the drawback that it cannot be implemented in locations where the space above the column construction site is limited by the piers of the expressway, such as revetment repair work on rivers. there were. Further, since a working operation of welding the connecting member to the steel pipe having a required diameter is required, there is an inconvenience that the steel pipe cannot be used as it is.
【0004】[0004]
【課題を解決するための手段】本発明は上記のような従
来の問題点を解決するために、外周面に連結部材が突設
されていない鋼管杭を適当間隔おきに所定深さまで圧入
し、隣接する鋼管杭の間には、2本の小口径鋼管を両鋼
管杭の最接近位置の左右両側に振り分けて所要深さまで
圧入し、この2本の小口径鋼管と両側の鋼管杭とで囲ま
れた領域内にモルタル充填等の止水処理を施すことを特
徴とする鋼管杭柱列構築工法を提案するものである。In order to solve the above-mentioned conventional problems, the present invention press-fits steel pipe piles on the outer peripheral surface of which no connecting member is projected to a predetermined depth at appropriate intervals, Between the adjacent steel pipe piles, two small-diameter steel pipes are distributed to the left and right sides of the closest position of both steel pipe piles and press-fitted to the required depth, surrounded by these two small-diameter steel pipes and the steel pipe piles on both sides. We propose a steel pipe pile column construction method, which is characterized by performing water-stopping treatment such as mortar filling in a closed area.
【0005】[0005]
【実施例】以下、本発明の一実施例を添付の例示図に基
づいて説明すると、図1及び図2に於いて、1は本発明
工法によって構築された護岸用鋼管杭柱列であり、2は
当該鋼管杭柱列1の上端に構築した頭繋部である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the accompanying drawings. In FIGS. 1 and 2, reference numeral 1 represents a steel pipe pile column for a sea wall constructed by the method of the present invention, Reference numeral 2 is a head connecting portion constructed on the upper end of the steel pipe pile column array 1.
【0006】前記鋼管杭柱列1は、図3にも示すよう
に、外周面に軸心方向に沿った連結部材が突設されてい
ない鋼管杭3を適当間隔おきに回転させながら圧入し、
隣接する鋼管杭3の間に、2本の小口径鋼管4,5を両
鋼管杭3の最接近位置の左右両側に振り分けて所要深さ
まで圧入し、この2本の小口径鋼管4,5と両側の鋼管
杭3とで囲まれた領域6内にモルタル7を充填すること
により構成したものである。In the steel pipe pile column array 1, as shown in FIG. 3, the steel pipe piles 3 on the outer peripheral surface of which the connecting members along the axial direction do not project are press-fitted while rotating at appropriate intervals.
Between the adjacent steel pipe piles 3, two small-diameter steel pipes 4, 5 are distributed to the left and right sides of the closest positions of both steel pipe piles 3 and press-fitted to the required depth. It is configured by filling a mortar 7 in a region 6 surrounded by the steel pipe piles 3 on both sides.
【0007】前記鋼管杭3の回転圧入作業には、図4に
示すように、垂直に立設されたリーダー8に沿って昇降
せしめられる本体9の下側に、チャック10を備えた回
転リング11を支承する可動フレーム12をシリンダー
ユニット13により昇降可能に結合した、杭打機を使用
することが出来る。即ち、前記本体9及び回転リング1
1に貫通させた前記鋼管杭3をチャック10により当該
回転リング11に固定し、当該鋼管杭3が地盤で支持さ
れる高さまで前記本体9をリーダー8に対して下降させ
た状態で当該本体9をリーダー8に固定し、係る状態で
回転リング11をモーター14で回転駆動させると共に
シリンダーユニット13により可動フレーム12を強制
下降させ、可動フレーム12が本体9に対し下降限位置
まで下降したならば、チャック10を開放した後にシリ
ンダーユニット13により可動フレーム12を上昇限位
置まで上昇させ、再びチャック10で鋼管杭3を回転リ
ング11に固定する動作を反復させることにより、鋼管
杭3を回転駆動しながらシリンダーユニット13のスト
ローク分づつ間歇的に圧入することが出来る。For rotary press-fitting work of the steel pipe pile 3, as shown in FIG. 4, a rotary ring 11 having a chuck 10 is provided below a main body 9 which can be raised and lowered along a vertically standing leader 8. It is possible to use a pile driving machine in which a movable frame 12 for supporting the above is connected by a cylinder unit 13 so as to be able to move up and down. That is, the main body 9 and the rotating ring 1
The steel pipe pile 3 penetrating through 1 is fixed to the rotating ring 11 by a chuck 10, and the main body 9 is lowered with respect to the leader 8 to a height at which the steel pipe pile 3 is supported by the ground. Is fixed to the leader 8, and the rotating ring 11 is rotationally driven by the motor 14 in such a state, and the movable frame 12 is forcibly lowered by the cylinder unit 13, and if the movable frame 12 is lowered to the lower limit position with respect to the main body 9, After the chuck 10 is opened, the movable frame 12 is raised to the upper limit position by the cylinder unit 13, and the operation of fixing the steel pipe pile 3 to the rotary ring 11 by the chuck 10 again is repeated, so that the steel pipe pile 3 is driven to rotate. It is possible to press-fit intermittently for each stroke of the cylinder unit 13.
【0008】鋼管杭3は、必要な垂直支持強度が得られ
るように図1に示す如く河川床15から所要深さD1ま
で回転圧入されるが、全長が長くなるときは、複数本の
単位長さの鋼管杭を現場溶接その他の方法で順次接続し
て回転圧入される。勿論、この鋼管杭3に圧入方法は、
上記の回転圧入方法に限定されるものではなく、状況に
よっては従来の振動杭打ち機によるバイブロハンマー工
法や、中掘り圧入工法等により圧入することも可能であ
る。The steel pipe pile 3 is rotationally press-fitted from the river bed 15 to the required depth D1 as shown in FIG. 1 so as to obtain the required vertical support strength, but when the total length becomes long, a plurality of unit lengths are used. Steel pipe piles are sequentially connected by on-site welding or other methods, and then press-fitted by rotation. Of course, the method of press fitting into this steel pipe pile 3 is
The method is not limited to the above rotary press-fitting method, and depending on the situation, it is also possible to perform press-fitting by a conventional vibro hammer method using a vibrating pile driver, a hollow digging press-fitting method, or the like.
【0009】前記小口径鋼管4,5は、既に回転圧入さ
れて2本の鋼管杭3間に、1本づつ又は2本同時に、振
動杭打ち機によるバイブロハンマー工法やウォータージ
ェット併用の圧入工法等により垂直に圧入されるが、鋼
管杭3間の止水効果を得るために、河川床15から当該
止水効果を得ることの出来る深さD2まで圧入される。
勿論、当該小口径鋼管4,5の上端は、鋼管杭3の上端
と略同一レベルに位置する。The small-diameter steel pipes 4 and 5 have already been rotationally press-fitted into the two steel pipe piles 3, one by one or two at the same time, and the vibro hammer construction method using a vibrating pile driving machine or the press-fitting construction method using water jet together. Although it is vertically press-fitted with the steel pipe piles 3, it is press-fitted from the river bed 15 to a depth D2 at which the water-stopping effect can be obtained in order to obtain the water-stopping effect between the steel pipe piles 3.
Of course, the upper ends of the small diameter steel pipes 4 and 5 are located at substantially the same level as the upper ends of the steel pipe piles 3.
【0010】前記2本の小口径鋼管4,5と両側の鋼管
杭3とで囲まれた領域6内にモルタル7を充填するに際
しては、当該領域6内をウォータージェットにより洗浄
して泥土を排出した後、図5に示すように、当該領域6
内にモルタル充填用筒状袋16が挿入され、このモルタ
ル充填用筒状袋16内にモルタル7がモルタルポンプに
より充填される。而して、当該袋16の周面が前記小口
径鋼管4,5の周面と両側の鋼管杭3の周面とに密着し
た状態でモルタル7が硬化することにより、所期の止水
効果が得られる。When filling the mortar 7 into the area 6 surrounded by the two small diameter steel pipes 4 and 5 and the steel pipe piles 3 on both sides, the area 6 is washed with a water jet to discharge mud. Then, as shown in FIG.
The cylindrical bag 16 for mortar filling is inserted therein, and the mortar 7 is filled by the mortar pump in the cylindrical bag 16 for mortar filling. Thus, the mortar 7 is hardened while the peripheral surface of the bag 16 is in close contact with the peripheral surfaces of the small-diameter steel pipes 4 and 5 and the peripheral surfaces of the steel pipe piles 3 on both sides, whereby the desired water blocking effect is obtained. Is obtained.
【0011】図5では、1つのモルタル充填用筒状袋1
6が領域6内に挿入されている状態を示しているが、前
記領域6の横断面積の大きさ、或いは使用するモルタル
充填用筒状袋16の直径によっては、複数本のモルタル
充填用筒状袋16を並列状に挿入することになる。又、
前記モルタル充填用筒状袋16の併用は、前記2本の小
口径鋼管4,5と両側の鋼管杭3との間の隙間よりモル
タルが流出してしまうのを防止するためであるから、図
1の河川床15より下の地盤内に位置する領域6に対し
ては、当該領域6の周囲が地盤で囲まれていて、前記領
域6内よりモルタルが流出してしまう恐れが実質的にな
いので、前記モルタル充填用筒状袋16の挿入は省くこ
とが出来る。In FIG. 5, one cylindrical bag 1 for mortar filling is used.
6 shows the state of being inserted into the region 6, but depending on the size of the cross-sectional area of the region 6 or the diameter of the mortar-filling tubular bag 16 to be used, a plurality of mortar-filling tubular forms may be used. The bags 16 will be inserted side by side. or,
The joint use of the mortar-filling tubular bag 16 is to prevent mortar from flowing out from the gap between the two small-diameter steel pipes 4, 5 and the steel pipe piles 3 on both sides. For the area 6 located in the ground below the river bed 15 of No. 1, the area 6 is surrounded by the ground, and there is substantially no risk of mortar flowing out of the area 6. Therefore, the insertion of the mortar-filling tubular bag 16 can be omitted.
【0012】尚、本発明工法によって構築される鋼管杭
柱列の用途は、図1及び図2に示すような護岸壁に限定
されないが、護岸壁として使用するときは、図1及び図
2に示すように頭繋部2は、鉄筋コンクリートや鋼材に
より構築することが出来、必要に応じて、水面上に露出
する鋼管杭柱列1の上部外側面をカバーする化粧パネル
17を併設したり、頭繋部2を遊歩道として使用するた
めの手摺り18を併設することも出来る。又、前記2本
の小口径鋼管4,5と両側の鋼管杭3とで囲まれた領域
6内に対する止水処理として、泥土を洗浄排出してモル
タル7を充填する工法を採用したが、当該領域6内に土
壌が存在する場合には硬化剤を注入する工法等も採用出
来る。Note that the use of the steel pipe pile column constructed by the method of the present invention is not limited to the revetment wall as shown in FIGS. 1 and 2, but when it is used as a revetment wall, it is as shown in FIGS. As shown, the head connecting part 2 can be constructed by reinforced concrete or steel material, and if necessary, a decorative panel 17 for covering the upper outer surface of the steel pipe pile column 1 exposed on the water surface is provided side by side, or the head is connected. A handrail 18 for using the connecting portion 2 as a promenade can also be provided. Further, as the water stop treatment for the region 6 surrounded by the two small diameter steel pipes 4 and 5 and the steel pipe piles 3 on both sides, a method of cleaning and discharging mud and filling the mortar 7 is adopted. When soil exists in the area 6, a method of injecting a hardening agent can be adopted.
【0013】[0013]
【発明の作用及び効果】本発明工法は以上の如く実施し
得るものであって、係る本発明工法によれば、外周面に
連結部材が突設されていない鋼管杭を圧入するのである
から、圧入する鋼管杭内部の地盤を掘削するアースオー
ガーが不要であり、又、実施例でも説明したように鋼管
杭の中間部を把持して回転圧入するタイプの低空間用杭
打機を活用して鋼管杭圧入作業を行うことが出来るの
で、柱列構築場所の上方空間が制限されるような場所で
も、支障なく鋼管杭柱列を構築することが出来る。The method and method of the present invention can be carried out as described above. According to the method of the present invention, a steel pipe pile having no connecting member protruding from the outer peripheral surface is press-fitted. It is not necessary to use an earth auger to excavate the ground inside the steel pipe pile to be press-fitted, and as described in the embodiment, a low space pile driver of the type that grips the middle part of the steel pipe pile and press-fits it by rotation is utilized. Since the steel pipe pile press-fitting work can be performed, the steel pipe pile column can be constructed without any trouble even in a place where the space above the column formation site is limited.
【0014】しかも鋼管杭間には、2本の小口径鋼管を
両鋼管杭に最接近位置の左右両側に振り分けて所要深さ
まで圧入し、この2本の小口径鋼管と両側に鋼管杭とで
囲まれた領域内にモルタル充填等の止水処理を施すので
あるから、鋼管杭間隔のばらつきが大きくとも前記小口
径鋼管を支障なく打設して、所期通りの止水効果を得る
ことが出来る。Moreover, between the steel pipe piles, two small-diameter steel pipes are distributed to both steel pipe piles on the left and right sides of the closest position and press-fitted to the required depth, and the two small-diameter steel pipes and the steel pipe piles on both sides are formed. Since water-stopping treatment such as mortar filling is performed in the enclosed area, it is possible to drive the small-diameter steel pipes without any problems even if there are large variations in the intervals between the steel pipe piles, and obtain the desired water-stopping effect. I can.
【0015】更に、鋼管杭としては所要口径の鋼管をそ
のまま活用することが出来、止水用ジョイントにも所要
口径の小口径鋼管をそのまま活用することが出来るの
で、低コストで止水効果のある護岸等が構築出来る。Further, as the steel pipe pile, a steel pipe having a required diameter can be used as it is, and a small diameter steel pipe having a required diameter can also be used as it is for the water shutoff joint. You can build a seawall.
【図1】本発明工法により構築された護岸壁の正面図で
ある。FIG. 1 is a front view of a seawall constructed by the method of the present invention.
【図2】同縦断側面図である。FIG. 2 is a vertical sectional side view of the same.
【図3】同要部の横断平面図である。FIG. 3 is a cross-sectional plan view of the main part.
【図4】鋼管杭の回転圧入方法を説明する一部切り欠き
側面図である。FIG. 4 is a partially cutaway side view for explaining a method for rotationally press-fitting a steel pipe pile.
【図5】図3の要部の拡大横断平面図である。5 is an enlarged cross-sectional plan view of the main part of FIG.
1…護岸用鋼管杭柱列 3…鋼管杭 4,5…小口径鋼管 6…止水処理を施す領域 7…モルタル 16…モルタル充填用筒状袋 1 ... Steel pipe pile columns for seawalls 3 ... Steel pipe piles 4, 5 ... Small diameter steel pipes 6 ... Water-stop treatment area 7 ... Mortar 16 ... Mortar filling tubular bag
───────────────────────────────────────────────────── フロントページの続き (72)発明者 川端 則之 東京都千代田区大手町2丁目6番3号 新 日本製鐵株式会社内 (72)発明者 岡林 正宏 大阪市北区中之島3丁目2番4号 新日本 製鐵株式会社大阪支店内 (72)発明者 柴田 厚志 千葉県市川市高谷新町4 株式会社クボタ 市川工場内 (72)発明者 柿本 龍二 千葉県市川市高谷新町4 株式会社クボタ 市川工場内 (72)発明者 森 瑞樹 大阪市大正区小林東1丁目2番44号 株式 会社藤井組内 (72)発明者 原田 和彦 大阪市大正区小林東1丁目2番44号 株式 会社藤井組内 (72)発明者 藤田 親 東京都港区芝浦1丁目2番3号 清水建設 株式会社内 (72)発明者 大澤 泰 東京都港区芝浦1丁目2番3号 清水建設 株式会社内 (72)発明者 長江 哲生 東京都港区芝浦1丁目2番3号 清水建設 株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Noriyuki Kawabata 2-3-6 Otemachi, Chiyoda-ku, Tokyo Within Nippon Steel Corporation (72) Masahiro Okabayashi 3-2-1 Nakanoshima, Kita-ku, Osaka No. 4 Shin-Nippon Steel Corporation Osaka Branch (72) Inventor Atsushi Shibata 4 Takaya Shinmachi, Ichikawa City, Chiba Prefecture Kubota Ichikawa Plant, Inc. (72) Inventor Ryuji Kakimoto 4 Takaya Shinmachi, Ichikawa City, Chiba Prefecture Kubota Ichikawa Plant, Inc. (72) Inventor Mizuki Mori 1-24-44, Kobayashi Higashi, Taisho-ku, Osaka City Fujii Gumi Co., Ltd. (72) Inventor Kazuhiko Harada 1-2-44 Kobayashi Higashi, Taisho-ku, Osaka City Fujii Gumi Co., Ltd. ( 72) Inventor Chika Fujita 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Yasushi Osawa 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Incorporated (72) Inventor Tetsuo Nagae 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation
Claims (1)
杭を適当間隔おきに所定深さまで圧入し、隣接する鋼管
杭の間には、2本の小口径鋼管を両鋼管杭の最接近位置
の左右両側に振り分けて所要深さまで圧入し、この2本
の小口径鋼管と両側の鋼管杭とで囲まれた領域内にモル
タル充填等の止水処理を施すことを特徴とする鋼管杭柱
列構築工法。1. A steel pipe pile having no connecting member protruding from the outer peripheral surface thereof is press-fitted to a predetermined depth at appropriate intervals, and two small-diameter steel pipes are inserted between adjacent steel pipe piles at the maximum of both steel pipe piles. Steel pipe piles that are distributed to the left and right sides of the approaching position and press-fitted to the required depth, and water-stop treatment such as mortar filling is performed in the area surrounded by these two small diameter steel pipes and the steel pipe piles on both sides. Column construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30690991A JP2948384B2 (en) | 1991-10-24 | 1991-10-24 | Steel pipe pile column construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30690991A JP2948384B2 (en) | 1991-10-24 | 1991-10-24 | Steel pipe pile column construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH05112928A true JPH05112928A (en) | 1993-05-07 |
JP2948384B2 JP2948384B2 (en) | 1999-09-13 |
Family
ID=17962733
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP30690991A Expired - Lifetime JP2948384B2 (en) | 1991-10-24 | 1991-10-24 | Steel pipe pile column construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2948384B2 (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005133348A (en) * | 2003-10-28 | 2005-05-26 | Giken Seisakusho Co Ltd | Continuous construction method of revetment, and method of widening river or the like |
JP6227824B1 (en) * | 2017-05-26 | 2017-11-08 | 朝日エンヂニヤリング株式会社 | Mountain retaining structure using piles |
JP2019002186A (en) * | 2017-06-14 | 2019-01-10 | 株式会社技研製作所 | Method for constructing cut-off wall |
JP2019002187A (en) * | 2017-06-14 | 2019-01-10 | 株式会社技研製作所 | Method for recovering solidification material of cut-off wall, and cut-off wall |
JP2019039158A (en) * | 2017-08-23 | 2019-03-14 | 株式会社技研製作所 | Construction method of water cut-off wall |
JP2019065642A (en) * | 2017-10-04 | 2019-04-25 | 株式会社技研製作所 | Mounting structure for excavation blade of steel pipe pile, annular excavation tool and press-in method for steel pipe pile |
JP2019127765A (en) * | 2018-01-25 | 2019-08-01 | 大成建設株式会社 | Ground improvement apparatus and ground improvement method |
KR102077830B1 (en) * | 2019-09-20 | 2020-02-14 | 주식회사 지오이엔비 | Cutoff wall using pressing possible water-proofing apparatus and temporary wall construction method using the same |
JP2020045614A (en) * | 2018-09-14 | 2020-03-26 | 株式会社技研製作所 | Continuous wall and construction method therefor |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7357524B2 (en) * | 2019-12-02 | 2023-10-06 | 株式会社竹中工務店 | Yamadome waterproofing method |
-
1991
- 1991-10-24 JP JP30690991A patent/JP2948384B2/en not_active Expired - Lifetime
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005133348A (en) * | 2003-10-28 | 2005-05-26 | Giken Seisakusho Co Ltd | Continuous construction method of revetment, and method of widening river or the like |
JP6227824B1 (en) * | 2017-05-26 | 2017-11-08 | 朝日エンヂニヤリング株式会社 | Mountain retaining structure using piles |
JP2018199931A (en) * | 2017-05-26 | 2018-12-20 | 朝日エンヂニヤリング株式会社 | Earth retaining structure using piles |
JP2019002186A (en) * | 2017-06-14 | 2019-01-10 | 株式会社技研製作所 | Method for constructing cut-off wall |
JP2019002187A (en) * | 2017-06-14 | 2019-01-10 | 株式会社技研製作所 | Method for recovering solidification material of cut-off wall, and cut-off wall |
JP2019039158A (en) * | 2017-08-23 | 2019-03-14 | 株式会社技研製作所 | Construction method of water cut-off wall |
JP2019065642A (en) * | 2017-10-04 | 2019-04-25 | 株式会社技研製作所 | Mounting structure for excavation blade of steel pipe pile, annular excavation tool and press-in method for steel pipe pile |
JP2019127765A (en) * | 2018-01-25 | 2019-08-01 | 大成建設株式会社 | Ground improvement apparatus and ground improvement method |
JP2020045614A (en) * | 2018-09-14 | 2020-03-26 | 株式会社技研製作所 | Continuous wall and construction method therefor |
KR102077830B1 (en) * | 2019-09-20 | 2020-02-14 | 주식회사 지오이엔비 | Cutoff wall using pressing possible water-proofing apparatus and temporary wall construction method using the same |
Also Published As
Publication number | Publication date |
---|---|
JP2948384B2 (en) | 1999-09-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH05112928A (en) | Steel pipe pile column construction method | |
US3429126A (en) | Method of producing a continuous bore pile wall | |
KR100415809B1 (en) | precast pile for braced wall and the method using the same | |
KR100375020B1 (en) | a pole for mud wall and constrution method of fence for mud | |
JP3423394B2 (en) | Underwater frame structure | |
JP2001115458A (en) | Deep well construction method using earth retaining wall | |
JPH05112929A (en) | Steel pipe pile column construction method | |
JP2007009505A (en) | Foundation reinforcing method | |
JPH0619124B2 (en) | Steel pipe pile column construction method | |
WO2009139510A1 (en) | Construction method for continuous cut-off wall using overlap casing | |
JP2005146756A (en) | Earth retaining impervious wall construction method and earth retaining impervious wall formed by it | |
KR19990042532A (en) | Bridge construction of wells and drywall equipment | |
KR200296444Y1 (en) | Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method | |
JPS638249B2 (en) | ||
CN115492053B (en) | River widening construction method for water-carrying operation | |
KR20030091836A (en) | A Continuous and Cut Off wall And Foundation Method By Overlap Casing | |
KR20180014792A (en) | H-beam extraction method used in retaining wall methods | |
JPH09111754A (en) | Soldier pile cut-of wall construction method | |
KR20040017168A (en) | Construction method for retaining of earth | |
JP3125033B2 (en) | Construction method of improved wall | |
JP7435970B2 (en) | Countermeasures for soil defects in soil-cement column walls | |
KR102244505B1 (en) | Self-supporting Type Sheeting Structure and Method for Sheeting Construction using the same | |
KR102117392B1 (en) | Method for constructing earth retaining wall | |
JPH10176329A (en) | Temporary anchor and temporary anchor execution working method | |
JP3944005B2 (en) | Chemical injection method to press-fit shaft and its excavation ground |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19990608 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20070702 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080702 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090702 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090702 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100702 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110702 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120702 Year of fee payment: 13 |
|
EXPY | Cancellation because of completion of term | ||
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120702 Year of fee payment: 13 |