KR102117392B1 - Method for constructing earth retaining wall - Google Patents

Method for constructing earth retaining wall Download PDF

Info

Publication number
KR102117392B1
KR102117392B1 KR1020190071686A KR20190071686A KR102117392B1 KR 102117392 B1 KR102117392 B1 KR 102117392B1 KR 1020190071686 A KR1020190071686 A KR 1020190071686A KR 20190071686 A KR20190071686 A KR 20190071686A KR 102117392 B1 KR102117392 B1 KR 102117392B1
Authority
KR
South Korea
Prior art keywords
ljp
double rod
jetting
injection
construction
Prior art date
Application number
KR1020190071686A
Other languages
Korean (ko)
Inventor
홍진호
Original Assignee
한경건설(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한경건설(주) filed Critical 한경건설(주)
Priority to KR1020190071686A priority Critical patent/KR102117392B1/en
Application granted granted Critical
Publication of KR102117392B1 publication Critical patent/KR102117392B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention relates to an earth retaining wall construction method. According to the present invention, the earth retaining wall construction method comprises: a jetting machine moving and installing step; a perforation step; a low jet pile (LJP) construction mode changing step; an LJP construction starting step; an LJP construction proceeding step; an LJP construction completion step; a double rod washing step; a jetting machine moving step; and a wall construction step. According to the present invention, each existing PHC pile can be integrated.

Description

흙막이 벽체 시공방법{Method for constructing earth retaining wall}Method for constructing earth retaining wall

본 발명은, 흙막이 벽체 시공방법에 관한 것으로서, 더욱 구체적으로는, 각각의 PHC 기성말뚝을 일체화할 수 있으며, 특히 지반 중에 원주상의 고결체를 조성하는 강제 치환공법으로서 확실한 효과를 제공할 수 있는 흙막이 벽체 시공방법에 관한 것이다.The present invention relates to a method for constructing a retaining wall, and more specifically, each PHC ready-made pile can be integrated, and in particular, it can provide a certain effect as a forced displacement method for forming a columnar solid body in the ground. It relates to a method of constructing a retaining wall.

토목공사 또는 건축공사에서 지하 구조물을 건설하기 위해서는 지반을 굴착하여 지하공간을 활용하고 있으며, 지반 굴착 전 지반의 굴착면에는 건설 공사 중 발생하는 토압에 의해 지반이 붕괴하지 않도록 가설 흙막이 구조체를 시공하고 있다.In order to construct underground structures in civil works or architectural works, underground ground is used by excavating the ground, and on the excavation surface of the ground before excavation, a temporary mudguard structure is constructed to prevent the ground from collapsing due to soil pressure generated during construction. have.

가설 흙막이 구조체는 굴착면에 작용하는 토압의 크기, 현장 여건, 시공되는 구조물의 종류, 시공 공법 등에 따라 다양한 공법으로 시공된다.The temporary mudguard structure is constructed by various construction methods depending on the size of the earth pressure acting on the excavation surface, the site conditions, the type of the construction, and the construction method.

이와 같은 가설 흙막이 구조체의 시공 공법으로는 시트 파일(Sheet Pile) 공법, RSW 공법, RPRW 공법, PSS 공법, SGP 공법, 2열 H-파일을 이용한 흙막이 공법, CSR 공법, e-PHC 공법, 버팀보 공법 등이 있다.The construction method of this hypothetical mudguard structure includes the sheet pile method, RSW method, RPRW method, PSS method, SGP method, mudguard method using two-row H-file, CSR method, e-PHC method, and strut method And so on.

시트 파일 공법은 널말뚝의 이음부를 물리게 하여 진동 해머, 워터 제트(WATER JET) 등을 이용하여 지중에 타입함으로써 연속벽을 형성하는 공법으로, 경질지반에서는 타입이 어려움이 있고, 연약지반에서 배면의 지반침하가 우려되며, 지하매설물이 있을 시 시공이 지연되고, 깊은 굴착이 곤란하고, 구간이 절단되는 경우 수압이나 토압에 취약하며, 타입 시 소음이 큰 문제점이 있다.The sheet pile method is a method of forming a continuous wall by biting the joints of a board pile and using a vibrating hammer, water jet, etc., to form a continuous wall. It is difficult to type on hard ground, and on soft ground There is concern about settlement, construction is delayed in the presence of underground burial, deep excavation is difficult, and when the section is cut, it is vulnerable to water pressure or earth pressure, and there is a big noise problem when typed.

상기 RSW 공법은 H-Pile을 천공 또는 직항타로 근입하고, H-Pile 사이에 절곡한 강판을 바이브로 해머로 근입시켜 벽체를 조성한 후 굴착하면서 버팀보를 설치하는 흙막이 벽체 공법으로, 강판 1면 지지이므로 굴착 후 토압으로 인한 벽체의 배부름 현상 발생하며, 벽체의 강성이 작아서 큰 토압이 작용하는 현장에 적용이 어려움이 있고, 시공의 정밀도가 요구되어 시공이 어려운 문제점이 있다.The RSW method is a mud-wall construction method in which H-Pile is punched or punched directly, a steel plate bent between H-Piles is inserted into a vibro hammer to create a wall, and then excavations are installed while supporting beams. After excavation, wall swelling occurs due to earth pressure, and wall stiffness is small, so it is difficult to apply it to a site where large earth pressure is applied.

상기 RPRW 공법은 굴착 배면측과 전면측에 소정의 각도로 근입되는 2개의 엄지말뚝이 두부에서 서로 마찰없는 힌지로 연결되어 토압 작용에 저항하는 구조로 된 흙막이 벽체 공법으로, 굴착 후 토압으로 인한 벽체의 배부름 현상 발생하며, 길이 방향으로 고려하였을 경우 토압 지지력이 0에 가까우므로 굴착면 전체가 굴착면 쪽으로 밀려 들어오는 현상 발생하고, 억지말뚝 삽입과 간격재 설치로 인한 시공 효율성저하가 있고, 거동특성에 대한 해석이 다소 난해함은 물론 도심지 공사시 경사말뚝에 의한 사유지침범 우려 발생하는 문제점이 있다.The RPRW method is a mud wall construction method in which two thumb piles, which are inserted at a predetermined angle on the back side and the front side of the excavation, are connected to each other by friction-free hinges at the head to resist earth pressure action, and the wall of the wall due to earth pressure after excavation When it is considered in the longitudinal direction, the earth pressure bearing force is close to 0 when considered in the longitudinal direction, so the entire excavation surface is pushed toward the excavation surface. There is a problem that the interpretation of Korea is somewhat difficult, and there is a possibility of infringement of private guidelines by inclined piles when constructing downtown.

상기 PSS 공법은 천공 및 항타를 위한 대형장비를 사용하지 않고 자재조립 후 압입시키고 그 내부를 소규모 굴착장비만으로 굴착하므로 소음 및 진동이 발생하지 않는 공법으로, 자체 강성을 키우기 위해 강재량을 많이 사용하여 시공비가 높고, 설치와 굴착이 동시에 이루어지기 때문에 수직도 관리가 중요하여 작업이 난해하며, 차수성이 나쁘고, 특수 버팀대가 필요하여 시공비가 증대되는 문제점이 있다. 또한, 상기 PSS 공법은 하부에 암 노출시 파쇄 후 작업을 해야 하는데, 포스트에 지장물이 있을 시 자립이 어렵다.The PSS method is a method that does not generate noise and vibration because it is press-fitted after assembling the material without using large equipment for drilling and driving, and the inside is excavated with only small-sized drilling equipment.It uses a large amount of steel to increase its own rigidity. Since the construction cost is high, and installation and excavation are performed simultaneously, verticality management is important, which makes the work difficult, the water repellency is poor, and a special brace is required to increase the construction cost. In addition, the PSS method should work after crushing when the cancer is exposed to the lower portion, and it is difficult to become self-reliant when there are obstacles in the post.

상기 SGP 공법은 가시설 계획면에 등간격(C.T.C 1,280 혹은 1,300)으로 가이드 파일을 근입시킨 후 가이드 파일의 사이에 계획근입장에 알맞은 열연강판을 근입시켜 흙막이 벽체를 터파기에 앞서 완성하는 공법이다.The SGP method is a method of completing a guide file at a regular interval (C.T.C 1,280 or 1,300) on a plan surface of a provisional facility, and then inserting a hot rolled steel sheet suitable for a planned location between guide files to complete the earthen wall before breaking.

상기 2열 H-파일을 이용한 흙막이 공법은 흙막이 벽체의 역할을 하는 전열말뚝과 억지말뚝 개념으로 흙막이 벽체의 전단파괴를 방지하는 후열 말뚝으로 조합된 흙막이 공법이다.The two-column H-pile is a mudguard method combined with a post-heat pile that prevents shear failure of the mud wall with the concept of a heat-pile pile and a forced pile that serves as a mud-wall.

상기 CSR 공법은 흙막이 벽체의 역할을 하는 전열말뚝과, 억지말뚝 개념으로 흙막이 벽체의 전단파괴를 방지하는 후열말뚝으로 조합된 자립식 흙막이 공법이다.The CSR method is a self-supporting retaining method combined with an electric heat pile acting as a retaining wall and a post-heating pile preventing shear failure of the retaining wall in the concept of a forced pile.

상기 e-PHC 공법은 e-PHC(고강도원심력파일) 기성말뚝을 근입하여 토류벽 형성하는 공법이다.The e-PHC method is a method of forming an earth wall by advancing an e-PHC (high strength centrifugal pile) ready-made pile.

상기 버팀보 공법은 버팀 구조물을 적용한 것으로서 도 1과 같은 구조로 시공된다. 즉 터파기 영역의 가장자리를 따라 다수개의 H형 강재를 일정 간격으로 지중 소정의 깊이까지 타입한 후, 내측의 영역에서 지면의 하측으로 깊이를 갖는 터파기 공사를 수행하게 된다. 작업장 내로 토압에 의해 토사가 유입되거나 지하수가 유입되는 것을 방지하도록 일정간격으로 배치된 상기 H형 강재(1)들 사이에 목재로 된 토류판(2)을 삽입하여 흙막이 구조물을 설치하게 된다. 상기 토류판(2)은 흙막이 구조물의 내측에서 터파기 공사를 진행함에 따라 H형 강재(1) 사이에 추가로 삽입하는 방식으로 터파기 공사와 함께 진행된다.The support beam construction method is applied to the support structure and is constructed in a structure as shown in FIG. 1. That is, after a plurality of H-type steel materials are formed along the edge of the trenching area to a predetermined depth in the ground at regular intervals, a trenching construction having a depth from the inner area to the lower side of the ground is performed. The earth retaining structure is installed by inserting a wood earthing plate 2 between the H-shaped steel materials 1 arranged at regular intervals to prevent the inflow of soil or groundwater by the earth pressure into the work place. The earth plate 2 is progressed together with the trenching construction by additionally inserting it between the H-shaped steel materials 1 as the trenching construction proceeds from the inside of the mudguard structure.

한편, 전술한 어떠한 공법을 사용하더라도 흙막이 공사는 터파기를 안전하게 하기 위한 수단으로 충분한 강도와 강성을 가져야 하고, 이로 인해 작용하중에 견딜 수 있도록 설계되어야 한다. 그 때문에 전술한 바와 같은 다양한 공법이 준용되고 있기는 하지만 상기 공법들의 경우, 나름대로 단점을 갖는다는 점에서 아직 완벽한 공법은 제안된 바 없다.On the other hand, even if any of the above-described construction methods are used, the mud construction must have sufficient strength and stiffness as a means to safely dig, and therefore must be designed to withstand the working load. For this reason, although various construction methods as described above are applied, the construction methods have not yet been proposed in that they have their own disadvantages.

다만, 도 1에 도시된 공법과 더불어 PHC 기성말뚝을 사용한 방법이 흙막이 벽체 시공을 위해 주로 사용되는 방법이다.However, in addition to the construction method shown in FIG. 1, a method using a PHC ready-made pile is a method mainly used for constructing a retaining wall.

다만, 종래기술의 경우, PHC 기성말뚝 시공 시 말뚝과 말뚝의 이격거리로 인해 각각의 말뚝이 일체화되지 못하고, 기성말뚝의 직경이 선천공 직경보다 작아서(508mm 천공 후 450mm 말뚝 건입) 발생한 유격으로 인해 앞뒤, 좌우로의 위치이동이 있다는 점에서 PHC 기성말뚝은 변위억제와 강성이 중요한 흙막이 벽체 적용에는 적합하지 않다.However, in the case of the prior art, when constructing a PHC ready-made pile, each pile cannot be integrated due to the separation distance between the pile and the pile, and the diameter of the ready-made pile is smaller than the diameter of the pre-drilled hole (450 mm pile after 508 mm drilling). In the sense that there is a shift in position from side to side, PHC ready-made piles are not suitable for the application of retaining walls where displacement control and rigidity are important.

LOW JET PILE(L.J.P) 벽체 조성공사는 각각의 PHC 기성말뚝 이격거리에 그라우트를 충진하여, 각각의 PHC 기성말뚝을 일체화하여 변위억제와 강성이 뛰어난 흙막이 벽체를 조성한다.LOW JET PILE(L.J.P) wall composition construction fills the grouts at the separation distance of each PHC ready-made pile, and integrates each PHC ready-made pile to form an earth retaining wall with excellent displacement control and rigidity.

또한, 흙막이 배면 교반된 지반의 그라우트 충진을 통해 지반개량과, 흙막이 배면 차수에 뛰어난 효과를 나타낸다.In addition, through the filling of the grout of the agitated soil on the back of the mudguard, it shows an excellent effect on the soil improvement and the rear order of the mudguard.

그리고 J.S.P 공법과는 달리, 모래 자갈 지반에도 적용이 가능하다. 지하수의 유속이 빠르거나 지하수위가 높을 시 L.J.P 전용 혼화재 및 물유리계의 약품을 사용 하여 그라우트 양생시간 조절이 가능하기 때문이다.And unlike J.S.P method, it can be applied to sandy gravel ground. This is because, when the flow rate of the groundwater is high or the groundwater level is high, the grouting curing time can be adjusted by using L.J.P-only admixture and water-glass chemicals.

한편, 일반적으로 이용되고 있는 약액 주입공법은 대상 지반의 토층 구성 및 토질에 따라 그 효과가 좌우되고 있다.On the other hand, the effect of the generally used chemical injection method depends on the soil layer composition and soil quality of the target ground.

특히, 복잡하게 누적된 다층 지반이나 얇은 층이 많이 개재되는 지반에서는 층 경계에 연하여 약액이 빠져나가는 경향이 있어서 목적하는 지반의 토립자의 간격에 침투가 대단히 어렵고, 또 기대하는 효과를 얻기 위한 주입량을 미리 산정하기가 곤란하다.Particularly, in a multi-layered complex or a layer with many thin layers interposed there is a tendency for the chemical solution to escape from the boundary of the layer, so it is very difficult to penetrate the gap between the particles of the desired ground and the amount of injection to obtain the expected effect. It is difficult to estimate in advance.

더욱이 소기의 주입 효과가 발휘되어 있는지를 확인하기가 어려워서 자칫하면 전혀 그 효과가 나타나지 않는 경우가 발생하기도 한다.Moreover, it is difficult to confirm whether the desired infusion effect is exerted, and sometimes the effect does not appear at all.

따라서, 이러한 종래의 주입공법이 갖는 결점을 제거하고 확실한 효과를 기대하기 위한 여러 가지의 유도 주입공법이 연구되고 있으나 현재까지는 실제 시공에 적합한 공법이 없었다는 점을 고려해볼 때, 기존에 알려지지 않은 신개념의 흙막이 벽체 시공기술에 대한 필요성이 대두된다.Accordingly, various induction injection methods have been studied to remove the defects of the conventional injection method and to expect a certain effect, but considering that there has been no suitable method for actual construction until now, a new concept is not known. The need for construction technology for retaining walls emerges.

대한민국특허청 출원번호 제10-2015-0094711호Korea Patent Office Application No. 10-2015-0094711 대한민국특허청 출원번호 제10-2015-0108121호Korea Patent Office Application No. 10-2015-0108121 대한민국특허청 출원번호 제10-2016-0048716호Korea Patent Office Application No. 10-2016-0048716 대한민국특허청 출원번호 제10-2017-0079546호Korea Patent Office Application No. 10-2017-0079546

본 발명의 목적은, 각각의 PHC 기성말뚝을 일체화할 수 있으며, 특히 지반 중에 원주상의 고결체를 조성하는 강제 치환공법으로서 확실한 효과를 제공할 수 있는 흙막이 벽체 시공방법을 제공하는 것이다.An object of the present invention is to provide a method for constructing a retaining wall which can provide a certain effect as a forced displacement method that can integrate each PHC ready-made pile, and in particular forms a columnar solid body in the ground.

상기 목적은, 기설치된 기성말뚝과 기성말뚝 사이의 위치로 천공기능과 주입기능이 가능한 제팅 머신(JETTING MACHINE)을 이동시켜 설치하는 제팅 머신 이동 설치단계; 회전 가능한 더블 로드(Double Rod)를 지중에 근입해서 회전시키는 한편 상기 더블 로드를 통해 드릴 비트까지 청수를 압송시켜 계획심도까지 상기 더블 로드가 굴진토록 하는 더블 로드를 이용한 천공단계; 상기 더블 로드의 작용으로 천공작업이 완료되면, 상기 제팅 머신의 타이머를 조절해서 상기 더블 로드의 회전수를 LJP(LOW JET PILE)의 시공모드로 변경하는 LJP 시공모드 변경단계; 상기 제팅 머신에 탑재된 초고압 펌프(PUMP)를 조절하여 주입재의 주입압을 상승시키되 주입압이 계획치에 도달하면 상기 더블 로드의 선단에 제팅 노즐(Jetting Nozzle)을 장착하여 주입재를 분사하면서 회전하게 하되 상기 제팅 노즐이 한 바퀴 또는 한 바퀴 반을 회전하면서 자동으로 상승하는 동작이 반복되도록 하는 LJP 작업이 개시되는 LJP 작업 개시단계; 상기 더블 로드를 회전시키되 목적된 심도까지 제팅 노즐이 상승토록 하면서 계획된 주입 상한선까지 상기 LJP 작업을 계속 진행하는 LJP 작업 진행단계; 상기 주입 상한선까지 시공하여 지반 중에 주입재에 의한 원주상의 고결체를 조성 완료함으로써 각각의 PHC 기성말뚝을 일체화시키는 LJP 작업 완료단계; 상기 LJP 작업의 완료 후, 상기 더블 로드를 세척하는 더블 로드 세척단계; 및 상기 제팅 머신을 다음 위치로 이동시키는 제팅 머신 이동단계를 포함하는 것을 특징으로 하는 흙막이 벽체 시공방법에 의해 달성된다.The above object is, a jetting machine moving installation step of moving and installing a jetting machine (JETTING MACHINE) capable of puncturing and injection function to a position between a pre-installed ready-made pile and a ready-made pile; A puncturing step using a double rod that rotates a rotatable double rod near the ground and pushes fresh water to the drill bit through the double rod to make the double rod roll up to a planned depth; LJP construction mode changing step of changing the number of revolutions of the double rod to the construction mode of LJP (LOW JET PILE) by adjusting the timer of the jetting machine when the drilling operation is completed by the action of the double rod; By adjusting the ultra-high pressure pump (PUMP) mounted on the jetting machine to increase the injection pressure of the injection material, but when the injection pressure reaches a predetermined value, a jetting nozzle is mounted on the tip of the double rod to rotate while spraying the injection material. An LJP operation initiation step in which an LJP operation is initiated such that an operation of automatically rising while the nozzle rotates one or a half of a wheel is repeated; An LJP operation proceeding step of rotating the double rod but continuing the LJP operation to a planned injection upper limit while the jetting nozzle is raised to a desired depth; LJP work completion step of integrating each PHC ready-made pile by constructing to the upper limit of the injection and completing the formation of a columnar solid body by the injection material in the ground; A double rod washing step of washing the double rod after completion of the LJP operation; And a jetting machine moving step of moving the jetting machine to a next position.

상기 원주상의 고결체를 기초로 해서 흙막이 벽체를 시공하는 벽체 시공단계를 더 포함할 수 있다.A wall construction step of constructing a retaining wall based on the columnar solid body may be further included.

상기 LJP 작업 개시단계에서 상기 청수를 현탁액으로 변경시킬 수 있다.At the beginning of the LJP operation, the fresh water may be changed into a suspension.

상기 더블 로드 세척단계에서 청수를 압송시켜 상기 더블 로드를 세척할 수 있다.The double rod may be washed by pressing fresh water in the double rod washing step.

상기 더블 로드를 이용한 천공단계에는 천공되는 제1 방향으로 천공수가 토출되되 압축공기 분출구를 통해 공기가 계속 분출됨으로써 슬라임(SLIME)의 역류로 인해 압축공기 분출구가 막히는 현상을 방지하며, 상기 LJP 작업 개시단계 및 상기 LJP 작업 진행단계에서는 상기 제1 방향에 교차되는 제2 방향으로 주입재가 토출될 수 있다.In the puncturing step using the double rod, the puncture water is discharged in the first direction to be punctured, but air is continuously blown through the compressed air jet to prevent clogging of the compressed air jet due to backflow of slime (SLIME) and start the LJP operation In the step and the LJP work progress step, the injection material may be discharged in a second direction crossing the first direction.

삭제delete

본 발명에 따르면, 각각의 PHC 기성말뚝을 일체화할 수 있으며, 특히 지반 중에 원주상의 고결체를 조성하는 강제 치환공법으로서 확실한 효과를 제공할 수 있는 효과가 있다.According to the present invention, each PHC ready-made pile can be integrated, and in particular, there is an effect capable of providing a certain effect as a forced displacement method for forming a columnar solid body in the ground.

도 1은 일반적인 흙막이 시공구조를 나타낸 도면
도 2는 본 발명의 일 실시예에 따른 흙막이 벽체 시공방법의 순서도이다.
도 3 내지 도 7은 도 2의 흙막이 벽체 시공방법 중에서 일부 공정도이다.
도 8은 LJP 작업 완료 후 두부 노출 이미지이다.
도 9는 본 발명의 다른 실시예에 따른 흙막이 벽체 시공방법의 순서도이다.
1 is a view showing a general mud construction structure
2 is a flowchart of a method for constructing a retaining wall according to an embodiment of the present invention.
3 to 7 are some process diagrams of the method of constructing the retaining wall of FIG. 2.
8 is an image of tofu exposed after the completion of the LJP operation.
9 is a flowchart of a method for constructing a retaining wall according to another embodiment of the present invention.

아래에서는 첨부한 도면을 참고로 하여 본 발명의 실시예에 대하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 쉽게 실시할 수 있도록 상세히 설명한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art to which the present invention pertains may easily practice.

그러나 본 발명에 관한 설명은 구조적이나 기능적 설명을 위한 실시예에 불과하므로 본 발명의 권리범위는 본문에 설명된 실시예에 의하여 제한되는 것으로 해석되어서는 아니 된다.However, since the description of the present invention is only an example for structural or functional description, the scope of the present invention should not be interpreted as being limited by the examples described in the text.

예컨대, 실시예는 다양한 변경이 가능하고 여러 가지 형태를 가질 수 있어서 본 발명의 권리범위는 기술적 사상을 실현할 수 있는 균등물들을 포함하는 것으로 이해되어야 한다.For example, the embodiments can be variously modified and have various forms, so it should be understood that the scope of the present invention includes equivalents capable of realizing technical ideas.

또한, 본 발명에서 제시된 목적 또는 효과는 특정 실시예가 이를 전부 포함하여야 한다거나 그러한 효과만을 포함하여야 한다는 의미는 아니므로 본 발명의 권리범위는 이에 의하여 제한되는 것으로 이해되어서는 아니 될 것이다.In addition, the purpose or effect presented in the present invention does not mean that a specific embodiment should include all of them or only such an effect, so the scope of the present invention should not be understood as being limited thereby.

본 명세서에서, 본 실시예는 본 발명의 개시가 완전하여지도록 하며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이다. 그리고 본 발명은 청구항의 범주에 의해 정의될 뿐이다.In this specification, the present embodiment is provided to make the disclosure of the present invention complete, and to fully inform the scope of the invention to those of ordinary skill in the art. And the present invention is only defined by the scope of the claims.

따라서 몇몇 실시예에서, 잘 알려진 구성 요소, 잘 알려진 동작 및 잘 알려진 기술들은 본 발명이 모호하게 해석되는 것을 피하려고 구체적으로 설명되지 않는다.Thus, in some embodiments, well-known components, well-known operations, and well-known techniques are not specifically described to avoid obscuring the present invention.

한편, 본 발명에서 서술되는 용어의 의미는 사전적 의미에 제한되지 않으며, 다음과 같이 이해되어야 할 것이다.Meanwhile, the meaning of the terms described in the present invention is not limited to the dictionary meaning, and should be understood as follows.

어떤 구성 요소가 다른 구성 요소에 "연결되어" 있다고 언급된 때에는, 그 다른 구성 요소에 직접 연결될 수도 있지만, 중간에 다른 구성 요소가 존재할 수도 있다고 이해되어야 할 것이다. 반면에, 어떤 구성 요소가 다른 구성 요소에 "직접 연결되어" 있다고 언급된 때에는 중간에 다른 구성 요소가 존재하지 않는 것으로 이해되어야 할 것이다. 한편, 구성 요소 간의 관계를 설명하는 다른 표현들, 즉 "~사이에"와 "바로 ~사이에" 또는 "~에 이웃하는"과 "~에 직접 이웃하는" 등도 마찬가지로 해석되어야 한다.When a component is said to be "connected" to another component, it may be understood that other components may exist in the middle, although other components may be directly connected. On the other hand, when a component is said to be "directly connected" to another component, it should be understood that no other component exists in the middle. On the other hand, other expressions describing the relationship between the components, that is, "between" and "immediately between" or "neighboring to" and "directly neighboring to" should be interpreted similarly.

단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한 복수의 표현을 포함하는 것으로 이해되어야 하고, "포함하다" 또는 "가지다" 등의 용어는 설시된 특징, 숫자, 단계, 동작, 구성 요소, 부분품 또는 이들을 조합한 것이 존재함을 지정하려는 것이며, 하나 또는 그 이상의 다른 특징이나 숫자, 단계, 동작, 구성 요소, 부분품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해되어야 한다.Singular expressions are to be understood as including plural expressions unless the context clearly indicates otherwise, and terms such as "comprises" or "have" include the features, numbers, steps, actions, components, parts or components described. It is to be understood that a combination is intended to indicate the existence, and does not preclude the existence or addition possibility of one or more other features or numbers, steps, actions, components, parts or combinations thereof.

여기서 사용되는 모든 용어는 다르게 정의되지 않는 한, 본 발명이 속하는 분야에서 통상의 지식을 가진 자에 의해 일반적으로 이해되는 것과 같은 의미가 있다.All terms used herein have the same meaning as generally understood by a person skilled in the art to which the present invention pertains, unless defined otherwise.

일반적으로 사용되는 사전에 정의된 용어들은 관련 기술의 문맥상 가지는 의미와 일치하는 것으로 해석되어야 하며, 본 발명에서 명백하게 정의하지 않는 한 이상적이거나 과도하게 형식적인 의미를 지니는 것으로 해석될 수 없다.Generally used dictionary definitions should be interpreted to be consistent with meanings in the context of related technologies, and cannot be interpreted as having ideal or excessively formal meanings unless explicitly defined in the present invention.

이하, 도면을 참조하여 본 발명의 실시예를 상세히 설명한다. 실시예의 설명 중 같은 구성에 대해서는 같은 참조부호를 부여하도록 하며, 때에 따라 같은 참조부호에 대한 설명은 생략하도록 한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. In the description of the embodiment, the same reference numerals are assigned to the same components, and the descriptions of the same reference numerals are sometimes omitted.

(일 실시예)(One embodiment)

도 2는 본 발명의 일 실시예에 따른 흙막이 벽체 시공방법의 순서도이고, 도 3 내지 도 7은 도 2의 흙막이 벽체 시공방법 중에서 일부 공정도이며, 도 8은 LJP 작업 완료 후 두부 노출 이미지이다.2 is a flowchart of a method of constructing a retaining wall according to an embodiment of the present invention, FIGS. 3 to 7 are some process diagrams of a method of constructing a retaining wall of FIG. 2, and FIG. 8 is an image of tofu exposed after completion of the LJP operation.

이들 도면을 참조하면, 본 실시예에 따른 흙막이 벽체 시공방법에 의하면, 각각의 PHC 기성말뚝을 일체화할 수 있으며, 특히 지반 중에 원주상의 고결체(130)를 조성하는 강제 치환공법으로서 확실한 효과를 제공할 수 있다.Referring to these drawings, according to the method of constructing a retaining wall according to the present embodiment, each PHC ready-made pile can be integrated, and in particular, it has a certain effect as a compulsory displacement method of forming a columnar solid body 130 in the ground. Can provide.

특히, 본 실시예의 경우는 저압에서 고압으로 주입재(CEMENT PASTE)를 분사시켜 원주상의 고결체(130)를 형성하는 것으로서, PHC 기성말뚝의 배면 차수를 하는데 있어서 그 적용범위가 매우 넓다.Particularly, in the case of the present embodiment, the injection material (CEMENT PASTE) is injected from low pressure to high pressure to form a columnar solid body 130, and the range of application is very wide in obtaining the rear order of the PHC ready-made pile.

이러한 효과를 제공할 수 있는 본 실시예에 따른 흙막이 벽체 시공방법은 제팅 머신 이동 설치단계(S10), 더블 로드를 이용한 천공단계(S20), LJP 시공모드 변경단계(S30), LJP 작업 개시단계(S40), LJP 작업 진행단계(S50), LJP 작업 완료단계(S60), 더블 로드 세척단계(S70), 제팅 머신 이동단계(S80) 및 벽체 시공단계(S90)를 포함할 수 있다.The method of constructing a retaining wall according to this embodiment, which can provide such an effect, is a jetting machine moving installation step (S10), a drilling step using a double rod (S20), a LJP construction mode change step (S30), and an LJP work initiation step ( S40), LJP work progress step (S50), LJP work completion step (S60), double rod washing step (S70), jetting machine moving step (S80) and wall construction step (S90).

제팅 머신 이동 설치단계(S10)는 도 3처럼 기설치된 기성말뚝과 기성말뚝 사이의 위치로 천공기능과 주입기능이 가능한 제팅 머신(100, JETTING MACHINE)을 이동시켜 설치하는 공정이다.The jetting machine movement installation step (S10) is a process of moving and installing a jetting machine 100 (JETTING MACHINE) capable of puncturing and injection into a position between a pre-installed ready-made pile and a ready-made pile as shown in FIG.

더블 로드를 이용한 천공단계(S20)는 도 3 및 도 4처럼 회전 가능한 더블 로드(110, Double Rod)를 지중에 근입해서 회전시키는 한편 더블 로드(110)를 통해 드릴 비트(111)까지 청수를 압송시켜 계획심도까지 더블 로드(110)가 굴진토록 하는 공정이다.The drilling step using a double rod (S20) rotates the rotatable double rod 110 (Double Rod) as shown in FIGS. 3 and 4 in the ground while reciprocating the fresh water to the drill bit 111 through the double rod 110. This is the process of allowing the double rod 110 to roll up to the planned depth.

이러한 더블 로드를 이용한 천공단계(S20)에서는 천공되는 제1 방향(제팅 노즐의 하부 방향)으로 천공수가 토출되되 압축공기 분출구를 통해 공기가 계속 분출됨으로써 슬라임(SLIME)의 역류로 인해 압축공기 분출구가 막히는 현상을 방지하도록 한다. 이때의 천공수는 청수이다. 여기서, 천공되는 제1 방향이란 도 3 및 도 4의 진한 화살표 방향으로 제팅 노늘(120)의 하부 방향을 가리킨다.In the perforation step using the double rod (S20), the perforated water is discharged in the first direction (the lower direction of the jetting nozzle) being perforated, but air is continuously blown through the compressed air blowing port, so that the compressed air blowing port is caused by the reverse flow of the slime. Try to prevent clogging. The number of punctures at this time is blue water. Here, the first direction to be perforated refers to the lower direction of the jetting bar 120 in the direction of the dark arrows in FIGS. 3 and 4.

LJP 시공모드 변경단계(S30)는 도 5처럼 더블 로드(110)의 작용으로 천공작업이 완료되면, 제팅 머신(100)의 타이머(미도시)를 조절해서 더블 로드(110)의 회전수를 LJP(LOW JET PILE)의 시공모드로 변경하는 공정이다.In the LJP construction mode changing step (S30), when the drilling operation is completed by the action of the double rod 110 as shown in FIG. 5, the number of revolutions of the double rod 110 is adjusted by adjusting the timer (not shown) of the jetting machine 100. It is a process to change to the construction mode of (LOW JET PILE).

LJP 작업 개시단계(S40)는 도 5처럼 제팅 머신(100)에 탑재된 초고압 펌프(PUMP)를 조절하여 주입압을 상승시키되 주입압이 계획치에 도달하면 더블 로드(110)의 선단에 제팅 노즐(120, Jetting Nozzle)을 장착하여 주입재(CEMENT PASTE)를 분사하면서 회전하게 하되 제팅 노즐(120)이 한 바퀴 또는 한 바퀴 반을 회전하면서 자동으로 상승함과 동시에 상기 동작이 반복되도록 하는 공정이다. 이러한 LJP 작업 개시단계(S40)에서는 청수를 현탁액으로 변경시켜 작업을 진행할 수 있다.The LJP operation starting step (S40) increases the injection pressure by adjusting the ultra high pressure pump (PUMP) mounted on the jetting machine 100 as shown in FIG. 5, but when the injection pressure reaches a planned value, the jetting nozzle 120 at the tip of the double rod 110, Jetting nozzle is installed to rotate while spraying the injection material (CEMENT PASTE), but the jetting nozzle 120 is automatically raised while rotating one or a half of a wheel, and the operation is repeated. In the LJP work initiation step (S40), the fresh water can be changed into a suspension to proceed.

특히, 본 실시예의 경우, 제팅 노즐(120)에서 주입재가 직접 공벽 파쇄 후 교란, 혼합되는 주입이 아닌 분사 방식을 적용하고 있어서 효율이 우수하다.Particularly, in the present embodiment, since the injection material is directly crushed after the blast wall is crushed and mixed in the jetting nozzle 120, the injection method is applied, and the efficiency is excellent.

전술한 것처럼 주입재는 시멘트풀(CEMENT PASTE)일 수 있으나 필요에 따라 LJP 전용 약품으로 변경될 수도 있다.As described above, the injection material may be cement paste (CEMENT PASTE), but may be changed to an LJP-only drug as needed.

LJP 작업 진행단계(S50)는 도 6처럼 더블 로드(110)를 회전시키되 목적된 심도까지 제팅 노즐(120)이 상승토록 하면서 계획된 주입 상한선까지 LJP 작업을 계속 진행하는 공정이다.The LJP operation proceeding step (S50) is a process of rotating the double rod 110 as shown in FIG. 6 but continuing the LJP operation up to the planned injection upper limit while the jetting nozzle 120 is raised to a desired depth.

이러한 LJP 작업 개시단계(S40) 및 LJP 작업 진행단계(S50)에서는 제1 방향(제팅 노즐 하부방향)에 교차되는 제2 방향(제팅 노즐 가로방향)으로 주입재가 분사되면서 진행할 수 있다. 주입재의 분사는 앞서 기술한 것처럼 도 6처럼 제팅 노즐(120)에 의한 제2 방향(제팅 노즐 가로방향) 이 될 수 있다.In the LJP work initiation step (S40) and LJP work initiation step (S50), the injection material is injected in the second direction (the jetting nozzle horizontal direction) intersecting the first direction (the jetting nozzle lower direction). The injection of the injection material may be the second direction (the jetting nozzle transverse direction) by the jetting nozzle 120 as described above.

LJP 작업 완료단계(S60)는 도 7처럼 주입 상한선까지 시공하여 지반 중에 주입재에 의한 원주상의 고결체(130)를 조성 완료함으로써 각각의 PHC 기성말뚝(미도시)을 일체화시키는 공정이다.The LJP work completion step (S60) is a process of integrating each PHC ready-made pile (not shown) by constructing to the upper limit of the injection as shown in FIG. 7 and completing the circumferential solid body 130 by the injection material in the ground.

LJP 시공모드 변경단계(S30), LJP 작업 개시단계(S40), LJP 작업 진행단계(S50) 및 LJP 작업 완료단계(S60)를 반복적으로 진행함으로써 본 실시예의 경우, 지반 중에 원주상의 고결체(130)를 조성하는 강제 치환공법으로서 확실한 효과를 볼 수 있다.In the case of the present embodiment by repeatedly performing the LJP construction mode changing step (S30), the LJP work initiation step (S40), the LJP work initiation step (S50), and the LJP work completion step (S60), solid consolidation on the column during the ground ( 130) can be seen as a certain effect as a forced substitution method to create.

다시 말해, 본 실시예는 저, 중, 고압의 제트(JET)류를 이용해서 지반을 교란시킴과 동시에 기성말뚝의 시공 시 공 간격에 그라우트(GROUT)재를 충진하여, 각각의 PHC 기성말뚝을 일체화하는 벽체 조성공법 중 하나인데, 본 실시예의 경우는 이러한 일반론에서 벗어나 지층에 관계없이 주입량을 조절할 수 있으며, 또한, 지반에 맞는 적정 주입량을 시간과 압력을 이용하여 심도별로 시멘트 페이스트의 주입량을 조절할 수도 있는 매우 효과적인 공법이다.In other words, this embodiment uses low, medium, and high pressure jets (JETs) to disturb the ground and at the same time fill the grout (GROUT) material at the construction intervals of the ready-made piles, so that each PHC ready-made pile It is one of the wall composition methods to be integrated. In the case of this embodiment, the amount of injection can be adjusted regardless of the strata outside the general theory, and also, the amount of cement paste is adjusted for each depth by using time and pressure to adjust the amount of injection suitable for the ground. It is a very effective construction method.

더블 로드 세척단계(S70)는 도 7처럼 LJP 작업의 완료 후, 더블 로드(110)를 세척하는 공정이다. 이때는 청수를 압송시켜 더블 로드(110)를 세척하는 것이 바람직하다.Double rod washing step (S70) is a process of washing the double rod 110 after completion of the LJP operation as shown in FIG. In this case, it is preferable to wash the double rod 110 by feeding fresh water.

제팅 머신 이동단계(S80)는 제팅 머신(100)의 설치 상태를 해제하고 제팅 머신(100)을 다음 위치로 이동시키는 공정이다.The jetting machine moving step S80 is a process of releasing the installation state of the jetting machine 100 and moving the jetting machine 100 to the next location.

벽체 시공단계(S90)는 원주상의 고결체(130)를 기초로 해서 흙막이 벽체를 시공하는 공정이다. 이때는 PHC 기성말뚝을 사용해서 벽체를 시공할 수 있다.The wall construction step (S90) is a process of constructing a retaining wall based on a columnar solid body 130. At this time, the wall can be constructed using PHC ready-made piles.

이하, 본 실시예의 흙막이 벽체 시공방법에 대해 알아본다.Hereinafter, the construction method of the retaining wall of the present embodiment will be described.

우선, 기설치된 기성말뚝과 기성말뚝 사이의 위치로 천공기능과 주입기능이 가능한 제팅 머신(100, JETTING MACHINE)을 이동시켜 설치한다(S10).First, the jetting machine (100, JETTING MACHINE) capable of puncture and injection functions is moved to a position between the pre-installed ready-made pile and the ready-made pile (S10).

다음, 회전 가능한 더블 로드(110, ROD)를 지중에 근입해서 회전시키는 한편 더블 로드(110)를 통해 드릴 비트(111)까지 청수를 압송시켜 계획심도까지 더블 로드(110)가 굴진토록 한다(S20).Next, while rotating the rotatable double rod (110, ROD) to the ground while rotating the water to the drill bit 111 through the double rod 110 to the double rod 110 to the planned depth (S20) ).

다음, 더블 로드(110)의 작용으로 천공작업이 완료되면, 제팅 머신(100)의 타이머(미도시)를 조절해서 더블 로드(110)의 회전수를 LJP(LOW JET PILE)의 시공모드로 변경한다(S30).Next, when the drilling operation is completed by the action of the double rod 110, the timer (not shown) of the jetting machine 100 is adjusted to change the rotation speed of the double rod 110 to the construction mode of LJP (LOW JET PILE). (S30).

그런 다음, 제팅 머신(100)에 탑재된 초고압 펌프(PUMP)를 조절하여 주입압이 계획치에 도달하면 더블 로드(110)의 선단에 제팅 노즐(120, Jetting Nozzle)을 장착하여 주입재를 분사하면서 회전하게 하되 제팅 노즐(120)이 한 바퀴 또는 한 바퀴 반을 회전하면서 자동으로 상승함과 동시에 상기 동작이 반복되도록 하는 LJP 작업이 개시되게 한다(S40).Then, by adjusting the ultra-high pressure pump (PUMP) mounted on the jetting machine 100, when the injection pressure reaches a planned value, a jetting nozzle 120 is mounted on the tip of the double rod 110 to rotate while spraying the injection material. However, the jetting nozzle 120 is automatically raised while rotating one or a half of a wheel, and at the same time, the LJP operation is started so that the above operation is repeated (S40).

다음, 더블 로드(110)를 회전시키되 목적된 심도까지 제팅 노즐(120)이 상승토록 하면서 계획된 주입 상한선까지 LJP 작업을 계속 진행한다(S50).Next, while rotating the double rod 110 but the jetting nozzle 120 is raised to the desired depth, the LJP operation is continued until the planned injection upper limit (S50).

다음, 주입 상한선까지 시공하여 지반 중에 원주상의 고결체(130)를 조성 완료함으로써 각각의 PHC 기성말뚝(미도시)을 일체화한다(S60).Next, each PHC ready-made pile (not shown) is integrated by constructing to the upper limit of the injection and completing the formation of a columnar solid body 130 in the ground (S60).

다음, LJP 작업이 완료되면 더블 로드(110)를 세척한 후(S70), 제팅 머신(100)을 다음 위치로 이동시키켜 상기 작업을 반복한다(S80).Next, when the LJP operation is completed, after washing the double rod 110 (S70), the jetting machine 100 is moved to the next position to repeat the operation (S80).

한편, 이후에는 원주상의 고결체(130)를 기초로 해서 흙막이 벽체를 시공하면 된다(S90). 이때는 PHC 기성말뚝을 사용해서 벽체를 시공할 수 있다.On the other hand, thereafter, a wall of a retaining wall may be constructed based on a columnar solid body 130 (S90). At this time, the wall can be constructed using PHC ready-made piles.

이상 설명한 바와 같은 구조를 기반으로 작용을 하는 본 실시예에 따르면, 각각의 PHC 기성말뚝을 일체화할 수 있으며, 특히 지반 중에 원주상의 고결체(130)를 조성하는 강제 치환공법으로서 확실한 효과를 제공할 수 있게 된다.According to this embodiment acting on the basis of the structure as described above, each PHC ready-made pile can be integrated, and in particular, it provides a certain effect as a forced displacement method for forming a columnar solid body 130 in the ground. I can do it.

본 실시예의 효과에 대해 부연한다.The effects of this embodiment will be elaborated.

첫째, 토층 구성이나 토질에 의한 영향을 받지 않으며 필요 개소에 필요량의 주입재를 계획적으로 주입할 수 있다.First, it is not affected by the soil composition or soil quality, and it is possible to intentionally inject the necessary amount of injection material at the required location.

둘째, 보통의 주입공법으로는 주입이 곤란한 세립토 지반에도 적용할 수 있다.Second, it can be applied to fine-grained soils, which are difficult to inject using ordinary injection methods.

셋째, 토중에 인공적으로 만든 간격에 주입재를 강제치환 및 충진하는 것이기 때문에 보통의 약액주입 공법처럼 인근의 건물이나 지하 매설물에 영향을 미치는 일이 없다.Third, since it is forcibly displaced and filled the injection material at artificially created intervals in the middle of the soil, it does not affect nearby buildings or underground buried materials like the normal chemical injection method.

본 실시예의 공법은 약액주입을 포함하는 차수공사 전반에 가능하며, PHC 흙막이 벽체 조성에 매우 적합하다.The method of this embodiment is possible throughout the water repellent construction including injection of chemicals, and is very suitable for the composition of the PHC retaining wall.

(다른 실시예)(Other Examples)

도 9는 본 발명의 다른 실시예에 따른 흙막이 벽체 시공방법의 순서도이다.9 is a flowchart of a method for constructing a retaining wall according to another embodiment of the present invention.

이 도면을 참조하면, 본 실시예에 따른 흙막이 벽체 시공방법 역시, 제팅 머신 이동 설치단계(S10), 더블 로드를 이용한 천공단계(S20), LJP 시공모드 변경단계(S30), LJP 작업 개시단계(S40a), LJP 작업 진행단계(S50a), LJP 작업 완료단계(S60), 더블 로드 세척단계(S70), 제팅 머신 이동단계(S80) 및 벽체 시공단계(S90)를 포함할 수 있다.Referring to this drawing, the method for constructing a retaining wall according to this embodiment also includes a jetting machine movement installation step (S10), a drilling step using a double rod (S20), an LJP construction mode change step (S30), and an LJP work initiation step ( S40a), LJP work progress step (S50a), LJP work completion step (S60), double rod washing step (S70), jetting machine moving step (S80) and wall construction step (S90) may be included.

한편, 본 실시예의 경우에는 전술한 실시예와 달리, LJP 작업 개시단계(S40a) 및 LJP 작업 진행단계(S50a)에서는 제1 방향에 교차되는 제2 방향으로 공기가 1차로 분사된 후, 뒤이어 주입재가 주입되게 하고 있는데, 이러한 방법이 적용되더라도 각각의 PHC 기성말뚝을 일체화할 수 있으며, 특히 지반 중에 원주상의 고결체(130)를 조성하는 강제 치환공법으로서 확실한 효과를 제공할 수 있다.On the other hand, in the case of the present embodiment, unlike the above-described embodiment, in the LJP work start step (S40a) and LJP work proceeding step (S50a), air is first injected in a second direction crossing the first direction, followed by the injection material Even if such a method is applied, each PHC ready-made pile can be integrated, and in particular, it can provide a certain effect as a forced displacement method of forming a columnar solid body 130 in the ground.

이처럼 본 발명은 기재된 실시예에 한정되는 것이 아니고, 본 발명의 사상 및 범위를 벗어나지 않고 다양하게 수정 및 변형할 수 있음은 이 기술의 분야에서 통상의 지식을 가진 자에게 자명하다. 따라서 그러한 수정예 또는 변형예들은 본 발명의 청구범위에 속한다고 하여야 할 것이다.As described above, the present invention is not limited to the described embodiments, and it is obvious to those skilled in the art that various modifications and modifications can be made without departing from the spirit and scope of the present invention. Therefore, it should be said that such modifications or variations belong to the claims of the present invention.

100 : 제팅 머신 110 : 더블 로드
120 : 제팅 노즐 130 : 원주상의 고결체
100: jetting machine 110: double rod
120: jetting nozzle 130: columnar solidified body

Claims (6)

기설치된 기성말뚝과 기성말뚝 사이의 위치로 천공기능과 주입기능이 가능한 제팅 머신(100, JETTING MACHINE)을 이동시켜 설치하는 제팅 머신 이동 설치단계(S10);
회전 가능한 더블 로드(110, Double Rod)를 지중에 근입해서 회전시키는 한편 상기 더블 로드(110)를 통해 드릴 비트(111)까지 청수를 압송시켜 계획심도까지 상기 더블 로드(110)가 굴진토록 하는 더블 로드를 이용한 천공단계(S20);
상기 더블 로드(110)의 작용으로 천공작업이 완료되면, 상기 제팅 머신(100)의 타이머를 조절해서 상기 더블 로드(110)의 회전수를 LJP(LOW JET PILE)의 시공모드로 변경하는 LJP 시공모드 변경단계(S30);
더블 로드를 이용한 천공단계(S20)의 청수를 현탁액으로 변경시켜 상기 제팅 머신(100)에 탑재된 초고압 펌프(PUMP)를 조절하여 주입재의 주입압을 상승시키되 주입압이 계획치에 도달하면 상기 더블 로드(110)의 선단에 제팅 노즐(120, Jetting Nozzle)을 장착하여 주입재를 분사하면서 회전하게 하되 상기 제팅 노즐(120)이 한 바퀴 또는 한 바퀴 반을 회전하면서 자동으로 상승하는 동작이 반복되도록 하는 LJP 작업이 개시되는 LJP 작업 개시단계(S40);
상기 더블 로드(110)를 회전시키되 목적된 심도까지 제팅 노즐(120)이 상승토록 하면서 계획된 주입 상한선까지 상기 LJP 작업을 계속 진행하는 LJP 작업 진행단계(S50);
상기 주입 상한선까지 시공하여 지반 중에 주입재에 의한 원주상의 고결체(130)를 조성 완료함으로써 각각의 PHC 기성말뚝을 일체화시키는 LJP 작업 완료단계(S60);
상기 LJP 작업의 완료 후, 청수를 압송시커 상기 더블 로드(110)를 세척하는 더블 로드 세척단계(S70);
상기 제팅 머신(100)을 다음 위치로 이동시키는 제팅 머신 이동단계(S80);
상기 원주상의 고결체(130)를 기초로 해서 흙막이 벽체를 시공하는 벽체 시공단계(S90)를 포함하는 것을 특징으로 하는 흙막이 벽체 시공방법.
A jetting machine movement installation step (S10) of moving and installing a jetting machine (100, JETTING MACHINE) capable of puncturing and injection into a position between a pre-installed ready-made pile and a ready-made pile;
The rotatable double rod (110, Double Rod) is rotated by being brought into the ground while the fresh water is pumped through the double rod (110) to the drill bit (111), so that the double rod (110) is excavated to the planned depth. Drilling step using a rod (S20);
When the drilling operation is completed by the action of the double rod 110, the LJP construction changes the rotation speed of the double rod 110 to the construction mode of LJP (LOW JET PILE) by adjusting the timer of the jetting machine 100. Mode change step (S30);
By changing the fresh water of the drilling step (S20) using a double rod into a suspension to adjust the ultra high pressure pump (PUMP) mounted on the jetting machine 100 to increase the injection pressure of the injection material, but when the injection pressure reaches the planned value, the double rod 110 Jetting Nozzle (120) is mounted on the front end of the jet to rotate while jetting the injection material, but the LJP operation is repeated so that the jetting nozzle 120 rotates one or one and a half turns automatically. LJP work start step (S40) to be started;
An LJP operation proceeding step (S50) of rotating the double rod 110 to continue the LJP operation up to a planned injection upper limit while the jetting nozzle 120 is raised to a desired depth;
LJP work completion step of integrating each PHC ready-made pile by constructing to the upper limit of the injection to complete the circumferential solid body 130 by the injection material in the ground (S60);
After the completion of the LJP operation, the double rod washing step (S70) for washing the double rod 110 by pressure feeding the fresh water (S70);
A jetting machine moving step (S80) of moving the jetting machine 100 to a next position;
And a wall construction step (S90) of constructing a retaining wall on the basis of the columnar solid body 130.
삭제delete 삭제delete 삭제delete 제1항에 있어서,
상기 더블 로드(110)를 이용한 천공단계(S20)에는 천공되는 제1 방향(제팅노즐(120) 하부방향)으로 천공수가 토출되되 압축공기 분출구를 통해 공기가 계속 분출됨으로써 슬라임(SLIME)의 역류로 인해 압축공기 분출구가 막히는 현상을 방지하며,
상기 LJP 작업 개시단계(S40) 및 상기 LJP 작업 진행단계(S50)에서는 상기 제1 방향(하향)에 교차되는 제2 방향(제팅노즐 가로방향)으로 주입재가 토출되는 것을 특징으로 하는 흙막이 벽체 시공방법.
According to claim 1,
In the drilling step (S20) using the double rod 110, the perforated water is discharged in the first direction (the lower direction of the jetting nozzle 120), but air is continuously blown out through the compressed air blowing port, so as to reverse flow of slime (SLIME). Prevents clogging of compressed air jets,
In the LJP work initiation step (S40) and the LJP work initiation step (S50), a method for constructing a retaining wall, characterized in that the injection material is discharged in a second direction (horizontal direction of jetting nozzle) crossing the first direction (downward) .
삭제delete
KR1020190071686A 2019-06-17 2019-06-17 Method for constructing earth retaining wall KR102117392B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190071686A KR102117392B1 (en) 2019-06-17 2019-06-17 Method for constructing earth retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190071686A KR102117392B1 (en) 2019-06-17 2019-06-17 Method for constructing earth retaining wall

Publications (1)

Publication Number Publication Date
KR102117392B1 true KR102117392B1 (en) 2020-06-03

Family

ID=71087594

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190071686A KR102117392B1 (en) 2019-06-17 2019-06-17 Method for constructing earth retaining wall

Country Status (1)

Country Link
KR (1) KR102117392B1 (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030024723A (en) * 2003-02-10 2003-03-26 주식회사 동아지질 The inserting method of steel pipe for Jet Grouting Pile
KR20060099889A (en) * 2005-03-15 2006-09-20 남기천 Structure and construction method of cut-off wall using jet grouting
KR20090028025A (en) * 2007-09-13 2009-03-18 제이씨개발(주) Micro-pile method
KR20150094711A (en) 2012-12-13 2015-08-19 닛산 가가쿠 고교 가부시키 가이샤 Liquid crystal alignment agent, liquid crystal alignment film, and liquid crystal display element
KR20150108121A (en) 2014-03-17 2015-09-25 김규진 Process for Annulling Deliquescence of Calcium Nitrate in Solid Fuel Compound
KR101557048B1 (en) * 2014-08-12 2015-10-02 한국기초(주) the construction method of the improved smart wall cast injected concrete pile structure
KR20160048716A (en) 2013-09-05 2016-05-04 아스모 가부시키가이샤 Wiper blade and wiper
KR20170079546A (en) 2015-12-30 2017-07-10 (주) 스카이미디어 Polarizing film for dual vision and polarized stereoscopic display device having the same

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030024723A (en) * 2003-02-10 2003-03-26 주식회사 동아지질 The inserting method of steel pipe for Jet Grouting Pile
KR20060099889A (en) * 2005-03-15 2006-09-20 남기천 Structure and construction method of cut-off wall using jet grouting
KR20090028025A (en) * 2007-09-13 2009-03-18 제이씨개발(주) Micro-pile method
KR20150094711A (en) 2012-12-13 2015-08-19 닛산 가가쿠 고교 가부시키 가이샤 Liquid crystal alignment agent, liquid crystal alignment film, and liquid crystal display element
KR20160048716A (en) 2013-09-05 2016-05-04 아스모 가부시키가이샤 Wiper blade and wiper
KR20150108121A (en) 2014-03-17 2015-09-25 김규진 Process for Annulling Deliquescence of Calcium Nitrate in Solid Fuel Compound
KR101557048B1 (en) * 2014-08-12 2015-10-02 한국기초(주) the construction method of the improved smart wall cast injected concrete pile structure
KR20170079546A (en) 2015-12-30 2017-07-10 (주) 스카이미디어 Polarizing film for dual vision and polarized stereoscopic display device having the same

Similar Documents

Publication Publication Date Title
KR20100068597A (en) A shoring method using arch plate pile and h-pile
KR101065017B1 (en) A shoring method using arch plate pile and H-Pile
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
JP2019015100A (en) Removing method of earth retaining wall
JP2013147933A (en) Earth retaining wall construction method, cast-in-place pile construction method, earth retaining wall, and cast-in-place pile
KR101095393B1 (en) Method and apparatus for improving ground using cement grouting
KR100719875B1 (en) Structure and construction method of cut-off wall using jet grouting
KR20110079475A (en) Apparatus for constructing pile using spray type excavating bit
KR102117392B1 (en) Method for constructing earth retaining wall
KR100781492B1 (en) Structure of retaining wall, and construction methods for the same
JP2001098541A (en) Steel pipe soil cement composite pile, and construction method and device
JP4485006B2 (en) Construction method for underground structures
KR101031603B1 (en) Method and apparatus for drilling road of rotate discharge
KR102287362B1 (en) Reinforcement method fot tip of PHC pile using loe fluidity mortar
JP3760343B2 (en) Drilling bottom stabilization method and construction method of underground building
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
RU2238366C1 (en) Method of injection pile building
KR100507983B1 (en) Method for piling sheet in the base rock
KR101224440B1 (en) Construction method of screw file
KR20180062669A (en) Micropile and micropile molding method for earthquake-proof and strengthening ground
JP2010281084A (en) Constructive method of bracing wall, constructive method of pile, bracing wall, pile
JP4905296B2 (en) Method for constructing retaining wall and retaining wall
JP2005146756A (en) Earth retaining impervious wall construction method and earth retaining impervious wall formed by it
JP2007120154A (en) Foundation pile erection method
KR20160028565A (en) A Displacement Bored Pile Method with Impermeable and Detachable Casing Shoe

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant