JP2005133348A - Continuous construction method of revetment, and method of widening river or the like - Google Patents
Continuous construction method of revetment, and method of widening river or the like Download PDFInfo
- Publication number
- JP2005133348A JP2005133348A JP2003368034A JP2003368034A JP2005133348A JP 2005133348 A JP2005133348 A JP 2005133348A JP 2003368034 A JP2003368034 A JP 2003368034A JP 2003368034 A JP2003368034 A JP 2003368034A JP 2005133348 A JP2005133348 A JP 2005133348A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pipe pile
- revetment
- press
- constructed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 29
- 238000000034 method Methods 0.000 title claims abstract description 14
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 129
- 239000010959 steel Substances 0.000 claims abstract description 129
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 7
- 238000009412 basement excavation Methods 0.000 claims description 12
- 239000004576 sand Substances 0.000 claims description 8
- 239000013049 sediment Substances 0.000 abstract description 2
- 230000000694 effects Effects 0.000 description 4
- 238000007796 conventional method Methods 0.000 description 2
- 238000009418 renovation Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Revetment (AREA)
Abstract
Description
本発明は、河川や堤防等のコンクリート護岸あるいは石材等で構成した護岸(以下、コンクリート護岸という)の改修工事あるいは補強工事を行うための護岸の連続構築方法およびそれを利用した河川や沼、海岸等の拡幅工法に関するものである。 The present invention relates to a method for continuously constructing a seawall for repairing or reinforcing a seawall (hereinafter referred to as a concrete seawall) composed of a concrete seawall or stone material such as a river or a dike, and a river, a swamp or a coast using the same. This is related to the widening method.
河川の氾濫を防ぐために、川巾を拡幅したり川底を浚渫するなどして流路面積を大きくする工事が行われているが、従来の工法では護岸の巾以上の拡幅は不可能であった。また、従来の護岸の形状はコンクリートブロックなどを法面に積載したものが多く、これは河川の巾を狭める結果となっていた。 In order to prevent the flooding of the river, work has been done to increase the flow area by widening the river width or dredging the river bottom, but it was impossible to widen the width of the revetment beyond the conventional method. . In addition, the shape of the conventional revetment is often a concrete block loaded on the slope, which resulted in narrowing the width of the river.
従来の川底を深くする方法には、例えば特開平9−31935に開示されたのがある。この方法は河川に鋼矢板壁を対向して設置しこれを切梁で支え、この上にクレーンを搭載した移動台を走行レール上に移動自在としたものである。 A conventional method for deepening a riverbed is disclosed in, for example, JP-A-9-31935. In this method, a steel sheet pile wall is installed opposite to a river, supported by a beam, and a moving table on which a crane is mounted is movable on a traveling rail.
このような従来の装置では、重機が河川の中に入るため川の流れをせき止めなくてはならず、改修作業が大掛かりとなり、費用も人手もかかり工期も長くなっていた。さらには、流路が狭くなるため、増水時には重機を撤収する作業が行えなくなるなどの問題点があった。
本発明は上記の点に鑑みなされたものであり、大掛かりな仮設装置又は仮設工事などを必要とせず、安定した状態で鋼管杭を連続して打設して効率的に河川や堤防の護岸の改修あるいは補強ができる構築方法と、それを利用した河川や沼、海岸等の拡幅工法を提供するものである。 The present invention has been made in view of the above points, and does not require a large-scale temporary device or temporary work, and the steel pipe piles are continuously placed in a stable state to efficiently revet a river or a dike. It provides a construction method that can be renovated or reinforced, and a widening method for rivers, swamps, coasts, etc. using it.
本発明の要旨とするところは、鋼管杭を回転圧入できる鋼管杭圧入装置を用いてコンクリート護岸に鋼管杭列を構築し、この鋼管杭列から反力を得ながら、上記鋼管杭列に連続して鋼管杭を回転圧入して連続壁を構築する護岸の連続構築方法である。 The gist of the present invention is that a steel pipe pile row is constructed on a concrete revetment using a steel pipe pile press-fitting device capable of rotary press-fitting of steel pipe piles, and a reaction force is obtained from the steel pipe pile row while continuing to the steel pipe pile row. This is a continuous revetment construction method in which steel pipe piles are rotationally press-fitted to construct a continuous wall.
また本発明の要旨とするところは、鋼管杭を回転圧入できる鋼管杭圧入装置を用いてコンクリート護岸に鋼管杭列を構築し、この鋼管杭列から反力を得ながら掘削用鋼管杭を圧入してコンクリート護岸に対して所定の深さの穴を掘削し、その後上記掘削用鋼管杭を引き抜いて上記穴の中に鋼管杭を圧入して連続壁を構築する護岸の連続構築方法である。 In addition, the gist of the present invention is that a steel pipe pile row is constructed on a concrete revetment using a steel pipe pile press-fitting device capable of rotationally press-fitting a steel pipe pile, and the steel pipe pile for excavation is press-fitted while obtaining a reaction force from the steel pipe pile row. This is a continuous construction method of a revetment in which a hole having a predetermined depth is excavated with respect to a concrete revetment, and then the steel pipe pile for excavation is pulled out and the steel pipe pile is pressed into the hole to construct a continuous wall.
また本発明の要旨とするところは、上記の護岸の連続構築方法において、鋼管杭等を鋼管杭圧入装置に装着するために必要なクレーン、鋼管杭等の搬送装置等の付帯設備を鋼管杭列上で作業可能に配置して連続壁を構築する護岸の連続構築方法である。 Further, the gist of the present invention is that in the above-described continuous construction method of a revetment, ancillary equipment such as a crane, a steel pipe pile, and the like necessary for mounting a steel pipe pile or the like on a steel pipe pile press-fitting device is connected to a steel pipe pile row. This is a continuous construction method of revetment where a continuous wall is constructed so that it can be worked on.
また本発明の要旨とするところは、上記の護岸の連続構築方法を用いて連続壁を構築し、その後、拡幅作業を行う作業装置あるいは撤去作業を行う撤去装置を鋼管杭列上又は鋼管杭列近傍に配置して、上記構築された連続壁の拡幅する側の土砂等の撤去あるいは近傍の水底を浚渫する河川等の拡幅工法である。 Further, the gist of the present invention is that the continuous wall is constructed using the above-described continuous construction method of the revetment, and then the work device for performing the widening work or the removal device for performing the removal work is provided on the steel pipe pile row or the steel pipe pile row. This is a method of widening a river or the like that is disposed in the vicinity and removes earth and sand on the widening side of the constructed continuous wall or drowns the water bottom in the vicinity.
請求項1の発明より、コンクリート護岸の改修工事や護岸の補強工事あるいは河川等の浚渫工事等が安全かつ効率よく行える。
特に従来では拡幅不可能な河川等における改修工事が可能となり、この拡幅工事を行うための仮設工事を一切必要としないので工期の短縮、工費の削減を図ることができる。また、鋼管杭を回転しながら圧入するため、アースオーガ等の装置も必要としない。
請求項2の発明より、上記請求項1の効果に加えて、護岸のコンクリート部分のみビットを備えた掘削用の鋼管杭で掘削してから掘削用鋼管杭を抜き、その後一般の鋼管杭すなわちビットなしの鋼管杭を圧入することにより工事のコストダウンが図れる。
請求項3の発明より、鋼管杭を鋼管杭圧入装置に装着するために必要なクレーン、鋼管杭の搬送装置等の付帯設備を設置するための架設工事の必要がないため、そのために工期の短縮、工費の削減を図ることができる。
請求項4の発明より、河川等の拡幅のための土砂等の撤去作業あるいは河川等の浚渫作業において、撤去用や浚渫用の作業機械を河川等の水中に投入せずに撤去作業や浚渫作業が行えるため、従来のような河川の流路変更などの撤去作業や浚渫作業に付帯した仮設工事は必要としない。また例えば洪水時のような増水時にもこれらの作業が可能となった。
According to the invention of
In particular, it is possible to perform repair work in rivers and the like that cannot be widened conventionally, and no temporary work is required to perform this widening work, so the construction period can be shortened and the construction cost can be reduced. Moreover, since a steel pipe pile is pressed in while rotating, an apparatus such as an earth auger is not required.
According to the invention of claim 2, in addition to the effect of
According to the invention of claim 3, since there is no need for installation work for installing ancillary equipment such as a crane, a steel pipe pile conveying device, etc. necessary for mounting the steel pipe pile to the steel pipe pile press-fitting device, the construction period is shortened accordingly. This can reduce the construction cost.
According to the invention of claim 4, in removal work such as earth and sand for widening rivers or dredging work in rivers, removal work or dredging work without throwing work machines for removal or dredging into the water of rivers etc. Therefore, there is no need for temporary work associated with removal work and dredging work, such as changing the river flow path. In addition, these operations became possible even when the water volume increased, such as during a flood.
本発明を実施するための最良の形態は、クレーン等の付帯設備を鋼管杭列上で作業可能に配置して、鋼管杭を回転圧入できる鋼管杭圧入装置を用いてコンクリート護岸に鋼管杭列を構築し、この鋼管杭列から反力を得ながら、上記鋼管杭列に連続して鋼管杭を回転圧入して連続壁を構築する護岸の連続構築方法である。
また、本発明を実施するための最良の形態は、上記の護岸の連続構築方法を用いて連続壁を構築し、その後、拡幅作業を行う作業装置あるいは撤去作業を行う撤去装置を鋼管杭列上又は鋼管杭列近傍に配置して、上記構築された連続壁の河川側の土砂等の撤去あるいは近傍の水底を浚渫する河川等の拡幅工法である。
In the best mode for carrying out the present invention, ancillary equipment such as a crane is arranged so as to be able to work on a steel pipe pile row, and a steel pipe pile row is placed on a concrete revetment using a steel pipe pile press-fitting device capable of rotationally press-fitting a steel pipe pile. It is a continuous revetment construction method in which a continuous wall is constructed by rotating and press-fitting a steel pipe pile continuously into the steel pipe pile row while building and obtaining reaction force from the steel pipe pile row.
Moreover, the best mode for carrying out the present invention is to construct a continuous wall using the above-described continuous construction method for revetment, and then install a working device for widening work or a removing device for removing work on a steel pipe pile row. Or it is the widening method of the river etc. which arrange | positions in the steel pipe pile row | line | column vicinity, removes the earth and sand etc. of the river side of the constructed said continuous wall, or drowns the water bottom of the vicinity.
図1は本発明の一実施例を示すもので図1は鋼管杭の構築方法を説明する正面図、図2は図1のI−I線断面図、図3は図1のII−II線断面図、図4は実施例3を示す説明図、図5は実施例4を示す説明図、図6は実施例5を示す説明図及び図7は従来の護岸の断面図である。 FIG. 1 shows an embodiment of the present invention. FIG. 1 is a front view for explaining a method for constructing a steel pipe pile, FIG. 2 is a cross-sectional view taken along the line II in FIG. 1, and FIG. 4 is an explanatory view showing the third embodiment, FIG. 5 is an explanatory view showing the fourth embodiment, FIG. 6 is an explanatory view showing the fifth embodiment, and FIG. 7 is a sectional view of a conventional revetment.
本実施例の護岸の連続構築方法を図に基づいて説明する。
図1において、符号11は鋼管杭圧入装置であり、鋼管杭列PL上を自走して移動する。符号12はクレーン、13は鋼管杭の搬送装置、14は鋼管杭搬送用の台車、15は浚渫装置であり、これらの付帯設備はすべて鋼管杭列PL上に敷設したレール20上を移動可能である。符号Pは鋼管杭である。
上記鋼管杭列PLは、鋼管杭Pを連続的に圧入したものであるが、鋼管杭P、P同士を互いに接触して圧入することもでき、一定の間隔を有して圧入することもできる。
The revetment continuous construction method of the present embodiment will be described with reference to the drawings.
In FIG. 1, the code |
Although the said steel pipe pile row | line PL is what press-fits the steel pipe pile P continuously, it can also press-fit the steel pipe piles P and P mutually and can also press-fit with a fixed space | interval. .
本実施例の護岸の連続構築方法は、河川に設けられたコンクリート護岸102に複数の鋼管杭P,Pを連続して圧入した鋼管杭列PL上に配置した鋼管杭圧入装置11、クレーン12、鋼管杭の搬送装置13等を用いて行う。
上記鋼管杭圧入装置11は、鋼管杭Pを圧入する際に、鋼管杭Pを回転させながら圧入することができ、同時に通常の圧入機のように鋼管杭Pを回転させないで上部からの圧力のみによって圧入できるものである。このように鋼管杭の圧入を回転によって行うため、アースオーガ等の大掛かりな装置を必要としない上に、作業も迅速となる。
The continuous revetment construction method of the present embodiment is a steel pipe pile press-in
The steel pipe pile press-in
なお、図1ではすでにコンクリート護岸102に鋼管杭P,Pを圧入してある状態を示しているが、構築の最初は鋼管杭圧入機11は公知の反力架台から反力を得て適宜本数の鋼管杭Pを圧入するのである。そして、この鋼管杭Pに鋼管杭圧入機11を配置し、以後は圧入された鋼管杭Pより反力を得て、新たな鋼管杭Pを圧入していくのである。
Although FIG. 1 shows a state where steel pipe piles P are already press-fitted into the
まず、鋼管杭圧入装置11を用い、上記鋼管杭列PL上に配置したクレーン12によって台車14より鋼管杭Pを鋼管杭圧入装置11に運搬して、装着する。その後、鋼管杭圧入装置11を作動させて、鋼管杭Pを既設の鋼管杭Pに連続して圧入する。この場合鋼管杭Pは、既設の鋼管杭Pと接触して圧入しても良いが、一定の距離をおいて圧入しても良い。このときの反力は鋼管杭列PLから得る。
また、本実施例では、コンクリート護岸102を打ち抜くために、鋼管杭として先端にビットを備えた掘削用鋼管杭を用いている。この掘削用鋼管杭Pを回転させながら支持層109まで圧入して鋼管杭列PL、すなわち連続壁を構築するのである。
First, using the steel pipe pile press-in
In this embodiment, in order to punch out the
その後、上記のようにして構築した鋼管杭列PLの河川101側のコンクリート護岸102と土砂を撤去する。この撤去は鋼管杭列PL上に配置したブレーカ等の破砕機(図示せず)によって行う。これによって河川101の巾が広くなり、河川の有効利用が図れる。
Thereafter, the
さらに、図2に示すような岸に近い川底103の浚渫を行い河川の拡幅工事を行う。この浚渫工事は、鋼管杭列PL上に配置した浚渫作業装置15によって行う。この装置は鋼管杭Pの上に限らず側部に配置しても良い。
上記のようにコンクリート護岸102と土砂の撤去作業と河川101の拡幅工事の終了後、鋼管杭列PLの表面を化粧板Kで被覆する。
Furthermore, the
As described above, the surface of the steel pipe pile row PL is covered with the decorative plate K after the
上記のように本実施例によれば、従来では拡幅不可能な河川における改修工事が可能となる。この場合従来の護岸の構造体を活用できるため、工期が短縮され工費が削減される上に、鋼管杭Pが大きな強度部材となり護岸の補強がなされる。
また、圧入のための反力を鋼管杭より得ることができるため装置がコンパクトになり、拡幅工事を行うための仮設工事を一切必要とせず、コンクリート護岸の改修工事が安全かつ効率よく行える。
なお、本実施例では、河川101について説明したが、沼、湖の堤防や海岸の防波堤についても適用でき同様の効果を奏する。
As described above, according to the present embodiment, it is possible to perform repair work in a river that cannot be widened conventionally. In this case, since the conventional revetment structure can be utilized, the construction period is shortened and the construction cost is reduced, and the steel pipe pile P becomes a large strength member and the revetment is reinforced.
In addition, since the reaction force for press-fitting can be obtained from the steel pipe pile, the apparatus becomes compact, and there is no need for temporary work for widening work, and the renovation work for the concrete revetment can be performed safely and efficiently.
In this embodiment, the
次に、本発明の実施例2について説明する。
この実施例は、上記実施例1のように鋼管杭列PLから反力を得ながら掘削用鋼管杭Pをコンクリート護岸102に圧入するが、この掘削用鋼管杭Pがコンクリート護岸102を打ち抜いて所定の深さまで到達したら圧入を停止する。
その後、鋼管杭圧入装置11によって掘削用鋼管杭Pを引き抜いて、これによって掘削された穴の中に一般の鋼管杭Pを配置して圧入することで連続壁である鋼管杭列PLを構築するものである。
Next, a second embodiment of the present invention will be described.
In this embodiment, the excavation steel pipe pile P is press-fitted into the
Thereafter, the steel pipe pile P for excavation is pulled out by the steel pipe pile press-fitting
本実施例は上記実施例1で説明した効果を有するが、さらに次の効果も有する。すなわちコンクリート護岸の部分だけを掘削用鋼管杭で掘削して、その後、土の部分は一般の鋼管杭すなわちビットなしの鋼管杭を圧入するため工事のコストダウンが図れるのである。 This embodiment has the effects described in the first embodiment, but also has the following effects. That is, only the portion of the concrete revetment is excavated with a steel pipe pile for excavation, and then the portion of the soil is pressed into a general steel pipe pile, that is, a steel pipe pile without a bit, so that the construction cost can be reduced.
実施例3は図4に示すもので、上記実施例1あるいは実施例2の鋼管杭Pをコンクリート護岸102の上端より河川側の位置に圧入するものである。
この実施例では、鋼管杭Pのコンクリート護岸102への圧入距離が短くなるため圧入が容易に行え、かつ撤去する土砂等も少量となりフーチングも一部分の撤去ですむため工期が短縮できるという長所がある。
Example 3 is shown in FIG. 4, and the steel pipe pile P of Example 1 or Example 2 is press-fitted into the river side position from the upper end of the
In this embodiment, since the press-fitting distance of the steel pipe pile P to the
実施例4は図5に示すもので、護岸が道路より高く構築されている場合であり、このような護岸に対しては河川101側だけでなく、道路側のコンクリート護岸および土砂105も除去する。これによって、道路が広くなるというメリットがある。
また、この場合にも鋼管杭列PL上ですべての作業が行われるため、工事用のトラック等の往来もなく通行を妨げることはない。
Example 4 is shown in FIG. 5 and is a case where the revetment is constructed higher than the road. For such a revetment, not only the
In this case as well, since all the work is performed on the steel pipe pile row PL, the traffic is not hindered without traffic of a construction truck or the like.
実施例5は図6に示すもので、コンクリート護岸107の基部のフーチング108に鋼管杭Pを圧入するものである。この実施例は既存の護岸の補強工事を目的とするものである。
Example 5 is shown in FIG. 6, and the steel pipe pile P is press-fitted into the
11 鋼管杭圧入装置
12 クレーン
13 搬送装置
14 台車
15 浚渫装置
20 レール
101 河川等
102 コンクリート護岸
103 川底
105 土砂等(拡幅部分)
P 鋼管杭(掘削用鋼管杭及び一般の鋼管杭)
K 化粧板
DESCRIPTION OF
P Steel pipe pile (steel pipe pile for excavation and general steel pipe pile)
K decorative board
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003368034A JP4105076B2 (en) | 2003-10-28 | 2003-10-28 | Revetment continuous construction method and river widening method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003368034A JP4105076B2 (en) | 2003-10-28 | 2003-10-28 | Revetment continuous construction method and river widening method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2005133348A true JP2005133348A (en) | 2005-05-26 |
JP4105076B2 JP4105076B2 (en) | 2008-06-18 |
Family
ID=34645860
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003368034A Expired - Lifetime JP4105076B2 (en) | 2003-10-28 | 2003-10-28 | Revetment continuous construction method and river widening method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4105076B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017043992A (en) * | 2015-08-27 | 2017-03-02 | 鹿島建設株式会社 | Pile row construction system and pile row construction method |
JP2020076277A (en) * | 2018-11-09 | 2020-05-21 | ジオスター株式会社 | Method for constructing earth retaining wall |
JP2021099007A (en) * | 2019-12-24 | 2021-07-01 | Jfeスチール株式会社 | Steel pipe, steel pipe structure, and construction method of steel pipe structure |
JP2021099006A (en) * | 2019-12-24 | 2021-07-01 | Jfeスチール株式会社 | Continuous wall construction method |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012197618A (en) * | 2011-03-22 | 2012-10-18 | Shinei Kk | Repair method for existing revetment |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05112928A (en) * | 1991-10-24 | 1993-05-07 | Nippon Steel Corp | Steel pipe pile column construction method |
JPH0621962Y2 (en) | 1987-06-23 | 1994-06-08 | 株式会社技研製作所 | Clamping device for pile press-in / pull-out machine |
JPH06240672A (en) * | 1993-02-12 | 1994-08-30 | Giken Seisakusho Co Ltd | Hydraulic unit |
JPH0931935A (en) * | 1995-07-18 | 1997-02-04 | Kawasaki Steel Corp | Repair method for urban river |
JPH09195273A (en) | 1996-01-13 | 1997-07-29 | Okumuragumi Doboku Kogyo Kk | Pile driven hole forming method for bulkhead |
JPH11107664A (en) | 1997-10-06 | 1999-04-20 | Marutoku Kigyo:Kk | Excavation casing |
JP2001214434A (en) | 2000-02-01 | 2001-08-07 | Nippon Sharyo Seizo Kaisha Ltd | Steel pipe piling wall and method for constructing it |
JP2002348870A (en) | 2001-05-23 | 2002-12-04 | Tosa Kikai Kogyo Kk | Machine for pressing-in and extracting steel pipe pile |
JP2003082636A (en) * | 2001-09-13 | 2003-03-19 | Kobe Steel Ltd | Breakwater structure and method for constructing the same |
JP2003138563A (en) | 2001-11-06 | 2003-05-14 | Giken Seisakusho Co Ltd | Chucking device, pile press-in device and pile press-in technique |
-
2003
- 2003-10-28 JP JP2003368034A patent/JP4105076B2/en not_active Expired - Lifetime
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0621962Y2 (en) | 1987-06-23 | 1994-06-08 | 株式会社技研製作所 | Clamping device for pile press-in / pull-out machine |
JPH05112928A (en) * | 1991-10-24 | 1993-05-07 | Nippon Steel Corp | Steel pipe pile column construction method |
JPH06240672A (en) * | 1993-02-12 | 1994-08-30 | Giken Seisakusho Co Ltd | Hydraulic unit |
JPH0931935A (en) * | 1995-07-18 | 1997-02-04 | Kawasaki Steel Corp | Repair method for urban river |
JPH09195273A (en) | 1996-01-13 | 1997-07-29 | Okumuragumi Doboku Kogyo Kk | Pile driven hole forming method for bulkhead |
JPH11107664A (en) | 1997-10-06 | 1999-04-20 | Marutoku Kigyo:Kk | Excavation casing |
JP2001214434A (en) | 2000-02-01 | 2001-08-07 | Nippon Sharyo Seizo Kaisha Ltd | Steel pipe piling wall and method for constructing it |
JP2002348870A (en) | 2001-05-23 | 2002-12-04 | Tosa Kikai Kogyo Kk | Machine for pressing-in and extracting steel pipe pile |
JP2003082636A (en) * | 2001-09-13 | 2003-03-19 | Kobe Steel Ltd | Breakwater structure and method for constructing the same |
JP2003138563A (en) | 2001-11-06 | 2003-05-14 | Giken Seisakusho Co Ltd | Chucking device, pile press-in device and pile press-in technique |
Non-Patent Citations (11)
Title |
---|
JPN3011000322; 'くっさく、せっさくの項' 大辞林 新装第2版, 19991001, P.722,1408, 株式会社三省堂 |
JPN3013000412; '工法革命で世界の建設を変える' 技研製作所のHP , 20130318, (株)技研製作所 |
JPN3013000413; '圧入工法' 技研製作所のHP , 20130318, (株)技研製作所 |
JPN3013000414; '硬質地盤クリア工法' 硬質地盤対応機スーパークラッシュ SCU-400M SCU-600M 技術資料 OR Ver 5.0JA03, 20120130, (株)技研製作所 |
JPN3013000415; 「硬質地盤クリア工法」の実施に関する写真 |
JPN3013000416; 「硬質地盤クリア工法」の実施に関する図面 , 2001 |
JPN3013000417; '圧入施工の家元' 技研施工のHP , 20130318, (株)技研施工 |
JPN3013000418; (株)技研施工のHP , 20130318, (株)技研施工 |
JPN3013000419; (株)技研施工のHP , 20130318, (株)技研施工 |
JPN3013000420; 'バイオルーガ併用圧入' (株)技研施工のHP , 20130318, (株)技研施工 |
JPN3013000421; 硬質地盤クリア工法 , SEKO |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017043992A (en) * | 2015-08-27 | 2017-03-02 | 鹿島建設株式会社 | Pile row construction system and pile row construction method |
JP2020076277A (en) * | 2018-11-09 | 2020-05-21 | ジオスター株式会社 | Method for constructing earth retaining wall |
JP7102319B2 (en) | 2018-11-09 | 2022-07-19 | ジオスター株式会社 | How to build a retaining wall |
JP2021099007A (en) * | 2019-12-24 | 2021-07-01 | Jfeスチール株式会社 | Steel pipe, steel pipe structure, and construction method of steel pipe structure |
JP2021099006A (en) * | 2019-12-24 | 2021-07-01 | Jfeスチール株式会社 | Continuous wall construction method |
JP7172978B2 (en) | 2019-12-24 | 2022-11-16 | Jfeスチール株式会社 | Steel pipe, steel pipe structure, method for constructing steel pipe structure |
JP7290105B2 (en) | 2019-12-24 | 2023-06-13 | Jfeスチール株式会社 | continuous wall construction method |
Also Published As
Publication number | Publication date |
---|---|
JP4105076B2 (en) | 2008-06-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6139225A (en) | Method for building an underground continuous wall | |
KR100758113B1 (en) | Cast-in-place large diameter piling method by casing rotator in underwater rock conditions | |
JP4105076B2 (en) | Revetment continuous construction method and river widening method | |
CN112523233B (en) | Construction method of water-through type river-blocking cofferdam | |
JP3733533B2 (en) | Foundation reinforcement method under pressure of existing structures | |
KR20180096552A (en) | Multi-wall construction method for construction of ports, rivers, dams, and concrete buildings that can prevent the inflow of soil and water, and building structure using the multi-wall structure | |
JP2002146811A (en) | Construction method for underwater structure foundation | |
CN115614542B (en) | Pipe jacking construction method taking existing foundation pit in water as starting point | |
JP5524642B2 (en) | Cutting method | |
JP3250709B2 (en) | Open shield method | |
JP4504864B2 (en) | Dam body reinforcement structure with wave-dissipating function | |
CN112962641A (en) | Construction method for dismantling riverbank cofferdam structure | |
JP3192661B2 (en) | Novel sewage wall, method of forming the sewage wall, and members used therefor | |
CN105625428A (en) | Mechanized dam breach pile inserting and damming equipment and method thereof | |
JP3773459B2 (en) | Construction method of underground continuous wall | |
KR100589131B1 (en) | Construction device of underwater bridge base structure that use of barge | |
JP2014177787A (en) | Open shield method | |
CN113737790B (en) | Bridge pile and steel sheet pile synchronous construction method | |
JP6403300B1 (en) | How to embed sheet pile | |
JP3766423B2 (en) | Retaining wall construction method | |
CN217710783U (en) | Occupy full section cofferdam of river course structure and break stream structure not | |
CN110004916B (en) | Deep buried sewage pipe obstacle clearing structure and obstacle clearing method suitable for underground diaphragm wall construction | |
CN107059839A (en) | A kind of construction method of armored concrete waveform sheet pile underground structure | |
JP2007231641A (en) | Collapse prevention construction method for dike | |
JP3248102B2 (en) | Ground improvement method for soft ground |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20051206 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20071109 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20071114 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20071225 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080228 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080326 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4105076 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110404 Year of fee payment: 3 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140404 Year of fee payment: 6 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140404 Year of fee payment: 6 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140404 Year of fee payment: 6 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140404 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |