JP2003082636A - Breakwater structure and method for constructing the same - Google Patents

Breakwater structure and method for constructing the same

Info

Publication number
JP2003082636A
JP2003082636A JP2001278550A JP2001278550A JP2003082636A JP 2003082636 A JP2003082636 A JP 2003082636A JP 2001278550 A JP2001278550 A JP 2001278550A JP 2001278550 A JP2001278550 A JP 2001278550A JP 2003082636 A JP2003082636 A JP 2003082636A
Authority
JP
Japan
Prior art keywords
block
wave
breakwater
offshore
blocks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001278550A
Other languages
Japanese (ja)
Inventor
Osamu Kiyomiya
理 清宮
Yasuto Kataoka
保人 片岡
Naoto Takehana
直人 竹鼻
Yasuo Ichikawa
靖生 市川
Yoshihiro Hamazaki
義弘 濱崎
Fujihiko Hashino
藤彦 橋野
Yoji Hanawa
洋二 塙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP2001278550A priority Critical patent/JP2003082636A/en
Publication of JP2003082636A publication Critical patent/JP2003082636A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Revetment (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a breakwater structure for embankment, such as a breakwater and a quay, which facilitates its construction and stabilizes the condition thereof after the construction, in addition to its advantageous shape of a high wave-damping characteristic, and to provide a method for constructing the breakwater structure. SOLUTION: There are provided blocks 8 which form the breakwater structure extending along a shore and overhanging from an upper portion of an offing-side wall surface toward the offing in a manner repelling waves arriving from the offing. Each block is formed in one piece of an offing-side portion (concrete structure 3) forming a breakwater shape, and a sleeve 5 into which a pile is insertable in the vertical direction. These blocks thus formed are arranged side by side to construct the breakwater structure.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、港湾、海岸沿岸域
において、波浪越波、波力から船舶や陸上の人命、建築
物等を防護する防波堤や岸壁など護岸用の防波構造物及
びその施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a breakwater structure for constructing a seawall such as a breakwater and a quay wall for protecting ships, land lives and buildings from wave overtopping and wave forces and its construction in a harbor and coastal coastal area. It is about the method.

【0002】[0002]

【従来の技術】港湾、海岸沿岸域において、波浪越波、
波力から船舶や陸上の人命、建築物等を防護する防波堤
や岸壁など護岸用の防波構造物としては例えば、図1に
示すような直立型ケーソン防波構造物が従来、用いられ
ている。
[Background Art] Overtopping waves,
For example, an upright caisson breakwater structure as shown in FIG. 1 has been conventionally used as a breakwater structure for a seawall such as a breakwater or a quay for protecting ships, land lives, buildings, etc. from wave forces. .

【0003】この直立型ケーソン防波構造物は、海底を
掘り下げ、砂41で置換して地盤改良した上に捨石マウ
ント42を設けることにより基礎40を形成し、その上
に直立型ケーソン30からなる防波構造物本体50が載
置されて構成されている。
This upright caisson breakwater structure is formed by digging the seabed, replacing it with sand 41 to improve the ground, and providing a rubble mount 42 to form a foundation 40, on which the upright caisson 30 is formed. The breakwater structure main body 50 is placed and configured.

【0004】また、従来よく用いられる防波構造物の一
つとして、図2に示すような、いわゆる消波ブロック被
覆護岸と呼ばれる防波構造物がある。この消波ブロック
被覆護岸を新設する場合の施工方法は図3のようにな
る。すなわち、まず基礎を施工した(図3a〜d)の
ち、防波構造物本体製作用の作業用足場53の他、鉄
筋、型枠54を現地で組み立て、型枠54内にコンクリ
ートを打設して防波構造物本体50を製作する(図3e
〜f)。その際、通常、コンクリートを上下方向に何回
かに分けて打設する。その後、裏込石55を投入し(図
3g〜i)、現場近辺で製作した消波ブロック56を運
搬し、トラッククレーン57によって一つずつ据え付
け、図中の点線で示すように防波構造物天端高さまで台
形状に積層して消波ブロック被覆護岸を製作する。(図
3j〜l)ところで、直立型ケーソン防波構造物や消波
ブロック被覆護岸など従来の防波構造物では、十分な非
越波性能を得るために、天端高さを大きくしたり、図2
に示す消波ブロック56の裾広がりを大きくしなければ
ならないという不都合があった。
Further, as one of the conventionally used breakwater structures, there is a breakwater structure called a so-called wave-dissipating block covered revetment as shown in FIG. The construction method for newly constructing this wave-dissipating block covered revetment is as shown in Fig. 3. That is, after first constructing the foundation (FIGS. 3 a to 3 d), in addition to the work scaffold 53 for producing the main body of the wave-proof structure, the reinforcing bar and the form 54 are assembled on site, and concrete is placed in the form 54. To produce the main body 50 of the wave structure (FIG. 3e).
~ F). At that time, usually, concrete is poured in several times in the vertical direction. After that, throw back stones 55 (Figs. 3g to i), carry the wave-dissipating blocks 56 manufactured near the site, install them one by one with a truck crane 57, and install the wave-preventing structure as shown by the dotted line in the figure. A wave-dissipating block covered revetment is manufactured by stacking trapezoids up to the top height. (Figs. 3j to 1) By the way, in the conventional wave-breaking structure such as the upright type caisson wave-breaking structure or the wave-dissipating block-covered seawall, in order to obtain sufficient non-overtopping performance, the crown height is increased or Two
There is an inconvenience that the bottom spread of the wave-dissipating block 56 shown in FIG.

【0005】そこで近年は、沖側壁面の上部が沖側から
到来する波をはね返すように沖側にせり出す部分を有す
る防波形状(曲面や平面で構成される)とすることで、
天端高さを低く抑えながら、高い非越波特性を得る防波
構造物の開発が進められている(以下、沖側壁面の上部
が沖側から到来する波をはね返すように沖側にせり出す
部分を有する防波構造物をその防波形状が曲面か平面か
に関わらず、フレア型防波構造物と総称する)。
Therefore, in recent years, the upper part of the offshore wall surface has a wave-preventing shape (composed of a curved surface or a flat surface) having a portion protruding toward the offshore side so as to repel waves coming from the offshore side.
The development of a breakwater structure that achieves high non-overtopping characteristics while keeping the top height low is underway (hereinafter, the upper part of the offshore wall surface is reflected off the waves coming from the offshore side to the offshore side. A wave-breaking structure having a protruding portion is collectively called a flare-type wave-breaking structure regardless of whether the wave-proof shape is a curved surface or a flat surface).

【0006】例えば、特開平11−241323号公報
には図4に示すように、沖側壁面10の上部に沖側から
到来する波をはね返すように沖側に傾斜する上部傾斜面
11を設けるとともに、陸側に傾斜する下部傾斜面12
を設けて、前記上部傾斜面11に作用する波圧の上向き
分力成分とこの下部傾斜面12に作用する波圧の下向き
分力成分とを相殺させた防波構造物が開示されている。
この構成は低天端でありながら、越波量や波の打ち上げ
高さを大幅に低減することができるものである。
For example, in Japanese Unexamined Patent Publication No. 11-241323, as shown in FIG. 4, an upper inclined surface 11 is provided on the upper part of the offshore side wall surface 10 to incline offshore so as to repel waves coming from the offshore side. , Lower slope 12 that slopes to the land
Is provided to cancel the upward component force component of the wave pressure acting on the upper inclined surface 11 and the downward component force component of the wave pressure acting on the lower inclined surface 12 are disclosed.
This structure is capable of significantly reducing the amount of overtopping waves and the launch height of waves, despite the low ceiling.

【0007】[0007]

【発明が解決しようとする課題】しかし、前述の従来の
防波構造物は、いずれもその製作、施工にあたって、現
地で防波構造物本体のコンクリート打設用の作業用足
場、鉄筋、型枠の組み立てをしなければならず、またコ
ンクリート打設を上下方向に何回かに分けて行わなけれ
ばならないなど、全体として工事期間が長くなるという
問題があった。特に、防波構造物を設置する場所の波浪
条件が良くない場合は、現地工事が1年では終わらず
に、越冬して2年にわたるということもしばしば起き
る。このように現地の工事期間が長くなることは、事故
等の発生する確率を増加させるので、作業の安全という
観点からも好ましくない。
However, all of the above-mentioned conventional wave-breaking structures are used for the production and construction of work scaffolds, reinforcing bars, and formwork for concrete pouring on the body of the wave-breaking structure at the site. There was a problem that the construction period would be long as a whole because the assembling would have to be done, and the concrete pouring would have to be done several times in the vertical direction. In particular, if the wave conditions of the place where the breakwater structure is installed are not good, it often happens that the on-site work does not end in one year and overwinters for two years. Such a long construction period on site increases the probability that an accident or the like will occur, which is not preferable from the viewpoint of work safety.

【0008】さらに、従来の施工方法では、現地で使用
するコンクリートの量が多いために、コンクリートが海
に流出したり、水質汚濁を生じたりするおそれがあっ
た。
Further, in the conventional construction method, since the amount of concrete used locally is large, there is a risk that the concrete may flow out into the sea or cause water pollution.

【0009】特に、フレア型防波構造物の場合は、沖側
壁面の上部が沖側から到来する波をはね返すように沖側
にせり出しているため、その構造が複雑であり、施工に
関して言えば、他の防波構造物と同等であるか、あるい
はそれ以上に施工が困難である。
In particular, in the case of the flare type breakwater structure, since the upper part of the offshore wall surface is projected to the offshore side so as to repel the waves coming from the offshore side, the structure is complicated and, in terms of construction, , It is equivalent to other breakwater structures or more difficult to construct.

【0010】このような不都合を解消する手段として、
例えば、フレア型防波構造物をいくつかのブロックに分
割し、各ブロックを工場で製作して現地まで輸送したの
ち、積み上げるという施工方法が考えられるが、フレア
型防波構造物は上部が沖側にせり出しているので、衝突
する水塊の運動方向が円弧面に沿って強制的に沖向きに
変わり、防波構造物本体を上方に押し上げるように作用
するため、防波構造物各部のブロック各境界面での摩擦
抵抗力の減少を招き、ブロックが浮きあがったり、防波
構造物全体の転倒が生じやすくなるという問題が生じ
る。
As means for solving such inconvenience,
For example, the flare-type breakwater structure may be divided into several blocks, each block manufactured at the factory, transported to the site, and then piled up. Since it protrudes to the side, the moving direction of the colliding water mass is forcibly changed to the offshore direction along the arc surface, and it acts to push up the main body of the breakwater structure. This causes a reduction in the frictional resistance force at each boundary surface, which raises a problem that the block is lifted up and the entire wave preventing structure is likely to fall.

【0011】また、このような浮きあがりや転倒を防止
するために防波構造物の体積や重量を大きくすると、こ
れを支える基礎も大型化し、地盤改良等の施工に要する
コストや時間も増大することになる。
When the volume and weight of the wave preventing structure is increased in order to prevent such floating and falling, the foundation supporting the wave preventing structure also becomes large and the cost and time required for construction such as ground improvement increases. It will be.

【0012】本発明はこのような従来の防波構造物の問
題点に鑑みてなされたものであり、高い非越波特性を持
つ形状としながら、その施工を容易にし、かつ、施工後
の状態を安定なものにすることができる防波構造物とそ
の施工方法を提供することを目的としている。
The present invention has been made in view of the above-mentioned problems of the conventional wave-breaking structure, and facilitates the construction while having a shape having high non-wave overtopping characteristics, and after the construction. It is an object of the present invention to provide a breakwater structure that can be kept in a stable state and a construction method thereof.

【0013】[0013]

【課題を解決するための手段】上記課題を解決するため
の本発明は、すなわち、岸に沿って延び、かつ、沖側壁
面の上部に沖側から到来する波をはね返すように沖側に
せり出す防波形状を持つ防波構造物を形成するためのブ
ロックであって、前記防波形状を形成する沖側部分と、
その後部に設けられ、杭が鉛直方向に挿通可能な鞘管と
を一体に有することを特徴とする防波構造物用ブロック
である。(請求項1)このように本発明は、沖側壁面の
上部に沖側から到来する波をはね返すように沖側にせり
出す部分を有する防波形状を持つ防波構造物用ブロック
であるので、直立型ケーソン防波構造物や消波ブロック
被覆護岸などの従来の防波構造物と比較して高い非越波
特性を有している。このため、特に越波や波の打ち上げ
が問題となる沿岸道路等においては天端高さを抑えなが
ら越波や波の打ち上げを防止することができ、また、消
波ブロックで防波構造物を被覆する必要がないので、設
置する場所の景観を損なうことがない。
Means for Solving the Problems The present invention for solving the above-mentioned problems is to extend to the offshore side so as to extend along the shore and rebound the waves coming from the offshore side to the upper part of the offshore side wall surface. A block for forming a breakwater structure having a breakwater shape, and an offshore portion forming the breakwater shape,
A block for a wave preventing structure, characterized in that the pile is integrally provided with a sheath pipe which is provided at a rear portion thereof and through which a pile can be vertically inserted. (Claim 1) As described above, the present invention is a block for a wave preventing structure having a wave preventing shape, which has a portion protruding to the off side so as to bounce waves coming from the off side on the upper part of the off side wall surface. Compared with conventional wave-breaking structures such as upright caisson wave-breaking structures and wave-blocking block-covered seawalls, it has higher non-overtopping characteristics. For this reason, especially on coastal roads where overtopping or wave launching is a problem, it is possible to prevent overtopping or wave launching while suppressing the crown height, and to cover the wave-breaking structure with a wave-eliminating block. Since it is not necessary, it does not spoil the landscape of the installation site.

【0014】また、前記防波形状を形成する沖側部分
と、その後部に設けられ、杭が鉛直方向に挿通可能な鞘
管とを一体に有するので、地盤上に立設した杭を後部に
設けられた鞘管に挿通して地盤に対するブロックの固定
を確実なものにすることができ、沖側壁面に衝突する水
塊によってブロックが浮きあがったり、防波構造物が転
倒したりすることがない。
Further, since the offshore side portion forming the above-mentioned wave preventing shape and the pile pipe which is provided at the rear portion thereof and through which the pile can be inserted in the vertical direction are integrally formed, the pile standing on the ground is provided at the rear portion. The block can be fixed to the ground securely by inserting it into the provided sheath pipe, and the block may float up due to the water mass colliding with the offshore side wall, or the breakwater structure may fall down. Absent.

【0015】請求項2に記載の発明は、請求項1記載の
防波構造物用ブロックにおいて、前記沖側部分がコンク
リート構造であり、それよりも陸側の部分が複数本の金
属製骨材と上記鞘管を組み合わせてなる骨組構造である
ことを特徴とする防波構造物用ブロックである。
According to a second aspect of the present invention, in the block for a wave preventing structure according to the first aspect, the offshore side portion is a concrete structure, and the land side portion is a plurality of metal aggregates. A wave-breaking structure block having a skeleton structure formed by combining the above and the above-mentioned sheath tube.

【0016】この発明によると、ブロックの沖側部分の
みをコンクリート構造とし、陸側を複数本の金属製骨材
と上記鞘管を組み合わせてなる骨組構造としたので、大
規模な防波構造物の場合、全体をコンクリートで構成す
るよりも軽量化することができ、運搬が容易になるな
ど、施工上の利点がある。
According to the present invention, only the offshore side of the block has a concrete structure, and the land side has a frame structure in which a plurality of metal aggregates and the above-mentioned sheath pipe are combined. In this case, there is an advantage in construction such that the whole can be made lighter than the case where it is made of concrete and the transportation becomes easy.

【0017】請求項3に記載の発明は、請求項2記載の
防波構造物用ブロックにおいて、骨組構造の沖側前面に
配され、沖側壁面と略同等の形状をもつ金属製板材と、
前記金属製板材の沖側表面に配された複数の金属製棒材
とを備え、その金属製板材の沖側前面にコンクリートが
打設されていることを特徴とする防波構造物用ブロック
である。
According to a third aspect of the present invention, in the block for a wave preventing structure according to the second aspect, a metal plate material is provided on the front side of the skeleton structure on the offshore side, and has a shape substantially similar to the offshore side wall surface.
A block for a wave-proof structure, comprising a plurality of metal rods arranged on the offshore surface of the metal plate, and concrete is placed on the offshore front surface of the metal plate. is there.

【0018】この発明によると、金属製板材と、前記金
属製板材の沖側表面に配された複数の金属製棒材とを備
え、その金属製板材の沖側前面にコンクリートが打設さ
れているので、コンクリート表面に存在する金属製板材
によって当該コンクリートを補強することができ、コン
クリートの亀裂や剥離がより生じにくくなる。
According to the present invention, the metal plate member and the plurality of metal rod members arranged on the offshore surface of the metal plate member are provided, and concrete is placed on the offshore front surface of the metal plate member. Therefore, the concrete can be reinforced by the metal plate material existing on the surface of the concrete, and cracking and peeling of the concrete are less likely to occur.

【0019】請求項4に記載の発明は、請求項1〜請求
項3のいずれかに記載の複数のブロックと、地盤に立設
される複数の杭とを備え、これらの杭が前記各ブロック
の鞘管に挿通された状態で各ブロックが地盤上に固定さ
れ、かつ、これらのブロックが岸に沿う方向に並べられ
ることにより、一連の防波形状が形成されていることを
特徴とする防波構造物である。
The invention according to claim 4 is provided with a plurality of blocks according to any one of claims 1 to 3 and a plurality of piles which are erected on the ground, and these piles are provided in each of the blocks. Each block is fixed on the ground in a state of being inserted into the sheath pipe of, and these blocks are arranged in the direction along the shore to form a series of wave-proof shapes. It is a wave structure.

【0020】この発明によると、前述のブロックが岸に
沿う方向に並べられることにより、一連の防波形状が形
成されているので、現地ではこれらのブロックを並べる
だけでよく、現地での工事期間は、著しく短縮される。
また、地盤に立設される複数の杭を備え、これらの杭が
前記各ブロックの鞘管に挿通された状態で各ブロックが
地盤上に固定されるので、地盤に対するブロックの固定
を確実なものにすることができ、沖側壁面に衝突する水
塊によってブロックが浮きあがったり、防波構造物が転
倒したりすることがない。
According to the present invention, the blocks are arranged in the direction along the shore to form a series of breakwater shapes. Therefore, it is sufficient to arrange these blocks on site, and the construction period at the site can be improved. Is significantly shortened.
Moreover, since each block is fixed on the ground with a plurality of piles erected on the ground, and these piles are inserted into the sheath pipes of the blocks, the block is firmly fixed to the ground. Therefore, the block does not float up and the breakwater structure does not fall due to the water mass colliding with the offshore wall surface.

【0021】請求項5に記載の発明は、請求項4記載の
防波構造物において、上記杭と上記鞘管との間の隙間に
固形化剤が充填されていることを特徴とする防波構造物
である。
According to a fifth aspect of the present invention, in the breakwater structure according to the fourth aspect, the gap between the pile and the sheath pipe is filled with a solidifying agent. It is a structure.

【0022】この発明によると、杭と鞘管との間の隙間
に固形化剤が充填されることにより、上記ブロックが杭
に強固に固定されるので、地盤に対する防波構造物の固
定をより確実なものにすることができ、沖側壁面に衝突
する水塊によってブロックが浮きあがったり、防波構造
物が転倒したりすることがない。
According to the present invention, since the block is firmly fixed to the pile by filling the gap between the pile and the sheath pipe with the solidifying agent, the wave-proof structure can be more firmly fixed to the ground. It can be made reliable, and the block does not float up or the breakwater structure does not fall due to the water mass colliding with the offshore wall surface.

【0023】請求項6に記載の発明は、請求項4または
5の防波構造物において、前記各ブロック同士をその沖
側壁面よりも後方の位置で締結する締結具を備え、その
締結により前記複数のブロックが一体化されて前記防波
形状が形成されていることを特徴とする防波構造物であ
る。
According to a sixth aspect of the present invention, in the breakwater structure according to the fourth or fifth aspect, a fastener for fastening the blocks to each other at a position rearward of the offshore side wall surface is provided, and by the fastening, It is a wave-proof structure characterized in that a plurality of blocks are integrated to form the wave-proof shape.

【0024】この発明によると、ブロック同士をその沖
側壁面よりも後方の位置で締結して一体化することによ
り、上記防波形状を形成するので、沖側壁面に衝突する
水塊によってブロックが浮きあがったり、防波構造物が
転倒したりすることを一層防止することができる。
According to the present invention, the blocks are fastened to each other at a position rearward of the offshore wall surface to be integrated with each other, thereby forming the above-mentioned wave-proof shape. It is possible to further prevent the floating structure and the breakwater structure from falling.

【0025】請求項7に記載の発明は、岸に沿って延
び、かつ、沖側壁面の上部に沖側から到来する波をはね
返すように沖側にせり出す部分を有する防波形状を持つ
防波構造物の施工方法であって、請求項1〜請求項3の
いずれかに記載のブロックを形成する工程と、前記杭を
立設する工程と、前記鞘管に前記杭を挿通して前記ブロ
ックを地盤に固定する工程とを含み、これらの工程によ
り、複数のブロックを岸に沿う方向に並べることによ
り、一連の防波形状を形成することを特徴とする防波構
造物の施工方法である。
The invention according to claim 7 is a breakwater having a wave-proof shape which extends along the shore and has a portion protruding to the offshore side so as to repel a wave coming from the offshore side at the upper part of the offshore side wall surface. A method of constructing a structure, comprising the steps of forming the block according to any one of claims 1 to 3, the step of standing the pile, and the block obtained by inserting the pile into the sheath pipe. And a step of fixing to the ground, by these steps, by arranging a plurality of blocks in the direction along the shore, to form a series of wave-proof shape is a method of constructing a wave-proof structure. .

【0026】この発明によると、杭を立設する工程と、
鞘管に前記杭を挿通してブロックを地盤に固定する工程
とを含んでいるので、地盤に対するブロックの固定を確
実なものにすることができ、沖側壁面に衝突する水塊に
よってブロックが浮きあがったり、防波構造物が転倒し
たりすることがない。
According to the present invention, the step of erection the pile,
Since it includes the step of inserting the pile into the sheath pipe and fixing the block to the ground, it is possible to ensure the fixation of the block to the ground, and the block floats due to the water mass colliding with the offshore side wall surface. It does not go up and the breakwater structure does not fall.

【0027】また、複数のブロックを岸に沿う方向に並
べることにより、一連の防波形状を形成するので、現地
でコンクリート打設用の作業用足場、鉄筋、型枠を組み
立てる必要がなく、また、上下方向に何回かに分けてコ
ンクリート打設を行う必要もないなど従来の施工方法と
比較して、工事をより容易にすることができる。このた
め、現地工事期間を大幅に短縮することができ、施工に
かかるコストを低減することができる。また、現地の工
事期間が短くなることにより、工事期間中の事故等の発
生する確率が減少するため、作業の安全上からも好まし
い。さらに、従来の防波構造物と比較して現地でのコン
クリートの使用量が少ないために、コンクリートが海に
流出したり、水質汚濁を生じたりする可能性を最小限に
することができる。
Since a series of wave-breaking shapes are formed by arranging a plurality of blocks in the direction along the shore, it is not necessary to assemble work scaffolds for concrete pouring, reinforcing bars, and formwork on site, and As compared with the conventional construction method, it is not necessary to perform concrete pouring in several times in the vertical direction, which makes the construction easier. Therefore, the on-site construction period can be significantly shortened and the construction cost can be reduced. Further, since the on-site construction period is shortened, the probability of an accident or the like occurring during the construction period is reduced, which is preferable from the viewpoint of work safety. Further, since the amount of concrete used in the field is smaller than that of the conventional wave-breaking structure, it is possible to minimize the possibility of the concrete leaking into the sea or causing water pollution.

【0028】請求項8に記載の発明は、請求項7記載の
防波構造物の施工方法において、上記杭と上記鞘管との
間の隙間に固形化剤を充填することにより、上記防波構
造物を地盤に固定する工程を含むことを特徴とする防波
構造物の施工方法である。
The invention according to claim 8 is the method for constructing a breakwater structure according to claim 7, wherein the gap between the pile and the sheath pipe is filled with a solidifying agent, whereby A method for constructing a breakwater structure, characterized by including the step of fixing the structure to the ground.

【0029】この発明によると、杭と鞘管との間の隙間
に固形化剤が充填することにより、上記防波構造物を地
盤に固定するので、地盤に対するブロックの固定をより
確実なものにすることができ、沖側壁面に衝突する水塊
によってブロックが浮きあがったり、防波構造物が転倒
したりすることがない。
According to the present invention, the wave-proof structure is fixed to the ground by filling the gap between the pile and the sheath pipe with the solidifying agent, so that the block can be more securely fixed to the ground. It is possible to prevent the block from rising and the wave-preventing structure from falling due to the water mass colliding with the offshore wall surface.

【0030】請求項9に記載の発明は、請求項7または
8記載の防波構造物の施工方法において、互いに隣り合
うブロック同士をその沖側壁面よりも後方の位置で締結
して一体化することにより、上記防波形状を形成する工
程を含むことを特徴とする防波構造物の施工方法であ
る。
According to a ninth aspect of the present invention, in the method for constructing a breakwater structure according to the seventh or eighth aspect, blocks adjacent to each other are fastened and integrated at a position rearward of the offshore wall surface. Accordingly, the method for constructing a breakwater structure is characterized by including the step of forming the breakwater shape.

【0031】この発明によると、ブロック同士をその沖
側壁面よりも後方の位置で締結して一体化することによ
り、上記防波形状を形成するので、沖側壁面に衝突する
水塊によってブロックが浮きあがったり、防波構造物が
転倒したりすることを一層防止することができる。
According to the present invention, the block is formed by fastening the blocks to each other at a position rearward of the offshore wall surface and integrating them, so that the block is formed by the water mass colliding with the offshore wall surface. It is possible to further prevent the floating structure and the breakwater structure from falling.

【0032】[0032]

【発明の実施の形態】以下、図面をもとにして本発明の
実施の形態を説明するが、説明を簡単にするため、ま
ず、上下方向のブロック数が1の場合、すなわち、上下
方向には防波構造物を分割せず、一つのブロックを置
き、これを岸に沿う方向に複数個並べた場合について説
明する。上下方向および岸に沿う方向のブロック数は、
設計条件、設置位置の条件等によって決定するが、波浪
条件が厳しくない条件においては、このように上下方向
のブロック数を1とすることにより、工程の簡素化を図
ることができる。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings. To simplify the description, first, when the number of blocks in the vertical direction is 1, that is, in the vertical direction. Describes a case in which one block is placed without dividing the breakwater structure and a plurality of blocks are arranged in the direction along the shore. The number of blocks in the vertical direction and the direction along the shore is
Although it is determined according to design conditions, conditions of installation positions, etc., under conditions where wave conditions are not severe, by setting the number of blocks in the vertical direction to 1 in this way, the process can be simplified.

【0033】図5は、本発明の実施の形態に係る防波構
造物の構造(上下方向のブロック数が1の場合)を示す
斜視図である。
FIG. 5 is a perspective view showing the structure (when the number of blocks in the vertical direction is 1) of the wave preventing structure according to the embodiment of the present invention.

【0034】同図を参照して、本発明の実施の形態に係
る防波構造物用ブロック8は、沖側から到来する波をは
ね返すように沖側にせり出す防波形状を形成する沖側部
分(コンクリート構造3)と、沖側部分よりも陸側の部
分に骨組構造7とを備えている。
Referring to the figure, the wave-preventing structure block 8 according to the embodiment of the present invention is an offshore-side portion forming a wave-preventing shape protruding toward the offshore so as to bounce waves coming from the offshore side. (Concrete structure 3) and a skeleton structure 7 are provided on the land side rather than the offshore side.

【0035】上記沖側部分(コンクリート構造3)は沖
側壁面と略同等の形状をもつ金属製板材すなわち鋼板1
と、前記金属製板材の沖側表面に配された複数の金属製
棒材すなわちスタッド2と、金網25とを備え、前記鋼
板1の表面にはコンクリートが打設されている。
The offshore side portion (concrete structure 3) is a metal plate material, that is, a steel plate 1 having a shape substantially similar to that of the offshore wall surface.
And a plurality of metal rods or studs 2 arranged on the offshore surface of the metal plate, and a wire mesh 25, and concrete is cast on the surface of the steel plate 1.

【0036】上記鋼板1は、沖側壁面と略同等の形状を
もつ金属製板材であり、その表面に植設される多数のス
タッド2と、同じく沖側壁面と略同等の形状に曲成され
スタッド2に溶接で取り付けられた金網25と一体とな
った状態で、鋼板1の表面に打設されるコンクリートを
支持しており、当該コンクリートの剥離や脱落を防止し
ている。
The steel plate 1 is a metal plate material having a shape substantially similar to that of the offshore wall surface, and a large number of studs 2 planted on the surface thereof and also bent into a shape substantially similar to that of the offshore wall surface. Concrete that is cast on the surface of the steel plate 1 is supported in a state where it is integrated with the wire net 25 that is attached to the stud 2 by welding, and the concrete is prevented from peeling or falling off.

【0037】上記スタッド2は、金属製の棒材であり、
上記鋼板の表面に垂直に溶接などで多数植設されるとと
もに金網25を部分溶接で支持している。
The stud 2 is a metal rod,
A large number of them are vertically implanted on the surface of the steel sheet by welding or the like, and the wire mesh 25 is supported by partial welding.

【0038】また上記金網25は線状の鋼材を縦横に編
んで形成したものであり、鋼板1の沖側に、鋼板1とは
一定の間隔を保ってスタッド2に部分的に溶接され、鋼
板1及びスタッド2と一体となって、この上に打設され
るコンクリートを支持し、コンクリートの剥離や脱落を
防止している。
The wire mesh 25 is formed by knitting a linear steel material in the lengthwise and crosswise directions, and is partially welded to the stud 2 on the offshore side of the steel plate 1 with a certain distance from the steel plate 1 to form a steel plate. 1 and the stud 2 are integrated with each other to support concrete cast thereon and prevent concrete from peeling off or falling off.

【0039】次に、上記骨組構造7は、ブロックの上記
沖側部分よりも陸側の部分に複数本の金属製骨材4と鞘
管5とを組み合わせてなる構造物である。
Next, the skeleton structure 7 is a structure in which a plurality of metal aggregates 4 and the sheath pipe 5 are combined in a portion of the block on the land side rather than the offshore portion.

【0040】ここで、上記金属製骨材4は、鉄骨などの
型鋼部材であり、後述する2本の鞘管5同士を左右方向
につなぎ、また、各鞘管5と前述の鋼板1を前後方向に
つなぐように、溶接等で組み合わされて前記骨組構造7
を形成している。
Here, the metal aggregate 4 is a shaped steel member such as a steel frame, which connects two sheath pipes 5 to be described later to each other in the left-right direction, and each sheath pipe 5 and the above-mentioned steel plate 1 are front and back. The frame structure 7 is assembled by welding or the like so as to connect in the direction.
Is formed.

【0041】また、上記鞘管5は、ブロック8の後部に
設けられ、地盤上に立設された杭9(図6参照)が鉛直
方向に挿通可能な金属製の管状鋼材であり、前述の金属
製骨材4と組み合わされて前記骨組構造7を一体に形成
するとともに、杭9に挿通されることにより、ブロック
全体を地盤上に固定する。
Further, the sheath pipe 5 is a tubular metal material made of metal, which is provided at the rear portion of the block 8 and into which the pile 9 (see FIG. 6) erected on the ground can be vertically inserted. The frame structure 7 is integrally formed by being combined with the metal aggregate 4, and the entire block is fixed on the ground by being inserted into the pile 9.

【0042】そして、複数の防波構造物用ブロック8が
岸に沿う方向にならべられた後は、上部にプレキャスト
上部コンクリート16が打設されるとともに、下部に底
板18が打設され、次に円弧状のコンクリート構造3の
境界部分に止水を目的とした止水材80が充填されて、
当該の防波構造物全体が形成される。
After the plurality of blocks 8 for wave preventing structures are arranged in the direction along the shore, the precast upper concrete 16 is placed on the upper part and the bottom plate 18 is placed on the lower part. The boundary portion of the arc-shaped concrete structure 3 is filled with a waterproof material 80 for the purpose of waterproofing,
The entire breakwater structure is formed.

【0043】図6は、この防波構造物の現地における施
工方法の概略を示す施工フローである。現地では、まず
複数の杭9をそれぞれブロック8の鞘管5に対応する位
置に略鉛直に立設するようにして基礎を完成する(図6
)。そしてブロック8を図示しないトラッククレーン
で吊り上げ、ブロック8の後方にある鞘管5に杭9を挿
通するようにして、ブロック8を基礎上に据え付ける
(図6、)。最後に鞘管5の内周と杭9の外周との
隙間に固形化剤81(例えばモルタルや可塑性樹脂等)
を注入して基礎へのブロック8の固定を確実なものにす
る。
FIG. 6 is a construction flow chart showing an outline of the construction method of the wave-proof structure on site. In the field, first, a plurality of piles 9 are vertically erected at positions corresponding to the sheath pipes 5 of the blocks 8 to complete the foundation (Fig. 6).
). Then, the block 8 is lifted by a truck crane (not shown), the pile 9 is inserted into the sheath pipe 5 behind the block 8, and the block 8 is installed on the foundation (FIG. 6). Finally, a solidifying agent 81 (for example, mortar or plastic resin) is provided in the gap between the inner circumference of the sheath tube 5 and the outer circumference of the pile 9.
To ensure the fixation of the block 8 to the foundation.

【0044】次に、図7〜9を参照しながら、本発明に
かかる防波構造物の工場における製作の詳細を述べる。
Next, with reference to FIGS. 7 to 9, the details of the production of the breakwater structure according to the present invention in the factory will be described.

【0045】図7は、鋼板1と骨組構造7の製作フロー
であり、図8は、コンクリート構造3の製作フローであ
る。そして、図9は、端部に位置するブロック8の側壁
部の製作フローである。
FIG. 7 is a manufacturing flow of the steel plate 1 and the frame structure 7, and FIG. 8 is a manufacturing flow of the concrete structure 3. Then, FIG. 9 is a manufacturing flow of the side wall portion of the block 8 located at the end portion.

【0046】図7を参照して、まず、曲げ加工した鋼板
1には縦リブ22と、横リブ23と、型鋼などの金属製
骨材4とを溶接した上、鋼板1の表面にスタッド2を植
設する(〜)。次に、骨組構造7は、金属製骨材4
と鞘管5をを溶接して組み立てる(〜)。そして、
最後に鋼板1に接合された金属製骨材4に上記の骨組構
造を溶接して一体化する()。
Referring to FIG. 7, first, a vertical rib 22, a horizontal rib 23, and a metal aggregate 4 such as a shaped steel are welded to the bent steel plate 1, and then the stud 2 is formed on the surface of the steel plate 1. Plant (~). Next, the frame structure 7 is made up of the metal aggregate 4
The sheath tube 5 is welded and assembled (-). And
Finally, the above frame structure is welded and integrated with the metal aggregate 4 joined to the steel plate 1 ().

【0047】次に図8を参照して、コンクリート構造3
の製作は以下の通りである。すなわち、まず、鋼板1と
骨組構造7を横置きし()、鋼板1に金網25と円弧
面型枠26を設置する()。そしてこの鋼板1と円弧
面型枠26の間にコンクリートを打設し()、養生す
ることによりコンクリート構造3を製作する()。そ
して最後に金属部を塗装してブロック8の工場での製作
を完了し、現地に輸送する(〜)。
Next, referring to FIG. 8, the concrete structure 3
The production of is as follows. That is, first, the steel plate 1 and the frame structure 7 are placed horizontally (), and the wire net 25 and the arc surface form 26 are installed on the steel plate 1 (). Then, concrete is placed between the steel plate 1 and the arcuate surface form 26 () and cured to produce the concrete structure 3 (). Finally, the metal part is painted, the production of the block 8 in the factory is completed, and the block 8 is transported to the site (~).

【0048】ところで、図9を参照して、端部に位置す
るブロック8の側壁部の製作は以下の通りである。すな
わち、前記と同様にして製作したブロック8の側壁部
に、さらに側壁型枠27を設置した後()、側壁型枠
27の内部にコンクリートを打設し()、さらに養生
して端部用ブロック8の側壁部の製作を完了する
()。
By the way, referring to FIG. 9, the side wall of the block 8 located at the end is manufactured as follows. That is, after the side wall form 27 is further installed on the side wall of the block 8 manufactured in the same manner as above (), concrete is placed inside the side wall form 27 (), and further cured for the end part. The fabrication of the side wall of the block 8 is completed ().

【0049】さらに、図10〜12を参照しながら、本
発明にかかる防波構造物の現地における施工の詳細を述
べる。
Further, with reference to FIGS. 10 to 12, details of the construction of the breakwater structure according to the present invention on site will be described.

【0050】図10は、3個のブロック8からなる1つ
のユニットの据え付けを示す施工フローであり、図11
は、ユニットの内部、上部の施工を示す施工フローであ
る。また、図12は、ユニットの増設を示す施工フロー
である。
FIG. 10 is a construction flow showing the installation of one unit consisting of three blocks 8.
Is a construction flow showing construction inside and above the unit. FIG. 12 is a construction flow showing the addition of units.

【0051】図10を参照して、ユニット39の現地に
おける施工は、まず複数の杭9をそれぞれブロック8の
鞘管5に対応する位置に略鉛直に立設するように基礎4
0を完成させた後、その上に底版コンクリートを打設す
るための準備として、基礎40上にスペーサー31と下
配筋32を設置しておく()。次に立設した杭9にブ
ロック8の鞘管5を挿通させ、ブロック8をスペーサ3
1上に載せるようにして、ユニット39に属する複数の
ブロック8を岸に沿う方向に並べる。この時、ブロック
8同士はかすがい33とガイド34などの締結具を使っ
て締結していく()。そしてスペーサー31と下配筋
32とにより形成された基礎40とブロック8との隙間
に底版コンクリート18を打設(−a、−b)して
一つのユニット39の据え付けを完了する。
Referring to FIG. 10, in the construction of the unit 39 on site, first, a plurality of piles 9 are erected substantially vertically at positions corresponding to the sheath pipes 5 of the blocks 8, respectively.
After completing 0, a spacer 31 and a lower reinforcing bar 32 are set on a foundation 40 as a preparation for placing bottom slab concrete thereon (). Next, the sheath pipe 5 of the block 8 is inserted into the pile 9 which is erected upright, and the block 8 is attached to the spacer 3
The plurality of blocks 8 belonging to the unit 39 are arranged in the direction along the shore so as to be placed on the shore 1. At this time, the blocks 8 are fastened to each other by using the clasp 33 and a fastener such as a guide 34 (). Then, the bottom slab concrete 18 is placed (-a, -b) in the gap between the block 40 and the foundation 40 formed by the spacer 31 and the lower reinforcing bar 32 to complete the installation of one unit 39.

【0052】次に、図11を参照して、ユニット39の
内部、上部の施工は、以下の通りである。すなわち、ブ
ロック8の内部に上方から中詰砂、あるいは砕石36を
投入してブロック8の内部の空隙を埋めた後(−
a)、ブロック8の上部を覆うように蓋コンクリート3
7を施工し−b)、プレキャスト上部コンクリート1
6をブロック8の上部に設置して(−c)防波構造物
を形成する。なお、既設のユニット39の側壁にはゴム
60を貼り付けるとともに、前述の要領と同様に次のユ
ニット39用のスペーサー31と下配筋32を設置し
て、ユニット39を増設する準備をする()。
Next, referring to FIG. 11, the construction of the inside and the upper part of the unit 39 is as follows. That is, after filling the inside of the block 8 with filling sand or crushed stone 36 from above to fill the voids inside the block 8 (-
a), cover concrete 3 to cover the top of block 8
7-b), precast top concrete 1
6 is installed on the upper part of the block 8 (-c), and a breakwater structure is formed. In addition, the rubber 60 is attached to the side wall of the existing unit 39, and the spacer 31 and the lower bar 32 for the next unit 39 are installed in the same manner as described above to prepare to add the unit 39 ( ).

【0053】さらに、図12を参照して、ユニット39
の増設の要領は、以下の通りである。すなわち、一方の
ユニット39と他方のユニット39の隣接する箇所に設
けられた凹凸の形状をしたスライドガイド61を嵌合う
ようにするとともに、立設した杭9にブロック8の鞘管
5を挿通させるようにして、隣のユニット39の端部ブ
ロック62を所定の位置に設置して一体化する()。
そして引き続き、前述の図10及び図11の要領で次の
ユニット39の施工を進めていき()、全てのユニッ
ト39の施工が完了した後、最後に天端部63を工事し
て防波構造物全体の施工を完了する()。
Further, referring to FIG. 12, the unit 39
The outline of the expansion is as follows. That is, the slide guide 61 having an uneven shape provided in the adjacent portion of the one unit 39 and the other unit 39 is fitted, and the sheath pipe 5 of the block 8 is inserted into the standing pile 9. In this way, the end block 62 of the adjacent unit 39 is installed at a predetermined position and integrated ().
Then, the construction of the next unit 39 is proceeded in the same manner as the above-mentioned FIGS. 10 and 11 (), and after the construction of all the units 39 is completed, finally the top end portion 63 is constructed to construct the wave-proof structure. Complete the construction of the whole thing ().

【0054】以上、製作、施工方法の詳細を述べるの
に、説明を簡単にするため、上下方向のブロック数1の
場合について述べたが、ブロック数が2以上の場合も基
本的には同様である。
In the above, the details of the manufacturing and construction methods have been described, for the sake of simplicity, the case where the number of blocks in the vertical direction is 1 has been described, but basically the same applies when the number of blocks is 2 or more. is there.

【0055】図13は上下方向のブロック数が2の場合
の施工フローである。上下方向のブロック数が2の場合
は、複数の杭9をそれぞれブロック8の鞘管5に対応す
る位置に略鉛直に立設するように基礎40を完成させた
後、図10、図11と同様に下段ブロック13を据え付
け、かすがい33やガイド34などの締結具により、下
段ブロック13同士を締結するとともに、下段ブロック
13の上面にゴムなどの止水材80を貼り付ける
()。次に、下段ブロック13と同様に、上段ブロッ
ク15を据え付け、かすがい33やガイド34などの締
結具により上段ブロック15同士を締結する。また、下
段ブロック13と上段ブロック15をボルト35とナッ
ト68などの締結具により締結する()。最後に、ボ
ルト35とナット68で締結した箇所に防食塗装を行う
()。
FIG. 13 is a construction flow when the number of blocks in the vertical direction is two. When the number of blocks in the up-and-down direction is 2, after completing the foundation 40 so that the plurality of piles 9 are erected substantially vertically at the positions corresponding to the sheath tubes 5 of the blocks 8, respectively, as shown in FIGS. Similarly, the lower block 13 is installed, the lower blocks 13 are fastened to each other by fasteners such as the scintillation 33 and the guide 34, and the water blocking material 80 such as rubber is attached to the upper surface of the lower block 13 (). Next, similarly to the lower block 13, the upper block 15 is installed, and the upper blocks 15 are fastened to each other by fasteners such as the glare 33 and the guide 34. Further, the lower block 13 and the upper block 15 are fastened with fasteners such as bolts 35 and nuts 68 (). Finally, anticorrosion coating is applied to the portion fastened with the bolt 35 and the nut 68 ().

【0056】この後、底版コンクリートの打設、中詰砂
あるいは砕石の投入、蓋コンクリートの施工、プレキャ
スト上部コンクリートの設置、天端部の工事など、完成
に至る工程は、図11、図12と同様である。図14
は、上下方向のブロック数3の場合についての防波構造
物本体の縦断面図であり、上下方向に下段ブロック1
3、中段ブロック14、上段ブロック15の3段をこの
順に載置するとともに、岸に沿う方向にならべ、背後に
裏込石55を投入している。また、プレキャスト上部コ
ンクリート16を打設し、必要に応じて根回・被覆ブロ
ック17を据え付けている。
After this, the steps such as placing the bottom slab concrete, introducing the filling sand or crushed stone, constructing the lid concrete, installing the precast upper concrete, and constructing the top end are completed as shown in FIG. 11 and FIG. It is the same. 14
FIG. 3 is a vertical cross-sectional view of the main body of the breakwater structure in the case where the number of blocks in the vertical direction is 3, and the lower block 1 in the vertical direction.
3, the middle block 14 and the upper block 15 are placed in this order, and the back stones 55 are put in the back along the direction along the shore. Further, the precast upper concrete 16 is placed, and the root girder / cover block 17 is installed if necessary.

【0057】この実施の形態を新設する場合の製作、施
工方法を図15に示す。現地では、まず基礎を工事した
後、杭9を設置する(図15a〜d)。そして下段ブロ
ック13をトラッククレーン57で吊り上げ、ブロック
の後方にある鞘管5に杭9を挿通して据え付ける(図1
5e)。次に中段ブロック14、上段ブロック15を同
様に吊り上げ、ブロックの後方にある鞘管5に杭9を挿
通して据え付け(図15f〜g)、接合し、背後に裏込
石55を投入する(図15h)。最後にプレキャスト上
部コンクリート16を据え付け、打設し(図15i)、
必要に応じて根回・被覆ブロック17を据え付ける(図
15j)。なお、設計条件によっては、下段ブロック1
3にコンクリートを打設する場合もある。
FIG. 15 shows a manufacturing and construction method when this embodiment is newly installed. In the field, first, after constructing the foundation, the pile 9 is installed (Figs. 15a to 15d). Then, the lower block 13 is hoisted by the truck crane 57, and the pile 9 is inserted into the sheath pipe 5 at the rear of the block to install it (Fig. 1).
5e). Next, the middle block 14 and the upper block 15 are similarly lifted up, the pile 9 is inserted into the sheath pipe 5 located behind the block and installed (Figs. 15f to 15g), joined, and the backfill stone 55 is put in the back ( Figure 15h). Finally, the precast upper concrete 16 was installed and placed (Fig. 15i),
Install the root girder / cover block 17 as needed (Fig. 15j). Depending on the design conditions, the lower block 1
In some cases, concrete may be placed in No. 3.

【0058】このように、本実施形態ではブロックの沖
側のみをコンクリート構造3とし、陸側を複数本の金属
製骨材4を組み合わせてなる骨組構造7としたので大規
模な防波構造物の場合、全体をコンクリートで構成する
よりも軽量化することができ、運搬が容易になるなど、
施工上の利点がある。
As described above, in this embodiment, only the offshore side of the block is the concrete structure 3 and the land side is the frame structure 7 in which a plurality of metal aggregates 4 are combined. In the case of, it can be made lighter than the whole structure made of concrete, and it becomes easier to transport.
There are construction advantages.

【0059】また、金属製骨材4を組み合わせた骨組構
造7でコンクリート構造3を支持するとともに、その骨
組構造7同士をかすがいやガイド34あるいはボルト3
5やナット68などの締結具で締結するので、各ブロッ
ク8の締結を確実なものにすることができ、沖側壁面に
衝突する水塊によってブロック8が浮きあがったり、防
波構造物が転倒したりするのをより確実に防止できる。
Further, the concrete structure 3 is supported by the frame structure 7 in which the metal aggregates 4 are combined, and the frame structures 7 are scratched by the guides 34 or the bolts 3.
Since it is fastened with fasteners such as 5 and nuts 68, the fastening of each block 8 can be ensured, and the block 8 floats up due to the water mass colliding with the offshore side wall surface, or the breakwater structure falls over. It can be prevented more reliably.

【0060】ここで、従来の消波ブロック被覆護岸(図
2)と、本発明の防波構造物(図14)の工程を比較
し、本発明の優秀性を示す。図2と図14には防波構造
物の外観に加えて、比較の前提となる寸法が併せて示さ
れている。設計条件等を下記に示す。 ・設置水深1.3m ・設計潮位1.8m ・法線方向延長100m ・消波ブロック重量10ton ・フレア各ブロック重量最大10ton ・フレア各ブロック長さ最長3.5m
Here, the excellence of the present invention is shown by comparing the steps of the conventional wave-blocking block-covered revetment (FIG. 2) and the wave-proof structure of the present invention (FIG. 14). In addition to the appearance of the breakwater structure, FIGS. 2 and 14 also show the dimensions on which the comparison is based. The design conditions are shown below.・ Installed water depth 1.3m ・ Design tide level 1.8m ・ Normal direction extension 100m ・ Dissipation block weight 10ton ・ Flare each block weight max 10ton ・ Flare block length max 3.5m

【0061】図16は各施工方法の工程図である。表
1,表2に、それぞれ消波ブロック被覆護岸、本発明に
かかる防波構造物(分割式フレア護岸)の工程表を示
す。表中、実線が現地での工事、破線は現地以外での工
事を示している。消波ブロック被覆護岸の場合、護岸本
体の現地製作、施工に約5ヶ月も要し、最初の基礎工1
ヶ月、最後の消波ブロック掘え付け1ヶ月をあわせて、
現地工事期間は合計約7ヶ月と試算された。これに対し
て、本施工方法によるフレア型防波構造物の場合、護岸
施工に要した期間は約1ヶ月で、基礎工と合わせた工事
期間合計は約2ヶ月と試算され、大幅に現地工事期間を
短縮できることがわかる。
FIG. 16 is a process diagram of each construction method. Tables 1 and 2 show process charts of the wave-blocking block-covered revetment and the breakwater structure (divided flare revetment) according to the present invention, respectively. In the table, the solid line shows the construction at the site and the broken line shows the construction outside the site. In the case of wave-blocking block-covered revetment, it takes about 5 months for the local production and construction of the revetment body, and the first foundation work 1
Months, including the last month of digging in the wave-dissipating block,
The total on-site construction period was estimated to be about 7 months. On the other hand, in the case of the flare type breakwater structure by this construction method, the time required for revetment construction is about 1 month, and the total construction period including the foundation work is estimated to be about 2 months, which is a significant on-site construction. It turns out that the period can be shortened.

【0062】また、消波ブロック(重量10ton)を
据え付ける際には、かなり沖側までクレーンの腕を伸ば
す必要があるため、120ton吊りクレーンが必要で
あったが、本発明にかかるブロックの場合は、腕の長さ
が短くてすむため、45ton吊りクレーンで十分であ
った。
Further, when installing the wave-dissipating block (weight: 10 ton), it was necessary to extend the arm of the crane to a considerably offshore side, so a 120-ton suspension crane was required, but in the case of the block according to the present invention, Since the length of the arm is short, the 45ton suspension crane was sufficient.

【0063】以上は本発明にかかる防波構造物を新設す
る場合であったが、次に本発明にかかる防波構造物を既
設の護岸前面に設置する場合について示す。
The above is the case where the breakwater structure according to the present invention is newly installed. Next, the case where the breakwater structure according to the present invention is installed on the front of an existing seawall will be described.

【0064】図17は既設護岸51の前面に本発明にか
かる防波構造物を設置する場合を示している。また、図
18は既設護岸51の前面に本発明にかかる防波構造物
を設置する場合の施工フローを示している。
FIG. 17 shows a case where the breakwater structure according to the present invention is installed on the front surface of the existing seawall 51. Further, FIG. 18 shows a construction flow in the case of installing the breakwater structure according to the present invention on the front surface of the existing seawall 51.

【0065】ここで前述の比較と同様に、既設護岸51
の前面に従来の消波ブロック被覆護岸を設置した場合
(図2)と、本発明にかかる防波構造物を設置した場合
(図17)の工程を比較し、本発明の優秀性を示す。図
2と図17には防波構造物の外観の他、比較の前提とな
る寸法も併せて記載されている。設計条件等を下記に示
す。 ・設置水深1.3m ・設計潮位1.8m ・法線方向延長100m ・消波ブロック重量10ton ・フレア各ブロック重量最大10ton ・フレア各ブロック長さ最長3.5m ・道路幅9.0m
Here, as in the above comparison, the existing revetment 51
The excellence of the present invention is shown by comparing the steps in the case of installing a conventional wave-dissipating block covered revetment (Fig. 2) and the case of installing the breakwater structure according to the present invention (Fig. 17) in front of the. 2 and FIG. 17, in addition to the appearance of the breakwater structure, the dimensions on which the comparison is based are also shown. The design conditions are shown below.・ Installation water depth 1.3m ・ Design tide level 1.8m ・ Normal direction extension 100m ・ Dissipation block weight 10ton ・ Flare block weight 10ton max ・ Flare block length max 3.5m ・ Road width 9.0m

【0066】図16は各施工方法の工程図である。表
3,4に、それぞれ消波ブロック被覆護岸と、本発明に
かかる防波構造物(分割式フレア護岸)の工程表を示
す。表中、実線が現地での工事、破線は現地以外での工
事を示している。既設護岸前面に設置する場合、両者と
も現地工事期間は約1.5ヶ月であった。
FIG. 16 is a process drawing of each construction method. Tables 3 and 4 show process charts of the wave-blocking block-covered revetment and the breakwater structure (split-type flare revetment) according to the present invention. In the table, the solid line shows the construction at the site and the broken line shows the construction outside the site. When installed on the front of the existing seawall, the construction period for both was about 1.5 months.

【0067】このように既設護岸前面に設置する場合は
工程上は大きな差はないが、一方、使用するトラックク
レーンの大きさは大きく異なる。すなわち、消波ブロッ
ク(重量10ton)を据え付ける際には、かなり沖側
までクレーンの腕を伸ばす必要があるため、120t吊
りクレーンが必要であり、消波ブロックを据付ける1ヶ
月の間、9.0m幅の道路を全面通行止めにしなければ
ならないが、本発明にかかる防波構造物の場合は、腕の
長さが短くてすむため、45ton吊りクレーンで十分
であり、また、アウトリガーの張り出し幅も5mでよ
く、現地工事期間中、片側通行止めだけで対応すること
ができる。
When installing on the front of the existing seawall in this way, there is no great difference in the process, but the size of the truck crane to be used differs greatly. That is, when installing the wave-dissipating block (weight: 10 ton), it is necessary to extend the arm of the crane to a considerably offshore side, so a 120-ton hanging crane is required. A 0 m wide road must be completely closed, but in the case of the breakwater structure according to the present invention, the length of the arm can be short, so a 45 ton suspension crane is sufficient, and the overrigger extension width is also sufficient. It only needs to be 5 meters long, and it can be accommodated by only one side of the road being closed during the on-site construction.

【0068】このように、施工の観点からも、本発明は
現地の工事期間が短く、また、工事期間中の事故等の発
生する確率が減少するため、作業の安全上からも好まし
い。また、従来の防波構造物と比較して現地でのコンク
リートの使用量が少ないために、コンクリートが海に流
出し、水質汚濁を生じる可能性を最小限にすることがで
きる。
As described above, from the viewpoint of construction, the present invention is preferable from the viewpoint of work safety because the construction period on site is short and the probability of an accident during the construction period is reduced. Further, since the amount of concrete used in the field is smaller than that of the conventional wave-breaking structure, it is possible to minimize the possibility that the concrete will flow out into the sea and cause water pollution.

【0069】さらに前述のように、消波ブロック被覆護
岸の場合と比較すると、本発明の場合、沖側まで消波ブ
ロックを据え付けるような作業がないので、比較的小型
のトラッククレーンで対応でき、このため、工事に係る
コストの低減を図ることができる。また、道路護岸など
の既設護岸に適用する場合は、工事にともなう通行止め
の範囲(道幅方向)も小さくすることができて道路を全
面通行止めにせずともよいなど、交通安全上も好まし
い。
Further, as described above, in the case of the present invention, as compared with the case of the wave-dissipating block covered revetment, since there is no work to install the wave-dissipating block to the offshore side, a relatively small truck crane can cope with Therefore, the cost for construction can be reduced. Further, when applied to an existing revetment such as a road revetment, it is also preferable in terms of traffic safety that the area of road closure due to construction (road width direction) can be reduced and the road need not be completely closed.

【0070】上述した実施の形態は本発明の好ましい具
体例を例示したものに過ぎず、本発明は上述した実施の
形態に限定されない。
The above-described embodiment is merely an example of a preferred specific example of the present invention, and the present invention is not limited to the above-described embodiment.

【0071】例えば、鞘管の数は必ずしも1個のブロッ
クに対して2個である必要はなく、1個であっても3個
以上であってもよい。図19は1個のブロックに対して
1個の鞘管5を設けた構造の概略を示しており、図20
は1個のブロックに対して3個の鞘管5を設けた構造の
概略を示している。
For example, the number of sheath tubes does not necessarily have to be two per block, and may be one or three or more. FIG. 19 shows an outline of the structure in which one sheath tube 5 is provided for one block.
Shows an outline of a structure in which three sheath tubes 5 are provided for one block.

【0072】その他、本発明の特許請求の範囲内で種々
の設計変更が可能であることはいうまでもない。
Needless to say, various design changes can be made within the scope of the claims of the present invention.

【0073】[0073]

【発明の効果】本発明の構造上の効果は、次の通りであ
る。すなわち、本発明はいずれも沖側壁面の上部に沖側
から到来する波をはね返すように沖側にせり出す部分を
有する防波形状を持つ防波構造物としたので、直立型ケ
ーソン防波構造物や消波ブロック被覆護岸などの従来の
防波構造物と比較して高い非越波特性を有している。
The structural effects of the present invention are as follows. That is, all of the present invention is a wave-preventing structure having a wave-preventing shape having a portion protruding toward the offshore side so as to repel the waves coming from the offshore side at the upper part of the offshore side wall surface. It has higher non-overtopping characteristics compared to conventional wave-breaking structures such as wave-dissipating block-covered seawalls.

【0074】このため、特に越波や波の打ち上げが問題
となる沿岸道路等においては天端高さを抑えながら越波
や波の打ち上げを防止することができ、また、消波ブロ
ックで防波構造物を被覆する必要がないので、設置する
場所の景観を損なうことがない。
For this reason, especially on coastal roads where overtopping or wave launching is a problem, it is possible to prevent overtopping or wave launching while suppressing the crown height, and a wave-blocking block is used to prevent wave-breaking structures. Since it does not need to be covered, it does not spoil the landscape of the installation location.

【0075】また、防波形状を形成する沖側部分と、そ
の後部に設けられ、杭が鉛直方向に挿通可能な鞘管とを
一体に有するので、地盤上に立設した杭を後部に設けら
れた鞘管に挿通することにより地盤に対するブロックの
固定を確実なものにすることができ、沖側壁面に衝突す
る水塊によってブロックが浮きあがったり、防波構造物
が転倒したりすることがない。
Further, since the offshore side portion forming the wave preventing shape and the sheath pipe which is provided at the rear portion thereof and through which the pile can be inserted in the vertical direction are integrally provided, the pile standing on the ground is provided at the rear portion. The block can be securely fixed to the ground by inserting it into the sheath pipe, and the block of water may float up or the breakwater structure may fall due to the water mass colliding with the offshore side wall surface. Absent.

【0076】次に、本発明の施工上の効果は次の通りで
ある。すなわち、本発明は複数のブロックを岸に沿う方
向に並べて配置することにより前記防波形状を形成する
ので、現地でコンクリート打設用の作業用足場、鉄筋、
型枠を組み立てる必要がなく、また、上下方向に何回か
に分けてコンクリート打設を行う必要もないなど従来の
防波構造物の施工方法と比較して、工事をより容易にす
ることができる。しかも各ブロックの固定は、その鞘管
に杭を挿通するだけの簡単な工程で行うことができ、さ
らに、隙間に固形化剤を注入すれば,当該固定をより確
実なものにできる。
The construction effects of the present invention are as follows. That is, since the present invention forms the wave-proof shape by arranging a plurality of blocks side by side in the direction along the shore, scaffolding for work for concrete placement on site, rebar,
There is no need to assemble the formwork, and it is not necessary to place concrete in several parts in the vertical direction. it can. Moreover, each block can be fixed by a simple process of inserting the pile into the sheath tube, and further, by injecting the solidifying agent into the gap, the fixation can be made more reliable.

【0077】これにより、現地工事期間を大幅に短縮す
ることができ、施工にかかるコストを低減することがで
きる。また、現地の工事期間が短くなることにより、工
事期間中の事故等の発生する確率が減少するため、作業
の安全上からも好ましい。
As a result, the on-site construction period can be greatly shortened and the construction cost can be reduced. Further, since the on-site construction period is shortened, the probability of an accident or the like occurring during the construction period is reduced, which is preferable from the viewpoint of work safety.

【0078】しかも、上記のように、防波構造物を複数
のブロックに分割しながら、前記ブロックを締結具によ
り一体化すれば、沖側壁面に衝突する水塊によってブロ
ックが浮きあがったり、防波構造物が転倒したりするの
をより確実に防ぐことができる。
Moreover, as described above, if the block structure is divided into a plurality of blocks and the blocks are integrated by the fasteners, the blocks may float or be prevented by the water mass that collides with the offshore wall surface. It is possible to more reliably prevent the wave structure from falling.

【0079】さらに、従来の防波構造物と比較して現地
でのコンクリートの使用量が少ないために、コンクリー
トが海に流出したり、水質汚濁を生じたりする可能性を
最小限にすることができる。
Furthermore, since the amount of concrete used in the field is smaller than that of the conventional wave-breaking structure, it is possible to minimize the possibility that the concrete will flow into the sea or cause water pollution. it can.

【図面の簡単な説明】[Brief description of drawings]

【図1】 従来の直立型ケーソン防波構造物の縦断面図
である。
FIG. 1 is a vertical cross-sectional view of a conventional upright caisson breakwater structure.

【図2】 従来の消波ブロック被覆護岸の縦断面図であ
る。
FIG. 2 is a vertical sectional view of a conventional wave-dissipating block-covered revetment.

【図3】 従来の消波ブロック被覆護岸を新設する場合
の施工フローである。
[Fig. 3] Fig. 3 is a construction flow for newly installing a conventional wave-dissipating block covered revetment.

【図4】 フレア型防波構造物の斜視図である。FIG. 4 is a perspective view of a flare type breakwater structure.

【図5】 上下方向のブロック数が1の本発明にかかる
防波構造物の斜視図である。
FIG. 5 is a perspective view of a breakwater structure according to the present invention having one block in the vertical direction.

【図6】 本発明の実施の形態にかかる防波構造物の施
工フローである。
FIG. 6 is a construction flow of the wave-proof structure according to the embodiment of the present invention.

【図7】 鋼板と骨組構造の製作フローである。FIG. 7 is a manufacturing flow of a steel plate and a frame structure.

【図8】 コンクリート構造の製作フローである。FIG. 8 is a flow of manufacturing a concrete structure.

【図9】 端部に位置するブロックの側壁部の製作フロ
ーである。
FIG. 9 is a manufacturing flow of a side wall portion of a block located at an end portion.

【図10】 3個のブロックからなる1つのユニットの
据え付けを示す施工フローである。
FIG. 10 is a construction flow showing the installation of one unit composed of three blocks.

【図11】 ユニットの内部、上部の施工を示す施工フ
ローである。
FIG. 11 is a construction flow showing construction inside and above the unit.

【図12】 ユニットの増設を示す施工フローである。FIG. 12 is a construction flow showing the addition of units.

【図13】 上下方向のブロック数が2の場合の施工フ
ローである。
FIG. 13 is a construction flow when the number of blocks in the vertical direction is two.

【図14】 上下方向のブロック数が3の場合の防波構
造物の縦断面図である。
FIG. 14 is a vertical cross-sectional view of the wave-proof structure when the number of blocks in the vertical direction is three.

【図15】 図14の上下方向のブロック数が3の場合
の防波構造物を新設する場合の施工フローである。
FIG. 15 is a construction flow in the case of newly installing a breakwater structure when the number of blocks in the vertical direction in FIG. 14 is three.

【図16】 各施工方法の工程図である。FIG. 16 is a process drawing of each construction method.

【図17】 既設護岸前面にフレア型防波構造物を設置
する場合の縦断面図である。
FIG. 17 is a vertical cross-sectional view in the case of installing a flare type breakwater structure on the front of an existing seawall.

【図18】 既設護岸前面にフレア型防波構造物を設置
する場合の施工フローである。
FIG. 18 is a construction flow in the case of installing a flare type breakwater structure in front of an existing seawall.

【図19】 1個のブロックに対して1個の鞘管5を設
けた構造の概略を示す斜視図である。
FIG. 19 is a perspective view schematically showing a structure in which one sheath tube 5 is provided for one block.

【図20】 1個のブロックに対して3個の鞘管5を設
けた構造の概略を示す斜視図である。
FIG. 20 is a perspective view schematically showing a structure in which three sheath tubes 5 are provided for one block.

【符号の説明】[Explanation of symbols]

1 鋼板(金属製板材) 2 スタッド(金属製棒材) 3 コンクリート構造(沖側部分) 4 金属製骨材 5 鞘管 7 骨組構造 8 ブロック 9 杭 10 沖側壁面 11 上部傾斜面 12 下部傾斜面 13 下段ブロック 14 中段ブロック 15 上段ブロック 16 プレキャスト上部コンクリート 17 根回・被覆ブロック 18 底版 19 前面曲面板 20 モルタル注入口 21 差込部分 22 縦リブ 23 横リブ 25 金網 26 円弧面型枠 27 側壁型枠 30 直立型ケーソン 31 スペーサー 32 下配筋 33 かすがい 34 ガイド 35 ボルト 36 中詰砂、あるいは砕石 37 蓋コンクリート 39 ユニット 40 基礎 41 砂 42 捨石マウント 50 防波構造物本体 51 既設護岸 53 作業用足場 54 型枠 55 裏込石 56 消波ブロック 57 トラッククレーン 60 ゴム 61 スライドガイド 62 端部ブロック 63 天端部 68 ナット 1 Steel plate (metal plate material) 2 studs (metal rod) 3 Concrete structure (offshore side) 4 metal aggregate 5 sheath tube 7 Frame structure 8 blocks 9 piles 10 Offshore wall surface 11 Upper slope 12 Lower slope 13 Lower block 14 Middle block 15 Upper block 16 Precast upper concrete 17 Roots and coated blocks 18 Bottom plate 19 Front curved plate 20 mortar inlet 21 Insertion part 22 Vertical ribs 23 Horizontal ribs 25 wire mesh 26 Arc surface formwork 27 Side wall formwork 30 Upright caisson 31 Spacer 32 Lower bar 33 Scratch 34 Guide 35 volts 36 Medium sand or crushed stone 37 Lid concrete 39 units 40 basics 41 sand 42 rubble mount 50 Wave breaker structure body 51 Existing seawall 53 Working scaffolding 54 formwork 55 back stone 56 Wave-dissipating block 57 truck crane 60 rubber 61 Slide guide 62 end block 63 Crown 68 nuts

フロントページの続き (72)発明者 竹鼻 直人 神戸市中央区脇浜町1丁目3番18号 株式 会社神戸製鋼所神戸本社内 (72)発明者 市川 靖生 神戸市中央区脇浜町1丁目3番18号 株式 会社神戸製鋼所神戸本社内 (72)発明者 濱崎 義弘 神戸市中央区脇浜町1丁目3番18号 株式 会社神戸製鋼所神戸本社内 (72)発明者 橋野 藤彦 神戸市中央区脇浜町1丁目3番18号 株式 会社神戸製鋼所神戸本社内 (72)発明者 塙 洋二 神戸市西区高塚台1丁目5番5号 株式会 社神戸製鋼所神戸総合技術研究所内 Fターム(参考) 2D018 BA16 BA18 Continued front page    (72) Inventor Naoto Takehana             1-3-18 Wakihamacho, Chuo-ku, Kobe-shi Stock             Company Kobe Steel, Ltd.Kobe Head Office (72) Inventor Yasuo Ichikawa             1-3-18 Wakihamacho, Chuo-ku, Kobe-shi Stock             Company Kobe Steel, Ltd.Kobe Head Office (72) Inventor Yoshihiro Hamasaki             1-3-18 Wakihamacho, Chuo-ku, Kobe-shi Stock             Company Kobe Steel, Ltd.Kobe Head Office (72) Inventor Fujihiko Hashino             1-3-18 Wakihamacho, Chuo-ku, Kobe-shi Stock             Company Kobe Steel, Ltd.Kobe Head Office (72) Inventor Yoji Hanawa             1-5-5 Takatsukadai, Nishi-ku, Kobe City Stock Association             Company Kobe Steel Works, Kobe Research Institute F-term (reference) 2D018 BA16 BA18

Claims (9)

【特許請求の範囲】[Claims] 【請求項1】 岸に沿って延び、かつ、沖側壁面の上部
に沖側から到来する波をはね返すように沖側にせり出す
防波形状を持つ防波構造物を形成するためのブロックで
あって、前記防波形状を形成する沖側部分と、その後部
に設けられ、杭が鉛直方向に挿通可能な鞘管とを一体に
有することを特徴とする防波構造物用ブロック。
1. A block for forming a breakwater structure extending along the shore and having a breakwater shape protruding toward the offshore side so as to repel waves coming from the offshore side above the offshore side wall surface. A block for a wave-breaking structure, which integrally includes an offshore-side portion forming the wave-breaking shape and a sheath pipe provided at a rear portion thereof and through which a pile can be vertically inserted.
【請求項2】 前記沖側部分がコンクリート構造であ
り、それよりも陸側の部分が複数本の金属製骨材と上記
鞘管を組み合わせてなる骨組構造であることを特徴とす
る請求項1記載の防波構造物用ブロック。
2. The offshore side portion has a concrete structure, and the land side portion thereof has a frame structure formed by combining a plurality of metal aggregates and the sheath pipe. Block for the described wave break structure.
【請求項3】 骨組構造の沖側前面に配され、沖側壁面
と略同等の形状をもつ金属製板材と、前記金属製板材の
沖側表面に配された複数の金属製棒材とを備え、その金
属製板材の沖側前面にコンクリートが打設されているこ
とを特徴とする請求項2記載の防波構造物用ブロック。
3. A metal plate material, which is arranged on the front surface of the frame structure on the offshore side and has substantially the same shape as the offshore side wall surface, and a plurality of metal rod materials, which are arranged on the offshore surface of the metal plate material. The block for a wave preventing structure according to claim 2, further comprising: a concrete plate placed on the front surface of the metal plate material on the offshore side.
【請求項4】 請求項1〜請求項3のいずれかに記載の
複数のブロックと、地盤に立設される複数の杭とを備
え、これらの杭が前記各ブロックの鞘管に挿通された状
態で各ブロックが地盤上に固定され、かつ、これらのブ
ロックが岸に沿う方向に並べられることにより、一連の
防波形状が形成されていることを特徴とする防波構造
物。
4. A plurality of blocks according to any one of claims 1 to 3 and a plurality of piles erected on the ground are provided, and these piles are inserted into the sheath pipes of the blocks. In a state, each block is fixed on the ground, and by arranging these blocks in the direction along the shore, a series of wave-proof shapes are formed, which is a wave-proof structure.
【請求項5】 上記杭と上記鞘管との間の隙間に固形化
剤が充填されていることを特徴とする請求項4記載の防
波構造物。
5. The breakwater structure according to claim 4, wherein the gap between the pile and the sheath pipe is filled with a solidifying agent.
【請求項6】 前記各ブロック同士をその沖側壁面より
も後方の位置で締結する締結具を備え、その締結により
前記複数のブロックが一体化されて前記防波形状が形成
されていることを特徴とする請求項4または5記載の防
波構造物。
6. A fastener for fastening the blocks to each other at a position rearward of the offshore side wall surface, wherein the fastening forms the plurality of blocks into one piece to form the wave-proof shape. 6. The breakwater structure according to claim 4 or 5.
【請求項7】 岸に沿って延び、かつ、沖側壁面の上部
に沖側から到来する波をはね返すように沖側にせり出す
部分を有する防波形状を持つ防波構造物の施工方法であ
って、請求項1〜請求項3のいずれかに記載のブロック
を形成する工程と、前記杭を立設する工程と、前記鞘管
に前記杭を挿通して前記ブロックを地盤に固定する工程
とを含み、これらの工程により、複数のブロックを岸に
沿う方向に並べることにより、一連の防波形状を形成す
ることを特徴とする防波構造物の施工方法。
7. A method of constructing a breakwater structure having a breakwater shape, which extends along the shore and has a portion protruding to the offshore side so as to repel waves coming from the offshore side at the upper part of the offshore side wall surface. A step of forming the block according to any one of claims 1 to 3, a step of standing the pile, and a step of inserting the pile into the sheath pipe to fix the block to the ground. And a plurality of blocks are arranged in the direction along the shore by these steps to form a series of breakwater shapes.
【請求項8】 上記杭と上記鞘管との間の隙間に固形化
剤を充填する工程を含むことを特徴とする請求項7記載
の防波構造物の施工方法。
8. The method for constructing a breakwater structure according to claim 7, further comprising the step of filling a gap between the pile and the sheath pipe with a solidifying agent.
【請求項9】 互いに隣り合うブロック同士をその沖側
壁面よりも後方の位置で締結して一体化することによ
り、上記防波形状を形成する工程を含むことを特徴とす
る請求項7または8記載の防波構造物の施工方法。
9. The method according to claim 7, further comprising the step of forming the wave-proof shape by fastening adjacent blocks to each other at a position rearward of the offshore side wall surface and integrating them. The method of construction of the described breakwater structure.
JP2001278550A 2001-09-13 2001-09-13 Breakwater structure and method for constructing the same Pending JP2003082636A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001278550A JP2003082636A (en) 2001-09-13 2001-09-13 Breakwater structure and method for constructing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001278550A JP2003082636A (en) 2001-09-13 2001-09-13 Breakwater structure and method for constructing the same

Publications (1)

Publication Number Publication Date
JP2003082636A true JP2003082636A (en) 2003-03-19

Family

ID=19102901

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001278550A Pending JP2003082636A (en) 2001-09-13 2001-09-13 Breakwater structure and method for constructing the same

Country Status (1)

Country Link
JP (1) JP2003082636A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005133348A (en) * 2003-10-28 2005-05-26 Giken Seisakusho Co Ltd Continuous construction method of revetment, and method of widening river or the like
JP2007126885A (en) * 2005-11-04 2007-05-24 Kobe Steel Ltd Method of constructing breakwater structure, and breakwater structure
JP2007205129A (en) * 2006-02-06 2007-08-16 Kobe Steel Ltd Construction method of breakwater structure and breakwater structure
JP2009114689A (en) * 2007-11-05 2009-05-28 Kobe Steel Ltd Construction method for revetment structure
CN102352614A (en) * 2011-08-19 2012-02-15 杨丽萍 Continuous multiple arc type wave-absorbing bank
JP2017186758A (en) * 2016-04-04 2017-10-12 株式会社神戸製鋼所 Improvement method for breakwater structure
CN111236289A (en) * 2020-01-20 2020-06-05 重庆大学 Bridge group pile foundation anti-scouring bearing platform and construction method thereof

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005133348A (en) * 2003-10-28 2005-05-26 Giken Seisakusho Co Ltd Continuous construction method of revetment, and method of widening river or the like
JP2007126885A (en) * 2005-11-04 2007-05-24 Kobe Steel Ltd Method of constructing breakwater structure, and breakwater structure
KR100807958B1 (en) 2005-11-04 2008-02-28 가부시키가이샤 고베 세이코쇼 Method for constructing breakwater structure and breakwater structure
JP2007205129A (en) * 2006-02-06 2007-08-16 Kobe Steel Ltd Construction method of breakwater structure and breakwater structure
JP2009114689A (en) * 2007-11-05 2009-05-28 Kobe Steel Ltd Construction method for revetment structure
CN102352614A (en) * 2011-08-19 2012-02-15 杨丽萍 Continuous multiple arc type wave-absorbing bank
CN102352614B (en) * 2011-08-19 2014-03-05 沈阳农业大学 Continuous multiple arc type wave-absorbing bank
JP2017186758A (en) * 2016-04-04 2017-10-12 株式会社神戸製鋼所 Improvement method for breakwater structure
CN111236289A (en) * 2020-01-20 2020-06-05 重庆大学 Bridge group pile foundation anti-scouring bearing platform and construction method thereof

Similar Documents

Publication Publication Date Title
US20180274191A1 (en) Breakwater construction blocks having improved stability against over-turning and pulling-out when struck by natural forces
RU2432431C2 (en) Long-length device for marine and river hydraulic facilities and method of its manufacturing
KR102097760B1 (en) Coastal assembly for preventing coastal erosion and manufacturing method thereof
JP4569525B2 (en) Steel wall for composite structure
JP2003082636A (en) Breakwater structure and method for constructing the same
US4669913A (en) Method of raising and extending an ocean beach
CN109594530A (en) A kind of thin silt flood control dam new structure
KR102294871B1 (en) Core wall structure method of the independent cassion for offshore runway
JP3905776B2 (en) Revetment structure
KR101439164B1 (en) a gabion block
JP3170990U (en) Breakwater for overturning drag
JP3301739B2 (en) Caisson offshore structure
WO2017175676A1 (en) Method for improving breakwater structure
JP2006161402A (en) Construction method for improving water breaking structure
JP2002227167A (en) Breakwater structure and construction method thereof
CN209989781U (en) Novel structure of silty-fine sand stratum flood control dam
CN204875664U (en) A retaining wall structure for interim pier in bay
CN212956576U (en) Confined space high fill roadbed side slope foam concrete's reinforced structure
JP2001032231A (en) Lattice type installation material, wave absorbing structure using it, hume pipe used for the structure, and construction method of wave absorbing structure
KR102294870B1 (en) Core wall structure of composite cassion for offshore runway
KR100227536B1 (en) Bell type caisson foundation method
RU2240398C2 (en) Building method for gabion slope stabilizing structure
KR100493516B1 (en) Micro pile and assembly foundation reinforcement structure member and its method for pier
JP4231194B2 (en) Revetment structure
JP5065131B2 (en) Wall work in reinforced embankment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040409

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060306

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060328

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060529

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060815

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061006

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20070306