JPH0468140A - Construction of beam - Google Patents

Construction of beam

Info

Publication number
JPH0468140A
JPH0468140A JP17780190A JP17780190A JPH0468140A JP H0468140 A JPH0468140 A JP H0468140A JP 17780190 A JP17780190 A JP 17780190A JP 17780190 A JP17780190 A JP 17780190A JP H0468140 A JPH0468140 A JP H0468140A
Authority
JP
Japan
Prior art keywords
steel
members
lower chord
concrete
steel frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP17780190A
Other languages
Japanese (ja)
Other versions
JP2934668B2 (en
Inventor
Makio Yoshihara
吉原 牧夫
Katsuyuki Mitani
三谷 勝之
Akemasa Miyauchi
宮内 明正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP17780190A priority Critical patent/JP2934668B2/en
Publication of JPH0468140A publication Critical patent/JPH0468140A/en
Application granted granted Critical
Publication of JP2934668B2 publication Critical patent/JP2934668B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PURPOSE:To reduce construction cost and facilitate execution of work by forming a lower chord member into a steel framed reinforced concrete construction and applying bending moment to the structural steel in said member in the direction opposite to the deflection of the beam, wherein an upper chord member, vertical member and diagonal member have a steel frame construction. CONSTITUTION:A beam 10 is formed into a trussed structure comprising lower chord members 11, upper chord members 12, vertical members 13 and diagonal members 14. A structural body comprising columns 18, 18 and a large space 20 as far as a floor surface is constructed and a structural steel 15 is assembled. Next, the steel 15 is provided between the upper ends of the columns 18, 18. Each of the members 13, 14 and 12 is foxed to the steel 15 to form a truss. Reinforcing bars 16 are arranged outside the steel 15 and forms are installed and concrete is placed inside the steel 15, while concrete is placed outside the steel 15, to form the member 11 of steel framed reinforced concrete. In this case, bending moment is applied to the steel 15 in a direction opposite to that of the deflection of the beam 10. Further a load is applied to the beam 10 in advance through a wire 41 to keep the beam 10 approximately horizontally when structures are installed on the beam 10.

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は建築物の躯体を構成する長大スパンかつ大断面
の梁の構造に関する。
DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to the structure of beams with long spans and large cross sections that constitute the framework of buildings.

「従来の技術」 近年、建築物の構造形式として、いわゆるメガストラク
チュア(巨大架構)と称するものが検討されている。第
10図はメガストラクチュアか採用された建築物の一例
を示すもので、4本の鉄骨造の柱】と、それらの上端間
に架設された鉄骨造の1〜ラス梁2どによって巨大な門
型フレームであるメガストラクチュアを構成し、そのメ
ガストラクチュアの上部に、通常の柱3、梁4によって
上層階を構築した形態のものであって、メガス)・ラク
チュアの下部に自由度の高い大空間を得るようになした
ものである。
"Prior Art" In recent years, so-called megastructures have been studied as a structural form of buildings. Figure 10 shows an example of a building in which a megastructure was adopted.A huge gate was constructed using four steel-framed pillars and steel-framed lath beams 1 to 2 installed between their upper ends. It consists of a megastructure, which is a type frame, and the upper floor is constructed using ordinary columns 3 and beams 4 on the top of the megastructure, and the lower part of the megastructure has a large space with a high degree of freedom. It was designed to obtain the following.

この第10図に示す建築物にあっては、メガストラクチ
ュアを構成しているトラス梁2のスパンは数十メートル
にも及ぶ長大なものとされ、その梁成(ま数メートルに
も及ぶものとされている。そして、このような建築物を
施工するに当たってIJ1トラス梁2に予め上方に反る
ようなむくりをっけておき、施工途中段階においては、
図示されているように、トラス梁2の両端部に設置した
ジヤツキによって山形に張ったワイヤ5を緊張すること
により、トラス梁2の中央部に下向きの先行荷重を加え
てトラス梁2がほぼ水平となるように変形させておくと
ともに、上層階の施工が進むにつれてワイヤ5を緩めて
いって先行荷重を解除していき、上層階が完成した時点
でその荷重により1−ラス梁2が自ずと水平となるよう
にしている。
In the building shown in Figure 10, the span of the truss beams 2 making up the megastructure is long, reaching several tens of meters; When constructing such a building, the IJ1 truss beam 2 is curved upward in advance, and during the construction stage,
As shown in the figure, by tensioning the wire 5 strung in a chevron shape using jacks installed at both ends of the truss beam 2, a downward preload is applied to the center of the truss beam 2, and the truss beam 2 becomes almost horizontal. At the same time, as the construction of the upper floor progresses, the wire 5 is loosened to release the preceding load, and when the upper floor is completed, the load causes the 1-lath beam 2 to become horizontal by itself. I am trying to make it so that

「発明が解決しようとする課題」 ところで、上記の建築物においては、メガストラクヂュ
アを構成する長大スパンかつ大断面の梁として鉄骨造の
トラス梁2を採用しているために、そのトラス梁2に要
する鉄骨量が膨大となるはかりでなく溶接あるいはボル
ト締結箇所数が膨大となり、工費がかさむとともに施工
の手間がががるという不具合がある。
"Problem to be Solved by the Invention" By the way, in the above building, since the steel truss beam 2 is used as the long span and large cross-section beam composing the megastructure, the truss beam 2 requires a huge amount of steel, and the number of welded or bolted parts is huge, which increases construction costs and takes time.

本発明は上記の事情に鑑みてなされたもので、メガスト
ラクチュアを構成する梁等の長大スパンかつ大断面が要
求される梁に適用して好適な構造を提供することを目的
とする。
The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a structure suitable for application to beams that require a long span and a large cross section, such as beams constituting a megastructure.

「課題を解決するための手段」 本発明は、建築物の躯体を構成する長大スパンかつ大断
面の梁の構造であって、下弦材と下弦材およびそれらを
連結する垂直材と斜材とからなるトラス構造とされ、か
つ、前記下弦材か鉄骨鉄筋コンクリート造とされている
とともにこの下弦材中の鉄骨自体が梁の撓み方向ど逆方
向の曲げモーメン1−を付与されており、前記上弦材、
垂直材、斜材がいずれも鉄骨造とされ、しかも、前記下
弦材および上弦材は、それぞれそれら自身でこの建築物
の梁を兼ねるとともに、前記垂直材および斜材は、それ
ぞれそれら自身でこの建築物の柱お」=びブレースを兼
ねるものとされていることを特徴とするものである。
"Means for Solving the Problems" The present invention is directed to a structure of a beam with a long span and a large cross section constituting the frame of a building, which consists of a lower chord member, a lower chord member, and a vertical member and diagonal member connecting them. The lower chord has a truss structure, and the lower chord is made of steel reinforced concrete, and the steel frame itself in the lower chord is given a bending moment of 1- in the direction opposite to the direction of deflection of the beam, and the upper chord,
Both the vertical members and the diagonal members are made of steel, and the lower chord members and the upper chord members each serve as the beams of this building, and the vertical members and the diagonal members each serve as the beams of this building. It is characterized by being said to double as a pillar and brace.

「実施例」 以下、本発明の一実施例を第1図〜第9図を参照して説
明する。
``Example'' An example of the present invention will be described below with reference to FIGS. 1 to 9.

第1図は本実施倒の構造の梁10が採用されて構築され
た建築物の躯体を示す部分立面図である。
FIG. 1 is a partial elevation view showing the frame of a building constructed using a beam 10 having the structure of this embodiment.

=3 この梁10は、基本的には下弦材11、上弦材12、垂
直材】3、斜材14から構成されるトラス構造のもので
あるが、その断面を第2図に示すように、下弦材11は
ボックス状の鉄骨15の内側にコンクリートが充填され
るとともに、外側に鉄筋16が配筋されたうえでコンク
リ−1・が打設されて形成された鉄骨鉄筋コンクリート
造(より厳密には充填被覆室鋼管コンクリ−1・造)の
ものとされている。また、上記の上弦材J2、垂直利1
3、斜材14はいずれも鉄骨造とされている。
=3 This beam 10 is basically of a truss structure consisting of a lower chord member 11, an upper chord member 12, a vertical member]3, and a diagonal member 14, and its cross section is shown in Fig. 2. The lower chord member 11 is a steel-framed reinforced concrete structure (more precisely, it is formed by filling concrete inside a box-shaped steel frame 15, placing reinforcing bars 16 on the outside, and pouring concrete 1). It is said that the filling and coating chamber is made of steel pipe concrete. In addition, the above upper chord member J2, vertical gain 1
3. The diagonal members 14 are all made of steel.

この梁10は、第1図に示されるように下弦材1】の両
端が鉄骨鉄筋コンクリート造の大断面の柱18.18に
接合されてそれらの上端相互間に架設され、この梁10
の下方に、この建築物の4スパンにわたる幅を有し、か
つ、5層分が吹き抜けた無柱の大空間″;40が形成さ
れるようになっている。すなわち、この梁10および柱
18.18によって、そのような大空間20を形成する
とともに上層階の躯体を支持するための門型フレームで
あるメガス)・ラクチュアか構成されている。
As shown in FIG. 1, this beam 10 is constructed such that both ends of the lower chord member 1] are joined to large-section columns 18 and 18 made of steel-framed reinforced concrete, and the beam 10 is constructed between their upper ends.
A pillarless large space ``40'' is formed below the beam 10 and the pillar 18, which has a width spanning four spans of this building and has five floors. .18 constitutes a megastructure, which is a gate-shaped frame for forming such a large space 20 and supporting the framework of the upper floor.

そして、この梁10の下弦材1]の上面の位置には、上
記大空間20の直上階の床が形成され、上弦材12の」
二面の位置にはさらにその上階の床が形成されるように
なっていて、この梁10の下弦材11はそれ自身で大空
間20の直上階の床梁を兼ねるとともに、垂直材13お
よび斜材14はそれら自身でそれぞれこの階の柱および
ブレースを兼ねるものとされ、上弦材12はそれ自身で
その上階の床梁を兼ねるものとされている。
The floor of the floor directly above the large space 20 is formed at the upper surface of the lower chord 1 of this beam 10, and the floor of the upper chord 12 is formed.
The floor of the upper floor is further formed at the position of the second side, and the lower chord member 11 of this beam 10 also serves as the floor beam of the floor immediately above the large space 20, and the vertical member 13 and The diagonal members 14 each serve as columns and braces for this floor, and the upper chord members 12 serve as floor beams for the floor above.

なお、第1図において符号30.31はメガストラクチ
ュア以外の躯体である柱および梁であり、これらは通常
の鉄骨造とされている。
Note that in FIG. 1, reference numerals 30 and 31 indicate columns and beams that are the building blocks other than the megastructure, and these are made of normal steel structures.

上記梁10の施工手順の一例を第3図〜第9図を参照し
て説明する。
An example of the procedure for constructing the beam 10 will be described with reference to FIGS. 3 to 9.

第3図に示すように、柱18.18および大空間20の
床面までの躯体を構築した後、大空間20の床面上にお
いて梁10の下弦材11となる鉄骨15を組み立てる。
As shown in FIG. 3, after constructing the frame up to the columns 18, 18 and the floor of the large space 20, the steel frame 15 that will become the lower chord member 11 of the beam 10 is assembled on the floor of the large space 20.

この鉄骨15は、図示されるように、中央部15aと両
側部15b、15bとの3ピースにより構成し、その中
央部15aが上方に変位するようにむくりをつ(ブてお
く。そのむくり寸法d1は、後述するようにトラスの剛
性やコンクリートの重量等を考慮したうえで、梁10か
建築物の荷重を最終的に受けたときにほぼ水平となるよ
うに設定しておく。また、梁10の中央に位置して設け
られる垂直月13を予めこの鉄骨15の中央部15aに
取り付けておく。
As shown in the figure, this steel frame 15 is composed of three pieces, a central part 15a and both side parts 15b, which are bent so that the central part 15a is displaced upward. The cutout dimension d1 is set so that it will be approximately horizontal when the beam 10 finally receives the load of the building, taking into account the rigidity of the truss, the weight of the concrete, etc., as will be described later. , a vertical moon 13 provided at the center of the beam 10 is attached to the center portion 15a of the steel frame 15 in advance.

そして、そのように組み立てた鉄骨15を、柱18.1
8から反力をとっ゛Cリフトアップしていき、第4図に
示すようにそれら柱1848の−」二端間に架設する。
Then, the steel frame 15 assembled in this way is attached to the column 18.1.
The reaction force is removed from column 1848 to lift it up, and the column is installed between the two ends of column 1848 as shown in FIG.

次に、上記のように架設した鉄骨15に下向きの先行荷
重をかけ、むくり寸法がd2(d2<a+)となるまで
むくりを低減さゼる。それには、第5図に示すように、
鉄骨15の中央に設けられた上記垂直拐13に添わせて
油圧ジヤツキ40を上向きに取り付けるとともに、柱1
5.18と梁10どの仕口部にワイヤ41の両端を定着
し、そのワイヤ41の中央部を油圧ジヤツキ40に係合
させ、油圧ジャツギ40を作動させてそのワイヤ4Jの
中*部を押し上げて緊張することによって、その反力を
垂直材13を介して鉄骨15の中央部15aに下向きに
加えることが良い。なお、引上げ式の油圧ジヤツキを下
向きに設け、その油圧ジヤツキによりワイヤ41の中央
部を引っ張り上げるようにしても良い。
Next, a downward preliminary load is applied to the steel frame 15 constructed as described above, and the bulge is reduced until the bulge dimension becomes d2 (d2<a+). To do this, as shown in Figure 5,
A hydraulic jack 40 is attached upward along the vertical wall 13 provided in the center of the steel frame 15, and the column 1
5. Fix both ends of the wire 41 to the joint part of 18 and the beam 10, engage the center part of the wire 41 with the hydraulic jack 40, and operate the hydraulic jack 40 to push up the middle* part of the wire 4J. It is preferable to apply the reaction force downwardly to the central portion 15a of the steel frame 15 via the vertical member 13 by applying tension to the steel frame 15. Note that a lifting type hydraulic jack may be provided facing downward, and the central portion of the wire 41 may be pulled up by the hydraulic jack.

そして、その状態で、第6図に示すように、他の垂直拐
13、斜材14、上弦材12をそれぞれ鉄骨15に取り
付け、トラスを形成する。
In this state, as shown in FIG. 6, the other vertical beams 13, diagonal members 14, and upper chord members 12 are respectively attached to the steel frame 15 to form a truss.

その後、鉄骨15に加えた先行荷重を一旦解除する。こ
れにより、第7図に示すように鉄骨15のむくりは大き
くなるが、そのむくり寸法d3は、形成されたトラスの
剛性分たけ当初のむくり寸法d1よりは小さくなる。
Thereafter, the preceding load applied to the steel frame 15 is temporarily released. As a result, as shown in FIG. 7, the bulge of the steel frame 15 increases, but the bulge dimension d3 becomes smaller than the original bulge dimension d1, which takes into account the rigidity of the formed truss.

その後、鉄骨1!1Hの外側に鉄筋16を配筋して型枠
を組み立てたうえで、鉄骨15の内側にコンクリートを
充填するとともに外側にコンクリートを打設し、鉄骨鉄
筋コンクリート造の下弦材11を形成する。これにより
、第8図に示すように、梁10がむくりのイすいた状態
で形成されるが、この段階における梁10のむくり寸法
d、はコンクリートの重量分だけ上記のむくり寸法d3
より小さくなり、当然ながら鉄骨15に当初に付与され
ていたむくり寸法d1より小さくなる。この段階のむく
り寸法d、が、この後に梁10に負荷される上層階の躯
体およびその他の各種建築部材の荷重に対応するものと
なっていて、最終的にその荷重か梁10に加わることで
梁10が自ずとほぼ水平となるように設定されている。
After that, reinforcing bars 16 are arranged outside the steel frame 1!1H and a formwork is assembled, and concrete is filled inside the steel frame 15 and concrete is poured on the outside, and the lower chord member 11 of the steel-framed reinforced concrete construction is installed. Form. As a result, as shown in FIG. 8, the beam 10 is formed with less bulge, but the bulge dimension d of the beam 10 at this stage is equal to the above bulge dimension d3 by the weight of the concrete.
It becomes smaller, and of course becomes smaller than the exposed dimension d1 originally given to the steel frame 15. The exposed dimension d at this stage corresponds to the load of the upper floor frame and other various building components that will be applied to the beam 10 after this, and that load will eventually be applied to the beam 10. The beam 10 is set so that it is naturally almost horizontal.

そこで、コンクリ−1・強度が確保された後、梁10よ
り上階の施工により梁10が撓むとされるレベルよりや
や高めのレベルまで(第9図に示すようにほぼ水平とな
るまで)むくりを低減させるべく、ワイヤ41を介して
梁10に先行荷重をかける。その後、梁工0の上部に上
層階の躯体を施工するとともに各種建築部材を取り付け
ていき、その荷重に応じて順次ワイヤ41を緩めていっ
て先行荷重を段階的に低減させていくことにより、梁1
0を常にほぼ水平に保持する。
Therefore, after the strength of concrete 1 is ensured, the concrete is constructed on the floor above the beam 10 to a level slightly higher than the level at which the beam 10 is expected to bend (until it becomes almost horizontal as shown in Figure 9). A preload is applied to the beam 10 via the wire 41 in order to reduce the bowing. After that, the upper floor frame is constructed on top of beam construction 0, and various building components are attached, and the wires 41 are gradually loosened according to the load, thereby reducing the preceding load in stages. Beam 1
0 is always kept almost horizontal.

以上により、上層階か完成した時点で梁ioに加えた先
行荷重を全て解除すれば、梁10は上層階の躯体および
各種の建築部材の荷重により自ずと水平となる。
As described above, if all the preceding loads applied to the beam io are released when the upper floor is completed, the beam 10 will automatically become horizontal due to the loads of the upper floor frame and various building members.

上記の梁10では、下弦材11および上弦利12とによ
り全体としては十分な梁成寸法が確保されて十分な剛性
か得られ、これにJ:って、梁IOの下方に上記のよう
な大空間20が確保できることは勿論のこと、下弦材1
1を鉄骨鉄筋コンクリ−4造とし、かつ、この下弦材1
】の鉄骨15には梁10の撓み方向と逆方向の曲げモー
メントが付与されたものとなるので、第10図に示した
もののように梁全体を単純なトラス構造とする場合に比
して鉄骨量を削減できるとともに鉄骨加工が簡略化され
、工費、施工手間の点で有利である。
In the above beam 10, the lower chord member 11 and the upper chord member 12 ensure sufficient beam dimensions as a whole, and sufficient rigidity is obtained. Not only can a large space 20 be secured, but also the lower chord 1
1 is a steel-frame reinforced concrete 4 structure, and this lower chord material 1
] Since a bending moment is applied to the steel frame 15 in the direction opposite to the deflection direction of the beam 10, the steel frame 15 is It is possible to reduce the amount of steel and simplify the steel processing, which is advantageous in terms of construction costs and labor.

しかも、下弦材11.上弦材12、垂直材13、斜材1
4がそれぞれこの建築物の梁、柱、ブレースを兼ねるの
で、建築物全体の躯体が簡略化されるという利点もある
Moreover, the lower chord material 11. Upper chord member 12, vertical member 13, diagonal member 1
4 also serves as beams, columns, and braces of this building, so there is also the advantage that the frame of the entire building can be simplified.

また、上記実施例の施工手順では、トラスを形成するに
際して鉄骨1.5に先行荷重をかけてむくりを低減させ
てから垂直材13、斜材14、上弦材12を組み立てる
ので、その作業を容易に行うことができるものである。
In addition, in the construction procedure of the above embodiment, when forming a truss, the vertical members 13, diagonal members 14, and upper chord members 12 are assembled after applying a preliminary load to the steel frame 1.5 to reduce the bulge, so this work is This is something that can be done easily.

すなわち、鉄骨15に当初の大きなむくり(むくり寸法
dI)が付いている状態のままでトラスを組み立てる場
合にあっては、垂直材13が外側に傾いてしまうことに
なってトラスの建方が非常に困難となるのに対し、上記
の場合には、むくり寸法がd2となるまでむくりを低減
させてからトラスを組み立てるので、垂直材13を支障
なく鉛直に建てることができ、したがってトラスを容易
に組み立てることができる。
In other words, when assembling a truss with the steel frame 15 still having a large bulge (the bulge dimension dI), the vertical members 13 will tilt outward, making it difficult to erect the truss. However, in the above case, the truss is assembled after reducing the bulge until the bulge dimension becomes d2, so the vertical members 13 can be erected vertically without any hindrance. The truss can be easily assembled.

また、鉄骨15に対してコンクリートを打設して下弦材
11を形成するに際し、鉄骨15に加えた先行荷重を一
旦解除してd2よりも大きなむくりの付いた状態に戻し
、その状態でコンクリートを打設するようにしたので、
鉄骨15のむ<リヲd2に低減させたままの状態でコン
クリートを打設して下弦材■1を形成する場合に比して
、梁1oの剛性をより高めることができる。
In addition, when pouring concrete to the steel frame 15 to form the lower chord member 11, the preceding load applied to the steel frame 15 is temporarily released to return it to a state with a bulge greater than d2, and in that state, the concrete is poured into the steel frame 15. Since we decided to pour
The rigidity of the beam 1o can be further increased compared to the case where the lower chord member (1) is formed by pouring concrete while the steel frame 15 remains reduced to d2.

なお、鉄骨15、梁1oに対して先行荷重な加えるため
には、」二記実施例に限定されるこ2なく適宜の手法を
採用し得る。
In addition, in order to apply a preliminary load to the steel frame 15 and the beam 1o, an appropriate method can be adopted without being limited to the second embodiment.

また、上記実施例では、梁1oの下弦材11を充填被覆
型鋼管コンクリ−j・造りものとしたが、これは鉄骨J
5の内部にのみコンクリートを充填する充填鋼管コンク
リート構造としても良いし、あるいは、ボックス状の鉄
骨に限らず任意の断面形状の鉄骨を使用した一般の鉄骨
鉄筋コンクリート造としても良い。また、上弦材12、
垂直材13、斜材14も鉄骨造に限らず、鉄骨鉄筋コン
クリート造や鋼管コンクリート構造としてモ良く、垂直
材13や斜材14の位置、形式は、設計上の要求等に応
じて適宜変更して良いことはいうまでもない。さらに、
上記の梁1oの上部や下部にさらにトラスを一体に形成
した複合トラス構造の梁とすることにより、剛性をより
高めることもできる。
In addition, in the above embodiment, the lower chord member 11 of the beam 1o was made of a filled-covered steel pipe concrete structure, but this is a steel frame J.
It may be a filled steel pipe concrete structure in which only the inside of the tube 5 is filled with concrete, or it may be a general steel reinforced concrete structure using not only a box-shaped steel frame but also a steel frame with an arbitrary cross-sectional shape. In addition, the upper chord material 12,
The vertical members 13 and diagonal members 14 are also suitable not only for steel frame structures but also for steel reinforced concrete structures and steel pipe concrete structures, and the positions and formats of the vertical members 13 and diagonal members 14 may be changed as appropriate according to design requirements. Needless to say, it's a good thing. moreover,
Rigidity can be further increased by forming a beam with a composite truss structure in which a truss is further integrally formed at the upper and lower portions of the beam 1o.

また、上記実施例では、梁1oの両端が支持される柱1
8を鉄骨鉄筋コンクリート造としたが、必ずしもそれに
限定されない。また、柱18を鉄骨鉄筋コンクリート造
とする場合においても、その柱18に対するコンクリー
ト打設は、梁10の下弦材llに対するコンクリート打
設と同時に行っても良い。勿論、柱18の上端部にのみ
ならずその途中に梁10を設けることもできる。さらに
、上記実施例では、梁10の下弦材11となる鉄骨15
をリフトアップして柱18上端間に架設するようにした
が、スパンが比較的小さい場合等においては必ずしもリ
フ1へアップ工法によることはない。
Further, in the above embodiment, the column 1 on which both ends of the beam 1o are supported
8 is made of steel-framed reinforced concrete construction, but it is not necessarily limited thereto. Further, even when the column 18 is made of steel-framed reinforced concrete, the concrete placement for the column 18 may be performed simultaneously with the concrete placement for the lower chord member 11 of the beam 10. Of course, the beam 10 can be provided not only at the upper end of the column 18 but also in the middle thereof. Furthermore, in the above embodiment, the steel frame 15 serving as the lower chord member 11 of the beam 10
However, in cases where the span is relatively small, etc., the lift-up method is not necessarily used.

また、上記実施例は、本発明の構造の梁を、その下方に
無柱の大空間が設けられるとともに上部に上層階の躯体
が設けられる形態の建築物に適用した場合の例であるが
、本発明の構造の梁はそのような形態の建築物に適用さ
れるのみならず、種々の形態の建築物全般に対して同様
に適用できることはいうまでもない。
Further, the above embodiment is an example in which the beam of the structure of the present invention is applied to a building in which a large column-free space is provided below and a frame of an upper floor is provided above. It goes without saying that the structural beam of the present invention can be applied not only to such types of buildings, but also to various types of buildings in general.

「発明の効果」 以上で詳細に説明したように、本発明の梁の構造は、下
弦材を鉄骨鉄筋コンクリート造とするととも?ここの下
弦材中の鉄骨自体に梁の撓み方向と逆方向の曲げモーメ
ントを付与し、上弦材、垂直材、斜材を鉄骨造となした
ものであるから、十分な剛性が得られることは勿論のこ
と、梁全体を単純なトラス構造とする場合に比して鉄骨
量を削減できるとともにその加工が簡略化されて工費や
施工手間の点で存利であり、また、下弦利、上弦材、垂
直材、斜材がそれぞれこの建築物の梁、柱、ブレースを
兼ねるので、建築物全体の躯体が簡略化されるという利
点も有し、メガストラクチュアを構成する梁として採用
して好適である。
"Effects of the Invention" As explained in detail above, the structure of the beam of the present invention is such that the lower chord is made of steel-framed reinforced concrete. The steel frame in the bottom chord itself is given a bending moment in the direction opposite to the deflection direction of the beam, and the top chord, vertical members, and diagonal members are made of steel, so it is possible to obtain sufficient rigidity. Of course, compared to the case where the entire beam has a simple truss structure, the amount of steel can be reduced and the processing is simplified, which is advantageous in terms of construction cost and construction time. , vertical members, and diagonal members serve as the beams, columns, and braces of this building, respectively, so they have the advantage of simplifying the frame of the entire building, and are suitable for use as beams constituting a megastructure. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図および第2図は本発明に係る梁の構造の一実施例
を示すもので、第1図はその梁が採用されて構築された
建築物の躯体を示す部分立面図、第2図はその梁の断面
図(第1図の■−■線矢視図)である。第3図〜第9図
は上記梁の施工手順の一例を工程順に8F!Aするため
の図である。 第1O図は、メガストラクチュアによる建築物の一従来
例を示す斜視図である。 0・・・・・・梁、 l 1 ・・ ・・下弦拐、1 ・・・・・上弦材、 ■ 3・・・・・垂直材、 4・・・・・・斜材、 5・・・・・・鉄骨、 6・・・・・・鉄筋、1 ・・・・・柱。
Figures 1 and 2 show an example of the structure of a beam according to the present invention; Figure 1 is a partial elevation view showing the frame of a building constructed using the beam; The figure is a cross-sectional view of the beam (a view taken along the line ■-■ in FIG. 1). Figures 3 to 9 show an example of the construction procedure for the above-mentioned beam in the order of steps on 8F! This is a diagram for A. FIG. 1O is a perspective view showing a conventional example of a building using a megastructure. 0... Beam, l 1... Lower chord, 1... Top chord, ■ 3... Vertical member, 4... Diagonal member, 5... ...steel frame, 6 ...reinforcement, 1 ...column.

Claims (1)

【特許請求の範囲】[Claims]  建築物の躯体を構成する長大スパンかつ大断面の梁の
構造であって、上弦材と下弦材およびそれらを連結する
垂直材と斜材とからなるトラス構造とされ、かつ、前記
下弦材が鉄骨鉄筋コンクリート造とされているとともに
この下弦材中の鉄骨自体が梁の撓み方向と逆方向の曲げ
モーメントを付与されており、前記上弦材、垂直材、斜
材がいずれも鉄骨造とされ、しかも、前記下弦材および
上弦材は、それぞれそれら自身でこの建築物の梁を兼ね
るとともに、前記垂直材および斜材は、それぞれそれら
自身でこの建築物の柱およびブレースを兼ねるものとさ
れていることを特徴とする梁の構造。
A beam structure with a long span and a large cross section that constitutes the frame of a building, and is a truss structure consisting of an upper chord member, a lower chord member, and vertical members and diagonal members that connect them, and the lower chord member is a steel frame. It is made of reinforced concrete, and the steel frame itself in the lower chord is given a bending moment in the direction opposite to the direction of deflection of the beam, and the upper chord, vertical members, and diagonal members are all made of steel, and, The lower chord member and the upper chord member each serve as a beam of the building, and the vertical member and the diagonal member each serve as a column and a brace of the building. The structure of the beam.
JP17780190A 1990-07-05 1990-07-05 Beam structure Expired - Lifetime JP2934668B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17780190A JP2934668B2 (en) 1990-07-05 1990-07-05 Beam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17780190A JP2934668B2 (en) 1990-07-05 1990-07-05 Beam structure

Publications (2)

Publication Number Publication Date
JPH0468140A true JPH0468140A (en) 1992-03-03
JP2934668B2 JP2934668B2 (en) 1999-08-16

Family

ID=16037330

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17780190A Expired - Lifetime JP2934668B2 (en) 1990-07-05 1990-07-05 Beam structure

Country Status (1)

Country Link
JP (1) JP2934668B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001220829A (en) * 2000-01-12 2001-08-17 Cds International:Kk Connecting member and connecting method
JP2003105870A (en) * 2001-09-28 2003-04-09 Okuju Co Ltd Connecting construction for structural member of building
CN105525684A (en) * 2016-01-22 2016-04-27 中建钢构有限公司 Steel plate wall hoisting sliding beam capable of intelligently avoiding influence of jacking steel platform truss
CN106760712A (en) * 2017-01-20 2017-05-31 华电重工股份有限公司 A kind of jacking installation method of steel structure cooling tower
CN106759924A (en) * 2017-01-20 2017-05-31 华电重工股份有限公司 A kind of lifting installation method of steel structure cooling tower
CN115306031A (en) * 2022-09-20 2022-11-08 中国航空规划设计研究总院有限公司 Adopt super high large-span structural system of huge reinforced concrete lattice column

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001220829A (en) * 2000-01-12 2001-08-17 Cds International:Kk Connecting member and connecting method
JP2003105870A (en) * 2001-09-28 2003-04-09 Okuju Co Ltd Connecting construction for structural member of building
CN105525684A (en) * 2016-01-22 2016-04-27 中建钢构有限公司 Steel plate wall hoisting sliding beam capable of intelligently avoiding influence of jacking steel platform truss
CN106760712A (en) * 2017-01-20 2017-05-31 华电重工股份有限公司 A kind of jacking installation method of steel structure cooling tower
CN106759924A (en) * 2017-01-20 2017-05-31 华电重工股份有限公司 A kind of lifting installation method of steel structure cooling tower
CN115306031A (en) * 2022-09-20 2022-11-08 中国航空规划设计研究总院有限公司 Adopt super high large-span structural system of huge reinforced concrete lattice column
CN115306031B (en) * 2022-09-20 2024-04-05 中国航空规划设计研究总院有限公司 Ultra-high large-span structural system adopting giant reinforced concrete lattice column

Also Published As

Publication number Publication date
JP2934668B2 (en) 1999-08-16

Similar Documents

Publication Publication Date Title
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
JP6339923B2 (en) How to build a building frame
JPH0468140A (en) Construction of beam
JPH05287901A (en) Construction of stairs
JP2916587B2 (en) Construction method of building
JP3413584B2 (en) Construction method of frame structure
JP2916585B2 (en) Construction method of building
JP7169765B2 (en) How to build structures
JPH04368528A (en) Frame construction using void beam
JP2974025B1 (en) Construction method of large span large beam upper frame
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam
JPS6314937A (en) Reinforcing bar composite pillar
JP2522708B2 (en) Reinforcing bar tip assembly beam with formwork and reinforcing bar tip assembly method with formwork
JP2916588B2 (en) Construction method of building
JP2659329B2 (en) Construction method of PC structure
JP2514859B2 (en) Precast Steel Reinforced Concrete Concrete Column
JP2023067236A (en) Slab base structure before concrete placement, reinforced concrete slab structure, method of constructing slab base structure before concrete placement, and method of constructing reinforced concrete slab structure
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPH08270255A (en) Seismic isolation structuring method of existing building
JPH0468168A (en) Building method
JP2023022563A (en) Concrete wall construction method
JP2022163290A (en) Structure
JP2761527B2 (en) How to build structures
JPH03197734A (en) Lift up method by replacement of scaffold body
JP2003148094A (en) Timbering construction method