JP3413584B2 - Construction method of frame structure - Google Patents

Construction method of frame structure

Info

Publication number
JP3413584B2
JP3413584B2 JP07914595A JP7914595A JP3413584B2 JP 3413584 B2 JP3413584 B2 JP 3413584B2 JP 07914595 A JP07914595 A JP 07914595A JP 7914595 A JP7914595 A JP 7914595A JP 3413584 B2 JP3413584 B2 JP 3413584B2
Authority
JP
Japan
Prior art keywords
layer
frame
floor
load
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP07914595A
Other languages
Japanese (ja)
Other versions
JPH08270081A (en
Inventor
正恒 小倉
一智 横山
博之 関
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP07914595A priority Critical patent/JP3413584B2/en
Publication of JPH08270081A publication Critical patent/JPH08270081A/en
Application granted granted Critical
Publication of JP3413584B2 publication Critical patent/JP3413584B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 【0001】 【産業上の利用分野】本発明は、例えば地上部に大空間
を形成するために、地上部を柱のない無柱空間としたビ
ルを構築するのに好適な架構構造物に関するものであ
る。 【0002】 【従来の技術】従来、図4に示すように、地上部に大空
間1を形成するために、外周部にのみ柱2,2,…を立
設するとともに、地上から一定寸法上方に基準階3を設
置し、その上に上層階4を設けた形式として、基準階3
の下方を無柱空間6としたビル(架構構造物)5があ
る。そして、このようなビル5は、言うまでもなく、下
方から上方に向けて順次積み上げ構築していくのが通常
である。 【0003】このようなビル5では、基準階3の躯体
に、それより上方の上層階4の荷重が集中してかかるた
め、基準階3の躯体を設計するに際しては、前記荷重を
支持できるようにしているのは周知のとおりである。 【0004】 【発明が解決しようとする課題】しかしながら、上述し
たような従来の架構構造物には、以下のような問題が存
在する。すなわち、前述したように、基準階3の躯体で
上層階4の全荷重を支持するため、基準階3を構成する
各部材には、前記荷重に耐え得る大断面のものを採用し
ており、非常に不経済であるという問題がある。しか
も、地震時の振動による応力等を組み合わせると、その
設計が非常に複雑で困難なものになってしまう。この問
題は、ビル5が高層となればなるほど顕著なものとなっ
ている。 【0005】また、近年では、ビル5の最上部5aをト
ラス構造とすることによって、上層階4の荷重を基準階
3と最上部5aとで分担して支持する構造も採用されて
いるが、このような構造においても、その施工に際し、
最上部5aの構築が完了するまでの間は、基準階3に上
層階4の全荷重がかかることになる。このため、基準階
3に、最上部5aを除く上層階の荷重を支持するだけの
強度を持たせなければならず、また、施工完了後も上層
階4の荷重による応力が基準階3に残存するため、前記
の問題の解決には至っていない。 【0006】本発明は、以上のような点を考慮してなさ
れたもので、経済的で、かつ設計の容易化を図ることの
できる架構構造物の施工方法を提供することを目的とす
る。 【0007】 【課題を解決するための手段】請求項1に係る発明は、
外周部に立設されたコア柱と、地表面から一定寸法上方
に設けられたトラス構造の基準層躯体と、トラス構造の
最上層躯体とから外周フレームが構成され、該外周フレ
ームの前記基準層躯体と最上層躯体との間に中間層躯体
が設けられた構成からなる架構構造物を施工するに際
し、前記中間層躯体を上層部と下層部とに区分してお
き、前記基準層躯体と最上層躯体とをそれぞれ定められ
た高さにおいて前記コア柱に接合するとともに、前記基
準層躯体で前記中間層躯体の下層部の荷重を支持し、前
記最上層躯体で前記中間層躯体の上層部の荷重を支持し
た状態とし、しかる後に、前記中間層躯体の上層部と下
層部とを接合する構成とした架構構造物の施工方法であ
って、まず前記コア柱を所定の高さまで構築した時点
で、基準層躯体を定められた高さに建方した後、コア柱
の構築と、前記基準層躯体上への中間層躯体の建方とを
行っていき、前記中間層躯体の下層部を建方した後、中
間層躯体の上層部を建方するときに、下層部の柱部材と
上層部の柱部材とを接合せずにそれらの間にジャッキを
介装して双方の柱部材を上下方向に所定寸法だけ離間さ
せておき、前記中間層躯体の最上階までの建方が完了し
た後に、前記最上層躯体を建方して、該最上層躯体と前
記中間層躯体の上層部とを接合した後、前記ジャッキを
操作して中間層躯体の上層部をジャッキダウンすること
により、上層部の柱部材と下層部の柱部材との間の離間
寸法をそれらを溶接するためのルートギャップとなるよ
うにし、その状態でそれら柱部材どうしを溶接して接合
することを特徴としている。 【0008】 【作用】請求項1記載の発明では、基準層躯体と最上層
躯体とをコア柱に接合するとともに、基準層躯体で中間
層躯体の下層部の荷重を支持し、最上層躯体で前記中間
層躯体の上層部の荷重を支持した状態とした後、最終的
に中間層躯体の上層部と下層部とを接合する構成とし
た。これにより、施工中においてはもちろんのこと、中
間層躯体の上層部と下層部とを接合した後においても、
中間層躯体の下層部の荷重を基準層躯体で支持し、上層
部の荷重を最上層躯体で支持する状態を維持することが
できる。 【0009】また、基準層躯体上に中間層躯体を建方し
ていき、その下層部を建方した後に上層部を建方する際
には、下層部の柱部材と上層部の柱部材とを接合せずに
それらの間にジャッキを介装して所定寸法だけ離間させ
ておき、中間層躯体の上層部を最上層躯体に接合した後
に上層部をジャッキダウンして、双方の柱部材の間の離
間寸法をそれらを溶接するためのルートギャップとなる
ようにし、その状態でそれら柱部材どうしを溶接して接
合する構成とした。これにより、基準層躯体で下層部の
荷重を支持し、最上層躯体で上層部の荷重を支持し、そ
の状態で最終的に中間層躯体の上層部と下層部とを接合
することができる。したがって、施工途中においてはも
ちろんのこと施工完了後においても、中間層躯体の上層
部の荷重は最上層躯体に支持され、下層部の荷重は基準
層躯体によって支持されることになる。 【0010】 【実施例】以下、本発明を図1〜図3に示す実施例を参
照して説明する。 【0011】まず、本発明にかかる架構構造物の施工方
法を適用して構築すべき架構構造物について説明する。
図1に示すように、ビル(架構構造物)10は、例えば
平面視矩形で、その両側面10a,10aには、両端部
と中間部とに、メガ柱(コア柱)11,11,…が立設
されている。各メガ柱11は、鉄筋コンクリート造を主
体とした、例えば上下方向に連続する断面視ロ字状のコ
アウォール構造となっており、その内部には、例えばエ
レベータや各種設備、機械室等が収められている。 【0012】これらメガ柱11,11,…によって支持
されたビル10の躯体12は、その最下部である基準層
躯体13が例えば地上4階に相当する高さに設けられ、
その下方に大空間14が形成された構成となっている。 【0013】基準層躯体13は、例えば2階分の高さ離
間して配された上弦材13aと下弦材13bとの間に、
柱部材13cとラチス材13dとが組み合わされたトラ
ス構造とされている。 【0014】また、躯体12の最上部を構成する最上層
躯体15も同様に、例えば2階分の高さを有しており、
上弦材15aと下弦材15bとの間に、柱部材15cと
ラチス材15dとが組み合わされたトラス構造とされて
いる。 【0015】そして、基準層躯体13と最上層躯体15
との間において、躯体12の中間の各階を構成する中間
層躯体16は、例えば鉄骨造で、一定間隔毎に立設され
た柱17と、各階毎に架設された梁18とからなる、通
常のラーメン構造となっている。 【0016】上記した鉄筋コンクリート造のメガ柱1
1,鉄骨トラス構造の基準層躯体13および最上層躯体
15とから、強固なメガストラクチャー(外周フレー
ム)20が構成されており、ビル10の躯体12は、こ
のメガストラクチャー20の内方に、中間層躯体16が
配された構成となっている。 【0017】次に、このようなビル10の施工方法につ
いて図1ないし図3を参照して説明する。まず、図2に
示すように、地盤G中に構築した図示しない基礎あるい
は地下階躯体上の所定の位置に、メガ柱11,11,…
を構築していく。 【0018】そして、これらのメガ柱11の構築作業
が、少なくとも基準層躯体13を建方すべき高さよりも
上方にまで進行した後に、基準層躯体13を所定の高さ
に建方してメガ柱11,11,…に接合する。 【0019】基準層躯体13の建方が完了した後には、
各メガ柱11の構築作業と、基準層躯体13上における
中間層躯体16の建方作業とを平行して進行させてい
く。 【0020】このようにして中間層躯体16の下層部1
6aを積み上げ構築していき、中間層躯体16の予め定
めた階Fを建方するときには、この階Fを構成する柱部
材17aと、既に建方の完了した直下階F’を構成する
柱部材17’aとを接合しないでおく。そして、この階
Fの組み立てが完了した後、図3に示すように、各柱部
材17aの下部に予め設けておいたブラケット21,2
1と、直下階F’の梁18との間に、例えば油圧ジャッ
キ等のジャッキ機構22,22を介装させる。次いで、
これらジャッキ機構22を一斉に伸長させて、互いに上
下に位置する柱部材17a,17’a間を予め設定した
寸法δだけ離間させておく。 【0021】この後は、図2に示したように、通常と同
様にして、メガ柱11の構築と、中間層躯体16の上層
部16bの建方とを続行し、これらを最上部まで建方す
る。 【0022】そして、中間層躯体16上に最上層躯体1
5を建方し、この最上層躯体15を、各メガ柱11およ
び中間層躯体16に接合する。 【0023】この時点で、ジャッキ機構22,22,…
を設置した階Fよりも下方側の下層部16aの荷重は、
基準層躯体13によって支持されていることになる。一
方、前記階Fよりも上方側の上層部16bの荷重は、最
上層躯体15にも支持されているが、ジャッキ機構2
2,22,…および下層部16aを介して、基準層躯体
13によっても支持された状態となっている。 【0024】この後に、全てのジャッキ機構22を一斉
に収縮させてジャッキダウンさせる。このとき、柱部材
17a,17’aのジャッキダウン前の初期の離間寸法
δ(図3参照)は、ジャッキダウン時の荷重の減少によ
って基準層躯体13の下方へのたわみ量が減少したとき
に、その離間寸法δ’が上下の柱部材17a,17’a
を互いに溶接するためのルートギャップとなるように設
定されている。すなわち、上下に位置する柱部材17
a,17’aどうしはジャッキダウン後においても、当
接せずに前記離間寸法δ’だけ離間した状態となるよう
になっている。 【0025】すると、これらのジャッキ機構22を設置
した階Fよりも下方側の下層部16aの荷重は、基準層
躯体13によって支持されていることに変わりはない
が、上層部16bの荷重は、最上層躯体15によっての
み支持された状態となる。したがって、ジャッキダウン
する前の状態と比較すると、基準層躯体13で支持する
荷重は上層部16bの分だけ減少し、その分だけ応力が
解除されることになる。 【0026】そして、ジャッキダウンの完了後、この階
Fにおいて、各柱部材17a,17’aのジョイント部
を溶接して接合する。 【0027】このようにして、図1に示したビル10の
躯体12の構築が完了する。これ以降においては、ジャ
ッキ機構22を設置した階Fよりも下方側の下層部16
aの荷重が基準層躯体13によって支持され、上層部1
6bの荷重は最上層躯体15によって支持された状態が
維持される。 【0028】上述したビル10の施工方法では、基準層
躯体13上に中間層躯体16を建方していき、定められ
た階Fの中間層躯体16を建方するに際して、この階F
の各柱部材17aと、先に建方した直下階F’の柱部材
17’aとを接合せずにこれらの間にジャッキ機構2
2,22を介装させておき、この後に上層部16bおよ
び最上層躯体15を建方した後に、ジャッキ機構22,
22,…を取り外して、その上下に位置する柱部材17
a,17’aどうしを溶接して接合する構成とした。こ
れにより、ビル10の完成後は、ジャッキ機構22を設
置した階Fよりも下方側の下層部16aの荷重は基準層
躯体13によって支持され、上層部16bの荷重は最上
層躯体15によって支持されることになる。このように
して中間層躯体16の荷重を、それぞれトラス構造の基
準層躯体13と最上層躯体15とで分担して支持するこ
とによって、特に基準層躯体13を構成する各部材の断
面寸法を小さくすることができ、これを経済的なものと
することができる。また、ビル10の基準層躯体13の
設計に際して、施工途中においては中間層躯体16全体
の荷重を支持できるようにして、完成後にはジャッキ機
構22を設置した階Fよりも下方側の下層部16aの荷
重を支持できるように設計すればよい。しかも、施工途
中と完成後を比較すると、支持しなければならない荷重
が激減し、残存する応力が大幅に減少するため、設計の
容易化を図ることができる。しかも減少した応力の分で
地震の水平動、上下動による応力に対する耐力の少なく
とも一部が確保できるため、この点からもビル10の躯
体構造を経済的なものとすることができる。 【0029】しかも、ジャッキ機構22,22,…で、
柱部材17aをジャッキアップするときに、柱部材17
a,17’aの離間間隔δを、ジャッキダウン後の離間
間隔δ’が溶接のルートギャップとなるように予め設定
しておいたので、柱部材17a,17’aの溶接作業を
容易かつ確実に行うことができる。 【0030】なお、上記実施例において、ジャッキ機構
22を設置する階Fについては限定するものではなく、
例えば中間層躯体16の最下階、すなわち基準層躯体1
3の直上階としてもよいし、また、中間層躯体16の最
上階等、他の階としてもよい。例えば、ジャッキ機構2
2を設置する階Fを中間層躯体16の最下階とした場合
には、基準層躯体16で支持する荷重は、ジャッキアッ
プ時には基準層躯体16よりも上方の荷重全てであった
のが、ジャッキダウン後には、基準層躯体16自身の荷
重のみに激減することになる。すると、仕上げ材による
荷重や、基準階に積載する機器等の荷重による応力、自
身の水平動上下動による応力を組み合わせても、その大
部分あるいは全部を、減少した分の荷重に対する耐力で
カバーすることも可能であり、設計を非常に容易に行う
ことが可能となる。 【0031】また、上記実施例において、基準層躯体1
3,最上層躯体15をそれぞれ例えば2階分の高さを有
する構成としたが、トラス構造とするのであれば、もち
ろんこれを1階分の高さとしたり、あるいは3階分以上
の高さを有する構成としてよいのは言うまでもない。 【0032】また、構築すべきビル10のメガ柱11,
11,…を、ビル10の両側面に一定間隔毎に配する構
成としたが、その配置については限定するものではな
い。例えば、これを四隅のみに配する構成としてもよい
し、ビル10の両側面全体をメガ柱とする構成としても
よいし、さらには外周部全体にメガ柱を適宜間隔毎に配
する構成としてもよい。加えて、断面視矩形のチューブ
状のメガ柱11を、鉄筋コンクリート造からなる構成と
したが、これを鉄骨鉄筋コンクリート造、鋼管造、充填
鋼管コンクリート造等としてもよいし、また、鉄骨をチ
ューブ状に組んだ立体トラス構造等としてもよい。 【0033】また、基準層躯体13が、一定寸法上方、
すなわち空中に位置するのであれば、その設定階数につ
いては限定するものではない。さらには、ビル10が地
下階を備えている場合はもちろんのこと、例えば地上1
階から3階部分を有するビルにおいて地上5階に基準階
を位置させる場合等においても、前記施工方法を同様に
適用することが可能であり、上記と同様の効果を奏する
ことができる。さらには、各階に打設する床コンクリー
ト、あるいはPCスラブ板等の施工タイミングについて
は、基準層躯体13で施工中および完了後に支持する荷
重のバランス等を考慮して、適宜決定すればよい。 【0034】 【発明の効果】以上説明したように、請求項1に係る架
構構造物の施工方法によれば、基準層躯体と最上層躯体
とをコア柱に接合するとともに、基準層躯体で中間層躯
体の下層部の荷重を支持し、最上層躯体で前記中間層躯
体の上層部の荷重を支持した状態とした後、最終的に中
間層躯体の上層部と下層部とを接合する構成とし、
に、中間層躯体の下層部の柱部材と上層部の柱部材とを
接合せずにそれらの間にジャッキを介装して所定寸法だ
け離間させておき、中間層躯体の上層部を最上層躯体に
接合した後に上層部をジャッキダウンして、双方の柱部
材の間の離間寸法をそれらを溶接するためのルートギャ
ップとなるようにし、その状態でそれら柱部材どうしを
溶接して接合する構成とした。これにより、施工中にお
いてはもちろんのこと、中間層躯体の上層部と下層部と
を接合した後においても、中間層躯体の下層部の荷重を
基準層躯体で支持し、上層部の荷重を最上層躯体で支持
する状態を維持することができる。このようにして、中
間層躯体の荷重を、それぞれトラス構造の基準層躯体と
最上層躯体とで分担して支持することによって、特に基
準層躯体を構成する各部材の断面寸法を小さくすること
ができ、これを経済的なものとすることができる。ま
た、施工途中と完成後を比較すると、支持しなければな
らない荷重が激減し、残存する応力が大幅に減少するた
め、設計の容易化を図ることができる。しかも減少した
応力の分で地震の水平動、上下動による応力に対する耐
力の少なくとも一部が確保できるため、この点からも架
構構造物の躯体構造を経済的なものとすることができ
る。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the construction of a building having a pillar-free space without pillars in order to form a large space above the ground, for example. It relates to a suitable frame structure. 2. Description of the Related Art Conventionally, as shown in FIG. 4 , in order to form a large space 1 on the ground, pillars 2, 2,... The base floor 3 is installed in the base floor, and the upper floor 4 is provided thereon.
There is a building (frame structure) 5 having a column-free space 6 below. Needless to say, such buildings 5 are usually built up one by one from bottom to top. In such a building 5, since the load of the upper floor 4 above the base floor 3 is concentrated on the skeleton of the base floor 3, when the skeleton of the base floor 3 is designed, the load can be supported. Is well known. [0004] However, the conventional frame structure as described above has the following problems. That is, as described above, in order to support the entire load of the upper floor 4 by the frame of the reference floor 3, each member constituting the reference floor 3 has a large cross section capable of withstanding the load, There is a problem that it is very uneconomical. In addition, the combination of stress due to vibration during an earthquake and the like makes the design very complicated and difficult. This problem becomes more prominent as the building 5 becomes higher. In recent years, a structure has been adopted in which the load on the upper floor 4 is shared and supported by the reference floor 3 and the uppermost portion 5a by making the uppermost portion 5a of the building 5 a truss structure. Even in such a structure,
Until the construction of the uppermost portion 5a is completed, the entire load of the upper floor 4 is applied to the reference floor 3. For this reason, the reference floor 3 must have enough strength to support the load of the upper floor except for the uppermost portion 5a, and the stress due to the load of the upper floor 4 remains on the reference floor 3 even after the completion of the construction. Therefore, the above-mentioned problem has not been solved. The present invention has been made in consideration of the above points, and has as its object to provide a method of constructing a frame structure which is economical and can facilitate design. Means for Solving the Problems The invention according to claim 1 is:
An outer peripheral frame is composed of a core pillar erected on the outer peripheral portion, a reference truss structure of a truss structure provided above the ground surface by a certain dimension, and an uppermost truss structure of the truss structure. When constructing a frame structure consisting of a structure in which an intermediate layer frame is provided between the frame and the top layer frame
Then, the intermediate layer skeleton is divided into an upper layer and a lower layer, and the reference layer skeleton and the uppermost layer skeleton are joined to the core pillars at predetermined heights, respectively. A structure in which the load of the lower layer of the intermediate layer is supported, and the load of the upper layer of the intermediate layer is supported by the uppermost layer, and thereafter, the upper layer and the lower layer of the intermediate layer are joined. The construction method of the framed structure
Therefore, first, when the core pillar is constructed to a predetermined height, the reference layer frame is constructed at a predetermined height, and then the core pillar is constructed and the intermediate layer frame is constructed on the reference layer frame. After constructing the lower layer of the intermediate layer building,
When building the upper part of the inter-story building,
Without joining the upper column members, jack them between them
With the two pillars separated by a specified distance in the vertical direction
Was advance, after the person denominated to the top floor of the intermediate layer precursor is complete, the erection of the uppermost skeleton, after joining the upper part of the the top layer precursor intermediate layer precursor, said jack To
Operation to jack down the upper part of the middle structure
The distance between the upper column member and the lower column member
The dimensions will be the root gap for welding them
And then weld and join the column members together
It is characterized in that. According to the first aspect of the present invention, the reference layer frame and the uppermost layer frame are joined to the core pillar, and the reference layer frame supports the load of the lower layer of the intermediate layer frame. After the load of the upper layer portion of the intermediate layer body was supported, the upper layer portion and the lower layer portion of the intermediate layer frame were finally joined. This allows not only during construction, but also after joining the upper and lower layers of the intermediate layer skeleton,
It is possible to maintain a state in which the lower layer load is supported by the reference layer frame while the upper layer load is supported by the upper layer frame. In addition, an intermediate layer skeleton is built on the reference layer skeleton.
When building the upper part after building the lower part,
Without joining the lower column member and the upper column member
Insert a jack between them and separate them by a predetermined size.
After joining the upper layer of the middle layer to the upper layer
Jack down the upper part of the
The inter-dimension becomes the root gap for welding them
And then weld the column members together
It was configured to match. As a result, the lower layer
The load is supported, and the uppermost frame supports the upper layer load.
Finally, the upper and lower layers of the intermediate frame are joined
can do. Therefore, the load of the upper layer portion of the intermediate layer skeleton is supported by the uppermost layer skeleton, and the load of the lower layer portion is supported by the reference layer skeleton, not only during the construction but also after the completion of the construction. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the embodiments shown in FIGS. First, a frame structure to be constructed by applying the method for constructing a frame structure according to the present invention will be described.
As shown in FIG. 1, a building (frame structure) 10 is, for example, rectangular in a plan view, and has mega pillars (core pillars) 11, 11,... On both side surfaces 10a, 10a at both ends and an intermediate portion. Is erected. Each mega pillar 11 has a core wall structure mainly made of reinforced concrete, for example, having a rectangular shape in cross section that is continuous in the vertical direction, and accommodates, for example, elevators, various facilities, machine rooms, and the like. ing. The frame 12 of the building 10 supported by the mega pillars 11, 11,... Has a reference layer frame 13, which is the lowermost portion thereof, provided at a height corresponding to, for example, four floors above ground.
A large space 14 is formed below the large space 14. The reference layer frame 13 is provided, for example, between an upper chord member 13a and a lower chord member 13b which are arranged at a height of two floors.
It has a truss structure in which the column member 13c and the lattice member 13d are combined. Similarly, the uppermost frame 15 constituting the uppermost portion of the frame 12 has a height of, for example, two floors.
A truss structure in which a column member 15c and a lattice member 15d are combined between the upper chord material 15a and the lower chord material 15b. The reference layer frame 13 and the uppermost layer frame 15
In between, the intermediate layer skeleton 16 constituting each intermediate floor of the skeleton 12 is, for example, a steel frame, and usually includes columns 17 erected at regular intervals and beams 18 erected for each floor. It has a ramen structure. The above reinforced concrete mega column 1
1, a rigid megastructure (peripheral frame) 20 is composed of the reference layer frame 13 and the uppermost layer frame 15 of the steel frame truss structure. The frame 12 of the building 10 has an intermediate structure inside the megastructure 20. It has a configuration in which the layer frames 16 are arranged. Next, a method of constructing such a building 10 will be described with reference to FIGS. First, as shown in FIG. 2, mega pillars 11, 11,...
To build. After the construction work of these mega pillars 11 has progressed at least to the height above the height at which the reference layer frame 13 is to be built, the reference layer frame 13 is built at a predetermined height and Are joined to the columns 11, 11,... After the construction of the reference layer frame 13 is completed,
The construction work of each mega pillar 11 and the construction work of the intermediate layer frame 16 on the reference layer frame 13 proceed in parallel. Thus, the lower layer 1 of the intermediate layer frame 16 is formed.
When the predetermined floor F of the intermediate layer frame 16 is constructed by stacking and constructing the floor members 6a, the column member 17a constituting the floor F and the column member constituting the immediately lower floor F 'which has already been constructed are completed. 17′a is not joined. Then, after the assembly of the floor F is completed, as shown in FIG.
For example, jack mechanisms 22, 22 such as hydraulic jacks are interposed between 1 and the beam 18 on the lower floor F '. Then
The jack mechanisms 22 are extended at the same time so that the column members 17a and 17'a positioned above and below each other are separated by a predetermined dimension δ. Thereafter, as shown in FIG. 2, the construction of the mega pillar 11 and the construction of the upper layer portion 16b of the intermediate layer frame 16 are continued in the same manner as usual, and these are constructed up to the top. You. The uppermost frame 1 is placed on the intermediate layer 16.
The uppermost building 15 is joined to each of the mega pillars 11 and the intermediate building 16. At this point, the jack mechanisms 22, 22,...
The load on the lower portion 16a below the floor F where
It is supported by the reference layer frame 13. On the other hand, the load on the upper layer portion 16b above the floor F is also supported by the uppermost layer frame 15, but the jack mechanism 2
Are supported by the reference layer frame 13 via the lower layer portion 16a. Thereafter, all the jack mechanisms 22 are simultaneously contracted to lower the jacks. At this time, the initial separation dimension δ (see FIG. 3) of the column members 17a and 17′a before jack-down is reduced when the amount of flexing downward of the reference layer body 13 is reduced due to a decrease in the load at jack-down. , The separation dimension δ ′ of which is the upper and lower column members 17a, 17′a
Are set to be a root gap for welding to each other. That is, the pillar members 17 located at the top and bottom
a and 17'a are separated from each other by the distance δ 'without contact even after the jack-down. Then, the load on the lower portion 16a below the floor F on which these jack mechanisms 22 are installed is still supported by the reference layer frame 13, but the load on the upper portion 16b is The state is supported only by the uppermost frame 15. Therefore, as compared with the state before jack-down, the load supported by the reference layer frame 13 is reduced by the upper layer portion 16b, and the stress is released by that amount. After the jack-down is completed, the joints of the column members 17a and 17'a are welded and joined at this floor F. Thus, the construction of the frame 12 of the building 10 shown in FIG. 1 is completed. Thereafter, the lower layer portion 16 below the floor F on which the jack mechanism 22 is installed will be described.
a is supported by the reference layer frame 13 and the upper layer 1
The state where the load of 6b is supported by the uppermost frame 15 is maintained. In the construction method of the building 10 described above, the intermediate layer frame 16 is constructed on the reference layer frame 13, and when the intermediate layer frame 16 of the predetermined floor F is constructed, the floor F
Of each of the pillar members 17a and the pillar member 17'a of the immediately lower floor F 'previously constructed without joining the jack mechanism 2 between them.
After the upper layer 16b and the uppermost frame 15 are erected, the jack mechanism 22,
, Are removed, and the column members 17 located above and below are removed.
a, 17'a were welded and joined. Thus, after completion of the building 10, the load of the lower layer 16a below the floor F on which the jack mechanism 22 is installed is supported by the reference layer frame 13, and the load of the upper layer 16b is supported by the upper layer frame 15. Will be. In this way, the load of the intermediate layer frame 16 is shared and supported by the reference layer frame 13 and the uppermost layer frame 15 of the truss structure, respectively, so that the cross-sectional dimension of each member constituting the reference layer frame 13 is particularly reduced. And this can be economical. Further, when designing the reference layer frame 13 of the building 10, it is possible to support the load of the entire intermediate layer frame 16 during construction, and after completion, the lower layer 16a below the floor F on which the jack mechanism 22 is installed is completed. What is necessary is just to design so that it can support the said load. In addition, comparing the work in progress and after the work is completed, the load to be supported is drastically reduced, and the remaining stress is greatly reduced, so that the design can be simplified. Moreover, at least a part of the strength against the stress caused by the horizontal movement and the vertical movement of the earthquake can be secured by the reduced stress, so that the frame structure of the building 10 can be made economical also from this point. Moreover, the jack mechanisms 22, 22,...
When jacking up the column member 17a, the column member 17
a, 17'a is set in advance so that the spacing δ 'after jack-down becomes the root gap of welding, so that the welding work of the column members 17a, 17'a can be performed easily and reliably. Can be done. In the above embodiment , the floor F on which the jack mechanism 22 is installed is not limited.
For example, the lowest floor of the intermediate layer frame 16, that is, the reference layer frame 1
3 or another floor such as the top floor of the intermediate building 16. For example, jack mechanism 2
In the case where the floor F on which the second floor 2 is installed is the lowest floor of the intermediate layer frame 16, the load supported by the reference layer frame 16 was all loads above the reference layer frame 16 at the time of jacking up. After the jack-down, the load is drastically reduced only to the load of the reference layer frame 16 itself. Then, even if the load due to the finishing material, the stress due to the load of the equipment loaded on the standard floor, and the stress due to the horizontal and vertical movements of itself are combined, most or all of them are covered by the reduced load capacity. It is also possible to design very easily. In the above embodiment , the reference layer frame 1
3. The uppermost frame 15 is configured to have a height of, for example, two floors. However, if a truss structure is used, it is needless to say that the height is one floor or three or more floors. Needless to say, the configuration may be provided. The mega pillar 11 of the building 10 to be constructed,
Are arranged at regular intervals on both sides of the building 10, but the arrangement is not limited. For example, a configuration in which these are arranged only at the four corners, a configuration in which the entire both side surfaces of the building 10 are configured as mega columns, and a configuration in which mega columns are disposed at appropriate intervals over the entire outer peripheral portion may be employed. Good. In addition, although the tube-shaped mega pillar 11 having a rectangular cross section is made of a reinforced concrete structure, it may be made of a steel reinforced concrete structure, a steel tube structure, a filled steel tube concrete structure, or the like, or a steel frame formed in a tube shape. A three-dimensional truss structure or the like may be used. Further, when the reference layer frame 13 is located above a certain dimension,
That is, as long as the floor is located in the air, the set floor number is not limited. Further, not only when the building 10 has a basement floor, for example,
Even in a case where a reference floor is located at the fifth floor above the ground in a building having a three-story portion from the first floor, the above-described construction method can be similarly applied, and the same effects as above can be obtained. Furthermore, the execution timing of the floor concrete or the PC slab plate to be cast on each floor may be appropriately determined in consideration of the balance of the load to be supported by the reference layer frame 13 during and after the construction. As described above, according to the method for constructing a frame structure according to the first aspect, the reference layer skeleton and the uppermost layer skeleton are joined to the core pillar, and the reference layer skeleton is interposed between the core columns. After supporting the load of the lower layer of the layered structure and supporting the load of the upper layer of the intermediate layered structure with the uppermost layered structure, the upper layer and the lower layer of the intermediate layered structure are finally joined. , Special
Then, the lower column member and the upper column member of the intermediate layer frame are connected to each other.
It is a predetermined size with a jack interposed between them without joining
Separate the upper part of the intermediate layer structure into the uppermost layer structure.
After joining, jack down the upper part, and both pillars
The gap between the materials is the root gap for welding them.
So that the column members are
It was configured to be welded and joined. As a result, not only during construction but also after the upper and lower layers of the intermediate structure are joined, the load of the lower layer of the intermediate structure is supported by the reference structure and the load of the upper structure is minimized. The state supported by the upper frame can be maintained. In this way, the load of the intermediate layer skeleton is shared and supported by the reference layer skeleton of the truss structure and the uppermost layer skeleton, respectively, so that the cross-sectional dimensions of each member constituting the reference layer skeleton can be particularly reduced. And this can be economical. In addition, when the construction is completed and after completion, the load to be supported is drastically reduced, and the remaining stress is greatly reduced, so that the design can be simplified. In addition, at least a part of the strength against the stress caused by the horizontal and vertical motions of the earthquake can be secured by the reduced stress, so that the frame structure of the frame structure can be made economical from this point as well.

【図面の簡単な説明】 【図1】本発明に係る架構構造物の施工方法を適用して
構築するビルの一例を示す図であって、(a)正面図、
(b)側面図である。 【図2】本発明に係る架構構造物の施工方法の実施例
示す図であって、前記施工方法を適用して構築中のビル
を示す正面図である。 【図3】前記ビルの要部を示す正面図である。 【図4】従来の架構構造物の施工方法を適用して構築し
たビルの一例を示す立面図である。 【符号の説明】 10 ビル(架構構造物) 11 メガ柱(コア柱) 13 基準層躯体 15 最上層躯体 16 中間層躯体 16a,16d,16e 下層部 16b,16c,16f 上層部 17a,17’a 柱部材 20 メガストラクチャー(外周フレーム) 22 ジャッキ
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a view showing an example of a building constructed by applying a method of constructing a frame structure according to the present invention, wherein (a) is a front view,
(B) It is a side view. FIG. 2 is a view showing an embodiment of a method for constructing a frame structure according to the present invention, and is a front view showing a building being constructed by applying the construction method. FIG. 3 is a front view showing a main part of the building. FIG. 4 is an elevation view showing an example of a building constructed by applying a conventional method of constructing a frame structure. [Description of Signs] 10 Building (frame structure) 11 Mega pillar (core pillar) 13 Reference layer frame 15 Top layer frame 16 Intermediate layer frame 16a, 16d, 16e Lower layers 16b, 16c, 16f Upper layers 17a, 17'a Column member 20 Mega structure (peripheral frame) 22 Jack

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平4−153460(JP,A) 特開 平5−248009(JP,A) 特開 平6−322827(JP,A) 特開 平7−26726(JP,A) (58)調査した分野(Int.Cl.7,DB名) E04B 1/35 E04G 21/14 ────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-4-153460 (JP, A) JP-A-5-248009 (JP, A) JP-A-6-322827 (JP, A) JP-A-7- 26726 (JP, A) (58) Field surveyed (Int. Cl. 7 , DB name) E04B 1/35 E04G 21/14

Claims (1)

(57)【特許請求の範囲】 【請求項1】 外周部に立設されたコア柱と、地表面か
ら一定寸法上方に設けられたトラス構造の基準層躯体
と、トラス構造の最上層躯体とから外周フレームが構成
され、該外周フレームの前記基準層躯体と最上層躯体と
の間に中間層躯体が設けられた構成からなる架構構造物
を施工するに際し、 前記中間層躯体を上層部と下層部とに区分しておき、前
記基準層躯体と最上層躯体とをそれぞれ定められた高さ
において前記コア柱に接合するとともに、前記基準層躯
体で前記中間層躯体の下層部の荷重を支持し、前記最上
層躯体で前記中間層躯体の上層部の荷重を支持した状態
とし、 しかる後に、前記中間層躯体の上層部と下層部とを接合
する構成とした架構構造物の施工方法であって、 まず前記コア柱を所定の高さまで構築した時点で、基準
層躯体を定められた高さに建方した後、コア柱の構築
と、前記基準層躯体上への中間層躯体の建方とを行って
いき、前記中間層躯体の下層部を建方した後、中間層躯体の上
層部を建方するときに、下層部の柱部材と上層部の柱部
材とを接合せずにそれらの間にジャッキを介装して双方
の柱部材を上下方向に所定寸法だけ離間させておき、 前記中間層躯体の最上階までの建方が完了した後に、前
記最上層躯体を建方して、該最上層躯体と前記中間層躯
の上層部とを接合した後、前記ジャッキを操作して中間層躯体の上層部をジャッキ
ダウンすることにより、上層部の柱部材と下層部の柱部
材との間の離間寸法をそれらを溶接するためのルートギ
ャップとなるようにし、その状態でそれら柱部材どうし
を溶接して接合する ことを特徴とする架構構造物の施工
方法。
(57) [Claims] [Claim 1] A core pillar erected on an outer peripheral portion, a reference truss structure of a truss structure provided a certain dimension above the ground surface, and a top truss structure of a truss structure A frame structure having a configuration in which an intermediate frame is provided between the reference layer frame and the uppermost frame of the outer frame.
When constructing, the intermediate layer skeleton is divided into an upper layer and a lower layer, and the reference layer skeleton and the uppermost layer skeleton are joined to the core pillars at predetermined heights, respectively, and the reference layer The frame supports the lower layer load of the intermediate layer frame, and the uppermost layer frame supports the upper layer load of the intermediate layer frame. Thereafter, the upper layer and the lower layer of the intermediate layer frame are It is a construction method of a frame structure having a configuration to be joined, at the time when the core column is first constructed to a predetermined height, after constructing a reference layer frame at a predetermined height, and constructing a core column, will conduct and erection of the intermediate layer precursor to the reference layer precursor on, after erection of the lower portion of the intermediate layer skeleton, on the intermediate layer precursor
When constructing the layer, the lower column member and the upper column member
Without connecting the material and jacks between them
Are separated by a predetermined dimension in the vertical direction, and after the construction up to the top floor of the intermediate building is completed, the top building is constructed and the top building and the middle building are constructed. After joining with the upper layer , the jack is operated to jack the upper layer of the intermediate layer frame.
By going down, the upper column member and the lower column member
The distance between the material and the root
So that the column members
A method of constructing a framed structure, characterized by welding and joining .
JP07914595A 1995-04-04 1995-04-04 Construction method of frame structure Expired - Fee Related JP3413584B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP07914595A JP3413584B2 (en) 1995-04-04 1995-04-04 Construction method of frame structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP07914595A JP3413584B2 (en) 1995-04-04 1995-04-04 Construction method of frame structure

Publications (2)

Publication Number Publication Date
JPH08270081A JPH08270081A (en) 1996-10-15
JP3413584B2 true JP3413584B2 (en) 2003-06-03

Family

ID=13681801

Family Applications (1)

Application Number Title Priority Date Filing Date
JP07914595A Expired - Fee Related JP3413584B2 (en) 1995-04-04 1995-04-04 Construction method of frame structure

Country Status (1)

Country Link
JP (1) JP3413584B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3755117B2 (en) * 1996-11-29 2006-03-15 株式会社竹中工務店 Construction method of multi-layer structure with multiple super beams
JP3932112B2 (en) * 2002-05-31 2007-06-20 東日本旅客鉄道株式会社 Jackdown method for steel building
JP5737578B2 (en) * 2011-06-15 2015-06-17 清水建設株式会社 Construction method of suspended structure
JP6944776B2 (en) * 2016-11-02 2021-10-06 株式会社竹中工務店 Repair method
JP7041463B2 (en) * 2016-12-16 2022-03-24 大成建設株式会社 How to build a building
JP6917720B2 (en) * 2017-01-30 2021-08-11 大成建設株式会社 How to build a composite suspended structure

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2916591B2 (en) * 1990-10-17 1999-07-05 三菱重工業株式会社 Building construction method and device
JPH05248009A (en) * 1992-03-05 1993-09-24 Shimizu Corp Lift up method for framed girder
JPH06322827A (en) * 1993-05-11 1994-11-22 Shimizu Corp Super rigid-frame frame construction, and its constructing method
JP2576035B2 (en) * 1993-05-14 1997-01-29 三菱重工業株式会社 Zone module construction method for steel structure construction

Also Published As

Publication number Publication date
JPH08270081A (en) 1996-10-15

Similar Documents

Publication Publication Date Title
US7444793B2 (en) Method of constructing a concrete shear core multistory building
JPH02243845A (en) Stereo skelton structure and constituting method thereof
JP3413584B2 (en) Construction method of frame structure
JPH10159344A (en) Building method of multi-layered structure provided with a plurality of super beam
JP7169765B2 (en) How to build structures
JPH04323435A (en) Assembling type construction
JP2009013592A (en) Frame assembling method and frame of building
JPS6314937A (en) Reinforcing bar composite pillar
JP3040309B2 (en) Construction method of multi-layer suspension structure
JPH074049A (en) Construction method of building
JPH0468140A (en) Construction of beam
JPH06136990A (en) Base isolation structure
JP2527975B2 (en) Building structure
JP2916585B2 (en) Construction method of building
JP2860499B2 (en) Skip floor type building
JPH0657769A (en) Underground concrete structure and working method thereof
JP2007284950A (en) Variable story height type structure and its constructing method
JP3721482B2 (en) Seismic reinforcement method and structure for existing buildings
JPH0711160B2 (en) Construction method of frame in steel building
JPH07279247A (en) Skeleton of building consisting of concrete core wall and structural steel frame
JP3880341B2 (en) Construction method of steel plate concrete structure
JPH0893049A (en) Framework of building structure
JPS6156735B2 (en)
JPS6286270A (en) Slab construction method
JP2998572B2 (en) Building structural frame

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20030212

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100404

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110404

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120404

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees