JP2009013592A - Frame assembling method and frame of building - Google Patents

Frame assembling method and frame of building Download PDF

Info

Publication number
JP2009013592A
JP2009013592A JP2007173337A JP2007173337A JP2009013592A JP 2009013592 A JP2009013592 A JP 2009013592A JP 2007173337 A JP2007173337 A JP 2007173337A JP 2007173337 A JP2007173337 A JP 2007173337A JP 2009013592 A JP2009013592 A JP 2009013592A
Authority
JP
Japan
Prior art keywords
column
frame
building
steel
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2007173337A
Other languages
Japanese (ja)
Other versions
JP4996370B2 (en
Inventor
Makoto Kayashima
誠 萱嶋
Masanori Misawa
政範 三沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2007173337A priority Critical patent/JP4996370B2/en
Publication of JP2009013592A publication Critical patent/JP2009013592A/en
Application granted granted Critical
Publication of JP4996370B2 publication Critical patent/JP4996370B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a frame assembling method, reducing the term of work by adopting a vertically divided method even in the case of a building using columns of reinforced concrete construction. <P>SOLUTION: According to this frame assembling method, a frame of a building having the column of reinforced concrete construction and a beam of steel construction is assembled. In this frame assembling method, the frame includes a column unit 10 provided with a beam joint 14, and a beam member joined to the beam joint 14 of the column unit 10. The column unit 10 includes a temporary column 11, a column bar 12 supported on the temporary column 11, and a cylindrical sheath tube 13, which is provided on the temporary column 11, to which the beam joint 14 is joined, and through which the column bar 12 is passed. The frame of the building is divided into three work sections A, B, C in a plan view, the column unit 10 is field-preassembled in every work section, these column units 10 and beam members are lifted using a crawler crane to perform erection of framing up to the top floor, and such erection of framing is sequentially repeated by each adjacent work section to construct the frame. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、架構組立方法および建物の架構に関する。詳しくは、鉄筋コンクリート造の柱と鉄骨造の梁とを有する建物の架構を組み立てる架構組立方法およびこの建物の架構に関する。   The present invention relates to a frame assembling method and a building frame. Specifically, the present invention relates to a frame assembling method for assembling a frame of a building having reinforced concrete columns and steel beams and a frame of the building.

従来より、鉄骨造(S造)や鉄骨鉄筋コンクリート造(SRC造)の建物の架構を、建て逃げ工法(屏風立て工法とも呼ぶ)により組み立てることが行われている(特許文献1参照)。
建て逃げ工法では、まず、建物の架構を平面視で複数の工区に分割する。そして、工区ごとに、揚重機を用いて鉄骨柱および鉄骨梁を揚重し、最上階までの建方を行う。
この建方作業を、揚重機の動線の奥側から手前側に向かって揚重機を移動しながら繰り返すことで、動線確保のための後施工部分が生じるのを防止する。
2. Description of the Related Art Conventionally, a steel frame (S structure) or steel reinforced concrete (SRC structure) building frame is assembled by a construction escape method (also referred to as a folding wind method) (see Patent Document 1).
In the building escape method, the building frame is first divided into a plurality of work zones in plan view. For each work area, the steel columns and steel beams are lifted using a lifting machine, and the construction up to the top floor is performed.
This construction work is repeated while moving the lifting machine from the back side to the near side of the flow line of the lifting machine, thereby preventing the occurrence of a post-construction part for securing the flow line.

この建て逃げ工法によれば、中低層のショッピングセンタ、工場、倉庫、事務所など、平面的な広がりのある建物では、1フロア毎に躯体を構築する作業を繰り返す積層工法に比べて、工期の短縮を図ることができる。
特開2001−311312号公報
According to this built-in escape method, compared to the layered method that repeats the work of constructing the frame for each floor in buildings with two-dimensional spread, such as shopping centers, factories, warehouses, and offices in the middle and low rise, Shortening can be achieved.
JP 2001-311312 A

しかしながら、近年、鉄骨の材料費が上昇しており、鉄骨造や鉄骨鉄筋コンクリート造の建物について、鉄骨量を軽減して、コストの上昇を抑制することが要請されている。そこで、梁を鉄骨とし、柱を鉄筋コンクリート造(RC造)とした複合構造が提案されている。   However, in recent years, the material cost of steel frames has increased, and there is a demand for reducing the amount of steel frames and suppressing the increase in costs for steel structures and steel reinforced concrete buildings. Therefore, a composite structure in which the beam is a steel frame and the column is a reinforced concrete structure (RC structure) has been proposed.

柱を鉄筋コンクリート造とすると、柱のコンクリートを打設した後、養生期間が必要となり、短期間で架構を最上階まで完成させることができない。そのため、建て逃げ工法を採用できず、揚重機の動線となる後施工部分を計画して、下階から上階に向かって順番にコンクリートを打設していくことになる。その結果、後施工部分に係る架構を施工するまで、設備配管工事や仕上げ工事に着手できず、工期を短縮することが困難になる。   If the pillar is made of reinforced concrete, a curing period is required after placing the concrete of the pillar, and the frame cannot be completed to the top floor in a short period of time. Therefore, the built-up escape method cannot be adopted, and the post-construction part that becomes the flow line of the lifting machine is planned, and concrete is placed in order from the lower floor to the upper floor. As a result, until the construction related to the post-construction part is constructed, the equipment piping work and the finishing work cannot be started, and it becomes difficult to shorten the construction period.

本発明は、柱が鉄筋コンクリート造の建物であっても、建て逃げ工法を採用して、工期を短縮できる架構組立方法および建物の架構を提供することを目的とする。   An object of the present invention is to provide a frame assembling method and a building frame that can shorten the construction period by adopting a built-in escape method even if the column is a reinforced concrete building.

請求項1に記載の架構組立方法は、鉄筋コンクリート造の柱(例えば、後述の柱2)と鉄骨造の梁(例えば、後述の梁4)とを有する建物(例えば、後述の建物1)の架構を組み立てる架構組立方法であって、前記架構を、梁継手(例えば、後述の梁継手14)が設けられた柱ユニット(例えば、後述の柱ユニット10)と、当該柱ユニットの梁継手に接合される梁部材(例えば、後述の梁部材20)と、を含んで構成し、前記柱ユニットを、鉄骨柱(例えば、後述の仮設柱11)と、当該鉄骨柱に支持される柱筋(例えば、後述の柱筋12)と、前記鉄骨柱に設けられて前記梁継手が接合されかつ前記柱筋が挿通される筒状の鞘管(例えば、後述の鞘管13)と、を含んで構成し、揚重機(例えば、後述のクローラークレーン50)を用いて、地組みした前記柱ユニットおよび前記梁部材を揚重して最上階まで建方作業を行い、当該建方作業を隣接する工区ごとに順次繰り返しながら、前記架構を組み立てることを特徴とする。   The frame assembling method according to claim 1 is a structure of a building (for example, a building 1 described later) having a reinforced concrete column (for example, column 2 described later) and a steel beam (for example, beam 4 described later). The frame is joined to a column unit (for example, a column unit 10 to be described later) provided with a beam joint (for example, a beam joint 14 to be described later) and a beam joint of the column unit. A beam member (e.g., a beam member 20 described later), and the column unit includes a steel column (e.g., a temporary column 11 described later) and a column reinforcement (e.g., supported by the steel column). And a cylindrical sheath tube (for example, a sheath tube 13 to be described later) provided on the steel column, to which the beam joint is joined and through which the column reinforcement is inserted. , Using a lifting machine (for example, a crawler crane 50 described later) Performs erection work top floor with Agekasane the column unit and the beam member and Chikumi, while sequentially repeated for each work area adjacent the erection work, characterized in that assembling the Frame.

請求項1に記載の発明によれば、鉄骨柱を用意し、この鉄骨柱に柱筋を支持させる。さらに、鉄骨柱に筒状の鞘管を設け、この鞘管に、柱筋を挿通するとともに梁継手を接合して、柱ユニットとする。そして、建て逃げ工法により、この柱ユニットおよび梁部材の建方を行う。
よって、柱が鉄筋コンクリート造の建物であっても、建て逃げ工法を採用できるから、工期を短縮できる。また、仮設柱に用いられる鉄骨量は、鉄骨造や鉄骨鉄筋コンクリート造の柱に用いられる鉄骨量よりも少なくなるため、コストの上昇を抑えることができる。
According to the first aspect of the present invention, a steel column is prepared, and column bars are supported by the steel column. Furthermore, a cylindrical sheath tube is provided on the steel column, and a column bar is inserted into the sheath tube and a beam joint is joined to form a column unit. Then, the pillar unit and the beam member are erected by the erection method.
Therefore, even if the pillar is a reinforced concrete building, the construction escape method can be adopted, so the construction period can be shortened. Moreover, since the amount of steel frames used for temporary columns is less than the amount of steel frames used for steel frames and steel-framed reinforced concrete columns, an increase in cost can be suppressed.

請求項2に記載の建物の架構は、鉄筋コンクリート造の柱と鉄骨造の梁とを有する建物の架構であって、前記架構は、梁継手が設けられた柱ユニットと、当該柱ユニットの梁継手に接合される梁部材と、を有し、前記柱ユニットは、鉄骨柱と、当該鉄骨柱に支持される柱筋と、前記鉄骨柱に設けられて前記梁継手が接合されかつ前記柱筋が挿通される筒状の鞘管と、を有し、前記鞘管は、プレート(例えば、後述の下部補強プレート136)を介して前記鉄骨柱に支持されることを特徴とする。   The building frame according to claim 2 is a building frame having a reinforced concrete column and a steel beam, and the frame includes a column unit provided with a beam joint, and a beam joint of the column unit. The column unit includes a steel column, a column bar supported by the steel column, the beam joint provided to the steel column and the column unit being connected to the column member. And a cylindrical sheath tube to be inserted, and the sheath tube is supported by the steel column via a plate (for example, a lower reinforcing plate 136 described later).

本発明によれば、鉄骨柱を用意し、この鉄骨柱に柱筋を支持させる。さらに、鉄骨柱に筒状の鞘管を設け、この鞘管に、柱筋を挿通するとともに梁継手を接合して、柱ユニットとする。そして、建て逃げ工法により、この柱ユニットおよび梁部材の建方を行う。よって、柱が鉄筋コンクリート造の建物であっても、建て逃げ工法を採用できるから、工期を短縮できる。また、仮設柱に用いられる鉄骨量は、鉄骨造や鉄骨鉄筋コンクリート造の柱に用いられる鉄骨量よりも少なくなるため、コストの上昇を抑えることができる。   According to the present invention, a steel column is prepared, and column bars are supported by the steel column. Furthermore, a cylindrical sheath tube is provided on the steel column, and a column bar is inserted into the sheath tube and a beam joint is joined to form a column unit. Then, the pillar unit and the beam member are erected by the erection method. Therefore, even if the pillar is a reinforced concrete building, the construction escape method can be adopted, so the construction period can be shortened. Moreover, since the amount of steel frames used for temporary columns is less than the amount of steel frames used for steel frames and steel-framed reinforced concrete columns, an increase in cost can be suppressed.

以下、本発明の一実施形態を図面に基づいて説明する。
図1は、本発明の一実施形態に係る架構組立方法が適用された建物1の架構の一部を示す側面図である。
Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
FIG. 1 is a side view showing a part of a frame of a building 1 to which a frame assembly method according to an embodiment of the present invention is applied.

建物1は、ショッピングセンタであり、1階から3階までは店舗、4階および5階は駐車場である。この建物の1階から3階までの柱2は、鉄骨の仮設柱が内蔵された鉄筋コンクリート造であり、4階および5階の柱3は、鉄骨造である。また、全ての梁4は、鉄骨造である。2階からR階までの床5は、鉄骨梁4にデッキプレートを敷設してコンクリート打設することで形成されている。   Building 1 is a shopping center, from 1st floor to 3rd floor is a store, 4th floor and 5th floor are parking lots. The pillars 2 from the first floor to the third floor of this building are reinforced concrete with a built-in steel temporary pillar, and the pillars 3 on the fourth and fifth floors are steel. Moreover, all the beams 4 are steel structures. The floor 5 from the second floor to the R floor is formed by laying a deck plate on the steel beam 4 and placing the concrete.

図2は、建物1の架構の一部の鉄骨図である。
建物1の1階から3階までの鉄骨は、梁継手14が設けられた柱ユニット10と、この柱ユニット10の梁継手14に接合される鉄骨の梁部材20と、を含んで構成される。
ここで、柱ユニット10は、図2に示すように、1階床レベルから2階立ち上がりまでの1層分の高さを有する第1節柱ユニット10Aと、2階立ち上がりから4階立ち上がりまでの2層分の高さを有する第2節柱ユニット10Bと、から構成される。
また、この建物1の4階および5階の鉄骨は、4階立ち上がりからR階床レベルまでの鉄骨の柱部材30と、この柱部材30に接合される鉄骨の梁部材40と、を含んで構成される。
FIG. 2 is a steel frame diagram of a part of the frame of the building 1.
The steel frame from the first floor to the third floor of the building 1 includes a column unit 10 provided with a beam joint 14 and a steel beam member 20 joined to the beam joint 14 of the column unit 10. .
Here, as shown in FIG. 2, the pillar unit 10 includes a first node pillar unit 10A having a height of one layer from the first floor level to the second floor rise, and from the second floor rise to the fourth floor rise. And a second node unit 10B having a height of two layers.
Further, the steel frames of the fourth floor and the fifth floor of the building 1 include a steel column member 30 from the 4th floor rising to the R floor level, and a steel beam member 40 joined to the column member 30. Composed.

図3は、柱ユニット10の平断面図である。図4および図5は、柱ユニット10の側面図である。
柱ユニット10は、上下方向に延びる鉄骨柱としての仮設柱11と、水平方向に延びる4つの梁継手14と、この仮設柱11に支持される柱筋12と、仮設柱11に設けられて梁継手14が接合されかつ柱筋12が挿通される筒状の鞘管13と、を備える。
FIG. 3 is a plan sectional view of the column unit 10. 4 and 5 are side views of the column unit 10.
The column unit 10 is provided with a temporary column 11 as a steel column extending in the vertical direction, four beam joints 14 extending in the horizontal direction, column bars 12 supported by the temporary column 11, and a beam provided on the temporary column 11. And a tubular sheath tube 13 into which the joint 14 is joined and the column bar 12 is inserted.

柱筋12は、12本の柱主筋121と、この柱主筋121の延出方向に沿って所定間隔おきに巻き回された複数の帯筋122と、を備える。
柱主筋121は、建物1の柱の角部に3本ずつ配置される。
The column reinforcement 12 includes twelve column reinforcements 121 and a plurality of strip reinforcements 122 wound at predetermined intervals along the extending direction of the column reinforcements 121.
Three column main bars 121 are arranged at each corner of the column of the building 1.

仮設柱11は、H鋼であり、下仮設柱111と、下仮設柱111にプレート114を介してボルト接合された中間仮設柱112と、中間仮設柱112にプレート115を介してボルト接合された上仮設柱113と、を備える。   Temporary column 11 is H steel, lower temporary column 111, intermediate temporary column 112 bolted to lower temporary column 111 via plate 114, and bolted to intermediate temporary column 112 via plate 115. And an upper temporary pillar 113.

これら仮設柱11のフランジ面には、柱主筋121を支持するアングル材である鉄筋支持部材(図示省略)が溶接されている。柱の角部に配置される3本の柱主筋121を、鉄筋支持部材を挟んで配筋することにより、仮設柱11は、鉄筋支持部材を介して柱主筋121を支持する。   Reinforcing bar support members (not shown) that are angle members for supporting the column main bars 121 are welded to the flange surfaces of the temporary columns 11. The temporary column 11 supports the column main bar 121 via the reinforcing bar support member by arranging the three column main bars 121 arranged at the corners of the column with the reinforcing bar support member interposed therebetween.

鞘管13は、上下方向に延びる略四角筒状の筒部131と、この筒部131の上下端面を塞ぐ下ダイアフラム132および上ダイアフラム133と、を備える。   The sheath tube 13 includes a cylindrical portion 131 having a substantially square cylindrical shape extending in the vertical direction, and a lower diaphragm 132 and an upper diaphragm 133 that block the upper and lower end surfaces of the cylindrical portion 131.

2つのダイアフラム132、133の中央には、略円形のコンクリート充填孔134が形成される。このコンクリート充填孔134には、中間仮設柱112が挿通され、これにより、この中間仮設柱112は、鞘管13の上下に露出している。   A substantially circular concrete filling hole 134 is formed at the center of the two diaphragms 132 and 133. The intermediate temporary pillar 112 is inserted into the concrete filling hole 134, and thereby the intermediate temporary pillar 112 is exposed above and below the sheath tube 13.

中間仮設柱112は、振れ止め135により上ダイアフラム133に固定されるとともに、下部補強プレート136により下ダイアフラム132に固定される。振れ止め135は、アングル材であり、一方の面は上ダイアフラム133に3周で溶接され、他方の面は中間仮設柱112にボルト接合される。また、下部補強プレート136は、一端側で下ダイアフラム132に溶接され、他端側で中間仮設柱112に溶接される。   The intermediate temporary column 112 is fixed to the upper diaphragm 133 by the steady rest 135 and is fixed to the lower diaphragm 132 by the lower reinforcing plate 136. The steady rest 135 is an angle member, one surface is welded to the upper diaphragm 133 in three rounds, and the other surface is bolted to the intermediate temporary column 112. The lower reinforcing plate 136 is welded to the lower diaphragm 132 on one end side and is welded to the intermediate temporary column 112 on the other end side.

また、2つのダイアフラム132、133の4隅には、柱主筋121が挿通される柱筋貫通孔137が形成される。この柱筋貫通孔137は、柱主筋121が鞘管13の筒部131の内側を通るような位置に形成される。   Also, column reinforcement through holes 137 through which the column main reinforcement 121 is inserted are formed at the four corners of the two diaphragms 132 and 133. This columnar through hole 137 is formed at a position where the column main reinforcement 121 passes through the inside of the cylindrical portion 131 of the sheath tube 13.

梁継手14は、H鋼であり、下ダイアフラム132に溶接された下フランジ141と、筒部131の外周面に溶接されたウエブ142と、上ダイアフラムに溶接された上フランジ143と、を備える。   The beam joint 14 is H steel, and includes a lower flange 141 welded to the lower diaphragm 132, a web 142 welded to the outer peripheral surface of the cylindrical portion 131, and an upper flange 143 welded to the upper diaphragm.

次に、以上の柱ユニット10を製作する手順について、図6(a)および図6(b)を参照しながら説明する。
柱ユニット製作ヤードには、一対の架台6が設けられている。
仮設柱11、鞘管13、梁継手14は、鉄骨製作工場で柱ピース7として組み立てられ、この柱ピース7は、トレーラなどで建築現場に搬入される。柱ピース7は、架台6の上に寝かせた状態で載置され、この状態で柱筋12を配筋し、さらに、溶接またはボルト締めを行うための溶接足場8を取り付ける。また、柱筋12の柱主筋121の下端には、柱主筋121を接続するための鉄筋スリーブ9を取り付ける。
Next, a procedure for manufacturing the above column unit 10 will be described with reference to FIGS. 6 (a) and 6 (b).
A pair of mounts 6 are provided in the column unit production yard.
The temporary column 11, the sheath tube 13, and the beam joint 14 are assembled as a column piece 7 in a steel frame manufacturing factory, and this column piece 7 is carried into a building site by a trailer or the like. The column piece 7 is placed on the gantry 6 in a state of being laid, and in this state, the column reinforcement 12 is arranged, and a welding scaffold 8 for performing welding or bolting is attached. Further, a reinforcing bar sleeve 9 for connecting the column main bar 121 is attached to the lower end of the column main bar 121 of the column bar 12.

次に、建物1の建方作業の手順について、図7を参照しながら説明する。
まず、建物の架構を平面視で複数の工区に分割する。ここでは、3スパンずつ、A工区、B工区、C工区に分割する。
まず、図7に示すように、A工区について、柱ユニット10を地組みし、揚重機としてのクローラークレーン50を用いて柱ユニット10、柱部材30、梁部材20、40を揚重して、最上階まで建方作業を行う。
この建方作業を、クローラークレーン50の動線の奥側のA工区から、手前側のC工区に向かって、隣接する工区ごとに繰り返す。
Next, the procedure of the building work of the building 1 will be described with reference to FIG.
First, the building frame is divided into a plurality of work zones in plan view. Here, it is divided into A zone, B zone, and C zone in increments of 3 spans.
First, as shown in FIG. 7, for the A section, the column unit 10 is assembled, and the column unit 10, the column member 30, the beam members 20 and 40 are lifted using a crawler crane 50 as a lifting machine, Perform construction work up to the top floor.
This construction work is repeated for each adjacent work section from the A section on the back side of the flow line of the crawler crane 50 toward the C section on the near side.

次に、建物1の工区毎の施工手順を、図8〜図10を参照しながら説明する。
まず、図8(a)に示すように、第1節柱ユニット10Aの建方を行う。具体的には、クローラークレーンで第1節柱ユニット10Aを吊り上げて、この第1節柱ユニット10Aを図示しないアンカーボルトで1階床に固定し、控えワイヤを張る。
Next, the construction procedure for each work area of the building 1 will be described with reference to FIGS.
First, as shown in FIG. 8 (a), the first node unit 10A is erected. Specifically, the first knot post unit 10A is lifted by a crawler crane, the first knot post unit 10A is fixed to the first floor with an anchor bolt (not shown), and a conservative wire is stretched.

次に、図8(b)に示すように、2階の梁部材20を取り付けた後、歪み直しを行い、これら梁部材20を本締めする。   Next, as shown in FIG. 8 (b), after the beam members 20 on the second floor are attached, the distortion is corrected and these beam members 20 are finally tightened.

次に、図8(c)に示すように、第2節柱ユニット10Bの建方を行い、図9(a)に示すように、3、4階の梁部材20を取り付けた後、歪み直しを行い、これら梁部材20を本締めする。   Next, as shown in FIG. 8 (c), the second node unit 10B is erected, and as shown in FIG. Then, these beam members 20 are finally tightened.

次に、図9(b)に示すように、第3節の柱部材30の建方を行い、図9(c)に示すように、5、R階の梁部材40を取り付けた後、歪み直しを行い、これら梁部材40を本締めする。   Next, as shown in FIG. 9 (b), the column member 30 of the third section is erected, and, as shown in FIG. Repair is performed, and these beam members 40 are finally tightened.

次に、図10(a)に示すように、1階柱の周囲に足場51を組んで、1階柱の型枠52の建て込みを行うとともに、2階床のデッキプレート敷き込みおよび配筋作業を行い、1階柱および2階床のコンクリート打設を行う。これにより、図10(b)に示すように、1階柱2および2階床5を形成する。   Next, as shown in FIG. 10 (a), a scaffold 51 is assembled around the first-floor pillar, and the formwork 52 of the first-floor pillar is built, and the deck plate is laid and arranged on the second floor Work and put concrete on the 1st floor pillar and 2nd floor. Thereby, as shown in FIG.10 (b), the 1st floor pillar 2 and the 2nd floor 5 are formed.

同様の手順で、図10(c)に示すように、2階柱2および3階床5を形成し、さらに、3階柱2、および4〜R階床5を形成する。   In the same procedure, as shown in FIG. 10 (c), the second floor pillar 2 and the third floor 5 are formed, and further, the third floor pillar 2 and the 4th to Rth floors 5 are formed.

本実施形態によれば、以下のような効果がある。
(1)仮設柱11を用意し、この仮設柱11に柱筋12を支持させる。さらに、仮設柱11に筒状の鞘管13を設け、この鞘管13に、柱主筋121を挿通するとともに梁継手14を接合して、柱ユニット10とする。そして、建て逃げ工法により、この柱ユニット10および梁部材20の建方を行う。
よって、柱2が鉄筋コンクリート造の建物1であっても、建て逃げ工法を採用できるから、工期を短縮できる。また、仮設柱11に用いられる鉄骨量は、鉄骨造や鉄骨鉄筋コンクリート造の柱に用いられる鉄骨量よりも少なくなるため、コストの上昇を抑えることができる。
According to this embodiment, there are the following effects.
(1) The temporary pillar 11 is prepared, and the pillar 12 is supported on the temporary pillar 11. Further, a cylindrical sheath tube 13 is provided on the temporary column 11, and the column main bar 121 is inserted into the sheath tube 13 and the beam joint 14 is joined to form the column unit 10. Then, the pillar unit 10 and the beam member 20 are erected by the erection method.
Therefore, even if the pillar 2 is a reinforced concrete building 1, the construction escape method can be adopted, so that the construction period can be shortened. Moreover, since the amount of steel frames used for the temporary columns 11 is smaller than the amount of steel frames used for steel frames or steel-framed reinforced concrete columns, an increase in cost can be suppressed.

なお、本発明は前記実施形態に限定されるものではなく、本発明の目的を達成できる範囲での変形、改良等は本発明に含まれるものである。
例えば、本実施形態では、柱ユニット10として、1層分の高さを有する第1節柱ユニット10Aや、2層分の高さを有する第2節柱ユニット10Bを設けたが、これに限らない。例えば、柱ユニットを3層分の高さとすれば、工期をさらに短縮できるうえに、鉄筋の柱主筋のジョイント箇所数を削減でき、コストを低減できる。
また、1階から3階までを施工した後、R階、5階、4階の順に施工してもよい。このように、最上階の床スラブまたは屋根を先攻して施工すれば、天候に左右されずに下階を施工でき、施工能率を向上できる。
It should be noted that the present invention is not limited to the above-described embodiment, and modifications, improvements, etc. within a scope that can achieve the object of the present invention are included in the present invention.
For example, in the present embodiment, as the column unit 10, the first node column unit 10A having a height of one layer and the second node column unit 10B having a height of two layers are provided. Absent. For example, if the height of the column unit is three layers, the construction period can be further shortened, and the number of joints of the column main reinforcing bars can be reduced, thereby reducing the cost.
Moreover, after constructing from the first floor to the third floor, construction may be performed in the order of the R floor, the fifth floor, and the fourth floor. In this way, if the top floor slab or roof is constructed first, the lower floor can be constructed without being influenced by the weather, and the construction efficiency can be improved.

また、本実施形態では、鞘管13の下面にのみ補強プレート136を設け、鞘管13の上面には振れ止め135を設けて、鞘管13の下面を仮設柱11に支持させたが、これに限らない。すなわち、鞘管13の上下面に補強プレートを設けて、鞘管13の上下面を仮設柱11に支持させてもよいし、鞘管13の上面にのみ補強プレートを設け、鞘管13の下面には振れ止めを設けて、鞘管13の上面を仮設柱11に支持させてもよい。   In the present embodiment, the reinforcing plate 136 is provided only on the lower surface of the sheath tube 13 and the steady rest 135 is provided on the upper surface of the sheath tube 13 so that the lower surface of the sheath tube 13 is supported by the temporary column 11. Not limited to. In other words, reinforcing plates may be provided on the upper and lower surfaces of the sheath tube 13, and the upper and lower surfaces of the sheath tube 13 may be supported by the temporary column 11, or a reinforcing plate may be provided only on the upper surface of the sheath tube 13. May be provided with a steady rest, and the upper surface of the sheath tube 13 may be supported by the temporary column 11.

また、本実施形態では、建物1の柱2を鉄筋コンクリート造としたが、仮設柱を本設に利用して、鉄骨鉄筋コンクリート造としてもよい。
また、建物1の床5を現場打ちコンクリートにより形成したが、これに限らず、床5をハーフプレキャストコンクリート(ハーフPC)またはフルプレキャストコンクリート(フルPC)としてもよい。このようにすれば、さらに工期を短縮できる。
また、建物1の4、5階にブレースを設けていないが、これに限らず、ブレースを設けてもよい。
In this embodiment, the pillar 2 of the building 1 is reinforced concrete. However, a temporary pillar may be used for the main construction to form a steel-framed reinforced concrete structure.
Moreover, although the floor 5 of the building 1 is formed of cast-in-place concrete, the present invention is not limited thereto, and the floor 5 may be half precast concrete (half PC) or full precast concrete (full PC). In this way, the construction period can be further shortened.
Moreover, although the brace is not provided in the 4th and 5th floors of the building 1, it is not limited to this, and a brace may be provided.

また、本実施形態では、柱ユニット10に4つの梁継手14を設けたが、これに限らず、梁継手の数は適宜決定されてよい。
また、梁継手14をH鋼としたが、これに限らず、梁継手をガセットプレートのみとしてもよい。
In the present embodiment, the four beam joints 14 are provided in the column unit 10. However, the present invention is not limited to this, and the number of beam joints may be determined as appropriate.
Further, although the beam joint 14 is made of H steel, the present invention is not limited to this, and the beam joint may be made of only a gusset plate.

また、柱ユニット10の柱主筋121の本数を12本とし、この柱主筋121を柱の角部に3本ずつ配置したが、これに限らず、柱主筋の本数や位置は適宜決定されてよい。
また、仮設柱11をH鋼としたが、これに限らず、2本のCチャンネル材を背中合わせに溶接して、仮設柱としてもよい。
また、本実施形態では、仮設柱11を1階から3階までの柱2に設けたが、これに限らず、2階から3階までのように途中階の柱に仮設柱を設けてもよい。
Further, the number of column main bars 121 of the column unit 10 is twelve, and three column main bars 121 are arranged at the corners of the column. However, the present invention is not limited to this, and the number and position of the column main bars may be appropriately determined. .
Although the temporary pillar 11 is made of H steel, the present invention is not limited to this, and two C channel materials may be welded back to back to form a temporary pillar.
In this embodiment, the temporary pillar 11 is provided on the pillar 2 from the first floor to the third floor. However, the present invention is not limited to this, and a temporary pillar may be provided on the middle floor pillar such as from the second floor to the third floor. Good.

本発明の一実施形態に係る架構組立方法が適用された建物の架構の一部を示す側面図である。It is a side view which shows a part of building frame to which the frame assembly method which concerns on one Embodiment of this invention was applied. 前記実施形態に係る建物の架構の一部の鉄骨図である。It is a steel-frame figure of a part of frame of the building which concerns on the said embodiment. 前記実施形態に係る柱ユニットの平断面図である。It is a plane sectional view of the pillar unit concerning the embodiment. 前記実施形態に係る柱ユニットの側面図である。It is a side view of the pillar unit which concerns on the said embodiment. 前記実施形態に係る柱ユニットの側面図である。It is a side view of the pillar unit which concerns on the said embodiment. 前記実施形態に係る柱ユニットを製作する手順を説明するための図である。It is a figure for demonstrating the procedure which manufactures the pillar unit which concerns on the said embodiment. 前記実施形態に係る建物の建方手順を説明するための図である。It is a figure for demonstrating the building procedure of the building which concerns on the said embodiment. 前記実施形態に係る建物の工区毎の第2節柱建方までの施工手順を説明するための図である。It is a figure for demonstrating the construction procedure to the 2nd node pillar construction for every work area of the building which concerns on the said embodiment. 前記実施形態に係る建物の工区毎の建方完了までの施工手順を説明するための図である。It is a figure for demonstrating the construction procedure until the construction completion for every construction area of the building which concerns on the said embodiment. 前記実施形態に係る建物の工区毎のコンクリート打設完了までの施工手順を説明するための図である。It is a figure for demonstrating the construction procedure until the concrete placement completion for every construction area of the building which concerns on the said embodiment.

符号の説明Explanation of symbols

1 建物
2 柱
4 梁
10 柱ユニット
11 仮設柱
12 柱筋
13 鞘管
14 梁継手
20 梁部材
50 クローラークレーン(揚重機)
DESCRIPTION OF SYMBOLS 1 Building 2 Column 4 Beam 10 Column unit 11 Temporary column 12 Column reinforcement 13 Sheath pipe 14 Beam joint 20 Beam member 50 Crawler crane (lifter)

Claims (2)

鉄筋コンクリート造の柱と鉄骨造の梁とを有する建物の架構を組み立てる架構組立方法であって、
前記架構を、梁継手が設けられた柱ユニットと、当該柱ユニットの梁継手に接合される梁部材と、を含んで構成し、
前記柱ユニットを、鉄骨柱と、当該鉄骨柱に支持される柱筋と、前記鉄骨柱に設けられて前記梁継手が接合されかつ前記柱筋が挿通される筒状の鞘管と、を含んで構成し、
揚重機を用いて、地組みした前記柱ユニットおよび前記梁部材を揚重して最上階まで建方を行い、当該建方作業を隣接する工区ごとに順次繰り返しながら、前記架構を組み立てることを特徴とする架構組立方法。
A frame assembly method for assembling a frame of a building having reinforced concrete columns and steel beams,
The frame includes a column unit provided with a beam joint, and a beam member joined to the beam joint of the column unit,
The column unit includes a steel column, a column bar supported by the steel column, and a cylindrical sheath tube provided on the steel column to which the beam joint is joined and the column bar is inserted. Consisting of
Using a lifting machine, lifting the grounded column unit and beam member to build up to the top floor, and assembling the frame while sequentially repeating the building work for each adjacent work area The frame assembly method.
鉄筋コンクリート造の柱と鉄骨造の梁とを有する建物の架構であって、
前記架構は、梁継手が設けられた柱ユニットと、当該柱ユニットの梁継手に接合される梁部材と、を有し、
前記柱ユニットは、鉄骨柱と、当該鉄骨柱に支持される柱筋と、前記鉄骨柱に設けられて前記梁継手が接合されかつ前記柱筋が挿通される筒状の鞘管と、を有し、
前記鞘管は、プレートを介して前記鉄骨柱に支持されることを特徴とする建物の架構。
A frame of a building having reinforced concrete columns and steel beams,
The frame includes a column unit provided with a beam joint, and a beam member joined to the beam joint of the column unit,
The column unit includes a steel column, a column bar supported by the steel column, and a cylindrical sheath tube provided on the steel column to which the beam joint is joined and the column bar is inserted. And
The building frame is characterized in that the sheath tube is supported by the steel column through a plate.
JP2007173337A 2007-06-29 2007-06-29 Frame assembly method and building frame Active JP4996370B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007173337A JP4996370B2 (en) 2007-06-29 2007-06-29 Frame assembly method and building frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007173337A JP4996370B2 (en) 2007-06-29 2007-06-29 Frame assembly method and building frame

Publications (2)

Publication Number Publication Date
JP2009013592A true JP2009013592A (en) 2009-01-22
JP4996370B2 JP4996370B2 (en) 2012-08-08

Family

ID=40354821

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007173337A Active JP4996370B2 (en) 2007-06-29 2007-06-29 Frame assembly method and building frame

Country Status (1)

Country Link
JP (1) JP4996370B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102352655A (en) * 2011-07-28 2012-02-15 华南理工大学 Multi-floor type rectangular steel pipe concrete column and floor system beam connecting node and manufacturing method thereof
JP2015101890A (en) * 2013-11-25 2015-06-04 大成建設株式会社 Support structure and construction method
JP2016094766A (en) * 2014-11-14 2016-05-26 株式会社安藤・間 Building frame construction method
KR102190622B1 (en) * 2020-07-02 2020-12-14 이형훈 Multi-steel boxes for connecting structures and construction method using the same

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59829U (en) * 1982-06-25 1984-01-06 鹿島建設株式会社 Reinforcement structure for column-beam joints
JPH08270066A (en) * 1995-03-31 1996-10-15 Ando Corp Precast reinforced concrete unit and multistory building
JPH10231559A (en) * 1997-02-18 1998-09-02 Tokyu Constr Co Ltd Center pillar provided with beam steel frame, and construction method for mixed structure using same
JP2000265555A (en) * 1999-03-15 2000-09-26 Toda Constr Co Ltd Jointing method between reinforced concrete column and steel beam, and joint construction therefor
JP2003193564A (en) * 2001-12-27 2003-07-09 Kajima Corp Column-beam structural body, its construction method, and connection metal fitting

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59829U (en) * 1982-06-25 1984-01-06 鹿島建設株式会社 Reinforcement structure for column-beam joints
JPH08270066A (en) * 1995-03-31 1996-10-15 Ando Corp Precast reinforced concrete unit and multistory building
JPH10231559A (en) * 1997-02-18 1998-09-02 Tokyu Constr Co Ltd Center pillar provided with beam steel frame, and construction method for mixed structure using same
JP2000265555A (en) * 1999-03-15 2000-09-26 Toda Constr Co Ltd Jointing method between reinforced concrete column and steel beam, and joint construction therefor
JP2003193564A (en) * 2001-12-27 2003-07-09 Kajima Corp Column-beam structural body, its construction method, and connection metal fitting

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102352655A (en) * 2011-07-28 2012-02-15 华南理工大学 Multi-floor type rectangular steel pipe concrete column and floor system beam connecting node and manufacturing method thereof
JP2015101890A (en) * 2013-11-25 2015-06-04 大成建設株式会社 Support structure and construction method
JP2016094766A (en) * 2014-11-14 2016-05-26 株式会社安藤・間 Building frame construction method
KR102190622B1 (en) * 2020-07-02 2020-12-14 이형훈 Multi-steel boxes for connecting structures and construction method using the same

Also Published As

Publication number Publication date
JP4996370B2 (en) 2012-08-08

Similar Documents

Publication Publication Date Title
JP4823790B2 (en) Column unit and method of building building using column unit
KR101658648B1 (en) Beam-column joint and simultaneous construction method of upper and lower part of building using thereof
JP2010242390A (en) Joining method and structure of column-beam joint part having steel brace
JP2020037775A (en) Non-brace steel frame building construction method and column base unit
JP4996370B2 (en) Frame assembly method and building frame
CN108951862B (en) Node structure for rigid connection of rolled steel beam and steel column, manufacturing method and residential structure system
JP6339923B2 (en) How to build a building frame
JP2010261270A (en) Composite structure and method for constructing composite structure building
KR100856723B1 (en) System and method for underground downward construction using cantilever type steel frame
JP2013133662A (en) Suspension type steel-framed roof frame, and method for constructing steel-framed roof
CN108867872B (en) Node structure for rigid connection of steel structure beam column, manufacturing method thereof and residential structure system
JP2005188102A (en) Structure of building and construction method
JP6736226B2 (en) Structure and construction method of the structure constructed on the tower-shaped building
JP4550534B2 (en) Building basic structure
JPH10159344A (en) Building method of multi-layered structure provided with a plurality of super beam
KR200358912Y1 (en) Connection structure for girder &amp; column
KR100578641B1 (en) Steel-Concrete Hybrid Column, Hybrid Structure System Using the Same, and Construction Method Thereof
JP7169765B2 (en) How to build structures
JP7186655B2 (en) Construction method of beam-column connection structure
JP5259638B2 (en) Construction method of viaduct portal ramen structure
JP2004019306A (en) Tower-shaped building and its construction method
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JP6752006B2 (en) Fixed structure of building unit and unit building
JP5375174B2 (en) Construction method of column beam frame
JPH1136231A (en) Composite column base structure and its construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20091214

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20111214

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120110

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120302

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120424

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120511

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20180518

Year of fee payment: 6

R150 Certificate of patent or registration of utility model

Ref document number: 4996370

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250