JP2916587B2 - Construction method of building - Google Patents

Construction method of building

Info

Publication number
JP2916587B2
JP2916587B2 JP17780490A JP17780490A JP2916587B2 JP 2916587 B2 JP2916587 B2 JP 2916587B2 JP 17780490 A JP17780490 A JP 17780490A JP 17780490 A JP17780490 A JP 17780490A JP 2916587 B2 JP2916587 B2 JP 2916587B2
Authority
JP
Japan
Prior art keywords
steel frame
load
building
truss
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP17780490A
Other languages
Japanese (ja)
Other versions
JPH0468169A (en
Inventor
牧夫 吉原
勝之 三谷
明正 宮内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP17780490A priority Critical patent/JP2916587B2/en
Publication of JPH0468169A publication Critical patent/JPH0468169A/en
Application granted granted Critical
Publication of JP2916587B2 publication Critical patent/JP2916587B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、長大スパンかつ大断面の梁を有し、その梁
に各種建築部材の荷重が負荷される形態の建築物の施工
方法に関する。
Description: TECHNICAL FIELD The present invention relates to a construction method of a building having a beam having a long span and a large cross section, and to which a load of various building members is applied.

「従来の技術」 近年、建築物の構造形式として、いわゆるメガストラ
クチュア(巨大架構)と称するものが検討されている。
第10図はメガストラクチュアが採用された建築物の一例
を示すもので、4本の鉄骨造の柱1と、それらの上端間
に架設された鉄骨造のトラス梁2とによって巨大な門型
フレームであるメガストラクチュアを構成し、そのメガ
ストラクチュアの上部に、通常の柱3、梁4によって上
層階を構築した形態のものであって、メガストラクチュ
アの下部に自由度の高い大空間を得るようになしたもの
である。
"Conventional technology" In recent years, what is called a so-called megastructure (giant frame) has been studied as a structural form of a building.
FIG. 10 shows an example of a building employing a megastructure, in which a huge portal frame is constructed by four steel columns 1 and a steel truss beam 2 erected between the upper ends thereof. A structure in which the upper floor is constructed by ordinary pillars 3 and beams 4 on the upper part of the megastructure, so that a large space with a high degree of freedom is obtained at the lower part of the megastructure. What was done.

この第10図に示す建築物にあっては、メガストラクチ
ュアを構成しているトラス梁2のスパンは数十メートル
にも及ぶ長大なものとされ、その梁成は数メートルにも
及ぶものとされている。そして、このような建築物を施
工するに当たっては、トラス梁2に予め上方に反るよう
なむくりをつけておき、施工途中段階においては、図示
されているように、トラス梁2の両端部に設置したジャ
ッキによって山形に張ったワイヤ5を緊張することによ
り、トラス梁2の中央部に下向きの先行荷重を加えてト
ラス梁2がほぼ水平となるように変形させておくととも
に、上層階の施工が進むにつれてワイヤ5を緩めていっ
て先行荷重を解除していき、上層階が完成した時点でそ
の荷重によりトラス梁2が自ずと水平となるようにして
いる。
In the building shown in FIG. 10, the span of the truss beam 2 constituting the megastructure is as long as several tens of meters, and the span of the beam is as long as several meters. ing. In constructing such a building, the truss beam 2 is previously provided with a bend so as to be warped upward, and in the middle of construction, as shown in FIG. The truss beam 2 is deformed so that the truss beam 2 becomes almost horizontal by applying a downward precedent load to the central portion of the truss beam 2 by tensioning the wire 5 stretched in a mountain shape by the installed jack. , The wire 5 is loosened to release the preceding load, and the truss beam 2 is naturally leveled by the load when the upper floor is completed.

「発明が解決しようとする課題」 ところで、上記の建築物においては、メガストラクチ
ュアを構成する長大スパンかつ大断面の梁として鉄骨造
のトラス梁2を採用しているために、そのトラス梁2に
十分な剛性をもたせるためには鉄骨量が膨大となるばか
りでなく、溶接あるいはボルト締結箇所数が膨大とな
り、工費がかさむとともに著しく施工の手間がかかると
いう不具合がある。
[Problems to be Solved by the Invention] By the way, in the above-described building, since the steel truss beam 2 is adopted as a beam having a long and long span and a large cross section constituting the megastructure, the truss beam 2 is not used. In order to provide sufficient rigidity, not only does the amount of steel frame become enormous, but also the number of welding or bolt fastening points becomes enormous, resulting in a problem that the construction cost is increased and the construction work is extremely time-consuming.

また、上記の建築物を施工するに際しては、第10図に
示されているように、トラス梁2に対する先行荷重をそ
のトラス梁2の中央に位置して立設される柱3を介して
加えるようにしており、このため、先行荷重を加えてむ
くりを解消させるに先立ってトラス梁2の上部に3層分
の躯体を施工するようにしていたが、むくりの付いたま
まのトラス梁2の上部において躯体の施工を行うこと
は、中央に位置するもの以外の柱3が外側に傾いてしま
うことになるので、その施工が極めて困難である。
Further, when constructing the above-mentioned building, as shown in FIG. 10, a precedent load to the truss beam 2 is applied via a column 3 that is erected at the center of the truss beam 2. Therefore, prior to the application of the preceding load to eliminate the peeling, three layers of the skeleton were constructed on the upper part of the truss beam 2, but the truss beam with the peeling still attached Performing construction of the skeleton at the upper part of 2 is extremely difficult because columns 3 other than those located at the center are inclined outward.

本発明は上記の事情に鑑みてなされたもので、長大ス
パンかつ大断面の梁に荷重が負荷される形態の建築物を
施工する際に採用して好適な施工方法を提供することを
目的とする。
The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a suitable construction method adopted when constructing a building in which a load is applied to a beam having a long span and a large cross section. I do.

「課題を解決するための手段」 本発明は、中央部が上方に反る形状に予めむくりが付
けられた鉄骨を柱間に架設し、その鉄骨に下向きの先行
荷重をかけてむくりを所定のむくりとなるまで低減させ
た後、その鉄骨の上部に垂直材、斜材、上弦材を連結し
てトラスを形成し、その後、前記鉄骨に対する先行荷重
を解除したうえでその鉄骨に対してコンクリートを打設
して下弦材を形成し、以上により形成された梁に対して
下向きの先行荷重をかけることによってその梁をほぼ水
平となし、その後、その梁に負荷する荷重となる残余の
建築部材を施工しつつ前記梁の撓みが許容撓み範囲内と
なるように先行荷重を漸次低減させていくことを特徴と
するものである。
"Means for Solving the Problems" The present invention provides a steel frame having a central portion warped upward with a pre-peeled portion interposed between columns, and applies a downward preload to the steel frame to remove the peal. After reducing to the predetermined peeling, vertical material, diagonal material, and upper chord material are connected to the upper part of the steel frame to form a truss, and then, after releasing the preceding load on the steel frame, The lower chord is formed by casting concrete, and the beam formed as described above is subjected to a downward precedent load to make the beam almost horizontal, and then the remaining load to be applied to the beam is applied. The present invention is characterized in that the precedent load is gradually reduced so that the bending of the beam is within the allowable bending range while the building member is being constructed.

「実施例」 以下、本発明の一実施例を第1図〜第9図を参照して
説明する。
Embodiment An embodiment of the present invention will be described below with reference to FIGS.

第1図は本発明方法により構築された建築物の躯体を
示す部分立面図であって、図中符号10はその下方に大空
間20を形成するために設けられた長大スパンかつ大断面
の梁である。
FIG. 1 is a partial elevational view showing a skeleton of a building constructed by the method of the present invention. In the figure, reference numeral 10 denotes a long span and a large cross section provided for forming a large space 20 thereunder. It is a beam.

この梁10は、基本的には下弦材11、上弦材12、垂直材
13、斜材14から構成されるトラス構造のものであるが、
その断面を第2図に示すように、下弦材11はボックス状
の鉄骨15の内側にコンクリートが充填されるとともに、
外側に鉄筋16が配筋されたうえでコンクリートが打設さ
れて形成された鉄骨鉄筋コンクリート造(より厳密には
充填被覆型鋼管コンクリート造)のものとされ、上弦材
12、垂直材13、斜材14はいずれも鉄骨造とされている。
This beam 10 basically consists of a lower chord material 11, an upper chord material 12, a vertical
It is of truss structure composed of 13, diagonal material 14,
As shown in FIG. 2, the lower chord 11 is filled with concrete inside the box-shaped steel frame 15,
It is made of steel-framed reinforced concrete (more precisely, filled and coated steel pipe concrete) formed by casting concrete after reinforcing bars 16 are arranged on the outside.
12, vertical member 13, and diagonal member 14 are all made of steel.

この梁10は、第1図に示されるように下弦材11の両端
が鉄骨鉄筋コンクリート造の大断面の柱18,18に接合さ
れてそれらの上端相互間に架設され、この梁10の下方
に、この建築物の4スパンにわたる幅を有し、かつ、5
層分が吹き抜けた無柱の大空間20が形成されるようにな
っている。すなわち、この梁10および柱18,18によっ
て、そのような大空間20を形成するとともに上層階の躯
体を支持するための門型フレームであるメガストラクチ
ュアが構成されている。
As shown in FIG. 1, this beam 10 has both ends of a lower chord material 11 joined to columns 18 and 18 of large sections made of steel-reinforced concrete, and is erected between the upper ends thereof. Have a width spanning 4 spans of this building and 5
A column-free large space 20 through which the layers flow is formed. That is, the beams 10 and the columns 18, 18 form a megastructure that is a portal frame for forming such a large space 20 and supporting the frame on the upper floor.

そして、この梁10の下弦材11の上面の位置には、上記
大空間20の直上階の床が形成され、上弦材12の上面の位
置にはさらにその上階の床が形成されるようになってい
て、この梁10に下弦材11はそれ自身で大空間20の直上階
の床梁を兼ねるとともに、垂直材13および斜材14はそれ
ら自身でそれぞれこの階の柱およびブレースを兼ねるも
のとされ、上弦材12はそれ自身でその上階の床梁を兼ね
るものとされている。
Then, the floor of the upper floor of the large space 20 is formed at the position of the upper surface of the lower chord material 11 of the beam 10, and the floor of the upper floor is further formed at the position of the upper surface of the upper chord material 12. In this beam 10, the lower chord 11 itself also serves as a floor beam on the floor directly above the large space 20, and the vertical member 13 and the diagonal member 14 themselves also serve as columns and braces on this floor, respectively. The upper chord 12 itself is also used as a floor beam on the upper floor.

なお、第1図において符号30,31はメガストラクチュ
ア以外の躯体である柱および梁であり、これらは通常の
鉄骨造とされている。
In FIG. 1, reference numerals 30 and 31 denote pillars and beams, which are other than the megastructure, which are ordinary steel structures.

上記の建築物の施工手順の一例を第3図〜第9図を参
照して説明する。
An example of a construction procedure of the above building will be described with reference to FIGS.

第3図に示すように、柱18,18および大空間20の床面
までの躯体を構築した後、大空間20の床面上において梁
10の下弦材11となる鉄骨15を組み立てる。この鉄骨15
は、図示されるように、中央部15aと両側部15b,15bとの
3ピースにより構成し、その中央部15aが上方に変位す
るようにむくりをつけておく。そのむくり寸法d1は、後
述するようにトラスの剛性やコンクリートの重量等を考
慮したうえで、梁10が建築物の荷重を最終的に受けたと
きにほぼ水平となるように設定しておく。また、梁10の
中央に位置して設けられる垂直材13を予めこの鉄骨15の
中央部15aに取り付けておく。
As shown in FIG. 3, after constructing the frame to the floor of the pillars 18 and 18 and the large space 20, beams are formed on the floor of the large space 20.
Assemble the steel frame 15 to be the lower chord material 11 of the 10. This steel frame 15
As shown in the figure, the center part 15a and the two side parts 15b, 15b are constituted by three pieces, and the center part 15a is peeled so as to be displaced upward. The peeling dimension d 1 is set so that the beam 10 becomes substantially horizontal when finally receiving the load of the building, taking into account the rigidity of the truss and the weight of the concrete as described later. deep. In addition, a vertical member 13 provided at the center of the beam 10 is attached to the central portion 15a of the steel frame 15 in advance.

そして、そのように組み立てた鉄骨15を、柱18,18か
ら反力をとってリフトアップしていき、第4図に示すよ
うにそれら柱18,18の上端面に架設する。
Then, the steel frame 15 assembled as described above is lifted up by taking a reaction force from the columns 18, 18, and is erected on the upper end surfaces of the columns 18, 18, as shown in FIG.

次に、上記のように架設した鉄骨15に下向きの先行荷
重をかけ、むくり寸法がd2(d2<d1)となるまでむくりを
低減させる。それには、第5図に示すように、鉄骨15の
中央に設けられた上記垂直材13に添わせて油圧ジャッキ
40を上向きに取り付けるとともに、柱18,18と梁10との
仕口部にワイヤ41の両端を定着し、そのワイヤ41の中央
部を油圧ジャッキ40に係合させ、油圧ジャッキ40を作動
させてそのワイヤ41の中央部を押し上げて緊張すること
によって、その反力を垂直材13を介して鉄骨15の中央部
15aに下向きに加えることが良い。なお、センターホー
ル型ジャッキのように引上げ式の油圧ジャッキを設け、
その油圧ジャッキによりワイヤ41の中央部を引っ張り上
げるようにしても良い。
Next, a downward leading load is applied to the steel frame 15 erected as described above to reduce the peeling until the peeling dimension becomes d 2 (d 2 <d 1 ). As shown in FIG. 5, a hydraulic jack is attached to the vertical member 13 provided at the center of the steel frame 15.
Attach 40 upward and fix both ends of the wire 41 at the connection between the columns 18, 18 and the beam 10, engage the central part of the wire 41 with the hydraulic jack 40, and operate the hydraulic jack 40. By pushing up the central portion of the wire 41 and tightening, the reaction force is applied to the central portion of the steel frame 15 through the vertical member 13.
It is good to add downward to 15a. In addition, a lifting hydraulic jack is provided like a center hole type jack,
The central portion of the wire 41 may be pulled up by the hydraulic jack.

そして、その状態で、第6図に示すように、他の垂直
材13、斜材14、上弦材12をそれぞれ鉄骨15に取り付け、
トラスを形成する。
Then, in that state, as shown in FIG. 6, other vertical members 13, diagonal members 14, and upper chord members 12 are attached to the steel frames 15, respectively.
Form a truss.

その後、鉄骨15に加えた先行荷重を一旦解除する。こ
れにより、第7図に示すように鉄骨15のむくりは大きく
なるが、そのむくり寸法d3は、形成されたトラスの剛性
分だけ当初のむくり寸法d1よりは小さくなる。
Thereafter, the preceding load applied to the steel frame 15 is temporarily released. Thus, although Mukuri steel frame 15 as shown in FIG. 7 is increased, the Mukuri dimension d 3, only the stiffness component of the formed truss initial smaller than Mukuri dimension d 1.

その後、鉄骨15の外側に鉄筋16を配筋して型枠を組み
立てたうえで、鉄骨15の内側にコンクリートを充填する
とともにその外側にもコンクリートを打設し、鉄骨鉄筋
コンクリート造の下弦材11を形成する。これにより、第
8図に示すように、梁10がむくりの付いた状態で形成さ
れるが、この段階における梁10のむくり寸法d4はコンク
リートの重量分だけ上記のむくり寸法d3より小さくな
り、当然ながら鉄骨15に当初に付与されていたむくり寸
法d1より小さくなる。この段階のむくり寸法d4が、この
後に梁10に負荷される上層階の躯体およびその他の各種
建築部材の荷重に対応するものとなっていて、最終的に
その荷重が梁10に加わることで梁10が自ずとほぼ水平と
なるように設定されている。
After that, reinforcing steel 16 is arranged outside the steel frame 15 to assemble the formwork, then the concrete is filled inside the steel frame 15 and concrete is poured outside the steel frame 15, and the lower chord material 11 of the steel frame reinforced concrete is formed. Form. As a result, as shown in FIG. 8, the beam 10 is formed in a state in which the beam 10 is peeled. At this stage, the beam dimension d 4 of the beam 10 is equal to the above-mentioned dimension d 3 by the weight of the concrete. becomes smaller, of course smaller than Mukuri dimension d 1, which has been granted to the original in steel frame 15. The peel size d 4 at this stage corresponds to the load of the upper-story skeleton and other various building members to be subsequently applied to the beam 10, and the load is finally applied to the beam 10. Is set so that the beam 10 is substantially horizontal by itself.

そこで、コンクリート強度が確保された後、梁10より
上階の施工による梁10が撓むとされるレベルよりやや高
めのレベルまで(第9図に示すようにほぼ水平となるま
で)むくりを低減させるべく、ワイヤ41を介して梁10に
先行荷重をかける。その後、梁10の上部に上層階の躯体
を施工するとともに各種建築部材を取り付けていき、そ
の荷重に応じて順次ワイヤ41を緩めていって先行荷重を
段階的に低減させていくことにより、梁10を常にほぼ水
平に保持する。
Therefore, after the concrete strength is secured, the peeling is reduced to a level slightly higher than the level at which the beam 10 due to the construction on the floor above the beam 10 is deflected (until it is almost horizontal as shown in Fig. 9). A preload is applied to the beam 10 via the wire 41 in order to cause the beam to move. After that, the upper-floor skeleton is constructed at the top of the beam 10 and various building members are attached, and the wires 41 are sequentially loosened according to the load to gradually reduce the preceding load, thereby reducing the beam. Keep 10 almost level at all times.

以上により、上層階がほぼ完成した時点で梁10に加え
た先行荷重を全て解除し、残余の建築部材の取り付け、
組み立てを行えば、梁10は上層階の躯体および各種の建
築部材の総荷重により自ずと水平となる。なお、先行荷
重の付与方法や手段はこの実施例に限らず躯体構造に順
応して自由に採用すれば良い。
As described above, when the upper floor is almost completed, all the preceding loads applied to the beam 10 are released, and the remaining building members are attached.
Once assembled, the beams 10 are naturally leveled by the total load of the upper floor skeleton and various building components. The method and means for applying the preceding load are not limited to this embodiment, and may be freely adopted in accordance with the frame structure.

上記の梁10では、下弦材11および上弦材12とにより全
体としては十分な梁成寸法が確保されて十分な剛性が得
られ、これによって、梁10の下方に上記のような大空間
20が確保できることは勿論のこと、下弦材11を鉄骨鉄筋
コンクリート造とし、かつ、この下弦材11の鉄骨15には
梁10の撓み方向と逆方向の曲げモーメントが付与された
ものとなるので、第10図に示したもののように梁全体を
単純なトラス構造とする場合に比して鉄骨量を削減でき
るとともに鉄骨加工が簡略化され、工費、施工手間の点
で有利である。しかも、下弦材11、上弦材12、垂直材1
3、斜材14がそれぞれこの建築物の梁、柱、ブレースを
兼ねるので、建築物全体の躯体が簡略化されるという利
点もある。
In the above-mentioned beam 10, the lower chord material 11 and the upper chord material 12 as a whole ensure a sufficient beam forming dimension and obtain sufficient rigidity.
Of course, the lower chord 11 is made of steel reinforced concrete, and the steel 15 of the lower chord 11 is given a bending moment in a direction opposite to the bending direction of the beam 10, so that the second chord 11 can be secured. Compared to the case where the whole beam has a simple truss structure as shown in Fig. 10, the amount of steel frame can be reduced and the steel frame processing is simplified, which is advantageous in terms of construction cost and labor. Moreover, lower chord 11, upper chord 12, vertical 1
3. Since the diagonal members 14 also serve as beams, columns and braces of the building, there is an advantage that the structure of the entire building is simplified.

また、上記実施例の施工手順では、トラスを形成する
に際して鉄骨15に先行荷重をかけてむくりを低減させて
から垂直材13、斜材14、上弦材12を組み立てるので、そ
の作業を容易に行うことができるものである。すなわ
ち、鉄骨15に当初の大きなむくり(むくり寸法d1)が付
いている状態のままでトラスを組み立てる場合にあって
は、垂直材13が外側に傾いてしまうことになってトラス
の建方が非常に困難となるのに対し、上記の場合には、
むくり寸法がd2となるまでむくりを低減させてからトラ
スを組み立てるので、垂直材13を支障なく鉛直に建てる
ことができ、したがってトラスを容易に組み立てること
ができる。
In addition, in the construction procedure of the above embodiment, the vertical member 13, the diagonal member 14, and the upper chord member 12 are assembled after applying a precedent load to the steel frame 15 when forming the truss to reduce the peeling. Is what you can do. That is, when assembling a truss with the steel frame 15 having the initial large swelling (scaling dimension d 1 ), the vertical members 13 are inclined outward and the truss construction Is much more difficult, whereas in the above case,
Since Mukuri dimensions assembled truss from reducing the Mukuri until d 2, it is possible to build uprights 13 vertically without any problem, thus it is possible to assemble the truss easily.

また、鉄骨15に対してコンクリートを打設して下弦材
11を形成するに際し、鉄骨15に加えた先行荷重を一旦解
除して大きなむくりの付いた状態に戻し、その状態でコ
ンクリートを打設するようにしたので、鉄骨15のむくり
を低減させた状態のままでコンクリートを打設して下弦
材11を形成する場合に比して、梁10の剛性をより高める
ことができる。
Also, cast concrete on steel frame 15
In forming 11, the prior load applied to the steel frame 15 was once released and returned to a state with large peeling, and concrete was poured in that state, so the peeling of the steel frame 15 was reduced. The rigidity of the beam 10 can be further increased as compared with the case where the lower chord material 11 is formed by casting concrete in the state.

なお、鉄骨15、梁10に対して先行荷重を加えるために
は、上記実施例に限定されることなく適宜の手法を採用
し得る。
In addition, in order to apply a preceding load to the steel frame 15 and the beam 10, an appropriate method can be adopted without being limited to the above-described embodiment.

また、上記実施例では、梁10の下弦材11を充填被覆型
鋼管コンクリート造のものとしたが、これは鉄骨15の内
部にのみコンクリートを充填する充填鋼管コンクリート
構造としても良いし、あるいは、ボックス状の鉄骨に限
らず任意の断面形状の鉄骨を使用した一般の鉄骨鉄筋コ
ンクリート造としても良い。また、上弦材12、垂直材1
3、斜材14も鉄骨材に限らず、鉄骨鉄筋コンクリート造
や鋼管コンクリート構造としても良く、垂直材13や斜材
14の位置、形式は、設計上の要求等に応じて適宜変更し
て良いことはいうまでもない。さらに、上記の梁10の上
部や下部にさらにトラスあるいは梁を一体に形成した複
合トラス構造の梁とすることにより、剛性をより高める
こともできる。
Further, in the above embodiment, the lower chord material 11 of the beam 10 is made of a filling-coated steel pipe concrete, but this may be a filled steel pipe concrete structure in which concrete is filled only inside the steel frame 15, or a box. It is also possible to use a general steel-framed reinforced concrete structure using a steel frame having an arbitrary cross-sectional shape without being limited to the steel frame. In addition, upper chord material 12, vertical material 1
3, the diagonal members 14 are not limited to steel members, but may be steel frame reinforced concrete or steel pipe concrete structures.
Needless to say, the position and format of 14 may be appropriately changed according to design requirements and the like. Furthermore, by using a truss or a beam of a composite truss structure in which a beam is integrally formed above and below the beam 10, rigidity can be further increased.

また、上記実施例では、梁10の両端が支持される柱18
を鉄骨鉄筋コンクリート造としたが、必ずしもそれに限
定されない。また、柱18を鉄骨鉄筋コンクリート造とす
る場合においても、その柱18に対するコンクリート打設
は、梁10の下弦材11に対するコンクリート打設と同時に
行っても良い。勿論、この柱18の上端にのみならず長大
スパンの梁を複数階設ける場合等には柱の途中に梁10を
設けることでも良い。さらに、上記実施例では、梁10の
下弦材11となる鉄骨15をリフトアップして柱18上端間に
架設するようにしたが、スパンが比較的小さい場合等に
おいては必ずしもリフトアップ工法によることはない。
Further, in the above embodiment, the pillars 18 on which both ends of the beam 10 are supported are provided.
Is made of steel-framed reinforced concrete, but is not necessarily limited thereto. Further, even when the column 18 is made of a steel-framed reinforced concrete structure, the concrete placing on the column 18 may be performed simultaneously with the concrete placing on the lower chord material 11 of the beam 10. Needless to say, the beam 10 may be provided in the middle of the pillar when a plurality of long span beams are provided not only at the upper end of the pillar 18 but also on a plurality of floors. Furthermore, in the above embodiment, the steel frame 15 that becomes the lower chord material 11 of the beam 10 is lifted up and erected between the upper ends of the columns 18, but when the span is relatively small, the lift-up method is not necessarily used. Absent.

また、上記実施例は、本発明の施工方法を、梁の下方
に無柱の大空間が設けられるとともに梁の上部に上層階
の躯体が設けられる形態の建築物に適用した場合の例で
あるが、本発明はそのような形態の建築物に適用される
のみならず、種々の形態の建築物全般に対して同様に適
用できることはいうまでもない。
Further, the above embodiment is an example of a case where the construction method of the present invention is applied to a building in which a large pillarless space is provided below the beams and a skeleton of an upper floor is provided above the beams. However, it goes without saying that the present invention can be applied not only to such forms of buildings, but also to various types of buildings in general.

「発明の効果」 以上で詳細に説明したように、本発明の施工方法で
は、下弦材が鉄骨コンクリート造とされたトラス構造の
梁を採用したので、単純なトラス構造の梁を採用する場
合に比して鉄骨量を削減できるとともに鉄骨加工が簡略
化され、工費、施工手間の点で有利であることは勿論の
こと、その梁を施工するに際しては、中央部が上方に反
る形状に予めむくりが付けられた鉄骨を柱間に架設し、
その鉄骨に下向きの先行荷重をかけてむくりを所定のむ
くりとなるまで低減させた後、その鉄骨の上部に垂直
材、斜材、上弦材を連結してトラスを形成するようにし
たので、鉄骨の上部に垂直材を支障なく鉛直に建てるこ
とができ、したがってトラスを容易に形成することがで
きる。また、その後、前記鉄骨に対する先行荷重を解除
したうえでその鉄骨に対してコンクリートを打設して下
弦材を形成するようにしたので、梁の剛性を十分に高め
ることができる。
[Effects of the Invention] As described in detail above, in the construction method of the present invention, since the lower chord material employs a truss structure beam made of steel concrete, a simple truss structure beam is adopted. In addition to reducing the amount of steel frames and simplifying steel frame processing, it is advantageous not only in terms of construction cost and labor, but also when constructing the beams, the center part must be bent upwards in advance. A steel frame with a hole is installed between the pillars,
After applying a downward preload to the steel frame to reduce the peeling to a predetermined level, the vertical, diagonal and upper chords were connected to the upper part of the steel to form a truss. The vertical members can be erected vertically on the upper part of the steel frame without any trouble, so that the truss can be easily formed. Further, after that, after releasing the preceding load on the steel frame, concrete is cast on the steel frame to form the lower chord material, so that the rigidity of the beam can be sufficiently increased.

【図面の簡単な説明】[Brief description of the drawings]

第1図および第2図は本発明方法により構築された建築
物の一例を示すもので、第1図はその躯体の部分立面
図、第2図は梁の断面図(第1図のII−II線矢視図)で
ある。第3図〜第9図は上記建築物の施工手順の一例を
工程順に説明するための図である。 第10図は、メガストラクチュアによる建築物の一従来例
を示す斜視図である。 10……梁、11……下弦材、12……上弦材、13……垂直
材、14……斜材、15……鉄骨、18……柱。
1 and 2 show an example of a building constructed by the method of the present invention. FIG. 1 is a partial elevational view of the skeleton, and FIG. 2 is a sectional view of a beam (II in FIG. 1). -II line arrow view). 3 to 9 are diagrams for explaining an example of the construction procedure of the building in the order of steps. FIG. 10 is a perspective view showing a conventional example of a megastructure building. 10 ... beam, 11 ... lower chord material, 12 ... upper chord material, 13 ... vertical material, 14 ... diagonal material, 15 ... steel frame, 18 ... pillar.

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平4−44569(JP,A) 特開 平3−122333(JP,A) 特開 平3−107048(JP,A) 特開 昭58−91274(JP,A) (58)調査した分野(Int.Cl.6,DB名) E04G 21/14 E04B 1/30 E04B 1/18 ──────────────────────────────────────────────────続 き Continuation of front page (56) References JP-A-4-44569 (JP, A) JP-A-3-122333 (JP, A) JP-A-3-107048 (JP, A) JP-A-58-58 91274 (JP, A) (58) Field surveyed (Int. Cl. 6 , DB name) E04G 21/14 E04B 1/30 E04B 1/18

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】中央部が上方に反る形状に予めむくりが付
けられた鉄骨を柱間に架設し、その鉄骨に下向きの先行
荷重をかけてむくりを所定のむくりとなるまで低減させ
た後、その鉄骨の上部に垂直材、斜材、上弦材を連結し
てトラスを形成し、その後、前記鉄骨に対する先行荷重
を解除したうえでその鉄骨に対してコンクリートを打設
して下弦材を形成し、以上により形成された梁に対して
下向きの先行荷重をかけることによってその梁をほぼ水
平となし、その後、その梁に負荷する荷重となる残余の
建築部材を施工しつつ前記梁の撓みが許容撓み範囲内と
なるように先行荷重を漸次低減させていくことを特徴と
する建築物の施工方法。
1. A steel frame having a central portion warped upward and having a preliminarily peeled shape is erected between pillars, and a downward precedent load is applied to the steel frame to reduce fluffing to a predetermined value. After that, the vertical, diagonal and upper chords are connected to the upper part of the steel frame to form a truss, and then the precedent load on the steel frame is released and concrete is cast on the steel frame to lower the chord. Forming the beam, applying a downward precedent load to the beam formed as described above, making the beam substantially horizontal, and then constructing the remaining building member that will be the load applied to the beam, A method for constructing a building, characterized in that a preceding load is gradually reduced so that the deflection of the preform is within an allowable deflection range.
JP17780490A 1990-07-05 1990-07-05 Construction method of building Expired - Lifetime JP2916587B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17780490A JP2916587B2 (en) 1990-07-05 1990-07-05 Construction method of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17780490A JP2916587B2 (en) 1990-07-05 1990-07-05 Construction method of building

Publications (2)

Publication Number Publication Date
JPH0468169A JPH0468169A (en) 1992-03-03
JP2916587B2 true JP2916587B2 (en) 1999-07-05

Family

ID=16037380

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17780490A Expired - Lifetime JP2916587B2 (en) 1990-07-05 1990-07-05 Construction method of building

Country Status (1)

Country Link
JP (1) JP2916587B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3061333B2 (en) * 1992-12-25 2000-07-10 株式会社竹中工務店 Floor deflection control method and construction method of steel frame multi-story building.
JP7049950B2 (en) * 2018-07-05 2022-04-07 株式会社竹中工務店 Gate type frame structure

Also Published As

Publication number Publication date
JPH0468169A (en) 1992-03-03

Similar Documents

Publication Publication Date Title
JP2934668B2 (en) Beam structure
JP2916587B2 (en) Construction method of building
JP3261255B2 (en) Shell roof lift-up method
JP2916585B2 (en) Construction method of building
JPH02136445A (en) Construction of structure including superframe
JPH10159344A (en) Building method of multi-layered structure provided with a plurality of super beam
JP2974025B1 (en) Construction method of large span large beam upper frame
JPH04368528A (en) Frame construction using void beam
JP2916586B2 (en) Construction method of building
JP3116767B2 (en) Existing building seismic isolation structuring method
JP2916588B2 (en) Construction method of building
JPH09264050A (en) Building structure
JP2522708B2 (en) Reinforcing bar tip assembly beam with formwork and reinforcing bar tip assembly method with formwork
JP3079334B2 (en) Construction method of steel building with long projecting girders.
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam
JP2817591B2 (en) Construction method of steel reinforced concrete building
JP2641836B2 (en) Precast prestressed concrete U-beam
JPH07238593A (en) Building of tube structure
JP3115942B2 (en) Building construction method
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JP2659329B2 (en) Construction method of PC structure
JPH0742238A (en) Roof structure and construction method
JPH0598703A (en) Multilayer rc core wall structure and construction method thereof
JP2934749B2 (en) Beam deflection control structure and deflection control method
JPH07279247A (en) Skeleton of building consisting of concrete core wall and structural steel frame