JPH0446023Y2 - - Google Patents

Info

Publication number
JPH0446023Y2
JPH0446023Y2 JP20478285U JP20478285U JPH0446023Y2 JP H0446023 Y2 JPH0446023 Y2 JP H0446023Y2 JP 20478285 U JP20478285 U JP 20478285U JP 20478285 U JP20478285 U JP 20478285U JP H0446023 Y2 JPH0446023 Y2 JP H0446023Y2
Authority
JP
Japan
Prior art keywords
steel column
steel
column
work
erection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP20478285U
Other languages
Japanese (ja)
Other versions
JPS62110446U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP20478285U priority Critical patent/JPH0446023Y2/ja
Publication of JPS62110446U publication Critical patent/JPS62110446U/ja
Application granted granted Critical
Publication of JPH0446023Y2 publication Critical patent/JPH0446023Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【考案の詳細な説明】 「産業上の利用分野」 本考案は、鉄骨柱建入れ調整用ユニツトに係
り、一層詳細には、鉄骨柱建入れ時に、鉄骨架構
の梁等と建込みされる鉄骨柱の脚部との間に着脱
自在に介設される鉄骨柱建入れ調整装置に、溶接
等の作業床と該作業に伴う各種安全、養生施設と
を一体的に組付けたものに関する。
[Detailed description of the invention] "Field of industrial application" The invention relates to a unit for adjusting the erection of steel columns, and more specifically, the invention relates to a unit for adjusting the erection of steel columns. This invention relates to a steel column erection adjustment device that is removably interposed between the legs of the column, and a work floor for welding, etc., and various safety and curing facilities associated with the work are integrally assembled.

「従来の技術」 従来、高層建築鉄骨造で、各節の柱ジヨイント
部が溶接で固定されている場合は、その組立手順
として大半が、先に固定した(固めた)骨組の上
に次節の鉄骨を積み上げる積層工法を行つてい
る。
``Conventional technology'' Conventionally, in high-rise steel structures, when the column joints of each section are fixed by welding, the majority of the assembly procedures are to build the next section on top of the previously fixed (hardened) framework. We use the layered construction method of piling up steel frames.

この工法の手順は、例えば第8図に示すよう
に、建込みされた鉄骨柱1aを既に固定された先
行鉄骨柱1bにエレクシヨンピース2を用いて仮
保持させ、次いで相互に隣接する鉄骨柱1aの仕
口部3間に梁4を仮付けし、しかる後に、鉄骨柱
1aの頭部を正規の平面位置(即ち垂直)に組上
げるべく、ワイヤー或いはチエーン5を必要な範
囲の鉄骨柱1a間に張りめぐらし所謂歪直しと称
される鉄骨柱建入れ調整を行う。
The procedure of this construction method is, for example, as shown in Fig. 8, the erected steel column 1a is temporarily held on the already fixed preceding steel column 1b using the erection piece 2, and then the adjacent steel column The beam 4 is temporarily attached between the joint parts 3 of the steel column 1a, and then the wire or chain 5 is attached to the required range of the steel column 1a in order to assemble the head of the steel column 1a in the normal plane position (that is, vertically). Adjustments to the erection of steel columns will be made, also known as straightening the gaps.

その後、速やかに吊足場6及び溶接カゴ7等を
設置して梁4部及び鉄骨柱1a脚部の固定作業
(本締め、溶接)を行い、仮設物であるエレクシ
ヨンピース2の撤去(切断)やワイヤー或いはチ
エーン5の撤去を完了させて一節分の鉄骨建方作
業を終了する。
Thereafter, the hanging scaffold 6 and welding basket 7, etc. were quickly installed, and the beam 4 and the legs of the steel column 1a were fixed (final tightening, welding), and the temporary erection piece 2 was removed (cut). The removal of wires, wires, and chain 5 is completed, and the steel frame erection work for one section is completed.

「考案が解決しようとする問題点」 ところで、上記した手順においては、歪直し作
業や吊足場6及び溶接カゴ7等の設置及び撤去作
業が高所作業となつて安全性が低いことから熟練
した作業員を要するばかりか、仮設資材であるエ
レクシヨンピース2、ワイヤー5等の維持管理に
要する費用もばかにならないと共に、仮設資材の
組立、解体とその安全対策のための工期を要する
という難点があつた。
``Problem that the invention seeks to solve'' By the way, in the above-mentioned procedure, the work of straightening the distortion and the installation and removal work of the hanging scaffold 6 and the welding cage 7 are work at heights, which is less safe and requires a skilled worker. Not only does it require more workers, but it also costs a considerable amount of money to maintain and manage temporary materials such as the erection piece 2 and wire 5, and it also has the disadvantage of requiring a long construction period for assembling and dismantling the temporary materials and implementing safety measures. It was hot.

また、上記エレクシヨンピース2が溶接(固
定)作業時に邪魔になつて作業性を低下させるこ
とから、溶接欠陥を生じるという虞れもあつた。
Further, since the erection piece 2 becomes an obstacle during welding (fixing) work and reduces workability, there is a risk that welding defects may occur.

そこで、本考案は、施工能率の向上、工期の短
縮及び安全性、労務、品質の確保がはかれる鉄骨
柱建入れ調整用ユニツトを提供することを目的と
する。
Therefore, the object of the present invention is to provide a steel column erecting adjustment unit that can improve construction efficiency, shorten construction period, and ensure safety, labor, and quality.

「問題点を解決するための手段」 上記目的を達成するため、本考案は、第1図乃
至第5図に示すように、鉄骨架構の堅固な平面部
に固定可能なL字状の架台17上から伸縮自在で
かつ先端部が建込み鉄骨10bの脚部へ連結可能
な適数のアーム19を延出した調整機構部20
を、少なくとも水平面内にて直角方向に二つ配設
すると共に、これら調整機構部の架台相互間に連
結手段32a,32bを講じて一体化させてなる
鉄骨柱建入れ調整装置13を設け、該鉄骨柱建入
れ調整装置に、上記各架台に一体的に組付けられ
たフレーム32a,32bを介して少なくとも上
下二段からなる中央開口の作業床14a,14b
と、該作業床を囲繞する各種安全、養生施設1
5,16を取付けると共に、上記作業床と各種安
全、養生施設の一側部に、上記中央開口部に対す
る鉄骨柱の出入りを許容するための開閉手段35
a,35b,36…を設けたことを特徴とする。
"Means for Solving the Problems" In order to achieve the above object, the present invention has an L-shaped frame 17 that can be fixed to a solid flat part of a steel frame, as shown in FIGS. 1 to 5. Adjustment mechanism section 20 extending from above with an appropriate number of arms 19 which are extendable and whose tips can be connected to the legs of the built-in steel frame 10b.
A steel frame column erection adjustment device 13 is provided, in which at least two of the adjustment mechanism parts are arranged at right angles in a horizontal plane, and are integrated by connecting means 32a, 32b between the frames of these adjustment mechanism parts. A work floor 14a, 14b with a central opening, consisting of at least two upper and lower stages, is attached to the steel column erection adjustment device via frames 32a, 32b integrally assembled to each of the above-mentioned frames.
and various safety and curing facilities surrounding the work floor 1
5 and 16, and an opening/closing means 35 on one side of the work floor and various safety and curing facilities for allowing the steel column to enter and exit the central opening.
A, 35b, 36... are provided.

「作用」 鉄骨柱建入れ時には、例えば、先ず鉄骨柱建入
れ調整用ユニツト11を地上にてこれから建込む
鉄骨柱10aの脚部に装着する。
"Function" When erecting a steel frame column, for example, first, the steel column erecting adjustment unit 11 is attached on the ground to the leg of the steel frame column 10a to be erected.

この際、鉄骨柱建入れ調整装置13における各
調整機構部20のそれぞれの架台17下部先端
(第2図中A点参照)とアーム19先端(第2図
中C点参照)とを結ぶ直線が、予め、架台17底
面に対し垂直になるようにそれぞれのアーム19
を伸長或いは収縮作動させて調整し、この後各ア
ーム19の先端をこれから建込む鉄骨柱10aの
脚上部に連結する。また、この時、適宜の手段に
より上記鉄骨柱建入れ調整装置13を鉄骨柱10
aに剛に一体化すれば、架台17底面に対して鉄
骨柱10aが鉛直に組込まれて好適である。
At this time, a straight line connecting the lower tip of each frame 17 (see point A in FIG. 2) and the tip of the arm 19 (see point C in FIG. 2) of each adjustment mechanism section 20 in the steel column erection adjustment device 13 is , in advance, so that each arm 19 is perpendicular to the bottom surface of the pedestal 17.
are adjusted by extending or contracting, and then the tips of each arm 19 are connected to the upper leg of the steel column 10a to be erected. At this time, the steel column erection adjustment device 13 is adjusted to the steel column 10 by appropriate means.
If it is rigidly integrated with the frame 17, the steel column 10a will be vertically incorporated into the bottom surface of the pedestal 17, which is preferable.

次に、上記鉄骨柱10aを、取付ける鉄骨柱1
0eの頭部近くまでクレーン等で吊りあげ、そし
て該鉄骨柱10eの頭部近くの吊足場等に待機し
た作業員により、上記鉄骨柱建入れ調整装置13
の各架台17の下部先端を上記鉄骨柱10eの頭
部側面に押付けるようにして降し、各架台17下
部を、鉄骨架構の堅固な平面部(図示例では仕口
部12a)に適宜の手段により固定し、しかる後
に鉄骨柱10aを吊上げていたワイヤーを開放す
る。
Next, the steel column 10a is attached to the steel column 1.
The steel column erecting adjustment device 13 is lifted up to near the head of the steel column 10e by a crane or the like, and then the steel column erection adjustment device 13
The lower end of each frame 17 is lowered so as to be pressed against the head side of the steel column 10e, and the lower part of each frame 17 is properly placed on a solid flat part of the steel frame (in the illustrated example, the joint part 12a). After that, the wire that was lifting the steel column 10a is released.

これで、鉄骨柱10aは略垂直に取付けられた
ことになるが、次に該鉄骨柱10aの頭部が正規
の平面位置に対して許容範囲内に納つているかを
上記鉄骨柱建入れ調整装置13に一体的に組付け
られた多段作業床14a,14bの下段側に乗込
んだ作業員等が機械的(上方から重錘の付いた紐
を垂らす等)或いは電気的(地上等から鉄骨柱1
0aに設けたターゲツトに向けてレーザー光線を
走射する等)な測定装置で確認し、必要に応じて
各アーム19を伸長或いは収縮作動させて建入れ
微調整を行う。この時点で、上記下段作業床14
a上の作業員或いは自動溶接機等による一柱毎の
柱ジヨイント部の固定(溶接)作業に入るが、次
工程の梁取付作業を先行させる場合は、隣接する
鉄骨柱10aも同様にして建込み、その間の梁1
2を落し込んだ後に、鉄骨柱10a、梁12の各
ジヨイント部の固定作業に入る。
Now, the steel column 10a is installed almost vertically.Next, the steel column erection adjustment device Workers who have boarded the lower tiers of the multi-tiered work floors 14a and 14b, which are integrally assembled with the 1
This is confirmed using a measuring device (such as a laser beam directed toward a target provided at 0a), and fine adjustments are made by extending or contracting each arm 19 as necessary. At this point, the lower work floor 14
Fixing (welding) work will begin on the column joint of each column by the worker above a or an automatic welding machine, but if the beam installation work in the next process is to be carried out in advance, the adjacent steel column 10a will also be erected in the same way. Including, beam 1 between
2, work begins on fixing the joints of the steel column 10a and the beam 12.

固定作業完了後は、上段作業床14bに作業員
が乗込むなどして鉄骨柱建入れ調整装置13のア
ーム19と鉄骨柱10aとの連結を解くと共に、
上記作業床14a,14b及び各種安全、養生施
設15,16の開閉手段35a,36b,36…
を開放し、さらに鉄骨柱建入れ調整装置13の架
台17と仕口部12a等との連結を解いて鉄骨柱
建入れ調整用ユニツト11を鉄骨柱10aから取
外し、地上に吊り降して次の建方準備に入る。
After the fixing work is completed, a worker climbs onto the upper work floor 14b and disconnects the arm 19 of the steel column erection adjustment device 13 from the steel column 10a,
Opening/closing means 35a, 36b, 36 for the working floors 14a, 14b and various safety and curing facilities 15, 16...
The steel column erection adjustment unit 11 is removed from the steel column 10a by releasing the connection between the frame 17 of the steel column erection adjustment device 13 and the joint part 12a, etc., and is lowered to the ground for the next step. Preparation for construction begins.

このようにして、鉄骨柱建入れ調整用ユニツト
11の作業床14a,14b上で、建入れ微調
節、固定作業及び管理作業等が連続して行ない得
る。
In this way, fine erection adjustment, fixing work, management work, etc. can be performed continuously on the working floors 14a, 14b of the steel column erection adjustment unit 11.

「実施例」 以下添付図面に基づいて、本考案の一実施例を
説明する。
``Example'' An example of the present invention will be described below based on the accompanying drawings.

第1図において、10aはこれから建込みされ
る鉄骨柱で、該鉄骨柱10aの脚部には、予め鉄
骨柱建入れ調整様ユニツト11が装着されてい
る。10bは建入れ調整中の鉄骨柱、10cは上
記建入れ調整を終えて仮保持中の鉄骨柱、10d
は固定作業中の鉄骨柱で、10eは固定された先
行鉄骨柱である。
In FIG. 1, reference numeral 10a denotes a steel column that is to be erected, and a steel column erecting adjustment unit 11 is attached in advance to the leg portion of the steel column 10a. 10b is a steel frame column undergoing erection adjustment, 10c is a steel frame column being temporarily maintained after the above erection adjustment, and 10d
10e is a steel column that is being fixed, and 10e is a preceding steel column that has been fixed.

建入れ調整中乃至固定作業中の上記鉄骨柱10
b、10c,10dに装着された鉄骨柱建入れ調
整用ユニツト11の下部は、既に固定された先行
鉄骨柱10e間に組立てられた梁12(厳密には
仕口部12a)の上面に連結固定されている。
The above-mentioned steel column 10 is under construction adjustment or fixing work
The lower part of the steel column erection adjustment unit 11 attached to b, 10c, and 10d is connected and fixed to the upper surface of the beam 12 (strictly speaking, the joint part 12a) assembled between the preceding steel columns 10e that have already been fixed. has been done.

次に、上記鉄骨柱建入れ調整用ユニツト11
は、第2図乃至第5図に示すように、鉄骨柱建入
れ調整装置13と、上下二段の中央開口の作業床
14a,14bと、風養生ネツト15、手摺16
等の各安全、養生施設とから構成される。
Next, the steel column erection adjustment unit 11
As shown in FIGS. 2 to 5, there is a steel column erection adjustment device 13, upper and lower work floors 14a and 14b with a central opening, a wind protection net 15, and a handrail 16.
It consists of various safety and curing facilities.

上記鉄骨柱建入れ調整装置13はL字状の架台
17と第1及び第2の二本のアーム18,19と
からなる二つの調整機構部20,20を、鉄骨架
構の水平面状の直角二方向(図示例ではX−Y軸
方向)から建入れ調整が可能に、上記二つの架台
17,17の水平台部21底面を同一平面上に位
置させて、これら架台17,17間に架設した連
結部材(図示例では後述するフレーム32a,3
2bが兼用する)を介して一体化してなる。
The above-mentioned steel frame column erection adjustment device 13 moves two adjustment mechanism parts 20, 20 consisting of an L-shaped pedestal 17 and two first and second arms 18, 19 at right angles on the horizontal plane of the steel frame. The bottom surfaces of the horizontal pedestals 21 of the two pedestals 17, 17 are positioned on the same plane, and the pedestals 17, 17 are constructed between the two pedestals 17, 17, so that the construction can be adjusted from the direction (in the illustrated example, the X-Y axis direction). Connecting members (in the illustrated example, frames 32a and 3 described later)
2b is also used).

上記架台17は、仕口部12aの上面へ着脱自
在に固定された水平台部21の後部から支持柱部
22を剛に起立している。即ち、上記仕口部12
aの上面には、予め、架台受金物23が固定治具
24を介して二つ固設され、該架台受金物23に
上記水平台部21がピン25結合されるのであ
る。
The pedestal 17 has a support column 22 rigidly erected from the rear of a horizontal platform 21 that is detachably fixed to the upper surface of the joint section 12a. That is, the above-mentioned joint part 12
Two pedestal brackets 23 are fixed in advance on the upper surface of the frame holder 23 via fixing jigs 24, and the horizontal table portion 21 is connected to the pedestal brackets 23 by pins 25.

上記水平台部21の上部先端には、図示しない
ルーズホール等のスライド機構により水平台部2
1の長手方向に進退動可能なガイドローラ26が
付設され、該ガイドローラ26が、固定された先
行鉄骨柱10eの頭部側面に当接している。
A sliding mechanism such as a loose hole (not shown) is provided at the top end of the horizontal platform 21 to allow the horizontal platform 21 to
A guide roller 26 that can move forward and backward in the longitudinal direction of the steel frame 1 is attached, and the guide roller 26 is in contact with the side surface of the head of the fixed leading steel column 10e.

上記支持柱部22の上部からは、油圧シリンダ
からなる第1アーム18が水平でかつ剛に延出さ
れ、そのピストンロツド部27先端が適宜スタツ
ドボルト等を介して建込みされた鉄骨柱10b等
の脚下部側面に連結されている。
A first arm 18 consisting of a hydraulic cylinder extends horizontally and rigidly from the upper part of the support column section 22, and the tip of the piston rod section 27 is attached to a steel column 10b or the like which is erected via stud bolts or the like as appropriate. Connected to the lower side of the leg.

上記支持柱部22の上端には外筒28が回動自
在に枢支されると共に該外筒28の先端に油圧シ
リンダ29が連設され、これら外筒28と油圧シ
リンダ29とで第2アーム19を構成している。
An outer cylinder 28 is rotatably supported at the upper end of the support column 22, and a hydraulic cylinder 29 is connected to the tip of the outer cylinder 28, and the outer cylinder 28 and the hydraulic cylinder 29 form a second arm. It consists of 19.

上記油圧シリンダ29のピストンロツド部30
先端が建込みされた鉄骨柱10b等の脚上部側面
にピン31結合されている。
Piston rod portion 30 of the hydraulic cylinder 29
A pin 31 is connected to the side surface of the upper part of the leg of the steel column 10b or the like where the tip end is erected.

上記作業床14a,14bは、上記鉄骨柱建入
れ調整装置13における各架台17の水平台部2
1上方に、枠状に一体的に組付けられた多数の横
フレーム32a及び縦フレーム32bを利用し
て、上下に二段設けられる。
The work floors 14a, 14b are the horizontal base portions 2 of each frame 17 in the steel column erection adjustment device 13.
1, two vertical frames are provided using a large number of horizontal frames 32a and vertical frames 32b that are integrally assembled into a frame shape.

下段作業床14aは、下方の横フレーム32a
上にチエツカープレート33を敷設してなり、該
作業床14a上で建入れ調整及び溶接(固定)作
業を行うものである。また、該作業床14aは溶
接作業時の火花養生用の床ともなる。
The lower work floor 14a has a lower horizontal frame 32a.
A checker plate 33 is laid on top of the work floor 14a, and erection adjustment and welding (fixing) work are performed on the work floor 14a. Further, the working floor 14a also serves as a floor for curing sparks during welding work.

上段作業床14bは、上方の横フレーム32b
上に床板34を敷設してなり、該作業床14b上
で上記鉄骨柱建入れ調整装置13の取付、解体作
業を行うものである。また、該作業床14bは溶
接作業時の雨養生用の屋根ともなる。
The upper work floor 14b has an upper horizontal frame 32b.
A floor plate 34 is laid on top of the working floor 14b, on which the installation and dismantling work of the steel column erection adjustment device 13 is performed. Further, the working floor 14b also serves as a roof for rain protection during welding work.

そして、上記作業床14a,14b間の周囲に
は、縦フレーム32b等を利用して風養生ネツト
15が、また上段作業床14aの周縁上部には、
手摺16がそれぞれ周設されている。
A wind curing net 15 is installed around the area between the work floors 14a and 14b by using the vertical frame 32b, and above the periphery of the upper work floor 14a.
Handrails 16 are provided around each.

また、上記作業床14a,14b、風養生ネツ
ト15及び手摺16の一側部が部分開口されて、
上記作業床14a,14bの中央開口部分への鉄
骨柱10a等の出入りが許容されるようになつて
いる。そのうちの作業床14a,14b及び風養
生ネツト15の開口部には、片開きの上段開閉養
生ネツト36が取着されている。勿論、手摺16
にも図示しない開閉手段が設けられる。
Further, one side of the working floors 14a, 14b, the wind curing net 15 and the handrail 16 are partially opened,
The steel columns 10a and the like are allowed to enter and exit the central openings of the work floors 14a and 14b. At the openings of the working floors 14a, 14b and the wind curing net 15, a single-open upper curing net 36 is attached. Of course, handrail 16
Also provided is an opening/closing means (not shown).

尚、図中37は上段作業床14aの中央開口部
分を閉塞する雨養生シートで、38a,38bは
風養生ネツト15に設けた調整装置取付用の出入
口を開閉する扉である。さらに、39a,39b
は作業床14a,14bに設けた昇降口を開閉す
る蓋であり、40は固定された先行鉄骨柱10e
に付設された作業員昇降用のタラツプである。
In the figure, numeral 37 is a rain protection sheet that closes the central opening of the upper work floor 14a, and 38a and 38b are doors that open and close the entrance and exit for installing the adjustment device provided in the wind protection net 15. Furthermore, 39a, 39b
40 is a lid for opening and closing the elevator opening provided on the work floors 14a and 14b, and 40 is a fixed leading steel column 10e.
This is a ramp attached to the platform for raising and lowering workers.

従つて、本実施例では、上記鉄骨柱建入れ調整
用ユニツト11即ち、鉄骨柱建入れ調整装置13
を、建込みされる鉄骨柱10aに装着する際に
は、予め、ガイドローラ26の先端(第2図中A
点参照)と油圧シリンダ(第1アーム)18のピ
ストンロツド部27先端(第2図中B点参照)の
二点を結ぶ直線が、架台17(水平台部21)底
面に対し垂直になるように適宜両部材26,27
を進退動させて調整する。
Therefore, in this embodiment, the steel column erection adjustment unit 11, that is, the steel column erection adjustment device 13
When installing it on the steel column 10a to be erected, first attach the tip of the guide roller 26 (A in Fig. 2).
(see point) and the tip of the piston rod portion 27 of the hydraulic cylinder (first arm) 18 (see point B in Figure 2) so that the straight line connecting the two points is perpendicular to the bottom surface of the pedestal 17 (horizontal pedestal portion 21). Both members 26, 27 as appropriate
Adjust by moving forward and backward.

そして、上記油圧シリンダ18のピストンロツ
ド部27先端を上記鉄骨柱10aの脚下部に連結
した後、第2アーム19を構成する油圧シリンダ
29のピストンロツド部30先端を上記鉄骨柱1
0aの脚上部に連結する。
After connecting the tip of the piston rod portion 27 of the hydraulic cylinder 18 to the lower leg of the steel column 10a, the tip of the piston rod portion 30 of the hydraulic cylinder 29 constituting the second arm 19 is connected to the steel column 10a.
Connect to the upper leg of 0a.

次いで、上記油圧シリンダ29を収縮作動させ
てそのピストンロツド部30先端(第2図中C点
参照)を、上記ガイドローラ26の先端と油圧シ
リンダ18のピストンロツド部27先端を結ぶ直
線の延長上に位置決めする。
Next, the hydraulic cylinder 29 is contracted to position the tip of the piston rod 30 (see point C in FIG. 2) on the extension of the straight line connecting the tip of the guide roller 26 and the tip of the piston rod 27 of the hydraulic cylinder 18. do.

このような鉄骨柱建入れ調整装置11を、鉄骨
柱建入れ時に、そのガイドローラ26を固定され
た先行鉄骨柱10eの頭部に押付けるようにし
て、仕口部12a上面の架台受金物23に固定す
れば、前述したと同様に鉄骨柱10aは鉄骨柱1
0eに対して略垂直に取付けられたことになる。
この際、下段作業床14a上に乗込んだ作業員に
より、柱ジヨイント部における微小なズレは油圧
シリンダ18で補正し、鉄骨柱10eの頭部位置
の微調整は油圧シリンダ29で補正出来ることは
言う迄もない。
When the steel column erecting adjustment device 11 is erected, the guide roller 26 is pressed against the head of the fixed preceding steel column 10e, and the frame support 23 on the upper surface of the joint section 12a is pressed. If the steel column 10a is fixed to the steel column 1 as described above, the steel column 10a
This means that it is installed substantially perpendicular to 0e.
At this time, it is possible for the worker on the lower work floor 14a to correct minute shifts in the column joint using the hydraulic cylinder 18, and to make fine adjustments to the head position of the steel column 10e using the hydraulic cylinder 29. Needless to say.

尚、上記実施例において、鉄骨柱建入れ調整用
ユニツト11を、最初、建込みされる鉄骨柱10
aに代えて、鉄骨架構の一階の床や固定された先
行鉄骨柱10e等にセツトしておいて、この後建
込みされる鉄骨柱10aを定位置に受け止めかつ
調整するようにしても良い。また、第1及び第2
アーム18,19の伸縮機構は、油圧シリンダに
限らず、ラツクアンドピニオン等の各種の機械的
調整手段を採用しても良い。さらにまた、建込み
された鉄骨柱10bの頭部が正規の平面位置に対
して許容範囲内に納つているかを測定する装置と
して、地上や鉄骨柱建入れ調整装置13の架台1
7上から上記鉄骨柱10bの頭部に設けたターゲ
ツトに向けてレーザー光線を走射するものが考え
られるが、この場合、ターゲツトで光線を電気信
号に変換し、ケーブルにてこれを架台17の位置
へもたらして増幅し、表示手段により調整機構部
20の調整量として表示させ、これに基づき油圧
シリンダ等のストローク量を調整するようにして
も良い。この際、太陽光線との判別のため、パル
ス化するとより好適である。
In the above embodiment, the steel column erecting adjustment unit 11 is initially installed on the steel column 10 to be erected.
Instead of a, it may be set on the floor of the first floor of a steel frame structure, a fixed preceding steel column 10e, etc., and the steel column 10a to be erected later can be received and adjusted in a fixed position. Also, the first and second
The extension and contraction mechanism of the arms 18 and 19 is not limited to hydraulic cylinders, and various mechanical adjustment means such as a rack and pinion may be used. Furthermore, as a device for measuring whether the head of the erected steel column 10b is within an allowable range with respect to the regular plane position, the mount 1 of the steel column erecting adjustment device 13 on the ground or the
It is conceivable that a laser beam is emitted from above 7 toward a target provided at the head of the steel column 10b, but in this case, the target converts the beam into an electrical signal and sends it to the position of the pedestal 17 using a cable. It is also possible to amplify and display the adjustment amount of the adjustment mechanism section 20 by the display means, and adjust the stroke amount of the hydraulic cylinder or the like based on this. At this time, it is more suitable to pulse the light in order to distinguish it from sunlight.

次に、第6図及び第7図は、本考案の別の実施
例を示すもので、鉄骨柱建入れ調整用ユニツト1
1内における溶接作業を、下段作業床14a上に
設置した自動溶接機(多軸溶接ロボツト)41
a,41bで行つて、連続自動溶接による品質向
上をはかるようにした例である。
Next, FIGS. 6 and 7 show another embodiment of the present invention, in which a steel column erection adjustment unit 1 is shown.
An automatic welding machine (multi-axis welding robot) 41 installed on the lower work floor 14a performs the welding work in 1.
This is an example in which continuous automatic welding is performed to improve quality by performing continuous automatic welding.

「考案の効果」 以下説明したように本考案によれば、鉄骨架構
の堅固な平面部に固定可能なL字状の架台上から
伸縮自在でかつ先端部が建込み鉄骨柱の脚部へ連
結可能な適数のアームを延出した調整機構部を、
少なくとも水平面内にて直角方向に二つ配設する
と共に、これら調整機構部の架台相互間に連結手
段を講じて一体化させてなる鉄骨柱建入れ調整装
置を設け、該鉄骨柱建入れ調整装置に、上記各架
台に一体的に組付けられたフレームを介して少な
くとも上下二段からなる中央開口の作業床と、該
作業床を囲繞する各種安全、養生施設を取付け、
かつ、上記作業床と各種安全、養生施設との一側
部に、上記中央開口部に対する鉄骨柱の出入りを
許容するための開閉手段を設けているので、鉄骨
柱建入れ時に、鉄骨柱建入れ調整装置における上
記各調整機構部の架台にて予めその鉄骨柱の脚部
に装着して建入れし、それからの架台を鉄骨架構
の堅固な平面部に固定することにより、その鉄骨
柱を、鉄骨柱建入れ調整装置を基準に垂直に建方
でき、また、その作業に当たり、その鉄骨柱建入
れ調整装置に装着した少なくとも上下二段からな
る作業床及び該作業床を囲繞する各種安全、養生
施設にて容易かつ安全に作業でき、而して、上記
構成であるから、 1 鉄骨柱建込みと同時に垂直精度が確保される
ため、建入れ直しは微調整のみとなり施工能率
が上がる。即ち、従来の歪直しの工程を無くす
ことで、工期短縮につながるのである。
"Effects of the invention" As explained below, according to the invention, the L-shaped pedestal can be freely extended and contracted from the top of the L-shaped frame, which can be fixed to a solid flat surface of the steel frame, and the tip is connected to the leg of the built-in steel column. Adjustment mechanism part with the appropriate number of arms extended as possible,
A steel column erection adjustment device is provided, which is arranged at least in two directions at right angles in a horizontal plane, and is integrated by connecting means between the frames of these adjustment mechanism parts, and the steel column erection adjustment device is provided. Attach a centrally opened work floor consisting of at least two upper and lower stages and various safety and curing facilities surrounding the work floor via a frame integrally assembled to each of the above-mentioned mounts,
In addition, an opening/closing means is provided on one side of the work floor and various safety and curing facilities to allow the steel columns to enter and exit the central opening. The frame of each of the above-mentioned adjustment mechanisms in the adjustment device is attached to the leg of the steel column in advance and erected, and then the frame is fixed to a solid flat part of the steel frame, so that the steel column can be fixed to the steel frame. A work floor that can be erected vertically with reference to the column erection adjustment device, and for the work, a working floor consisting of at least two upper and lower stages attached to the steel column erection adjustment device, and various safety and curing facilities surrounding the working floor. With the above configuration, 1. Since vertical accuracy is ensured at the same time as the steel columns are erected, re-erecting requires only minor adjustments, increasing construction efficiency. In other words, eliminating the conventional distortion correction process leads to shorter construction times.

2 高所での柱建方用、溶接用の足場の架け払し
作業や各種安全、養生施設の設置作業が不要と
なるため、作業の安全性が一段と向上する。
2. Work safety is further improved as there is no need to erect pillars at high places, remove scaffolding for welding, or install various safety and curing facilities.

3 各種安全、養生施設が柱建込みと同時に完了
するため、作業性の向上、コスト低減及び工期
短縮がはかれる。
3. Various safety and curing facilities will be completed at the same time as the pillar erection, improving work efficiency, reducing costs, and shortening the construction period.

4 溶接作業に邪魔なエレクシヨンピースが不要
となるため、溶接作業が容易となり、品質向上
がはかれる。
4. Since there is no need for an erection piece that obstructs welding work, welding work becomes easier and quality is improved.

等の効果が得られる。Effects such as this can be obtained.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は、本考案の構成要領図、第2図は、鉄
骨柱建入れ調整用ユニツトの縦断側面図、第3図
は、第2図の横断平面図、第4図は、第3図A矢
視図、第5図は、同じく第3図のB矢視図、第6
図及び第7図は、本考案の別の実施例を示す鉄骨
柱建入れ調整用ユニツトの縦断側面図及び横断平
面図、第8図は、従来例の構成要領図である。 10a〜10e……鉄骨柱、11……鉄骨柱建
入れ調整用ユニツト、12……梁、13……鉄骨
柱建入れ調整装置、14a,14b……作業床、
15……風養生ネツト、16……手摺、17……
架台、19……第2アーム、20……調整機構
部。
Fig. 1 is a schematic diagram of the construction of the present invention, Fig. 2 is a longitudinal cross-sectional side view of a unit for adjusting steel column erection, Fig. 3 is a cross-sectional plan view of Fig. 2, and Fig. 4 is Fig. 3. The A arrow view, Figure 5 is the same as the B arrow view, Figure 6 in Figure 3.
7 and 7 are a longitudinal sectional side view and a lateral plan view of a steel column erection adjustment unit showing another embodiment of the present invention, and FIG. 8 is a schematic diagram of a conventional example. 10a to 10e... Steel column, 11... Steel column erection adjustment unit, 12... Beam, 13... Steel column erection adjustment device, 14a, 14b... Working floor,
15... Wind curing net, 16... Handrail, 17...
Frame, 19...second arm, 20...adjustment mechanism section.

Claims (1)

【実用新案登録請求の範囲】 (1) 鉄骨架構の堅固な平面部に固定可能なL字状
の架台上から、伸縮自在でかつ先端部が建込み
される鉄骨柱の脚部へ連結可能な少なくとも一
本のアームを延出した調整機構部を、少なくと
も直角方向に二つ配設すると共に、これら調整
機構部を、上記架台間に架設した連結手段を介
して一体化してなる鉄骨柱建入れ調整装置に、
上記各架台に一体的に組付けられたフレームを
介して、少なくとも上下二段からなる中央開口
の作業床と、該作業床を囲繞する各種安全、養
生施設を取付けると共に、上記作業床と各種安
全、養生施設の一側部に、上記中央開口部に対
する鉄骨柱の出入りを許容するための開閉手段
を設けたことを特徴とする鉄骨柱建入れ調整用
ユニツト。 (2) 上記下段側作業床上に自動溶接機を設置して
なることを特徴とする実用新案登録請求の範囲
第1項記載の鉄骨柱建入れ調整用ユニツト。
[Scope of Claim for Utility Model Registration] (1) An L-shaped pedestal that can be fixed to a solid flat surface of a steel frame, and that can be extended and contracted and whose tip can be connected to the legs of a steel column to be erected. A steel frame column erected in which at least two adjustment mechanism sections each having at least one arm extending therefrom are disposed in at least a right angle direction, and these adjustment mechanism sections are integrated via a connecting means installed between the frames. In the adjustment device,
A work floor with a central opening consisting of at least two upper and lower stages and various safety and curing facilities surrounding the work floor are attached via a frame integrally assembled to each of the above-mentioned mounts. A unit for adjusting the erection of a steel frame column, characterized in that an opening/closing means is provided on one side of the curing facility to allow the steel column to enter and leave the central opening. (2) The steel column erecting adjustment unit as set forth in claim 1 of the utility model registration claim, characterized in that an automatic welding machine is installed on the lower work floor.
JP20478285U 1985-12-28 1985-12-28 Expired JPH0446023Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20478285U JPH0446023Y2 (en) 1985-12-28 1985-12-28

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20478285U JPH0446023Y2 (en) 1985-12-28 1985-12-28

Publications (2)

Publication Number Publication Date
JPS62110446U JPS62110446U (en) 1987-07-14
JPH0446023Y2 true JPH0446023Y2 (en) 1992-10-29

Family

ID=31170774

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20478285U Expired JPH0446023Y2 (en) 1985-12-28 1985-12-28

Country Status (1)

Country Link
JP (1) JPH0446023Y2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2675570B2 (en) * 1988-03-26 1997-11-12 株式会社竹中工務店 How to rebuild steel columns
JP5640483B2 (en) * 2010-06-14 2014-12-17 株式会社大林組 Demolition method and column holding device
JP5984628B2 (en) * 2012-11-05 2016-09-06 大成建設株式会社 Fire curing jig

Also Published As

Publication number Publication date
JPS62110446U (en) 1987-07-14

Similar Documents

Publication Publication Date Title
JP5394334B2 (en) Construction method of work floor for work at height
KR20190041189A (en) Modular work platform of a long span bridge main tower rebar and construction method using the same
JPH0446023Y2 (en)
CN113404281A (en) Climbing type scaffold, climbing and mounting method thereof and construction method of fabricated building
JP2539150B2 (en) Bridge erection equipment
JP5356091B2 (en) Crane girder exchanging method and crane girder exchanging apparatus
JPH05133016A (en) Peripheral supporting self-rising type building engineering method
JP2834588B2 (en) Climb-up type building construction apparatus and construction method
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
JPH07150767A (en) Beam truss erecting method in building having overhead traveling crane
JP3328172B2 (en) Work floor equipment for elevator installation
JPH0648683A (en) Tower crane
JP3214407B2 (en) Connection method of beam members and scaffolding equipment for work at height
JP2776128B2 (en) Lifting device for building frame
JP2528452Y2 (en) High work equipment
JP2592980B2 (en) Construction method of steel frame material for high-rise structure
JPS62156478A (en) Method and apparatus for controlling building of reinforcing bar pillar
JPH026906B2 (en)
JP6525857B2 (en) Construction method of roofed building and roof intermediate structure
US2288167A (en) Movable scaffold
JPH0317356A (en) Construction of multi-story building
JP2717155B2 (en) Building construction equipment
JP3239154B2 (en) Lift-up device for all-weather temporary roof
JPH0447072A (en) Construction method for multistory building and its device
JP2539142Y2 (en) Lifting device for temporary roof