JPH04247126A - Construction works for underground structure - Google Patents

Construction works for underground structure

Info

Publication number
JPH04247126A
JPH04247126A JP3011959A JP1195991A JPH04247126A JP H04247126 A JPH04247126 A JP H04247126A JP 3011959 A JP3011959 A JP 3011959A JP 1195991 A JP1195991 A JP 1195991A JP H04247126 A JPH04247126 A JP H04247126A
Authority
JP
Japan
Prior art keywords
walls
floor
pits
construction
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3011959A
Other languages
Japanese (ja)
Inventor
Hiroshi Ogawa
浩 小川
Yoshiya Kase
加瀬 善弥
Terushige Miyashita
宮下 輝重
Akio Tomita
昭夫 富田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP3011959A priority Critical patent/JPH04247126A/en
Publication of JPH04247126A publication Critical patent/JPH04247126A/en
Pending legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Piles And Underground Anchors (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To shorten the term of construction and lower costs by constructing land slide protection walls, individual continuous walls and individual pits underground until they come down to a support ground, and thereby using these construction members as the outer walls, the bearing walls and the columns of an underground floor. CONSTITUTION:Individual continuous walls 2 and individual pits 3 are constructed in the inner sides of land slid protection walls 1 until they come down to the depth of a support ground by means of poured reinforced concrete. In this case, ready-made pits such as PC pits and steel pits may be used as the pit 3. The land slide protection walls 1, the continuous walls 2 and the pits 3 are made to function as the foundation of a structure, and they can concurrently be used as the outer walls, the bearing walls and columns of an underground structure. By this constitution, the execution of construction can be simplified, and cost can also be lowered.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】この発明は、地下構造物の構築工
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention This invention relates to a method for constructing underground structures.

【0002】0002

【従来の技術および発明が解決しようとする課題】地下
構造物の構築工法としては、従来より様々な方法が実施
されている。その多くは地盤面下を深く掘り下げる根切
り工事を伴う。根切り工事には山留め壁や切り梁などの
多くの支保工材と多くの人手を必要とする。また、工期
の長期化が避けられないだけでなく、地盤面下の作業で
あるため大きな危険を伴う。
BACKGROUND OF THE INVENTION Various methods have been used to construct underground structures. Most of these involve root cutting work that involves digging deep beneath the ground surface. Root cutting work requires a lot of supporting materials such as retaining walls and cut beams, and a lot of manpower. Furthermore, not only is the construction period unavoidably long, but the work is carried out below the ground level, which is very dangerous.

【0003】この発明はこのような前期従来の課題を解
決するために提案されたもので、短期施工と安全施工を
可能にした地下構造物の構築工法を提供することを目的
とするものである。
[0003] This invention was proposed in order to solve the above-mentioned problems of the prior art, and its purpose is to provide a construction method for underground structures that enables short-term construction and safe construction. .

【0004】0004

【課題を解決するための手段】前記課題を解決するため
にこの発明にかかる地下構造物の構築工法は、山留め壁
を地下階の外壁とし、独立した連続壁を地下階の耐力壁
とし、かつ、支持杭を地下階の柱として地下構造物を構
築する。
[Means for Solving the Problems] In order to solve the above problems, the method for constructing an underground structure according to the present invention is such that a retaining wall is used as the outer wall of the basement floor, an independent continuous wall is used as the load-bearing wall of the basement floor, and , construct an underground structure using support piles as pillars of the basement floor.

【0005】[0005]

【実施例】以下、この発明を図示する一実施例に基づい
て説明すると、図1乃至図7はこの発明にかかる地下構
造物の構築工法を示すもので、図において番号1は山留
め壁、2は独立壁、そして、番号3は支持杭である。
[Embodiment] The present invention will be explained below based on an illustrated embodiment. Figs. 1 to 7 show a method of constructing an underground structure according to the present invention. In the figures, number 1 indicates a retaining wall, 2 is an independent wall, and number 3 is a support pile.

【0006】以下、施工方法を順をおって説明する。[0006] The construction method will be explained step by step below.

【0007】■  まず、地盤面を作業床として、地盤
中に山留め壁1、独立壁2および支持杭3を造成する。 山留め壁1は地下構造物の外壁となるものであり、地下
構造物の外周に沿って連続して施工する。また、独立壁
2は地下構造物の耐力壁となるものであり、支持杭3と
3との間および支持杭3と山留め壁1との間に山留め壁
1および支持杭3と一体的に施工する。そして、支持杭
3は地下構造物の柱となるものであり、前後左右に等ス
パンに構築する。
[0007] First, a retaining wall 1, an independent wall 2, and a support pile 3 are constructed in the ground using the ground surface as a working floor. The retaining wall 1 serves as the outer wall of the underground structure, and is constructed continuously along the outer periphery of the underground structure. In addition, the independent wall 2 serves as a load-bearing wall for the underground structure, and is constructed integrally with the retaining wall 1 and the retaining wall 3 between the supporting piles 3 and between the supporting pile 3 and the retaining wall 1. do. The support piles 3 serve as pillars of the underground structure, and are constructed with equal spans in the front, back, left and right directions.

【0008】また、山留め壁1、独立壁2および支持杭
3は原則としていずれも場所打ち鉄筋コンクリートによ
って支持地盤に達する深さまで構築し、支持杭3の柱脚
部には基礎部3aを設けることにより支持杭3の支持強
度を可能な限り高めるものとする(図2参照)。なお、
支持杭3は必ずしも場所打ちコンクリート構造である必
要はなく、PC杭や鋼杭などの既製杭を使用してもよい
Furthermore, in principle, the retaining wall 1, independent wall 2, and support pile 3 are all constructed of cast-in-place reinforced concrete to a depth that reaches the supporting ground, and by providing a foundation portion 3a at the base of the support pile 3. The support strength of the support pile 3 shall be increased as much as possible (see Figure 2). In addition,
The support pile 3 does not necessarily have to be a cast-in-place concrete structure, and ready-made piles such as PC piles and steel piles may be used.

【0009】■  続いて、山留め壁1、独立壁2およ
び支持杭3の上端部に鉄骨部材4を建て付け、当該鉄骨
部材4は地上階の柱5のアンカー部材とする。鉄骨部材
4にはH形鋼などの形鋼若しくは角形鋼管や円形鋼管な
どの鋼管を使用するものとし、山留め壁1、独立壁2お
よび支持杭3のコンクリート中に少なくと地下1階程度
の深さまで深く埋め込んで柱5の柱脚部の固定を完全な
ものとする。
[0009] Subsequently, a steel frame member 4 is erected at the upper ends of the retaining wall 1, independent wall 2, and support pile 3, and the steel frame member 4 is used as an anchor member for the column 5 on the ground floor. The steel frame members 4 shall be made of steel sections such as H-beams or steel pipes such as square steel pipes and circular steel pipes, and the concrete of the retaining walls 1, independent walls 2, and supporting piles 3 should be at least as deep as the first floor underground. The base of the column 5 is completely fixed by embedding it deeply.

【0010】■  続いて、地盤面を所定深さまで掘り
下げ、その掘り下げた部分に1階の梁6と床スラブ7を
構築する。梁6は鉄骨梁、PC梁或いは場所打ち鉄筋コ
ンクリート梁のいづれの形式でもよく、また、床スラブ
7もPC板構造若しくは場所打ち鉄筋コンクリート構造
のいづれの構造としてもよいが、梁6は鉄骨梁若しくは
PC梁とし、床スラブ7はPC板構造とするほうが現場
施工の簡略化、工期の短縮化が可能となる。
[0010] Next, the ground surface is dug to a predetermined depth, and the beams 6 and floor slabs 7 of the first floor are constructed in the dug-out portion. The beam 6 may be a steel beam, a PC beam, or a cast-in-place reinforced concrete beam, and the floor slab 7 may also have a PC board structure or a cast-in-place reinforced concrete structure, but the beam 6 may be a steel beam or a cast-in-place reinforced concrete beam. If the floor slab 7 is made of a beam and the floor slab 7 is made of a PC board structure, on-site construction can be simplified and the construction period can be shortened.

【0011】なお、1階の床スラブ7をフラットスラブ
とせず、梁を設ける構造としたのは、柱5の柱脚部の固
定度を高めて応力の伝達をスムーズにするためである。
[0011] The reason why the floor slab 7 on the first floor is not made of a flat slab but has a structure in which a beam is provided is to increase the degree of fixation of the base portion of the column 5 and to smoothen the transmission of stress.

【0012】■  続いて、今構築した梁6および床ス
ラブ7直下の地盤を地下一階の床スラブの位置までさら
に地盤を掘り下げる。かかる場合、山留め壁1が周囲の
法面の崩壊を防ぎ、梁6および床スラブ7が山留め壁1
の切り梁となるため、あえて山留め壁や切り梁を設ける
必要がない。
[0012] Next, the ground directly below the beam 6 and floor slab 7 that has just been constructed is further dug down to the position of the floor slab on the first basement floor. In such a case, the retaining wall 1 prevents the surrounding slope from collapsing, and the beam 6 and floor slab 7 prevent the retaining wall 1 from collapsing.
There is no need to intentionally install retaining walls or cut beams.

【0013】■  続いて、根切り底を平坦にし、その
上に地下1階の床スラブ8を場所打ち鉄筋コンクリート
構造若しくはPC板構造によって構築する。また、床ス
ラブ8は周囲の山留め壁1、独立壁2および支持柱3と
一体的に構築する。
[0013] Subsequently, the root cut bottom is made flat, and a floor slab 8 for the first basement floor is constructed on it using a cast-in-place reinforced concrete structure or a PC board structure. Furthermore, the floor slab 8 is constructed integrally with the surrounding retaining walls 1, independent walls 2, and support columns 3.

【0014】■  続いて、今造成した床スラブ8直下
の地盤を地下二階の床スラブの位置まで掘り下げる。か
かる場合には、地上一階の梁6および床スラブ7、さら
に地下一階の床スラブ8が山留め壁1の切り梁となるた
め、あえて切り梁を設ける必要がない。
[0014] Next, the ground immediately below the floor slab 8 just created is dug down to the position of the floor slab on the second basement floor. In such a case, the beams 6 and floor slabs 7 on the first floor above ground, and the floor slabs 8 on the first basement floor serve as the cut beams of the retaining wall 1, so there is no need to provide cut beams.

【0015】以下、同様にして地下階の床スラブの構築
と地盤の掘削とを交互に行うことによって地下最下階ま
で構築し、最下階の床スラブは中間階の床スラブより厚
くすることにより基礎スラブ9とする。また、地下階の
構築と並行して地上階の構築も行う(図5,6,7参照
)。
[0015] Thereafter, in the same manner, the construction of the basement floor slab and the ground excavation are performed alternately to construct the basement to the lowest floor, and the floor slab of the lowest floor is made thicker than the floor slab of the intermediate floor. Accordingly, the foundation slab 9 is obtained. Additionally, the ground floor will be constructed in parallel with the construction of the basement floor (see Figures 5, 6, and 7).

【0016】[0016]

【発明の効果】この発明は以上の構成からなるので、以
下の効果を有する。
[Effects of the Invention] Since the present invention has the above configuration, it has the following effects.

【0017】■  地上1階の床スラブを構築してしま
えば、これより下の地下階の施工は天候に全く左右され
ないで行うことができる。
[0017] Once the floor slab for the first floor above ground has been constructed, the construction of the basement floor below this can be carried out completely unaffected by the weather.

【0018】■  地下階の外壁となる山留め壁、耐力
壁となる独立壁および地下階の柱となる支持杭はすべて
地盤中で構築するため型枠工事を一切省略できる。また
、地盤の掘削に際し、地下階の各床スラブを山留め壁の
切り梁や支保工とすることができるため、切り梁や支保
工をあえて設ける必要がない。さらに、地下階の施工と
同時に地上階の施工も行うことができるため、工期の大
幅短縮および建設コストの大幅低減が図れる。
[0018] ■ The retaining wall that will be the outer wall of the basement floor, the independent wall that will be the load-bearing wall, and the support piles that will be the pillars of the basement floor will all be constructed in the ground, so any formwork work can be omitted. Furthermore, when excavating the ground, each floor slab of the basement floor can be used as a cut beam or support for a retaining wall, so there is no need to intentionally provide a cut beam or support. Furthermore, since the construction of the ground floor can be carried out at the same time as the construction of the basement floor, the construction period can be significantly shortened and the construction cost can be significantly reduced.

【0019】■  また、山留め壁を地下構造物の外壁
として、独立壁を地下構造物の耐力壁として、さらに、
支持杭を地下構造物の柱としてそのまま利用できるため
、きわめて経済的である。
[0019] Also, the retaining wall can be used as an outer wall of an underground structure, the independent wall can be used as a load-bearing wall of an underground structure, and
It is extremely economical because the support piles can be used as pillars for underground structures.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】地下構造物の構築工法の一工程を示す一部平面
図である。
FIG. 1 is a partial plan view showing one step of the underground structure construction method.

【図2】地下構造物の構築工法の一工程を示す一部縦断
面図である。
FIG. 2 is a partial vertical sectional view showing one step of the underground structure construction method.

【図3】地下構造物の構築工法の一工程を示す一部縦断
面図である。
FIG. 3 is a partial vertical sectional view showing one step of the underground structure construction method.

【図4】地下構造物の構築工法の一工程を示す一部縦断
面図である。
FIG. 4 is a partial vertical sectional view showing one step of the underground structure construction method.

【図5】地下構造物の構築工法の一工程を示す一部縦断
面図である。
FIG. 5 is a partial vertical sectional view showing one step of the underground structure construction method.

【図6】地下構造物の構築工法の一工程を示す一部縦断
面図である。
FIG. 6 is a partial vertical sectional view showing one step of the underground structure construction method.

【図7】地下構造物の構築工法の一工程を示す一部縦断
面図である。
FIG. 7 is a partial vertical sectional view showing one step of the underground structure construction method.

【符号の説明】[Explanation of symbols]

1…山留め壁、2…独立壁、3…独立杭、4…鉄骨部材
、5…柱、6…梁、7  …地上階の床スラブ、8…地
下1階の床スラブ、9…基礎スラブ。
1... Mountain retaining wall, 2... Independent wall, 3... Independent pile, 4... Steel frame member, 5... Column, 6... Beam, 7... Floor slab on the ground floor, 8... Floor slab on the first basement floor, 9... Foundation slab.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】山留め壁を地下階の外壁とし、独立した連
続壁を地下階の耐力壁とし、かつ、支持杭を地下階の柱
として地下構造物を構築することを特徴とする地下構造
物の構築工法。
Claim 1: An underground structure characterized in that the retaining wall is used as the outer wall of the basement floor, the independent continuous wall is the load-bearing wall of the basement floor, and the supporting pile is used as the column of the basement floor. construction method.
JP3011959A 1991-02-01 1991-02-01 Construction works for underground structure Pending JPH04247126A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3011959A JPH04247126A (en) 1991-02-01 1991-02-01 Construction works for underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3011959A JPH04247126A (en) 1991-02-01 1991-02-01 Construction works for underground structure

Publications (1)

Publication Number Publication Date
JPH04247126A true JPH04247126A (en) 1992-09-03

Family

ID=11792157

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3011959A Pending JPH04247126A (en) 1991-02-01 1991-02-01 Construction works for underground structure

Country Status (1)

Country Link
JP (1) JPH04247126A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57178033A (en) * 1981-04-27 1982-11-02 Ohbayashigumi Ltd Constructing method for building underground floor
JPS62125119A (en) * 1985-11-25 1987-06-06 Fudo Kenken Kk Construction of basement
JPS63151726A (en) * 1986-12-15 1988-06-24 Takenaka Komuten Co Ltd Underground structure consisting of continuous underground wall
JPS63280153A (en) * 1987-05-12 1988-11-17 清水建設株式会社 Underground inverted lining method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57178033A (en) * 1981-04-27 1982-11-02 Ohbayashigumi Ltd Constructing method for building underground floor
JPS62125119A (en) * 1985-11-25 1987-06-06 Fudo Kenken Kk Construction of basement
JPS63151726A (en) * 1986-12-15 1988-06-24 Takenaka Komuten Co Ltd Underground structure consisting of continuous underground wall
JPS63280153A (en) * 1987-05-12 1988-11-17 清水建設株式会社 Underground inverted lining method

Similar Documents

Publication Publication Date Title
JP2012107479A (en) Method for constructing underground and aboveground structure
JP2001262595A (en) Building construction method of underground building frame
JP2004100157A (en) Retaining wall structure and its construction method
KR0179708B1 (en) Working method for underground structure of a building
JP2868651B2 (en) Earth retaining method above existing underground structure
KR20000058239A (en) Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts
JPH0684690B2 (en) Building basement extension method
JP2000257088A (en) Earth retaining wall and its construction method
JPH04247126A (en) Construction works for underground structure
JP3109038B2 (en) Underground skeleton structure and construction method
JP6534026B2 (en) Seismic isolation building and its construction method
JPH1130053A (en) Construction method of base isolation building
KR100593203B1 (en) a deck supportframe and a construction methed
JPH07138972A (en) Construction method for underground skeleton
KR102392517B1 (en) Top-down method using by double beam system
CN111648375B (en) Inner supporting structure based on shear wall as support
JPH0742179A (en) Modified inversion placing construction method
JPH08291526A (en) Construction method for underground structure
JP3162654B2 (en) Construction method of floor slab support structure in building structure using pile as pillar
JP2555796B2 (en) Underground construction method using hollow PC columns
JPH0726567A (en) Underground beam footing construction method for house architecture
JPH0447021A (en) Construction method for sheathing guide pile
JPS6350491B2 (en)
JPH10152853A (en) Method of building underground structure and structure member used therein
JPH0492021A (en) Foundation structure of building and construction method thereof

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19950822