JPH04238919A - Construction of underground beam - Google Patents

Construction of underground beam

Info

Publication number
JPH04238919A
JPH04238919A JP3013047A JP1304791A JPH04238919A JP H04238919 A JPH04238919 A JP H04238919A JP 3013047 A JP3013047 A JP 3013047A JP 1304791 A JP1304791 A JP 1304791A JP H04238919 A JPH04238919 A JP H04238919A
Authority
JP
Japan
Prior art keywords
underground
sleeve body
shaft
underground beam
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3013047A
Other languages
Japanese (ja)
Inventor
Michio Hakiri
羽切 道雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP3013047A priority Critical patent/JPH04238919A/en
Publication of JPH04238919A publication Critical patent/JPH04238919A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To effectively construct the above underground beam for the underground portion of an existing facility by a method in which a sleeve is pressingly penetrated from one vertical pit to the other vertical pit, reinforcing bars are set inside, and concrete is packed into it. CONSTITUTION:Vertical pits 10A and 10B are formed in both ends of an underground beam 4 to be constructed. While connecting precast concrete sleeves 15A and 15B, they are penetrated from one vertical pit 10A to the other vertical pit 10B into the ground. When the tips of a series of the sleeves 15A and 15B reach the other vertical pit 10B, the inside of the sleeves 15A and 15B is excavated to form a cave, reinforcing bars are set in the cave, and concrete is packed into it. The underground beam 4 can thus be constructed for the underground portion of the existing facility while using the facility.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は地中梁を施工するための
方法に関し、特に、地上に存する既存の施設をそのまま
使用しながらその地下部分に地中梁を設ける場合に採用
して好適な地中梁の施工方法に関する。
[Industrial Application Field] The present invention relates to a method for constructing underground beams, and is particularly suitable for use when installing underground beams in the underground portion of existing above-ground facilities while using them as they are. Regarding construction methods for underground beams.

【0002】0002

【従来の技術】近年、地上に存する既存の建築物あるい
は線路や道路等の構造物の上方の空間を有効利用するこ
とを目的として、たとえば図6に示すように、既存施設
(図示例の場合は鉄道の線路)の上方を大スパンのトラ
スからなる人工地盤1により覆い、その人工地盤1上に
新たな建築物や構造物を建造することが考えられている
。 そして、そのような人工地盤1を、既存施設をそのまま
使用しながら(図示例のものでは鉄道の運行を停止する
ことなく)施工するための各種の工法が提案されつつあ
る。
[Prior Art] In recent years, for the purpose of effectively utilizing the space above existing buildings on the ground or structures such as railways and roads, existing facilities (in the illustrated example It is being considered to cover the upper part of the railway (railroad tracks) with an artificial ground 1 consisting of a large-span truss, and to construct new buildings and structures on the artificial ground 1. Various construction methods are being proposed for constructing such artificial ground 1 while using existing facilities as they are (in the illustrated example, without stopping railway operations).

【0003】0003

【発明が解決しようとする課題】ところで、上記のよう
な人工地盤1を既存施設の上方に設ける場合には、図6
に示すように、人工地盤1を支持するための柱2および
それら柱2に連なる杭3を既存施設の周囲に設ける必要
があることは勿論のこと、それら杭3の杭頭部どうし(
あるいは柱2の柱脚部どうし)を地中において連結する
ための地中梁4も不可欠なものである。ところが、それ
らの地中梁4は、既存施設をそのまま使用しながらその
地下部分に設けなければならず、しかも、そのような地
中梁4を施工するために必要な作業スペースを既存施設
の周囲に十分に確保することは困難であることが通常で
あり、したがって、そのような条件下で地中梁4を施工
し得る有効な手段は未だ提供されていないことが実状で
ある。
[Problem to be Solved by the Invention] By the way, when the above-mentioned artificial ground 1 is installed above an existing facility, as shown in FIG.
As shown in , it is necessary to install pillars 2 to support the artificial ground 1 and piles 3 connected to these pillars 2 around the existing facility, as well as to ensure that the pile heads of these piles 3 (
An underground beam 4 for connecting the bases of the columns 2 underground is also essential. However, these underground beams 4 must be installed underground while using the existing facilities as they are, and the work space required to construct such underground beams 4 must be constructed around the existing facilities. Generally, it is difficult to secure a sufficient amount of soil under such conditions, and therefore, the reality is that no effective means for constructing underground beams 4 under such conditions has yet been provided.

【0004】本発明は上記の事情に鑑みてなされたもの
で、たとえば既存施設の上方に人工地盤を設けるに当た
って、既存施設を使用しながらその地下部分に地中梁を
施工するための有効な施工方法を提供することを目的と
している。
The present invention has been made in view of the above circumstances, and provides an effective construction method for constructing underground beams in the underground portion of the existing facility while using the existing facility, for example, when constructing an artificial ground above the existing facility. The purpose is to provide a method.

【0005】[0005]

【課題を解決するための手段】本発明は、地中に鉄筋コ
ンクリート造の地中梁を施工する方法であって、施工す
るべき地中梁の両端部の位置にそれぞれ設けられた立坑
の一方から、プレキャストコンクリート製のスリーブ体
を順次連結しながら他方の立坑に向けて地中に圧入して
いき、それら一連のスリーブ体の先端が他方の立坑に到
達したらそれらスリーブ体の内部を掘削して空洞となし
、次いで、スリーブ体の内側に鉄筋を配してコンクリー
トを充填することにより、それらスリーブ体を外層部と
する地中梁を形成することを特徴とするものである。
[Means for Solving the Problems] The present invention is a method of constructing an underground beam made of reinforced concrete underground, in which the method is carried out from one side of a vertical shaft provided at both ends of the underground beam to be constructed. , Sleeve bodies made of precast concrete are sequentially connected and pressed into the ground toward the other shaft, and when the tips of the series of sleeve bodies reach the other shaft, the insides of the sleeve bodies are excavated to create a cavity. The method is characterized in that reinforcing bars are placed inside the sleeve body and then filled with concrete to form an underground beam having the sleeve body as the outer layer.

【0006】[0006]

【実施例】以下、本発明方法の実施例を図1ないし図5
を参照しながら説明する。図1は、図6に示したような
人工地盤1を既存の鉄道線路の上方に設けるに当たって
、その鉄道線路の地下部分に地中梁4を施工している状
態を示すものである。
[Example] Examples of the method of the present invention are shown below in Figures 1 to 5.
This will be explained with reference to. FIG. 1 shows a state in which an underground beam 4 is being constructed in the underground portion of the railway track when an artificial ground 1 as shown in FIG. 6 is provided above the existing railway track.

【0007】この場合、まず杭3を施工し、施工するべ
き地中梁4の両端部が連結される対の杭3,3の上部に
それぞれ立坑10A,10Bを設ける。杭3の形式は適
宜で良いがたとえば現場打ちコンクリート杭とすれば良
い。また、立坑10A,10Bを掘削するに先立ってシ
ートパイルによる山留壁11を設けるが、一方の立坑1
0A(図1において左側の立坑)の壁面にはH鋼パイル
による反力壁12を設けておく。
In this case, the piles 3 are first constructed, and vertical shafts 10A and 10B are respectively provided above the pair of piles 3 and 3 to which both ends of the underground beam 4 to be constructed are connected. The pile 3 may be of any suitable type, and may be, for example, a cast-in-place concrete pile. In addition, prior to excavating the shafts 10A and 10B, a retaining wall 11 made of sheet piles is provided, but one shaft 1
A reaction wall 12 made of H steel piles is provided on the wall of 0A (the left shaft in FIG. 1).

【0008】そして、その反力壁12より反力をとるこ
とによって、この一方の立坑10Aからスリーブ体15
Aを他方の立坑10Bに向けて油圧ジャッキ13により
地中に圧入していく。また、そのスリーブ体15Aを圧
入したら、その後部に他のスリーブ体15Bを連結して
さらに圧入していく。なお、図1における符号14は杭
3の上部に設けられて圧入するべきスリーブ体15A,
15Bを支持してスライドさせるための仮設のベース板
である。
By taking the reaction force from the reaction wall 12, the sleeve body 15 is removed from the one shaft 10A.
A is forced into the ground by a hydraulic jack 13 toward the other shaft 10B. Further, once the sleeve body 15A is press-fitted, another sleeve body 15B is connected to the rear part thereof and further press-fitted. Note that the reference numeral 14 in FIG. 1 indicates a sleeve body 15A, which is provided on the upper part of the pile 3 and is to be press-fitted.
This is a temporary base plate for supporting and sliding 15B.

【0009】それらスリーブ体15A,15Bは、最終
的には地中梁4の外層部となるプレキャストコンクリー
ト製のものであって、最初に圧入されるスリーブ体15
Aは図2および図3に示すように先端に刃口16が形成
されているとともに後部には他のスリーブ体15Bを連
結するための嵌合溝17が形成されたものとなっており
、また、そのスリーブ体15Aの後部に連結される他の
スリーブ体15Bは、図4および図5に示すように、先
端部に刃口16に代わって上記スリーブ体15Aの嵌合
溝17に嵌入し得る嵌合凸部18が形成されている他は
上記のスリーブ体15Aと同様に形成されたものとなっ
ている。そして、スリーブ体15Aとスリーブ体15B
、およびスリーブ体15Bどうしは嵌合溝17と嵌合凸
部18とを嵌合させてボルトにより締結されることによ
って、全体として真っ直ぐとなる状態で強固に連結され
るようになっている。
These sleeve bodies 15A and 15B are made of precast concrete, which will eventually become the outer layer of the underground beam 4, and the sleeve body 15 is press-fitted first.
As shown in FIGS. 2 and 3, A has a cutting edge 16 formed at the tip and a fitting groove 17 formed at the rear for connecting another sleeve body 15B. As shown in FIGS. 4 and 5, another sleeve body 15B connected to the rear part of the sleeve body 15A can fit into the fitting groove 17 of the sleeve body 15A at its tip instead of the blade opening 16. The sleeve body 15A is formed in the same manner as the sleeve body 15A described above except that the fitting convex portion 18 is formed. Then, the sleeve body 15A and the sleeve body 15B
, and the sleeve body 15B are firmly connected in a straight state as a whole by fitting the fitting groove 17 and the fitting protrusion 18 and fastening them with bolts.

【0010】上記のように、一方の立坑10A内から他
方の立坑10Bに向けてスリーブ体15Aを油圧ジャッ
キ13により圧入し、その後部に他のスリーブ体15B
を連結してはさらに圧入していき、それを順次繰り返し
て一連のスリーブ体の先端を他方の立坑10Bに到達さ
せる。その後、油圧ジャッキ13を撤去し、一連のスリ
ーブ体の内部を掘削して空洞となし、その内部に梁鉄筋
を配筋し、その梁鉄筋を必要に応じて杭鉄筋や柱鉄筋と
を締結した後、それらスリーブ体の内部と杭頭部にコン
クリートを打設する。これにより、地中梁4が杭3の頭
部に一体化された状態で形成される。そこで、図6に示
したように、杭3の上部に柱2を施工し、その柱2に支
持して人工地盤1を施工すれば良い。
As described above, the sleeve body 15A is press-fitted from the inside of one shaft 10A toward the other shaft 10B using the hydraulic jack 13, and the other sleeve body 15B is inserted into the rear part of the sleeve body 15A.
are connected and further press-fitted, and this process is repeated one after another until the tips of the series of sleeve bodies reach the other shaft 10B. After that, the hydraulic jack 13 was removed, the inside of the series of sleeve bodies was excavated to form a cavity, beam reinforcing bars were arranged inside, and the beam reinforcing bars were connected to pile reinforcing bars and column reinforcing bars as necessary. After that, concrete is poured into the inside of the sleeve body and the pile head. Thereby, the underground beam 4 is formed integrally with the head of the pile 3. Therefore, as shown in FIG. 6, a pillar 2 may be constructed on top of the pile 3, and the artificial ground 1 may be constructed while being supported by the pillar 2.

【0011】以上の施工方法によれば、地中梁4を施工
するに当たっては既存施設の周囲に立坑10A,10B
を設けるのみで、それ以外の部分については地上から掘
削を行う必要が全くなく、したがって、既存施設をその
まま使用しながら地中梁4を施工することができる。勿
論、スリーブ体15A,15B…を連結して地中に圧入
していくので、地中に空洞が生じることもなく、地盤沈
下等を生じる恐れもない。
According to the above construction method, when constructing the underground beam 4, the vertical shafts 10A and 10B are installed around the existing facility.
There is no need to excavate any other parts from the ground, and therefore the underground beam 4 can be constructed while using the existing facilities as they are. Of course, since the sleeve bodies 15A, 15B... are connected and press-fitted into the ground, no cavities will be created in the ground, and there is no risk of ground subsidence or the like.

【0012】なお、以上の説明で明らかであろうが、立
坑10Aの水平断面積はスリーブ体15A,15Bを圧
入方向に向けた状態で横置きできるように設定すれば良
く、したがって、スリーブ体15A,15Bの長さ寸法
を十分に短かくすれば、立坑10Aの水平断面積も立坑
10Bと同様に杭3の断面積よりやや大きい程度とする
ことで済み、既存施設の周囲に十分な作業スペースを確
保し得ないような狭小な敷地に対しても適用することが
できる。また、逆に、既存施設の周囲に十分な作業スペ
ースを確保できる場合には、立坑10Aの水平断面積を
大きくして長いスリーブ体を用いることもでき、その場
合にはスリーブ体どうしの連結箇所を少なくすることが
できて作業効率が良くなるという利点がある。しかし、
余り長いスリーブ体を用いることは、その搬送やハンド
リングが困難となるので、その点も考慮して最適な長さ
に設定すれば良い。
As should be clear from the above description, the horizontal cross-sectional area of the shaft 10A may be set so that the sleeve bodies 15A, 15B can be placed horizontally with the sleeve bodies 15A and 15B facing in the press-fitting direction. , 15B are made sufficiently short, the horizontal cross-sectional area of the shaft 10A can be made slightly larger than the cross-sectional area of the pile 3, similar to the shaft 10B, and there is enough work space around the existing facility. It can also be applied to narrow sites where it is impossible to secure. Conversely, if sufficient work space can be secured around the existing facility, it is possible to increase the horizontal cross-sectional area of the shaft 10A and use a long sleeve body, and in that case, the connection points between the sleeve bodies This has the advantage of being able to reduce the amount of work and improve work efficiency. but,
If a sleeve body is too long, it will be difficult to transport and handle it, so it is sufficient to take this into account and set the sleeve body to an optimum length.

【0013】[0013]

【発明の効果】以上で説明したように、本発明は、プレ
キャストコンクリート製のスリーブ体を一方の立坑にお
いて順次連結しながら他方の立坑に向けて地中に圧入し
ていくことにより、それら一連のスリーブ体の先端を他
方の立坑に到達させ、そして、それら一連のスリーブ体
の内部に配筋してコンクリートを充填することで地中梁
を形成するので、既存施設の周囲に立坑を設けるのみで
それ以外の部分については地上から掘削を行う必要が全
くなく、したがって、既存施設をそのまま使用しながら
地中梁を施工することができるとともに、地中に空洞が
生じることがないので地盤沈下等を生じる恐れもなく、
しかも、十分に短いスリーブ体を用いることにより立坑
の水平断面積も小さくて済むのでさほどの作業スペース
を必要としないという利点があり、既存施設の上方に人
工地盤を設ける場合等に採用して好適である。
[Effects of the Invention] As explained above, the present invention enables a series of precast concrete sleeve bodies to be connected in sequence in one shaft and press-fitted into the ground toward the other shaft. The tip of the sleeve body reaches the other shaft, and an underground beam is formed by arranging reinforcement inside the series of sleeve bodies and filling it with concrete, so you can simply install a shaft around the existing facility. For other parts, there is no need to excavate from the ground. Therefore, it is possible to construct underground beams while using existing facilities as is, and since no cavities are created underground, ground subsidence etc. can be prevented. There is no fear that this will occur,
Moreover, by using a sufficiently short sleeve body, the horizontal cross-sectional area of the shaft can be small, so it has the advantage of not requiring much work space, and is suitable for use when constructing artificial ground above existing facilities. It is.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】本発明方法により地中梁を施工している状態を
示す立断面図である。
FIG. 1 is an elevational sectional view showing a state in which an underground beam is being constructed by the method of the present invention.

【図2】同方法において用いるスリーブ体の側断面図で
ある。
FIG. 2 is a side sectional view of a sleeve body used in the same method.

【図3】同スリーブ体の正面図である。FIG. 3 is a front view of the sleeve body.

【図4】同方法において用いる他のスリーブ体の側断面
図である。
FIG. 4 is a side sectional view of another sleeve body used in the same method.

【図5】同スリーブ体の正面図である。FIG. 5 is a front view of the sleeve body.

【図6】既存の線路の上方に人工地盤を設ける場合の概
念図である。
FIG. 6 is a conceptual diagram when an artificial ground is provided above an existing railway line.

【符号の説明】[Explanation of symbols]

4  地中梁 10A,10B  立坑 12  反力壁 13  油圧ジャッキ 15A,15B  スリーブ体。 4 Underground beam 10A, 10B Vertical shaft 12 Reaction wall 13 Hydraulic jack 15A, 15B Sleeve body.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】  地中に鉄筋コンクリート造の地中梁を
施工する方法であって、施工するべき地中梁の両端部の
位置にそれぞれ設けられた立坑の一方から、プレキャス
トコンクリート製のスリーブ体を順次連結しながら他方
の立坑に向けて地中に圧入していき、それら一連のスリ
ーブ体の先端が他方の立坑に到達したらそれらスリーブ
体の内部を掘削して空洞となし、次いで、スリーブ体の
内側に鉄筋を配してコンクリートを充填することにより
、それらスリーブ体を外層部とする地中梁を形成するこ
とを特徴とする地中梁の施工方法。
Claim 1: A method for constructing a reinforced concrete underground beam underground, the method comprising: inserting a precast concrete sleeve body from one of vertical shafts provided at both ends of the underground beam to be constructed; The sleeve bodies are pressed into the ground toward the other shaft while being connected one after another, and when the tips of the sleeve bodies reach the other shaft, the insides of the sleeve bodies are excavated to form a cavity, and then the sleeve bodies are pressed into the ground toward the other shaft. A method for constructing an underground beam, characterized by forming an underground beam having the sleeve body as an outer layer by arranging reinforcing bars inside and filling the concrete with concrete.
JP3013047A 1991-01-10 1991-01-10 Construction of underground beam Pending JPH04238919A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3013047A JPH04238919A (en) 1991-01-10 1991-01-10 Construction of underground beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3013047A JPH04238919A (en) 1991-01-10 1991-01-10 Construction of underground beam

Publications (1)

Publication Number Publication Date
JPH04238919A true JPH04238919A (en) 1992-08-26

Family

ID=11822209

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3013047A Pending JPH04238919A (en) 1991-01-10 1991-01-10 Construction of underground beam

Country Status (1)

Country Link
JP (1) JPH04238919A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017089226A (en) * 2015-11-10 2017-05-25 株式会社竹中工務店 Foundation construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017089226A (en) * 2015-11-10 2017-05-25 株式会社竹中工務店 Foundation construction method

Similar Documents

Publication Publication Date Title
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JP3166007B2 (en) Underground structure and its construction method
JPH04238919A (en) Construction of underground beam
JP3648664B2 (en) Building renovation method and building
JPS63280153A (en) Underground inverted lining method
JP3790310B2 (en) Construction method of the building by the prior construction of steel frame
JP2005282115A (en) Construction method of steel element concrete type underground structure
JP2860751B2 (en) Construction method of underpass introduction section
JP3012896B2 (en) Reverse cutting method combined with advance cutting
JP3406370B2 (en) Horizontal shaft construction method
JPH0584773B2 (en)
JPS61211497A (en) Support construction method of existing underground structure
JPS6012494B2 (en) Stray beam jack-up method
JPH0114400B2 (en)
JPH10159094A (en) Timbering structure of earth retaining wall
JP3171716B2 (en) Foundation construction method on inclined surface
JP3646698B2 (en) Construction method for underground structures
JPH09256366A (en) Permanent sub-structural column used for pliers and underground building construction making use thereof
JP3457440B2 (en) Building construction method using earth anchor
JPH02266016A (en) Structural process of underground concrete body of building
JPH06220872A (en) Underground beam construction method
JPH0466965B2 (en)
JPH06146308A (en) Construction method of underground skeleton
JPH0776508B2 (en) Existing tunnel protection method
JPH0430026A (en) Constructing method of underground structure

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19990309