JPH0347321A - Shore strut and underground construction work by composite steel beam - Google Patents

Shore strut and underground construction work by composite steel beam

Info

Publication number
JPH0347321A
JPH0347321A JP1180531A JP18053189A JPH0347321A JP H0347321 A JPH0347321 A JP H0347321A JP 1180531 A JP1180531 A JP 1180531A JP 18053189 A JP18053189 A JP 18053189A JP H0347321 A JPH0347321 A JP H0347321A
Authority
JP
Japan
Prior art keywords
beams
floor
steel
steel beam
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1180531A
Other languages
Japanese (ja)
Other versions
JP2757209B2 (en
Inventor
Tatsuo Sato
龍生 佐藤
Kazumi Sakai
酒井 和三
Sumio Maezawa
澄夫 前沢
Arata Furuta
古田 新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP1180531A priority Critical patent/JP2757209B2/en
Publication of JPH0347321A publication Critical patent/JPH0347321A/en
Application granted granted Critical
Publication of JP2757209B2 publication Critical patent/JP2757209B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To make the lift-down work of each steel beam easier as well as simplify the construction work by using steel beams for the first stair and underground stair floors in which the ends of the adjacent beams are connected with each other by winding around structural straight columns with them. CONSTITUTION:Structural straight columns 3 are wound with beam ends 4a and 4'a to form a corner bracing, where steel beams 4 and 4' for the first stair and underground stair floors are built connectedly to each other. After the primary excavation, the beam 4 is lowered to a given position under the guidance of the columns 3 and temporarily supported on the columns 3, and the beams 4' are temporarily set under the beam 4. The secondary excavation is made by using the beam 4 as a shore strut, and the beam 4' is lowered to a given position and set on the columns 3 to use it as a shore strut. The same operations are repeated for construction until the lowest stair, and concrete is orderly placed from the lower stairs to construct an underground structure.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は合成鉄骨梁を切梁として兼用する地下躯体の構
築工法に係るものである。
DETAILED DESCRIPTION OF THE INVENTION (Industrial Field of Application) The present invention relates to a construction method for an underground framework in which synthetic steel beams also serve as struts.

(従来の技術) 従来、地下の躯体工事は、通常H1imlを使用した切
梁、腹起しを基盤目状に配設して地下掘削を行っている
。この際、前記切梁はあくまでも仮設であるため、躯体
打設時、あるいは打設後に解体撤去され、場外に搬出さ
れる。
(Prior Art) Conventionally, in underground framework construction, underground excavations are usually carried out by arranging struts and stand-up beams using H1iml in the shape of a foundation. At this time, since the struts are only temporary, they are dismantled and removed during or after the construction of the framework and are carried outside the site.

また地下階の上階から順次コンクリートを打設する逆打
ち工法が行なわれている。
In addition, a reverse pouring method is used, in which concrete is poured sequentially from the upper floor of the basement.

(発明が解決しようとする課題) 前者の方法においては、切梁を解体撤去し、場外に搬出
するために多大の手間と時間とを要し、工期が延引する
(Problems to be Solved by the Invention) In the former method, a great deal of effort and time is required to dismantle and remove the struts and carry them out of the site, prolonging the construction period.

また後者の方法においては、地下階の上階から順次コン
クリートを打設するため、柱や壁がすべて逆打ちとなり
、コンクリートの打ち継ぎ処理が極めて困難である。
In addition, in the latter method, since concrete is poured sequentially from the upper floor of the basement floor, all columns and walls are poured backwards, making it extremely difficult to pour concrete.

本発明は前記従来技術の有する問題点に鑑みて提案され
たもので、その目的とする処は、施工が大幅に省力化さ
れ、施工上皿に構造上信転度の高い合成鉄骨梁による切
梁兼用地下工法を提供する点にある。
The present invention has been proposed in view of the problems of the prior art, and its purpose is to significantly save labor in construction, and to use synthetic steel beams with high structural reliability for the construction top plate. The point is that it provides an underground construction method that can also be used as a beam.

(課題を解決するための手段) 前記の目的を達成するため、本発明に係る合成鉄骨梁に
よる切梁兼用地下工法によれば、山留め壁と抗及び構真
−柱を建込み、1次掘削したのち、梁端部が前記構真柱
を取り巻くように迂回された相隣る梁同士を互いに緊結
した1階床鉄骨梁を、前記構真柱を案内として所定位置
まで下降せしめて同構真柱に仮支持し、前記1階床鉄骨
梁の下部に同梁と同様に構成された地下階鉄骨梁を仮置
きし、次いで前記1階床鉄骨梁を切梁として作用させて
2次掘削し、同鉄骨梁の下に仮置きした地下1階床鉄骨
梁を所定位置まで下降せしめ、前記構真柱にセットして
切梁として作用させ、以下前記同様の工程を反復して最
下階まで施工したのち、下階より順にコンクリートを打
設して地下躯体を横築するものである。
(Means for Solving the Problems) In order to achieve the above-mentioned object, according to the underground construction method using synthetic steel beams according to the present invention, retaining walls, shafts, and structural pillars are erected, and the first excavation is carried out. After that, the first floor steel beams, whose beam ends are detoured around the structural pillars and which are tied to each other, are lowered to a predetermined position using the structural pillars as a guide. Temporarily supported by columns, a basement floor steel beam configured in the same manner as the first floor steel beam was temporarily placed below the first floor steel beam, and then secondary excavation was performed using the first floor steel beam as a strut. The first basement floor steel beam, which had been temporarily placed under the steel beam, was lowered to a predetermined position, set on the structural pillar, and acted as a strut, and the same process was repeated until the bottom floor was reached. After construction is completed, concrete will be poured in order from the lower floors and the underground framework will be built horizontally.

(作用) 本発明によれば前記したように、山留め壁と抗及び構真
柱を建込んで1次掘削したのち、梁端部が前記構真柱を
貫通することなく、間柱を取り巻くように迂回した相隣
る粱同志を互いに緊結して1階床鉄骨梁を構成し、同1
階床鉄骨梁を前記構真柱を案内として同社に沿って所要
位置にまで下降せしめ、同位置において前記横真柱に仮
支持せしめるとともに、前記1階床鉄骨梁の下部に同乗
と同様に構成された下階鉄骨梁を仮置きする。
(Function) According to the present invention, as described above, after the retaining walls, shafts, and structural pillars are erected and the primary excavation is carried out, the beam ends do not pass through the structural pillars, but surround the studs. The first-floor steel beams are constructed by connecting the detoured adjoining pieces of steel to each other.
The floor steel beams are lowered along the line to a required position using the structural pillars as guides, and are temporarily supported by the horizontal pillars at the same position, and are placed under the first floor steel beams in the same manner as in the same structure. Temporarily place the steel beams on the lower floor.

次いで前記1階床鉄骨梁に切梁を兼用せしめて2次掘削
したのち、同1階床鉄骨梁の下に仮置していた地下1階
床鉄骨梁を、前記横真柱を案内として所定位置まで下降
し、前記構真柱にセットして切梁として作用せしめ、以
下前記同様の工程を反復して最下階まで施工する。
Next, after secondary excavation was carried out using the steel beams for the first floor floor which also served as cut beams, the steel beams for the first basement floor, which had been temporarily placed under the steel beams for the first floor floor, were placed in place using the horizontal straight columns as guides. It is lowered to the position and set on the structural pillar to act as a strut, and the same steps as described above are repeated until the bottom floor is constructed.

この際柱梁の仕口部における前記鉄骨梁と構真柱との空
き寸法が大きいので、地下階の鉄骨梁のリフトダウンが
容易に行なわれる。
At this time, since the space between the steel beam and the structural column at the joint between the columns and beams is large, the steel beam on the basement floor can be easily lifted down.

而して前記鉄骨梁は、前記したように端部で構真柱を取
り巻く形で迂回しており、梁同志が互いに緊結されてお
り、所定位置において構真柱に仮受けされている状態で
切梁として働くように構成されているので、構真柱の四
方より鉄骨梁に軸力が働き、一方の梁からの力は45°
に別れて左右の鉄骨梁に伝達され、更にこの伝達力は4
5°分岐して反対側の梁に伝達され、反対側からの力と
釣合い、前記鉄骨梁は切梁としての機能を確実に発揮す
る。
As described above, the steel beams are detoured around the structural pillars at their ends, the beams are tightly connected to each other, and temporarily supported by the structural pillars at predetermined positions. Since it is configured to act as a strut, axial force acts on the steel beam from all sides of the structural column, and the force from one beam is 45°.
The force is divided into two and transmitted to the left and right steel beams, and this transmitted force is further increased to 4
The force is branched at 5° and transmitted to the beam on the opposite side, and the force from the opposite side is balanced, so that the steel beam reliably functions as a strut.

かくして最下階までの施工が完了したのち、下階から順
にコンクリートを打設して地下製体を構築するものであ
るが、この際、切梁として使用された前記梁鉄骨がスラ
ブコンクリートと一体化され、合成梁として躯体の一部
を構成し、従って躯体の完成後、撤去、搬出する必要が
ない。
After the construction to the lowest floor is completed, concrete is poured in order from the lower floor to construct an underground structure, but at this time, the steel beam used as the strut is integrated with the slab concrete. It forms part of the frame as a composite beam, so there is no need to remove or transport it after the frame is completed.

(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.

従来の逆打ち工法と同様に、山留め壁(1)と抗(2)
または深礎及び構真柱(3)を建込む、(第1図参照)
次いで1次掘削として所定深さまで掘削し、1階床鉄骨
梁(4)及び下階鉄骨梁(4′)を前記横真柱(3)に
沿って間柱(3)を案内として下降せしめ、1階床鉄骨
梁(4)を構真柱(3)における所定位置において、同
社(3)に取付けた仮受ブラケット(5)に支持させ、
地下階床鉄骨梁を順次吊り材(6)を介して前記1階床
鉄骨梁(4)より懸吊し、仮置する。(第2図参照)な
お図示の実施例においては説明を筒略化するため、地下
1階床鉄骨梁(4′)のみ示されている。
Similar to the conventional reverse construction method, retaining walls (1) and counters (2)
Or erect a deep foundation and structural pillars (3) (see Figure 1)
Next, as primary excavation, excavation is carried out to a predetermined depth, and the first floor steel beam (4) and the lower floor steel beam (4') are lowered along the horizontal straight column (3) using the stud (3) as a guide. The floor steel beam (4) is supported at a predetermined position on the structure pillar (3) by the temporary support bracket (5) installed by the company (3),
The underground floor steel beams are sequentially suspended from the first floor steel beams (4) via hanging members (6) and temporarily placed. (See FIG. 2) In the illustrated embodiment, only the first basement floor steel beam (4') is shown to simplify the explanation.

前記各鉄骨梁(4) (4’lは第5図及び第6図に示
すように、梁端部(4a) (イ8)で構真柱(3)を
取り巻くように迂回した火打状に形成され、相隣る梁同
士が溶接またはボルト等で互いに緊結されている。
Each of the above-mentioned steel beams (4) (4'l is a flint-shaped structure with a detour surrounding the main pillar (3) at the beam end (4a) (A8), as shown in Figures 5 and 6) Adjacent beams are tightly connected to each other by welding or bolts.

次いで前記11床鉄骨梁(4)を切梁として作用させて
2次掘削を開始し、地下1階レベルより所定深さまで掘
削したのち、前記1階床鉄骨梁(4)の下に仮置きした
地下1階床鉄骨梁(4′)を構真柱(3)を案内として
下降し、所定の位置に間柱(3)に取付けた仮受ブラケ
ット(5)に支持し、前記鉄骨梁(4′)を切梁として
作用させる。(第3図参照)以下前記と同様の工程を反
復して最下階まで施工したのち、通常の地上階躯体の場
合と同様に下階から順にコンクリートを打設して、地下
躯体を完成させる。(第4図参照) 図中(7)は基礎梁、(8)は地下壁、(9)は地下階
床コンクリート、00)は1階床コンクリート、θ1)
は梁コンクリート、O′lJは柱コンクリート、03)
は社主筋、Iはフープ筋である。
Next, secondary excavation was started using the 11th floor steel beam (4) as a strut, and after excavating to a predetermined depth from the 1st floor underground level, it was temporarily placed under the 1st floor steel beam (4). The first basement floor steel beam (4') is lowered using the structural pillar (3) as a guide, and is supported at a predetermined position by the temporary support bracket (5) attached to the stud (3). ) to act as a strut. (Refer to Figure 3) After repeating the same process as above until the bottom floor is constructed, concrete is poured from the bottom floor in order as in the case of a normal above-ground floor structure to complete the underground structure. . (See Figure 4) In the figure, (7) is the foundation beam, (8) is the basement wall, (9) is the basement floor concrete, 00) is the first floor concrete, θ1)
is beam concrete, O'lJ is column concrete, 03)
is for company owners, and I is for hoops.

なお前記鉄骨梁(4)(41と構真柱(3)との仕口部
においては、両部材間の空き寸法が大きいので、下階の
鉄骨梁(4′)のリフトダウンが容易になり、更に従来
の逆打ち工法で要求される構真柱の建方精度も本方法で
は比較的ラフな精度で施工可能となる。
In addition, at the joint between the steel beam (4) (41) and the structural pillar (3), there is a large gap between the two members, making it easy to lift down the steel beam (4') on the lower floor. Moreover, with this method, it is possible to construct structural pillars with relatively rough accuracy, which is required by the conventional reverse casting method.

なお前記各鉄骨梁(4)(41を構真柱(3)の仮受ブ
ラケット(5)に支持して切梁として作用させる場合、
4方から前記鉄骨梁に軸力が作用し、一方向からの力は
梁先端で45°に別れて左右の梁に伝達され、更に分岐
して反対側の梁に伝達され、反対側からの力と釣合う。
In addition, when each of the steel beams (4) (41) is supported by the temporary support bracket (5) of the structural pillar (3) and acts as a strut,
Axial forces act on the steel beam from four directions, and the force from one direction is split at a 45° angle at the tip of the beam and transmitted to the left and right beams, further divided and transmitted to the beam on the opposite side, and the force from the other side is balance with power.

(発明の効果) 本発明によれば前記したように、構真柱を案内として同
社に沿ってリフトダウンされる1階床鉄骨梁及び地下階
床鉄骨梁を、梁端部が前記構真柱を取り巻くように迂回
した相隣る梁同士を互いに緊結して構成したことによっ
て、仕口部における構真柱と前記各鉄骨梁との空き寸法
が大となり、同各鉄骨梁のリフトダウンが容易になり、
更に構真柱の精度も、従来の逆打工法におけるような厳
密な精度が要求されることがなく、施工が簡略化される
(Effects of the Invention) According to the present invention, as described above, when the first floor steel beam and the basement floor steel beam are lifted down along the same direction using the structural pillar as a guide, the beam ends are aligned with the structural pillar. By configuring adjacent beams that are detoured to surround each other and tightly connected to each other, the space between the structural pillar and each of the steel beams at the joint part is large, making it easy to lift down the steel beams. become,
Furthermore, the precision of the structural pillars does not require the same exact precision as in the conventional reverse hammer construction method, which simplifies construction.

而して前記1階床鉄骨梁を、構真柱を案内として所定位
置まで下降せしめ、当該位置で構真柱に仮支持するとと
もに、前記鉄骨梁の下部に地下階床鉄骨梁を仮置きし、
前記1階床鉄骨梁を切梁として作用させて2次掘削し、
地下1階床鉄骨梁を所定位置まで下降して前記構真柱に
セットし、切梁として作用させ、以下前記同様の工程を
反復して最下階まで施工するものであり、前記鉄骨梁を
切梁として作用させる場合、同鉄骨梁間の応力の伝達が
円滑に行なわれるものであり、前記鉄骨梁が切梁として
の機能を十分に発揮し、工事が円滑且つ安全に行なわれ
る。
Then, the first floor steel beam is lowered to a predetermined position using the structural pillar as a guide, and is temporarily supported by the structural pillar at that position, and the basement floor steel beam is temporarily placed below the steel beam. ,
Perform secondary excavation using the first floor steel beam as a strut,
The steel beams for the first basement floor are lowered to a predetermined position, set on the structural pillars, and act as struts, and the same process described above is repeated until the lowest floor is constructed. When acting as a strut, stress transmission between the steel beams is carried out smoothly, the steel beams fully exhibit their function as a strut, and construction work can be carried out smoothly and safely.

か(して最下階まで施工したのち、下階から順次コンク
リートを打設して地下躯体を完成するようにしたので、
柱コンクリートは順打ちされ、また前記鉄骨梁の端部が
柱を貫通することなく、同社を取り巻くように迂回して
いるので、柱鉄筋の配筋、コンクリート打設が鉄骨梁に
邪魔されることなく、高品質の柱コンクリートの打設が
可能となる。
After construction was completed to the lowest floor, concrete was poured sequentially from the lower floor to complete the underground structure.
The column concrete is poured in order, and the ends of the steel beams do not penetrate the columns, but instead go around the company, so the steel beams do not interfere with column reinforcement and concrete pouring. This makes it possible to cast high-quality column concrete.

また前記したように、切梁として使用された鉄骨梁はス
ラブコンクリートと一体化され、合成梁として地下躯体
の一部を構成するので、同躯体の完成後撤去、搬出する
必要がなく、労務が軽減され、工期が縮減されるととも
に、工費が節減される。
Furthermore, as mentioned above, the steel beams used as struts are integrated with the slab concrete and form part of the underground framework as composite beams, so there is no need to remove or transport them after the framework is completed, reducing labor. This reduces construction time and costs.

【図面の簡単な説明】[Brief explanation of drawings]

第1図乃至第4図は本発明に係る合成鉄骨梁による切梁
兼用地下工法の一実施例の工程を示す縦断面図、第5図
は掘削時における切梁として作用する鉄骨梁と構真柱と
の関係を示す平面図で第6図の矢視V−V図、第6図は
その側面図で第5図の矢視vt−vt図、第7図は地下
躯体完成時の柱梁仕口部を示す平面図で第8図の矢視■
−■図、第8図はその縦断面図で第7図の矢視■−■図
である。 (1)・・・山留め壁、   (2)・・・杭、(3)
−・・構真柱、    (4)・・・1階床鉄骨梁、(
4a)・・・1階鉄骨梁の端部、 (4’l ・・・地下1階床鉄骨梁、 (イa)・・・地下1階鉄骨梁の端部、(5)・・・仮
受ブラケット、(6)・・・吊り材、(7)・・・基礎
梁、    (8)・・・地下壁、(9)・・・地下階
床コンクリート、 00)・・・1階床コンクリート、 00・・・梁コンクリート、 0り・・・柱コンクリート。
Figures 1 to 4 are longitudinal sectional views showing the steps of an embodiment of the underground construction method using synthetic steel beams according to the present invention, which also serves as a strut, and Figure 5 shows the steel beams and structural beams that act as struts during excavation. A plan view showing the relationship with the columns, taken from the arrow V-V in Figure 6, a side view showing the V-V view taken from the arrow in Figure 5, and Figure 7 showing the columns and beams when the underground framework is completed. A plan view showing the joint section, viewed from the arrow in Figure 8 ■
Figures -■ and 8 are longitudinal sectional views taken along arrows -■ in FIG. 7. (1)...Mountain retaining wall, (2)...Pile, (3)
−...Structural pillars, (4)...1st floor steel beams, (
4a)... End of the steel beam on the first floor, (4'l... Steel beam on the first basement floor, (a)... End of the steel beam on the first basement floor, (5)... Temporary Support bracket, (6)... Hanging material, (7)... Foundation beam, (8)... Basement wall, (9)... Basement floor concrete, 00)... First floor concrete , 00...Beam concrete, 0ri...Column concrete.

Claims (1)

【特許請求の範囲】[Claims] 山留め壁と杭及び構真柱を建込み、1次掘削したのち、
梁端部が前記構真柱を取り巻くように迂回された相隣る
梁同士を互いに緊結した1階床鉄骨梁を、前記構真柱を
案内として所定位置まで下降せしめて同構真柱に仮支持
し、前記1階床鉄骨梁の下部に同梁と同様に構成された
地下階鉄骨梁を仮置きし、次いで前記1階床鉄骨梁を切
梁として作用させて2次掘削し、同鉄骨梁の下に仮置き
した地下1階床鉄骨梁を所定位置まで下降せしめ、前記
構真柱にセットして切梁として作用させ、以下前記同様
の工程を反復して最下階まで施工したのち、下階より順
にコンクリートを打設して地下躯体を構築することを特
徴とする合成鉄骨梁による切梁兼用地下工法。
After erecting retaining walls, piles, and structural pillars, and conducting the first excavation,
The first-floor steel beams, in which adjacent beams are tied together so that the beam ends surround the structural pillars, are lowered to a predetermined position using the structural pillars as a guide, and temporarily attached to the structural pillars. A basement floor steel beam constructed in the same manner as the first floor steel beam is temporarily placed below the first floor steel beam, and then secondary excavation is performed using the first floor steel beam as a strut. The steel beams for the first basement floor, which had been temporarily placed under the beams, were lowered to a predetermined position, set on the structural pillars, and acted as struts, and the same process described above was repeated until the bottom floor was constructed. , an underground construction method using synthetic steel beams that can be used for both sills and beams, which is characterized by constructing an underground framework by pouring concrete from the lower floors.
JP1180531A 1989-07-14 1989-07-14 Cut-and-joint underground construction method using synthetic steel beams Expired - Fee Related JP2757209B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1180531A JP2757209B2 (en) 1989-07-14 1989-07-14 Cut-and-joint underground construction method using synthetic steel beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1180531A JP2757209B2 (en) 1989-07-14 1989-07-14 Cut-and-joint underground construction method using synthetic steel beams

Publications (2)

Publication Number Publication Date
JPH0347321A true JPH0347321A (en) 1991-02-28
JP2757209B2 JP2757209B2 (en) 1998-05-25

Family

ID=16084894

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1180531A Expired - Fee Related JP2757209B2 (en) 1989-07-14 1989-07-14 Cut-and-joint underground construction method using synthetic steel beams

Country Status (1)

Country Link
JP (1) JP2757209B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0594342U (en) * 1992-05-22 1993-12-24 清水建設株式会社 Structure of the true pillar
CN104196032A (en) * 2014-08-12 2014-12-10 上海隧道工程有限公司 Subway station supporting plate and inversed operation combined construction method
KR101648945B1 (en) * 2016-04-19 2016-08-18 주식회사 메스코리아 Vest attached first-aid pouch

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0594342U (en) * 1992-05-22 1993-12-24 清水建設株式会社 Structure of the true pillar
CN104196032A (en) * 2014-08-12 2014-12-10 上海隧道工程有限公司 Subway station supporting plate and inversed operation combined construction method
KR101648945B1 (en) * 2016-04-19 2016-08-18 주식회사 메스코리아 Vest attached first-aid pouch

Also Published As

Publication number Publication date
JP2757209B2 (en) 1998-05-25

Similar Documents

Publication Publication Date Title
JPH0412111Y2 (en)
JPH10152998A (en) Earthquake-resistant reinforcing structure of existing building
JPH0347321A (en) Shore strut and underground construction work by composite steel beam
JPS5829922A (en) Constructing method for underground outer wall
JPS6137692Y2 (en)
JP3057466B2 (en) How to build underground structures
JPH0754364A (en) Construction method of basement floor
JPH07103583B2 (en) Construction method for large span underground structure
WO2021149266A1 (en) Building construction method
JPS6286242A (en) Reverse casting consttructin method
JP2763488B2 (en) Prefabricated pillar and inverted ramen prefabricated construction method
JP2514859B2 (en) Precast Steel Reinforced Concrete Concrete Column
JPH09111721A (en) Execution method and structure of bridge pier
JPS6217233A (en) Foundation base column
JP2572680B2 (en) Underground structure by reverse strike method
JPS63312437A (en) Construction of underground structure
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH0657769A (en) Underground concrete structure and working method thereof
JPS63184609A (en) Method for constructing underground continuous wall
JPH0347320A (en) Base structure by inverted placing method
JP2023108327A (en) Reconstruction method of building having underground structure
JP3567387B2 (en) How to build an underground skeleton
JPH116162A (en) Construction method for reinforced concrete underground external wall
JPH0748848A (en) Construction method for underground skeleton by inverted construction method
JPH0441817A (en) Sheathing method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees