JPH03269296A - Delivery method of structure block - Google Patents

Delivery method of structure block

Info

Publication number
JPH03269296A
JPH03269296A JP2067101A JP6710190A JPH03269296A JP H03269296 A JPH03269296 A JP H03269296A JP 2067101 A JP2067101 A JP 2067101A JP 6710190 A JP6710190 A JP 6710190A JP H03269296 A JPH03269296 A JP H03269296A
Authority
JP
Japan
Prior art keywords
block
piping
ipb
construction method
final installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2067101A
Other languages
Japanese (ja)
Inventor
Kiyobumi Azuma
東 清文
Hitoshi Isa
伊佐 均
Shuji Takahashi
修二 高橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2067101A priority Critical patent/JPH03269296A/en
Publication of JPH03269296A publication Critical patent/JPH03269296A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

PURPOSE:To prevent congesting works in a plant building from occurring by assembling well in advance pipings, IPBs, cable trays, supporting frames and so on of a thermal and a nuclear power systems at a place with good workability and safety, other than a final fixing place. CONSTITUTION:Pipings 2, IPBs 2, cable trays 3, supporting frames 4 and so on are assembled to a structural block at a place with good operability other than a final fixing place, and the block is fixed to holding parts provided on columns and beams of a plant building. In this occasion, congestion of works can be avoided by fixing equipments such as an electrical board 6 and so on which are arranged underneath the block, after the block is completely fixed. In this case, since a plurality of equipments are fixed after they are assembled to an integral block, shortening of work schedule resulted from an improvement of workability becomes possible and a good effect on safety aspect can be expected.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、火力・原子カプラント等の配管。[Detailed description of the invention] [Industrial application field] The present invention relates to piping for thermal power, nuclear couplants, etc.

IPBなど、特に、混在かつ密集する部分の据付作業に
好適な工法に関する。
This invention relates to a construction method suitable for installation work, especially in mixed and dense areas such as IPB.

〔従来の技術〕[Conventional technology]

従来、配管、IPB等の直尺物の本設品のみによるブロ
ック工法に注目した出願例はなく、仮設品を伴うブロッ
ク工法に注目したものには特開昭58−123087号
公報が挙げられる。
Until now, there has been no application that focuses on a block construction method using only permanently installed straight items such as piping, IPB, etc., and Japanese Patent Application Laid-Open No. 123087/1987 focuses on a block construction method that involves temporary construction.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

上記従来技術は、最終取付場所以外では本設品と仮設品
を一体に組立て、組立て完了後に最終取付場所まで移動
し、取付を行い取付完了後に組立て時にのみ必要であっ
た仮設材を取外さねばならず安定性、経済性9作業性の
問題があった。
In the above-mentioned conventional technology, the permanent product and the temporary product must be assembled together at a location other than the final installation location, and after assembly is completed, the temporary component must be moved to the final installation location, installed, and after the installation is completed, the temporary material that was necessary only during assembly must be removed. However, there were problems with stability, economy, and workability.

本発明の目的は、長尺物の据付作業を、作業性の制約を
受けないプラント建屋外でブロック化のだめの仮設品を
使用しない全て本設品のみによるブロック化を行う事に
より、安全性、経済性9作業性の向上を図ることにある
The purpose of the present invention is to improve safety by performing the installation work of long objects outside the plant building, where there are no restrictions on workability, by blocking only permanent parts without using any temporary parts. Economical efficiency 9 The objective is to improve work efficiency.

〔課題を解決するための手段〕[Means to solve the problem]

」二足目的は、ブロック工法設計とプラン1〜建屋建築
設計2機器設計の同期化、及び、自走式昇降台車により
ブロックの移動、取付を行うことにより達成される。
The two-legged objective is achieved by synchronizing the block construction method design and the equipment design of Plan 1 to Building Architectural Design 2, and by moving and installing the blocks using a self-propelled lifting cart.

〔作用〕[Effect]

ブロック工法設計とプラント建屋建築設計9撮器設計を
同期化することにより、仮設サポー1〜材が不要となり
、ブロック取付完了後の仮設品の撤去作業が発生しない
By synchronizing the block construction method design and the plant building architectural design 9 camera equipment design, the temporary supports 1 to 1 are not required, and the removal work of temporary items after the block installation is completed is not required.

〔実施例〕〔Example〕

以下、本発明の一実施例を第1図により説明する。本図
は、操作性の良い最終取付場所以外で配管、IPB、ケ
ーブルトレイン、サポート等をブロックに組立て、プラ
ント建屋内の最終取付位置まで移動して取付を行う様子
を示したものである。
An embodiment of the present invention will be described below with reference to FIG. This figure shows how piping, IPB, cable trains, supports, etc. are assembled into blocks at a location other than the final installation location that is easy to operate, and then moved to the final installation location inside the plant building for installation.

最終取付場所以外で配管1.IPB2.ケープ− シトレイ3.サポート4等をブロックに組立てプラン1
〜建屋内の最終取付位置まで移動しプラント建屋の柱及
び梁に設けた仕口5にブロックを取付ける。
Piping other than the final installation location 1. IPB2. Cape-Sitley 3. Assembling support 4 etc. into blocks Plan 1
-Move to the final installation position in the building and attach the block to the joints 5 provided on the pillars and beams of the plant building.

この際、ブロックの下部に配置される電気盤6等の機器
は、ブロック取付完了後に据付けることにより作業の幅
岐を回避することが出来る。
At this time, by installing equipment such as the electrical panel 6 located at the bottom of the block after the block installation is completed, it is possible to avoid a wide range of work.

ここで、ブロックの構造、及び、プラント建屋内への移
動について第2図により説明する。組立てたブロックは
、プラント敷地内に設けた走行レール7」二を移動可能
な自走式昇降台車8に乗せプラント建屋内最終取付位置
の下まで移動する。
Here, the structure of the block and its movement into the plant building will be explained with reference to FIG. The assembled block is placed on a movable self-propelled elevating cart 8 on a traveling rail 7'' provided within the plant site and moved to the bottom of the final installation position within the plant building.

次に、最終設定位置でのブロックの設定方法について第
3図により説明する。最終取付位]11下まで移動した
ブロックは、自走式昇降台車8の昇降装置により最終取
付位置まで移動し、プラント建屋柱、及び、梁に設けた
仕口5に取付ける事によりブロックの据付は完了する。
Next, a method of setting blocks at the final setting position will be explained with reference to FIG. Final installation position] The block that has been moved to the bottom of 11 is moved to the final installation position by the lifting device of the self-propelled lifting cart 8, and the block is installed by attaching it to the joints 5 provided on the plant building pillars and beams. Complete.

又、ブロック設定に際しては、複数のブロックを最終取
付位置下で予め接続し、塗装、保温等を実施後最終取付
位置4 まで移動、仕口5への取付けを行う事により、作業性の
向上、工事期間の短縮、及び、安全性向」―等の効果が
ある。
In addition, when setting blocks, work efficiency is improved by connecting multiple blocks in advance at the final installation position, and after performing painting, heat insulation, etc., move to the final installation position 4 and attach it to the joint 5. This has the effect of shortening the construction period and improving safety.

〔発明の効果〕〔Effect of the invention〕

本発明によれば、プラント建屋内の@軽工事を防ぐこと
ができ、又1作業性の良い場所で複数の機器を一体のブ
ロックに組立てた後、据付けられるため、作業性の向上
に伴う工事期間の短縮が可能で、安全性の面での効果が
大きい。
According to the present invention, it is possible to prevent @light construction work inside the plant building, and since multiple devices can be assembled into a single block and then installed in a location with good workability, construction work associated with improved workability can be avoided. It is possible to shorten the period and has a large effect in terms of safety.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は、本発明の一実施例のブロック搬入工法を示す
斜視図、第2図、第3図はブロックの構造を示す斜視図
である。
FIG. 1 is a perspective view showing a block loading method according to an embodiment of the present invention, and FIGS. 2 and 3 are perspective views showing the structure of the block.

Claims (1)

【特許請求の範囲】 1、火力・原子力等の配管、IPB、ケーブルトレイ、
サポート、足場等をあらかじめ作業性・安全性の良い最
終取付場所以外で組立てるブロック化工法。 2、請求項1において、前記配管、前記IPB、前記ケ
ーブルトレイ、前記サポート、前記足場等のブロックを
前記最終取付場所に移動し、設定レベルまでの吊場、各
ブロック間の接続を行なうブロック化工法。 3、請求項1に於ける前記ブロック内の前記配管、前記
IPB、前記ケーブルトレイ、前記足場を本設のサポー
トを用いて接続を行なうブロック化工法。 4、請求項2に於けるブロックを敷地内に布設した走行
レール上を走行する台車に乗せ前記各最終取付場所に移
動するブロック化工法。 5、請求項2に於けるブロックを自走式昇降台車の上に
乗せ前記最終取付場所に移動し、設定レベルまでの前記
吊場、各ブロック間の接続を行なうブロック化工法。 6、請求項1に於ける前記配管、前記IPB、前記ケー
ブルトレイ、前記サポート、前記足場等のブロックを前
記最終取付場所下の床上まで移動し、作業性の良い床で
各ブロックの接続作業を行ない、複数のブロックを一体
化した後一拠に吊場作業を行なうブロック化工法。 7、請求項1においてブロック化する前記配管、前記I
PB、前記ケーブルトレイ、前記サポート、前記足場等
をあらかじめブロック化しやすい建屋柱スパンに基づい
た管割を選定するブロック化工法。 8、請求項6に於ける前記配管、前記IPB、前記ケー
ブルトレイ、前記サポート等のブロックを最終取付場所
下の床上まで移動し、床上で各ブロックの接続作業を行
ない、前記配管のフラッシング、耐圧、保温・塗装、前
記IPB・ケーブルの耐圧試験が完了した段階で吊場、
設定作業を行なうブロック化工法。
[Claims] 1. Piping for thermal power, nuclear power, etc., IPB, cable tray,
A block construction method in which supports, scaffolding, etc. are assembled in advance at a location other than the final installation location where workability and safety are good. 2. In claim 1, the block conversion work includes moving the blocks such as the piping, the IPB, the cable tray, the support, the scaffolding, etc. to the final installation location, and providing a hanging place to a set level and connections between each block. Law. 3. The block construction method according to claim 1, wherein the piping, the IPB, the cable tray, and the scaffolding in the block are connected using a built-in support. 4. The block conversion method according to claim 2, in which the blocks are placed on a trolley running on running rails laid on the site and moved to each of the final installation locations. 5. The block construction method according to claim 2, wherein the block is placed on a self-propelled lifting cart and moved to the final installation location, and the hanging place and each block are connected to a set level. 6. In claim 1, move the blocks such as the piping, the IPB, the cable tray, the support, the scaffolding, etc. to the floor below the final installation location, and connect each block on the floor with good workability. This is a block construction method in which multiple blocks are assembled into a single block and then a hanging site is carried out in one area. 7. The piping to be blocked in claim 1, the I
A blocking construction method in which pipe divisions are selected based on building column spans that make it easy to block the PB, the cable tray, the support, the scaffolding, etc. in advance. 8. In claim 6, move the blocks such as the piping, the IPB, the cable tray, and the support to the floor below the final installation location, perform the connection work of each block on the floor, flush the piping, pressure resistance, etc. , heat insulation, painting, and the above-mentioned IPB/cable pressure test are completed.
A block construction method that performs setting work.
JP2067101A 1990-03-19 1990-03-19 Delivery method of structure block Pending JPH03269296A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2067101A JPH03269296A (en) 1990-03-19 1990-03-19 Delivery method of structure block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2067101A JPH03269296A (en) 1990-03-19 1990-03-19 Delivery method of structure block

Publications (1)

Publication Number Publication Date
JPH03269296A true JPH03269296A (en) 1991-11-29

Family

ID=13335161

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2067101A Pending JPH03269296A (en) 1990-03-19 1990-03-19 Delivery method of structure block

Country Status (1)

Country Link
JP (1) JPH03269296A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0712977A (en) * 1993-06-15 1995-01-17 Hitachi Ltd Installation of piping group

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0712977A (en) * 1993-06-15 1995-01-17 Hitachi Ltd Installation of piping group

Similar Documents

Publication Publication Date Title
JP6728309B2 (en) MODULAR BUILDING UNIT AND METHOD OF CONSTRUCTING AND TRANSPORTING THE SAME
CN111749474B (en) Construction method of clean workshop
US5088263A (en) Construction apparatus and construction method
EP3889374B1 (en) Method for constructing buildings
CN103276840B (en) Nuclear power plant composite floor slab module and construction method thereof
JPH03269296A (en) Delivery method of structure block
KR100863592B1 (en) Temporary construction system for the automation of building projects and construction method using the same
SE528325C2 (en) Transformer station, method of making such and use
US20110146198A1 (en) Modular seismically restrained distribution system and method of installing the same
CN210002826U (en) detachable welding platform for steel column construction
CN110862019A (en) Installation method of device capable of simultaneously solving vertical and horizontal material transportation
KR101808296B1 (en) Method of installing scaffold for offshore plant
JP2878006B2 (en) Exterior wall construction method
JPH0759831B2 (en) Construction equipment
CN113338634B (en) Installation method of prefabricated chemotherapy equipment shielding room
KR200167125Y1 (en) Bracket for scaffoldings
JP2012112151A (en) Seismic strengthening method for roof
RU2124099C1 (en) Method for erection of framework for stories added to dwelling building
JPH10126918A (en) Composite body of cable tray and air-conditioning duct and installation thereof
JPH0932297A (en) Work execution method for warehouse facility
JPH09287283A (en) Work scaffold device for coal bunker
JP2022089706A (en) Building inside staircase preceding construction method
JP2004191080A (en) Method of constructing central control room in facility for nuclear reactor
SU66989A1 (en) Prefab building
JPH10260284A (en) Plant building, construction method for the building and modular structure used for the construction