JP2004191080A - Method of constructing central control room in facility for nuclear reactor - Google Patents
Method of constructing central control room in facility for nuclear reactor Download PDFInfo
- Publication number
- JP2004191080A JP2004191080A JP2002356307A JP2002356307A JP2004191080A JP 2004191080 A JP2004191080 A JP 2004191080A JP 2002356307 A JP2002356307 A JP 2002356307A JP 2002356307 A JP2002356307 A JP 2002356307A JP 2004191080 A JP2004191080 A JP 2004191080A
- Authority
- JP
- Japan
- Prior art keywords
- control room
- central control
- unit
- work
- nuclear reactor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、原子炉施設の制御建屋に設けられる中央制御室の構築工法に関する。
【0002】
【従来の技術】
原子力発電所等の原子炉施設には、原子炉建屋やタービン建屋の他に、制御建屋が設けられている。この制御建屋は、原子炉の運転等を制御する設備などを収容する建物であり、その内部には、各種機器・電気系統の制御盤が集中して設置される中央制御室が設けられている。
【0003】
この中央制御室は、原子炉施設全体の中でも非常に重要な設備の1つであり、その建設工事が終了しない限り、原子炉施設全体の試運転等を行うことができない。そこで、中央制御室の建設工事を早期に終了させるために、中央制御室の躯体の構築工事と並行として、各種サポートやダクト、照明機器などの取付をはじめとする機電工事が行われている。
【0004】
この中央制御室の従来の構築工法について説明する。図13〜図19は、中央制御室の従来の構築工法の一例を説明するものである。中央制御室を構築する場合には、まず、図13に示すように、中央制御室の構築位置にコンクリートを打設して中央制御室の床部2を構築する。そして、構築した床部2の上に作業用足場4を設置し、この作業用足場4を利用して、中央制御室の壁部を構成する壁鉄筋6と、この壁鉄筋6を保持するための鉄筋架台8とをそれぞれ配設する。さらに、これら壁鉄筋6と鉄筋架台8とを取り囲むようにその周りにコンクリート型枠10を配置する。その後、コンクリート型枠10内にコンクリートを打設して、その打設したコンクリートが十分に硬化した後、コンクリート型枠10を解体して、1段目の壁部とする。
【0005】
次に、図14に示すように、構築した壁部12の間の床部2上に、中央制御室の上部床、即ち天井部を構築するための棚足場14を構築する。
次に、図15に示すように、棚足場14の上方に、中央制御室の上部床を支持する鉄骨架構24を構築する。鉄骨架構24は、鉄骨主構16を大梁として1本1本相互に間隔をあけて順次配設するとともに、各鉄骨主構16の相互間に、小梁として梁部材18や、ブレース20、下地鉄骨部材22を配設して組み立てる。鉄骨主構16は、3分割されたものを現地で地組して製作してクレーンにより吊り込む。
【0006】
そして、図16に示すように、鉄骨架構24の構築後、別途、作業用足場(図示外)を構築し、当該作業用足場を利用して、鉄骨架構24の本締め作業を行うとともに、当該鉄骨架構24に取り付けられる各種サポート26やダクト28などを先入れして棚足場14上に仮置きする。そして、図17に示すように、鉄骨架構24の各梁部材18の上方に、中央制御室の天井部を構成するデッキプレート30を敷設する。
【0007】
その後、図18に示すように、1段目の壁部12の上部に2段目の壁部を構築すべく、当該上部より突出した壁鉄筋6および鉄筋架台8を取り囲むようにその周りにコンクリート型枠10を配置する。また、鉄骨架構24のデッキプレート30の上方には、中央制御室の上部床を構築するための床鉄筋32とコンクリート型枠34とを配設し、各コンクリート型枠10、34内にコンクリートを打設する。コンクリート硬化後、コンクリート型枠10、34を解体して、1段目の壁部12の上方に2段目の壁部を構築するとともに、その2段目の壁部間に中央制御室の上部床を構築する。また、鉄骨架構24には、同図に示すように、先行して各サポート26をそれぞれ所定の位置に取り付ける。
【0008】
そして、図19に示すように、2段目の壁部36および中央制御室40の上部床38が構築されることで、中央制御室40の躯体の構築工事が終了する。その後、同図に示すように、鉄骨架構24の鉄骨主構16などに錆止め処理を施したり、鉄骨架構24の下部のサポート26などには、光天井部41を構築するための光天井下地材42や光天井ルーバー44、天井ボード45等の各種ボード類、各種機器の取付けを行うとともに、塗装などを施して仕上げを行う。また、中央制御室40の壁面や床面には、塗装またはタイル等の仕上材46を施す。その後、中央制御室40内に制御盤等の各種機器48を搬入して各々所定位置に設置する。
【0009】
【特許文献1】
特許第3283735号公報(第1−5頁、第3−7図)
【0010】
【特許文献2】
特許第2873139号公報(第1−6頁、第1−6図)
【0011】
【特許文献3】
特開昭61−53963号公報(第1−2頁、第1−4図)
【0012】
【特許文献4】
特開昭61−270437号公報(第1−2頁、第1−4図)
【0013】
【発明が解決しようとする課題】
このような構築工法にあっては、次のような問題があった。すなわち、中央制御室40の上部床38を支持する鉄骨架構24の構築時には、当該鉄骨架構24を構成する鉄骨主構16を1本1本クレーンで吊り込んで設置しなければならず、手間と時間を要した。また、鉄骨主構16の設置後、当該鉄骨主構16の相互間に、梁部材18やブレース20、下地鉄骨部材22などを個別に配設しなければならず、さらに手間と時間を要した。また、鉄骨架構24の構築と並行に、各種サポート26やダクト28などの先入れ作業をしなければならず、狭隘部での作業となり、作業効率が悪く、工期の長期化を招いていた。
【0014】
また、鉄骨架構24への各種サポート26の取付時には、中央制御室40の躯体構築工事、即ち、壁鉄筋6や鉄筋架台8の周囲へのコンクリート型枠10の配置工事や鉄骨架構24の上方への床鉄筋32及びコンクリート型枠34の配設工事、構築した鉄骨架構24への錆止め工事などの建築側の工事と並行に行われているため、建築側の工事による影響、例えば騒音やゴミの問題、錆止め工事時における待避などの余計な配慮が必要となった。また、狭隘部での作業となるため、作業効率が悪く、工期の長期化を招いていた。
【0015】
また、ダクト28の先入れ時には、ダクト28の仮置場所も限られるとともに、ダクト28やそのサポートの取付に伴いダクト28の移動が多くなるとともに、狭隘部での作業となるため、作業効率が悪く、工期の長期化を招いていた。
【0016】
このように中央制御室40の構築工事が複雑で入り組むのは、中央制御室40自体が大スパンを有する大空間部からなり、その上部床38を支持するために大規模な鉄骨架構24を設けなければならず、その鉄骨架構24の構築工事が大掛かりなものとなるとともに、その大掛かりな工事に併せて機電工事も並行して行うからである。つまり、大掛かりな上部床38の鉄骨架構24の構築工事と、各種サポート26やダクト28の設置等の機電工事とが輻輳し、これによって、作業工程の複雑化や作業効率の低下が生じ、工期の長期化を招いていたのである。
【0017】
一方、中央制御室40の関連工事は、その工事が終了しない限り原子炉設備全体の試運転等が行えないことから、原子炉設備全体の建設工事内でクリティカルとなっており、厳しい工程を遵守しなければならなかった。すなわち、中央制御室40の工事の遅れは、原子炉設備全体の建設工事に対して大きな影響を及ぼすため、回避しなければならないのである。
【0018】
本発明は、このような事情に鑑みてなされたものであって、その目的は、中央制御室の躯体工事と、各種サポートやダクトなどの設置等の機電工事とが輻輳せずに効率的に工事を行え、工期の短縮が図れる原子炉施設の中央制御室の構築工法を提供することにある。
【0019】
【課題を解決するための手段】
このような目的を達成するために本発明に係る原子炉施設の中央制御室の構築工法にあっては、原子炉施設の制御建屋に設けられる中央制御室を構築する工法であって、前記中央制御室の上部床を支持する骨組みを組立て、当該骨組みに前記中央制御室の天井部に配設される付設器具を取り付けてユニットを製作し、このユニットを前記中央制御室の上部床の構築予定位置の下側に設置して前記中央制御室を構築することを特徴とする。
【0020】
このような構築工法にあっては、中央制御室の上部床を支持する骨組みを予め組み立て、この骨組みに前記中央制御室の天井部に配設される付設器具を取り付けてユニット化するから、大掛かりな上部床の骨組みの構築工事であっても、付設器具の設置等の機電工事との輻輳を解消することができ、これにより効率的に作業を行うことができ、工期の短縮を達成することができる。
【0021】
かかる原子炉施設の中央制御室の構築工法にあっては、前記骨組みが鉄骨架構により構成されていても良い。このように骨組みが鉄骨架構により構成されれば、中央制御室の上部床を相当な強度で支持することができる。
【0022】
また、かかる原子炉施設の中央制御室の構築工法にあっては、前記ユニットには、前記中央制御室の上部床を構成するデッキプレートが設けられていても良い。このようにユニットにデッキプレートが設けられていれば、現場でのデッキプレートの設置作業を省略することができる。
【0023】
また、かかる原子炉施設の中央制御室の構築工法にあっては、前記ユニットには、前記中央制御室の天井部に配設されるダクトが設けられていても良い。このようにユニットにダクトが設けられていれば、ダクトの先入れ作業や現場での取付作業を省略することができる。
【0024】
また、かかる原子炉施設の中央制御室の構築工法にあっては、前記ユニットには、前記付設器具として、前記中央制御室の天井部に配設される天井材や照明器具等を支持するサポートが設けられていても良い。このようにユニットに天井材や照明器具等を支持するサポートが設けられていることで、サポートの先入れ作業や現場での取付作業を省略することができる。
【0025】
また、かかる原子炉施設の中央制御室の構築工法にあっては、前記ユニットをクレーンにより吊り上げて前記構築予定位置に据え付けるようにしても良い。このようにユニットの据付にクレーンを用いることで、簡単に据付作業を済ませることができる。
【0026】
【発明の実施の形態】
以下に本発明に係る原子炉施設の中央制御室の構築工法の実施の形態について説明する。なお、ここでは、図11〜図17に示す前記従来例と同一の構成要素には、同一の符号を付して示す。
【0027】
図1は、本実施形態における原子炉施設を示した平面図である。この原子炉施設50は、加圧水型原子力発電プラントであり、原子炉建屋52とタービン建屋54とを備えている。原子炉建屋52には、原子炉格納容器56をはじめ、原子炉格納容器56に関連する各種設備が設けられている。また、タービン建屋54には、タービン発電装置をはじめ、タービン発電装置に関連する各種機器や設備を備えている。さらに、原子炉施設50は、原子炉の運転等を制御する設備などを収容する制御建屋60を備えている。
【0028】
図2は、この制御建屋60の一実施形態の内部構造を示した縦断面図である。制御建屋60は、例えば鉄筋コンクリート構造などにより構築された建物62からなり、その2F部分の中央部には、例えば、幅約40m×長さ約20m×高さ約7mほどの空間部として画成された中央制御室64が設けられている。この中央制御室64は、各種機器・電気系統の制御盤が集中して設置される部屋であり、同図に示すように大スパンを有することから、その上部床38には当該上部床38を支持するための鉄骨架構66が設けられている。
【0029】
このような制御建屋60の中央制御室64の構築工法の一実施形態について説明する。なお、本実施形態では、中央制御室64の床部2の構築から1段目の壁部12までの構築は、従来の図11〜図12の手順と同様の手順で行われる。図3〜図10は、1段目の壁部12より上方の部分の構築手順を示す。
【0030】
ここでは、図3に示すように、棚足場14の上方に、中央制御室の天井部を構築するためのユニット70を設置する。このユニット70は、予め製作したもので、中央制御室64の上部床を支持するために、大梁として配設された鉄骨主構72と、鉄骨主構72の間に配設された梁部材74やブレース76、下地鉄骨部材78とにより構成された鉄骨架構80を備えている。この他に、当該ユニット70には、ダクト84やデッキプレート86、それに中央制御室64の天井部に配設される天井材や照明器具等の機器を支持するための各種サポート82が設けられている。各種サポート82やダクト84は、鉄骨架構80に対して各々所定の位置に取り付けられている。また、デッキプレート86は、鉄骨架構80の上面部に配設されている。
【0031】
このようなユニット70の上方には、ワイヤー90を介して吊具92が接続され、ユニット70は、当該吊具92を介してクレーン等により吊下げられて移送され、所定位置、即ち中央制御室64の上部床構築位置に設置される。
【0032】
図4および図5は、このユニット70を示した斜視図である。図4は、ユニット70全体を示したものであり、図5は、ユニット70の一部を拡大して示したものである。このユニット70は、図4に示すように、I型鋼からなる複数本の鉄骨主構72を相互に間隔をあけて平行に並設するとともに、これら鉄骨主構72の各相互間に、梁部材74と、下地鉄骨部材76と、ブレース78とを配設して鉄骨架構80として組み立てられている。梁部材74は、図5に示すように、鉄骨主構72の上縁部間を結んで、鉄骨主構72の長さ方向に沿って相互に間隔をあけて設けられている。また、下地鉄骨部材76は、梁部材74とは対照的に、同図に示すように、鉄骨主構72の下縁部間を結んで、鉄骨主構72の長さ方向に沿って相互に間隔をあけて設けられている。また、ブレース78は、同図に示すように、各梁部材74の中央部から左右両側の鉄骨主構72の側面部にかけて斜めに配設されている。このようにして構成された鉄骨架構80の下部には、同図に示すように、ダクト84をはじめ、この他に各種サポートなどの付設器具(図示外)が取り付けられている。このようにユニット70は、1つの大きなブロックとして構築されている。
【0033】
図6は、このユニット70の製作方法を説明するものである。図6(a)は、ユニット70の製作現場を上方から見たときの図であり、図6(b)は、ユニット70の製作状況を横から見たときの図である。ユニット70を製作する場合には、まず、図6(a)に示すように、ユニット70の製作場所、即ち地組場100に仮設架台102を設置する。地組場100には、図6(b)に示すように、地組場100にコンクリートを打設して基礎部104が設けられており、仮設架台102は、この基礎部104上に設置される。ここでは、4本の仮設架台102を相互に間隔をあけて平行に設けている。
【0034】
こうして設置した仮設架台102の上に、図6(b)に示すように、仮設架台102の間を掛け渡して鉄骨主構72を順次設置する。鉄骨主構72は、図6(a)に示すように、仮設架台102の長さ方向に沿って相互に間隔をあけて平行に配置する。こうして配置した鉄骨主構72の相互間に、梁部材74や下地鉄骨部材76、ブレース78を介して鉄骨架構80を構築する。その後、各鉄骨主構72などに対して錆止めを目的に塗装などを施す。また、仮設架台102により形成された鉄骨主構72と基礎部104との間の隙間を利用して、鉄骨架構80の下部に、図5に示すように、ダクト84をはじめ、中央制御室64の天井部に配設される天井材や照明器具等の機器を支持するための各種サポート82などの付設器具を取り付ける。また、鉄骨架構80の上部には、デッキプレート86を配設する。その後、製作したユニット70をクレーンにより吊り上げて中央制御室64の構築位置まで移送する。
【0035】
図7は、ユニット70の地組場100と、実際の中央制御室64の構築位置110との関係を示した平面図である。ユニット70が製作される地組場100は、中央制御室64の構築位置110の近くに設定される。地組場100で製作したユニット70は、クレーン112により中央制御室64の構築位置110に移送される。クレーン112は、地組場100と中央制御室64の構築位置110との間の適宜なポイントに設置される。中央制御室64の構築位置110付近に移送されたユニット70は、現在構築が進められている中央制御室64の躯体の上部に設置される。
【0036】
図8は、ユニット70が設置されたときの様子を示す。同図に示すように、ユニット70は、中央制御室64の壁部との取り合い部分Aについて接続作業が行われる。図9は、その取り合い部分Aを詳しく示したものである。同図に示すように、ユニット70を支持するために、中央制御室64の壁部内に埋め込まれて設置された支持柱88に、ユニット70の各鉄骨主構72がそれぞれ接合される。各支持柱88は、鉄骨材により形成されており、ユニット70の各鉄骨主構72に夫々対応して設けられている。各支持柱88の上端部には、その側方に梁部88aが突出して設けられて、この梁部88aに各鉄骨主構72の端部が接続プレート89を介して接合される。
【0037】
その後、図10に示すように、従来と同様、1段目の壁部12の上部に2段目の壁部を構築すべく、当該上部より突出した壁鉄筋6および鉄筋架台8を取り囲むようにその周りにコンクリート型枠10を配置する。また、ユニット70の上部のデッキプレート30の上には、中央制御室64の上部床を構築するための床鉄筋32とコンクリート型枠34とを配設する。次に、各コンクリート型枠10、34内にコンクリートを打設して、コンクリート硬化後、コンクリート型枠10、34を解体することで、1段目の壁部12の上方に2段目の壁部を構築する。また、その2段目の壁部間に中央制御室64の上部床を構築する。
【0038】
そして、図11に示すように、2段目の壁部36と、中央制御室64の上部床38の構築終了後、鉄骨架構80の下部のサポート82などには、光天井部41を構築するための光天井下地材42や光天井ルーバー44、天井ボード45等の各種ボード類、各種機器の取付けを行うとともに、塗装などを施して仕上げを行う。また、中央制御室64の壁面や床面には、塗装またはタイル等の仕上材46を施す。その後、中央制御室64内に制御盤等の各種機器48を搬入して各々所定位置に設置する。
【0039】
図12は、ここで構築される光天井部41の様子を詳細に示したものである。光天井部は、同図に示すように、鉄骨主構72に取付具83を介して取り付けられたサポート82に、光天井下地材42a、42bや天井ボード45a、45bが設けられる。さらに天井ボード45aには、照明器具87が設けられるとともに、この照明器具87を下側から覆うように取付具85を介して光天井ルーバー44が設けられる。
【0040】
以上この構築工法によれば、制御建屋60の中央制御室64の上部床38を支持する鉄骨架構80を組立てて、当該鉄骨架構80に中央制御室64の天井部に配設される天井材や照明器具等の機器を支持するためのサポート82やダクト84などの付設器具を取り付けて予めユニットとして製作するから、大掛かりな鉄骨架構80の構築工事であっても、付設器具の設置等の機電工事との輻輳を解消することができ、これにより効率的に作業を行うことができ、工期の短縮を達成することができる。
【0041】
そして、このように中央制御室64の工期が短縮されることで、中央制御室64を構築した後に実施する諸試験等の各種作業、例えば、受電、フラッシング、水圧試験(CHT)、温態機能試験(HFT)、原子炉格納容器耐圧漏洩率試験(LRT)、燃料装荷(C/L)、起動試験(加熱試験、出力上昇・負荷試験)などについては、早期に実施することができ、プラントの稼働開始時期を早めることが可能である。
【0042】
【発明の効果】
本発明によれば、中央制御室の上部床を支持する骨組みを予め組み立て、この骨組みに中央制御室の天井部に配設される付設器具を取り付けてユニット化するから、大掛かりな上部床の骨組みの構築工事であっても、付設器具の設置等の機電工事との輻輳を解消することができ、これにより効率的に作業を行うことができ、工期の短縮を達成することができる。
【図面の簡単な説明】
【図1】原子炉施設の一例を示した縦断面図である。
【図2】本発明における原子炉施設の制御建屋とこれに設けられる中央制御室の一実施形態を示した縦断面図である。
【図3】本実施形態に係る原子炉施設の中央制御室の構築手順を説明する説明図である。
【図4】本実施形態におけるユニットを示した斜視図である。
【図5】本実施形態におけるユニットの主要部を詳細に示した斜視図である。
【図6】本実施形態におけるユニットの製作方法の一例を説明する説明図である。
【図7】本実施形態におけるユニットの製作場所と、中央制御室の構築予定位置との関係を示した平面図である。
【図8】本実施形態に係る原子炉施設の中央制御室の構築手順を説明する説明図である。
【図9】本実施形態におけるユニットの支持構造の一例を示した説明図である。
【図10】
本実施形態に係る原子炉施設の中央制御室の構築手順を説明する説明図である。
【図11】本実施形態に係る原子炉施設の中央制御室の構築手順を説明する説明図である。
【図12】本実施形態における中央制御室の光天井部の様子を部分的に詳しく示した説明図である。
【図13】従来の原子炉施設の中央制御室の構築手順の一例を説明する説明図である。
【図14】従来の原子炉施設の中央制御室の構築手順の一例を説明する説明図である。
【図15】従来の原子炉施設の中央制御室の構築手順の一例を説明する説明図である。
【図16】従来の原子炉施設の中央制御室の構築手順の一例を説明する説明図である。
【図17】従来の原子炉施設の中央制御室の構築手順の一例を説明する説明図である。
【図18】従来の原子炉施設の中央制御室の構築手順の一例を説明する説明図である。
【図19】従来の原子炉施設の中央制御室の構築手順の一例を説明する説明図である。
【符号の説明】
2 床部 6 壁鉄筋 8 鉄筋架台
12 壁部 32 床鉄筋 38 上部床
42 天井下地材 48 機器 50 原子炉施設
52 原子炉建屋 56 原子炉格納容器 60 制御建屋
64 中央制御室 70 ユニット 72 鉄骨主構
74 梁部材 76 下地鉄骨部材 78 ブレース
80 鉄骨架構 82 サポート 84 ダクト
86 デッキプレート 90 ワイヤー 92 吊具
100 地組場 110 構築位置 112 クレーン[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method for constructing a central control room provided in a control building of a nuclear reactor facility.
[0002]
[Prior art]
2. Description of the Related Art A reactor building such as a nuclear power plant includes a control building in addition to a reactor building and a turbine building. This control building is a building that houses equipment for controlling the operation of the reactor and the like, and has a central control room in which control panels for various devices and electric systems are centrally installed. .
[0003]
This central control room is one of the very important facilities in the whole reactor facility, and the trial operation of the whole reactor facility cannot be performed unless the construction work is completed. Therefore, in order to finish the construction work of the main control room early, in parallel with the construction work of the main body of the main control room, electromechanical work including installation of various supports, ducts, lighting devices, and the like is performed.
[0004]
A conventional construction method of the central control room will be described. FIGS. 13 to 19 illustrate an example of a conventional construction method of a central control room. When constructing the main control room, first, as shown in FIG. 13, concrete is poured into the construction position of the main control room to construct the
[0005]
Next, as shown in FIG. 14, a
Next, as shown in FIG. 15, a
[0006]
Then, as shown in FIG. 16, after constructing the
[0007]
Thereafter, as shown in FIG. 18, in order to construct a second-stage wall portion above the first-
[0008]
Then, as shown in FIG. 19, by constructing the second-
[0009]
[Patent Document 1]
Japanese Patent No. 3283735 (pages 1-5, FIG. 3-7)
[0010]
[Patent Document 2]
Japanese Patent No. 2873139 (pages 1-6, FIG. 1-6)
[0011]
[Patent Document 3]
JP-A-61-53963 (page 1-2, FIG. 1-4)
[0012]
[Patent Document 4]
JP-A-61-270437 (page 1-2, FIG. 1-4)
[0013]
[Problems to be solved by the invention]
Such a construction method has the following problems. That is, when constructing the
[0014]
When the
[0015]
In addition, when the
[0016]
The reason why the construction work of the
[0017]
On the other hand, the related work of the
[0018]
The present invention has been made in view of such circumstances, and its purpose is to efficiently construct the main control room and the electrical works such as installation of various supports and ducts without congestion. An object of the present invention is to provide a method for constructing a main control room of a nuclear reactor facility, which can perform construction and shorten the construction period.
[0019]
[Means for Solving the Problems]
In order to achieve such an object, a method for constructing a central control room of a nuclear reactor facility according to the present invention is a method of constructing a central control room provided in a control building of a nuclear reactor facility, Assembling a skeleton supporting the upper floor of the control room, attaching a fixture attached to the ceiling of the central control room to the skeleton to manufacture a unit, and planning to construct this unit on the upper floor of the central control room The central control room is constructed by being installed below the position.
[0020]
In such a construction method, a framework for supporting the upper floor of the central control room is pre-assembled and attached to the framework to attach additional equipment provided on the ceiling of the central control room, thereby forming a unit. Even when constructing a framework for the upper floor, it is possible to eliminate the congestion with the electromechanical work such as the installation of attached equipment, thereby enabling efficient work and shortening the construction period. Can be.
[0021]
In the construction method of the main control room of the nuclear reactor facility, the frame may be constituted by a steel frame. If the framework is made of a steel frame, the upper floor of the central control room can be supported with considerable strength.
[0022]
Further, in the construction method of the central control room of the nuclear reactor facility, the unit may be provided with a deck plate constituting an upper floor of the central control room. If the unit is provided with a deck plate as described above, the work of installing the deck plate on site can be omitted.
[0023]
Further, in such a construction method of the central control room of the nuclear reactor facility, the unit may be provided with a duct disposed on a ceiling of the central control room. If the duct is provided in the unit as described above, the work of pre-installing the duct and the work of attaching the duct on site can be omitted.
[0024]
Further, in the method for constructing a central control room of a nuclear reactor facility, the unit includes, as the attached device, a support for supporting a ceiling material, a lighting device, and the like provided on a ceiling portion of the central control room. May be provided. Since the unit is provided with the support for supporting the ceiling material, the lighting equipment, and the like, the work of first-installing the support and the work of attaching the support at the site can be omitted.
[0025]
Further, in the construction method of the central control room of the nuclear reactor facility, the unit may be lifted by a crane and installed at the planned construction position. By using the crane for installation of the unit in this way, the installation work can be easily completed.
[0026]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, an embodiment of a construction method of a central control room of a nuclear reactor facility according to the present invention will be described. Here, the same components as those in the conventional example shown in FIGS. 11 to 17 are denoted by the same reference numerals.
[0027]
FIG. 1 is a plan view showing a nuclear reactor facility in the present embodiment. The
[0028]
FIG. 2 is a longitudinal sectional view showing an internal structure of the control building 60 according to an embodiment. The
[0029]
An embodiment of the construction method of the
[0030]
Here, as shown in FIG. 3, a
[0031]
Above such a
[0032]
4 and 5 are perspective views showing the
[0033]
FIG. 6 illustrates a method of manufacturing the
[0034]
As shown in FIG. 6B, the steel frame
[0035]
FIG. 7 is a plan view showing the relationship between the
[0036]
FIG. 8 shows a state when the
[0037]
Thereafter, as shown in FIG. 10, as in the conventional case, in order to construct a second-stage wall portion above the first-
[0038]
Then, as shown in FIG. 11, after the construction of the second-
[0039]
FIG. 12 shows details of the
[0040]
According to this construction method, a
[0041]
And, by shortening the construction period of the
[0042]
【The invention's effect】
According to the present invention, a framework for supporting the upper floor of the central control room is pre-assembled, and an attached device provided on the ceiling of the central control room is attached to this framework to form a unit. In the construction work, the congestion with the electromechanical work such as installation of the attached equipment can be eliminated, whereby the work can be performed efficiently and the construction period can be shortened.
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view showing an example of a nuclear reactor facility.
FIG. 2 is a longitudinal sectional view showing an embodiment of a control building of a nuclear reactor facility and a central control room provided therein according to the present invention.
FIG. 3 is an explanatory diagram illustrating a procedure for constructing a central control room of a nuclear reactor facility according to the present embodiment.
FIG. 4 is a perspective view showing a unit according to the embodiment.
FIG. 5 is a perspective view showing a main part of the unit in the embodiment in detail.
FIG. 6 is an explanatory diagram illustrating an example of a method of manufacturing a unit in the present embodiment.
FIG. 7 is a plan view showing a relationship between a unit manufacturing place and a planned construction position of a central control room in the present embodiment.
FIG. 8 is an explanatory diagram illustrating a procedure for constructing a central control room of a nuclear reactor facility according to the present embodiment.
FIG. 9 is an explanatory diagram illustrating an example of a unit support structure according to the present embodiment.
FIG. 10
It is an explanatory view for explaining a construction procedure of a central control room of a nuclear reactor facility according to the present embodiment.
FIG. 11 is an explanatory diagram illustrating a procedure for constructing a central control room of a nuclear reactor facility according to the present embodiment.
FIG. 12 is an explanatory diagram partially showing in detail a state of a light ceiling portion of a central control room in the present embodiment.
FIG. 13 is an explanatory diagram illustrating an example of a conventional procedure for constructing a central control room of a nuclear reactor facility.
FIG. 14 is an explanatory diagram illustrating an example of a conventional procedure for building a central control room of a nuclear reactor facility.
FIG. 15 is an explanatory diagram illustrating an example of a conventional procedure for constructing a central control room of a nuclear reactor facility.
FIG. 16 is an explanatory diagram illustrating an example of a conventional procedure for constructing a central control room of a nuclear reactor facility.
FIG. 17 is an explanatory diagram illustrating an example of a conventional procedure for constructing a central control room of a nuclear reactor facility.
FIG. 18 is an explanatory diagram illustrating an example of a conventional procedure for constructing a central control room of a nuclear reactor facility.
FIG. 19 is an explanatory diagram illustrating an example of a conventional procedure for constructing a central control room of a nuclear reactor facility.
[Explanation of symbols]
2
Claims (6)
前記中央制御室の上部床を支持する骨組みを組立て、当該骨組みに前記中央制御室の天井部に配設される付設器具を取り付けてユニットを製作し、このユニットを前記中央制御室の上部床の構築予定位置の下側に設置して前記中央制御室を構築することを特徴とする原子炉施設の中央制御室の構築工法。A method of constructing a central control room installed in a control building of a nuclear reactor facility,
Assembling a skeleton supporting the upper floor of the central control room, attaching an accessory provided on the ceiling of the central control room to the skeleton to produce a unit, and attaching the unit to the upper floor of the central control room. A method for constructing a main control room of a nuclear reactor facility, wherein the main control room is constructed by being installed below a planned construction position.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002356307A JP2004191080A (en) | 2002-12-09 | 2002-12-09 | Method of constructing central control room in facility for nuclear reactor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002356307A JP2004191080A (en) | 2002-12-09 | 2002-12-09 | Method of constructing central control room in facility for nuclear reactor |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004191080A true JP2004191080A (en) | 2004-07-08 |
Family
ID=32756681
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002356307A Withdrawn JP2004191080A (en) | 2002-12-09 | 2002-12-09 | Method of constructing central control room in facility for nuclear reactor |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004191080A (en) |
-
2002
- 2002-12-09 JP JP2002356307A patent/JP2004191080A/en not_active Withdrawn
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2010275782A (en) | Module structure and plant construction method | |
JP2011153421A (en) | Module structure, plant, and method for constructing the plant using the module structure | |
KR19980080404A (en) | Method of construction of plant buildings and modular structures used in the construction thereof | |
JP4316161B2 (en) | Power plant construction method | |
JPH07292986A (en) | Device and method for constructing long-span roof | |
JP2004191080A (en) | Method of constructing central control room in facility for nuclear reactor | |
JP2003213953A (en) | Plant building constructing method | |
WO2012132161A1 (en) | Module structure, and module construction method | |
JP3559673B2 (en) | Plant building and construction method of the building | |
JP3281972B2 (en) | Reinforcing unit and method of constructing reinforced concrete building using the same | |
JP2004170319A (en) | Method for constructing main steam pipe room in nuclear reactor building | |
JP2002295203A (en) | Foundation pedestal for turbine generator and the construction method | |
JPH08209810A (en) | Anchor bolt installation method for large steel frame | |
JP2661302B2 (en) | Grating floor construction method | |
JP2002194892A (en) | Construction method of building | |
JP2001329689A (en) | Construction method for building | |
JP2888913B2 (en) | External wall panel mounting method | |
JP3207276B2 (en) | How to build a unit building | |
JPH02167937A (en) | Connecting work of steel plate-concrete structure | |
JP3537295B2 (en) | Unit building and its construction method | |
JP2002256643A (en) | Construction method for steel-framed reinforced concrete(src) structure | |
JPH1162077A (en) | Installation of wall panel and fixture therefor | |
JPS62228975A (en) | Method of construction of nuclear plant | |
JP2022089706A (en) | Building inside staircase preceding construction method | |
JPH0740029Y2 (en) | Work scaffold mounting jig to steel column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
RD04 | Notification of resignation of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7424 Effective date: 20040924 |
|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20060307 |