JP3559673B2 - Plant building and construction method of the building - Google Patents

Plant building and construction method of the building Download PDF

Info

Publication number
JP3559673B2
JP3559673B2 JP06270497A JP6270497A JP3559673B2 JP 3559673 B2 JP3559673 B2 JP 3559673B2 JP 06270497 A JP06270497 A JP 06270497A JP 6270497 A JP6270497 A JP 6270497A JP 3559673 B2 JP3559673 B2 JP 3559673B2
Authority
JP
Japan
Prior art keywords
ceiling
building
steel frame
floor
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP06270497A
Other languages
Japanese (ja)
Other versions
JPH10260284A (en
Inventor
寛 長谷川
忠彰 及川
孝一 後田
辰雄 牧田
修一 船木
澄人 前沢
栄 江端
和人 舘洞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP06270497A priority Critical patent/JP3559673B2/en
Publication of JPH10260284A publication Critical patent/JPH10260284A/en
Application granted granted Critical
Publication of JP3559673B2 publication Critical patent/JP3559673B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、プラントの建屋の建設技術に関するものである。
【0002】
【従来の技術】
原子力発電所プラントの建屋には部屋として中央制御室が含まれている。
【0003】
中央制御室の床,壁,天井は、鉄筋コンクリート構造となっており、床面には多数の基礎台,チャンネルベース,制御盤,ケーブルトレー,ケーブル、そして天井部には空調ダクト,照明設備が配置されており建設工程のクリテイカルパスとなっている。
【0004】
図2に、従来工法における中央制御室1の断面図を示す。
【0005】
すなわち、床3,側壁4のコンクリート打設し、その際に側壁4にブラケット9を受梁の受け台として固定し、屋根のデッキプレート受梁8とデッキプレート10を設定し、その受梁8より吊り足場23を支持し、次に、床面においては基礎台13,チャンネルベース17,ケーブルトレー14の工事、また、天井部においては、空調ダクト19,照明設備20,光天井21の工事、又、その上部おいては、鉄筋コンクリートを打設するシーケンスとなっている。
【0006】
従来工法は、天井スラブをデッキプレート構造とし、床及び壁のコンクリートを打設後天井部に仮設鉄骨受梁を据付けし、その上にデッキプレートを設定する。
【0007】
次に、その受梁を利用して天井工事用の仮設の吊り足場を設定した後、床部では基礎台のコンクリート打設工事,チャンネルベース及びケーブルトレー工事、また、吊り足場上の天井部では空調ダクトや照明設備工事、更にはデッキプレートの上面では天井スラブの配筋及びコンクリート打設工事を行うと言う多種類の工事がラップして実施される。
【0008】
そして、上記の工事完了後、中央制御室内部の仕上げ塗装を実施した後初めて中央制御盤が搬入設定される。
【0009】
次に、中央制御盤が設定された後、ケーブリング工事を行い、その後シーケンステストを経て幹線系統よりの受電が可能となる。
【0010】
このような多種類の工事のラップを避けるために、特開平4−293864 号公報に開示されているような、部屋全体をコンクリート部分を除いて内部設備を含んだ状態でルームモジュール化し、そのルームモジュールをその部屋の据えつけ位置に吊り込む建設方法が存在する。しかし、このルームモジュールによる建設方法は
(1)部屋を構成する本設あるいは仮設の鉄骨柱,壁,上方鉄骨天井梁、下方鉄骨天井梁を使用して、鳥カゴ状に形成した後、その中に機器設備,鉄筋,デッキプレート等建築部材を付加したモジュール工法となっている。このため、本ルームモジュールの上方階,下方階では鉄骨部分は柱あるいは壁のみとなり、モジュールを構成する鉄骨上方梁,下方梁がないためルームモジュールとはならず、従来工法を採用せざるを得なくなる。従って、ルームモジュールは一階おきにしかできず、従来工法に比べて大幅な工程短縮が不可能となる。
【0011】
(2)部屋が大きくなるとルームモジュールが大型重量化する上に、ルームモジュールの床の下階への結合が難しくなることも手伝って、据えつけに困難を来す懸念が生じる。
【0012】
そのために、部屋の天井部分だけをモジュール化して据えつけを容易にした例が、特開昭57−5289号公報及び特開平8−86037号公報に掲載されている。それらの公知例によれば、その天井部分のモジュールは、天井を構成する梁や鉄筋やデッキプレートの他に天井に取り付く配管やダクト等の付属構造物を一体にしたモジュール構造物を予め作成しておき、部屋の鉄筋コンクリート製の側壁がコンクリートが固化して強度が充分出た後に、その側壁の面から部屋の内側に突き出した受けに天井のモジュール構造物をクレーンで吊り込んで搭載し、デッキプレート上にコンクリートを打設してプラントの建屋内の部屋を建設している。しかしながら、本モジュール工法は、現地工数の低減には寄与するが、工程短縮については、従来工法に比べ若干の優位性はあるものの、抜本的対策とはなり得ない。
【0013】
【発明が解決しようとする課題】
中央制御室は、一般的には原子炉建屋の外周部の上階に設置され、また、所定のスペースに多くの設備が設置されている。
【0014】
そのため、建屋躯体工事側からのエリア引き渡し時期(完成時期)が遅く、エリア引き渡し後に、空調や照明等の設備工事,制御盤設定やケーブルトレー・ケーブリング等の電気工事,受電に至るシーケンステストが行われるため、建設工程のクリテイカルパスとなっている。
【0015】
上記を改善する方策として、上下のラップ作業により作業消化を図るべく、天井部より仮設の吊り足場を設定し、下層の制御盤用基礎廻り工事と平行して上部の空調ダクトや照明工事、更には天井スラブの躯体工事を実施する例では、作業工程消化が厳しく、また、吊り足場等の仮設設備が多くなると共に作業効率,作業環境,安全性の確保調整に苦慮している。
【0016】
また、ルームモジュールを採用する方法では、前記の通り、ルームモジュールの上方階,下方階は従来工法を採用せざるを得ないため、大幅な工程短縮は期待できず、更に据え付け作業に困難を強いられる。
【0017】
その点、天井だけをモジュール化した例では、据えつけ作業の困難性が解消できるものの、部屋の側壁面が強度的に本設強度評価並みにまで完成してからでないと天井モジュールを据え付け出来ない上、側壁面から天井モジュールを受ける高強度の受けを作る必要があった。このため、天井モジュールを据え付ける時期が遅くなり、部屋の内部で床に据え付けられる制御盤等の機器の据え付け時期が遅れて工程短縮に支障が生じる。しかも、部屋を側壁で囲ってしまうと、その部屋の床に据え付けるべき機器の部屋への搬入作業が行いにくい。
【0018】
従って、部屋の側壁面が完成する前に天井モジュールを据え付けて建設工程を短縮することが要望されていた。
【0019】
本発明の目的は、プラントの建屋をモジュール構造物を用いて建設するに際して、建設工程の短縮を図ることである。
【0020】
【課題を解決するための手段】
上記本発明の目的を達成するために、本発明のプラントの建屋は、プラントの建屋に構築される天井と床と側壁とにより区画される領域の天井構造材と前記天井に付帯する機器設備とを一体化したモジュール構造物は前記領域の柱の一部となる鉄骨をモジュールの構成メンバーとして備え、前記鉄骨の下端部は前記床、及び前記領域の側壁が設置される部分の少なくとも一方に設けられて前記柱の残りの部分となる他の鉄骨の上端部に結合されている構成を備えており、その様な構成を作るに際して採用される本発明の建設工法は、プラントの建屋に構築される天井と床と側壁とによって区画される領域の天井構造材と前記天井に付帯する機器設備と前記領域の柱の一部となる鉄骨とを一体化したモジュール構造物を作り、前記モジュール構造物を揚重機によって前記領域に吊り降ろし、前記鉄骨の下端部を、前記床、及び前記領域の側壁が設置される部分の少なくとも一方に設けられて前記柱の残りの部分となる他の鉄骨の上端部に結合して前記他の鉄骨で前記モジュール構造物を支持するプラントの建屋の建設方法である。
【0021】
【発明の実施の形態】
図1に本発明を適用して建設する原子力発電所プラントの原子炉建屋2の断面図を示す。
【0022】
すなわち、原子炉建屋2は、一般的にはグランドレベルGLを境にして下層階と上層階になっており、原子炉建屋2内の中央制御室1の部屋は建屋外周部の上層階に設置される。
【0023】
図3は、中央制御室1の部屋の天井のモジュール構造物26の鳥瞰図を示す。そのモジュール構造物26は、予め、建設現場のヤードにおいて、鉄骨製の柱の一部となる支持部材である垂直な屋根鉄骨7と水平な受梁8を一体に組立、その受梁8の上面にデッキプレート10を設定し、その屋根鉄骨7と受梁8との組立物を支持点として天井に付帯する機器である空調ダクト19,照明設備20,光天井21,埋設配管24,埋設電線管25、更にその天井の構成部材である上部の鉄筋11を取り付けたモジュールを地組しておく。このモジュール構造物を作成するに当たり、受梁8の間に配置される付帯構造物、例えば照明設備20は受梁8の間にサポート22を掛け渡してそのサポート22に取付、荷重をサポート22経由で受梁8に支持させ光天井21には荷重を加えないようにする。
【0024】
天井のモジュール構造26を建設現場のヤードで作っている間に、床3の工事を行い、床3のコンクリート打設後に部屋の側壁の鉄骨製の柱となる他の支持部材である柱鉄骨6を垂直に据え付ける。図3では、柱鉄骨6の上端部分が露出するように柱鉄骨6の周囲には鉄筋コンクリート乃至は無筋コンクリートが施工されている。
【0025】
次に前記モジュール構造物26を、図4のように、大型揚重機27にて中央制御室1の天井屋根の所定位置に吊り込み、屋根鉄骨7と柱鉄骨6とをボルトジョイント12により機械的に屋根鉄骨7下端部と柱鉄骨6上端部とを機械的に直列に接続して上下に一連の柱を完成させるという鉄骨建方工程を実施する。
【0026】
さらに上階を作る場合には、屋根鉄骨7の上端部に装備されたボルトジョイント12設備で上階の鉄骨柱下端部を接続し、その鉄骨柱の上端に上階用として予め作成したモジュール構造物の屋根鉄骨の下端部をボルトジョイントで結合して上下方向に隣接する階層を建設する。
【0027】
このようにしてモジュール構造物28は柱鉄骨6によって支持される。その支持を成立させるために、柱鉄骨6や屋根鉄骨7の強度は本設強度評価にて設計されることが、仮設強度評価にて設計されていても良い。いずれの場合にも、モジュール構造物26を鉄筋コンクリートや無筋コンクリートに頼ることなく支持するに必要な強度が柱鉄骨6や屋根鉄骨7に与えられている。
【0028】
ここで言う、本設強度評価とは、建築の強度部材と見なして荷重計算のみならず耐震計算も行って評価された強度を与えることであり、仮設強度評価とは、建築の強度部材とは見なさず、荷重計算のみ行って評価された強度が与えられる場合を意味している。
【0029】
仮設強度評価の強度しか与えられない場合には、柱鉄骨や屋根鉄骨はコンクリートに単に埋め殺され、コンクリートに各種の強度を期待する観点から多くの鉄筋の入った鉄筋コンクリートが採用される。
【0030】
柱鉄骨6と屋根鉄骨7とを結合した後は、それらの鉄骨で上部を支えることが出来るから、さらに上層階の部屋をひきつづいて同様に建設するか、上層階に部屋がない場合には、屋上階をそのモジュール構造物の上方に建設する。
【0031】
或いは、柱鉄骨6と屋根鉄骨7とを結合した後は、中央制御室1内の基礎台 13の工事と側壁の工事とを並進させて工程を短縮しても良い。
【0032】
或いは、部屋の側壁面を鉄筋コンクリートで作る前に部屋の床に据え付ける制御盤18などの機器を側壁面が無い開口状態の時点で部屋内に搬入し、その機器の据えつけと側壁面のコンクリート打設工事とを並行させて工程を短縮しても良い。
【0033】
或いは、中央制御室1の側壁面を鉄筋コンクリートで作る壁工事と中央制御室1内での制御盤18などの機器の据え付け工事或いはその据え付け工事とその据え付けに必要なチャンネルベース17の設定作業とを並行して行うことによって建設工程を短縮しても良い。
【0034】
このように、柱,壁,天井梁から成る本設あるいは仮設の鉄骨を利用して、機器設備,建築部材を付加したモジュールを建屋各階毎積み重ねてゆく工法を採用すれば、建屋が従来工法に比べて大幅に早く立ち上がり、中央制御室1内への据え付け機器の据え付けが早まり、その機器の試験も早まる。
【0035】
中央制御室1内への据え付け機器の搬入時期を早めて工程を短縮したい場合には、中央制御室1が原子炉建屋の外側に面して作られていることに着目して、柱鉄骨6と屋根鉄骨7とを結合した後、中央制御室1の側壁を作ることを後回しにして、側壁の無い大開口部が側面に存在している内にその据え付け機器をその大開口部を通して外側から迅速に搬入しても良い。
【0036】
デッキプレート上のコンクリート打設を伴う屋根工事を行うに際して、デッキプレートがデッキプレートより下での、例えば床上での工事に対して影響を防止するから、デッキプレートを境にした上方と下方との工事が同時に行えるから、工程の短縮が成される。
【0037】
図4に大型揚重機27を用いて原子炉建屋2の外周部に本実施例のモジュール構造物26を中央制御室1の天井位置に吊り降ろして搬入する状態を示す。
【0038】
本実施例の工法は、天井部の工事においては、鉄骨部材を組立、これに空調ダクト19,照明設備20、更には、鉄筋11や埋設配管等を組み込んで建屋躯体部材とシステム設備を一体化したところのモジュール構造物26を柱鉄骨6の建方を待って大型揚重機27により吊り込んで柱鉄骨6上端部に結合して設定することにより一気に天井部の躯体部材並びに空調ダクト19,照明設備20,鉄筋11,埋設配管等が据え付けられる。
【0039】
これにより、上記に引き続く制御盤1の搬入及びケーブリング作業を前倒しする事が出来、メインイベントである受電あるいはそれに引き続く系統機能試験が前倒しされ、原子力発電所プラントの建設工程を短縮することが出来る。
【0040】
以上の実施例によれば、中央制御室の床,壁,屋根の躯体工事の建設において、その躯体を鉄骨鉄筋コンクリート構造とすると共にその鉄骨部材を本設強度評価し、更に天井スラブをデッキプレート構造とした中央制御室の建設方法に用いるモジュール構造物が提供でき、このモジュール構造物を用いると、中央制御室天井床部に本モジュール構造物を搬入することで天井部の躯体構造物が一括して一気に搬入でき、所定位置での据付作業が低減され、原子力プラントの建設工程を短縮することができる。この際、鉄骨部材は仮設評価としても良い。
【0041】
同じく、柱,壁,天井梁から成る本設あるいは、仮設の鉄骨を利用して、これに機器設備,建築部材を付加したモジュールを建屋各階毎積み重ねてゆく工法の採用により、原子力プラントの建設工程を従来に比べ大幅に短縮することができる。
【0042】
同じく、中央制御室の天井スラブは受梁にデッキプレートを施設し、その上部には配筋と埋設配管、その下部に天井の付帯機器としての空調ダクトと照明設備等を配備することを特徴とした中央制御室の建設方法に用いるモジュール構造物を提供でき、屋根鉄骨と受梁による鉄骨フレームを利用して空調ダクトや照明設備等を組み込んで一括搬入することにより所定位置での天井の付帯機器の据付作業が低減され、原子力プラントの建設工程をより短縮することができる。
【0043】
同じく、中央制御室の天井に設置される空調ダクト及び照明設備等は、躯体構造物として本設強度評価された柱鉄骨や屋根鉄骨を利用して直接支持することを特徴とした中央制御室の建設方法に用いるモジュールが提供でき、本設強度評価の各種鉄骨を空調ダクト等の支持構造部材の一部として利用することにより天井のコンクリートへの埋込金物が低減され、据付作業の効率向上を図ることができる。
【0044】
同じく、中央制御室の天井に設置される空調ダクト及び照明設備等は、躯体構造物として本設強度評価を行わない仮設評価された鉄骨部材を利用して直接支持することを特徴とした中央制御室の建設方法に用いるモジュール構造物が提供でき、屋根鉄骨や受梁の鉄骨部材は仮設評価し支持部材の一部として利用することにより埋込金物が低減され、据付作業の効率向上を図ることができる。
【0045】
同じく、モジュール構造物を工場又は現地の地組ヤードで組立て、屋根鉄骨や受梁等の屋根躯体構造物と空調ダクトや照明設備等を一体化し、しかる後に組み立てられた前記モジュールを所定の据付位置に大型揚重機により直接搬入することことができ、所定位置への搬入作業と据付作業が低減され、原子力プラントの建設工程を短縮することができる。
【0046】
同じく、中央制御室の天井部のモジュールを工場又は現地で組み立て、その後に前記モジュールを建屋の所定位置に揚重機により直接搬入・設定することでその後に引き続く中央制御盤の据付とケーブリング工事並びに上部のコンクリート打設工事等を前倒しにして幹線系統よりの受電時期を早めることにより、原子力プラントの建設工程を短縮することができる。
【0047】
原子力発電所プラントの原子炉建屋内の中央制御室を例に取り上げ、実施例を以上に説明したが、通路,ポンプ室,熱交換器室等、プラントを構成する他の部屋においても同様の建設技術が適用できる。
【0048】
【発明の効果】
請求項1の発明によれば、モジュール構造物の据え付けが容易で建設領域に設定される機器の据え付けも早まるので、その機器の試験が前倒しに実施できて、プラント建設の工程短縮が成せるプラントの建屋の構造が提供できる。
【0049】
請求項2の発明によれば、請求項1の発明による効果に加えて、建屋の各階層を早期に立ち上げて各階層に装備する諸設備を早期に据え付けることによってプラント建設のより一層の工程短縮が成せるプラントの建屋の構造が提供できる。請求項3の発明によれば、モジュール構造物の据え付けが容易で建設領域に設定される機器の据え付けも早まるので、その機器の試験が前倒しに実施できて、プラント建設の工程短縮が成せるプラントの建屋の建設方法が提供できる。
【0050】
請求項4の発明によれば、請求項3の発明による効果に加えて、建屋の各階層を早期に立ち上げて各階層に装備する諸設備を早期に据え付けることによってプラント建設のより一層の工程短縮が成せるプラントの建屋の建設方法が提供できる。
【0051】
請求項5の発明によれば、建設途中で柱鉄骨にコンクリートを施工する建設過程を経て請求項3の発明による効果を達成することができる。
【図面の簡単な説明】
【図1】原子力発電プラントの原子炉建屋の縦断面図である。
【図2】従来工法による原子力発電プラントの原子炉建屋内の中央制御室の縦断面図である。
【図3】本発明の一実施例による工法による原子力発電プラントの原子炉建屋内の中央制御室の天井のモジュール構造物の吊り込み途中における鳥瞰図である。
【図4】本発明の一実施例による工法による原子力発電プラントの原子炉建屋内の中央制御室の天井のモジュール構造物の吊り込み作業状況を示した全体図である。
【符号の説明】
1…中央制御室、2…原子炉建屋、3…床、6…柱鉄骨(他の支持部材)、7…屋根鉄骨(支持部材)、8…受梁、10…デッキプレート、11…鉄筋、12…ボルトジョイント、13…基礎台、17…チャンネルベース、18…制御盤、26…モジュール構造物、27…大型揚重機。
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a construction technique for a plant building.
[0002]
[Prior art]
The building of the nuclear power plant includes a central control room as a room.
[0003]
The floor, walls, and ceiling of the main control room have a reinforced concrete structure, and a large number of bases, channel bases, control panels, cable trays, cables, and air conditioning ducts and lighting equipment are located on the ceiling. It is a critical path for the construction process.
[0004]
FIG. 2 shows a sectional view of the central control room 1 in the conventional method.
[0005]
That is, concrete is poured into the floor 3 and the side wall 4, and at that time, the bracket 9 is fixed to the side wall 4 as a receiving stand of the receiving beam, and the deck plate receiving beam 8 and the deck plate 10 of the roof are set. The suspended scaffolding 23 is supported, and then, on the floor surface, construction of the base 13, the channel base 17 and the cable tray 14, and on the ceiling portion, construction of the air-conditioning duct 19, lighting equipment 20 and light ceiling 21. In addition, the upper part has a sequence of placing reinforced concrete.
[0006]
In the conventional construction method, a ceiling slab has a deck plate structure, a concrete for the floor and walls is cast, a temporary steel beam is installed on the ceiling, and a deck plate is set thereon.
[0007]
Next, the temporary suspension scaffolding for ceiling construction is set using the receiving beams, and then the concrete placement work of the foundation base, the channel base and the cable tray construction work on the floor, and the ceiling on the suspension scaffolding Various types of construction, such as air conditioning ducts and lighting equipment construction, and reinforcement of ceiling slabs and concrete placing work on the upper surface of the deck plate are performed by wrapping.
[0008]
After the completion of the above construction, the central control panel is set to be carried in for the first time after finishing the interior of the central control room.
[0009]
Next, after the central control panel is set, cabling work is performed, and then power can be received from the main system through a sequence test.
[0010]
In order to avoid such various types of construction laps, as disclosed in Japanese Patent Application Laid-Open No. 4-293864, the entire room is converted into a room module including the internal equipment except for the concrete part, and the room is converted into a room module. There is a construction method in which the module is suspended in the installation position of the room. However, the construction method using this room module is as follows: (1) A bird cage is formed by using a permanent or temporary steel column, wall, upper steel ceiling beam, and lower steel ceiling beam that constitute the room, and then the room is formed. It is a modular construction method in which building components such as equipment, reinforcing bars, deck plates, etc. are added to the construction. For this reason, on the upper floor and lower floor of this room module, the steel frame part consists only of columns or walls, and there is no steel frame upper beam or lower beam that constitutes the module. Disappears. Therefore, the room module can be formed only every other floor, and it is impossible to greatly reduce the number of steps as compared with the conventional method.
[0011]
(2) As the size of the room increases, the size of the room module increases, and in addition, it becomes difficult to connect the room module to the lower floor of the floor.
[0012]
For this purpose, Japanese Patent Application Laid-Open Nos. 57-5289 and 8-86037 disclose examples in which only the ceiling portion of a room is modularized to facilitate installation. According to those known examples, the module of the ceiling portion is prepared in advance by forming a module structure in which ancillary structures such as pipes and ducts attached to the ceiling in addition to beams, reinforcing bars and deck plates constituting the ceiling are integrated. After the concrete wall of the room is solidified and the concrete is solid enough, the ceiling module structure is suspended by a crane and mounted on the deck that protrudes into the room from the side wall surface. Concrete is poured on the plate to build a room inside the plant. However, although this module method contributes to the reduction of man-hours in the field, it can not be a drastic measure to shorten the process, although it has some advantages over the conventional method.
[0013]
[Problems to be solved by the invention]
The main control room is generally installed on the upper floor of the outer periphery of the reactor building, and many facilities are installed in a predetermined space.
[0014]
For this reason, the area delivery time (completion time) from the building frame construction side is late, and after the area delivery, the sequence test from equipment work such as air conditioning and lighting, control panel setting, electrical work such as cable tray and cabling, and power reception is performed. This is a critical path for the construction process.
[0015]
As a measure to improve the above, temporary suspension scaffolding is set from the ceiling to reduce the work by upper and lower lap work, and the upper air conditioning duct and lighting work in parallel with the lower control panel foundation work In the example of the construction of the ceiling slab, the work process is severely digested, and the number of temporary facilities such as suspension scaffolds is increasing, and it is difficult to adjust the work efficiency, work environment and safety.
[0016]
Further, in the method using the room module, as described above, the upper floor and the lower floor of the room module have to adopt the conventional method, so that a significant reduction in the number of steps cannot be expected, and the installation work is more difficult. Can be
[0017]
In that respect, in the example where only the ceiling is modularized, the difficulty of the installation work can be solved, but the ceiling module can not be installed unless the side wall surface of the room is completed to the same level as the main installation strength evaluation It was necessary to make a high-strength receiver for receiving the ceiling module from the top and side walls. For this reason, the time for installing the ceiling module is delayed, and the time for installing devices such as a control panel that is installed on the floor inside the room is delayed. Moreover, if the room is surrounded by the side wall, it is difficult to carry in the equipment to be installed on the floor of the room into the room.
[0018]
Therefore, it has been demanded that the ceiling module be installed before the side wall surface of the room is completed to shorten the construction process.
[0019]
An object of the present invention is to shorten a construction process when constructing a plant building using a module structure.
[0020]
[Means for Solving the Problems]
In order to achieve the above object of the present invention, a plant building of the present invention has a ceiling structural material in an area defined by a ceiling, a floor, and side walls constructed in the plant building, and equipment and facilities attached to the ceiling. The module structure integrated with comprises a steel frame which is a part of the column in the area as a component member of the module, and a lower end of the steel frame is provided on at least one of the floor and a part where the side wall of the area is installed is provided with a configuration that is coupled to the upper end portion of the other steel as the rest of the post, the construction method of the present invention employed when making such a structure is built building plant A module structure that integrates a ceiling structural material in an area defined by a ceiling, a floor, and side walls, equipment and facilities attached to the ceiling, and a steel frame that is a part of a pillar in the area, and forms the module structure. Things the down hanging the area by the crane, the lower end portion of the steel, the floor, and sidewalls of the region provided on at least one part which is installed in the other steel as the rest of the column A method of constructing a plant building connected to an upper end portion and supporting the module structure with the another steel frame .
[0021]
BEST MODE FOR CARRYING OUT THE INVENTION
FIG. 1 shows a sectional view of a reactor building 2 of a nuclear power plant constructed by applying the present invention.
[0022]
That is, the reactor building 2 generally has a lower floor and an upper floor with the boundary of the ground level GL, and the room of the central control room 1 in the reactor building 2 is installed on the upper floor around the building outdoors. Is done.
[0023]
FIG. 3 shows a bird's-eye view of the module structure 26 on the ceiling of the room in the central control room 1. The module structure 26 previously assembles a vertical roof steel frame 7 which is a support member to be a part of a steel column and a horizontal receiving beam 8 integrally in a yard of a construction site in advance, and an upper surface of the receiving beam 8. Air conditioner duct 19, lighting equipment 20, light ceiling 21, buried piping 24, buried conduit, which is a device attached to the ceiling with the assembly of the roof steel frame 7 and the receiving beam 8 as a support point. 25. Further, a module to which the upper reinforcing bar 11, which is a component of the ceiling, is attached is laid. In making this modular structure, ancillary structures, such as the lighting equipment 20, which are arranged between the support beams 8, span the support 22 between the support beams 8 and are attached to the support 22, and the load is transmitted through the support 22. And the light ceiling 21 is not subjected to a load.
[0024]
While the ceiling module structure 26 is being made in the yard of the construction site, the floor 3 is constructed, and after the floor 3 is cast into concrete, the column steel frame 6 which is another supporting member that becomes a steel column on the side wall of the room. Is installed vertically. In FIG. 3, reinforced concrete or unreinforced concrete is constructed around the column steel frame 6 so that the upper end portion of the column steel frame 6 is exposed.
[0025]
Next, as shown in FIG. 4, the module structure 26 is suspended by a large lifting machine 27 at a predetermined position on the ceiling roof of the central control room 1, and the roof steel frame 7 and the column steel frame 6 are mechanically connected by the bolt joint 12. Then, a steel frame construction process of mechanically connecting the lower end of the roof steel frame 7 and the upper end of the column steel frame 6 in series to complete a series of columns up and down is performed.
[0026]
When the upper floor is further constructed, the lower end of the upper steel column is connected to the upper end of the roof steel frame 7 with a bolt joint 12 facility, and a modular structure previously created for the upper floor at the upper end of the steel column. The lower end of the object's roof steel frame is connected with a bolt joint to construct a vertically adjacent story.
[0027]
In this way, the module structure 28 is supported by the column steel 6. In order to realize the support, the strength of the column steel frame 6 and the roof steel frame 7 is designed by the permanent strength evaluation, and may be designed by the temporary strength evaluation. In any case, the column steel structure 6 and the roof steel structure 7 have the strength required to support the module structure 26 without relying on reinforced concrete or unreinforced concrete.
[0028]
The permanent strength evaluation referred to here is to give the evaluated strength by performing not only load calculation but also seismic calculation assuming that it is a building strength member, and temporary strength evaluation is It means that the evaluated strength is given by performing only the load calculation without considering it.
[0029]
When only the strength of the temporary strength evaluation is given, the column steel and the roof steel are simply buried in the concrete, and reinforced concrete containing many reinforcing bars is used from the viewpoint of expecting various strengths in the concrete.
[0030]
After the column steel frame 6 and the roof steel frame 7 are joined, the upper part can be supported by those steel frames. Therefore, the rooms on the higher floors can be constructed in succession, or if there is no room on the upper floor, A rooftop is built above the modular structure.
[0031]
Alternatively, after connecting the column steel frame 6 and the roof steel frame 7, the construction of the foundation 13 in the central control room 1 and the construction of the side wall may be translated to shorten the process.
[0032]
Alternatively, a device such as a control panel 18 to be installed on the floor of the room before the side wall surface of the room is made of reinforced concrete is carried into the room when there is no side wall surface, and the installation of the device and the concrete pouring of the side wall surface are performed. The process may be shortened in parallel with the construction work.
[0033]
Alternatively, the wall work for making the side wall surface of the main control room 1 made of reinforced concrete, the installation work of the equipment such as the control panel 18 in the main control room 1 or the installation work and the setting work of the channel base 17 necessary for the installation are performed. The construction process may be shortened by performing the processes in parallel.
[0034]
In this way, using a permanent or temporary steel frame consisting of pillars, walls, and ceiling beams and stacking modules with equipment and building components on each floor of the building, the building can be replaced with the conventional method. In this case, the equipment is started up much faster, the installation of the installation equipment in the central control room 1 is accelerated, and the test of the equipment is also accelerated.
[0035]
If it is desired to shorten the process by earliering the time for loading the installation equipment into the main control room 1 and paying attention to the fact that the main control room 1 is made to face the outside of the reactor building, After the side walls of the main control room 1 have been combined with the roof steel frame 7, the installation equipment can be externally passed through the large opening while the large opening without the side wall is present on the side. You may bring in quickly.
[0036]
When performing roofing work involving placing concrete on a deck plate, since the deck plate will not affect the work below the deck plate, for example, work on the floor, the upper and lower sides of the deck plate Since the construction can be performed at the same time, the process can be shortened.
[0037]
FIG. 4 shows a state in which the module structure 26 according to the present embodiment is suspended at the ceiling position of the central control room 1 and carried into the outer peripheral portion of the reactor building 2 using the large-sized hoisting machine 27.
[0038]
In the construction method of the present embodiment, in the construction of the ceiling part, a steel frame member is assembled, and the air conditioning duct 19, the lighting equipment 20, the reinforcing bar 11, the buried piping, and the like are incorporated into the building member to integrate the building frame member and the system equipment. The module structure 26 thus obtained is suspended by a large lifting machine 27 after waiting for the construction of the column steel frame 6 and connected to the upper end of the column steel frame 6 to be set at once. Equipment 20, rebar 11, buried piping, etc. are installed.
[0039]
As a result, the following loading and cabling work of the control panel 1 can be brought forward, and the main event of receiving power or the subsequent system function test can be brought forward, thereby shortening the construction process of the nuclear power plant. .
[0040]
According to the above embodiment, in the construction of the framing of the floor, walls and roof of the main control room, the framing is made into a steel reinforced concrete structure, the steel members are evaluated for their permanent strength, and the ceiling slab is constructed in a deck plate structure. A modular structure used for the construction method of the central control room can be provided, and by using this module structure, the module structure can be brought into the central control room ceiling floor, and the frame structure at the ceiling can be integrated. Thus, the installation work at a predetermined position can be reduced, and the construction process of the nuclear power plant can be shortened. At this time, the steel frame member may be used for temporary evaluation.
[0041]
Similarly, the construction process of a nuclear power plant is implemented by using a permanent construction consisting of pillars, walls, and ceiling beams, or using a temporary steel frame and stacking modules with equipment and construction members added to each floor of the building. Can be greatly reduced as compared with the conventional case.
[0042]
Similarly, the ceiling slab of the central control room is equipped with a deck plate on the receiving beam, reinforcing bars and buried piping on the upper part, and air conditioning ducts and lighting equipment as auxiliary equipment of the ceiling on the lower part. Equipment that can be used for the construction method of the main control room, which has been installed. Installation work can be reduced, and the construction process of a nuclear power plant can be further shortened.
[0043]
Similarly, air conditioning ducts, lighting equipment, etc. installed on the ceiling of the central control room are directly supported using pillar steel and roof steel, which have been fully evaluated for their strength, as the frame structure. We can provide modules used in the construction method, and by using various steel frames for permanent construction evaluation as a part of supporting structural members such as air conditioning ducts, the amount of hardware embedded in concrete on the ceiling is reduced and the efficiency of installation work is improved. Can be planned.
[0044]
Similarly, air conditioning ducts, lighting equipment, etc. installed on the ceiling of the central control room are directly supported using temporary evaluated steel members that are not subject to permanent strength evaluation as frame structures. A modular structure used for the room construction method can be provided, and the roof steel members and the steel members of the receiving beams are temporarily evaluated and used as a part of the support members, thereby reducing embedded hardware and improving the efficiency of installation work. Can be.
[0045]
Similarly, assemble the module structure at the factory or on-site yard, integrate the roof frame structure such as roof steel beams and receiving beams with the air conditioning ducts and lighting equipment, and then place the assembled module at the specified installation position. Can be directly carried in by a large-sized hoist, and the work of carrying in to a predetermined position and the work of installation can be reduced, and the construction process of a nuclear power plant can be shortened.
[0046]
Similarly, assembling the module at the ceiling of the central control room at the factory or on-site, and then directly loading and setting the module at a predetermined position in the building by a hoist, followed by installation of the central control panel and cabling work and The construction process of the nuclear power plant can be shortened by bringing the upper concrete placement work or the like ahead of schedule so as to advance the power receiving time from the main system.
[0047]
Although the embodiment has been described above by taking the main control room in the reactor building of a nuclear power plant as an example, the same construction is performed in other rooms constituting the plant, such as a passage, a pump room, and a heat exchanger room. Technology is applicable.
[0048]
【The invention's effect】
According to the first aspect of the present invention, since the installation of the module structure is easy and the installation of the equipment set in the construction area is quick, the test of the equipment can be carried out earlier, and the plant construction process can be shortened. Building structure can be provided.
[0049]
According to the invention of claim 2, in addition to the effect of the invention of claim 1, further steps of plant construction can be achieved by starting up each floor of the building at an early stage and installing various equipment to be installed on each floor at an early stage. It is possible to provide a plant building structure that can be shortened. According to the third aspect of the present invention, since the installation of the module structure is easy and the installation of the equipment set in the construction area is quick, the test of the equipment can be carried out ahead of time, and the plant construction process can be shortened. Can be provided.
[0050]
According to the invention of claim 4, in addition to the effect of the invention of claim 3, a further step of plant construction is achieved by starting up each floor of the building at an early stage and installing various equipment to be installed on each floor at an early stage. It is possible to provide a method of constructing a plant building that can be shortened.
[0051]
According to the fifth aspect of the present invention, the effect of the third aspect of the present invention can be achieved through a construction process of constructing concrete on a column steel frame during construction .
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view of a reactor building of a nuclear power plant.
FIG. 2 is a longitudinal sectional view of a central control room in a reactor building of a nuclear power plant according to a conventional method.
FIG. 3 is a bird's-eye view during suspension of a module structure on a ceiling of a central control room in a reactor building of a nuclear power plant by a method according to an embodiment of the present invention.
FIG. 4 is an overall view showing a hanging operation of a module structure on a ceiling of a central control room in a reactor building of a nuclear power plant by a construction method according to an embodiment of the present invention.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Central control room, 2 ... Reactor building, 3 ... Floor, 6 ... Column steel (other supporting members), 7 ... Roof steel frame (supporting members), 8 ... Receiving beam, 10 ... Deck plate, 11 ... Rebar, 12: bolt joint, 13: base, 17: channel base, 18: control panel, 26: module structure, 27: large hoist.

Claims (5)

プラントの建屋に構築される天井と床と側壁とにより区画される領域の天井構造材と前記天井に付帯する機器設備とを一体化したモジュール構造物は前記領域の柱の一部となる鉄骨をモジュールの構成メンバーとして備え、前記鉄骨の下端部は前記床、及び前記領域の側壁が設置される部分の少なくとも一方に設けられて前記柱の残りの部分となる他の鉄骨の上端部に結合されている構成を備えることを特徴としたプラントの建屋。The module structure integrating the ceiling structural material of the area defined by the ceiling, the floor, and the side walls and the equipment attached to the ceiling is a steel frame that is a part of the pillar of the area. Provided as a component of a module, a lower end of the steel frame is provided on at least one of the floor and a portion where a side wall of the area is installed, and is coupled to an upper end portion of another steel frame which is a remaining portion of the column. A plant building characterized by having the following configuration. 請求項1において、モジュール構造物を各鉄骨間の結合によって階層毎に設置した構造を備えたプラントの建屋。The plant building according to claim 1, comprising a structure in which the module structure is installed for each story by coupling between steel frames. プラントの建屋に構築される天井と床と側壁とによって区画される領域の天井構造材と前記天井に付帯する機器設備と前記領域の柱の一部となる鉄骨とを一体化したモジュール構造物を作り、前記モジュール構造物を揚重機によって前記領域に吊り降ろし、前記鉄骨の下端部を、前記床、及び前記領域の側壁が設置される部分の少なくとも一方に設けられて前記柱の残りの部分となる他の鉄骨の上端部に結合して前記他の鉄骨で前記モジュール構造物を支持するプラントの建屋の建設方法。A module structure that integrates a ceiling structural material in an area defined by a ceiling, a floor, and a side wall to be constructed in a plant building, equipment attached to the ceiling, and a steel frame that is a part of a pillar in the area. Making, the module structure is suspended in the area by a hoist, and the lower end of the steel frame is provided on at least one of the floor and the part where the side wall of the area is installed, and the remaining part of the column is provided. A method of constructing a plant building, wherein the module structure is connected to the upper end of another steel frame and the module structure is supported by the other steel frame. 請求項3において、前記プラントの建屋の建設を前記建屋の上下に隣接する複数の階層の建設に適用することを特徴とするプラントの建屋の建設方法。The method according to claim 3, wherein the construction of the plant building is applied to the construction of a plurality of floors vertically adjacent to the building. 請求項3において、前記モジュール構造物を揚重機によって前記領域に吊り降ろす以前に、前記他の鉄骨の周囲に、上端部が露出するようにして、鉄筋コンクリート又は無筋コンクリートを施工することを特徴とするプラントの建屋の建設方法。The reinforced concrete or the unreinforced concrete is constructed according to claim 3, wherein before the module structure is suspended in the area by a hoist, around the other steel frame, an upper end is exposed, and reinforced concrete or unreinforced concrete is constructed. How to build the building of the plant you want.
JP06270497A 1997-03-17 1997-03-17 Plant building and construction method of the building Expired - Fee Related JP3559673B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP06270497A JP3559673B2 (en) 1997-03-17 1997-03-17 Plant building and construction method of the building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP06270497A JP3559673B2 (en) 1997-03-17 1997-03-17 Plant building and construction method of the building

Publications (2)

Publication Number Publication Date
JPH10260284A JPH10260284A (en) 1998-09-29
JP3559673B2 true JP3559673B2 (en) 2004-09-02

Family

ID=13207979

Family Applications (1)

Application Number Title Priority Date Filing Date
JP06270497A Expired - Fee Related JP3559673B2 (en) 1997-03-17 1997-03-17 Plant building and construction method of the building

Country Status (1)

Country Link
JP (1) JP3559673B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004527679A (en) * 2000-11-24 2004-09-09 シーメンス アクチエンゲゼルシヤフト Module system for building industrial equipment
JP5134219B2 (en) * 2006-07-27 2013-01-30 株式会社日立製作所 Building construction method

Also Published As

Publication number Publication date
JPH10260284A (en) 1998-09-29

Similar Documents

Publication Publication Date Title
CN106013454B (en) Building and method of construction based on large spatial structure body and free-standing peripheral structure
US20230417045A1 (en) Method for constructing a concrete floor in a multistorey building
KR20210038684A (en) Precast building construction system
JP3569861B2 (en) Construction method of stairs and staircase, staircase support device, and staircase structure
JPH10266602A (en) Method for constructing building of plant, and module structure to be used for construction thereof
JP2750368B2 (en) Construction method of reactor containment top slab
JP3559673B2 (en) Plant building and construction method of the building
JPH07292986A (en) Device and method for constructing long-span roof
CN113047627A (en) Finished steel reinforcement cage grading assembly method suitable for bearing metal column template
RU2197578C2 (en) Structural system of multistory building and process of its erection ( variants )
JPH0699959B2 (en) Nuclear power plant building construction method
RU2338843C1 (en) Method of multistorey building carcassing
JP2002194892A (en) Construction method of building
JPH11247449A (en) Building construction method
JP3281421B2 (en) Construction method of horizontal beam erected on tower
JPS6025576B2 (en) Building construction method
JP3207276B2 (en) How to build a unit building
JP2000160686A (en) Composite structure of reinforced concrete column and steel frame beam, and its execution
JPH0270848A (en) Floor slab
JP2003213953A (en) Plant building constructing method
JP3205467B2 (en) Translational construction of the building and the equipment stand, and advance loading of equipment into the building
JPS63165634A (en) Construction of wall type building
JPH0227104Y2 (en)
JP2522494B2 (en) Nuclear power plant construction method
JPS6025575B2 (en) Building construction method

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040518

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040524

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080528

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080528

Year of fee payment: 4

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080528

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080528

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080528

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090528

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100528

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110528

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110528

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120528

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130528

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees