JPH0699959B2 - Nuclear power plant building construction method - Google Patents

Nuclear power plant building construction method

Info

Publication number
JPH0699959B2
JPH0699959B2 JP61178261A JP17826186A JPH0699959B2 JP H0699959 B2 JPH0699959 B2 JP H0699959B2 JP 61178261 A JP61178261 A JP 61178261A JP 17826186 A JP17826186 A JP 17826186A JP H0699959 B2 JPH0699959 B2 JP H0699959B2
Authority
JP
Japan
Prior art keywords
building
power plant
nuclear power
concrete
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP61178261A
Other languages
Japanese (ja)
Other versions
JPS6335931A (en
Inventor
良平 宮原
孝一 後田
澄雄 岩島
末治 石井
忠男 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP61178261A priority Critical patent/JPH0699959B2/en
Publication of JPS6335931A publication Critical patent/JPS6335931A/en
Publication of JPH0699959B2 publication Critical patent/JPH0699959B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Organic Low-Molecular-Weight Compounds And Preparation Thereof (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、原子力発電所建屋の建築工法に係り、特に建
設工事期間が短いプラントにおける建築側工事の作業消
化の早期化を図るのに好適な原子力発電所建屋の建築工
法に関する。
Description: TECHNICAL FIELD The present invention relates to a construction method for a nuclear power plant building, and is particularly suitable for accelerating the work exhaustion of construction work in a plant having a short construction period. Related to the construction method of the nuclear power plant building.

〔従来の技術〕[Conventional technology]

現状の原子力発電所は、巨大な一品生産的なプラントで
あり、その建設工事は膨大な物量と労働力を投入して進
められている。
The current nuclear power plant is a huge one-productive plant, and its construction work is carried out with a huge amount of material and labor.

最近の原子力発電所の建設工事は、諸般の電力事情か
ら、大巾な工程短縮と原価低減を求められており、従来
の建設工事期間を約1年程縮める超短縮工程の原子力発
電所の建設工法の開発が要求されている。
Due to various electric power circumstances, the recent construction work of a nuclear power plant is required to greatly shorten the process and reduce the cost. The construction of the ultra-short process nuclear power plant that shortens the conventional construction work period by about one year is required. Development of construction method is required.

ところが、現状の原子力発電所の建設工事は、発電所内
部に納められる膨大な機器据付工事と発電所建屋本体を
建設する土木建築工事が有機的に錯綜しており、単に物
量、労働力の多量投入による工事期間短縮には限界がき
ている。それでも、機械側工事は、据付品を工場或いは
現地加工場で機械、配管、タンク等を一体ユニット化し
たプレファブ製品を大型揚重機等で建屋内の所定の据付
位置へ直接吊り込むダイレクト・オン工法等の採用によ
り、従来に比べて格段の現地工事省力化、工事の早期化
が図られてきている。一方、建築側工事は従来の鉄筋コ
ンクリート工事を踏襲しているままである。
However, the construction work of the present nuclear power plant is organically complicated by the huge equipment installation work to be installed inside the power plant and the civil engineering construction work to construct the main body of the power plant. There is a limit to shortening the construction period by inputting. Even so, the machine side work is a direct-on construction method in which the prefabricated product, which is an integrated unit of machines, pipes, tanks, etc., is installed in a factory or on-site processing site, and a large hoist directly hangs the prefabricated product to a predetermined installation position in the building By adopting the above, etc., the labor saving on site construction and the construction work have been made much faster than before. On the other hand, the construction work is still following the conventional reinforced concrete work.

具体的には第9図の施工手順に示すように、(1)鉄筋
工事、(2)型枠及び支保工作業、(3)コンクリート
打設、(4)型枠及び支保工解体作業の繰返しである。
これら作業のうち(1)の鉄筋工事は原子力発電所の性
格上、配筋量が一般構造物に比べて多大であるため、省
力化の方向で進み、柱鉄筋の一部をユニット化して吊り
込むプレファブ鉄筋工法等が実用化されているが、継手
構造や他の埋設物との干渉問題等のため根本的な作業の
改善、工程短縮には至っていない。また、現状の鉄筋コ
ンクリート工事では、コンクリート打設時、型枠を保持
する構造体が必要であるが、一般に、柱、壁などの型枠
保持には足場材を用い、梁、床の型枠保持には重量支保
工を用いる、この梁、床の場合は、打設したコンクリー
トの重量をすべて仮設材で保持せねばならず、一般の足
場材では支持能力が不足である。これら型枠保持構造体
の使い分け、盛り替え作業による型枠作業の煩雑さも建
築作業工程短縮上の弊害となっている。
Specifically, as shown in the construction procedure in FIG. 9, (1) rebar construction, (2) formwork and support work, (3) concrete placing, (4) formwork and support dismantling work repeated Is.
Of the above works, the reinforcement work (1) has a large amount of reinforcements compared to general structures due to the nature of the nuclear power plant. Although the prefabricated reinforcing bar construction method has been put to practical use, fundamental work has not been improved and the process has not been shortened due to problems such as interference with the joint structure and other buried objects. Moreover, in the current reinforced concrete construction, a structure that holds the formwork is required when placing concrete, but generally, scaffolding is used to hold the formwork such as columns and walls, and the formwork of beams and floors is held. For this beam and floor, all the weight of the placed concrete must be held by the temporary material, and the supporting capacity of ordinary scaffolding materials is insufficient. The complexity of the formwork work due to the proper use of these formwork holding structures and the refilling work is also an obstacle to shortening the construction work process.

一般の建築工事では、躯体工事の早期立上りを図るた
め、例えば、特開昭49−82125号公報に記載のように、
基礎上に鉄骨パネルユニットを並列に立設し、該鉄骨パ
ネルユニット間に上方から遂次積層挿入するボックスユ
ニットの天井枠の横梁を鉄骨パネルユニットの柱に接合
し、ボックスユニットを各個に横梁で支持し、骨組を軽
量簡易にする「中高層プレハブビルの建設方法」を採用
する場合がある。しかし、原子力発電所建屋は、地震そ
の他の災害時における原子炉施設の安全性と機器保持の
ため、強固に耐震性を必要とし、そのため、建屋躯体構
造は一般建屋より重厚な鉄筋コンクリート構造となって
いて、前述のような簡易パネルユニットの接合によるプ
レハブビル構造で原子力発電所建屋を構築することは耐
震性の面から不適当であった。
In general building work, in order to achieve an early start of the frame work, for example, as described in JP-A-49-82125,
Steel panel units are erected in parallel on the foundation, and the transverse beams of the ceiling frame of the box unit, which are sequentially stacked and inserted between the steel panel units, are joined to the pillars of the steel panel unit, and the box units are individually provided with transverse beams. In some cases, the "construction method for medium- and high-rise prefabricated buildings" that supports and reduces the weight of the frame is adopted. However, the nuclear power plant building requires strong seismic resistance in order to ensure the safety and equipment retention of the reactor facility in the event of an earthquake or other disaster, and therefore the building structure has a heavier reinforced concrete structure than the general building. Therefore, it was inappropriate from the viewpoint of earthquake resistance to construct a nuclear power plant building with a prefabricated building structure by joining the above-mentioned simple panel units.

又、プレキャストコンクリート部材を用いて躯体構造の
早期立上りを図る建築工法として、特開昭51−177410号
公報に示す工法がある。これは、基礎部に溝型のプレキ
ャストコンクリート基礎パネルを建込み、その上に門型
のプレキャストコンクリート基準パネルを建込むことに
より、建屋各階層を構築してゆく建築工法である。この
建築工法を用いると、建屋躯体構造は強固なプレキャス
トコンクリート構造となり、耐震性を満足する。しか
し、一般に原子力発電所建屋の各階層構成は、大型機
器、タンク類を設置するため、床高で10m程度、梁スパ
ンで12m程度要求される。又、躯体壁、床厚も耐震性や
放射能遮蔽要求から2m程度必要とされる。このような規
模、寸法の構造体をプレキャストコンクリートのユニッ
トにすると、単位ユニットの自重のみで千トン超の重量
構造体となる。現在の原子力発電所建屋の建築工事にお
いて、前記のプレキャストコンクリートユニット工法を
用いることは、そのユニットの据付に使用する揚重機設
備や運搬施設の適応の面で能力、コスト的に不適当であ
った。
Further, as a construction method for early rising of a frame structure using a precast concrete member, there is a construction method disclosed in JP-A-51-177410. This is a construction method in which each floor of the building is constructed by building a groove-type precast concrete foundation panel in the foundation and then building a gate-type precast concrete reference panel on it. When this construction method is used, the building frame structure becomes a strong precast concrete structure and satisfies the earthquake resistance. However, in general, each floor structure of a nuclear power plant building requires a floor height of about 10 m and a beam span of about 12 m in order to install large equipment and tanks. In addition, the building wall and floor thickness are required to be about 2 m due to the requirements for earthquake resistance and radiation shielding. If a structure of such a scale and dimensions is made into a unit of precast concrete, the weight of the unit alone will be over 1,000 tons. In the construction work of the present nuclear power plant building, using the precast concrete unit construction method was inappropriate in terms of capacity and cost in terms of adaptation of the lifting machine equipment and the transportation facility used for the installation of the unit. .

又、特開昭51−31019号公報には、別途生産したコア・
ユニットを構築物施工現場へ搬入し、これを内型枠とし
てコンクリートを打設する構築物施工方法が記載されて
いるが、しかし、原子力発電所の高い天井高や大型機器
の据付けに対する配慮に欠けていた。
In addition, in Japanese Patent Laid-Open No. 51-31019, a separately manufactured core
Although a construction method is described in which the unit is brought into the construction site and concrete is placed using this as an internal formwork, however, consideration for the high ceiling height of nuclear power plants and the installation of large equipment was lacking. .

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

上記従来技術は、一般建造物の建築工事においては、各
種のプレファブ構築工法を用いることにより躯体工事の
早期立上りを可能としたが、これらの工法を原子力発電
所建屋の建築に用いるには、躯体強度、耐震性及び放射
能遮蔽能力の面で不適当で、更に建設設備の膨大化を招
くなどの弊害があるため採用できなかった。そのため従
来の一般的な鉄筋コンクリート工法を用いて建屋を建築
しており、その作業工程の輻輳さ故に、建築工事期間の
短縮化、更には原子力発電所建設工事期間の短縮化が阻
害されていた。
The above-mentioned conventional technology, in the construction work of general buildings, enabled early start-up of the frame work by using various prefabricated construction methods, but in order to use these construction methods for the construction of the nuclear power plant building, It was unsuitable because it was unsuitable in terms of strength, earthquake resistance, and radiation shielding ability, and also had the adverse effect of enlarging construction equipment. Therefore, the building is built by using the conventional general reinforced concrete construction method, and due to the congestion of the working process, the shortening of the construction work period and further the shortening of the nuclear power plant construction work period are hindered.

本発明の目的は、原子力発電所建屋の躯体工事期間を早
期化し、更に機械側工事を建築工程の中に取り入れ、機
械側工程の前倒しを可能とする建築躯体の建築工法を用
いることにより、建築工程を短縮された原子力発電所を
提供することにある。
The purpose of the present invention is to accelerate the construction period of the nuclear power plant building, and to incorporate the machine side construction into the construction process, and to use the construction method of the building frame that allows the machine side process to be moved forward. It is to provide a nuclear power plant with a shortened process.

〔課題を解決するための手段〕[Means for Solving the Problems]

上記目的は、原子力発電所建屋の建築工法において、
建屋床のコンクリート打設後に、床上の所定位置に柱筋
及び壁筋(4)を支持するサポート部材(3)を設定
し、予め組み立てた前記柱筋及び壁筋(4)を前記所
定位置に吊り込んで前記サポート部材(3)に固定し、
前記サポート部材(3)又は前記柱筋及び壁筋(4)
の工事と前後して、前記柱及び壁の施工位置以外の前記
床上の所定位置に配管(6)、トレイ、ダクト支持金具
或いは小型機器(5)等を搬入し、次に、鋼製構造材
からなる架構(1)の上面及び少なくとも対向する両側
面の外側が鉄板型枠(2)により閉ざされ、且つ下面を
開放して予め製作した構造体(8)(以下スチール・フ
ォーム・モジュール:SFMと称す)を、前記搬入した配管
(6)、トレイ、ダクト支持金具或いは小型機器(5)
等を内在するように吊りこみ、前記構造体(8)側面の
鉄板型枠(2)外面を所定位置に位置決めして固定し、
前記構造体(8)側面の鉄板型枠(2)を前記壁の少
なくとも一面のコンクリート打設用型枠として用いると
ともに、前記構造体の上面の鉄板型枠を天井のコンクリ
ート打設用型枠として用いることにより、壁と天井との
コンクリート(11)を同時に打設し、コンクリート
(11)打設後も、前記構造体の鉄板型枠内面を天井面及
び壁面として用いることを特徴とする原子力発電所建屋
の建築工法により達成される。
The above-mentioned purpose is in the construction method of the nuclear power plant building,
After placing concrete on the building floor, a support member (3) for supporting the column reinforcement and wall reinforcement (4) is set at a predetermined position on the floor, and the pre-assembled column reinforcement and wall reinforcement (4) are set at the predetermined position. Suspend and fix to the support member (3),
The support member (3) or the column and wall reinforcements (4)
Before and after the construction of, the pipes (6), trays, duct support fittings or small equipment (5), etc. are carried in to predetermined positions on the floor other than the positions where the pillars and walls are constructed, and then the steel structural material. A structure (8) (hereinafter referred to as a steel foam module: SFM) that is made in advance by closing the upper surface of the frame (1) made of (Referred to as) is the pipe (6), tray, duct support fitting or small device (5) that has been carried in.
Etc. are hung inside, and the iron plate formwork (2) on the side surface of the structure (8) is positioned and fixed at a predetermined position,
The iron plate formwork (2) on the side surface of the structure (8) is used as a concrete pouring formwork for at least one surface of the wall, and the iron plate formwork on the upper surface of the structure is used as a concrete pouring formwork for the ceiling. By using the concrete (11) for the wall and the ceiling at the same time, the inner surface of the steel plate form of the structure is used as the ceiling surface and the wall surface even after the concrete (11) is cast. Achieved by the construction method of the building.

〔作用〕[Action]

上記構成によれば、コンクリート型枠として前記SFMを
兼用することにより、型枠支保工が不要なので、コンク
リート打設或いは養生期間中でもSFM内で別途作業を行
うことができ、さらに、SFMを構成する鉄板型枠及び架
構が建屋内壁面として露出される結果、配管類、機器類
の支持金具位置が自在に設定でき、かつ、小型機器の据
付工事がコンクリート打設と平行して可能になり、ま
た、天井、壁の2段工程を省略したコンクリート打設を
行うことなどにより、原子力発電所建設工事の工期短縮
及び省力化を図ることができる。
According to the above configuration, by also using the SFM as a concrete formwork, there is no need for formwork support work, so it is possible to perform separate work within the SFM even during concrete pouring or curing periods, and further configure the SFM. As a result of the steel plate formwork and frame being exposed as the wall surface inside the building, it is possible to freely set the positions of supporting metal fittings for pipes and equipment, and it is possible to install small equipment in parallel with concrete pouring. In addition, it is possible to shorten the construction period of the nuclear power plant construction work and save labor by, for example, placing concrete without the two-step process of the ceiling and the wall.

〔実施例〕〔Example〕

以下、本発明の実施例を図面をもとに説明する。第1図
は、本実施例によるSFMの全体図を示し、第2図は、そ
の長手方向の垂直断面図、第3図は、平面断面、第4図
は、短辺方向の垂直断面を示す。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 shows an overall view of the SFM according to this embodiment, FIG. 2 shows a vertical sectional view in the longitudinal direction thereof, FIG. 3 shows a plane sectional view, and FIG. 4 shows a vertical sectional view in the short side direction. .

本実施例のSFMの構造を以下に説明する。架構1はSFMの
骨格をなす鋼製構造材であり、柱、壁、梁及び天井の各
部位ヘコンクリートを打設するとき、その荷重を支持す
る強度を有している。鉄板型枠2は柱、壁、梁及び天井
の各部位へコンクリートが打設されるときのコンクリー
ト型枠としての役割を果たす部材であり、架構1の外側
に架構を覆う形で設定されている。
The structure of the SFM of this embodiment will be described below. The frame 1 is a steel structural material that forms the framework of SFM, and has the strength to support the load of concrete when it is placed on columns, walls, beams and ceilings. The iron plate formwork 2 is a member that functions as a concrete formwork when concrete is placed on each part of columns, walls, beams and ceilings, and is set outside the frame 1 so as to cover the frame. .

つぎに、SFMを用いた躯体建築の施工順序を第5図をも
とに説明する。
Next, the construction sequence of the frame building using SFM will be described with reference to FIG.

1)床の上には、あらかじめ、鉄筋支持用のサポート材
3を設定しておく。
1) On the floor, the support material 3 for supporting the reinforcing bar is set in advance.

2)プレファブ化した柱筋や壁筋4をサポート材3上に
吊り込み、固定する。
2) Suspend prefabricated column and wall reinforcements 4 on the support material 3 and fix them.

3)次に機器5、配管6、間仕切り壁用の乾式パネル7
を揚重機を用いて搬入する。
3) Next, equipment 5, piping 6, dry panel 7 for partition walls
Are loaded using a lifting machine.

4)SFM8を揚重機を用いて吊り込み、ターンバックル9
や型枠締付用金具10等で固定する。
4) Suspend SFM8 using a lifting machine and turnbuckle 9
And the frame tightening metal fittings 10 etc.

5)コンクリート11を打設する。5) Concrete 11 is poured.

つぎに、SFMを用いた原子力発電所建屋の配置例を第6
図、第7図に示す。第6図は、原子炉建屋の断面図を示
し、第7図は、原子炉建屋の平面図を示す。図中の黒枠
で囲った区画にSFMを適用する。
Next, the sixth example of the layout of the nuclear power plant building using SFM
Shown in FIG. FIG. 6 shows a cross-sectional view of the reactor building, and FIG. 7 shows a plan view of the reactor building. SFM is applied to the section surrounded by the black frame in the figure.

以上のように、本実施例によるSFMを用いた原子力発電
所建屋の躯体建築工法により、従来工法の欠点が以下の
ように解消され、建築躯体建築の早期化を促し、建設工
程の短縮が図られる。
As described above, by the skeleton construction method of the nuclear power plant building using the SFM according to the present embodiment, the drawbacks of the conventional construction method are solved as follows, accelerating the construction of the skeleton structure and shortening the construction process. To be

1)SFMを用いることによって、従来工程のように、コ
ンクリート打設作業を壁、天井の2回に分けて行なう必
要がなくなり、作業工程が緩和される。
1) By using SFM, unlike the conventional process, it is not necessary to perform the concrete pouring work in two steps, that is, the wall and the ceiling, and the work process is eased.

2)SFMの骨格鋼材である架構が、コンクリート打設時
のコンクリート自重を保持するので、従来工法のよう
に、支保工組立、解体作業が不必要となる。
2) Since the frame structure, which is a skeletal steel material of SFM, holds the weight of concrete when pouring concrete, it is unnecessary to perform support and assembly and dismantling work as in the conventional method.

3)コンクリート打設及び養生時の支保工が不要なた
め、機械側作業の前倒し着工が可能となる。
3) Since it is not necessary to place concrete and support work during curing, it is possible to start work ahead of the machine side.

4)コンクリート躯体の壁、天井を覆うSFMの鉄板型枠
を利用して、建屋内に据付ける配管、トレイ及びダクト
の支持金具位置を自在に設定することが可能となり、従
来工法のように埋込金具を用いる必要がなくなる。これ
により、従来、配筋作業の途中に折り込まれていた埋込
金具の設定作業が削減され、配筋工程が緩和される。
4) By using the SFM steel plate formwork that covers the walls of the concrete frame and the ceiling, it is possible to freely set the positions of the support fittings for the pipes, trays, and ducts to be installed in the building. There is no need to use metal fittings. As a result, the work of setting the embedded metal fitting, which has been conventionally folded during the rebar work, is reduced, and the rebar process is alleviated.

5)建屋内壁面に鉄板型枠が露出しているため、建屋内
作業時の躯体保護がなされ、又、内壁の塗装作業も従来
のコンクリート面塗装に比べ、壁面研磨が不必要になる
などで作業が簡易化される。
5) Since the iron plate formwork is exposed on the wall surface inside the building, the building is protected during the work inside the building, and the painting work on the inside wall does not require wall polishing as compared with conventional concrete surface painting. The work is simplified.

6)建築躯体のプレファブ化を推進することにより、現
場作業量が削減され、現地作業環境の改善、作業工数の
平準化が図られる。又、プレファブ製品の工場生産部分
の機械化により、生産性の向上、製品の信頼性向上が図
られる。
6) By promoting prefabrication of the building frame, the amount of work on site can be reduced, the local work environment can be improved, and the work man-hours can be leveled. Further, the mechanization of the prefabricated product factory production part improves productivity and product reliability.

本実施例の応用例として以下の工法がある。The following construction method is an application example of this embodiment.

工場又は現地プレファブヤードでSFMを組立てる際、モ
ジュールの内側の鉄板型枠に、配管、トレイ、ダクト、
支持金具及び小型機器類を同時施工で据付けておき、そ
のまま大型揚重機で現場に吊り込む。本工法は、建築躯
体と機械類の複合モジュールであるが、建設現場の現地
作業の合理化、効率化の面で最も進んだ工法である。
When assembling the SFM in the factory or on-site prefab yard, the steel plate formwork inside the module has pipes, trays, ducts,
The support metal fittings and small equipment are installed at the same time, and they are hung on the site with a large lifting machine. This method, which is a composite module of building frame and machinery, is the most advanced method in terms of streamlining and improving the efficiency of on-site work at construction sites.

第8図は本実施例の応用例である配管、機器類を取り込
んだSFMの断面図を示す。ダクト12、トレイ13及び配管1
4は、SFM組立時、架構1や鉄板型枠2に同時施工で据付
けられている。尚モジュール本体の施工手順は第5図に
準ずる。
FIG. 8 shows a cross-sectional view of an SFM incorporating a pipe and equipment, which is an application example of this embodiment. Duct 12, tray 13 and piping 1
4 is installed on the frame 1 and the steel plate form 2 at the same time when the SFM is assembled. The procedure for constructing the module body conforms to Fig. 5.

〔発明の効果〕〔The invention's effect〕

本発明による原子力発電所建屋の建築工法によれば、SF
Mをコンクリート型枠として用いるので、従来別種工事
であった型枠工事を省略することができるため、型枠組
立て、支保工作業、及びコンクリート養生期間経過後の
支保工及び型枠解体作業などが不要となる。しかも、原
子力発電所建屋の大型機器類を事前搬入したのちSFMを
搬入するので、SFM内における原子力発電所機器側工事
と建築側躯体工事とを並行して行うことができる。
According to the construction method of the nuclear power plant building according to the present invention, the SF
Since M is used as a concrete formwork, it is possible to omit formwork work that was conventionally a different type of work, so formwork assembly, support work, and support work and concrete dismantling work after the concrete curing period has passed. It becomes unnecessary. Moreover, since the SFM is loaded after the large-scale equipment of the nuclear power plant building is loaded in advance, the nuclear power plant equipment side construction and the building side skeleton construction can be performed in parallel within the SFM.

また、SFMの鉄板型枠及び架構を、原子力発電所特有の
配管、トレイ、ダクト及び機器類、或いは、給排水、電
気設備等の支持母体として、従来のコンクリート埋込金
物に代えて利用することができるので、従来の配筋作業
の錯綜化を招いていた埋込金物の設定作業が省略され、
加えて、壁面が鉄板化されるため、コンクリート壁面に
比べて建物内装工事も簡略化される。
It is also possible to use the SFM steel plate formwork and frame instead of the conventional concrete embedded metal as a support base for pipes, trays, ducts and equipment specific to nuclear power plants, water supply and drainage, electrical equipment, etc. Since it is possible, the setting work of the embedded hardware, which has caused the complexity of the conventional bar arrangement work, is omitted,
In addition, since the walls are made of iron plates, the interior work of the building is simplified compared to concrete walls.

このように本発明によれば、建築側工事の省力化及び早
期化を図ることができ、また従来、建築工事の後工程で
あった機器側作業が、建築工事と並行して進められるた
め、機器側工事の前倒し着工が可能となり、さらに各種
付帯工事も促進可能となるなど、原子力発電所建設全体
の工程短縮化及び省力化を図ることができる。
Thus, according to the present invention, it is possible to save labor and speed up the construction work, and the equipment-side work, which was a post-process of the construction work in the past, is carried out in parallel with the construction work. Since it is possible to start the work on the equipment side ahead of time and also to promote various incidental works, it is possible to shorten the overall process of the nuclear power plant construction and save labor.

【図面の簡単な説明】[Brief description of drawings]

第1図はSFM全体図、第2図はその長手方向の垂直断面
図、第3図は水平断面図、第4図は短辺方向の垂直断面
図、第5図(A)〜(D)はSFMを用いた躯体建築の施
工手順を示す図、第6図はSFMを用いた原子炉建屋の断
面図、第7図はその平面図、第8図は複合SFMの断面
図、第9図は躯体建築の従来施工手順を示す図である。 1…架構、1…鉄板型枠、3…サポート材、4…プレフ
ァブ鉄筋、5…機器、6…配管、7…乾式パネル、8…
スチール・フォーム・モジュール(SFM)、9…ターン
バックル、10…型枠締付金具、11…コンクリート。
FIG. 1 is an overall view of the SFM, FIG. 2 is a vertical sectional view in the longitudinal direction thereof, FIG. 3 is a horizontal sectional view, FIG. 4 is a vertical sectional view in the short side direction, and FIGS. 5 (A) to (D). Is a diagram showing the construction procedure of the building structure using SFM, Fig. 6 is a sectional view of the reactor building using SFM, Fig. 7 is its plan view, Fig. 8 is a sectional view of composite SFM, and Fig. 9 [Fig. 6] is a diagram showing a conventional construction procedure of a building structure. DESCRIPTION OF SYMBOLS 1 ... Frame, 1 ... Iron plate formwork, 3 ... Support material, 4 ... Prefabricated rebar, 5 ... Equipment, 6 ... Piping, 7 ... Dry panel, 8 ...
Steel foam module (SFM), 9 ... Turnbuckle, 10 ... Form clamps, 11 ... Concrete.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 岩島 澄雄 茨城県日立市幸町3丁目1番1号 株式会 社日立製作所日立工場内 (72)発明者 石井 末治 茨城県日立市幸町3丁目1番1号 株式会 社日立製作所日立工場内 (72)発明者 鈴木 忠男 茨城県日立市幸町3丁目1番1号 株式会 社日立製作所日立工場内 (56)参考文献 特開 昭51−31019(JP,A) ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Sumio Iwashima 3-1-1 Sachimachi, Hitachi City, Ibaraki Hitachi Ltd. Hitachi factory (72) Inventor Suiji Ishii 3-chome, Hitachi City, Ibaraki Prefecture No. 1 Inside Hitachi Works, Hitachi Works (72) Inventor Tadao Suzuki 3 1-1, Saiwaicho, Hitachi City, Ibaraki Hitachi Works, Hitachi Works (56) References JP-A-51-31019 ( JP, A)

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】原子力発電所建屋の建築工法において、 建屋床のコンクリート打設後に、床上の所定位置に
柱筋及び壁筋を支持するサポート部材を設定し、 予め組み立てた前記柱筋及び壁筋を前記所定位置に
吊り込んで前記サポート部材に固定し、 前記サポート部材又は前記柱筋及び壁筋の工事と前
後して、前記柱及び壁の施工位置以外の前記床上の所定
位置に配管、トレイ、ダクト支持金具或いは小型機器等
を搬入し、 次に、鋼製構造材からなる架構の上面及び少なくと
も対向する両側面の外側が鉄板型枠により閉ざされ、且
つ下面を開放して予め製作した構造体を、前記搬入した
配管、トレイ、ダクト支持金具或いは小型機器等を内在
するように吊りこみ、前記構造体側面の鉄板型枠外面を
所定位置に位置決めして固定し、 前記構造体側面の鉄板型枠を前記壁の少なくとも一
面のコンクリート打設用型枠として用いるとともに、前
記構造体の上面の鉄板型枠を天井のコンクリート打設用
型枠として用いることにより、壁と天井とのコンクリー
トを同時に打設し、 コンクリート打設後も、前記構造体の鉄板型枠内面
を天井面及び壁面として用いることを特徴とする原子力
発電所建屋の建築工法。
1. A method of constructing a nuclear power plant building, wherein after the concrete is cast on the building floor, a support member for supporting the column reinforcement and the wall reinforcement is set at a predetermined position on the floor, and the column reinforcement and the wall reinforcement are preassembled. Fixed to the support member by suspending at the predetermined position, before and after the construction of the support member or the column reinforcement and the wall reinforcement, piping at a predetermined position on the floor other than the construction position of the column and the wall, the tray , A duct support metal fitting or small equipment, etc. are carried in, and then the upper surface of the frame made of steel structural material and at least the outer sides of the opposite side surfaces are closed by the iron plate formwork, and the lower surface is opened, and the structure is manufactured in advance. The body is hung so that the pipes, trays, duct support fittings, small equipment, etc. that have been carried in are contained therein, and the outer surface of the iron plate formwork on the side surface of the structure is positioned and fixed at a predetermined position. While using the iron plate formwork of the surface as a concrete pouring formwork of at least one surface of the wall, by using the iron plate formwork of the upper surface of the structure as a concrete pouring formwork of the ceiling, between the wall and the ceiling. A construction method for a nuclear power plant building, wherein concrete is poured at the same time, and the inner surface of the steel plate formwork of the structure is used as a ceiling surface and a wall surface even after the concrete is poured.
【請求項2】前記原子力発電所用機器の支持金具位置を
前記鉄板型枠に自在に設定する特許請求の範囲第1項記
載の原子力発電所建屋の建築工法。
2. A construction method for a nuclear power plant building according to claim 1, wherein the position of the support metal fittings of the equipment for the nuclear power plant is freely set on the iron plate form.
【請求項3】前記建屋内に設備する配管、トレイ、ダク
ト、支持金具又は小型機器類の据付工事を、前記コンク
リート打設工事と平行して行う特許請求の範囲第1項記
載の原子力発電所建屋の建築工法。
3. The nuclear power plant according to claim 1, wherein installation work of pipes, trays, ducts, support fittings or small equipments installed in the building is performed in parallel with the concrete placing work. Building construction method.
【請求項4】前記構造体であるスチール・フォーム・モ
ジュールの製作時に、該構造体に前記建屋内に設備する
配管、トレイ、ダクト、支持金具又は小型機器類を予め
取り付けておく特許請求の範囲第1項記載の原子力発電
所建屋の建築工法。
4. A pipe, a tray, a duct, a support metal fitting, or small equipment installed in the building is attached to the structure in advance when the steel foam module which is the structure is manufactured. The construction method for the nuclear power plant building described in paragraph 1.
JP61178261A 1986-07-29 1986-07-29 Nuclear power plant building construction method Expired - Fee Related JPH0699959B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61178261A JPH0699959B2 (en) 1986-07-29 1986-07-29 Nuclear power plant building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61178261A JPH0699959B2 (en) 1986-07-29 1986-07-29 Nuclear power plant building construction method

Publications (2)

Publication Number Publication Date
JPS6335931A JPS6335931A (en) 1988-02-16
JPH0699959B2 true JPH0699959B2 (en) 1994-12-12

Family

ID=16045398

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61178261A Expired - Fee Related JPH0699959B2 (en) 1986-07-29 1986-07-29 Nuclear power plant building construction method

Country Status (1)

Country Link
JP (1) JPH0699959B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011226067A (en) * 2010-04-15 2011-11-10 Hitachi Plant Technologies Ltd Method of constructing building, and room module

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007232420A (en) * 2006-02-28 2007-09-13 Hitachi Ltd Nuclear reactor containment
JP4938440B2 (en) * 2006-12-28 2012-05-23 株式会社共和電業 Steering force meter
JP5237008B2 (en) * 2007-07-31 2013-07-17 株式会社日立製作所 Module structure
JP5358516B2 (en) * 2010-06-07 2013-12-04 日立Geニュークリア・エナジー株式会社 Construction method of reactor containment vessel

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5131019A (en) * 1974-09-09 1976-03-16 Juken Setsukei Kk KATAWAKUOMOCHIINAITETSUKINKONKURIITOARUIHATETSUKOTSUTETSUKINKONKURIITOKHIKUBUTSUSEKOHO

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011226067A (en) * 2010-04-15 2011-11-10 Hitachi Plant Technologies Ltd Method of constructing building, and room module

Also Published As

Publication number Publication date
JPS6335931A (en) 1988-02-16

Similar Documents

Publication Publication Date Title
CN108005410B (en) Assembled steel-concrete combined structure residential system and construction method thereof
CN107989228B (en) Prefabricated steel reinforced concrete shear wall structure and preparation and installation methods thereof
US20220098851A1 (en) Prefabricated building system and methods
CN207739437U (en) A kind of prefabricated steel reinforced concrete shear wall structure
JP4316161B2 (en) Power plant construction method
CN104234436A (en) Modular building method of nuclear power plant stainless steel cladding surface
KR19980080404A (en) Method of construction of plant buildings and modular structures used in the construction thereof
JPH0699959B2 (en) Nuclear power plant building construction method
JPS6137692Y2 (en)
CN208184021U (en) A kind of construction wall
JP3105044B2 (en) How to build a unit building
CN218990467U (en) Connection node that secondary structure post was pour simultaneously with major structure
JPH0953277A (en) Construction method for atomic power station
JP3559673B2 (en) Plant building and construction method of the building
JPS63308B2 (en)
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPS6025576B2 (en) Building construction method
JP3207276B2 (en) How to build a unit building
JP2004061443A (en) Building of nuclear power plant and method for constructing it
JPS6326215B2 (en)
JPH0791876B2 (en) Radiation shielding slab and its construction method
CN115613707A (en) Assembled building wall, beam, vertical horizontal bearing member's of board combination node
JP2000220207A (en) Reinforced concrete building
JPS62260930A (en) Yield strength panel type building structure
JPS6326211B2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees