JPS6025575B2 - Building construction method - Google Patents

Building construction method

Info

Publication number
JPS6025575B2
JPS6025575B2 JP52028608A JP2860877A JPS6025575B2 JP S6025575 B2 JPS6025575 B2 JP S6025575B2 JP 52028608 A JP52028608 A JP 52028608A JP 2860877 A JP2860877 A JP 2860877A JP S6025575 B2 JPS6025575 B2 JP S6025575B2
Authority
JP
Japan
Prior art keywords
floor
construction method
floors
building
side wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP52028608A
Other languages
Japanese (ja)
Other versions
JPS53114211A (en
Inventor
保夫 森田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Tokyo Shibaura Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Shibaura Electric Co Ltd filed Critical Tokyo Shibaura Electric Co Ltd
Priority to JP52028608A priority Critical patent/JPS6025575B2/en
Publication of JPS53114211A publication Critical patent/JPS53114211A/en
Publication of JPS6025575B2 publication Critical patent/JPS6025575B2/en
Expired legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔発明の技術分納野〕 本発明は多層階コンクIJート建屋の建屋建設方法に関
する。
DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a building construction method for a multi-story concrete IJ building.

〔発明の技術的背景とその問題点) 従来の建屋建設方法について、原子炉建屋を例にとり、
添付図面を参照しながら説明する。
[Technical background of the invention and its problems] Regarding the conventional building construction method, taking a nuclear reactor building as an example,
This will be explained with reference to the attached drawings.

第1図は原子炉建屋の全体を示す断面図であって、原子
炉圧力容器10を囲んで原子炉格納容器11が設けられ
、原子炉格納容器11の外側にはコンクリート製の遮蔽
壁12と、これに連なる多数のコンクリート製の床13
と壁laがあり、空間を仕切って部屋を形成している。
このような原子炉建屋の建設は、第1図に符号ロで区画
した分を拡大して第2図に示されるように、コンクリー
ト打設した最下層部の床14の上に壁laを立上げて、
これに天井すなわち上層階の床13を架設し、更に壁l
aを立上げて更に上層階の床13を架設していた。
FIG. 1 is a sectional view showing the entire reactor building, in which a reactor containment vessel 11 is provided surrounding a reactor pressure vessel 10, and a concrete shielding wall 12 is provided on the outside of the reactor containment vessel 11. , many concrete floors 13 connected to this
There are walls and walls that divide the space and form rooms.
In the construction of such a reactor building, as shown in Figure 2, which is an enlarged view of the section marked by ``Ro'' in Figure 1, a wall ``la'' is erected on top of the floor 14 of the lowest floor, which has been poured with concrete. Raise,
The ceiling, that is, the floor 13 of the upper floor is built on this, and the wall l
A was raised and floor 13 of the upper floor was constructed.

すなわち第2図は、2階部の天井を建設中の状況を表わ
し、壁laがほぼ天井の梁の下部まで完成すると、支保
工lbを2階の床13の上面より立設して型枠ICを支
承させ、型枠ICの上に鉄筋lfを裾付け、必要に応じ
て天井から吊下げる機器の係止部材ld、あるし、は埋
込配管le等を配置した後、コンクリート1gを打設し
て2階の天井を仕上げていた。なおコンクリート1gの
2〜3日間の養生期間を経過した後、壁鉄筋l iの組
立て、足場lhの設置、および型枠liの積上げを行な
い、更に上方に側壁laを立上げてし、た。従来の工法
は上述のようであったが、このような工法では、打設し
たコンクリート1gの養生期間が終り、支保工lbおよ
び型枠lcの搬出、徹タ去後でなければ、床上裾付機器
や室内の配管、トイレ、ダクト等の工事に着手できない
と、コンクリート1gの打設後でなければ上層階の側壁
工事が進行しないこと、天井部に係合する配管、トイレ
、ダクト等の工事のために、支保工lbの撤去後に、再
び工事用足場を組む必要があること等、工期遅延の誘因
が内在していた。
In other words, Figure 2 shows the situation in which the ceiling of the second floor is being constructed, and when the wall la has been completed almost to the bottom of the ceiling beam, the support lb is erected from the top of the floor 13 of the second floor and the formwork is installed. After supporting the IC, attaching reinforcing bars lf to the top of the formwork IC, and arranging locking members ld for equipment suspended from the ceiling as necessary, or embedded piping le, etc., pour 1 g of concrete. The ceiling of the second floor was being finished. After 1 g of concrete had been cured for 2 to 3 days, wall reinforcing bars were assembled, scaffolding was installed, and formwork was stacked up, and side walls were erected upwards. The conventional construction method was as described above, but in such a construction method, the hem of the floor cannot be finished unless the curing period for 1 gram of poured concrete has finished, the shoring lb and formwork lc have been carried out, and the concrete has been removed. If work on equipment, indoor piping, toilets, ducts, etc. cannot begin, work on the side walls of the upper floors will not proceed until after 1 gram of concrete has been poured, and work on piping, toilets, ducts, etc. that engages with the ceiling. Therefore, there was an inherent cause for delays in the construction period, such as the need to erect construction scaffolding again after the removal of the shoring lb.

更に足場を使用した工事は、上下における同時作業によ
る安全上の制約を生じ、かつ床上の通行、運搬にも支障
が多い等、幾多の問題点を包蔵していた。〔発明の目的
〕 本発明は多層階コンクリート建屋の各階の建設1にあた
り、当該階の側壁工事終了後、すみやかに天井部の仕切
りを終え、当該階室空間における安全作業を可能とし、
建屋およびこの建屋を含むプラント等の建設工期の短縮
を図ることができる建屋建設方法を提供することを目的
とする。
Furthermore, construction work using scaffolding has many problems, such as safety restrictions due to simultaneous work on the upper and lower floors, and many obstacles to traffic and transportation on the floor. [Purpose of the Invention] The present invention is concerned with the construction of each floor of a multi-story concrete building, and after completion of the side wall work on the floor, the ceiling partitions can be completed promptly to enable safe work in the floor space.
The object of the present invention is to provide a building construction method that can shorten the construction period of a building and a plant including the building.

〔発明の概要〕[Summary of the invention]

即ち本発明においては下層階より順次上層階へ蓮上げる
建屋建設方法において、隣接上層階に敷設されるべき床
配筋と対崎する位鷹に継鉄筋を横向に突設させた下層階
の側壁を下層階に隣接する上層階に構築予定の床部のレ
ベルを超えて立設し、側壁の継鉄筋のレベルより低位檀
に支承面を有して内設された支持部材に桁部材を構架し
、この桁部材にあらかじめ形成された枠部材を搭載し、
この枠部材の上部に、突設させた継鉄筋と接続させて上
層階の床配筋を敷設し、次いで上層階の床部コンクリー
トを打設し、上記工程を反復して順次上層階へ蓮上げる
建屋建設方法を提供し、その下方に連接する側壁の工事
完成に先行して天井部、即ち隣接上層階床部構築用のブ
ロック化された枠部材を製作しておき、側壁工事の終了
後ただちに枠部材を搭載して上下階の仕切りを可能とし
、枠部材の支保工を削減乃至省略して上層階床部の構築
を可能とし、且つ上層階床部に打設されたコンクIJ−
トの養生を持たずに下層階室空間における機器据付等の
作業を可能とし、上記目的を達成している。
That is, in the present invention, in a building construction method in which the lower floors are raised sequentially from the lower floors to the upper floors, the side walls of the lower floors have reinforcing bars protruding horizontally at the ridges facing the floor reinforcements to be laid on the adjacent upper floors. will be erected on the upper floor adjacent to the lower floor beyond the level of the floor to be constructed, and the girder members will be constructed on support members installed internally with a bearing surface at a level lower than the level of the side wall reinforcing bars. Then, a pre-formed frame member is mounted on this girder member,
The floor reinforcement for the upper floors is laid on top of this frame member by connecting it with the protruding reinforcing bars, then the floor concrete for the upper floors is poured, and the above process is repeated to successively move the lotuses to the upper floors. This method provides a building construction method in which blocks of frame members for constructing the ceiling section, that is, the adjacent upper floor section, are manufactured prior to the completion of the construction of the side wall connected to the lower part, and after the completion of the side wall construction. It is possible to immediately install frame members to partition the upper and lower floors, reduce or omit the need for supporting the frame members, and construct the upper floors.
This achieves the above objective by making it possible to install equipment in the lower floor space without having to provide additional protection.

〔発明の実施例〕[Embodiments of the invention]

以下第3図乃至第7図を参照しながら本発明の一実施例
を説明する。
An embodiment of the present invention will be described below with reference to FIGS. 3 to 7.

第3図はブロック化した天井枠部材3iの構成を表わし
、所要寸法の波形鋼板2aには、上層階の床に据付ける
機器のアンカーボルト等の支持用埋込部材2eが各所に
溶接されている。
FIG. 3 shows the structure of a block ceiling frame member 3i, in which embedded members 2e for supporting, such as anchor bolts, for equipment to be installed on the floor of the upper floor are welded at various places to a corrugated steel plate 2a of the required dimensions. There is.

また波形鋼板2aの上面には、ドレン配管2bが固定さ
れている。更に下面には電気用トレイ2c、空調用ダク
ト2dが取付けられ、これら全体が、建設中の建屋以外
の例えば作業場、工場等であらかじめ組立てられている
。次に第4図乃至第7図によって、本発明の建屋建設方
法を工程順に示す。
Further, a drain pipe 2b is fixed to the upper surface of the corrugated steel plate 2a. Further, an electrical tray 2c and an air conditioning duct 2d are attached to the lower surface, and these are all assembled in advance in a workshop, factory, etc. other than the building under construction. Next, the building construction method of the present invention will be shown in order of steps with reference to FIGS. 4 to 7.

先ず第4図において、既に完成した床13より、壁配筋
3nを粗上げ、型枠(図示省略)を用いてコンクリート
を注入し、側壁3aを蓮上げる。
First, in FIG. 4, the wall reinforcement 3n is roughly raised from the already completed floor 13, concrete is poured using a formwork (not shown), and the side wall 3a is raised.

このとき側壁3aは、これから建設される上層階の床の
レベルを超えて、例えば1〜2m上方まで、側壁3bと
して蓮上げておく。同時に側壁3aの内側には、上層階
の床配筋に接続を予定される継鉄筋3cを、相当する位
置にコンクリートより露出させて設けておく。次いで第
5図に示すように、継鉄筋3cより低位層の側壁3aの
内側に、支持金物3dを設ける。
At this time, the side wall 3a is raised as the side wall 3b, for example, 1 to 2 meters above the level of the floor of the upper floor to be constructed. At the same time, inside the side wall 3a, a yoke reinforcing bar 3c, which is scheduled to be connected to the floor reinforcement on the upper floor, is provided at a corresponding position exposed from the concrete. Next, as shown in FIG. 5, a supporting hardware 3d is provided inside the side wall 3a at a lower level than the yoke reinforcing bar 3c.

更に側壁3bには、上層階における側壁3bの延長部を
建設するための足場型枠3fを支持する支持金物3eを
取付ける。完成している床13上には、同時に機器3g
の搬入・裾付を行なう。続いて第6図に示すように、支
持金物3dの間に支持桁3hを架けわたし、支持桁3h
の上に、前述した天井枠部材3iを、例えばクレーン等
を用いて順次積載する。積載後、隣接する天井枠部村3
i間の電気用トイレ2c、空調用ダクト2d、およびド
レン配管2bの接続を行ない、接地線3iを布設する。
なお支持桁3hには、予めスタツドポルトが溶接され、
天井枠部村3iを貫通させている。次いで天井枠部材3
iの上に、継鉄筋3cと接続させて床配筋3kを裾付け
、上層階床に配遣される機器固定用のアンカポルト31
を取付ける。同時に機器3gへの配管3pの取付け、お
よび側壁3bの立上げ作業が行なわれる。最後に第7図
に示すように、天井枠部材3iの上にコンクリート3m
を打設し、上層階の床13を完成させる。コンクリート
3mの養生期間が経過したならば、配管3pと接続する
配管3q、コンジット3r、電気トレイ2cに収容され
るケーブル3sの布設等、天井下すなわち上層階の床1
3の下面に関連する作業を実施する。このとき上層階の
側壁3bは、継鉄筋3cを露出させて、更に上層階に建
設されるべき床13のレベルを超えて蓮上げられている
。上記の工程を繰返しながら、順次上層階の建設を行な
う。
Furthermore, a supporting hardware 3e is attached to the side wall 3b to support a scaffold form 3f for constructing an extension of the side wall 3b on the upper floor. At the same time, 3g of equipment is placed on the completed floor 13.
Carry in and hem. Next, as shown in Fig. 6, the support girder 3h is strung between the support metal fittings 3d,
The above-mentioned ceiling frame members 3i are sequentially loaded onto the ceiling frame members 3i using, for example, a crane. After loading, the adjacent ceiling frame village 3
Connect the electric toilet 2c, air conditioning duct 2d, and drain pipe 2b between the terminals i, and install the grounding wire 3i.
In addition, a stud port is welded to the support girder 3h in advance.
It penetrates through the ceiling frame section 3i. Next, ceiling frame member 3
Anchor ports 31 for fixing equipment placed on upper floors are attached to floor reinforcement 3k by connecting them to yoke reinforcing bars 3c on top of i.
Install. At the same time, the installation of the piping 3p to the device 3g and the erection of the side wall 3b are performed. Finally, as shown in Figure 7, 3 m of concrete is placed on top of the ceiling frame member 3i.
concrete and complete the floor 13 of the upper floor. After the curing period of 3 m of concrete has passed, the installation of the pipe 3q connecting to the pipe 3p, the conduit 3r, the cable 3s accommodated in the electrical tray 2c, etc. is carried out under the ceiling, that is, on the floor 1 of the upper floor.
Perform work related to the bottom surface of 3. At this time, the side wall 3b of the upper floor is raised above the level of the floor 13 to be constructed on the upper floor, exposing the reinforcing bar 3c. The upper floors will be constructed one by one by repeating the above process.

この実施例によれば、設備の整った作業性のよい工場等
において、天井枠部材3iを製作することができるので
、精度が向上し、完成後の品質を高めることができると
同時に、各種工程を重複して施工できるので、建設期間
が削減され、例えば約5ケ月間の工期短縮が可能であっ
た。
According to this embodiment, the ceiling frame member 3i can be manufactured in a well-equipped factory with good workability, which improves accuracy and improves the quality after completion. Since the construction can be carried out in duplicate, the construction period can be reduced by, for example, about five months.

その他支持桁3hが、機核取付用の埋込金物として利用
できるので、埋込金物設置のためのコンクリート面の再
ハッリ作業がなくなること、および天井コンクリート面
に直接溶接熱が作用しないため、コンクリートの品質確
保、塗装の補修省略等の効果が期待できる。又天井下部
取付機材の工事用足場を削減、省略することができるの
で、上下作業による作業者の安全性の改善が計れるとと
もに、床面上での資材等の運搬ならびに人員通行上の自
由度が増加する。なお、天井枠部材3iは、波形鋼板2
aを使用する例について説明したが、平形板を採用して
もよいし、また木製やコンクリート製のものであっても
よい。
In addition, since the support girder 3h can be used as an embedded metal fitting for installing the machine core, there is no need to re-harsh the concrete surface for installing the embedded metal fittings, and since welding heat does not act directly on the ceiling concrete surface, the concrete It can be expected to have effects such as ensuring quality and eliminating the need for painting repairs. In addition, it is possible to reduce or eliminate the need for construction scaffolding for equipment installed below the ceiling, which improves the safety of workers during vertical work, as well as increasing the freedom of transportation of materials and personnel on the floor. To increase. Note that the ceiling frame member 3i is made of corrugated steel plate 2.
Although the example in which a is used has been described, a flat plate may be used, or it may be made of wood or concrete.

またドレン配管2b、電気用トレイ2c、および空調用
ダクト2dを取付けたものについて説明したが、その他
の機材をも含む当該床13における必要に応じて、所要
のもののみを設けたものであってよいことは勿論である
。更に支持金物3dを、側壁3aに取付ける例について
述べたが、支持桁3hの支承は、側壁3aに沿って床1
3より立設した支柱に代えるか、あるいは両者を併用し
てもよい。
In addition, although a case has been described in which a drain pipe 2b, an electric tray 2c, and an air conditioning duct 2d are installed, only the necessary items are installed according to the needs of the floor 13 including other equipment. Of course it's a good thing. Furthermore, although an example has been described in which the support hardware 3d is attached to the side wall 3a, the support of the support girder 3h is attached to the floor 1 along the side wall 3a.
3 may be replaced with an upright support, or both may be used in combination.

また本建設方法を、原子炉建屋の建設に例をとって説明
したが、その他同様な構成を持つ建屋の建設に適用する
ことも勿論可能である。
Further, although the present construction method has been explained by taking the construction of a nuclear reactor building as an example, it is of course possible to apply it to the construction of other buildings having a similar configuration.

〔発明の効果〕〔Effect of the invention〕

以上詳述したように、本発明の建屋建設方法によれば、
構造上の精度を増し、安全性の向上が計れると同時に、
従釆直列に施工されていた工程を並列化することができ
るので、建屋建設工期の大幅な短縮が可能となる。
As detailed above, according to the building construction method of the present invention,
At the same time, it increases structural precision and improves safety.
Since the construction processes that were previously performed in series can be parallelized, the building construction period can be significantly shortened.

図面の筒単な説明 第1図は原子炉建屋の概略構造を表わす断面図、第2図
は従釆の建設方法を説明するために第1図の一部を拡大
して示した断面図、第3図は本発明に適用される天井枠
部材を示す斜視図、第4図乃至第7図はそれぞれ本発明
の建屋建設方法を順次表わす断面図である。
Brief description of the drawings Figure 1 is a sectional view showing the schematic structure of the reactor building, Figure 2 is an enlarged sectional view of a part of Figure 1 to explain the construction method of the substructure; FIG. 3 is a perspective view showing a ceiling frame member applied to the present invention, and FIGS. 4 to 7 are sectional views sequentially showing the building construction method of the present invention.

3a……側壁、3b……側壁、3c……継鉄筋、3d・
・・・・・支持金物、3h・・・・・・支持桁、3i・
・・・・・天井枠部材、3k・・・・・・床配筋、3m
・・・・・・コンクリート、13・・・・・・床部。
3a... side wall, 3b... side wall, 3c... yoke reinforcing bar, 3d.
...Support hardware, 3h...Support girder, 3i.
...Ceiling frame members, 3k...Floor reinforcement, 3m
...Concrete, 13...Floor.

第4図 第1図 第2図 図 の 職 第5図 第6図 第7図Figure 4 Figure 1 Figure 2 figure of job Figure 5 Figure 6 Figure 7

Claims (1)

【特許請求の範囲】 1 下層階より順次上層階へ建上げる建屋建設方法にお
いて、隣接上層階に敷設されるべき床配筋と対峙する位
置に継鉄筋を横向に突設させた下層階の側壁を上記下層
階に隣接する上記上層階に構築予定の床部のレベルを超
えて立設し、上記側壁の上記継鉄筋のレベルより低位置
に支承面を有して内設された支持部材に桁部材を横架し
、この桁部材にあらかじめ形成された枠部材を搭載し、
この枠部材の上部に上部突設させた継鉄筋と接続させて
上記上層階の上記床配筋を敷設し、次いで上記上層階の
床部コンクリートを打設し、上記工程を反復して順次上
層階へ建上げることを特徴とする建屋建設方法。 2 床部上下に配設される機器およびアンカボルトを添
着してあらかじめ形成された枠部材を上記桁部材に搭載
する特許請求の範囲第1項記載の建屋建設方法。
[Scope of Claims] 1. In a building construction method in which the building is constructed from the lower floors to the upper floors, the side wall of the lower floor has yoke reinforcing bars protruding laterally at a position facing the floor reinforcement to be laid on the adjacent upper floor. shall be erected on the upper floor adjacent to the lower floor above the level of the floor section to be constructed, and shall be installed internally with a supporting surface at a position lower than the level of the yoke reinforcing bars of the side wall. A girder member is suspended horizontally, a pre-formed frame member is mounted on this girder member,
The above-mentioned floor reinforcement of the above-mentioned upper floor is laid by connecting it to the yoke reinforcing bars protruding from the upper part of this frame member, and then the floor concrete of the above-mentioned upper floor is poured, and the above-mentioned process is repeated until the upper floors are successively laid. A building construction method characterized by building up into floors. 2. The building construction method according to claim 1, wherein a pre-formed frame member with attached equipment and anchor bolts arranged above and below the floor is mounted on the girder member.
JP52028608A 1977-03-17 1977-03-17 Building construction method Expired JPS6025575B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP52028608A JPS6025575B2 (en) 1977-03-17 1977-03-17 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP52028608A JPS6025575B2 (en) 1977-03-17 1977-03-17 Building construction method

Publications (2)

Publication Number Publication Date
JPS53114211A JPS53114211A (en) 1978-10-05
JPS6025575B2 true JPS6025575B2 (en) 1985-06-19

Family

ID=12253277

Family Applications (1)

Application Number Title Priority Date Filing Date
JP52028608A Expired JPS6025575B2 (en) 1977-03-17 1977-03-17 Building construction method

Country Status (1)

Country Link
JP (1) JPS6025575B2 (en)

Also Published As

Publication number Publication date
JPS53114211A (en) 1978-10-05

Similar Documents

Publication Publication Date Title
US4065905A (en) Prefabricated building sections or room units and methods for the manufacture of such sections or units
EP1971727B1 (en) Construction of buildings
KR20210038684A (en) Precast building construction system
JP4441406B2 (en) Vertical alignment and leveling of modular building units
EP0065793B1 (en) Reinforcement structure for reinforced-concrete buildings
JPS6025575B2 (en) Building construction method
JPS6025576B2 (en) Building construction method
CA2639339A1 (en) Method of constructing a multi-storey building using prefabricated modular panels
JPH0699959B2 (en) Nuclear power plant building construction method
JP3559673B2 (en) Plant building and construction method of the building
JP2928002B2 (en) Column formwork structure
JP3187618B2 (en) How to assemble beam reinforcement
JP7151961B2 (en) Piping installation structure and piping pit construction method
JPS6326215B2 (en)
JPH0270848A (en) Floor slab
JP2972957B2 (en) Composite construction method such as RC construction
JP3281972B2 (en) Reinforcing unit and method of constructing reinforced concrete building using the same
RU2130106C1 (en) Methods for embodying structural system of fully prefabricated civic building
JPH0642184A (en) Construction of skeleton using half precast floor board
RU138854U1 (en) OPERATION NODE OF THE HORIZONTAL ELEMENT OF CONSTRUCTION STRUCTURES FOR PRECIOUS REINFORCED CONCRETE ASK-FREE CONSOLE COLUMNS (2 OPTIONS)
JPH08270255A (en) Seismic isolation structuring method of existing building
JP2023016370A (en) Construction method of structure
JP3207276B2 (en) How to build a unit building
JP2531045B2 (en) Construction method for reinforced concrete structure
JP3190059B2 (en) How to build a building