JPH03262833A - Construction of underground floor - Google Patents

Construction of underground floor

Info

Publication number
JPH03262833A
JPH03262833A JP2061240A JP6124090A JPH03262833A JP H03262833 A JPH03262833 A JP H03262833A JP 2061240 A JP2061240 A JP 2061240A JP 6124090 A JP6124090 A JP 6124090A JP H03262833 A JPH03262833 A JP H03262833A
Authority
JP
Japan
Prior art keywords
floor
slabs
wall
floor slabs
landslide prevention
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2061240A
Other languages
Japanese (ja)
Inventor
Masataka Kodera
小寺 正孝
Arata Furuta
古田 新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2061240A priority Critical patent/JPH03262833A/en
Publication of JPH03262833A publication Critical patent/JPH03262833A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Residential Or Office Buildings (AREA)

Abstract

PURPOSE:To shorten a term of work by lifting-down PC floor slabs, divided at the middle part, to a given floor to be force-added in a landslide prevention direction with a jack interposed between adjoining floor slabs, to be pressed- attached, and building an outer wall on the landslide prevention wall side of the floor slabs. CONSTITUTION:PC floor slab plates 4, previously divided at the middle part and irregular parts are provided on the outer side end part on a landslide prevention wall 1 side, are manufactured by the required number for an underground floor. Excavation is made to first underground floor, and the PC floor slab plates 4 are supported with hanging members 6 to be lifted down to the excavated ground 3' of the first underground floor. Then a jack 10 is interposed between the faced end parts of the adjoining floor slab plates 4 to be actuated, and the floor slabs 4 are horizontally force-added to the landslide prevention wall 1 side to be laterally pushed to press-attach the outer side ends of the floor slabs 4 for also using as struts. After that wall vertical reinforcements are inserted in recessed parts provided on the landslide prevention wall 1 side end parts of the floor slabs 4, and the floor slabs and outer walls 13 are integratedly built. This permits cost saving.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は逆打ち工法による地下階の構築工法に係るもの
である。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for constructing a basement floor using a reverse construction method.

(従来の技術) 地下階の構築に際しては、−船釣には山留壁を施工して
杭を打設し、山留壁内の掘削と切梁、腹起しの架設とを
繰返して床付まで掘削し、最下階より躯体部の配筋、コ
ンクリート打設を行なう。
(Conventional technology) When constructing a basement floor, - For boat fishing, a retaining wall is constructed, piles are driven, and the floor is constructed by repeatedly excavating the retaining wall, constructing struts, and raising the floor. Excavation will be carried out to the bottom floor, and reinforcement and concrete will be placed for the frame from the bottom floor.

また従来の逆打工法においては、山留壁を構築し、構真
柱を建込み柱脚コンクリートを打設し、地下1階の1次
掘削を行ない、1階床梁を施工し、その後は掘削と切梁
、腹起しの架設を繰り返して床付まで掘削し最下階より
躯体部の配筋、コンクリート打設を行っていた。
In addition, in the conventional reverse pouring method, the retaining walls are constructed, the structural pillars are erected, the column bases are poured, the first basement floor is excavated, the first floor floor beams are constructed, and then the first floor beams are constructed. After repeated excavation, cut beams, and erection, the excavation was carried out all the way to the floor, and reinforcement for the frame was laid out and concrete was poured from the lowest floor.

(発明が解決しようとする課題) 前記従来の工法においてはいずれも、切梁、腹起しとい
う最終的には不要のものが存在している。
(Problems to be Solved by the Invention) In all of the above-mentioned conventional construction methods, there are ultimately unnecessary components such as struts and erecting.

本発明は前記従来技術の有する問題点に鑑みて提案され
たもので、その目的とする処は、仮設の切梁、腹起しを
不要ならしめ、かつ、各階の床スラブを早期に設置する
事により作業床、作業通路として使用しうるようにする
事により工期の短縮と省力化安全の確保が図られる地下
階構築工法を提供する点にある。
The present invention has been proposed in view of the problems of the prior art, and its purpose is to eliminate the need for temporary struts and erecting, and to quickly install floor slabs on each floor. The object of the present invention is to provide a construction method for constructing an underground floor that can shorten the construction period, save labor, and ensure safety by allowing the floor to be used as a work floor and a work passage.

(課題を解決するための手段) 前記の目的を達成するため、本発明に係る地下階構築工
法によれば、中間部で分割され、且つ山留壁側端部に凹
凸部を有するPC床スラブを所定階にリフトダウンし、
相隣る同床スラブ間にジヤツキを介装し、同ジヤツキに
よって前記各床スラブを山留方向に水平に協力して前記
山留間に圧着せしめたのち、同山留壁に接する側の前記
各床スラブの凹凸面に外壁を構築するものである。
(Means for Solving the Problems) In order to achieve the above object, according to the basement floor construction method according to the present invention, a PC floor slab that is divided in the middle part and has an uneven part at the end on the retaining wall side. lift down to the designated floor,
A jack is interposed between adjacent slabs of the same floor, and the jack is used to press each of the floor slabs horizontally in the direction of the retaining wall between the retainers. An outer wall is constructed on the uneven surface of each floor slab.

(作用) 本発明によれば前記したように、予め中間部において分
割され、且つ山留壁側に位置する端部において凹凸部が
設けられたPC床スラブを製作しておき、根伐りの進行
に伴って同床スラブを所定の地下階にリフトダウンした
のち、相隣る前記両底スラブ間にジヤツキを介装し、同
ジヤツキを作動することによって前記各床スラブを夫々
同床スラブに対向する山留壁方向に水平に協力して横押
しして、前記各床スラブを山留壁に圧着せしめることに
よって、同各床スラブに切梁を兼用せしめ、同各床スラ
ブにおける山留に接する端部に設けられた凹凸面に外壁
を構築することによって、同外壁と前記各床スラブとを
一体化せしめるものであ(実施例) 以下本発明を図示の実施例について説明する。
(Function) According to the present invention, as described above, a PC floor slab that is divided in the middle part and provided with an uneven part at the end located on the retaining wall side is manufactured in advance, and the progress of root cutting is After the same floor slabs are lifted down to a predetermined basement floor, jacks are interposed between the two adjacent bottom slabs, and by operating the jacks, each of the floor slabs is opposed to the same floor slab. By pressing horizontally in the direction of the retaining wall to press each floor slab to the retaining wall, each floor slab can also serve as a strut, and contact the retaining wall in each floor slab. By constructing an outer wall on the uneven surface provided at the end, the outer wall and each of the floor slabs are integrated (Embodiment) The present invention will be described below with reference to the illustrated embodiment.

第1図に示すように山留壁(1)及び構真柱(2)を構
築し、1次掘削を行ない、掘削地盤(3)上におい′C
地下階の必要階数分のPC床スラブ(4)を製作する。
As shown in Figure 1, retaining walls (1) and structural pillars (2) are constructed, primary excavation is carried out, and odor is detected on the excavated ground (3).
Fabricate PC floor slabs (4) for the required number of basement floors.

同各床スラブ(4)は中間部で分割され、山留壁側外側
端部に凹凸部(4a) (4a iが設けられるととも
に、縦方向にルーズホール(4b)が穿設され、上端が
梁(5)に繋止され、且つ前記ルーズホール(4b)に
貫挿された吊材(6)によって支持されている。
Each of the floor slabs (4) is divided in the middle, and an uneven part (4a) (4a i) is provided at the outer end on the side of the retaining wall, and a loose hole (4b) is bored in the vertical direction. It is anchored to the beam (5) and supported by a hanging member (6) inserted through the loose hole (4b).

図中(7)は柱、(8)は柱筋、(9)は床スラブであ
る。
In the figure, (7) is a column, (8) is a column reinforcement, and (9) is a floor slab.

次いで地下1階まで掘削を行ない、前記PC床スラブ(
4)を地下1階の掘削地盤(3′)までリフトダウンさ
せ、地下1階用の相隣るPC床スラブ(4)の対向端部
間にジヤツキ(10)を介装し、同ジヤツキ(10)を
作動して、同各床スラブ(句を山留壁(1)側に水平に
協力し′ζ横押しし、同各床スラブ(4)の外側端を前
記山留壁(1)に圧着させ、前記地下1階のPC床スラ
ブ(4)に切梁を兼用せしめる。(第2図及び第5図乃
至第7図参照) 次いで第3図に示すように、地下階と並行して地上階躯
体(11)を施工し、地下2階まで掘削を行ない、前記
PC床スラブ(4)を地下2階の所定レヘル(3’lま
でリフトダウンさせる。
Next, excavation was carried out to the first basement floor, and the PC floor slab (
4) is lifted down to the excavated ground (3') on the first basement floor, a jack (10) is inserted between the opposite ends of the adjacent PC floor slabs (4) for the first basement floor, and the jack (10) is 10) to push each floor slab horizontally towards the retaining wall (1), and push the outer edge of each floor slab (4) towards the retaining wall (1). The PC floor slab (4) on the first basement floor also serves as a cross beam.(See Figure 2 and Figures 5 to 7) Next, as shown in Figure 3, the PC floor slab (4) on the basement floor is crimped. The above-ground floor frame (11) is constructed, excavation is carried out to the second basement floor, and the PC floor slab (4) is lifted down to a predetermined level (3'l) of the second basement floor.

なお外壁(13)を構築する場合、前記床スラブ(4)
の山留側端部に設けた凹部(4a)に壁縦筋(14)を
挿通して、同床スラブ(4)と前記外壁(13)と一体
化する。(第8図及び第9図参照) 又地下1 BPC床スラブ(4)間にスラブ筋(15)
を配筋してコンクリート(16)を打設し、同打設コン
クリ−) (16)の硬化後、ジヤツキ(10)を除去
する。
In addition, when constructing the outer wall (13), the floor slab (4)
The wall vertical reinforcement (14) is inserted into the recess (4a) provided at the end of the floor slab (4) on the side of the crest to integrate the same floor slab (4) and the outer wall (13). (See Figures 8 and 9) Also, underground 1: Slab reinforcement (15) between BPC floor slabs (4)
Reinforcement is arranged and concrete (16) is poured, and after the poured concrete (16) hardens, the jack (10) is removed.

地下2階床においても地下1階床と同様にPC床スラブ
(4)間に介装したジヤツキ(10)を作動してPC床
スラブ(4)を山留壁(1)に圧着し′ζ切梁を兼用せ
しめる。
Similarly to the first basement floor, on the second basement floor, the jacks (10) interposed between the PC floor slabs (4) are operated to press the PC floor slabs (4) to the retaining walls (1). It can also be used as a strut.

次いで第4図に示すように地下3階まで掘削して、掘削
地盤(3′)上に基礎板(17)、基礎梁(1日)を施
工し、地下3階用PC床スラブ(4)を地下3階位置ま
で降下させて基礎上に蔵置する。
Next, as shown in Fig. 4, excavation was carried out to the third basement floor, and the foundation plate (17) and foundation beam (1 day) were constructed on the excavated ground (3'), and the PC floor slab for the third basement floor (4) was constructed. The building will be lowered to the third floor underground and stored on the foundation.

なお、上記実施例では基礎板を在来工法で施工する例を
示したが基礎板をPC化する事もあるし、地下3階床ス
ラブにジヤツキを介装して加圧する事もある、又壁を上
階から施工する場合を例示したが、スラブのみを全層構
築し下階から柱、壁で施工するケースもある。
In addition, although the above example shows an example in which the foundation plate is constructed using a conventional construction method, the foundation plate may be made of PC, or the third floor basement slab may be pressurized by inserting jacks. Although we have given an example of a case in which walls are constructed from the upper floor, there are also cases in which only slabs are constructed at all levels and columns and walls are constructed from the lower floor.

(発明の効果) 本発明によれば前記したように、中間部で分割され、且
つ山留壁側端部に凹凸部を有するPC床スラブを所定階
にリフトダウンし、相隣る前記床スラブ間にジヤツキを
介装し、同ジヤツキによって前記各床スラブを山留壁方
向に水平に協力して、前記山留壁間に圧着支持せしめる
ことによって、前記PC床スラブに切梁を兼用せしめる
ようにしたことによって、仮設の切梁、腹起しが不要に
なり、作業床通路が早期に得られるで大幅に省力化され
、工期が短縮され、工費が!!!i減されかつ安全性が
確保できる。
(Effects of the Invention) According to the present invention, as described above, a PC floor slab that is divided in the middle and has uneven parts at the end on the retaining wall side is lifted down to a predetermined floor, and the adjacent floor slabs are A jack is interposed in between, and the jack horizontally cooperates with each of the floor slabs in the direction of the retaining wall, so that the PC floor slabs are crimped and supported between the retaining walls, so that the PC floor slab can also serve as a strut. By doing so, there is no need for temporary struts or erecting, and work floor passages can be obtained quickly, resulting in significant labor savings, shortening the construction period, and reducing construction costs! ! ! i can be reduced and safety can be ensured.

また前記PC床スラブの山留壁側が凹凸面に形成され、
同面に外壁を構築することによって、同外壁と前記PC
床スラブとが一体化されるものごある。
Further, the retaining wall side of the PC floor slab is formed into an uneven surface,
By constructing an outer wall on the same plane, the outer wall and the PC
Some are integrated with the floor slab.

【図面の簡単な説明】[Brief explanation of drawings]

第1図乃至第4図は本発明に係る地下階構築工法の一実
施側の工程を示す縦断面図、第5図は本発明による施工
状況を示す横断平面図、第6図はPC床スラブが山留壁
に圧着された状態を示1横断平面図、第7図は第6図の
矢視X−X図、第8図はPC床スラブと外壁とを一体化
した状態を示す横断平面図、第9図は第8図の矢視Y−
Y図ごある。 (1)−・山留壁、 (3) (3’l (3’) (3”1−・・掘削地盤
、(4)−PC床スラブ   (4a)・・・凹部、(
4a’) ・・・凸部、     (4b)・・・ルー
ズホール、(6)・−吊材、      (10)−・
ジヤツキ。
Figures 1 to 4 are longitudinal sectional views showing one implementation process of the basement floor construction method according to the present invention, Figure 5 is a cross-sectional plan view showing the construction status according to the present invention, and Figure 6 is a PC floor slab. 1 is a cross-sectional plan view showing the state in which the PC floor slab and the outer wall are crimped to the retaining wall, FIG. 7 is a cross-sectional view taken along the arrow XX in FIG. 6, and FIG. Figure 9 shows the direction of arrow Y- in Figure 8.
There is a diagram Y. (1)--Retaining wall, (3) (3'l (3') (3''1--Excavation ground, (4)-PC floor slab (4a)...Concavity, (
4a')...Protrusion, (4b)...Loose hole, (6)--hanging material, (10)--
Jyatsuki.

Claims (1)

【特許請求の範囲】[Claims] 地下階の構築方法において、中間部で分割され、且つ山
留壁側端部に凹凸部を有するPC床スラブを所定階にリ
フトダウンし、相隣る同床スラブ間にジャッキを介装し
、同ジャッキによって前記各床スラブを山留方向に水平
に協力して前記山留間に圧着せしめたのち、同山留壁に
接する側の前記各法スラブの凹凸面に外壁を構築するこ
とを特徴とする地下階構築工法。
In the method of constructing a basement floor, a PC floor slab that is divided in the middle and has uneven parts at the end on the side of the retaining wall is lifted down to a predetermined floor, and a jack is interposed between adjacent slabs of the same floor, After each of the floor slabs is pressed horizontally in the direction of the retaining wall by the jack, an outer wall is constructed on the uneven surface of each of the floor slabs on the side that contacts the retaining wall. Underground floor construction method.
JP2061240A 1990-03-14 1990-03-14 Construction of underground floor Pending JPH03262833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2061240A JPH03262833A (en) 1990-03-14 1990-03-14 Construction of underground floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2061240A JPH03262833A (en) 1990-03-14 1990-03-14 Construction of underground floor

Publications (1)

Publication Number Publication Date
JPH03262833A true JPH03262833A (en) 1991-11-22

Family

ID=13165510

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2061240A Pending JPH03262833A (en) 1990-03-14 1990-03-14 Construction of underground floor

Country Status (1)

Country Link
JP (1) JPH03262833A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07324343A (en) * 1994-05-31 1995-12-12 Toda Constr Co Ltd Construction method for constructing underground skeleton
JP2002188163A (en) * 2000-12-18 2002-07-05 Shimizu Corp First-story floor preceding underground construction method
JP2007154503A (en) * 2005-12-05 2007-06-21 Takenaka Komuten Co Ltd Mechanical parking garage in building basement
CN101956395A (en) * 2010-10-29 2011-01-26 浙江宝业建设集团有限公司 Base board for reducing deformation at periphery of base pit and construction method thereof
CN104088296A (en) * 2014-06-24 2014-10-08 上海市城市建设设计研究总院 Soft soil area basement layer adding construction method
JP2016065433A (en) * 2014-09-26 2016-04-28 株式会社竹中工務店 Construction method for elevator pit
CN112177667A (en) * 2020-09-26 2021-01-05 深圳市隆金达实业有限公司 Underground protection wall for municipal works

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07324343A (en) * 1994-05-31 1995-12-12 Toda Constr Co Ltd Construction method for constructing underground skeleton
JP2002188163A (en) * 2000-12-18 2002-07-05 Shimizu Corp First-story floor preceding underground construction method
JP2007154503A (en) * 2005-12-05 2007-06-21 Takenaka Komuten Co Ltd Mechanical parking garage in building basement
CN101956395A (en) * 2010-10-29 2011-01-26 浙江宝业建设集团有限公司 Base board for reducing deformation at periphery of base pit and construction method thereof
CN104088296A (en) * 2014-06-24 2014-10-08 上海市城市建设设计研究总院 Soft soil area basement layer adding construction method
CN104088296B (en) * 2014-06-24 2016-02-10 上海市城市建设设计研究总院 Soft clay area basement adds a layer construction method
JP2016065433A (en) * 2014-09-26 2016-04-28 株式会社竹中工務店 Construction method for elevator pit
CN112177667A (en) * 2020-09-26 2021-01-05 深圳市隆金达实业有限公司 Underground protection wall for municipal works
CN112177667B (en) * 2020-09-26 2021-10-29 深圳市隆金达实业有限公司 Underground protection wall for municipal works

Similar Documents

Publication Publication Date Title
KR102301605B1 (en) A Method of Bottom-up Removal of Underground Structures
KR20130006420A (en) Method of constructing underground structure to be newly built
KR20190083466A (en) Retaining wall and construction method thereof
JP3724320B2 (en) Construction method for underground structures
JPH03262833A (en) Construction of underground floor
JP2741259B2 (en) Reverse construction method and multifunctional work floor using multifunctional work floor
CN212801564U (en) Foundation ditch steel sheet pile supporting construction
JPH10306457A (en) Foundation block
JPH04330168A (en) Construction method for building with basement equipped with steel pipe pile foundation
CN221167772U (en) Upper rectangular lower circular reinforced concrete bored pile
JPH07138972A (en) Construction method for underground skeleton
JP4267175B2 (en) Construction method of underground structure
RU2753301C1 (en) Method for foundation construction under conditions of year-round negative temperatures
JPH0657769A (en) Underground concrete structure and working method thereof
JPH101957A (en) Underground construction method for building
JPH03147926A (en) construction method for basement
JPH04289329A (en) Concrete base structure for building and formation of thereof
JPS6272822A (en) Construction work of underground structure
JPH0393925A (en) Simultaneous construction method of structure above or under ground
JPH0874278A (en) Construction method for large underground space
CN116607537A (en) Reverse construction method for support-changing position structure in foundation pit construction
CN115405019A (en) Concrete connection structure and installation method thereof
KR100189716B1 (en) Working method of underground structure for underground construction work
SU912837A1 (en) Pile foundation
JPS6367327A (en) Construction of stressed concrete foundation slab