JPH03107068A - Working floor device for construction application - Google Patents

Working floor device for construction application

Info

Publication number
JPH03107068A
JPH03107068A JP24543189A JP24543189A JPH03107068A JP H03107068 A JPH03107068 A JP H03107068A JP 24543189 A JP24543189 A JP 24543189A JP 24543189 A JP24543189 A JP 24543189A JP H03107068 A JPH03107068 A JP H03107068A
Authority
JP
Japan
Prior art keywords
floor
working floor
working
work
steel beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24543189A
Other languages
Japanese (ja)
Inventor
Taneomi Deguchi
出口 種臣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP24543189A priority Critical patent/JPH03107068A/en
Publication of JPH03107068A publication Critical patent/JPH03107068A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PURPOSE:To improve working efficiency and safety by coupling stretchably an upper and a lower working floors provided with various working equipment by a plurality of hydraulic jacks and placing a holding device on the working floor to have it sequentially elevated like a measuring worm. CONSTITUTION:An upper working floor 5 provided with a device for mounting steel beams, etc. and a lower working floor 3 provided with a device for placing concrete, etc. are coupled stretchably with a plurality of hydraulic jacks 6. A holding device 7 for fixing the working floors 3,5 to a steel beam 2 is mounted on each of the working floors 3,5. When attaching of the beam 2 on a first stage to a pillar 1 is completed, a hydraulic jack 6 is stretched to push up the upper working floor 5 and then the lower working floor 3 is pulled up to have them elevated sequentially. Thus, operation can be done efficiently and safely.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、中高層建築における施工作業を自動化する建
築施工用作業床装置に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a construction work floor device for automating construction work in medium to high-rise buildings.

〔従来の技術〕[Conventional technology]

中高層建築の工法は、大きく区分すると鉄骨建方、鉄筋
配筋、型枠組立、コンクリート打設、型枠解体の各作業
からなっている。そのうち柱や梁の鉄骨建方作業では、
部材搬送、仮接合、建て入れ直し、本接合の作業がある
。これらの作業では、先ず、クレーンを使って鉄骨を所
定の位置に搬送して仮締めボルトにより各部材間を仮接
合し、しかる後3軸方向の位置決め、歪み直しを行って
溶接やボルトにより鉄骨を最終的に固定している。
Construction methods for mid-to-high-rise buildings can be roughly divided into the following steps: steel frame erection, reinforcing reinforcement, formwork assembly, concrete pouring, and formwork dismantling. During the steel frame erection work for columns and beams,
There is work such as transporting parts, temporary joining, rebuilding, and final joining. In these operations, first, a crane is used to transport the steel frame to a predetermined position, and each member is temporarily joined using temporary tightening bolts.Then, positioning in three axes is performed, distortion correction is performed, and the steel frame is welded or bolted. has finally been fixed.

従来の鉄骨建方におけるこれらの作業は、鉄骨の運搬時
にクレーンを使う以外、接合時に若干の治具を使う程度
で、ほとんど人手による作業である。
These tasks in conventional steel frame construction are mostly manual work, with only the use of cranes to transport the steel frames and the use of a few jigs for joining.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

上述のように人手による作業が中心になっている従来の
鉄骨建方作業では、高度に熟練した鳶職人の高所作業が
不可欠となり、建設現場で行われている各種の作業の中
でも取り分゜け危険度が高く、危険作業の第1番目に取
り上げられる作業となっている。また、高度熟練工の不
足、高齢化等により施工時間の遅延が問題となっている
As mentioned above, in the conventional steel frame erection work, which mainly involves manual work, it is essential for highly skilled craftsmen to work at heights, and this is one of the most important tasks among the various types of work carried out at construction sites. The level of danger is high and it is considered the number one dangerous work. Additionally, delays in construction time are becoming a problem due to a shortage of highly skilled workers and an aging population.

また、コンクリート打設工事においては、デッキプレー
ト、鉄筋等の足場の悪さに加えて、配管段取り替え等の
重量物を扱う作業が要求されるため、転落、転倒、挟ま
れる事故が多発している。
Furthermore, in concrete pouring work, in addition to the poor footing of deck plates and reinforcing bars, it is also necessary to handle heavy objects such as changing piping setups, so accidents such as falls, falling, and getting caught frequently occur. .

本発明は、上記の問題点を解決するものであって、鉄骨
建方およびコンクリート打設作業において人手による高
所作業をな<シ、作業の安全性を高め、工期の短縮を図
ることができる建築施工用作業床装置を提供することを
目的とするものである。
The present invention solves the above-mentioned problems, and eliminates manual work at high places during steel frame erection and concrete pouring work, improves work safety, and shortens the construction period. The object of the present invention is to provide a working floor device for construction work.

〔課題を解決するための手段〕[Means to solve the problem]

そのために本発明の建築施工用作業床装置は、複数の油
圧ジャッキ6により連結され、上下に伸縮自在に構成さ
れる下部作業床3および上部作業床5と、下部作業床3
および上部作業床5に配設され鉄骨梁2を把持するため
の把持装置7と、上部作業床5上の四隅に移動自在に配
設される鉄骨梁搬送装置10とを有することを特徴とす
る。
To this end, the construction work floor device of the present invention comprises a lower work floor 3 and an upper work floor 5, which are connected by a plurality of hydraulic jacks 6 and configured to be vertically telescopic.
and a gripping device 7 disposed on the upper working floor 5 for grasping the steel beam 2, and a steel beam conveying device 10 movably disposed at the four corners of the upper working floor 5. .

なお、上記構成に付加した番号は、理解を容易にするた
めに図面と対比させるためのもので、これにより本発明
の構成が限定されるものではない。
Note that the numbers added to the above configurations are for comparison with the drawings to facilitate understanding, and the configurations of the present invention are not limited thereby.

〔作用〕[Effect]

本発明においては、例えば第1図に示すように、先ず、
ステップ■、■で上部作業床5上において鉄骨柱1間に
鉄骨梁2を組立てた後、油圧ジャッキ6を伸長させ上部
作業床5を上の階まで持ち上げ、鉄骨梁2を組立てる。
In the present invention, for example, as shown in FIG.
After assembling the steel beams 2 between the steel columns 1 on the upper working floor 5 in steps (2) and (2), the hydraulic jack 6 is extended to lift the upper working floor 5 to the upper floor, and the steel beams 2 are assembled.

次いでステップ■において、上部作業床5を把持装置7
により鉄骨梁2に固定すると共に、下部作業床3の把持
H置7を解放し、油圧ジャッキ8を縮めて下部作業床3
を上の階の鉄骨梁2の位置まで持ち上げ、下部作業床3
を把持装置7により固定する。以下、ステップ■〜■に
示すよウに、上記作業を繰り返しながら油圧ジャッキ6
により下部作業床3と上部作業床5を交互に上昇させ、
次々に上の階の鉄骨粱2を組立ててゆく。
Next, in step (2), the upper working floor 5 is held by the gripping device 7.
At the same time, the grip H 7 of the lower work floor 3 is released, and the hydraulic jack 8 is retracted to lower the lower work floor 3.
Lift it up to the position of the steel beam 2 on the upper floor, and lower it to the lower work floor 3.
is fixed by the gripping device 7. Below, as shown in steps
The lower working floor 3 and the upper working floor 5 are raised alternately by
The steel frame 2 on the upper floor is being assembled one after another.

〔実施例〕〔Example〕

以下、実施例を図面を参照しつつ説明する。 Examples will be described below with reference to the drawings.

第1図は本発明に係る建築施工用作業床装置の1実施例
を示す工程図、第2図は作業床装置群の平面図である。
FIG. 1 is a process diagram showing one embodiment of a working floor device for construction work according to the present invention, and FIG. 2 is a plan view of a group of working floor devices.

図中、1は鉄骨柱、2は鉄骨梁で実線は組付けられた鉄
骨梁、点線は組付けられる前の鉄骨梁を示している。3
は下部作業床、5は上部作業床、6は油圧ジャッキ、7
は把持装置を示す。
In the figure, 1 is a steel column, 2 is a steel beam, the solid line shows the assembled steel beam, and the dotted line shows the steel beam before being assembled. 3
is the lower working floor, 5 is the upper working floor, 6 is the hydraulic jack, 7
indicates a gripping device.

下部作業床3と上部作業床5は、複数の油圧ジャッキ6
により連結され、上下に伸縮自在に構成されている。第
2図に示すように、下部作業床3と上部作業床5には、
その四辺に鉄骨梁2を把持するための把持装置7が設け
られている。該把持装置7は、伸縮自在であり把持装置
7を伸長させ鉄骨梁2を把持することにより、下部作業
床3または上部作業床5をその位置に固定するものであ
る。第2図に示す作業床装置群は、隣接する作業床装置
3、5の把持装置7が互いに干渉しない位置に設けられ
ていて、これにより、作業床装置3、5がそれぞれ独立
して上方に移動でき、鉄骨梁2の組立を同時平行して進
めることができる。
The lower work floor 3 and the upper work floor 5 are equipped with a plurality of hydraulic jacks 6.
It is connected by , and is configured to be able to expand and contract up and down. As shown in FIG. 2, the lower working floor 3 and the upper working floor 5 are
A gripping device 7 for gripping the steel beam 2 is provided on its four sides. The gripping device 7 is extendable and retractable, and by extending the gripping device 7 and gripping the steel beam 2, the lower work floor 3 or the upper work floor 5 is fixed at that position. In the group of work floor devices shown in FIG. 2, the gripping devices 7 of the adjacent work floor devices 3 and 5 are provided in positions where they do not interfere with each other, so that the work floor devices 3 and 5 can be moved upward independently. It can be moved, and the assembly of the steel beams 2 can proceed in parallel at the same time.

次に、第1図により鉄骨梁2の組立について説明する。Next, assembly of the steel beam 2 will be explained with reference to FIG.

先ず、ステップ■、■で上部作業床5上において鉄骨柱
1間に鉄骨梁2を組立てた後、油圧ジャッキ6を伸長さ
せ上部作業床5を上の階まで持ち上げ、鉄骨梁2を組立
てる。次いでステップ■において、上部作業床5を把持
装置7により鉄骨梁2に固定すると共に、下部作業床3
の把持装置7を解放し、油圧ジャッキ6を縮めて下部作
業床3を上の階の鉄骨梁2の位置まで持ち上げ、下部作
業床3を把持装置7により固定する。以下、ステップ■
〜■に示すように、上記作業を繰り返しながら油圧ジャ
ッキeにより下部作業床3と上部作業床5を交互に上昇
させ、次々に上の階の鉄骨梁2を組立ててゆく。
First, in steps (2) and (2), the steel beam 2 is assembled between the steel columns 1 on the upper work floor 5, and then the hydraulic jack 6 is extended to lift the upper work floor 5 to the upper floor and the steel beam 2 is assembled. Next, in step (3), the upper working floor 5 is fixed to the steel beam 2 by the gripping device 7, and the lower working floor 3 is fixed to the steel beam 2 by the gripping device 7.
The gripping device 7 is released, the hydraulic jack 6 is retracted, the lower working floor 3 is lifted to the position of the steel beam 2 on the upper floor, and the lower working floor 3 is fixed by the gripping device 7. Below are the steps
As shown in ~■, while repeating the above operations, the lower working floor 3 and the upper working floor 5 are raised alternately by the hydraulic jack e, and the steel beams 2 of the upper floors are assembled one after another.

第3図は上記した鉄骨梁の組立を行うための鉄骨粱搬送
装置の斜視図である。
FIG. 3 is a perspective view of a steel frame conveying device for assembling the above-mentioned steel beams.

鉄骨梁搬送装置10は、上部作業床5の四隅に配設され
、図示しないモータにより回転するマスト11と、マス
ト11に固定される回転台l2と、回転台12上に設け
られ垂直面内で旋回する孤状の旋回ブームl3と、旋回
ブームl3の先端に取付けられる吊下用ブーム15、ワ
イヤー16とから構成される。なお、マスト11は、上
部作業床5上を移動できるようにして、鉄骨梁2が上部
作業床5のどこにあってもこれを吊り下げ可能にしてい
る。
The steel beam transport device 10 is arranged at the four corners of the upper working floor 5, and includes a mast 11 that is rotated by a motor (not shown), a rotating table l2 fixed to the mast 11, and a rotating table l2 that is installed on the rotating table 12 and rotates within a vertical plane. It is composed of an arc-shaped swinging boom l3, a hanging boom 15 attached to the tip of the swinging boom l3, and a wire 16. The mast 11 is movable on the upper working floor 5 so that the steel beam 2 can be suspended wherever it is on the upper working floor 5.

その作用について説明すると、先ず、 (a)図に示す
よウに、鉄骨梁2の両端にワイヤーl6を固定した後、
旋回ブーム13を垂直面内で旋回させることにより、 
(b)図に示すように、鉄骨梁2を吊り上げ、吊り上げ
た鉄骨梁2の吊り心をマスト11の回転中心に一致させ
る。次で、 (C)図に示すように、マストl1を回転
させ旋回ブーム13の孤状部で鉄骨梁2の両端をかわし
て、鉄骨梁2を鉄骨柱1側に移動させた後、 (d)図
に示すように、旋回ブーム13を垂直面内で旋回させる
ことにより、鉄骨梁2を吊り下げ所定の位置で上げ、鉄
骨梁2を鉄骨柱1間に固定するものである。
To explain its effect, first, as shown in Figures (a) and (c), after fixing the wire l6 to both ends of the steel beam 2,
By rotating the swing boom 13 in a vertical plane,
(b) As shown in the figure, the steel beam 2 is lifted and the hanging center of the lifted steel beam 2 is aligned with the rotation center of the mast 11. Next, as shown in Figure (C), the mast l1 is rotated and the arc of the swing boom 13 bypasses both ends of the steel beam 2, and the steel beam 2 is moved toward the steel column 1, (d ) As shown in the figure, by rotating the swinging boom 13 in a vertical plane, the steel beam 2 is suspended and raised at a predetermined position, and the steel beam 2 is fixed between the steel columns 1.

次に、第4図によりコンクリート打設装置25について
説明する。
Next, the concrete placing device 25 will be explained with reference to FIG.

下部作業床3の下側には、コンクリート配管ボックス2
6が設けられ、コンクリート供給配管27、コンクリー
ト分岐配管29が接続されている。
A concrete piping box 2 is placed under the lower work floor 3.
6 is provided, and a concrete supply pipe 27 and a concrete branch pipe 29 are connected thereto.

コンクリート分岐配管29の一方は、他の下部作業床の
コンクリート配管ボックスに接続され、コンクリート分
岐配管29の他方は、下部作業床3の下部にあるコンク
リート打設床30に設置された接続ボックス31に接続
されている。この接続ボックス31は回転自在に形成さ
れており、フレキシブルコンクリート記管32により、
コンクリートを打設可能にしている。
One end of the concrete branch pipe 29 is connected to a concrete pipe box on another lower work floor, and the other end of the concrete branch pipe 29 is connected to a connection box 31 installed on a concrete pouring floor 30 at the bottom of the lower work floor 3. It is connected. This connection box 31 is formed to be rotatable, and a flexible concrete pipe 32 allows
Allows concrete to be poured.

なお、本発明は、種々の変形が可能であり、上記実施例
に限定されるものでないことはいうまでもない。
It goes without saying that the present invention can be modified in various ways and is not limited to the above embodiments.

〔発明の効果〕〔Effect of the invention〕

以上の説明から明らかなように、本発明によれば、鉄骨
梁組立およびコンクリート打設作業が自動化されるので
、生産性の向上、工期の短縮を図ることができる。また
、高所作業がなくなるので、安全性の向上、災害の低減
を図ることができる。
As is clear from the above description, according to the present invention, steel beam assembly and concrete placement work are automated, so productivity can be improved and the construction period can be shortened. Furthermore, since there is no need to work at heights, safety can be improved and accidents can be reduced.

さらには、足場等の仮設物が不要となるので仮設費の低
減を図ると共に、その組立、解体日数がなくなり工期が
短縮できる。
Furthermore, since temporary structures such as scaffolding are not required, temporary construction costs can be reduced, and the construction period can be shortened by eliminating the number of days required for assembly and disassembly.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明に係る建築施工用作業床装置の1実施例
を示す工程図、第2図は作業床装置群の平面図、第3図
(a)ないし第3図(d)は鉄骨梁搬送装置の構成及び
作用を説明するための斜視図、第4図はコンクリート打
設装置の斜視図である。 2・・・鉄骨梁、3・・・下部作業床、5・・・上部作
業床、6・・・油圧ジャッキ、7・・・把持装置、10
・・・鉄骨梁搬送!L25・・・コンクリート打設装置
。 第2図
Fig. 1 is a process diagram showing one embodiment of the construction work floor device according to the present invention, Fig. 2 is a plan view of the work floor device group, and Figs. 3 (a) to 3 (d) are steel frame FIG. 4 is a perspective view for explaining the configuration and operation of the beam conveying device, and FIG. 4 is a perspective view of the concrete placing device. 2... Steel beam, 3... Lower working floor, 5... Upper working floor, 6... Hydraulic jack, 7... Gripping device, 10
...Steel beam transportation! L25... Concrete placement equipment. Figure 2

Claims (2)

【特許請求の範囲】[Claims] (1)複数の油圧ジャッキにより連結され、上下に伸縮
自在に構成される下部作業床および上部作業床と、これ
ら下部作業床および上部作業床に配設され鉄骨梁を把持
するための把持装置と、前記上部作業床の四隅に移動自
在に配設される鉄骨梁搬送装置とを有することを特徴と
する建築施工用作業床装置。
(1) A lower working floor and an upper working floor connected by a plurality of hydraulic jacks and configured to be vertically expandable and retractable, and a gripping device disposed on these lower working floor and upper working floor for gripping a steel beam. A working floor device for construction work, comprising: a steel beam conveying device movably disposed at the four corners of the upper working floor.
(2)前記下部作業床の下側には、コンクリート打設装
置が配設されることを特徴とする請求項1に記載の建築
施工用作業床装置。
(2) The construction work floor device according to claim 1, wherein a concrete placing device is disposed below the lower work floor.
JP24543189A 1989-09-21 1989-09-21 Working floor device for construction application Pending JPH03107068A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24543189A JPH03107068A (en) 1989-09-21 1989-09-21 Working floor device for construction application

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24543189A JPH03107068A (en) 1989-09-21 1989-09-21 Working floor device for construction application

Publications (1)

Publication Number Publication Date
JPH03107068A true JPH03107068A (en) 1991-05-07

Family

ID=17133559

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24543189A Pending JPH03107068A (en) 1989-09-21 1989-09-21 Working floor device for construction application

Country Status (1)

Country Link
JP (1) JPH03107068A (en)

Similar Documents

Publication Publication Date Title
EP0358433B1 (en) Construction apparatus and construction method
KR20070116222A (en) Clamp for a construction apparatus
US5371993A (en) Frame construction method
US20070096006A1 (en) Overhead beam assembly
JPH03107068A (en) Working floor device for construction application
JPH04161566A (en) Constructing apparatus for large space building
JP2913216B2 (en) Building construction method
JPH05133016A (en) Peripheral supporting self-rising type building engineering method
JP2021116153A (en) Supporting platform for tower crane and climbing method using the same
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
JPH07150767A (en) Beam truss erecting method in building having overhead traveling crane
CN216196958U (en) Cooling tower with double-cross inclined strut structure
JPH07112807A (en) Rack construction method and jig for automatic store
JP3100574B2 (en) Suspended scaffold and its erection method
JPH035565A (en) Moving scaffold robot
JPH05171817A (en) Temporary house for all-weather type execution
JPH0642184A (en) Construction of skeleton using half precast floor board
JPH1037527A (en) Method for constructing inner and outer cylinder of chimney simultaneously
JPH04237769A (en) Climb-up method and device for constructing building
JPH03202560A (en) Sticking method of board material onto wall surface of building
JP3001876U (en) Lifting mechanism for stage equipment
JPH03212566A (en) Assembling device for pole and beam integrated type unit
CN116876818A (en) Construction method of movable high and large formwork
JPH0791603A (en) Assembly parallel progressing method for large suspension type boiler
JPH06173458A (en) Building constructing method and weight lifting device