JPH02194213A - Sheet piling method - Google Patents

Sheet piling method

Info

Publication number
JPH02194213A
JPH02194213A JP1379389A JP1379389A JPH02194213A JP H02194213 A JPH02194213 A JP H02194213A JP 1379389 A JP1379389 A JP 1379389A JP 1379389 A JP1379389 A JP 1379389A JP H02194213 A JPH02194213 A JP H02194213A
Authority
JP
Japan
Prior art keywords
hole
casing
sheet piles
ground
sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1379389A
Other languages
Japanese (ja)
Inventor
Akifumi Takagi
高木 彰史
Noriyoshi Kitagawa
北川 紀吉
Moriyuki Shimai
森幸 嶋井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP1379389A priority Critical patent/JPH02194213A/en
Publication of JPH02194213A publication Critical patent/JPH02194213A/en
Pending legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To easily perform sheet piling by excluding rock or the like in a drilled hole in the ground, replacing it by sand, crushed stone, etc., hereafter, continuously driving a plurality of sheet piles in the hole, and injecting stiffener in the lower rock-bed part in the hole for hardening. CONSTITUTION:A casing is pressed in the ground 1, the earth in the casing is drilled, the drilled earth is excluded, and a hole 7 is formed. The penetrated part of the hole 7 is backfilled with crushed stones (a), the remaining part is backfilled with sand (b), and hereafter the casing is drawn out. Nextly, a plurality of steel sheet piles 8 are continuously driven in the hole 7, and a plurality of injection rods are inserted up to the lower end of the penetrated part, neighboring with the steel sheet piles 8. Bentonite milk is injected into the penetrated part through the injection rods for hardening.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は矢板打設工法に関するもので、特に岩盤等の
打設困難な地層に矢板を打設する矢板打設工法に関する
ものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a sheet pile driving method, and particularly relates to a sheet pile driving method for driving sheet piles into strata where driving is difficult, such as bedrock.

[従来技術とその課題] 岩盤や巨石を含む堆積層に矢板を打設するのは困難であ
る。このために地盤に孔を掘削して、砂等に置換して矢
板を打設することが考えられる。
[Prior art and its problems] It is difficult to drive sheet piles into sedimentary layers containing bedrock and megaliths. For this purpose, it is conceivable to excavate a hole in the ground, replace it with sand, etc., and then drive the sheet pile.

しかし置換したばかりの孔内に矢板を打設するのは地盤
が軟弱であって、矢板を強固に埋設することができない
。且つ止水性を保持する事が困難である。
However, the ground is too soft to drive sheet piles into holes that have just been replaced, making it impossible to firmly bury the sheet piles. Moreover, it is difficult to maintain water-stop properties.

この発明は以上のような問題点を解決するためになされ
たもので、打設困難な地層であっても矢板を容易に打設
することができるとともに、打設した矢板が強固に地盤
中に起立する矢板打設工法に提供することを目的とする
This invention was made in order to solve the above-mentioned problems.It is possible to easily drive sheet piles even in difficult strata, and the driven sheet piles are firmly embedded in the ground. The purpose is to provide for the upright sheet pile driving method.

〔課題を解決するための手段) この発明にかかる矢板打設工法は、地盤を置換して矢板
を打設するものである。地盤に連続して複数の孔を掘削
して孔の転石、岩等を排出し、砂や砕石等によって置換
したあと孔内に複数本の矢板を連続して打設し、孔の下
部には硬化材を注入して硬化させるものである。
[Means for Solving the Problems] The sheet pile driving method according to the present invention replaces the ground and drives the sheet piles. Multiple holes are continuously drilled into the ground, boulders, rocks, etc. are removed from the holes, and after replacing them with sand, crushed stones, etc., multiple sheet piles are successively driven into the holes. A hardening material is injected and hardened.

前記硬化材としてはベントナイトミルクを使用してもよ
い。
Bentonite milk may be used as the hardening agent.

〔作 用〕[For production]

砂や砕石等によって置換した孔であり、矢板の打設が容
易である。
The holes were replaced with sand, crushed stone, etc., making it easy to drive sheet piles.

硬化材で孔内下部を補強して矢板の傾斜を防ぐ。また不
透水層化させる。
Reinforce the lower part of the hole with hardened material to prevent the sheet pile from tilting. Also, it becomes an impermeable layer.

C実施例〕 以下、図に示す一実施例に基づきこの発明の詳細な説明
する。
Embodiment C] The present invention will be described in detail below based on an embodiment shown in the drawings.

<1>  ケーシング圧入機設置 図において1は地盤であって、岩ズリの埋立層、転石を
混在する旧海底層、および岩盤の三層から成っている。
<1> In the casing press-in machine installation diagram, 1 is the ground, which consists of three layers: a reclaimed layer of rock waste, an old seabed layer containing boulders, and bedrock.

従って転石及び岩盤が矢板打設の支障とならないよう矢
板の打設深さを完全に掘削する必要がある。
Therefore, it is necessary to excavate completely to the driving depth of the sheet pile so that boulders and bedrock do not interfere with sheet pile driving.

ケーシング圧入機の沈下防止のために、地盤1上に反力
基礎2を形成する。(第1図)反力基礎2上にケーシン
グ圧入機3を組立てる。(第2図)ケーシング圧入機3
はケーシング4を回転圧入可能である。
A reaction foundation 2 is formed on the ground 1 to prevent the casing press-in machine from sinking. (Fig. 1) Assemble the casing press-fitting machine 3 on the reaction foundation 2. (Fig. 2) Casing press-fitting machine 3
The casing 4 can be rotated and press-fitted.

く2〉 ケーシング圧入 鉄筋で出した杭芯に円形リング定規をセットし、これに
合わせてケーシング4をセットする。
2〉 Set a circular ring ruler on the pile core produced by the casing press-fit reinforcing bar, and set the casing 4 accordingly.

精度は±20mm以内とする。Accuracy shall be within ±20mm.

又、ケーシング4の鉛直性を十字方向より2台のトラン
シットで規準し、その傾斜量が1/200×ケ一シング
4長以上となるよう調整する。
Also, the verticality of the casing 4 is determined from the cross direction using two transits, and the inclination is adjusted to be 1/200 x the length of the casing 4 or more.

杭芯にセットしたケーシング4にハンマクラブガイドを
取付け、50を級クローラクレーン5に装着した、ハン
マクラブ6で掘削して、地上へ排出する。ケーシング4
は先端は常に掘削面より先行するよう回転圧入し壁面の
崩れのないよう注意する。又、回転、圧入操作は充分注
意し、掘削機に横スベリが生じないよう留意する。(第
3図) 掘削土は捨て掘りとして一定量を集積したのち、指定処
分地に運搬する。
A hammer club guide is attached to a casing 4 set on a pile core, and excavation is carried out using a hammer club 6 attached to a class crawler crane 5, and the excavation is carried out to the ground. Casing 4
Rotate and press-fit so that the tip always precedes the excavated surface, and be careful not to collapse the wall surface. Also, be very careful when rotating and press-fitting, and be careful not to cause the excavator to slip sideways. (Figure 3) A certain amount of excavated soil will be collected as a dump and then transported to a designated disposal site.

以上のようにして地盤1に孔7を形成する。The hole 7 is formed in the ground 1 as described above.

〈3〉 ケーシング継足し 海底面の傾斜により、施工杭長が場所毎に異なるので一
本で足りない場合は、1m、  2m。
〈3〉 Adding casing The length of the construction pile varies depending on the slope of the seabed, so if one pile is not enough, add 1m or 2m.

3m、6mのケーシング4を組合わせ使用する。A combination of 3m and 6m casings 4 is used.

ケーシング圧入機3に付帯した作業足場床付近までケー
シング4が下がった時点で50を級クローラクレーン5
によりケーシング4を建込みジヨイントし、ロックピン
で緊結する。ロックピンは電動インパクトレンチを用い
締めっける。
When the casing 4 has been lowered to the vicinity of the work scaffolding floor attached to the casing press-in machine 3, the 50-class crawler crane 5
The casing 4 is built into the joint and tightened with a lock pin. Tighten the lock pin using an electric impact wrench.

(第4図) く4〉 砕石・砂埋戻し 砕石の根入れ部については後工程でベントナイトミルク
を注入するが注入による浸透性を高める為、根入部2.
0mを20胴単粒砕石aで埋戻し、残部は砂すで埋戻し
する。(第7図)ケーシング4内への投入はホッパー設
備を使用し、油圧式バックホウ若しくはタイヤ式トラク
ターショベルにより行なう。(第5図)埋戻し材料は5
日分程度を場内にストックする。又、埋戻し時に発生す
るケーシング内の濁水は4吋水中ポンプを用い汚水処理
池に送水する。
(Figure 4) 4〉 Bentonite milk will be injected into the embedded part of the crushed stone/sand backfill crushed stone in the later process, but in order to increase the permeability of the injection, the embedded part 2.
0m is backfilled with 20 cylinders of single-grain crushed stone a, and the remaining area is backfilled with sand. (FIG. 7) Throwing into the casing 4 is carried out using a hopper facility and a hydraulic backhoe or a tire-type tractor shovel. (Figure 5) Backfilling material is 5
Stock up on the premises for about a day. Also, the turbid water inside the casing generated during backfilling is sent to the sewage treatment pond using a 4-inch submersible pump.

く5〉 ケーシング引抜 埋戻し完了後、ケーシング4を引抜き、機材を移動させ
る。埋戻個所が軟弱となる場合は鉄板等を用いて養生す
る。(第6図) く6〉 矢板打設 以上のようにして連続して地盤1に形成した孔7内に鋼
矢板8を連続して打設する。(第8図)鋼矢板打設後ボ
ーリングマシンにて鋼矢板8に隣り合わせて複数本の注
入ロッド9を根入れ部下端まで至らせる。
5> After casing removal and backfilling is completed, casing 4 is pulled out and the equipment is moved. If the backfilled area becomes soft, use iron plates, etc. to cure it. (Fig. 6) 6〉 Driving of sheet piles Steel sheet piles 8 are continuously driven into holes 7 that have been continuously formed in the ground 1 as described above. (FIG. 8) After driving the steel sheet piles, a plurality of injection rods 9 are placed adjacent to the steel sheet piles 8 using a boring machine to reach the lower end of the insertion.

く7〉 ベントナイト注入 前記注入ロッド9を通して孔7の根入部にベントナイト
ミルク10を注入する。ベントナイトミルク10の配合
は以下の通りである。
7> Injection of bentonite Bentonite milk 10 is injected into the root of the hole 7 through the injection rod 9. The composition of bentonite milk 10 is as follows.

水・・・・・・・・・・・・・・・・・・・・・・ 5
1セメント(高炉B種)・・・・・・・・1600 g
ベントナイト(筑前5号)・・・・ 375gW/C・
・・・・・・・・・・・・・・・・・・・ 312.5
%ベントナイトミルクIOが硬化することによって根入
部の補強と不透水層化がなされる。
Water・・・・・・・・・・・・・・・・・・・・・・・・ 5
1 cement (blast furnace type B) 1600 g
Bentonite (Chikuzen No. 5)... 375gW/C・
・・・・・・・・・・・・・・・・・・ 312.5
% bentonite milk IO hardens, reinforcing the root part and making it an impermeable layer.

〈8〉 ビット埋設 以上のようにして鋼矢板8による止水を行なったのち、
この鋼矢板8と平行して一定間隔離して鋼矢板11を打
設する。(第9図)鋼矢板8と11の上部間にタイプル
12を掛は渡して鋼矢板8の復起しを行なう。その扱網
矢板8に沿って地盤1を掘削し、掘削した個所に止水ピ
ット13を設置する。(第10図)掘削土砂を埋め戻し
て止水ピット13を埋設し、鋼矢板8,11を引抜く。
<8> After burying the bit and sealing off the water with the steel sheet pile 8 as described above,
A steel sheet pile 11 is placed in parallel with this steel sheet pile 8 and spaced apart from it for a certain period of time. (FIG. 9) A tie plate 12 is hung between the upper parts of the steel sheet piles 8 and 11, and the steel sheet pile 8 is raised back up. The ground 1 is excavated along the handling net sheet pile 8, and a water stop pit 13 is installed at the excavated location. (Fig. 10) The excavated soil is backfilled to bury the water stop pit 13, and the steel sheet piles 8 and 11 are pulled out.

〔発明の効果〕〔Effect of the invention〕

この発明は以上のような構成を有し、地盤に孔を掘削し
て転石、岩等を排出し、その後砂や砕石によって置換し
た後矢板を打設するため、岩盤や巨石を含む堆積層であ
っても容易に矢板を打設できる。
This invention has the above-mentioned configuration, and in order to excavate a hole in the ground, discharge boulders, rocks, etc., replace them with sand or crushed stones, and then drive the sheet piles, so it is possible to drill holes in the sedimentary layer containing bedrock and megaliths. Even if there is, sheet piles can be easily installed.

孔内の下部には硬化材を注入するため、根入部の補強と
なって矢板を強固に起立できるとともに、不透水化とし
て止水効果を損なうようなことがない。
Since hardening material is injected into the lower part of the hole, it strengthens the root part and allows the sheet pile to stand up firmly, and does not impermeate water and impair the water-stopping effect.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第6図はこの発明の一実施例を示す施工順序断
面図、第7図は孔の断面図、第8図は孔の平面図、第9
図〜第11図はピット埋設工の施工順序断面図である。 l・・地盤、2・・反力基礎、3・・ケーシング圧入機
、4・・ケーシング、5・・クローラクレーン、6・・
ハンマクラブ、7・・孔、8・・鋼矢板、9・・注入ロ
ッド、10・・ベントナイトミルク、11・1鋼矢板、
12・・タイプル、13・・止水ピット。 第 図 第3図 ’′−7 第4図 第2図
1 to 6 are construction sequence sectional views showing an embodiment of the present invention, FIG. 7 is a sectional view of the hole, FIG. 8 is a plan view of the hole, and FIG.
Figures 1 to 11 are sectional views showing the construction sequence of the pit burial work. l...Ground, 2...Reaction foundation, 3...Casing press-in machine, 4...Casing, 5...Crawler crane, 6...
Hammer club, 7...hole, 8...steel sheet pile, 9...injection rod, 10...bentonite milk, 11.1 steel sheet pile,
12... Taipur, 13... Water stop pit. Figure 3''-7 Figure 4 Figure 2

Claims (2)

【特許請求の範囲】[Claims] (1)地盤に連続して複数の孔を掘削して孔内の岩等を
排出し、砂や砕石等によって置換した後、孔内に複数本
の矢板を連続して打設し、孔内の下部岩盤部には硬化材
を注入して硬化させることを特徴とする矢板打設工法。
(1) After drilling multiple holes in the ground in succession, expelling rocks, etc. from the holes, and replacing them with sand, crushed stones, etc., multiple sheet piles are successively driven into the holes. A sheet pile driving method characterized by injecting hardening material into the lower bedrock and hardening it.
(2)硬化材としてベントナイトミルクを使用したこと
を特徴とする請求項(1)記載の矢板打設工法。
(2) The sheet pile driving method according to claim (1), characterized in that bentonite milk is used as the hardening material.
JP1379389A 1989-01-23 1989-01-23 Sheet piling method Pending JPH02194213A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1379389A JPH02194213A (en) 1989-01-23 1989-01-23 Sheet piling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1379389A JPH02194213A (en) 1989-01-23 1989-01-23 Sheet piling method

Publications (1)

Publication Number Publication Date
JPH02194213A true JPH02194213A (en) 1990-07-31

Family

ID=11843126

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1379389A Pending JPH02194213A (en) 1989-01-23 1989-01-23 Sheet piling method

Country Status (1)

Country Link
JP (1) JPH02194213A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030087288A (en) * 2002-05-08 2003-11-14 주식회사 세원지오신테크 Executon method of wall for intercepting contamination zone of using steel sheet pile
JP2008248537A (en) * 2007-03-29 2008-10-16 Ohbayashi Corp Method of driving rotatingly press-fitted pile, method of constructing foundation structure, and foundation structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS53123505A (en) * 1977-04-01 1978-10-28 Kajima Corp Method of placing sheet pile and similars
JPS5640218A (en) * 1979-09-10 1981-04-16 Toshiba Corp Ac-dc converting transformer
JPS62206119A (en) * 1986-03-05 1987-09-10 Okumura Constr Co Ltd Construction of continuous cut-off wall

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS53123505A (en) * 1977-04-01 1978-10-28 Kajima Corp Method of placing sheet pile and similars
JPS5640218A (en) * 1979-09-10 1981-04-16 Toshiba Corp Ac-dc converting transformer
JPS62206119A (en) * 1986-03-05 1987-09-10 Okumura Constr Co Ltd Construction of continuous cut-off wall

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030087288A (en) * 2002-05-08 2003-11-14 주식회사 세원지오신테크 Executon method of wall for intercepting contamination zone of using steel sheet pile
JP2008248537A (en) * 2007-03-29 2008-10-16 Ohbayashi Corp Method of driving rotatingly press-fitted pile, method of constructing foundation structure, and foundation structure

Similar Documents

Publication Publication Date Title
Bell Methods of treatment of unstable ground
CN104963346A (en) Support construction method for deep foundation pit in complex geological condition
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
CN111608174A (en) Karst area karst cave treatment method based on punched cast-in-place pile
JP2019015100A (en) Removing method of earth retaining wall
CN106049467A (en) Method for treating slurry leakage of bored pile through percussion drill under complex geology
JPH02194213A (en) Sheet piling method
CN101353894B (en) Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone
CN111042144B (en) Excavation method for foundation pit of underground beam under condition of continuous flow of riverway in cold region
JP2005146756A (en) Earth retaining impervious wall construction method and earth retaining impervious wall formed by it
JP2004003306A (en) Sludge treatment method in prefabricated pile construction, and ground reinforcing structure obtained by method
JP2874906B2 (en) Shaft construction method
Davidson et al. Seepage cutoff wall for mud mountain dam
Haswell Thames Cable Tunnel.
JP2004218378A (en) Removing method for existing pile
JPH0470422A (en) Open caisson method
Davidson¹ et al. Design and construction of a plastic concrete cutoff wall for the Island Copper Mine
GB2232701A (en) Mini-piled retaining wall and a method for its construction
CN107059839A (en) A kind of construction method of armored concrete waveform sheet pile underground structure
JPS63223215A (en) In-situ concrete piling work
JPH02311617A (en) Construction of foundation pile
JP5068678B2 (en) Earth retaining method and excavation member for earth retaining member standing construction used therefor
JP2007231641A (en) Collapse prevention construction method for dike
CN116240883A (en) Stirring pile construction method for penetrating existing underground reinforced concrete structure
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator