CN101353894B - Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone - Google Patents
Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone Download PDFInfo
- Publication number
- CN101353894B CN101353894B CN2008101190883A CN200810119088A CN101353894B CN 101353894 B CN101353894 B CN 101353894B CN 2008101190883 A CN2008101190883 A CN 2008101190883A CN 200810119088 A CN200810119088 A CN 200810119088A CN 101353894 B CN101353894 B CN 101353894B
- Authority
- CN
- China
- Prior art keywords
- slurry
- hole
- area
- construction
- drilling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 34
- 238000000034 method Methods 0.000 title claims abstract description 32
- 239000004575 stone Substances 0.000 title claims description 10
- 239000002002 slurry Substances 0.000 claims abstract description 58
- 238000005553 drilling Methods 0.000 claims abstract description 25
- 238000004080 punching Methods 0.000 claims abstract description 11
- 239000002893 slag Substances 0.000 claims description 14
- 230000005484 gravity Effects 0.000 claims description 9
- 238000007599 discharging Methods 0.000 claims description 3
- 230000002829 reductive effect Effects 0.000 abstract description 5
- 239000010410 layer Substances 0.000 description 19
- 239000004567 concrete Substances 0.000 description 8
- 239000002689 soil Substances 0.000 description 7
- 239000004576 sand Substances 0.000 description 6
- 239000004927 clay Substances 0.000 description 5
- 239000010802 sludge Substances 0.000 description 4
- 230000003068 static effect Effects 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 238000004140 cleaning Methods 0.000 description 3
- 239000011229 interlayer Substances 0.000 description 3
- 230000001681 protective effect Effects 0.000 description 3
- 238000005086 pumping Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 230000035515 penetration Effects 0.000 description 2
- 239000011513 prestressed concrete Substances 0.000 description 2
- 238000010992 reflux Methods 0.000 description 2
- 230000001502 supplementing effect Effects 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000001125 extrusion Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000036961 partial effect Effects 0.000 description 1
- 238000009527 percussion Methods 0.000 description 1
- 230000002441 reversible effect Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 238000009987 spinning Methods 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
The invention discloses a drilling method for the construction of a cast-in-place pile of a dank ultra-deep loose refilling rubble area, which comprises the following steps: step 1: a slope area of 4m to 6m is arranged in an area right ahead an arranged pile casing to serve as a slurry return flow line, and a slurry pool is dug outside the slope area; step 2: residue is drawn out once every 1 hour to 3 hours during a punching process; step 3: all the drawn-out slurry flows backwards into a drilling hole by utilizing the slope area; step 4: when punching work is carried out, the proportion of the slurry in the hole is increased, thereby being capable of increasing wall retaining capability and reducing hole collapse risk; and step 5: after drilling is carried out to a stable stratum of certain depth, the proportion of the slurry in the hole is gradually reduced; slurry containing the residue is discharged; and the slurry is discharged once every 2 hours to 3 hours. By adopting the method that the slurry flows backwards naturally, the method of the invention changes the traditional mode of slurry circulation, maintains the balance of the slurry, simplifies the construction process and lowers the construction risk.
Description
Technical Field
The invention relates to a construction hole forming method for a filling pile in a permeable ultra-deep loose backfilling two-stone area.
Background
The existing conventional cast-in-place pile hole forming technology is roughly divided into the following steps:
1. forming holes in a non-soil-squeezing mode: for example, drilling (digging) to form a hole by a dry operation method, drilling (digging) to form a hole by a slurry wall protection drill, and drilling (digging) to form a hole by a full casing follow-up wall protection method; wherein,
drilling (digging) a hole and drilling (digging) a hole by a mud retaining wall by a dry operation method are suitable for field construction with good engineering geological conditions, and hole collapse is basically not easy to generate;
the construction cost of drilling (digging) the hole by the full casing follow-up wall protection method is high, and is generally 1/3 higher than that of other methods.
2. Forming holes in a partial soil extrusion mode: long screw spinning pore-forming, punching pore-forming, drilling hole extruding pore-forming, pre-drilling pore-forming and driving (static pressure) precast pile; wherein,
the long-spiral pressure hole forming is suitable for site construction with good engineering geological conditions, basically does not easily generate hole collapse, and is mainly applied to the construction of small-diameter (d is less than or equal to 250mm) and medium-diameter (d is more than 250mm and less than 800mm) piles;
the punching and pore-forming are basically suitable for pore-forming under various geological conditions;
the hole drilling, squeezing and expanding for hole forming is suitable for site construction with good engineering geological conditions, basically does not easily generate hole collapse, and is mainly applied to construction of large-diameter (d is more than or equal to 800mm) piles;
the pre-drilled hole-forming driven (static pressure) precast pile is suitable for site construction with good engineering geological conditions, basically does not easily generate hole collapse, and is mainly applied to construction of small-diameter (d is less than or equal to 250mm) piles and medium-diameter (d is more than 250mm and less than 800mm) piles.
3. Extruding soil to form holes: sinking pipe cast-in-place pile, sinking pipe ramming (squeezing) expanded cast-in-place pile, (driving) static pressure precast pile, closed prestressed concrete pipe pile and closed steel pipe pile; wherein,
the immersed tube cast-in-place pile and the immersed tube ramming (extruding) expanded cast-in-place pile are suitable for forming holes in various soil layers with low penetration degree, and are mainly applied to the construction of small-diameter (d is less than or equal to 250mm) piles and medium-diameter (d is more than 250mm and less than 800mm) piles;
the (driven) static pressure precast pile, the closed prestressed concrete pipe pile and the closed steel pipe pile are suitable for construction of various soil layers with low penetration degree, and are mainly applied to construction of small-diameter (d is less than or equal to 250mm) piles and medium-diameter (d is more than 250mm and less than 800mm) piles;
the cost of the precast pile is higher than that of a cast-in-place concrete filling pile, and the cost of the steel pipe pile is higher than that of the precast pile.
The traditional ready-made hole bored concrete pile construction mud circulation has no two modes: one is a positive circulation mode, wherein slurry is injected into a drill rod (or a slurry pipe and other channels) from a slurry tank through a slurry pump to reach the bottom of a hole, and drilling slag is carried to flow back to a grit chamber along a drill hole and flow back to the slurry tank after being precipitated, and then the slurry is circulated in the mode. This requires that the formation being drilled be relatively stable (not prone to loss of mud, not prone to collapse of the borehole wall). In the other reverse circulation mode, generally adopting a pumping type, the slurry carrying the drilling slag is directly pumped from the bottom of the hole to a grit chamber through a sand pump, and the settled slurry is replenished from the hole opening. This approach is prone to the following problems: 1. when slurry is sucked from the bottom of a hole, the slurry level of the slurry in the hole is changed greatly due to untimely slurry supplement at the hole opening, the wall protection pressure of the hole wall at each position is reduced rapidly, the stress of a soil body is changed, hole collapse is easily caused for unstable stratums (such as quicksand, uncompacted sand, soil layers and the like) of the hole wall, and even accidents of buried drilling and collapse of a drilling machine are caused. 2. Such variations can also have adverse consequences for the formation where the borehole wall is unstable due to large differences in the properties (e.g., viscosity, specific gravity, etc.) of the pumped and replenished mud.
Disclosure of Invention
The invention aims to solve the technical problem of providing a bored concrete pile construction hole forming method for a permeable ultra-deep loose backfilling two-stone area, which can meet the requirement of large-diameter piles, and can avoid hole collapse when bored concrete pile construction hole forming is carried out under the conditions of special engineering geology (permeable areas, tidal range areas, uncompacted huge thick backfill layers and soft sludge interlayers).
In order to solve the problems, the invention provides a method for forming a hole in the construction of a cast-in-place pile in a permeable ultra-deep loose backfilled two-stone area, which comprises the following steps:
and 5, after drilling to a certain depth of a stable stratum (a clay layer in the figure), gradually reducing the specific gravity of the slurry in the hole, and discharging the slurry containing slag once every 2-3 hours so as to shorten the hole cleaning time and ensure that the performance indexes (the specific gravity of the slurry is less than 1.25, the sand content is less than or equal to 8 percent and the viscosity is less than or equal to 28s) of the slurry before underwater concrete is poured are adjusted to be within the standard requirements.
Preferably, the slag is removed by using a slag removing barrel in the step 2.
The invention has the following advantages:
1. by adopting the method of natural backflow of the slurry, the traditional slurry circulation mode is changed, the in-out balance of the slurry is maintained, the construction process is simplified (the sand pump is not required to be used for pumping the slurry at the bottom of the hole), and the construction risk is reduced.
2. By adopting the method of mud natural backflow, the mud performance is easy to keep stable in the process of drilling special strata (permeable, tidal range sections, uncompacted huge thick backfill layers and soft sludge interlayers), the pressure of the hole wall retaining wall is kept relatively stable, and unfavorable results cannot be brought to the construction of the stratum with unstable hole walls.
3. By adopting the method, when the performance of the slurry needs to be adjusted, the method is simple and easy, and is beneficial to shortening the hole cleaning time, thereby reducing the construction time of the whole single hole and increasing the construction efficiency.
Drawings
FIG. 1 is a schematic cross-sectional view of the construction of the embodiment of the present invention.
Detailed Description
As shown in figure 1, the invention carries out bored concrete pile construction pore-forming on a backfilled two-stone layer 1, and a seabed silt layer 2, a powdery clay layer 3, a clay layer 4, a residual soil layer 5 and a strong weathering rock layer 6 are arranged below the backfilled two-stone layer 1 in sequence. The cast-in-place pile construction hole forming method specifically comprises the following steps:
2, digging slag once by using a slag digging barrel every 1-3 hours in the punching process, pouring the dug slag into a grit chamber (not shown) communicated with a mud tank 11, naturally settling the drilled slag, supplementing and refluxing the mud into the mud tank 11, collecting the mud by using the mud tank 11, and naturally refluxing and supplementing the mud into a drill hole 12 through a sloping region 10;
and 5, after drilling to a certain depth of a stable stratum (a clay layer 4 in the figure), reducing the slurry flowing back into the original slurry tank 11 in the drill hole 12, gradually adding water to dilute the slurry to gradually reduce the specific gravity of the slurry in the drill hole 12, and discharging the slurry containing slag once every 2-3 hours to shorten the hole cleaning time and ensure that the performance indexes (the specific gravity of the slurry is less than 1.25, the sand content is less than or equal to 8 percent and the viscosity is less than or equal to 28s) of the slurry before underwater concrete is poured are adjusted within the standard requirements.
By adopting the method of natural backflow of the slurry, the invention changes the traditional slurry circulation mode, maintains the balance of the slurry in and out, simplifies the construction process (the sand pump is not needed for pumping the slurry at the bottom of the hole), and reduces the construction risk; in addition, by adopting the method of natural backflow of the slurry, the slurry performance is easy to keep stable in the process of drilling special strata (permeable, tidal range sections, uncompacted huge thick backfill layers and soft sludge interlayers), the pressure of the wall protection wall of the hole wall is kept relatively stable, and unfavorable results cannot be brought to the construction of the stratum with unstable hole walls.
Therefore, any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (2)
1. A construction hole forming method for a filling pile in a permeable ultra-deep loose backfilling two-stone area is characterized by comprising the following steps:
step 1, arranging a flooding slope area of 4-6 m as a slurry backflow channel in an area right in front of a well-placed pile casing, and excavating a slurry pool outside the flooding slope area; the flooding slope area is an inclined plane with an inclination angle of 5-8 degrees;
step 2, taking out slag every 1-3 hours in the punching process;
step 3, the drawn mud is completely reflowed back to the drill hole by utilizing the slope-flooding area;
step 4, increasing the specific gravity of the slurry in the drill hole while performing the punching operation;
and 5, after drilling to a certain depth of a stable stratum, gradually reducing the specific gravity of the slurry in the drilled hole, and discharging the slurry containing the slag once every 2-3 hours.
2. A method according to claim 1, characterized in that the skimming is performed in step 2 by means of a skimming cylinder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008101190883A CN101353894B (en) | 2008-08-28 | 2008-08-28 | Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008101190883A CN101353894B (en) | 2008-08-28 | 2008-08-28 | Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101353894A CN101353894A (en) | 2009-01-28 |
CN101353894B true CN101353894B (en) | 2010-06-09 |
Family
ID=40306884
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008101190883A Active CN101353894B (en) | 2008-08-28 | 2008-08-28 | Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101353894B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102704873B (en) * | 2012-06-07 | 2015-01-21 | 徐守田 | Construction equipment of hole drilling/punching cast-in-place pile with self-provided mud pit and mud separating device |
CN104746511B (en) * | 2015-03-31 | 2016-07-06 | 广州协安建设工程有限公司 | Quality of pile control method is dug in rotation when a kind of rich water sand bed |
CN111677439A (en) * | 2020-06-24 | 2020-09-18 | 中建四局土木工程有限公司 | Drilling hole forming method of reverse circulation rotary drilling machine |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1075521A (en) * | 1993-02-23 | 1993-08-25 | 何庆林 | Pile-making method of concrete-cast drillhole |
CN1149662A (en) * | 1996-09-19 | 1997-05-14 | 薛仁定 | Positive and negative circulation impact holing method |
CN1540104A (en) * | 2003-10-30 | 2004-10-27 | 北京城建集团有限责任公司 | Post mudjack construction technics for sidewal and bottom of bore of filling pile |
-
2008
- 2008-08-28 CN CN2008101190883A patent/CN101353894B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1075521A (en) * | 1993-02-23 | 1993-08-25 | 何庆林 | Pile-making method of concrete-cast drillhole |
CN1149662A (en) * | 1996-09-19 | 1997-05-14 | 薛仁定 | Positive and negative circulation impact holing method |
CN1540104A (en) * | 2003-10-30 | 2004-10-27 | 北京城建集团有限责任公司 | Post mudjack construction technics for sidewal and bottom of bore of filling pile |
Non-Patent Citations (1)
Title |
---|
JP特开2000-297429A 2000.10.24 |
Also Published As
Publication number | Publication date |
---|---|
CN101353894A (en) | 2009-01-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108708743B (en) | Method for treating tunnel collapse by grouting | |
CN103046931B (en) | Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode | |
CN110735600B (en) | Mechanical pore-forming pile construction process for karst geology | |
Bell | Methods of treatment of unstable ground | |
CN104947690A (en) | Grooving construction method for embedding underground continuous wall into rock | |
CN104963346A (en) | Support construction method for deep foundation pit in complex geological condition | |
CN110656947B (en) | Method for tunneling raised section of seabed bedrock | |
Brown | Practical considerations in the selection and use of continuous flight auger and drilled displacement piles | |
CN105064336A (en) | Hole forming construction method for three-section type pedestal pile | |
CN104711973A (en) | Construction method for small-diameter pile composite foundation | |
CN103015408A (en) | Cast-in-place pile synchronous casing hole-forming constructing method | |
JP2008057184A (en) | Method of constructing underground wall by using h-shaped pc pile | |
CN108867673A (en) | A kind of underwater prevention method in the foundation pit based on the curtain that draws water | |
CN101353894B (en) | Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone | |
CN101481913A (en) | Construction method of rock-socketed underground continuous wall punching slot section | |
CN104141300A (en) | Foundation pile hole drilling construction process | |
CN104074184B (en) | Pile base post-grouted expanded-base bored pile | |
CN102425179B (en) | Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile | |
CN103556641A (en) | Grooving assisting method for in-pit underground diaphragm wall of existing basement | |
CN106049467A (en) | Method for treating slurry leakage of bored pile through percussion drill under complex geology | |
CN101255797B (en) | Method for mounting blown sand and slip-casting of mine well wall as well as slip-casting pipe | |
CN104452776B (en) | Meet with the one construction Treatment Methods of diaphragm wall during boulder | |
CN106192987A (en) | A kind of construction method that stake periphery is crushed geology reinforcing | |
CN105586978A (en) | Construction method of soil replacement stir waterproof curtain based on gravels | |
CN205100226U (en) | Underground continuous wall goes into rock grooving construction equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing Co-patentee after: China Oilfield Services Limited Patentee after: China Offshore Oil Group Co., Ltd. Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing Co-patentee before: China Oilfield Services Limited Patentee before: China National Offshore Oil Corporation |