CN101353894B - Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone - Google Patents
Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone Download PDFInfo
- Publication number
- CN101353894B CN101353894B CN2008101190883A CN200810119088A CN101353894B CN 101353894 B CN101353894 B CN 101353894B CN 2008101190883 A CN2008101190883 A CN 2008101190883A CN 200810119088 A CN200810119088 A CN 200810119088A CN 101353894 B CN101353894 B CN 101353894B
- Authority
- CN
- China
- Prior art keywords
- mud
- slurry
- hole
- construction
- boring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
The invention discloses a drilling method for the construction of a cast-in-place pile of a dank ultra-deep loose refilling rubble area, which comprises the following steps: step 1: a slope area of 4m to 6m is arranged in an area right ahead an arranged pile casing to serve as a slurry return flow line, and a slurry pool is dug outside the slope area; step 2: residue is drawn out once every 1 hour to 3 hours during a punching process; step 3: all the drawn-out slurry flows backwards into a drilling hole by utilizing the slope area; step 4: when punching work is carried out, the proportion of the slurry in the hole is increased, thereby being capable of increasing wall retaining capability and reducing hole collapse risk; and step 5: after drilling is carried out to a stable stratum of certain depth, the proportion of the slurry in the hole is gradually reduced; slurry containing the residue is discharged; and the slurry is discharged once every 2 hours to 3 hours. By adopting the method that the slurry flows backwards naturally, the method of the invention changes the traditional mode of slurry circulation, maintains the balance of the slurry, simplifies the construction process and lowers the construction risk.
Description
Technical field
The present invention relates to a kind of filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone.
Background technology
Existing conventional pouring pile hole technology roughly has several:
1, non-soil compaction mode pore-forming: for example do working system brill (digging) pore-forming, mud off brill (digging) pore-forming, a complete set of pipe follow-up retaining wall method brill (digging) pore-forming; Wherein,
Dried working system bores (digging) pore-forming and mud off bores the place construction that (digging) pore-forming is applicable to that engineering geological conditions is good, the basic difficult hole of collapsing that produces;
A complete set of pipe follow-up retaining wall method is bored (digging) drilling construction expense cost height, generally exceeds 1/3 than additive method.
2, part soil compaction mode pore-forming: long spiral press pore-forming, punching pore-forming, boring squeezed hole, preboring pore-forming are squeezed into (static pressure) preformed pile; Wherein,
The long spiral press pore-forming is applicable to the construction of the good place of engineering geological conditions, and basic being difficult for produces the hole of collapsing, and is mainly used in minor diameter (d≤250mm), the intermediate diameters (250mm<d<800mm) construction of stake;
The punching pore-forming is applicable to the pore-forming under the various geological conditionss substantially;
The boring squeezed hole is applicable to the place construction that engineering geological conditions is good, and basic being difficult for produces the hole of collapsing, and is mainly used in the major diameter (d 〉=800mm) construction of stake;
The preboring pore-forming is squeezed into (static pressure) preformed pile and is applicable to the construction of the good place of engineering geological conditions, and basic being difficult for produces the hole of collapsing, and is mainly used in minor diameter (d≤250mm), the intermediate diameters (250mm<d<800mm) construction of stake.
3, soil compaction mode pore-forming: tube-sinking cast-in-situ pile, immersed tube ram (squeezing) grouting pile, (squeezing into) Static Pressure Precast Piles, the remain silent prestressed concrete pipe pile and the steel pipe pile of remaining silent; Wherein,
Tube-sinking cast-in-situ pile, immersed tube ram (squeezing) grouting pile and are applicable to all kinds of soil layer pore-formings that pile penetration is lower, are mainly used in minor diameter (d≤250mm), intermediate diameters (250mm<d<800mm) construction;
(squeezing into) Static Pressure Precast Piles, remain silent prestressed concrete pipe pile and the steel pipe pile of remaining silent are applicable to all kinds of soil layers constructions that pile penetration is lower, are mainly used in minor diameter (d≤250mm), the intermediate diameters (250mm<d<800mm) construction of stake;
Preformed pile expense cost is higher than cast-in-situ concrete poured stake, and steel pipe pile expense cost is higher than preformed pile.
Traditional ready-made hole pouring pile construction mud circulation is dual mode nothing but: a kind of is the direct circulation mode, at the bottom of mud injects drilling rod passages such as (or) mud tubes and arrives the hole by slush pump from mud pit, carry boring mud and return out the aperture along boring and flow back to grit chamber, flow back to mud pit circulation in the above described manner again through (boring mud) post precipitation.This mode require the stratum of boring more stable (be difficult for leakage mud, hole wall is difficult for caving in).Another anti-endless form adopts pump suction type usually, and the mud that carries boring mud directly is drawn into the grit chamber at the bottom of the hole by gravel pump, replenishes the mud through (boring mud) post precipitation simultaneously from the aperture.This mode is easy to generate following problem: 1, at the bottom of the hole suction mud time, because it is untimely that aperture mud replenishes, cause in the hole mud level change bigger, cause diminishing fast of hole wall retaining wall pressure everywhere, cause soil body STRESS VARIATION, very easily produce the hole of collapsing for the unsettled stratum of hole wall (as quicksand, not closely knit sand, soil layer etc.), even the accident that causes bury drills, rig to subside to collapse takes place.2, since on the mud that aspirates out and the additional mud property (as viscosity, proportion or the like) have bigger difference, for the unsettled stratum of hole wall, this variation also can bring disadvantageous result to construction.
Summary of the invention
The technical problem to be solved in the present invention provides a kind of filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone, can satisfy large diameter pile, filling pile construction pore-creating under special engineering geology (permeable, tidal range location, not closely knit huge thick backfill layer, weak sludge interlayer) condition can be avoided the hole phenomenon of collapsing.
In order to address the above problem, the filling pile construction pore-creating method that the invention provides a kind of pervious ultra-deep loose backfill two-piece stone zone comprises the steps:
Add the mud balance in the macropore in the time of step 4, punching operation; Can improve retaining capacity like this, reduce the hole risk of collapsing;
Preferably, utilization is drawn the slag tube and is drawn slag in described step 2.
The present invention has following advantage:
1, passes through the method that employing mud flows backwards naturally, changed the pattern of traditional mud circulation, kept the discrepancy balance of mud, simplified construction technology (not needing to utilize gravel pump to carry out the suction of hole bottom slurry), reduced construction risk.
2, the method by adopting mud to flow backwards naturally, in bore meeting special formation (permeable, tidal range location, not closely knit huge thick backfill layer, weak sludge interlayer) process, make mud property keep stable easily, and make hole wall retaining wall pressure keep more stablely, bring disadvantageous result can for the construction on the unsettled stratum of hole wall.
3, adopt this method, simple and easy to do when needs carry out the mud property adjusting, be beneficial to and shorten the clear hole time, thereby reduced the engineering time of whole single hole, increase the construction effect.
Description of drawings
Fig. 1 is embodiment of the invention construction generalized section.
The specific embodiment
As shown in Figure 1, the present invention carries out filling pile construction pore-creating at backfill two-piece stone layer 1, and backfill two-piece stone layer 1 next coming in order are bottom silt layer 2, farinose argillic horizon 3, argillic horizon 4, remain soil layer 5 and severely-weathered rock stratum 6.Filling pile construction pore-creating of the present invention specifically comprises the steps:
Backflow by mud in the time of step 4, punching operation strengthens the 12 interior mud balances of holing, and can improve retaining capacity like this, reduces the hole risk of collapsing;
The present invention has changed the pattern of traditional mud circulation by the method that employing mud flows backwards naturally, has kept the discrepancy balance of mud, has simplified construction technology (not needing to utilize gravel pump to carry out the suction of hole bottom slurry), has reduced construction risk; In addition, the method that adopts mud to flow backwards naturally, in bore meeting special formation (permeable, tidal range location, not closely knit huge thick backfill layer, weak sludge interlayer) process, make mud property keep stable easily, and make hole wall retaining wall pressure keep more stablely, bring disadvantageous result can for the construction on the unsettled stratum of hole wall.
In sum; being preferred embodiment of the present invention only below, is not to be used to limit protection scope of the present invention, therefore; all any modifications of being done within the spirit and principles in the present invention, be equal to replacement, improvement etc., all should be included within protection scope of the present invention.
Claims (2)
1. the filling pile construction pore-creating method of a pervious ultra-deep loose backfill two-piece stone zone is characterized in that, comprises the steps:
Step 1,4~6m is set in the zone, casing dead ahead that places general slope district as the mud return flow line, mud pit is excavated beyond the district again in general slope; Described general slope district is for having the inclined plane at 5~8 degree angles of inclination;
Step 2, in punch process, drew primary slag in per 1~3 hour;
Step 3, the mud of drawing out utilize general slope district all to flow backwards and get back in the boring;
Strengthen the mud balance in the boring in the time of step 4, punching operation;
Step 5, be drilled into the good ground certain depth after, reduce mud balance in the boring gradually, slag inclusion mud of per 2~3 hours rows.
2. a kind of method as claimed in claim 1 is characterized in that, utilization is drawn the slag tube and drawn slag in described step 2.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008101190883A CN101353894B (en) | 2008-08-28 | 2008-08-28 | Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008101190883A CN101353894B (en) | 2008-08-28 | 2008-08-28 | Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101353894A CN101353894A (en) | 2009-01-28 |
CN101353894B true CN101353894B (en) | 2010-06-09 |
Family
ID=40306884
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008101190883A Active CN101353894B (en) | 2008-08-28 | 2008-08-28 | Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101353894B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102704873B (en) * | 2012-06-07 | 2015-01-21 | 徐守田 | Construction equipment of hole drilling/punching cast-in-place pile with self-provided mud pit and mud separating device |
CN104746511B (en) * | 2015-03-31 | 2016-07-06 | 广州协安建设工程有限公司 | Quality of pile control method is dug in rotation when a kind of rich water sand bed |
CN111677439A (en) * | 2020-06-24 | 2020-09-18 | 中建四局土木工程有限公司 | Drilling hole forming method of reverse circulation rotary drilling machine |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1075521A (en) * | 1993-02-23 | 1993-08-25 | 何庆林 | Pile-making method of concrete-cast drillhole |
CN1149662A (en) * | 1996-09-19 | 1997-05-14 | 薛仁定 | Positive and negative circulation impact holing method |
CN1540104A (en) * | 2003-10-30 | 2004-10-27 | 北京城建集团有限责任公司 | Post mudjack construction technics for sidewal and bottom of bore of filling pile |
-
2008
- 2008-08-28 CN CN2008101190883A patent/CN101353894B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1075521A (en) * | 1993-02-23 | 1993-08-25 | 何庆林 | Pile-making method of concrete-cast drillhole |
CN1149662A (en) * | 1996-09-19 | 1997-05-14 | 薛仁定 | Positive and negative circulation impact holing method |
CN1540104A (en) * | 2003-10-30 | 2004-10-27 | 北京城建集团有限责任公司 | Post mudjack construction technics for sidewal and bottom of bore of filling pile |
Non-Patent Citations (1)
Title |
---|
JP特开2000-297429A 2000.10.24 |
Also Published As
Publication number | Publication date |
---|---|
CN101353894A (en) | 2009-01-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101176400B (en) | New process for recultivating glebe in mine subsidence area | |
CN102051886B (en) | Light well point drainage construction technology | |
CN102296630A (en) | Construction method of long-screw high-pressure mix jetting cement diaphragm wall | |
CN101205721A (en) | Method for surrounding water by combination of steel cofferdam and heavy-pressure rotary-spraying pile in deep-water low-pile cap construction | |
CN104947690A (en) | Grooving construction method for embedding underground continuous wall into rock | |
CN103046931A (en) | Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode | |
CN108797618A (en) | One kind being used for Urban Underground pipe gallery drainage of foundation pit structure and its construction method | |
CN104329020B (en) | A kind of reinforced long spire embedding rock construction equipment and technique thereof | |
CN105239564A (en) | Construction method of cast-in-place pile with combination of full-sleeve and mud protecting wall | |
CN106677166A (en) | Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode | |
CN110424430A (en) | Deep basal pit powder land floor Deep Pumped Wells construction method and its application | |
CN109594575A (en) | A kind of open caisson periphery grouting and reinforcing soil body construction method | |
CN108867673A (en) | A kind of underwater prevention method in the foundation pit based on the curtain that draws water | |
CN101353894B (en) | Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone | |
CN104652427A (en) | Construction method of drilling pile | |
CN101481913A (en) | Construction method of rock-socketed underground continuous wall punching slot section | |
CN104141300A (en) | Foundation pile hole drilling construction process | |
CN113832991A (en) | Reverse construction method of pile plate wall | |
CN105926592A (en) | Construction method of hole drilling pile | |
CN102425179B (en) | Structure of reinforced soil sewer supported by bored concrete piles of mini steel tubes | |
CN215367226U (en) | Well draw reaming body expanding pile of solid reinforcing of back slip casting root | |
CN106192987A (en) | A kind of construction method that stake periphery is crushed geology reinforcing | |
CN106049467A (en) | Method for treating slurry leakage of bored pile through percussion drill under complex geology | |
CN217053672U (en) | Large-diameter inspection well pile drilling method construction system | |
CN110318392A (en) | A kind of major diameter cement earth pile method of construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing Co-patentee after: China Oilfield Services Limited Patentee after: China Offshore Oil Group Co., Ltd. Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing Co-patentee before: China Oilfield Services Limited Patentee before: China National Offshore Oil Corporation |