CN101353894B - Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone - Google Patents

Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone Download PDF

Info

Publication number
CN101353894B
CN101353894B CN2008101190883A CN200810119088A CN101353894B CN 101353894 B CN101353894 B CN 101353894B CN 2008101190883 A CN2008101190883 A CN 2008101190883A CN 200810119088 A CN200810119088 A CN 200810119088A CN 101353894 B CN101353894 B CN 101353894B
Authority
CN
China
Prior art keywords
slurry
hole
area
construction
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008101190883A
Other languages
Chinese (zh)
Other versions
CN101353894A (en
Inventor
金传宏
杨爱国
周飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Oilfield Services Ltd
China National Offshore Oil Corp CNOOC
Original Assignee
China Oilfield Services Ltd
China National Offshore Oil Corp CNOOC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Oilfield Services Ltd, China National Offshore Oil Corp CNOOC filed Critical China Oilfield Services Ltd
Priority to CN2008101190883A priority Critical patent/CN101353894B/en
Publication of CN101353894A publication Critical patent/CN101353894A/en
Application granted granted Critical
Publication of CN101353894B publication Critical patent/CN101353894B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a drilling method for the construction of a cast-in-place pile of a dank ultra-deep loose refilling rubble area, which comprises the following steps: step 1: a slope area of 4m to 6m is arranged in an area right ahead an arranged pile casing to serve as a slurry return flow line, and a slurry pool is dug outside the slope area; step 2: residue is drawn out once every 1 hour to 3 hours during a punching process; step 3: all the drawn-out slurry flows backwards into a drilling hole by utilizing the slope area; step 4: when punching work is carried out, the proportion of the slurry in the hole is increased, thereby being capable of increasing wall retaining capability and reducing hole collapse risk; and step 5: after drilling is carried out to a stable stratum of certain depth, the proportion of the slurry in the hole is gradually reduced; slurry containing the residue is discharged; and the slurry is discharged once every 2 hours to 3 hours. By adopting the method that the slurry flows backwards naturally, the method of the invention changes the traditional mode of slurry circulation, maintains the balance of the slurry, simplifies the construction process and lowers the construction risk.

Description

Bored concrete pile construction pore-forming method for water-permeable ultra-deep loose backfilling of two-stone area
Technical Field
The invention relates to a construction hole forming method for a filling pile in a permeable ultra-deep loose backfilling two-stone area.
Background
The existing conventional cast-in-place pile hole forming technology is roughly divided into the following steps:
1. forming holes in a non-soil-squeezing mode: for example, drilling (digging) to form a hole by a dry operation method, drilling (digging) to form a hole by a slurry wall protection drill, and drilling (digging) to form a hole by a full casing follow-up wall protection method; wherein,
drilling (digging) a hole and drilling (digging) a hole by a mud retaining wall by a dry operation method are suitable for field construction with good engineering geological conditions, and hole collapse is basically not easy to generate;
the construction cost of drilling (digging) the hole by the full casing follow-up wall protection method is high, and is generally 1/3 higher than that of other methods.
2. Forming holes in a partial soil extrusion mode: long screw spinning pore-forming, punching pore-forming, drilling hole extruding pore-forming, pre-drilling pore-forming and driving (static pressure) precast pile; wherein,
the long-spiral pressure hole forming is suitable for site construction with good engineering geological conditions, basically does not easily generate hole collapse, and is mainly applied to the construction of small-diameter (d is less than or equal to 250mm) and medium-diameter (d is more than 250mm and less than 800mm) piles;
the punching and pore-forming are basically suitable for pore-forming under various geological conditions;
the hole drilling, squeezing and expanding for hole forming is suitable for site construction with good engineering geological conditions, basically does not easily generate hole collapse, and is mainly applied to construction of large-diameter (d is more than or equal to 800mm) piles;
the pre-drilled hole-forming driven (static pressure) precast pile is suitable for site construction with good engineering geological conditions, basically does not easily generate hole collapse, and is mainly applied to construction of small-diameter (d is less than or equal to 250mm) piles and medium-diameter (d is more than 250mm and less than 800mm) piles.
3. Extruding soil to form holes: sinking pipe cast-in-place pile, sinking pipe ramming (squeezing) expanded cast-in-place pile, (driving) static pressure precast pile, closed prestressed concrete pipe pile and closed steel pipe pile; wherein,
the immersed tube cast-in-place pile and the immersed tube ramming (extruding) expanded cast-in-place pile are suitable for forming holes in various soil layers with low penetration degree, and are mainly applied to the construction of small-diameter (d is less than or equal to 250mm) piles and medium-diameter (d is more than 250mm and less than 800mm) piles;
the (driven) static pressure precast pile, the closed prestressed concrete pipe pile and the closed steel pipe pile are suitable for construction of various soil layers with low penetration degree, and are mainly applied to construction of small-diameter (d is less than or equal to 250mm) piles and medium-diameter (d is more than 250mm and less than 800mm) piles;
the cost of the precast pile is higher than that of a cast-in-place concrete filling pile, and the cost of the steel pipe pile is higher than that of the precast pile.
The traditional ready-made hole bored concrete pile construction mud circulation has no two modes: one is a positive circulation mode, wherein slurry is injected into a drill rod (or a slurry pipe and other channels) from a slurry tank through a slurry pump to reach the bottom of a hole, and drilling slag is carried to flow back to a grit chamber along a drill hole and flow back to the slurry tank after being precipitated, and then the slurry is circulated in the mode. This requires that the formation being drilled be relatively stable (not prone to loss of mud, not prone to collapse of the borehole wall). In the other reverse circulation mode, generally adopting a pumping type, the slurry carrying the drilling slag is directly pumped from the bottom of the hole to a grit chamber through a sand pump, and the settled slurry is replenished from the hole opening. This approach is prone to the following problems: 1. when slurry is sucked from the bottom of a hole, the slurry level of the slurry in the hole is changed greatly due to untimely slurry supplement at the hole opening, the wall protection pressure of the hole wall at each position is reduced rapidly, the stress of a soil body is changed, hole collapse is easily caused for unstable stratums (such as quicksand, uncompacted sand, soil layers and the like) of the hole wall, and even accidents of buried drilling and collapse of a drilling machine are caused. 2. Such variations can also have adverse consequences for the formation where the borehole wall is unstable due to large differences in the properties (e.g., viscosity, specific gravity, etc.) of the pumped and replenished mud.
Disclosure of Invention
The invention aims to solve the technical problem of providing a bored concrete pile construction hole forming method for a permeable ultra-deep loose backfilling two-stone area, which can meet the requirement of large-diameter piles, and can avoid hole collapse when bored concrete pile construction hole forming is carried out under the conditions of special engineering geology (permeable areas, tidal range areas, uncompacted huge thick backfill layers and soft sludge interlayers).
In order to solve the problems, the invention provides a method for forming a hole in the construction of a cast-in-place pile in a permeable ultra-deep loose backfilled two-stone area, which comprises the following steps:
step 1, arranging a flooding slope area of 4-6 m as a slurry backflow channel in an area right in front of a well-placed pile casing, and excavating a slurry pool outside the flooding slope area; the flooding slope area is an inclined plane with an inclination angle of 5-8 degrees;
step 2, taking out slag every 1-3 hours in the punching process;
step 3, the drawn mud is completely reflowed back to the drill hole by utilizing the slope-flooding area;
step 4, increasing the specific gravity of the slurry in the hole while performing the punching operation; therefore, the wall protection capability can be improved, and the hole collapse risk is reduced;
and 5, after drilling to a certain depth of a stable stratum (a clay layer in the figure), gradually reducing the specific gravity of the slurry in the hole, and discharging the slurry containing slag once every 2-3 hours so as to shorten the hole cleaning time and ensure that the performance indexes (the specific gravity of the slurry is less than 1.25, the sand content is less than or equal to 8 percent and the viscosity is less than or equal to 28s) of the slurry before underwater concrete is poured are adjusted to be within the standard requirements.
Preferably, the slag is removed by using a slag removing barrel in the step 2.
The invention has the following advantages:
1. by adopting the method of natural backflow of the slurry, the traditional slurry circulation mode is changed, the in-out balance of the slurry is maintained, the construction process is simplified (the sand pump is not required to be used for pumping the slurry at the bottom of the hole), and the construction risk is reduced.
2. By adopting the method of mud natural backflow, the mud performance is easy to keep stable in the process of drilling special strata (permeable, tidal range sections, uncompacted huge thick backfill layers and soft sludge interlayers), the pressure of the hole wall retaining wall is kept relatively stable, and unfavorable results cannot be brought to the construction of the stratum with unstable hole walls.
3. By adopting the method, when the performance of the slurry needs to be adjusted, the method is simple and easy, and is beneficial to shortening the hole cleaning time, thereby reducing the construction time of the whole single hole and increasing the construction efficiency.
Drawings
FIG. 1 is a schematic cross-sectional view of the construction of the embodiment of the present invention.
Detailed Description
As shown in figure 1, the invention carries out bored concrete pile construction pore-forming on a backfilled two-stone layer 1, and a seabed silt layer 2, a powdery clay layer 3, a clay layer 4, a residual soil layer 5 and a strong weathering rock layer 6 are arranged below the backfilled two-stone layer 1 in sequence. The cast-in-place pile construction hole forming method specifically comprises the following steps:
step 1, placing a protective cylinder 9 at a certain depth (not less than 1.5 m) of a backfilled two-stone layer 1, a seabed sludge layer 2 and a silty clay layer 3, wherein the protective cylinder 9 can be placed by adopting a vibration sinking method. And (3) utilizing a drilling machine 7 and a percussion bit 8 to carry out punching construction on the backfilled two stone layers 1. A flooding slope area 10 with the range of 4-6 m is reserved right ahead of the placed casing 9 (namely, the position opposite to the installation position of the drilling machine 7) and is used as a channel for backflow of slurry into a drilling hole 12, and the flooding slope area 10 is an inclined plane with a certain inclination angle, and the inclination angle is preferably 5-8 degrees. In addition, excavating a mud pit 11 outside the general slope area 10;
2, digging slag once by using a slag digging barrel every 1-3 hours in the punching process, pouring the dug slag into a grit chamber (not shown) communicated with a mud tank 11, naturally settling the drilled slag, supplementing and refluxing the mud into the mud tank 11, collecting the mud by using the mud tank 11, and naturally refluxing and supplementing the mud into a drill hole 12 through a sloping region 10;
step 3, the taken out slurry (containing drilling slag) is precipitated in a grit chamber, flows back to a slurry tank 11, then naturally flows back to a drill hole 12 through a sloping region 10, and flows into the drill hole 12 through a top opening of a protective cylinder 9;
step 4, increasing the specific gravity of the slurry in the drill hole 12 through the backflow of the slurry during the punching operation, so that the wall protection capability can be improved, and the hole collapse risk is reduced;
and 5, after drilling to a certain depth of a stable stratum (a clay layer 4 in the figure), reducing the slurry flowing back into the original slurry tank 11 in the drill hole 12, gradually adding water to dilute the slurry to gradually reduce the specific gravity of the slurry in the drill hole 12, and discharging the slurry containing slag once every 2-3 hours to shorten the hole cleaning time and ensure that the performance indexes (the specific gravity of the slurry is less than 1.25, the sand content is less than or equal to 8 percent and the viscosity is less than or equal to 28s) of the slurry before underwater concrete is poured are adjusted within the standard requirements.
By adopting the method of natural backflow of the slurry, the invention changes the traditional slurry circulation mode, maintains the balance of the slurry in and out, simplifies the construction process (the sand pump is not needed for pumping the slurry at the bottom of the hole), and reduces the construction risk; in addition, by adopting the method of natural backflow of the slurry, the slurry performance is easy to keep stable in the process of drilling special strata (permeable, tidal range sections, uncompacted huge thick backfill layers and soft sludge interlayers), the pressure of the wall protection wall of the hole wall is kept relatively stable, and unfavorable results cannot be brought to the construction of the stratum with unstable hole walls.
Therefore, any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (2)

1. A construction hole forming method for a filling pile in a permeable ultra-deep loose backfilling two-stone area is characterized by comprising the following steps:
step 1, arranging a flooding slope area of 4-6 m as a slurry backflow channel in an area right in front of a well-placed pile casing, and excavating a slurry pool outside the flooding slope area; the flooding slope area is an inclined plane with an inclination angle of 5-8 degrees;
step 2, taking out slag every 1-3 hours in the punching process;
step 3, the drawn mud is completely reflowed back to the drill hole by utilizing the slope-flooding area;
step 4, increasing the specific gravity of the slurry in the drill hole while performing the punching operation;
and 5, after drilling to a certain depth of a stable stratum, gradually reducing the specific gravity of the slurry in the drilled hole, and discharging the slurry containing the slag once every 2-3 hours.
2. A method according to claim 1, characterized in that the skimming is performed in step 2 by means of a skimming cylinder.
CN2008101190883A 2008-08-28 2008-08-28 Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone Active CN101353894B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008101190883A CN101353894B (en) 2008-08-28 2008-08-28 Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008101190883A CN101353894B (en) 2008-08-28 2008-08-28 Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone

Publications (2)

Publication Number Publication Date
CN101353894A CN101353894A (en) 2009-01-28
CN101353894B true CN101353894B (en) 2010-06-09

Family

ID=40306884

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008101190883A Active CN101353894B (en) 2008-08-28 2008-08-28 Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone

Country Status (1)

Country Link
CN (1) CN101353894B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704873B (en) * 2012-06-07 2015-01-21 徐守田 Construction equipment of hole drilling/punching cast-in-place pile with self-provided mud pit and mud separating device
CN104746511B (en) * 2015-03-31 2016-07-06 广州协安建设工程有限公司 Quality of pile control method is dug in rotation when a kind of rich water sand bed
CN111677439A (en) * 2020-06-24 2020-09-18 中建四局土木工程有限公司 Drilling hole forming method of reverse circulation rotary drilling machine

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1075521A (en) * 1993-02-23 1993-08-25 何庆林 Pile-making method of concrete-cast drillhole
CN1149662A (en) * 1996-09-19 1997-05-14 薛仁定 Positive and negative circulation impact holing method
CN1540104A (en) * 2003-10-30 2004-10-27 北京城建集团有限责任公司 Post mudjack construction technics for sidewal and bottom of bore of filling pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1075521A (en) * 1993-02-23 1993-08-25 何庆林 Pile-making method of concrete-cast drillhole
CN1149662A (en) * 1996-09-19 1997-05-14 薛仁定 Positive and negative circulation impact holing method
CN1540104A (en) * 2003-10-30 2004-10-27 北京城建集团有限责任公司 Post mudjack construction technics for sidewal and bottom of bore of filling pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开2000-297429A 2000.10.24

Also Published As

Publication number Publication date
CN101353894A (en) 2009-01-28

Similar Documents

Publication Publication Date Title
CN108708743B (en) Method for treating tunnel collapse by grouting
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
Bell Methods of treatment of unstable ground
CN104947690A (en) Grooving construction method for embedding underground continuous wall into rock
CN104963346A (en) Support construction method for deep foundation pit in complex geological condition
CN110656947B (en) Method for tunneling raised section of seabed bedrock
Brown Practical considerations in the selection and use of continuous flight auger and drilled displacement piles
CN105064336A (en) Hole forming construction method for three-section type pedestal pile
CN104711973A (en) Construction method for small-diameter pile composite foundation
CN103015408A (en) Cast-in-place pile synchronous casing hole-forming constructing method
JP2008057184A (en) Method of constructing underground wall by using h-shaped pc pile
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN101353894B (en) Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section
CN104141300A (en) Foundation pile hole drilling construction process
CN104074184B (en) Pile base post-grouted expanded-base bored pile
CN102425179B (en) Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile
CN103556641A (en) Grooving assisting method for in-pit underground diaphragm wall of existing basement
CN106049467A (en) Method for treating slurry leakage of bored pile through percussion drill under complex geology
CN101255797B (en) Method for mounting blown sand and slip-casting of mine well wall as well as slip-casting pipe
CN104452776B (en) Meet with the one construction Treatment Methods of diaphragm wall during boulder
CN106192987A (en) A kind of construction method that stake periphery is crushed geology reinforcing
CN105586978A (en) Construction method of soil replacement stir waterproof curtain based on gravels
CN205100226U (en) Underground continuous wall goes into rock grooving construction equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee after: China Oilfield Services Limited

Patentee after: China Offshore Oil Group Co., Ltd.

Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee before: China Oilfield Services Limited

Patentee before: China National Offshore Oil Corporation